MISSION/I-880 PROJECT. MISSION/I-880 PROJECT. PROJECT INFORMATION Construction started in April 2005 Approximately 3-4 years construction period Construction Admin by Caltrans Joint funding by ACTA, City of Fremont, and Caltrans, Alameda RIP Funds. I-880. Route 262. NUMMI Access. - PowerPoint PPT Presentation

Citation preview

DISTRICT 04

MISSION/I-880 PROJECT

DISTRICT 04

MISSION/I-880 PROJECT

• PROJECT INFORMATION– Construction started in April 2005 – Approximately 3-4 years construction period– Construction Admin by Caltrans– Joint funding by ACTA, City of Fremont, and

Caltrans, Alameda RIP Funds

DISTRICT 04

W. Warren

NUMMI AccessI-880

Route 262

Photo taken in 1998 - not current

DISTRICT 04

NUMMI Access

W Warren

Kato Road

Route 262I-880

Photo taken in 1998 – not current

DISTRICT 04

Route 262

E Warren

Kato Road

NB 880 Connector

NUMMI Access

RR UP

Photo taken in 1998 – not current

DISTRICT 04

MISSION/I-880 PROJECT

• PROJECT SCOPE

– New Warren Avenue Interchange

– New Route 262/I-880 Connectors

– New Kato Overcrossing

– Widen I-880 from Fremont Blvd. To Dixon Landing

– Re-stripe I-880 to Route 237

DISTRICT 04

Photo taken in 1998 – not current

Project Scope

DISTRICT 04

NEW WARREN AVENUE INTERCHANGE

Photo taken in 1998 – not current

DISTRICT 04

NEW CONNECTORS

Photo taken in 1998 – not current

DISTRICT 04

NEW CONNECTORS

Photo taken in 1998 – not current

DISTRICT 04

NEW KATO OVERCROSSING

Photo taken in 1998 – not current

DISTRICT 04

WB262-SB880

Warren OC & Connector

Kato OC

SB880-EB262

Photo taken in 1998 – not current

NEW BRIDGES

DISTRICT 04

W. Warren

NUMMI AccessI-880

Route 262

Widen I-880 to DIXON LANDING & Restripe to Rte. 237

Photo taken in 1998 – not current

DISTRICT 04

W. Warren

NUMMI AccessI-880

Route 262

Widen I-880 to DIXON LANDING & Restripe to Rte. 237