Mission Bay Ferry Landing Design Development & Permitting

1

Page 2: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

Informational PresentationMission Bay Ferry Landing - Setting

2

Page 3: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

Why is a Ferry Landing Needed? 

• Long Planned for Improvement

• Water transportation between central waterfront, downtown and East and North Bays.

• 46-acre, 550-bed UCSF Mission Bay Hospital

• UCSF Campus• 18,000-seat Golden State

Warriors Arena• 7,000,000 ft2 of New

commercial space• 1,000,000 ft2 of New retail

space• New hotel• 11,000 New housing units

3

Page 4: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

Ferry LandingOverview

• 4 alternate sites studied• Coordination with WETA,

BAE, GGBHTD, and other project stakeholders

• Wave & coastal analysis• Dredging requirements• Access to nearby public

transportation• Estimated total cost ranges

from $32.5 to $42.7 million depending on the location selected.

Page 5: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

Site Selection Criteria

5

Criteria• Proximity to Employment and Active Uses• Connectivity to other public transit• Maritime and other operational considerations

o Ability to operate under storm conditionso BAE Navigational needso Navigation around submerged Pier 64

• Protection from wave and storm action• Ease of permitting (USACOE)• Distance from Terry Francois Boulevard• Compatibility with Bayfront and Agua Vista Park

Page 6: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

Status Since June 2016

6

• Released and RFP for a design and permitting Team- COWI selected

• Narrowed Site to two locations• Identified Preferred Site• Ridership modeling (WETA/SFCTA)• Sediment Sampling for dredging strategy/cost• Analyzed ways to deliver early (2020/21)• Working on securing Capital Funds

o Grantso Federal/Local Transportation (OBAG- RM3, TIGER)o Transportation Impact Feeso Private

• Continued Public outreach

Page 7: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

7

Site Selected

Page 8: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

8

Site Selected

Page 9: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

9

Site Plan

Page 10: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

10

Mission Bay Ferry Landing

Page 11: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

11

Mission Bay Ferry Landing

Page 12: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

12

Mission Bay Ferry Landing

Page 13: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

13

Mission Bay Ferry Landing

Page 14: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

Next Steps• Conduct ongoing public outreach• Meet with permitting agencies

o USACOEo RWQCBo BCDCo SF Planning for CEQA

• Architectural /Landscape Architecture design

• 30% design complete by September 2016• Design Review• Start Construction June 2019• Operational Winter 2020/21 14

Page 15: Mission Bay Ferry Landing Design Development Permitting CWAG 6-5-17.pdfMicrosoft PowerPoint - MBFT CWAG 6-5-17.ppt [Compatibility Mode] Author: dbeaupre Created Date: 6/8/2017 11:27:21

Any Questions? 