Upload
sybil-kathleen-george
View
215
Download
1
Tags:
Embed Size (px)
Citation preview
Mississippi River Bridge
An Analysis of Alternatives
Mississippi River Bridge
An Analysis of AlternativesDRAFT Final Report
PresentationJanuary 31, 2007
OverviewOverview
• Study Objectives
• Alternatives Considered
• Comparison of Alternatives
• Key Findings
• Choices for the Future
Study ObjectivesStudy Objectives
• Provide common understanding ―Existing and projected traffic
conditions―Bridge alternatives―Capital costs―Committed funding―Potential funding shortfalls
• Identify options for moving forward
Fact vs. FictionFact vs. Fiction
• Fiction: “…the cost of an 8-lane bridge – last year estimated at $910 million – is now $1.76 billion…partly due to inflation…”
• Fact: The cost of an 8-lane bridge – last year estimated at $910 million – is now $999.2 million…entirely due to inflation…”
•
Existing NetworkExisting Network
Existing Daily CrossingsExisting Daily Crossings
0
50,000
100,000
150,000
200,000
250,000
300,000
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
Poplar Eads MLK
McKinley I-255 I-270
US 67 Downtown Total Overall Total
Source: Mississippi River Crossings: Average Daily Traffic History, Illinois Department of Transportation.
There is no question that additional
capacity is needed across the Mississippi River between Illinois
and Missouri in the East-West Gateway
region.
Bridge Alternatives: ComponentsBridge Alternatives: Components
• Proposed MRB (I-70)
• Proposed MLK “Coupler”
• Proposed I-64 Connector and “Tri-Level” Interchange
• Proposed IL-3 Relocation & Connector
“Build” Alternatives Considered“Build” Alternatives Considered
• New Mississippi River Bridge (MRB: I-70)―Current EIS/ROD pending―Capital cost (YOE): $999.2 million
• New Mississippi River Bridge with all connectors and ramps (MRB: I-70/I-64/IL-3)―Capital cost (YOE): $1,762.5 million
• New Mississippi River Bridge with principal connectors and ramps (MRB: I-70/I-64)―Capital cost (YOE): $1,561.5 million
• Proposed Martin Luther King Bridge “Coupler”―Capital cost (YOE): $545.9 million
Other Alternatives ConsideredOther Alternatives Considered
• Improvements to Existing Network (“TSM”)―Connectors, ramps, geometric
improvements―Capital cost: $450 million (+/-)
• “No Build”―Reference point or “datum”―Capital cost: $0
MRB: I-70MRB: I-70• Components:
I-70 Bridge
• Cost Estimate: $999.2M (YOE)
• Proposed Schedule: 2009-2014
• NEPA Status: ROD proposed 2007
• Potential Committed Funding: SAFETEA-LU Earmarks:
$239M Additional IDOT Funding:
$210M
• Tolling Considered: Yes
MRB: I-70/ I-64 / IL-3MRB: I-70/ I-64 / IL-3• Components:
I-70 Bridge I-64 Connection IL-3 Relocation & Connection
• Cost Estimate:$1,762.5M (YOE)
• Proposed Schedule:2009-2014
• NEPA Status: ROD proposed 2007
• Potential Committed Funding: SAFETEA-LU Earmarks: $239M Additional IDOT Funding:
$226M
• Tolling Considered: Yes
MRB: I-70 / I-64MRB: I-70 / I-64• Components:
I-70 Bridge I-64 Connection
• Cost Estimate: $1,561.5M (YOE)
• Proposed Schedule: 2009-2014
• NEPA Status: ROD proposed 2007
• Potential Committed Funding: SAFETEA-LU Earmarks:
$239M Additional IDOT Funding:
$226M
• Tolling Considered: Yes
MLK Coupler BridgeMLK Coupler Bridge• Components:
I-70 Bridge
• Cost Estimate: $545.9M (YOE)
• Proposed Schedule: 2012-2014
• NEPA Status: Not Analyzed
• Potential Committed Funding: SAFETEA-LU Earmarks:
$239M Additional IDOT Funding:
$210M
• Tolling Considered: No
Comparison of AlternativesComparison of Alternatives
• Enhance network capacity
• Improve local, regional, and national movement of people and goods
• Reduce congestion and traffic delay
• Provide redundancy for periods during which one or more of the other bridges are partially or fully closed for repairs and rehabilitation
Forecasts and ProjectionsForecasts and Projections
• Utilized updated EWG modeling system
• Based on comprehensive household surveys done in 2002
• Validated “on the ground” with 2002 traffic
Travel Forecasting: Toll FacilitiesTravel Forecasting: Toll Facilities
• How many drivers will use a toll bridge, and how many will choose free alternatives?―Time saved through congestion
avoidance―Financial considerations (household
income, etc.)
• Diversion is based on travel time savings, toll amount, and availability of “free” alternatives
Projected Traffic:2020 Downtown Bridges Traffic Volume Comparison
Projected Traffic:2020 Downtown Bridges Traffic Volume Comparison
2020 Downtown Bridges Average Daily Traffic Volume
0
50,000
100,000
150,000
200,000
250,000
No Build MRB 70/64/3 MRB 70/64 MRB 70 MLK Coupler MRB 70/64/3 -$1/$3
MRB 70/64 -$1/$3
MRB 70 -$1/$3
MRB 70/64/3 -$2/$4
Poplar St. New MRB MLK McKinley Eads
Source: East-West Gateway Council of Government Travel Demand Model Run
MRBMRB
PoplarPoplar
Projected Congestion Levels:2020 AM Westbound Volume to Capacity (V/C) Ratio
Projected Congestion Levels:2020 AM Westbound Volume to Capacity (V/C) Ratio
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
No Build MRB 70/64/3 MRB 70/64 MRB 70 MLKCoupler
MRB70/64/3-$1/$3
MRB 70/64-$1/$3
MRB 70-$1/$3
MRB70/64/3-$2/$4
Poplar New MRB MLK McKinley Eads
Source: East-West Gateway Council of Government Travel Demand Model Run
CO
NG
ES
TI
ON
MRBw/out tolls
MRBwith tolls
MLKCoupler
Projected Congestion Levels:2020 PM Eastbound Volume to Capacity (V/C) Ratio
Projected Congestion Levels:2020 PM Eastbound Volume to Capacity (V/C) Ratio
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
No Build MRB 70/64/3 MRB 70/64 MRB 70 MLKCoupler
MRB 70/64/3-$1/$3
MRB 70/64-$1/$3
MRB 70-$1/$3
MRB 70/64/3-$2/$4
Poplar New MRB MLK McKinley Eads
Source: East-West Gateway Council of Government Travel Demand Model Run
CO
NG
ES
TI
ON
MRBw/out tolls
MRBwith tolls
MLKCoupler
Local and Regional TravelLocal and Regional Travel
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
MRB 70/64/3 MRB 70/64 MRB 70 MLK Coupler MRB 70/64/3-$1/$3
MRB 70/64-$1/$3
MRB 70-$1/$3 MRB 70/64/3-$2/$4
IL to MO (Internal) IL to MO (External/Through) IL to MO (External-Internal)
Source: East-West Gateway Council of Government Travel Demand Model Run
Projected Annual Travel Time Savings:All Bridges
Projected Annual Travel Time Savings:All BridgesAnnual Weekday Travel Time Savings Compared to No Build:
AM Westbound Vehicle Trips - All Bridges (Hours)
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
400,000
450,000
MRB 70/64/3 MRB 70/64 MRB 70 MLK Coupler MRB 70/64/3-$1/$3
MRB 70/64-$1/$3
MRB 70-$1/$3 MRB 70/64/3-$2/$4
All Bridges
Source: East-West Gateway Council of Government Travel Demand Model Run
Key FindingsKey Findings• MRB 70 does not optimize
transportation benefits without the I-64 connection
• MRB 70/64 connection is the most cost-effective “MRB” alternative, with a capital cost of $1.56 billion
• MLK Coupler provides some 60% of the user benefits of MRB 70/64 at about 35% of the cost
• Tolling reduces the effectiveness of all MRB alternatives
Funding SourcesFunding Sources
• Committed Sources―SAFETEA-LU Earmarks ($239 million)―IDOT Funding ($210 million)
• Potential Sources―Local/regional taxes/assessments―Additional federal support―Tolls
Public Tolling Authority Public-Private Partnership/Concession
Committed Funding and Funding GapCommitted Funding and Funding Gap
Potential Funding Scenario/ Funding Gap Analysis(in millions)
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
$1,800
Funding Gap $1,295 $1,094 $560 $97
Potential Additional IDOT $227 $227 $210 $210
SAFETEA-LU Earmarks $239 $239 $239 $239
MRB 70/64/3 MRB 70/64 MRB 70 MLK
Potential Supplemental Funding: Toll RevenuePotential Supplemental Funding: Toll Revenue
• Public Toll Agency
• Public-Private Partnership Concession
Public Toll Agency Approach:Potential Bond IssuePublic Toll Agency Approach:Potential Bond Issue
Toll Revenue Bond Range
Percent of Total Project Costs
MRB 70/64/3$1 auto / $3 truck
$100-$150 M 6-9%
MRB 70/64$1 auto / $3 truck
$100-$150 M 7-9%
MRB 70$1 auto / $3 truck
$80-$110 M 8-11%
MRB 70/64/3$2 auto / $4 truck
$80-$160 M 5-9%
Public Toll Agency – Funding ScenarioPublic Toll Agency – Funding Scenario
Potential Funding Scenario/ Funding Gap Analysis(in millions)
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
$1,800
Funding Gap $1,172 $971 $450 $1,177
Toll Bonds $125 $125 $100 $120
IDOT Funds $227 $227 $210 $227
SAFETEA-LU Earmark $239 $239 $239 $239
MRB 70/64/3:$1A/$3T MRB 70/64-$1A/$3T MRB 70: $1A/$3T MRB 70/64/3: $2A/$4T
Public-Private Partnership ConcessionPublic-Private Partnership Concession• 75-Year Concession Period
• 99-Year Concession Period
Public-Private Partnership Concession:Potential Bid Value
Public-Private Partnership Concession:Potential Bid Value
75-Year Concession Value
Percent of Total Project Costs
99-Year Concession Value
Percent of Total Project Costs
MRB 70/64/3$1 auto / $3 truck
$235-$335 M
13-19%$325-$470
M18-27%
MRB 70/64$1 auto / $3 truck
$235-$330 M
15-21%$330-$460
M21-24%
MRB 70$1 auto / $3 truck
$185-$250 M
19-25%$260-$350
M26-35%
MRB 70/64/3$2 auto / $4 truck
$180-$360 M
10-20%$254-$490
M14-28%
Private Concession: 75-Year Funding ScenarioPrivate Concession: 75-Year Funding Scenario
Potential Funding Scenario/ Funding Gap Analysis(in millions)
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
$1,800
Funding Gap $962 $768 $300 $942
Private Concession $335 $328 $250 $355
IDOT Funds $227 $227 $210 $227
SAFETEA-LU Earmark $239 $239 $239 $239
MRB 70/64/3:$1A/$3T MRB 70/64-$1A/$3T MRB 70: $1A/$3T MRB 70/64/3: $2A/$4T
Private Concession: 99-Year Funding ScenarioPrivate Concession: 99-Year Funding Scenario
Potential Funding Scenario/ Funding Gap Analysis(in millions)
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
$1,800
Funding Gap $829 $640 $203 $804
Private Concession $468 $456 $347 $493
IDOT Funds $227 $227 $210 $227
SAFETEA-LU Earmark $239 $239 $239 $239
MRB 70/64/3:$1A/$3T MRB 70/64-$1A/$3T MRB 70: $1A/$3T MRB 70/64/3: $2A/$4T
What is the Funding Potential? (Order of Magnitude Estimates)What is the Funding Potential? (Order of Magnitude Estimates)
Public Toll Agency Approach
Public-Private PartnershipConcession Approach:
75-Year Period
Public-Private PartnershipConcession Approach:
99-Year Period
$80 - $160 M $180 - $360 M $250 - $470 M
Key Findings: Financing the ProjectKey Findings: Financing the Project• Tolling significantly reduces the
effectiveness of all alternatives• However, in the absence of other viable
sources, tolling and PPP/Concession could provide funding to partially offset shortfall―Remaining shortfall for MRB 70/64 is in the
range of $700 M
• Concession approach could create difficulty in improving existing free bridges, approach ramps, and connections
• Funding shortfall for MLK Coupler is approximately $100 M
Choices for the FutureChoices for the Future
• Can all parties agree on numbers and forecasts?
• Can Missouri and Illinois find common ground?―If there are insufficient sources of funds, will
Illinois accept “discounted” tolls for Illinois residents to achieve equity?
―If a toll authority or concession cannot be achieved, will Missouri accept the MLK Coupler alternative?
• Is the St. Louis business community willing to “pitch in?”
• In the absence of consensus, should the committed funds be used for early action projects, and defer building the bridge?
Choices for the FutureChoices for the Future
Option 1:
• Move forward with most significant components of new bridge: MRB 70/64
• Close funding gap Identify additional
funding sources – public/private
Achieve consensus on tolling
Choices for the FutureChoices for the Future
Option 2:
• Move forward with MLK “Coupler”
• Initiate design and environmental studies
• Close funding gap Identify additional
public funding sources
Choices for the FutureChoices for the Future
Option 3:
• Move forward with improvements to the existing bridges I-70/I-64 “tri-level”
interchange Connections from
Poplar Bridge to Interstates
• Leaves open the possibility for future new bridge
Choices for the FutureChoices for the Future
Option 4:
• Do nothing
• Reprogram federal earmarked funds
Mississippi River Bridge
An Analysis of Alternatives
Mississippi River Bridge
An Analysis of AlternativesFinal Report Presentation
January 31, 2007
Final Report PresentationJanuary 31, 2007
Sharon Greene & Associates