Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Chairman
1
Minutes of the 53rd
meeting of the
State Level Expert Appraisal Committee (SEAC)
held on 10th
to 13th
April, 2012 at 10:00 A.M.
The following members were present for the committee meeting.
Member Secretary SEAC, Environment Department welcomed the members of the
committee.
1. Dr. Sukumar Devotta
... Chairman 10th to 13th April, 2012
2. Er. G. K. Deshpande
… Member 10th to 13th April, 2012
3. Ar. Mukund S. Athavale
… Member 10th & 13th April, 2012
4. Dr. Prashant P. Bhave
… Member 10th to 13th April, 2012
5. Prof. Tarun Kant
… Member 10th to 13th April, 2012
6. Dr. Jay S. Samant
… Member 10th,12
th & 13th April,
2012
7. Er. Chandrakant I. Sambutwad
… Member 10th to 13th April, 2012
8. Er. Balbir Singh Sehgal
… Member 10th to 13th April, 2012
9. Shri A. R. Parshurame
… Member
Secretary
10th to 13th April, 2012
Chairman
2
Discussion Item 1
Subject: Pending praposals
SEAC noted that as on date, around 650 proposals are pending for appraisal. It was
decided to convene SEAC meeting twice in a month to clear this backlog. It is also noted that
some PPs’ concern about their inability to attend the meeting due to insufficient time they get for
preparation. Considering this it was decided to request Environment Department to display the
pending list on the website. Environment Department may verify the chronology from the
available documents and display the pending list in phase-wise manner (say the list of 200
proposals in two months). The agenda for SEAC meetings will also be prepared based on the
priority list and the completeness of the information provided by PP. The final list will be
displayed on the web after the approval of ED. ED will also request PPs to submit the required
information and copies of EIA reports. EIArReporst must be submitted to the SEAC members 10
days before the meeting. Proposals of PPs failing to submit the required information/EIA Reports
within the stipulated time to the Environment Department may be deferred to the next meeting.
Chairman
3
Discussion Item 2
Subject: TOR for the industrial projects
Many requests are being received from the PPs to issue a formal TOR by way of a letter.
It is therefore decided to circulate Model ToR for all sectors related to Category B to all SEAC
Members. Model ToRs will be fianalized accordingly in the next 10 days. Finalizaed Model
ToRs will be then uploaded on the website. All pending cases for ToR will be considered in next
few SEAC meetings. Additional project specific points, if any, may be prescribed in addition to
the corresponding Model ToR. ToR will be issued accordingly. This will save a lot of time of the
SEAC meeting and assist all in reducing the waiting time for TOR by PPs.
Chairman
4
Discussion Item 3
Subject: Minutes correction of the 44th
meeting of the SEAC for the item no. 18 and 19.
The Project proponent has submitted the letter dated 17th
February, 2012 for requesting
change in a 44th
SEAC minutes held on 13th
September, 2011 as details were wrongly
mentioned (typographical mistake as slight mix up of areas).
After verifying the documents following corrections in the 44th
SEAC minutes of the
meeting are approved:
For the Item No. 18 of the 44th
meeting of the SEAC
Point No. 1: “Name of the Project and location: Majra Limestone Mine (of area 11.898 hectares)
at village Wanjri, Tahsil Wani, District Yavatmal” mentioned in the 44th SEAC
minutes is replaced by “Majra Limestone Mine (of area 11.72 hectares) at village
Majra, Tahsil Wani, District Yavatmal.
Point No. 2: “Previous consideration/s: 34th SEAC mtg dt. 30
th September, 2010” mentioned in
the 44th SEAC minutes is replaced by 12
th SEAC mtg dt. 28th May, 2009.
For the Item No. 19 of the 44th
meeting of the SEAC
44th
SEAC minutes of the meeting
Point No. 1: “Name of the Project and location: Wanjri Limestone Mine (of area 8.863 hectares)
at village Wanjri, Tahsil Wani, District Yavatmal” mentioned in the 44th SEAC
minutes is replaced by “Majra Limestone and dolomite Mine (of area 18.83 hectares)
at village Majra, Tahsil Wani, District Yavatmal.
Point No. 2: “Previous consideration/s: 34th SEAC mtg dt. 30
th September, 2010” mentioned in
the 44th SEAC minutes is replaced by 12
th SEAC mtg dt. 28th May, 2009.
Point No. 3: “Brief details of the project (as per the proposal): “Lime stone mining” mentioned
in the 44th SEAC the minute is replaced by “Limestone and dolomite Mine”.
Chairman
5
Item No. 1
Subject: Environmental clearance for the Proposed Residential construction project –
“Marvel Arco” at Hadapsar, Tal Haveli, Dist: Pune by M/s. Marvel Sigma Homes
Pvt. Ltd.
(File No.: SEAC 2011/CR41/TC2) (New case)
The Project Proponent explained the proposal before the committee and committee noted
project details furnished by the Project Proponent as:
Name of the Project : Residential construction project “Marvel Arco”
Project Proponent : M/s M/s. Marvel Sigma Homes Pvt. Ltd
Consultant : M/s. Oasis Environmental Foundation
Category : 8(a)- B2
Location of the
project
: Sr.No. 176(parts) Hadapsar, Tal – Haveli, Dist: Pune.
Type of Project : Residential project
Plot Area : 25,400.00 m2
Proposed Total built
up area
: Total BUA : 42,582.00 m2
Ground coverage
area (%)
33.8 %
Estimated cost of the
project
: Rs.76 Cr
No. of Buildings : • Residential buildings: 6 Nos.
• Tenements: 228 Nos.
• Building configuration: 2 Basements + 1 Stilt + 12 floors
Height of building 37.50m
Water Requirement • Fresh Water: 128 m3/day
• Recycled water : 75 m3/day
Rain water
harvesting
No. of Recharge pits: 5 with 1.5 m x 2.5 m deep & 75 m deep bore
well.
Wastewater
generated
152 m3/day
Capacity of STP 160 m3/day, STP technology: FBBR (Fluidized Bed Bio Reactors)
Chairman
6
Solid Waste
Generation
• Biodegradable waste: 342 kg/day
• Non biodegradable waste: 210 kg/day
• STP Sludge (Dry sludge): 23 kg/day
Disposal • Use of Organic Waste Converter and disposal of compost in own
landscape.
• Dry STP sludge to be used as manure.
Energy • Energy requirement:3665 units/day, Source: MSEDCL
• DG set: 500 KVA x 3 No.
Energy
Conservation
• Use solar hot water system
Traffic Management • Parking area: 9764 Sq.m
• 4‐Wheeler : 252 Nos
• 2‐Wheeler : 501 Nos
• Bicycle: 501
• Width of internal rods: 6.0 – 9.0 m
Green Belt
Development
• Total R.G area: 3851 m2 (15%)
• RG area on the ground : 3711 m2
• RG area on the podium : 140 m2
• No. of trees to be planted: 340
Environment
Management Plan
• Capital cost: 1.16 Cr
• Operation and Maintenance cost: 11.74 Lakh.
Decision:
The case was discussed on the basis of the presentation made by the proponent. The PP has
submitted the Pre-certification for Green Building from Indian Green Building Council.
It is noted that the project proponent initiated the construction work without obtaining the prior
environmental clearance. Environment Department may look into matter and take necessary
action. As the presentation was not comprehensive, only preliminary assessment was made.
The PP is directed to comply with the following observations:
1. Submit site photographs from different corners of the plot.
2. PP shall make adequate temporary residential arrangement for the labours (including those
from other neighbouring plots) presently residing on the plot.
3. Consent for water supply and drainage from competent authority shall be obtained.
Chairman
7
4. Charasteristics of treated waste water shall be submitted.
5. Provision of Solar PV shall be considered wherever appropriate.
6. The project proponent shall draw up a sustainable model with appropriate EMP, as the
proposed EMP (O&M) is inadequate.
7. Use of the terminology “Podium” shall be consistent and appropriately followed.
8. Layout showing fire tender movement shall be submitted.
9. Under ground tanks shall not be located below internal roads.
10. Submit the exact layout drawing of basement as it differs in Landscape Design Layout and
Service Layout.
11. Proper arrangements for ventilation to be ensured in basement.
12. Clear 6 m width with appropriate turning radius of shall be provided for the fire tender
movement without any obstruction. The plan depicting the same shall be submitted.
13. The existing trees ( 7 nos) on the plot are to be preserved and 385 new trees to be planted.
Shrubs (100 nos) of different species to be planted on the podium and similar area ( 92 m2).
14. Trees of species ‘Sice’ and ‘Terminalia’ shall be planted on the bank of nalla.
The comprehensive assessment will be done after submission of above compliance.
Chairman
8
Item No. 2
Subject: Environmental clearance for the “Marvel Kyra” Residential Construction Project
at Sr.No. 134 (parts) Hadapsar, Taluka: Haveli, Dist: Pune by M/s. Marvel Sigma
Homes Pvt. Ltd.
(File No.: SEAC 2011/CR 11/TC2) (New case)
The Project Proponent explained the proposal before the committee and committee noted
project details furnished by the Project Proponent as:
Name of the Project : “Marvel Kyra” Residential Construction Project
Project Proponent : M/s M/s. Marvel Sigma Homes Pvt. Ltd.
Consultant : M/s. Oasis Environmental Foundation
Category : 8(a)B2
Previous
consideration/s
: Nil
Location of the
project
: Sr.No. 134 (parts) Hadapsar, Taluka: Haveli, Dist: Pune
Type of Project : Residential project
Plot Area : 24,600 m2
Proposed Total built
up area
: FSI : 30,400 m2
Non FSI : 27,872 m2
Total BUA : 58,223 m2
Ground coverage
area
7,090 m2 (29%)
Estimated cost of the
project
: Rs. 75 Cr
No. of Buildings : • Residential buildings: 3 Nos.
• Commercial building: 1 No.
• Tenements: 115 Nos.
• Residential Building configuration: 2 Basement + 1 Stilt + 26
floors
• Commercial Building configuration: Ground + 2 floors
Height of building Residential: 99.93 m
Commercial:12 m
Water Requirement • Fresh Water: 80 KLD
• Flushing :- 35 KLD
• Gardening:- 44 KLD
Chairman
9
Rain water
harvesting
• Pit Size: 1.5 m x 2.5 m deep & 75 m deep bore well
• No of Recharge Pits: 06 Nos.
Wastewater
generated
89 KLD
Capacity of STP 90 KLD m3/day
Solid Waste
Generation
• Biodegradable waste: 198 kg/day
• Non biodegradable waste: 119 kg/day
• STP Sludge (Dry sludge): 12 kg/day
Disposal • Use of Organic Waste Converter and disposal of compost in own
landscape.
• Non biodegradable waste will be handed over to the authorized
recycler.
• Dry STP sludge to be used as manure.
Energy • Energy requirement: 3233 units/day, Source: MSEDCL
• DG set: 500 KVA x 4 No.
Traffic Management • Parking area: 13991 m2
• 4‐Wheeler : 393 Nos.
• 2‐Wheeler : 604 Nos
• Bicycle: 278 Nos.
• Width of internal rods: 9.0 m
Green Belt
Development
• Total R.G area : 6170.00 m2
• RG area on the ground : 6170.00 m2
• Landscape area : 6170 m2
• Shrubbery area : 290.27 m2
• Ground cover : 2786.14 m2
• Proposed Plantation : 451 Trees
Sr Botanical Name Common Name No.
1. Alstonia scholaris Saptaparni 52
2. Anthocephallus cadamba Kadamb 01
3. Bauhinia blackeana Kanchan 13
4. Bauhinia purpurea Rakta kanchan 37
5. Caryota urens Fishtail palm 02
6. Cassia Fistula Bahava tree 36
Chairman
10
7. Callistemon Bottle brush 14
8. Cordia sebestina Cordia 24
9. Lagestromia racemosa - 24
10. Michelia champaca Champaca 06
11. Millingtonia hortensis Indian cork tree 03
12. Mimusops elengi Bakul tree 05
13. Nyctanthes arbortristis Parijatak 03
14. Peltophorum Copper pod 76
15. Plumeria alba Frangipani white 18
16. Plumeria rubra 12
17. Pongamia pinnata Karanj 17
18. Saraca asoka Sita ashok 48
19. Spathodea campanulata African tulip tree 59
20. Terminrlia catappa Badam 01
Total 451
Landscape area (sq. m.) 6170
Environment
Management Plan
• Capital cost: 97 Lacs • Operation and Maintenance cost: 9.55 Lac/year
Decision:
The case was discussed on the basis of the presentation made by the proponent. The PP has
submitted the Pre-certification for Green Building from Indian Green Building Council.
The PP is directed to comply with the following observations :
1. Submit site photographs from different corners of the plot.
2. As per the guidelines issued by MoEF for High Rise Buildings vide O.M. no. 21-270/2008-
IA.III dated 7th February, 2012, for buildings with height greater than 60 m the minimum
width of the road (right of way) is 30 and the nearest fire station should be located within
Chairman
11
distance of 2 km. The DP map submitted by the PP for the area shows the width of the road
to as 24 m and the height of the residential building proposed is more than 60 m. Therefore,
the PP shall recast the project proposal complying with the MoEF guidelines for High Rise
Building.
3. Consent for water supply and drainage from competent authority shall be obtained.
4. Submit a note on energy conservation measures in accordance with ECBC guidelines.
5. Submit details of STP and its location.
6. Out of 90 nos. of existing trees, 77 are to be retained, 13 are to be transplanted and 530 new
trees are to be planted. Shrubs (50 nos.) to be planted.
7. Submit a note on the existing trees, trees to be cut, trees to be transplanted and trees to be
planted (nos., size, age, and species) as per MoEF guidelines. In the list of trees, inclusion of
bushes to be removed and one species viz. India Cork Tree to be included.
As the project needs total recast pursuant to compliance of guidelines issued by MoEF for High
Rise Buildings, comprehensive assessment will be done after submission of above compliance.
Chairman
12
Item No. 3
Subject: TOR for the proposed industrial project at Village Savarsai, Pen Khopoli Road,
Tal. Pen, Dist. Raigad by M/s Echjay Industries Pvt. Ltd.
(File No.: SEAC 2011/CR-2401/TC-2) (TOR case)
The PP was absent.
Chairman
13
Item No. 4
Subject: TOR for the proposed expansion of industrial project at D-101, MIDC Malegaon,
Sinnar, Dist. Nashik by M/s Bhagwati Steel Cast Ltd.
(File No.: SEAC 2011/CR-9/TC-2) (TOR case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : M/s Bhagwati Steel Cast Ltd
Category : 3(a) – B1 [Metallurgical Industries]
Project Proponent : M/s Bhagwati Steel Cast Ltd
Consultant : M/s. Pollution and Ecology Control Services, Nagpur
Location of the project : D-101, MIDC Malegaon, Sinnar, Dist. Nashik
Type of Project : Metallurgical Industry
Previous consideration/s : Nil
Total Plot Area : Total Plot area: 16421 m2
Built up area: 5029 m2
Project cost : Existing : 14.22 Crores
Expansion : Rs. 1.5 Crores only in plant & machinery
Products : Product Existing Expansion Total
M.S. Ingots 2700 MT/M 3550 MT/M 6250 MT/M
CTD Bars & Rods 3500 MT/M 2500 MT/M 6000 MT/M Raw materials : List of raw
materials to
be used
Quantity
(tonnes/month) full
production capacity
Source of
materials
M S Scrap
3105 MT/Month (Existing)
4085 MT/Mont ( Expansion)
Domestic &
Imported
MS Ingots 3675 MT/Month (Existing)
2675 MT/Mont( Expansion)
Captive
consumption +
Domestic
procurement
Manufacturing process Manufacturing of M.S. Ingots:
Manufacturing of M. S. Ingots involves a process of melting M. S.
Scrap in a coreless medium frequency induction furnace and
converting it to liquid steel and subsequently to ingots. Specially
Chairman
14
required M. S. Scraps are procured from the market and tested for
their basic contents and grades. The approved and selected lots of the
said scraps are then fed into the induction furnace at medium
frequency and heated. The heat in the furnace heats up the scrap and
when the intensity of the heat reaches the melting point of steel, the
scraps start melting in the furnace crucible. When the total scrap as
per the capacity of the crucible is molten, the sample is taken from
liquid steel and tested for the composition of steel and the carbon
contents. Therefore some additives of ferro-alloys like Silico-
managanese, silicon, aluminum shots and boric acid are added to the
liquid steel to maintain the composition and quality. After
confirmation of the carbon content the liquid steelis poured into the
specially designed heated moulds for it to be given the desired shape
and size. After they are molded into the desired shapes, the strippings
are removed and they are finally given the dressing i.e. cleaning and
removal of unwanted particles finishing cleaning etc.The said
hot/cold ingots are removed to the storage site or trucks with the help
of hot and cold magnetic cranes for further dispatch. Thereafter they
are assembled and bundled and sent for onward dispatch.
Manufacturing Process details for Rolling Mill:
Qualitative raw materials MS Ingots & Billets is being tested and
push in re-heated furnace. The heated ingot & billet piece comes to
roughing mill 1st stand. There are 7 nos. passes in 1st stand then goes
to 2nd stand, 3rd stand from roughing mill. It goes to inter mill via
passing, rotary shearing and pinch roll. There are 6 stands in inter
mill where it got the finish size. From the inter mill, it goes to pinch
roll , then it passes through flying shearing where it is being cut for
required length. The small pieces cut from the cooling bed lying
rolled product and being tested for size,% Elongation, Bend & Re
bend and weight per meter. After visual inspection the bar being
bundled and keep in lot for dispatch.
Water Requirement : Total water required: 140. 5 m3/day; Source: MIDC
Quantity of recycled water: 110 m3/day (cooling water) Solid waste • Metal Slag & Fine Dust: 40 MT/M ( Existing) and 90 MT/M
(Expansion)
• Mill Scale ( from Rolling Mill): 100 MT/M ( Existing) and
80 MT/M (Expansion)
• Sludge from APC: 5 MT/M (Existing) and 5 MT/M (Expansion)
Solid waste is land filled at present within premises. It is proposed
to install slag crusher for metal fines recovery. Further the ground
slag can be used as building material and additive in cement mill.
Effluent Generation : Domestic effluent : 20 CMD
Air Pollution Control : Wet Scrubber with common stack of height 25 m
Chairman
15
Green Belt Development : 4000 m2, Proposed nos. of trees: 100 Nos.
Fuel Daily Consumption (TPD/KLD)_ Sr
Fuel
Existing Proposed
1 Furnace Oil
(used as stand by fuel
in rolling mill)
5000 Lit Per
Day
Nil
2 Coal 15 T 10 T
3 Electricity 6.3 MW Nil Energy Requirement : 6.3 MW (MSEDCL)
Environmental
Management Plan
: Capital cost: Rs.77,00,000/- O&M cost: Rs. 7,50,000/-
Decision:
The PP informed that they are proposing one more project at G-7, MIDC Malegaon, Tahsil
Sinnar, Dist. Nashik located at 2 km distance from the above proposed one(i.e. D-101, MIDC
Malegaon) and of same nature. The PP requested to consider both these project for issuance of
ToR. SEAC agreed for the same. The details of the other proposed project are as below:
Name of the Project : M/s Bhagwati Steel Cast Ltd
Category : 3(a) – B1 [Metallurgical Industries]
Project Proponent : M/s Bhagwati Steel Cast Ltd
Consultant : M/s. Pollution and Ecology Control Services, Nagpur
Location of the project : G-7, MIDC Malegaon, Tahsil Sinnar, Dist. Nashik
Type of Project : Metallurgical Industry
Total Plot Area : 88,000 m2
Products : M S Billets – 25000 TPM
Raw materials : M S Scrap 28000 TPM
Ferro Manganese 200 TPM
Ferro Silicon 50 TPM
Both the proposals were discussed on the basis of the presentation made by the proponent. The
PP has been advised to carry out the independent EIA studies for both the sites considering the
various comments made by the committee and the model TOR prescribed (Page No 127) and
then approach the committee for the appraisal. A QCI accredited consultant and MOEF/NABL
accredited lab shall be used for the preparation of EIA Report.
Chairman
16
Item No. 5
Subject: Environmental clearance for the proposed Establishment of 12 MLD CETP at
R.S. No. 610 A, Ichalkaranji Tal: Hatkanangale, Dist: Kolhapur by M/s.
Ichalkaranji Textile Development Cluster Ltd., Ichalkaranji
(File No.: SEAC 2011/CR-953/TC-2) (TOR case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : 12 MLD CETP for Small & Medium Scale Textile Process
Industries
Category : 7(h) – B 1
Project Proponent : Mr. G. R. Akiwate.Managing Director, Ichalkaranji Textile
Development Cluster Ltd.,
Location of the project : R.S. No. 610 A, Ichalkaranji Tal: Hatkanangale, Dist: Kolhapur
74.28 E, 16.41 N, MSL = 548 m
Type of Project : Common Effluent Treatment Plant
Total Plot Area : 10568 m2 (BUA = 2165 m
2)
Project cost : 22.75 Cr
Products : This project is for construction of CETP
Raw materials :
During Construction : Aggregate – 6000 MT, Cement – 3250 MT, Steel – 425 MT, Sand – 11200
MT, Excavation – 7000 Cum
During Operation :
Sr Name Number
of
Storage’s
Capacity
( TPD )
Physical
and Chemical
Composition
Consumption
( in TPD )
Maximum
Quantity of
storage at any
point of time
1
2
3
4
Hydrated Lime
Ferrous Sulfate
Sodium
Hypochlorite
Polyelectrolyte
One
One
One
One
25 M.T
25 M.T.
6 M.T.
1 M.T.
Calcium
Iron
Sodium
Acryl amide
3 TPD
3 TPD
0.2 TPD
24 KG/Day
20 M.T.
20 M.T.
6 M.T.
1 M.T.
Water Requirement : Construction Phase- 50 m
3/day – Bore well water.
Operational phase for domestic purpose- 10 m3/day from
Chairman
17
Ichalkaranji Municipal supply.
Effluent Generation : Domestic waste 7 m3/day shall be combined with industrial
effluent and send to CETP.
12000 m3/day disposed off into ‘Kala Nala’
ETP / STP capacity : 12 MLD CETP
Solid waste management : ETP Sludge = 350 TPM (Primary Sludge) & 87 TPM (Secondary
Sludge) - Sludge will be sent to CHWTSDF
Area in Sq.mtr : 3000 m2 Green Belt Development :
Existing nos. of trees ,
Proposed nos. of trees with
plant species
Existing No of trees- Nil
Proposed No of trees- 500
Energy Requirement : 1 MW, DG set – 1000 KVA
Environmental
Management Plan
: Sr. Item Recurring Cost
(Lakh / Y)
Capital Cost
(Lakh)
1 Air Pollution
Control
1 5
2 Water Pollution
Control
620 2200
3 Noise Pollution
Control
- 19
4 Environment
Monitoring and
Management
25 15
5 Reclaimation borrow
/mined area
- -
6 Occupational Health 1 1
7 Green Belt 0.5 1
8 Solid waste
management
175 34
9 Others -
Total (Lakh) 822.5 2275
Decision:
The case was discussed on the basis of the presentation made by the proponent. It was noted that
the project is implemented pursuant to issuance of Consent to Establish by MPCB, however for
some reason prior Environmental Clearance was not obtained. ED may look intot he matter and
take appropriate action.
The PP is directed to comply with the following observations:
Chairman
18
1. Submit the history of the project with explanatory notes and documentary evidences.
2. Justification for implemenating the project without obtaining prior Environmental
Clearance.
Considering the status of project, the Committee agreed to issue ToR in the interest of
environment. The project proponent has been advised to carry out EIA study considering the
model TOR prescribed (Page No111 ) and following additional aspects:
1. In view of the textile waste water, TDS removal shall be considered.
2. Arrangement for handling, temparory storage, transportation and disposal of large
quantity of sludge generated.
3. The PP shall draw up a sustainable model with appropriate EMP.
4. Recycle of treated waste water in the interest of water conservation.
5. Public consultation as per MoEF guidelines.
After completion the of EIA studies and Public Consultation PP may approach the committee for
the appraisal. A QCI accredited consultant and MOEF/NABL accredited lab shall be used for the
preparation of EIA Report.
Chairman
19
Item No. 6
Subject: Environmental clearance for the proposed Establishment of 1 MLD CETP at Plot
No 7-11 Phase I Sector – B, Shri Laxmi Co-op. Industrial Estate Ltd., Tal:
Hatkanangle, Dist: Kolhapur by M/s. Ichalkaranji Textile Development Cluster
Ltd., Ichalkaranji
(File No.: SEAC 2011/CR-954/TC-2) (TOR case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : 1 MLD CETP for Small & Medium Scale Textile Process
Industries
Category : 7(h) – B1
Project Proponent : Mr. G. R. Akiwate. Managing Director, Ichalkaranji Textile
Development Cluster Ltd., Ichalkaranji,
Location of the project : Plot No. 7,8,9,10,11, Phase I Sector – B,
Shri Laxmi Co-op. Industrial Estate Ltd., Tal: Hatkanangle.
16 0 44’N and 74
0 25’ E
Type of Project : Common Effluent Treatment Plant
Total Plot Area : 3514 m2 ( BUA = 540 m
2)
Project cost : 2.88 Cr
Products : This project is for construction of CETP
Raw materials :
During Construction : Aggregate – 1000 MT, Cement – 530 MT, Steel – 70 MT, Sand – 1000 MT,
Excavation – 5000 Cum
During Operation :
Sr Name Number
of
Storage’s
Capacity
( TPD )
Physical
and Chemical
Composition
Consumption
( in TPD )
Maximum
Quantity of
storage at any
point of time
1
2
3
4
Hydrated Lime
Ferrous Sulfate
Sodium
Hypochlorite
Polyelectrolyte
One
One
One
One
10 M.T
10 M.T.
0.5 M.T.
60 KG
Calcium
Iron
Sodium
Acryl amide
0.3 TPD
0.3 TPD
16 KG/Day
2 KG/Day
10 M.T.
10 M.T.
0.5 M.T.
60 KG
Water Requirement : 5 CMD
Chairman
20
Effluent Generation : Domestic waste 3.5 m3/day shall be combined with industrial
effluent and send to CETP.
ETP / STP capacity : 1 MLD CETP
Solid waste management : ETP Sludge = 19 TPM (Primary Sludge) & 7 TPM (Secondary
Sludge) - Sludge will be sent to CHWTSDF
Area in Sq.mtr : 1000 m2 Green Belt Development :
Existing nos. of trees ,
Proposed nos. of trees with
plant species
Existing No of trees- Nil
Proposed No of trees- 150
Energy Requirement : 0.2 MW, DG set – 200 KVA
Environmental
Management Plan
: Sr. Item Recurring Cost
(Lakh/Y)
Capital Cost
(Lakh)
1 Air Pollution
Control
0.5 5
2 Water Pollution
Control
40 253
3 Noise Pollution
Control
- 7
4 Environment
Monitoring and
Management
15 7
5 Reclaimation borrow
/mined area
- -
6 Occupational Health 0.5 0.5
7 Green Belt 0.15 0.50
8 Solid waste
management
18 15
9 Others -
Total 74.15 288
Decision:
The case was discussed on the basis of the presentation made by the proponent. It was noted that
the project is implemented pursuant to issuance of Consent to Establish by MPCB, however for
some reasons prior Environmental Clearance was not obtained. ED may look intot he matter and
take appropriate action.
The PP is directed to comply with the following observations:
Chairman
21
1. Submit the history of the project with explanatory notes and documentary evidences.
2. Justification for implemenating the project without obtaining prior Environmental
Clearance.
Considering the status of project, the Committee agreed to issue ToR in the interest of
environment. The project proponent has been advised to carry out the EIA study considering the
model TOR prescribed (Page No111 ) and following additional aspects:
1. In view of the textile wastewater, TDS removal shall be considered.
2. Arrangement for handling, temparory storage, transportation and disposal of large
quantity of sludge generated.
3. Recycle of treated waste water in the interest of water conservation.
4. The PP shall draw up a sustainable model with appropriate EMP.
After completion of EIA studies PP may approach the committee for the appraisal. A QCI
accredited consultant and MOEF/NABL accredited lab shall be used for the preparation of EIA
Report. Public consultation has been dispensed with as the plant is located in an industrial estate.
Chairman
22
Item No. 7
Subject: Environmental clearance for the Proposed SRA Project Balaji CHS (Prop) at
C.S.No. 167(Pt), 168, 169(Pt), 170(Pt), 171(Pt), 155(Pt), 658(Pt) of Parel Sewree
Division at G.D. Ambekar Marg, Jerbai Wadia Road, Mumbai-14 by M/s.
Renuka Realtors
(File No.: SEAC 2011/CR560/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : “Proposed Slum Rehabilitation Project”.
Project Proponent : M/s.Renuka Realtors
Consultant and
Accreditation
M/s. Ultra-Tech Environmental Consultancy & Laboratory
Category 8(a) B2
Location of the
project
: C. S. No. 167(Pt.), 168, 169 (Pt.), 170(Pt.), 171(Pt.), 155 (Pt.),
658(pt), 714 (Pt.), 715, 716, 717 (Pt.), 718 (Pt.), 719 (Pt.), 720
(Pt.), 989 (Pt.), of Parel Sewri Division, at G.D. Ambedkar
Marg, Jerabhai Wadia Road, Mumbai- 400 014.
Previous
consideration/s
47th meeting of SEAC held on 19.11.2011
49th meeting of SEAC held on 21.01.2012
Type of Project : Slum Rehabilitation Scheme.
Plot Area : Total plot area: 5863.62 Sq. mt.
Deduction: 372.54 Sq.m
Net plot Area: 5491.08 Sq.m
Proposed Total built
up area
: • FSI: 16420.47 Sq. mt. ( FSI :3.00)
• Non FSI: 25,048.81 sq. m.
• Total built up area: 41,469.28 sq. m.
Ground coverage
area
52 %
Estimated cost of the
project
: Rs. 186.40 Crores.
No. of Buildings and
its configuration
: Rehabilitation Building:
• One building of Ground + 13 Upper Floors.
• Flats: 277 nos.
• Shops: 13 nos.
• Balwadi: 4 nos.
Chairman
23
• Welfare Center: 4 nos.
• Society office: 4 nos.
Sale Building:
• One building of Part Basement(for services) + Ground+ 4
Parking Floors +5th floor for amenities+40 upper floors
• Flats: 99 nos.
• Shops: 15 nos.
Maximum Height of
building
• For Rehabilitation Building – 40.90 Mt.
• For Sale Building – 171.3 Mt
Total Water
Requirement
For Non Monsoon season:
Fresh Water:177m3/day[From M.C.G.M:174+From Tanker:3]
Recycled water: 92m3/day
Total water: 269 m3/day
For Monsoon season:
Fresh Water:177m3/day[From M.C.G.M:174+From Tanker:3]
Recycled water: 88m3/day
Total water: 265 m3/day
Sewage Generation • Rehabilitation:167 m3/day
• Sale:60 m3/day
STP capacity • Rehabilitation:185 m3
• Sale:70 m3
Storm water
drainage
• Quantity of storm water: 0.12m3/Sec
• Size of SWD:1 internal discharge point of 450 mm dia at
slope 1 250
Rain water
Harvesting
• 2 rain water harvesting tank of capacities 50 m3 for
rehabilitation building and 35 m3 for sale building.
• 4 no. of recharge pits.
Solid waste
management
• Dry waste: 275 Kg/day
• Wet waste : 613 Kg/day
• STP Sludge: 34 Kg/day
Disposal • There is provision for segregation and collection of bio-
degradable waste and recyclable waste within the premises.
• Wet garbage will be treated in an Organic Waste Converter
(OWC) and the dry garbage will be handed over to MCGM.
• Dried sludge from STP will be used as manure within the
premises for landscape development.
Green Belt
Development and
number of trees to
be planted
• R. G. Area: 779.13 m2
• Numbers and name of species of trees to be planted on ground
49 Nos.
• Number of shrubs to be planted: 28 nos.
Energy Requirement • Maximum demand: Rehabilitation:1117 KW, Sale:1585 KW
• D.G. Set: 1 D.G. set of 320 kVA (for rehabilitation building)
Chairman
24
& 1 D.G. set of 630 kVA (for sale building).
Traffic Management • Number of parking provided: 240 Nos
• Parking area: 6076.07 m2
Energy
Conservation
measures
• All lifts and pumps are proposed on VFD drives which
results in 30% saving in consumption.
• Provision of high energy efficient lamps (CFL).
• Use of solar energy for external lighting.
• Switch on and timer based lighting to be proposed on 30%
stages operation.
• Use of photo sensors.
Environmental
Management Plan
Construction phase: Capital cost:96 lakhs
Operation phase:
• Capital cost: 129.16 lakhs
• & M cost: 112.1 lakhs
Decision:
The case was discussed on the basis of the presentation made by the proponent.
It was noted that PP has already demolished existing structures without obtaining the prior
environmental clearance. Environment Department may look into the matter and take appropriate
action.
The water supply for the Sale building portion is likely to be available only after Completion of
‘Middle Vaitarana Project’.
It was further noted that the height of the proposed Sale building is 171 m and the width of the
access road is less than 30 m. This contravenes the guidelines issued by MoEF for High Rise
Buildings vide O.M. no. 21-270/2008- IA.III dated 7th February, 2012.
The PP has obtained the consent for water supply for a quantum of 45 LPCD for rehab, which is
much less than the recommended requirement of water, however, the PP has agreed to procure
the additional required water through tankers till the water supply is available from MCGM.
Considering above points, recommendation for prior Environmental Clearance for the project as
a whole is not possible. Therefore, SEAC decided to recommend the proposal for the prior
Environmental Clearance only for Rehabilitation Portion.
Chairman
25
If the above is acceptable, the PP shall provide independent OWC with adequate area, increase
RWH to reduce the freshwater requirement and revise EMP with adequate corpus for the Rehab
portion.
Chairman
26
Item No. 8
Subject: Environmental clearance for construction project - “PREMIA” at Village -Nerhe,
Dist.-Pune by M/s. CD Developers
(File No.: SEAC 2010/CR 731/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : Construction project - “PREMIA”
Project Proponent : M/s. CD Developers
Consultant : M/s. Ultra-Tech
Category : 8(a)- B2
Previous
consideration/s
: 50th meeting of the State Level Expert Appraisal Committee (SEAC)
held on 8th to 11th February, 2012
Location of the
project
: S.No. 35/2,35/3,35/4,35/5,35/6 ,34/3,34/2(P), Village Nerhe, Dist.-
Pune, State – Maharashtra
Type of Project : Construction Project
Plot Area : • Total Plot Area : 26654.68 m2
• Net Plot Area : 22115.03 m2
Proposed Total built
up area
: • FSI : 24052.91 m2
• Non FSI : 18783.47 m2
• Total : 42836.38 m2
Ground coverage
area (%)
24.41 %
Estimated cost of the
project
: Rs. 65.30 Crores
No. of Buildings : Residential:
• Bldgs A,B1,B2 = P+ 11 floors with 159 no of tenements
• C1,C2,D1,D2 =B+ P+ 11 floors with 212 no of tenements
• E and F types of row houses having 19 nos.
• Total No of Flats – 391Nos.
Commercial:
• 1 bldg having B+G+3 with 2nos of shops and 8 nos of offices.
Height of building 31.35 m
Chairman
27
Water Requirement Total Water Requirement = 317 CMD
Dry season:
• Narhe Grampanachayat for the domestic water: 182 CMD
• Tanker water: 8 CMD
• Recycled water: 127 CMD
Wet season:
• Narhe Grampanachayat for the domestic water: 112 CMD
• Tanker water: 8 CMD
• Recycled water: 96 CMD
Rain water
harvesting
• 2 nos. of RWH tanks having capacity 95 m3 of each
• 12 Nos. of RWH pits of 12.4 m x 5 m x 2.5 m
Wastewater
generated
241 m3 /day
Capacity of STP 255 m3
STP technology: Suspended Media Bio Reactor (SMBR)
Solid Waste
Generation
• Biodegradable waste: 639 kg/day
• Non biodegradable waste: 318 kg/day
• STP Sludge (Dry sludge): 33 kg/day
Disposal • Dry garbage will be segregated & disposed off to recyclers.
• Wet garbage will be composted using organic converter
technology and used as organic manure for landscaping.
• Dry STP sludge to be used as manure.
Energy • Source of power & supply capacity: 2120.7 kW
• DG set: 82.5 kVA and 100 kVA
Energy
Conservation
• CFL based lighting will be done in the common areas, landscape
areas, signage’s, Entry gates and boundary compound walls etc.
• Solar Street Lights will be provided for Internal Road.
• Timer Switch for Streetlight, Garden light, building staircase &
common passages of bldg. to be provided.
• Water Level Controller with Timer for water pumps system to be
provided.
Traffic Management • 4 W: 214 nos.
• 2 W: 433 nos.
• Bicycles: 494 nos.
Green Belt
Development
• Total R.G area: 5896.00 m2
• Trees to be plated inside the plot: 551Nos.
Chairman
28
• Existing trees details:
Botanical
Name
Common
name
Existi
ng
trees
(Nos)
Cutting
Trees
(Nos.)
Height
of tree
(mt)
Girt
h of
tree
(cm)
Age
(Year)
Mangifera
indica
Mango 2 0 4 60 5
Azadirachta
indica
limb 3 1 12 to
15
120 15
Syzygium
cumini
jambhul 3 2 15 90 10
Other Other 3 3 Environment
Management Plan
Construction phase: 9.5 lakhs
Operation phase:
• Capital Cost: 160.12 lakhs
• O&M Cost: 30.4 lakhs / annum
Decision:
The case was discussed on the basis of the presentation made by the proponent.
SEAC decided to recommend the proposal for Environmental Clearance only after complying
with following condition:
1. Rain water harvesting shall be maximized to minimize the fresh water requirement by
providing appropriate measures, including water storage facility.
Chairman
29
Item No. 9
Subject: Environmental clearance for the proposed “ARIHANT AKANKSHA” a
Residential cum Commercial project with Rental Housing Scheme of MMRDA
located at Survey no. 7/5, 14/6, 14/7, 15/1, 15/2(1), 15/2(2), 15/2(3), 15/2(4),
15/2(5), 15/2(6), 15/3, 15/4, 16, 18/1A, 18/1B, 23/3, 23/4, 24/1A, 149/1, 149/2,
149/3, 149/4, 149/5, 150/1, 150/2, 150/3, 150/4, 150/5, 150/6, 150/7 at village
Palaspe, Tal – Panvel, Dist- Raigad,developed by M/s. Arihant Abode Ltd.
(File No.: SEAC 2010/CR 578/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee
noted project details furnished by the Project Proponent as:
Name of the Project : “ARIHANT AKANKSHA” a Residential Project under Rental
Housing Scheme of MMRDA.
Project Proponent : M/s. Arihant Abode Ltd
Consultant : M/s. Enviro Analysts & Engineers Pvt. Ltd.
Category : 8(b)- B1
Previous
consideration/s
: 41st meeting of the State Level Expert Appraisal Committee (SEAC)
held on 16th March 2011
Location of the
project
: Plot Bearing S. No 7/5,14/6,14/7,15/1,15/2(1),15/2(2),15/2(3),
15/2(4),15/2(5),15/2(6,15/3,16,18/1A,18/1B,23/3,23/4, 24/1A, 149/1,
149/2, 149/3, 149/4, 149/5, 150/1, 150/2, 150/3, 150/4, 150/5, 150/6,
150/7 at village Palaspe, Tal – Panvel, Dist- Raigad
Type of Project : Construction Project
Plot Area : 66,751.620 sq.m.
Proposed Total built
up area
: Construction Area: 5,07,283.83 sq.m.
FSI Area: 2,48,560.45 sq.m.
Non FSI area: 2,58,723.38 sq.m.
Ground coverage 42.39 %
Estimated cost of the
project
: Rs.316 Cr
No. of Buildings : Total Buildings: 25nos
Sale Section:
Buildings: 22nos Residential buildings + 1no of School,
Type A, A1, B, B1 : B + ST +2P + 35 Floors,
Type C: ST + 35 Floors,
School: G + 7 Floors
MMRDA Section:
Building: 2no,
Chairman
30
Type A & B: G + 28 Floors
Height of building Sale max height:113.20m
MMRDA max height:87.55m
Water Requirement • Total Water Requirement: 4.525 MLD
• Fresh Water: 2.978 MLD
• Recycled water : 1.655 MLD
Rain water
harvesting
• 4nos of rain water harvesting tanks of total capacity 1000m3
capacity
• 103 nos. of recharge pits with Size: 3m x 3m x 3m
Wastewater
generated
3.591 MLD
Capacity of STP • 4nos of STP of total 3.6 MLD capacity (for Sale:1.840MLD &
MMRDA:1.760MLD)
• STP technology: SAFF Technology
Solid Waste
Generation
• Biodegradable waste: 9.92 MT/day
• Non biodegradable waste: 6.68 MT/day
• STP Sludge (Dry sludge): 0.26 MT/day
Disposal • Organic waste generated will be composted using OWC.
• Non Biodegradable waste will be handed over to authorized
recycler.
• Dry STP sludge to be used as manure.
Energy For Sale: 15nos of 990KVA,
MMRDA:7nos of 990KVA ,
Source: MSEB
Energy
Conservation
Solar energy harvesting for Common Area Lighting Sytem.
Traffic Management • Parking area: 70, 921.34 sq.m.
• 2‐Wheelar: 295 Nos.
• 4‐Wheeler: 1,847 Nos.
• Width of internal rods : 9m & 11m, Ramps: 7.0 wide, Driveways:
9.0 m wide
Green Belt
Development
• Total R.G area: 6821.48 Sq. m (8%)
• RG on Ground: 5,304 m2
• RG on podium: 1,517.41 m2
Environment
Management Plan
Operation phase:
• Capital Cost: 13.0 lakhs
• O&M Cost: 185 lakhs / annum
Chairman
31
Decision:
The case was discussed on the basis of the presentation made by the proponent. Following points
were observed during the presentation:
1. As per the guidelines issued by MoEF for High Rise Buildings vide O.M. no. 21-
270/2008- IA.III dated 7th February, 2012, for any building with height greater than 60
m, the nearest fire station should be located within a distance of 2 km. The PP informed
that they have agreement with another private agency having their own fire station.
However, the PP has not submitted any such agreement.
2. The PP stated that for the provision of water supply, drainage facility, waste disposal and
other amenities / infrastructure, MMRDA is responsible. However the PP has failed to
submit such a letter of commitment from MMRDA.
3. PP has not addressed the issue of reduction in the tenement density to the maximum
desirable figure less than 1000/ha. The consequences of such a high tenement density
have been articukated in the earlier MOMs.
In view of above, SEAC decided to recommend the project for rejection.
Chairman
32
Item No. 10
Subject: Environmental clearance for proposed the Expansion Residential project “Oval
Nest” at Warje, Pune by M/s. Shri Sai Associates.
(File No.:SEAC2010/CR 684/ TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : Expansion Residential project “Oval Nest”
Project Proponent : M/s. Shri Sai Associates
Consultant Aditya Environmental Services Pvt. Ltd
Location of the
project
: S. No. 77/2/1+2+3+4+5+77/1(P) & S. No. 78/1B/1 at Warje, Pune.
Type of Project : Construction project (Expansion)
Previous
consideration/s
48th meeting of the SEAC held on 27th to 30
th December, 2011 and
50th meeting of the SEAC held on 8
th to 11
th February,2012
Plot Area : Total plot area: 33,802.70 m2
Proposed Total built
up area
: • FSI Area: 26,372.76 m
2
• Non FSI Area: 19,814.34 m
2
• Total Built up Area: 46,187.1 m
2
Ground Coverage
Area
: 38.92 %
Estimated cost of the
project
: Rs. 96.22 Crores
No. of Buildings : Existing:
• 6 Buildings ( Basement +Stilt parking + 11 floors with 258 units)
• 1 Club house (G+1)
• One commercial building (G + 1)
Proposed:
• 1 Residential Building (Stilt parking +32 )
Maximum Height of
building
Existing : 36 m
Proposed: 97m (Upto terrace level)
Total Water
Requirement
• Fresh water:130 KLD, from PMC,
• Recycled water: 132.22 KLD
• Total water requirement: 262.22 KLD
Chairman
33
Sewage Generation 156.42 KLD
STP capacity Existing capacity – 150 KLD; Proposed capacity – 15 KLD
STP Technology Existing – Sludge Return Bio Reactor (SRBR);
Proposed – Suspended Media Bio Reactor (SMBR)
Rain water
Harvesting
• No. of recharge pits : 3 Nos. with 5.0 m X 3.0 m X 1.5 m size
• the surface storm water runoff flows to an existing nala adjoining
the access road to the site.
Solid waste
Generation
• Dry quantity (kg/day): 179.40 kg/day
(Existing – 163.20 kg/day; Proposed – 16.20 kg/day)
• Wet Quantity (kg /day): 256.70 kg/day
(Existing – 232.20 kg/day; Proposed – 24.5 kg/day)
• STP Sludge (Dry Sludge) : 61.00 kg/day
(Existing – 55.00 kg/day; Proposed – 6.00 kg/day)
Solid waste
Management
• The wet waste shall be treated in Vermi-composting pits; Dry
waste shall be segregated and led to recyclers or scrap dealers.
• STP sludge will be used as manure.
Green Belt
Development
• RG on ground (sqm) 9795 sqm; 41.19% of gross plot area
• RG on podium (sqm) 3958 sqm; 16.64% of gross plot area
• Trees to be planted on ground: 327 nos.
• Trees on podium: 48 nos.
Energy Requirement • Source: MSEDCL
• Existing – 1478 KW; Proposed – 165 KW
• D.G. Set: 2 Nos. of D.G. Set of 125 kVA each
Traffic Management • 2 –Wheeler: Existing – 688 nos. ; Proposed – 81 nos.
• 4-Wheeler: Existing – 348 nos. ; Proposed – 54 nos.
• Width of all Internal Roads – 6.00 meters
Energy
Conservation
measures
• Use of Energy Efficient Luminaries – LED lights, CFL lamps, T5
tube fixtures with electronic ballast;
• Energy efficient lifts with group control;
• BEE star rated Air Conditioners (Club House & Residential
Units)
• Solar Water Heating system;
• Sleep mode code for air conditioners in bedrooms;
• Use of wind – solar hybrid system for energy generation for
common area lighting in lobbies and staircases at each floor in
each building.
• Energy efficient pumps and motors
Environmental
Management Plan
• Capital cost: 1,97,41,000/-
• Operation and maintenance cost: 11,36,000/-
Chairman
34
Decision:
The case was discussed on the basis of the presentation made by the proponent.
SEAC decided to recommend the proposal for Environmental Clearance subject to complying
with the following conditions:
1. Internal roads for fire engine movement are not adequate, particularly within the
existing complex. This has to be rectified by providing appropriate access for fire
engines.
2. Documentary proof of complying with the the guidelines issued by MoEF for
High Rise Buildings vide O.M. no. 21-270/2008- IA.III dated 7th February,
2012,with respect to the width of the road and fire station location in the vicinity
shall be submitted.
3. Tree to be planted: 979 trees on RG on ground, 395 small trees and shrubs on RG
on podium, and suitable plants on garden area. Attempts to be made plant trees
like mulberry, bomsax etc. to attract birds. The biodiversity park area on the
slopes of the hill shall have trails and tree groves.
Chairman
35
Item No. 11
Subject: Environmental clearance for proposed the proposed SRA Scheme on plot bearing
CTS No. 128-A/4(pt) of Village Kandivali at Renuka Nagar, New Link Road,
Dahanukarwadi, Kandivali (W), Mumbai by M/s. Bau Developers Pvt. Ltd.
(File No.: SEAC2011/CR952/TC2)
Project proponent was absent.
Item No. 12
Subject: Environmental clearance for the Proposed Slum Rehabilitation Project at Byculla
Division, Mahatma Jyotiba Phule Marg, Kanjarwada Situated at B. J. Marg, and
K. K. Marg, Byculla (W), Mumbai by M/s. Krish Developers
(File No.: SEAC 2211/CR965/TC2) (New case)
Project proponent was absent.
Chairman
36
Item No. 13
Subject: Environmental clearance for the “IT/ITES, BFSI and Commercial with public
parking” at C.S.no.166 of Lower Parel division situated at N.M Joshi Marg, Lower
Parel, Mumbai by M/s. Marathon realty Pvt Ltd.
(File No.: SEAC 3511/CR 963/TC2) (New case)
The Project Proponent explained the proposal before the committee and committee noted
project details furnished by the Project Proponent as:
Name of the Project : “IT/ITES, BFSI and Commercial with public parking”
Project Proponent : M/s. Marathon Realty Pvt Ltd
Consultant : M/s. Ultra-Tech Environmental Consultancy & Laboratory
Category : 8(b)- B1
Previous
consideration/s
: New case
Location of the
project
: C.S.no.166 of Lower Parel division situated at N.M Joshi Marg,
Lower Parel, Mumbai
Type of Project : Expansion Project (Construction project)
Plot Area : Total Plot Area: 27163.38 m2, Deductions : 1069.84 m
2
Net Plot Area : 26093.54 m2
Proposed Total built
up area
: Existing Expansion Total
FSI (m2) 13298.18 81705.87 95004.05
Non FSI (m2) 5401.16 94294.75 99695.91
Total BUA (m2) 18699.34 176000.62 194699.96
Ground Coverage 46.5 %
Estimated cost of the
project
: Rs. 151.67 Cr
No. of Buildings : Existing: Building A & B: B + Gr + 3 Upper flrs.
Proposed: Building C: 3 B + Gr to 7 flrs parking + 8th to 39
th upper
floors
Height of building Building A : 17.20 m (Up to terrace level)
Building B: 17.35 m (Up to terrace level)
Building C: 171.45 m (Up to terrace level)
Water Requirement • Fresh Water: 231 m3/day, Source: MCGM
• Recycled water : 216 m3/day
Chairman
37
Rain water
harvesting
• It is proposed to provide rain water collection tanks of capacity
170 m3 where water from the terrace water shall be carried
through underground piping.
• Surface runoff will be used to recharge the ground water sources
through 4 Nos. of ring wells
Wastewater
generated
407 m3/day
Capacity of STP 500 m3/day , STP technology: MBBR (Moving Bed Bio Reactor)
Solid Waste
Generation
• Existing: Dry quantity kg/day:- 256 kg/day Wet quantity kg/day:- 110 kg/day
• Proposed:
Dry quantity kg/day:- 1573 kg/day Wet quantity kg/day:- 674 kg/day
• E-Waste & Hazardous waste :
Existing Building: 1436 kg/day Proposed Building: 8824 kg/day
• STP Sludge (Dry sludge): 61 kg/day
Disposal • Wet garbage will be treated in an Organic Waste Converter (OWC) and the dry garbage will be handed over to M.C.G.M.
• Waste oil which is generated due to usage of DG sets shall be
stored and subsequently given to the authorized hazardous waste
management agencies recognized by MPCB. • E-waste will be stored separately and recycled through authorized
dealers
• Dry STP sludge to be used as manure.
Energy • Maximum demand: 8050 KW, Local Authority
• DG set: 1 x 1250 KVA
Energy
Conservation
• Use of energy efficiency VRV system for air conditioning.
• Use of CFL/ T5 lamps in common areas, Timer/ BMS Control on
external lighting.
• Use of Multiple lighting circuits, Group control of elevators.
• Transformers close to point of use, Low loss capacitors
• Insulation of roof in compliance with ECBC.
• Use of glass with low thermal conductivity and solar heat gain
coefficient.
• Solar lighting for landscape area.
Traffic Management • Parking area: 47728.72 m2
MCGM: 24650 m2, Captive: 23078.72 m
2
• Parking spaces provided: 4-Wheeler: MCGM: 493 Nos.
Captive: 746 Nos.
Chairman
38
Green Belt
Development
• RG on ground : 5564.28 m2
• RG on podium : 1492.50 m2 (25% of Net Plot Area)
Existing trees: 107 Nos., Trees to be Planted: 351 Nos. • List of the trees:
Sr Botanical Name Total Sr. Botanical Name Total
1 Alstonia Scholaris 16 10 Mangifera indica 16
2 Cassia Fistula 18 11 Lagerstromia flos-
reginae
20
3 Michelia champaca
alba
11 12 Pongamia pinnata 15
4 Azadirachta indica 19 13 Plumeria alba 15
5 Anthocephallus
cadamba
15 14 Saraca asoka 12
6 Bauhinia racemosa 13 15 Terminalia arjuna 18
7 Erythrina indica 14 16 Terminalia catappa 18
8 Murraya paniculata 12 17 Albizia lebbeck 12
9 Caryota urens 19 18 Areca catechu 23
Environment
Management Plan
Capital cost: 202.82 Lakhs
Operation and Maintenance cost: 54.03 Lakhs
Decision:
The case was discussed on the basis of the presentation made by the proponent. The PP has
submitted the provisional certification for Green Building from Indian Green Building Council.
The proponent is directed to comply with the following observations:
1. Submit copy of LOI from MCGM for car parking.
2. Submit chronology of project from 1st appraisal and current stage of progress.
3. Submit copy of Environmental Clearance granted earlier, its compliance status and
report of Monitoring Committee.
4. Submit the consent for additional quantity of required water supply from competent
authority.
Chairman
39
5. The car parking for MCGM are worked out to be 50 m2 per car, which is much higher
than 30 m2 per car as per MoEF Guidelines. The car park area shall be reduced close
to 30 m2 per car.
6. Submit NOC from Airport Authority of India and CFO, Railway Authority and High
Rise Committee.
7. Justify the capacity of DG Set proposed for essential services.
8. Submit a note on energy conservation measures in accordance with ECBC guidelines.
9. Follow new DC Rules for fire and safety norms including fire-chute and fire-check
floors.
10. STP is already located in 3rd Basement, which should have been avoided. Proper
arrangements for ventilation and safety are to be ensured.
11. The project proponent shall draw up a sustainable model with appropriate EMP, as
the proposed EMP (O&M) is inadequate.
The PP has submitted EIA recently. The comprehensive assessment will be done after
submission of above compliance.
Chairman
40
Item No. 14
Subject: Environmental clearance for the proposed 2500 TCD of Sugar and 10 MW Co-
Generation Plant at Village Khamgaon, Tal Barshi, Dist. Solapur by M/s Aryan
Sugars Limited
(File No.: SEAC 2011/CR-9561 /TC-2) (TOR case)
Project proponent was absent.
Item No. 15
Date : 11.4.2012
Subject: Environmental clearance for the proposed “Gas bases Combined Cooling,
Heating and Power (CCHP) Plant of approx 40 MW capacity” at Mindspace
SEZ-Airoli, Plot No. 3, TTC, MIDC Area, Opp Airoli Railway Station, Thane
Belapur Road, Airoli, Navi Mumbai by M/s Serene Properties Pvt Ltd
(File No.: SEAC 2011/CR-9561 /TC-2) (TOR case)
Project proponent was absent.
Chairman
41
Item No. 16
Subject: Environmental clearance for the proposed expansion of industrial project (5.5
MW Natural Gas based Captive Power Plant) at Shrigaon, Post Poyanad, Tal
Alibag, Dist. Raigad by M/s Nitco Ltd.
(File No.: SEAC 2011/CR-953/TC-2) (TOR case)
The Project Proponent explained the proposal before the committee and committee noted
project details furnished by the Project Proponent as:
Name of the Project : M/s Nitco Ltd
Category : 1(d) – B1
Project Proponent : M/s Nitco Ltd
Consultant M/s SKY LAB (Application in process with NABET)
Location of the project : Shrigaon, Post :- Poyanad, Tal :- Alibag Dist. Raigad, 402 108.
Type of Project : 5.5 MW Natural Gas based Captive Power Plant
Total Plot Area : 72 Acer
Project cost : 22 Cr (Expansion)
Products : 5.5 MW Natural Gas based Captive Power Plant
Raw materials : RLNG Gas
Water Requirement : Avg. 500 KL / Day for existing unit & Approx. 15 KL/Day will be
required for Gas Turbine Effluent Generation : 0.1 KL/Day from Cooling tower
ETP / STP capacity : Capacity of STP: 25 KL / Day, Capacity of ETP: 1 MLD
Rain water Harvesting : Rain Water Harvesting (RWH): 3000 KL/ Month. Collected in Pit &
used in process after filtration
Storm Water Drainage : ----
Solid waste management : Sr.
No
Source Qty(TP
M)
Form
(Sludge/Dry/
Slurry etc.)
Composition
1 Raw water
treatment plant
--- Sludge Clays
2 ETP -- Sludge Clays
3 Process -- -- --
4 Spent Catalyst -- -- --
Chairman
42
5 Oily Sludge
3 T/Y Oily Sludge
Lubricating
Oil
6 Others like
Battery waste, e
waste etc (Pl.
Specify
20 Nos /
Y Battery Lead Slag Air Pollution Control : The proposed power plant would use natural gas (RLNG) as fuel
which is very clean & Environment friendly fuel, which does not
contain any sulphur. Hence, there would not be any emission of
sulphur dioxide in the flue gas & SPM level will be less than 100
mg/Nm3, The NOx emission will be <158 PPM maximum as per
suppliers specifications. Stacks of 31m Height will be provided. The
of hot flue gases from Gas Turbine in spry drier will reduced air
pollution due to reduction in coal consumption.
Green Belt Development : Green belt area: 10 Acers. ( 40000 m2)
Existing nos. of trees: - 3000 nos., Proposed nos. of trees with plant
species- local species 500 nos.
Number trees being cut/replanted or compensated- No Tree Cutting
required or re-plantation
Energy Requirement : Total Power Requirement (MW); Source of Power: MSEB
Present (in existing): 3.6 MW, Proposed: 150 kV
DG Sets: Two Nos. of 1500 KVA
Environmental
Management Plan
:
Sr.
No. Item
Recurring
Cost per
annum
Capital
Cost
1 Air Pollution Control 1 Lac 20 Lac
2 Water Pollution Control 1.5 Lac 5 Lac
3 Noise Pollution Control -- 50 Lac
4 Environment Monitoring
and Management 1 Lac --
5 Reclamation
borrow/mined area NA NA
6 Occupational Health 0.5 Lac --
7 Green Belt 1 Lac 5 Lac
8 Solid waste management -- --
9 Others ( Pl. Specify) -- --
Total 4 Lac 80 Lac
Chairman
43
Decision:
The case was discussed on the basis of the presentation made by the proponent. SEAC
noted the letter dated 12th April 2012, submitted by PP informing that the maximum power
generation will be 4.92 MW for average ambient inlet air temperature of 300C during winter
season and requested to allow to withdraw their application for EC for 5.5 MW Captive Power
Plant and grant exemption from the purview of EC considering the power generation capacity
below 5 MW. Hoverer considering Category no. 1(d) of Schedule of EIA Notification 2006, the
proposal falls under the purview of the Notification and EC is mandatory.
The project proponent has been advised to carry out public consultation and EIA study
considering the various comments made by the committee and the model TOR prescribed (Page
No.119) and then approach the committee for the appraisal. A QCI accredited consultant and
MOEF/NABL accredited lab shall be used for the preparation of EIA Report.
Chairman
44
Item No. 17
Subject: Environmental clearance for the proposed industrial project (237 MW-Gas Based
Combined Cycle Power Project) at Plot No. 60, 366/38 to 41, 366/43 to 45, 366/48
to 54, Village Dawadi, Tehsil Khed, Dist. Pune by M/s Khed Economic
Infrastructure Pvt. Ltd.
(File No.: SEAC 2011/CR-896/TC-2) (TOR case)
The Project Proponent explained the proposal before the committee and committee noted
project details furnished by the Project Proponent as:
Name of the Project : M/s Khed Economic Infrastructure Pvt. Ltd. - 237 MW-Gas Based
Combined Cycle Power Project
Category : 1(d) – B
Project Proponent : M/s Khed Economic Infrastructure Pvt. Ltd.
Location of the project : Plot No. 60, 366/38 to 41, 366/43 to 45, 366/48 to 54, Village
Dawadi, Tehsil Khed, Dist. Pune.
Type of Project : 237 MW-Gas Based Combined Cycle Power Project
Total Plot Area : 63 Acre
Project cost : 832.65 Cr
Products : 237 MW-Gas Based Combined Cycle Power Project
Raw materials : NG = 1.22 MMSCMD for power & 0.5 MMSCMD for non-power
utilities, LDO/HSD = 1111.65 KL/D
Water Requirement : 450 m3/Hr
ETP / STP capacity : ETP Proposed. Final disposal proposed in CETP of SEZ.
Decision:
The case was discussed on the basis of the presentation made by the proponent. It was
noted that the proposal was already issued ToR in the 43rd meeting of SEAC held on 20
th April,
2011.
The project proponent has been advised to carry out EIA study considering the various
comments made by the committee including gas pipeline laying, risk assessment, DMP and the
model TOR prescribed (Page No 119), conduct public consultation (although it is located in SEZ
as the EC issued by MoEF for the SEZ does not specifically mention power generation in the list
Chairman
45
of industries approved) and then approach the committee for the appraisal. A QCI accredited
consultant and MOEF/NABL accredited lab shall be used for the preparation of EIA Report.
Item No. 18
Subject: Environmental clearance for proposed MMRDA Rental Housing project at the
Village Kon & Arivali, Taluka - Panvel, Dist. Raigad by M/s. Diana Infrastructure
Ltd.
(File No.: SEAC 2010/CR-526/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted
project details furnished by the Project Proponent as:
Name of the Project : INDIABULLS GREENS
Project Proponent : M/s. Diana Infrastructure Ltd
Consultant : M/s. Ultra-Tech Environmental Consultancy & Laboratory
Category : 8(a) – Cat. B
Previous
consideration/s
: 44th SEAC meeting held on 14
th September, 2011
48th SEAC meeting held during 27-30 December 2011
50th SEAC meeting held during 11, February,2012
Location of the
project
: S. NO 63/0, 64/1, 65/1 to 3, 66/2, 66/3, 66/5 to 66/8, 66/13, 66/14,
66/15, 67/1A, 67/1B, 67/2, 68/1 to 7, 69/1A, 69/1B, 69/2, 69/6, 70/1,
70/2, 71/1A + 2A + 5B, 71/1B, 71/3, 71/4 + 25K, 71/5A, 71/8B +
9K, 71/6A, 71/11, 71/12 to 16, 71/17A, 71/17B, 71/17K, 71/18 to 20,
71/21B, 71/22 + 21A, 71/23B, 71/24 + 23A, 71/25A + 5K, 71/25B,
71/8A +9B, 71/10 + 9A, 81/1, 81/3, 81/4, 81/5, 81/6, 81/7 to 14, 82/1
to 4, 83/1, 83/5A, 83/4A, 83/6 village Kon & Arivali, Taluka -
Panvel, Dist. Raigad.
Type of Project : MMRDA Rental Housing Project
Plot Area : Total Plot Area: 114,610.00 m2
Net Plot Area : 106,215.96 m2
Proposed Total built
up area
: FSI area: 4,24,863.84 m2
Total BUA: 7,93,628 sq. m.
Estimated cost of the
project
: Rs. 1,775.58 Crores
No. of Buildings Sale Buildings: Residential:
3 Bldgs with B + LG + UG + Podium + 36 flrs
13 Bldgs with B + LG + UG + Podium + 37 flrs
Chairman
46
2 Bldgs with B + LG + UG + Podium + 42 flrs
Total Flats : 3130
Commercial
1 Bldg. with B + LGr + UG + 3 flrs of mall having multiplex with
1320 Seats 4th to 14
th floors of office area.
Rental Buildings:
Residential: 11 Bldgs of G+19 flrs , Flats: 6141 Nos. Shops: 8 Nos.,
Balwadi: 33 Nos, Welfare Center: 33 Nos, Society Offices: 11 Nos.
Height of building 133 m
Water Requirement Fresh Water: 4274 m3/day, Source: From MJP and 20 m
3/day
Source: From Potable Tankers
Recycled Water: 2390 m3/day
Rain water harvesting 5 rain water collection tanks of total capacity 2045 m3.
24 recharge pits with bore wells.
Wastewater generated Total Sewage: 5660 m3/day (For Rehabilitation: 3616 m
3/day, For
Sale: 2044 m3/day)
Capacity of STP For Sale : Residential :2015 KLD, For commercial :235 KLD
Rental:1 STP of 1000 KLD , 2 STP of 1500 KLD each
STP technology: SAFF
Solid Waste
Generation
Dry waste: 7755 kg/day ,
Wet quantity :- 16166 kg/day
E-Waste: 2445 kg/annum,
STP Sludge (Dry sludge): 849 Kg/day
Disposal • Construction phase debris and excavated material shall be used for
back filling and leveling of the plot and remaining will be disposed
to authorized sites.
• Solid waste generated from project will be segregated into dry and
wet garbage. Wet garbage will be treated in an Organic Waste
Converter (OWC) and the dry garbage will be handed over to the
authorized recycler.
• Waste oil which is generated due to usage of DG sets will be
handed over to authorized recyclers. E-waste will be stored
separately and recycled through authorized dealers.
• E - Waste will be stored separately and handed over to the
authorized recyler.
• Dried sludge from STP will be used as manure.
Energy Source of power : MSEDCL
Connected load : 69850 KW, Maximum demand : 34235 KW
DG Set: Sale:- Residential:- 15 Nos. of 750 KVA each & 2 Nos. of
630 KVAeach , Commercial:- 6 Nos. of 1600 KVA each
Rental:- 3 Nos. of 750 KVA each
Chairman
47
Energy Conservation • Energy conservation measures are proposed to reduce to Energy
• Copper conductor cables are specified for sizes of 16 sq mm and
below, this will reduce losses and improve reliability.
• All lifts shall be provided with AC variable voltage, variable
frequency drives (ACVVF).
• Power factor shall be maintained 0.95 or higher. This will reduce
electrical power distribution Losses in the installation.
• Compact Fluorescent Lamps (CFL’s) with high frequency ballast
shall be used for corridors And BOH areas. Energy efficient
fluorescent tube lights (T-5) shall be used. All fluorescent light
fixtures are specified to incorporate electronic chokes which have
less watt-loss compared to electro-magnetic chokes and result in
superior operating power factor. This indirectly saves energy.
Electronic chokes also improves life of the fluorescent lamps.
• Energy efficient fluorescent lamps & CFL lamps which give
approx. 30% more light output for the same watts consumed and
therefore require less nos. of fixtures and corresponding lower
point wiring costs.
• Solar water heating system for Premium buildings.
• An APFC relay based on thyristor switching is proposed to effect
the power factor correction / improvement within a few cycles of
deviation from the setting & also to reduce inrush currents.
• Transformers shall have minimum no load losses as compared to
conventional transformers. All cables shall be de-rated to avoid
heating during use. This also indirectly reduces losses and
improves reliability purposes.
Traffic Management Parking area: 141,898.61 m2
2-Wheeler: Nil , 4-Wheeler: 4227 Nos. , Public Transport: N.A.
6 mt. wide Internal Roads.
Green Belt
Development
R. G. Area : 20,058.49 Sq.mt
Numbers of trees to be planted Inside the plot: - 1105 Nos.
Environment
Management Plan
Construction phase: Rs. 44 lakhs
Operation Phase: Capital cost: Rs. 5443.42 lakhs
O&M Cost: Rs. 453.84 lakhs / annum
Decision:
Following queries were raised in the 44th
SEAC meeting held on 14th
September 2011:
1. The tenement density in rental portion is over 2000/ha, which is unacceptable and needs
drastic reduction.
Chairman
48
2. List of required amenities and those proposed, with details.
3. Infrastructure like water supply, drainage, roads, transport, electric supply available.
4. Whether Municipal services are available?
5. Town planning department’s or Collector’s letter approving the scheme with permissible
FSI, heights etc.
6. Attempts to reduce the total construction area to minimize congestion.
7. Fire fighting facilities in such locality where no municipality exists and where a large
population will stay.
8. Proposals for phasing of work, if any.
9. Details of availability of required infrastructure like roads, drainage system, municipal
services etc.
The site was visited by the SEAC on 30th
December, 2011 and following points were
incorporated in the minutes of 48th
SEAC meeting held during 27-30 December 2011:
It is observed that, another residential project, which includes MMRDA rental housing scheme is
being constructed on the adjoing plot. Total BUA for that neighbouring project is 6,03,339.07
sq.m. and the total BUA for the project under consideration is 7,93,628.50 sq.m. Considering
these, the following points including compliance of the points raised in the 44th meeting were
raised :
• The tenement density in the rental portion is above 2000/hector and is not environmentally
tenable. Such high density will cause serious health hazards caused by lack of adequate open
spaces, inadequate lighting and ventilation and living conditions. Even in slum development
schemes, the tenement density seldom exceeds about 1200 tenements per hector. In rural
areas and areas not yet developed, it will have to be substantially less. As buildings with very
high FSI are proposed, Local Authority should ensure that Regional Plan/ development plan
take care of these high density pockets and, if necessary, recast these plans.
• The facilities for municipal drainage are yet to be provided as there is no development in the
area, which is far away from Panvel. All areas around the site are undeveloped. Even water
supply will have to be made available by laying a pipe line of MJP away from the site. Public
amenities like hospitals, schools, transport, market, banks and post office, fire station, police
station, library etc. are not yet available in the area. The project proponents shall specify the
time frame to develop above said infrastructure.
Chairman
49
• It appears, the area falls outside Panvel Municipal jurisdiction and DC rules of Town
Planning Department should apply here. However MMRDA has evolved DC rules for this
plot exclusively under the rental scheme, which will not be available for areas surrounding
the plot. Thus a disharmonious development will take place with very high density
construction in one plot and rural type development in the surrounding areas. This may give
rise to slums, occupied by servants, labours and vendors etc. serving the habitants in the
rental scheme. The project proponent shall study these aspects and submit their mitigation
plans to avoid such unwanted developments.
• MMRDA should make arrangement to create dedicated corpus fund for each colony of
Rental Housing Scheme on organizational set-up along with the timely provision of adequate
funds required to ensure satisfactory implementation of EMP of the rental housing
component.
• MMRDA should enter into legally binding agreement/ issuing Notification or Government
Resolution with all corresponding local Authorities like CIDCO/ Municipal Corporation etc
regarding provision of necessary services like roads, transport facilities, electric supply,
drinking water supply and essential social infrastructures like hospitals, dispensaries, schools,
and other educational institutions, parks, gardens etc. This also should clearly specify the
responsibilities regarding the municipal services like water supply scheme, closed sewer lines
for discharge of excess treated effluent, waste disposal & treatment with appropriate
treatment facilities, treatment and disposal facilities of MSW generated , street light
maintenance, health facilities, fire fighting, educational facilities, regulating construction
activities, maintaining safety, health and inhabitants etc.
Following decision was taken in the 50th
SEAC held on 8th
to 11th
February, 2012:
The case was discussed on the basis of the presentation made by the proponent and the points
raised by SEAC in the earlier assessments. Representative of MMRDA clarified that the Rental
Housing Scheme with respect to the tenement density is being reviewed by the Government of
Maharashtra. The project proponents requested that considering the financial implications they
are ready to recast the proposal as per the direction of the SEAC to minimize the environmental
impacts. Considering this, SEAC decided that the project proponent may either wait for the final
Government decision on the Rental Housing Scheme or recast the proposal with approval of
MMRDA. The project proponent shall indicate their option. If their option is for the reduction of
tenement density, then they shall recast the proposal accordingly and approach SEAC for re-
appraisal. A tenement density of about 1000 per ha as seen in some of the SRA projects may be
aimed at. However, in case, the decision of Government on the tenements density is lower than
1000 per hector, the decision of the Government will be binding.
Chairman
50
Decision:
The case was discussed on the basis of the presentation made by the proponent. MMRDA
representative was present during the meeting. The SEAC reiterated its opinion to PP that the
tenement density shall be restricted to 1000/ha for rental housing and PP shall recast the project
meeting the tenement density limit with appropriate reduction in the Rental Housing Scheme
Building and Sale building as Phase-I. However PP stated that they were not in a position to
recast the proposal considering the MMRDA letter. This has constrained SEAC to recommend
rejection of the proposal.
Chairman
51
Item No. 19
Subject: Environmental clearance for the proposed expansion of Oxime and Byproducts
and Manufacturing of New Product Ketoxime & Byproducts at Plot No G-54,
MIDC, Butibori, Salai Dhaba Dist Nagpur by M/s. Star Orechem International
Pvt. Ltd
(File No.: SEAC2011/CR679/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted
project details furnished by the Project Proponent as:
Name of the Project : Proposed Expansion of Oxime and Byproducts and Manufacturing of
New Product Ketoxime & Byproducts
Project Proponent : M/s Star Orechem International Pvt .Ltd
Consultant M/s. Enviro Analysts & Engineers Pvt
Category 5(f) B1
Previous
consideration/s
: 49th meeting of the State Level Expert Appraisal Committee (SEAC)
held from 18th to 21st January, 2012
Location Plot No G-54, MIDC, Butibori, Salai Dhaba Dist Nagpur
Plant
Products Description Product Name
Product-I Oxime-51.5% : 250 MT/M
By-product Magnesium Sulphate :133.58 MT/M
By-product Sodium Sulphate : 37.70 MT/M
By-product Novolac Resin : 69.45MT/M
By-product Thinner : 49.5 MT/M
By-product Formalin(24%) : 22.66 MT/M
Product-II Ketoxime-50% :125MT/M
By-product Sodium Sulphate : 25.2MT/M
By-product Novolac Resin : 5.42MT/M
By-product Thinner :6.14MT/M
By-product HCl (30%) :29.47MT/M
By-product Polyaluminum chloride (PAC-30%)
:177.93MT/M
Chairman
52
Raw material Raw material for Oxime (250MT/Month) and Ketoxime (125
MT/Month):
Sr.
No.
Name of Raw Material Oxime
51.5%
(MT/M)
Ketoxime 50%
(MT/M)
1 Nonyl Phenol 169.8 35.2
2 Acetyl Chloride Nil 12.011
3 Magnesium metal 10.80 Nil
4 Formaldehyde 71.63 Nil
5 Hydroxylammonium
Sulphate
41.46 11.34
6 Toluene 11.11 1.824
7 Anhydrous Aluminium
Chloride
Nil 18.69
8 Calcium hydroxide Nil 13.70
9 Sulphuric Acid 54.38 10.85
10 Sodium Carbonate 26.43 1.27
11 Sodium Hydroxide Nil 29.41
12 Escaid-80 22.0 60.90
13 Solvent – TXIB 100.0 Nil
14 De-mineralized Water 571.02 293.16
Raw materials for PolyAcrylamide 90MT/M
Sr. No. Raw Material Quantity MT/M
1 Acrylamide 90
2 NaOH 13
3 Water 90
Raw Material for Surfactants 150 MT/M
Sr. No. Raw Material Quantity MT/M
1 Acrylamide 3.75
2 Ketonic Monomer
ADMEQUABA
11.25
3 Water 130.5
4 Emulsifier 0.75
5 Xylene 3.75
Raw material for Xanthate RM 450 MT/M
Chairman
53
Sr. No. Raw Material Quantity MT/M
1 Carbon do Sulphide 205.2
2 Isopropyl alcohol 162
3 Caustic Soda 108.0
Raw Material for DE Phthalate RM 300 MT/M
Sr. No. Raw Material Quantity MT/M
1 Monoethylphthalate
Recycle
3.49
2 Alcohol recycle 49.17
3 Sulphuric acid 3.13
4 Phthalic Anhydride 199.17
5 Fresh alcohol 100.83
6 Soda ash 3.34
7 Water 19.12
Total plot area 40,500 sq .m
Estimated cost of the
project
Rs. 9.00 Cr.
Total water
requirement
• Water Source : MIDC, Butibori
• Total water requirement : 149.1KLD
• Domestic : 4.0 KLD
• Cooling/Boiler : 114.5 KLD
• Industrial: 16.6 KLD
• Gardening : 10.0 KLD
Energy Requirement • Requirement: 240 MVA, Source: MSEB
• Alternate supply for essential service
• Existing 1 nos. of D. G. set with capacity of 180 KVA will be
used as back up for emergency there is a proposal to install
another DG set of capacity 250/350 KVA..
• Type of fuel : HSD
Green belt area 10000 sq.mt.
Fuel oil used Sr Fuel Existing Expansion
1 LDO 250 litres/day --
2 Bio-mass (Peanut Shelf
with binder)
5 T/day 5 T/day
3 HSD 17 litres/hr 18 litres/hr
Air pollution control
measures
• Use of Scrubber
• Fume / Dust Collection System (Wet Type) for Induction Furnace
along with Mechanical Dust Collector Type with Dia : 36 m, Ht :
Chairman
54
0.7 m of Performance: Collection of 97 to 99% dust particles
Water pollution
control measures
• Sewage generated will be treated in Septic tanks & Soak pits &
treated sewage will be used for green belt area.
• Industrial effluent will be given primary treatment in proposed
ETP of 50 KLD and then sent to CETP, Butibori.
Solid waste
management
# Source Total
Quantity
Mitigation
A Industrial
1 Chemical sludge from
waste water treatment
0.4MT/Month Sent to
CHWTSDF,
Butibori .
2 Discarded
Containers/Barrels/Liners
(Used Polythene bags)
1.5
MT/Month
Sent to
CHWTSDF,
Butibori.
B Domestic Waste 0.694
MT/Month
Composting
C Gardening Waste 1.16
MT/Month
Composting
EMP Sr. No Description
Cost (Rs in
Lakhs)
Operational Phase
1 Effluent Treatment Plant
(Pretreatment) 12
2 Air Pollution Control Measures 3.0
3 Landscaping 10
4 Solid Waste Management 15
5 Health Care & Safety 20
Total 60
Decision:
The case was discussed on the basis of the presentation made by the proponent. The
Project proponent submitted the revised EIA Report and pre-feasibility report. The PP has
complied with all the points raised in the 49th meeting of the State Level Expert Appraisal
Committee (SEAC) held from 18th to 21
st January, 2012. SEAC decided to recommend the
proposal for Environmental Clearance.
Chairman
55
Item No. 20
Subject: Environmental clearance for the Proposed Organic chemical manufacturing unit
at Plot No. K-53,MIDC Butibori, Dist. Nagpur by M/s. Jeevika Spachem Pvt. Ltd.
(File No.: SEAC2012/CR 001/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted
project details furnished by the Project Proponent as:
Name of the Project : Organic chemical manufacturing unit
Project Proponent : M/s. Jeevika Spachem Pvt. Ltd.
Consultant : M/s. Enviro Analysts & Engineers Pvt Ltd
Category : 5(f) B1
Location : G-54, MIDC-Butibiri, Dist Nagpur
Products :
Sr Name of Products Capacity
1 Esters 50 MT/ M
2 Surfactants / Sulphosuccinates 30 MT/M
3 Defoamers / Antifoamers 50 MT/M
4 Emulsifying agents 20 MT/M Raw material :
Name of Product Raw Material
S.M.S (Sorbitan Mono Stearate)
Yield 1600 Kg
Stearic Acid: 1056 Kg
Sorbitol: 677Kg
Caustic Soda: 5 Kg
S.M.P (Sorbitan Mono Plamitate)
Yield 1600 Kg
Palmic Acid: 1400 Kg
Sorbitol: 1000 Kg
Caustic Soda: 5 Kg
G.M.S. (Glycerol Mono Stearate)
Yield 1600 Kg
Stearic Acid: 1270 Kg
Glycerin: 411 Kg
Caustic Soda: 3 Kg
S.M.O (Sorbitol Mono Oleate)
Yield 2200 Kg
Rice Bran Fatty Acid / Oleic
Acid: 1450 Kg
Sorbitol: 935 Kg
Caustic Soda: 4.1Kg
Di - Octyl Sulphosuccinate
Yield 1750Kg
Stage I:
2 EHA (2 Ethlyl hexa Alchol):
955 Kg
Meleic Anhydride: 360 Kg
PTSA (Para Toluene Sulphonic
Chairman
56
Acid): 14 Kg
Stage II
Dioctyl Maleate: 800 Kg
Sodium Bi Sulphide: 260 Kg
Methanol: 400 Lit
Defoamers / Antifoamers
Yield 3000 Kg
S.M.O
O.S.A.A
Fussal Oil Total plot area 1974.00 m
2
Estimated cost of the
project
Rs. 93.00 Lakhs .
Total water
requirement
Total water requirement : 7 KLD, MIDC, Butibori
Domestic : 1 KLD
Industrial process : 0.5
Industrial CoolingTower : 2 KLD
Reactors and Tools Washing: 1.5KLD
Gardening : 2 KLD
Energy Requirement Requirement: 50 HP, Source: MSEB
Power back up: 1 nos. of D. G. set with capacity of 25 KVA will be
used as back up for emergency
Type of fuel used: Diesel
Green belt area 615.48 sq.mt.
Fuel oil used S. No. Fuel Total
1 LDO 90 KL/Annum
2 Diesel (DG set) 3000 Lit//Annum Air pollution control
measures
Use of Scrubber.
Fume / Dust Collection System (Wet Type) for Induction Furnace
along with venture scrubber wet type, Inter gas volume 15,000cum/hr
Cyclonic type Scrubber : Dia : 1600mm, Ht: 6000mm, Performance
Collection of 97 to 99% dust particles
Water pollution
control measures
Sewage generated will be treated in Septic tanks & Soak pits & treated
sewage will be used for green belt area.
Industrial effluent will be given primary treatment in proposed ETP of
3 KLD and then sent to CETP, Butibori.
Chairman
57
Solid waste
management
# Source Total Quantity Mitigation
A Non-Biodegradable
1 Discarded
Containers/Barrels/Liners
1.0 MT/Month Sold to
authorized
parties
B Biodegradable
1 Domestic Waste 0.75 MT/Month Composting
2 Chemical sludge from
waste water treatment
0.6MT/Month Sold to
authorized
parties
C Gardening Waste 0.075MT/Month Composting
Environment
Management Plan
Construction phase:
Sr Description In Lacs
1. Potable water requirement for workers 0.5
2. Health Care 1.0
Total 1.5
Operation Phase Capital Cost
Sr. No Description Cost (Rs in Lakhs)
Operational Phase
1 ETP(Pretreatment) 3.0
2 Rain Water Harwesting 0.10
3 Air Pollution Control Measures 0.10
4 Landscaping 0.50
5 Solid Waste Management 0.50
6 Health Care & Safety 0.75
7 Environmental Monitoring plan 0.50
Total 5.45
Decision:
The case was discussed on the basis of the presentation made by the proponent. The
Project proponent submitted the revised EIA Report and pre-feasibility report. The PP has
complied with all the points raised in the 49th meeting of the State Level Expert Appraisal
Chairman
58
Committee (SEAC) held from 18th to 21
st January, 2012. SEAC decided to recommend the
proposal for Environmental Clearance.
Item No. 21
Subject: Environmental clearance for the Slum Rehabilitation Scheme - Ganesh Nagar
Magathane Rahiwashi (SRA) Co-Op. Hsg Soc. Ltd at village Magathane,
Western Express Highway, Ganesh Nagar, Borivali East by M/s. Dhanshree
Developers
(File No.: SEAC 2010/CR 56/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted
project details furnished by the Project Proponent as:
Name of the Project : Slum Rehabilitation Scheme - Ganesh Nagar Magathane Rahiwashi
(SRA) Co-Op. Hsg Soc. Ltd
Project Proponent : M/s. Dhanshree Developers
Consultant M/s. Green Circleing
Category 8(a) B2
Previous
consideration/s
49th meeting of the State Level Expert Appraisal Committee (SEAC)
held from 18th to 21st January, 2012
Location of the
project
: Plot bearing CTS No. 182 (pt.) & 191 (pt.) of village Magathane,
Western Express Highway, Ganesh Nagar, Borivali East, Mumbai
400 066
Type of Project : SRA project
Plot Area : 12179.60 m2
Proposed Total built
up area
: • FSI : 41,161.50 m2
• Construction BUA (FSI + Non FSI) : 78,971.56 m2
Estimated cost of the
project
: Rs. 125 Crores
No. of Buildings : • One Rehab Building with 3 wings: Gr + 17 Floors
• One Sale Building with 1 wing: B+ Gr + 4P + E level + refuge
floor+26 Floors
Existing structure &
demolish of it-
Details with disposal
• Site is covered with slums .
• Slums will be demolished & debris will be handed over to
authorized vendors
Height of the
building
107.20 m
Chairman
59
Water Requirement Water requirement : 502 m3/day
Fresh water: For Sale: 238 m3/day, For REHAB : 87 m
3/day
Recycled water: For Sale: 53 m3/day, For REHAB : 124 m
3/day
Rain water
harvesting
• In REHAB building 3No. of Recharging pits are proposed
• In Sale building 4 No. of Recharging pits are proposed
• Recharge pit size: REHAB : 1m x 1m & 2m dia; SALE : 1m x
1m & 2.5m dia
Storm water
drainage
Dimensions of Storm Water Drain For REHAB
Width 450 mm, Depth 450 mm, Slope : 0.00667
Discharge : 924 .75 m3 /hr
Dimensions of Storm Water Drain For SALE
Width 450 mm, Depth 450 mm, Slope : 0.00667
Discharge : 924 .75 m3 /hr
Wastewater
generated
370 m3/day
Capacity of STP • Rehab : 300m3/day
• Sale : 100 m3/day, STP Technology: SAFF Technology
Solid Waste
Generation
• Biodegradable waste: 920 kg/day
• Non Biodegradable waste: 641 kg/day
• STP sludge: 4 m3/day.
Disposal • Construction debris will be reuse on site premises. The substratum
removed will be used for back filling, leveling, and road
construction.
• Entire top soil will be conserved and used later in landscape area
for plantation
• Waste oil which is generated due to usage of DG sets shall be
stored and subsequently given to the authorized hazardous waste
management agencies recognized by MPCB.
• Dry garbage will be segregated & disposed off to recyclers.
• Wet garbage will be composted by using the OWP and used as
organic manure for landscaping.
• Sewage sludge will be composted and then used as manure.
• E-waste will be stored separately and disposed through authorized
recyclers.
Energy • Demand Load: 4570 KW
• DG Set: 1 Nos. x 200 KVA (REHAB), 1 Nos. x 250 KVA
(SALE)
Energy
Conservation
• Power Capacitors are proposed for load power factor correction
and to maintain a healthy power situation. This also results in less
demand load factor for the project.
Chairman
60
• All lifts are proposed on VFD drives which results in 20% saving
in power consumption and approximately 20% savings in energy
consumption.
• Most of the common area lighting are proposed to work on high
energy efficient lamps (CFL) as specified in bureau of energy
efficiency and T-5 & T-8 Tube lights, which again results in
saving in general consumption.
• External lighting, 30% of the external lighting is proposed on
solar. These are set of lighting which are placed at critical
junctions and which would be lit round the night. Otherwise the
other 70% lighting is on timer circuits to achieve the max. saving
Traffic Management • Total No. of Parking Provided: 4- Wheeler Parking: SALE
Building : 332 Car, REHAB Building: 20 Nos.
Green Belt
Development
• Total R.G. Area : 1172.22 m2
• Proposed Tree Plantation: 76 Nos.
Plant Name Common
name
No. C/C Height Canopy
Pongamia
Pinnata
Karanj 14 5000 4500 6000
Cassia Fistula Bahava 5 4000 4500 5000
Ceasalpinia
Pulcherima
Shankasur 12 2000 2400 3000
Murraya
Paniculata
Kunti 23 2000 2400 3000
Bauhnia
Racemosa
Kanchan 03 2000 3000 3000
Saraca Asoca Sita Ashok 10 4000 3000 5000
Caryota Urens Bherli
Maad
09 4000 3000 5000
Environment
Management Plan
Sale bldg: capital cost: 56 lakhs and O&M cost: 17.7 lakhs/annum.
Rehab bldg: capital cost: 48 lakhs and O&M cost: 7.3 lakhs/annum.
Decision:
Chairman
61
The case was discussed on the basis of the presentation made by the proponent. The proponent
is directed to comply with the following observations:
1. It is noted that MCGM has agreed to provide 45 LPCD water for rehab portion only. PP
shall make adequate and sustainable arrangements for meeting additional water
requirement.
2. Reduce car parking area from proposed 48 m2 per car to 30 m
2 per car and submit the
revised plan accordingly.
3. STP treated water tanks shall be relocated away from the UG tanks for drinking water,
both in SRA and Sale buildings.
4.
5. The project proponent shall draw up a sustainable EMP model for both Rehab and Sale
projects with appropriate budget, as the proposed budget is inadequate. There shall be a
corpus fund for rehab portion. Provision of staff and equipment shall be also included in
the EMP budget.
6. Appropriate RWH to be considered and planned as the water table is very high.
7. Storm water drainage calculations shall be revised comprehensively and resubmitted.
8. New DC Rules shall be followed for fire and safety norms including fire-chute and fire-
check floors.
Chairman
62
Item No. 22
Subject: Environmental clearance for the Proposed SRA project "EKTA CHS" on
property bearing CTS No. 2603(pt) at village Dahisar, Tal. Borivali, S N Dube
Road, Rawalpada, Dahisar (East), Mumbai by M/s. Khushi Builders &
Developers (New case)
Project proponent was absent.
Chairman
63
Item No. 23
Subject: Environmental clearance for the proposed construction of Residential Project with
MMRDA Rental Housing Scheme ‘Auralis’ at Thane by M/s. Mercantile Plastic
Pvt. Ltd. (Name Changed to Deep Homes & Constructions Pvt. Ltd.)
(File No.:SEAC2011/CR 949/ TC2) (New case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : Proposed construction of Residential Project with MMRDA Rental
Housing Scheme
Project Proponent : M/s. Mercantile Plastic Pvt. Ltd. (Name Changed to Deep Homes &
Constructions Pvt. Ltd.)
Consultant : M/s. Mahabal Enviro Engg. Pvt. Ltd.
Location of the
project
: Plot Bearing CTS No. 136/B at village Hajuri, Thane
Type of Project : Construction project
Plot Area : 8,420.28 m2
Category : 8(a) B2
Previous
consideration/s
Nil
Proposed Total built
up area
: FSI Area: 31,861.13 m2 (Sale: 23,866.72 m
2. + 7944.41 m
2)
Non FSI area: 23,206.17 m2
Total Built up Area: 55,067.28 m2
Ground coverage 60%
Estimated cost of the
project
: 98 Crore
No. of Buildings : Building No. 1 (Sale): B + St + P + 32 Flrs
Building No. 2 (Sale): B + St + P + 32 Flrs
Building No. 3 (MMRDA): Stilt + 20 Flrs
Maximum Height of
building
: • Sale Bldg: 102.55 m
• MMRDA Bldg: 61.35 m
Total Water
Requirement
: • Fresh water: 314 m3/day
• Recycled water: 164 m3/day
Sewage Generation : 376 m3 /day
STP capacity : 425 m3/day (150 m3 for Sale Buildings and 275 m3 for Rental Building)
Chairman
64
STP Technology : SAFF – Submerged Aerated fixed Film Technology
Rain water
Harvesting
: • 2 RWH Tanks of Total capacity 150 m3
• 3 Nos. of Recharge wells of 2m dia and 3 m depth
Storm Water
Drainage
: Size of SWD - 0.3 m X 0.5 m
Solid waste
Generation
: • Biodegradable waste: 697 kg/day
• Non biodegradable waste: 1046 kg/day
• STP Sludge: 4 m3/day
Solid waste
Management
: • Dry garbage will be segregated & disposed off to recyclers.
• Wet garbage will be composted using Vermi Composting
Technology and used as organic manure for landscaping.
• STP sludge will be used as manure.
Green Belt
Development
: • R.G.Area Provided : 1711.18 m2 (20.32 %)
• RG area on ground: 776.62 sq. m.
• RG area on podium: 934.56 sq. m.
• Existing trees: 67 nos.
• Trees to be cut: 33 nos.
• Trees to be retained: 34 nos.
• No of trees to be planted: 215 Nos.
Energy Requirement : Energy: 4.1 MW
Capacity of DG Set provided for Sale will be 350 kVA and for Rental
180 kVA
Traffic Management : • Parking area provided: Gross Parking Area: 14,128.35 m2
• 2W: 249 Nos.
• 4W: 546 Nos.
Energy
Conservation
measures
: • Solar Panel lights will be installed for common facilities wherever
possible.
• Solar street lights are proposed for common areas such as open
spaces, pathways, RG etc.
Environmental
Management Plan
• Capital cost: Rs. 242 lakhs
• O & M Cost: 51 lakhs/annum
Decision:
The case was discussed on the basis of the presentation made by the proponent. The PP has
submitted the Pre-certification for Green Building from Indian Green Building Council.
Chairman
65
SEAC noted change in name of project proponent from M/s Mercantile Plastic Pvt Ltd to M/s
Deep Homes & Construction Pvt Ltd.
PP has demolished the existing structures to clear the site without obtaining the prior
environmental clearance. Environment Department may look into matter and take necessary
action.
The proponent is directed to comply with the following observations:
1. Submit a note on the history of the plot and present status at the site
2. Submit site photographs from different corners of the plot.
3. As per the guidelines issued by MoEF for High Rise Buildings vide O.M. no. 21-
270/2008- IA.III dated 7th February, 2012, for buildings with height greater than 60 m
the minimum width of the road (right of way) is 30 and the nearest fire station should be
located within distance of 2 km. In this case, the width of the road to as 18 m and the
height of the sale proposed is more than 102.55 m. Therefore, the PP shall recast the
project proposal by restricting the height complying with the MoEF guidelines for High
Rise Building.
4. Tenement density in Rental portion is about 2250/ha. The Committee is of the opinion
that it shall be restricted to maximum 1000/ha as such a high tenement density will affect
not only the environment but also the health of the residents..
5. Details of car parking justifying the local norms shall be submitted.
6. Submit the consent for required water supply from competent authority. If ground water
source is to be utilized as an alternate arrangement, the qualitative and quantitative of the
same shall be submitted.
7. STP for rental portion shall not be buried but located with adequate approach area, proper
ventilation and lighting for O&M.
8. Details of sludge disposal shall be submitted.
9. It is desirable to follow HRC Guidelines of MCGM in the interest of safety.
Chairman
66
10. Follow new DC Rules for fire and safety norms including fire-chute and fire-check
floors.
11. Submit a note on the existing trees, trees to be cut, trees to be transplanted and trees to be
planted (nos., size, age, and species) as per MoEF guidelines.
12. Small trees / shrubs (100 nos.) to be planted on Podium-RG
13. Submit Disaster Management Plant.
14. Ground coverage is more than 60%. The same shall be reducted to 50%.
15. Adequate ventilation measures need to be provided below podium and for the parking
area.
16. Submit large scale layout showing amenity spaces, RG area, water tanks and internal
roads.
Chairman
67
Item No. 24
Subject: Environmental clearance for the Proposed Slum Rehabilitation Project at Laxmi
Nagar, Andheri Link Road, Ghatkopar (East), ‘N’ Ward, Mumbai by M/s. Sri.Sai
Deep Realtors Pvt. Ltd
(File No.: SEAC 3511/CR962/TC2) (New case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : Construction project under SRA scheme
Project Proponent : M/s. Sri Sai Deep Realtors Pvt. Ltd
Consultant : M/s. Ultra-Tech Environmental Consultancy & Laboratory
Category : 8(a)- B2
Previous
consideration/s
: Nil
Location of the
project
: CTS No.184/C(Pt.) at Laxmi Nagar, Andheri Link Road, Ghatkopar
(East), ‘N’ Ward, Mumbai
Type of Project : SRA Project
Plot Area : 4,106.0 m2
Proposed Total built
up area
: FSI: 12,311.91 m2
Non - FSI: 16768.44 m2
Total BUA : 29071.61 m2
Ground coverage area 54 %
Estimated cost of the
project
: Rs.56.08 Cr
No. of Buildings : One composite building of 2 wings- wing A and Wing B
Rehabilitation:
Wing A : Stilt(Pt) + 15 +16 (Pt) upper floors
Flats: 200 flats.
Shops: 3Nos.
Balwadi: 3 Nos.
Welfare Centre: 3 Nos.
Society office: 2 Nos.
Mahila Mandal : 1 No.
Sale Building:
Wing B: 2 level basement + Ground (Pt) +Podium+1st to 14
th +15(Pt)
upper floors.
Flats: 114 flats. (Polyclinic, Pathology, Diagnostic, Clinic, Nursing
home : 5 Nos.)
Height of building 50.05 m (Up to terrace level)
Chairman
68
Water Requirement Fresh Water: 150 m3/day, Source: MCGM
Recycled water : 79 m3/day
Rain water harvesting 2 Rain water collection tanks of size 22 m3.
Wastewater generated 197 m3/day
Capacity of STP 217 m3/day, STP technology: MBBR Technology
Solid Waste
Generation
Biodegradable waste: 516 kg/day
Non biodegradable waste: 220 kg/day
STP Sludge (Dry sludge): 30 kg/day
Disposal Wet garbage will be treated in an Organic Waste Converter (OWC)
and the dry garbage will be handed over to M.C.G.M.
Dry STP sludge to be used as manure.
Energy For Rehabilitation: 300.8 Kw, and for Sale: 370.9 Kw.
DG set: 250 KVA x 1 No.
Energy Conservation Use of high energy efficient lamps (CFL, T5 lamps etc).
Use of all devices with low internal losses
Use of solar lights for the external street lighting poles
Insulated roof in order to reduce heat gain from sun.
Traffic Management Parking area = 3384,12 m2, 4‐Wheeler : 76 Nos
Width of internal rods: 4.0 - 6.0 m
Green Belt
Development
Total R.G area: 340.93 Sq. m. (8.30%)
New trees to be planted: 51 Nos.
Existing trees: 1 No., Trees to retained: 1 No.
Sr. Tree Varieties Botanical Name Total
1 Peepal (Existing) Ficus religiosa 01
2 Karanj Pongamia pinnata 09
3 Maharukh Alianthus excelsa 14
4 Ketesavar Bombax ceiba 06
5 Shirish Albizzia lebbeck 11
6 Neem Azadiracta indica 11 Environment
Management Plan
Capital cost: 82.29 Lakhs
Operation and Maintenance cost: 39.73 Lakhs
Decision:
The case was discussed on the basis of the presentation made by the proponent. It appears that
the sale building has been already built fully knowing that total BUA exceed construction area
20000 m2, however no EC was obtained. Environment Department may look into matter and take
necessary action.
The proponent is directed to comply with the following observations:
Chairman
69
1. Religious structures shall not be demolished.
2. Separate provisions shall be made for STP, Solid waste management, Environment
management plan for Rehab and Sale components.
3. Water supply (45 LPCD) is available only for rehab. Submit details of availability of
additional water supply in respect of the source, treatment and storage.
4. RG area is barely 8% and is located only near rehab building. No RG is proposed for sale
building.Therefore RG shall be properly distributed.
5. Underground water tanks shall be relocated away from STP to avoid contamination.
6. Number of parking shall be restricted to 68 as per requirement and area per car parking
shall be restricted to 30 m2 per car as the proposed is 46 m
2 per car.
7. A part of plot goes into the proposed road widening. This part is not deducted from area
calculations. The area calculations shall be revised accordingly and submitted.
8. Both Consultant and PP has not looked into many aspects of welfare of occupants and
their safety. The details of the same shall be submitted.
The comprehensive assessment will be done after submission of above compliance.
Chairman
70
Item No. 25
Subject: Environmental clearance for the proposed Residential Township at village
Kathivali,Tal.Shahapur, Distt. Thane M/s. Smart Value Homes Limited. (New
Case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : Residential Township
Project Proponent : M/s. Smart Value Homes Limited.
Consultant : M/S Enviro Analysts & Engineers Pvt. Ltd.
Category : 8(b) B1
Previous
consideration/s
: Nil
Location of the
project
: S. No. 279, 281, 285, 296, 298, 301, 305, 306, 310, 314, 315, 340,
342, 343, 318, 304, 311, 286, 287, 312, 288,302, 308, 309, 317, 341,
344 at Village Khativali, Tal- Shahapur, Dist- Thane
Type of Project : Construction project
Plot Area : 2, 04,160.00 m2
Proposed Total built
up area
: Total FSI area for Phase-I = 1,05,096.63 m2,
Total FSI area for Phase II = 34,548.90 m2
Total Non FSI area- 10,717.98 m2.
Total Built Up area- 1,50,363.42 m2
Ground coverage area 27.25 %
Estimated cost of the
project
: Rs. 241 crores
No. of Buildings : 70 Residential Buildings: 62 Bldgs(G+4), 8 Buildings(G+3)
121 Row Houses (G+1);
Highway Retail (G+1): 20 shops, 5 Restaurants, 1 Food court;
Retail Building 2 (G+1) : 22 shops;
Health care (G+1);
Community Center (G+1);
Club House(G+1);
Primary School.
Height of building 14.95 m maximum
Water Requirement Total water requirement: 1358.34 m3/day
Fresh Water: 791.17 m3/day
Recycled water : 567.17 m3/day
Rain water harvesting Rain Water Harvesting through Bore well Recharge Pits:
Size: (L=4.54 m x B=4 m x D= 3.0 m)
Total rainwater harvested: 4,438.18 m3/Day
Chairman
71
No. of Bore well recharge pits: 21 nos.
Runoff from the terrace shall be stored in storage tanks. Paved area
runoff shall be diverted to bore well recharge pits for the ground
water recharging. The overflow will be diverted to storm water drain
Wastewater generated 1086.672 m3/day
Capacity of STP STP with process SAFF Technology of 2nos having total capacity of
1655 KLD will be provided for the waste water treatment.
Solid Waste
Generation
Biodegradable waste: 2.9 T /day
Non biodegradable waste: 2.17 T /day
STP Sludge (Dry sludge): 272 Kg/day
Bio-Medical waste
Non infectious waste:-12 Kg/day
Infectious waste:-1.4 Kg/day
Hazardous waste:-0.7 Kg/day
Disposal • Organic waste will be sent to OWC, required amount of manure
from OWC will be used and rest will be handed over to the
vendors & Inorganic waste will be handed over to concerned
governing body.
• The biomedical waste will be handed over to the authorized
vendors for the further disposal.
• Some part of the sludge will be used for landscaping purpose
while the remaining 30kg/day will be handed over to the MoEF
certified vendor for safe disposal.
Energy Supply Capacity : 2420 KVA
9 no of DG set for essential power supply having capacities of
160,100,100,75,250,125,630,500,315(KVA)
Energy Conservation • Roofs will be insulated to minimize heat gain with 80 mm
expanded polystyrene or equivalent insulation.
• Light fixtures will be used with energy saving CFL & T5
fluorescent tube with electronic chocks.
• DG sets shall be PLC controlled to optimize their usage based on
the actual load requirements
• Use of Solar energy for street & landscape lightings.
• Small capacity transformers having low no load and load losses.
• Selection of Energy efficient equipments (BEE STAR RATED).
Traffic Management 4‐Wheeler : 826 nos.
Width of internal rods: 12 m
Chairman
72
Green Belt
Development
Name of Trees No. Of trees
Heliconia Psittacorum@450mmc/c 5753
Heliconia Rostrata@450mmc/c 1261
Alpina Zerembet@450mmc/c 991
Alpina Purpurata@450mmc/c 648
Bougainvillae Formosa@1mc/c 80
Bougainvillae Themma@1mmc/c 2632
Raphis Palms@450mmc/c 3980
Golden Durranta@450mmc/c 3029
Multicolour Acalypha@450mmc/c 2842
Cordyline Terminalis@450mmc/c 3266
Hawaiian Hibiscus@450mmc/c 2698
Hemelia Patens@450mmc/c 960
Pandanus Dwarf@300mmc/c 1989
Coedium Variagatum@300mmc/c 2261
Draceana Reflexa@300mmc/c 524
Spider Lily@300mmc/c 2970
Ophiogon Jaburan@300mmc/c 4046
Wadelia@300mmc/c 3463
Psittacorum Samanea Saman@10mc/c 101
Alstonia Scholaris@8mc/c 67
Lagerstroemia Floribunda@8mc/c 154
Lagerstroemia Speciosa@8mc/c 112
Drypetes Roxbhurghii@8mc/c 158
Azadirachta Indica 35
Cassia [email protected]/c 49
Cassia [email protected]/c 51
Ravanella Madagascurensis@6mc/c 14
[email protected]/c 86
Ficus [email protected]/c 34
Areca [email protected]/c 448
Bambusa [email protected]/c 141
Bahiunia [email protected]/c 118
Total R.G Area 19,055.05 m2
A Shrubs and Ground Cover
Area
8,071.12 m2
B Lawn 52,766.0 m2
C Grass Pavers at Parking 12,575.0 m2
D Pavers at Pathway 8,903.46 m2
Total Green Area 73,412.12 m2
Chairman
73
Taebuibia [email protected]/c 120
Taebuibia [email protected]/c 149
Delonix [email protected]/c 232
Cayrota Cuminghii@6mc/c 79
Plumeria Alba 46
Plumeria Rubra 22 Environment
Management Plan
Capital cost: 540 lakhs
Operation and Maintenance cost: 33.5 lakhs /annum
Decision:
The case was discussed on the basis of the presentation made by the proponent. The PP has
submitted the Pre-certification for Green Building from Indian Green Building Council. The PP
has not yet completed with the conditions of EC letter for the Phase 1 issued on 21st October,
2011 ,viz ...
(i) There shall be no discharge of surplus treated effluent to any nala, stream or any other
water body outside the project. The surplus effluent (after meeting the requirement for
flushing etc.) should have to be used for taking up gardening and horticultural
developments on the balance area of about 10 hectares.
(ii) PP shall lay a pipeline for carrying the surplus water to appropriate site as discussed in
SEAC & SEIAA Meetings.
(iii) Occupation/Third Party Rights should not be created unless and until water supply is
assured.
Without compliance of above conditions for Phase-I, application for Phase-II can not be
considered. PP has been advised to comply with the conditions mentioned in the EC granted for
Phase-I.
The comprehensive assessment will be done after submission of above compliance.
Chairman
74
Item No. 26
Subject: Environmental clearance for the SRA Project "Om Ganesh Nagar SRA Sahkari
Gruh Nirman Sanstha (prop) on plot bearing CTS No. 200 (pt) of Village
Wadhavali, Taluka Kurla, Mumbai by M/s. Deserve Exim Pvt Ltd
(File No.: SEAC 2010/CR558/TC2) (New Case)
Project proponent was absent.
Chairman
75
Item No. 27
Subject: Environmental clearance for the proposed Cement Grinding Unit (4.95 MTPA at
Additional Sinnar MIDC,Village Musalgaon, Dist. Nashik by M/s Eurotas
Infrastructure Limited (TOR case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : M/s Eurotas Infrastructure Limited, (Cement Grinding Unit)
Category : 3(b) – B1
Project Proponent : M/s Eurotas Infrastructure Limited
Consultant M/s Earthcare Labs. Pvt. Ltd.
Location of the project : Additional Sinnar MIDC,Village Musalgaon, Dist. Nashik
Latitude: 190 50’ 07” N to 19
0 54’ 37” N
Longitude: 740 00’ 53” E to 74
0 09’ 07”
MSL= 633 m
Type of Project : Cement Plant
Total Plot Area : 77 Acres (BUA = 50 Acres)
Project cost : 724.27 Cr
Products : Cement (CPC & OPC) - 4.95 MTPA
Raw materials : Clinker (3.56 MTPA), Fly ash (1.24 MTPA), Gypsum (0.17 MTPA),
Water
Water Requirement : 780 KLD ( Source – MIDC)
Effluent Generation : Domestic = 8 KLD
Rain water Harvesting : Ponds of total capacity of 600 m3 and 6 recharge pits.
Storm Water Drainage : MIDC Drain
Solid waste management : No domestic solid waste will be generated.
Small quantity of commercial waste generated will be recycled
through authorized dealers.
Air Pollution Control : Bag filters, dust suppression system
Green Belt Development : • Green belt area : 25.5 Acres (103195 m2)
• Pant species will be planted all along the internal roads and
boundary of the unit.
• Beautiful garden, lawn, waterfall, fountain etc. will be
developed. • Proposed to select plant saplings considering the parameters
as type, height, leaf area, crown area, growing nature, water
requirement etc. species such as Neem, badam, Imli, Umbar,
Gulmohar, Pipal, Katahal etc will be planted.
• About 500 saplings in the first year of commissioning
Chairman
76
Energy Requirement : 34 MW
Environmental
Management Plan
: Capital Cost of environmental protection measures =Rs. 8.7 Cr Recurring cost: Rs. 1.66 Cr/Y
Decision:
The case was discussed on the basis of the presentation made by the proponent.
The project proponent has been advised to carry out the EIA study considering the various
comments made by the committee and the model TOR prescribed (Page No 104) and then
approach the committee for the appraisal. A QCI accredited consultant and MOEF/NABL
accredited lab shall be used for the preparation of EIA Report.
Chairman
77
Item No. 28
Subject: Environmental clearance for the proposed expansion of industrial project
[Expansion of captive power plant] at S. N. 146 to 163, 165 to 190, Tal. Koparna,
Dist. Chandrapur by M/s. Manikgarh Cement
(File No.: SEAC 2011/CR-882 /TC-2) (TOR case)
The project proponet was absent.
Item No. 29
Subject: TOR for the proposed industrial project at Shilapur Village, S.N. 192 to 204 and
220, Nashik by M/s Utility Infrastructure & Works Pvt. Ltd., ( Nashik Grinding
& RMC Project)
(File No.: SEAC 2011/CR-2401/TC-2) (TOR case)
The project proponet was absent.
Item No. 30
Subject: Environmental clearance for the Hill station area development project at Village:
Mazgaon, Saltar, Barpe Bu., Bhambarde, Ekole, Ghutke and Adgaon, Taluka –
Mulshi, Pune by M/s. Maharashtra Valley View Pvt. Ltd
(File No.:SEAC2010/CR 571/ TC2) (Compliance case)
Project proponent was absent.
Chairman
78
Item No. 31
Subject: Environmental clearance for the construction project under SRA scheme at S. No.
263((pt), CTS No. 6A(PA), 6A/12/5(pt), 6A/12/6(pt), 6A(pt), Charkop, Malvani,
Village Kadivali (W), Mumbai by M/s. Shakti Property Developers Pvt. Ltd. (New
case)
(File No.: SEAC 2011/CR 951/TC2) (New Case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : Construction project under SRA scheme
Project Proponent : M/s. Shakti Property Developers Pvt. Ltd.
Consultant : SGM Corporate Consultants Pvt. Ltd
Category : 8(a)- B2
Location of the
project
: S. No. 263((pt), CTS No. 6A(PA), 6A/12/5(pt), 6A/12/6(pt), 6A(pt),
Charkop, Malvani, Village Kadivali (W), Mumbai
Type of Project : SRA Project
Plot Area : 23,122.00 m2
Proposed Total built
up area
: Total Construction area : 77,308.11 m2
Ground coverage area : 47.50 %
Estimated cost of the
project
: Rs. 98.98 Cr
No. of Buildings : Rehab Buildings:
Building 1 to 4,6,7 (G + 7 floors) (construction completed)
Building 5(G +8 floors)
Sale Buildings :
Building 1 (Wing O and P)(G + 7 ) Completed,
Building 1 (Wing Q) ( G + 22)
Building 2 (B +ST + P + 8)
Height of building : 69. 00 m
Existing structure &
demolition
: All the existing structure on plot has been demolished
Chairman
79
Water Requirement : Total Water Requirement: 888 m3/day
Fresh Water: 576 m3/day
Recycled water : 312 m3/day
Rain water harvesting : RWH tank : 2 Capacity 50 cum
Rain water harvesting pits: 4 nos. with size 3.0 x 3.0 x 3.0m
Wastewater generated : 698 KLD
Capacity of STP : 750 KLD
STP technology: MBBR Technology
Solid Waste
Generation
: Biodegradable waste: 1.30 MT/day
Non biodegradable waste: 1.31 MT/day
STP Sludge (Dry sludge): 0.040 MT/day
Disposal : Biodegredable waste will be composted by the OWC.
Non biodegradable waste will be handed over to the authorized
recycler.
Dry STP sludge to be used as manure.
Energy : Source of power & supply capacity: 3400 KVA, Reliance Energy
DG set: 250 KVA x 3 Nos.
Energy Conservation : Use of CFL and T5 fluorescent tube with electronic chocks
Use of solar energy for street and landscape lightings
Small capacity transformers having low no load an load losses.
Use of energy efficient equipments e.g. BEE STAR RARED
Traffic Management : 4‐Wheeler : 245 No
Width of internal rods: 6.0 and 9.0 m
Green Belt
Development
: Total R.G area: 2867.93 Sq. m.
Inside the plot:‐ 125 No
Outside the plot:‐ 45 No
Environment
Management Plan
: Construction phase:
Capital Cost: 5 lakhs
O&M Cost: 1.10 lakhs / annum
Operation phase:
Capital Cost: 225 lakhs
O&M Cost: 180 lakhs / annum
Decision:
The case was discussed on the basis of the presentation made by the proponent.
The proponent is directed to comply with the following observations:
1. Submit site photographs from different corners of the plot.
2. Submit a note on chronological details of the history of the plot with documentary
evidence and present status at the site
Chairman
80
3. As per the guidelines issued by MoEF for High Rise Buildings vide O.M. no. 21-
270/2008- IA.III dated 7th February, 2012, for buildings with height greater than 60 m
the minimum width of the road (right of way) is 30 and the nearest fire station should be
located within distance of 2 km. In this case, the width of the road to as 18.5 m and the
height of the proposed sale building is more than 60 m. Therefore, the PP shall restrict
the height complying with the MoEF guidelines for High Rise Building.
4. Submit the consent for required water supply from competent authority.
5. Fire hydrant shall be provided wherever fire engine is inaccessible.
6. Submit independent EMP for rehab and sale alongwith appropriate corpus for rehab
building.
7. Trees to be planted inside (45 nos) the plot and outside (45 nos) the plot. Small trees and
shrubs (100 nos.) shall be provided on podium. Details of the same shall be submitted.
Chairman
81
Item No. 32
Subject: Environmental clearance for proposed Residential Cum Commercial project
“ROSA GARDENIA” at S.No.25/1,25/2,29/8 at Village Kasavadvali, Taluka -
Thane, Dist. - Thane by M/s. Sai Enterprises.
(File No.: SEAC 2010/CR 665/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : Rosa Gardenia
Project Proponent : M/s. Sai Enterprises
Consultant : M/s. Enviro Analysts & Engineers Pvt. Ltd.
Category : 8 (a), B2
Previous
consideration/s
: 46th SEAC meeting dated 20
th October, 2011
49th SEAC meeting dated 18-21 January,2012
Location of the
project
: S.No.25/1,25/2,29/8, At Village Kasavadvali, Taluka - Thane, Dist.-
Thane
Type of Project : Residential Cum Commercial
Plot Area : 19,430 m2
Ground Coverage : 35.87 %
Proposed Total built
up area
: • FSI: 25,564.82 m
2
• Non-FSI: 17,426.66 m2
• Total Construction area: 42,991.48 m2
Estimated cost of the
project
: Rs. 140.00 Crores
No. of Buildings : Sr Description Details
1 No. of building 9 no.
2 No. of wings 2 no./Bldg
4 No. of floors Stilt + 16
5 No. of flats 496
6 No. of offices 1
7 No. of shops 32
8 Maternity hospital 01 Height of building Max height 56.56 m
Water Requirement Total water requirement = 409 KLD
Dry season:
• Fresh Water: 251KLD
• Recycled Water : 279 KLD
Chairman
82
• Excess treated water: 76 KLD
Wet season:
• Fresh Water: 251 KLD
• Recycled Water : 279 KLD Excess treated water: 102 KLD
Rain water
harvesting
• Percolation Pit Diameter : 1.5 M
• Depth: 6.00 M
• Fixed Depth: 2.40 M
• Total collection in RWH Tanks : 268 cum
Wastewater
generated
Sewage generation: 366 KLD, Technology: SAFF with R.O
Capacity of STP Capacity of STP: 5 STPs of total capacity of 378 KLD: The
wastewater generated from the proposed project will be treated by
sewage treatment plant and treated water will be recycled and used
for gardening & flushing requirement in the project. (Triple plumbing
the system)
Sewage holding tank of 658 KLD capacity which will store the 30%
RO reject (76 KLD during dry season) giving it a capacity of almost
7 - 8 days. After 7 - 8 days the RO reject from the holding tank will
be disposed off to the TMC sewer line along the Ghobunder Road.
Also the holding tank will serve as a sewage tank during the failure
or maintenance of the STP.
Solid Waste
Generation
• Total waste:1525.3 kg/day
• Organic waste: 924.2 Kg/day
• Non organic waste: 601.1 kg/day
• Bio-Medical Waste: 7.5 Kg/ day
• STP Sludge (Dry Sludge) : 78 Kg/day
Disposal • Organic waste will be sent to OWC for treatment and the manure
obtained after treatment will be used for gardening/landscaping.
• Inorganic waste will be handed over to the authorized recycler.
• The biomedical waste will be handed over to authorized agencies.
• Sewage sludge generated from the STP will be used as manure
for gardening.
Energy Energy requirement: 2.825 MW, Source: MSEB
DG Back up –
• DG sets with Acoustic enclosures for essential services
• For Tower A1 & A2 area only: 1 No. of 250 KVA
• For Common Area: 1 No. of 500 KVA
• For Hospital: 1 No. of 320 KVA
Energy
Conservation
Sr. Description Power
consumed
Power
consumed
Chairman
83
using
Conventional
method
(in kWh)
incorporatin
g energy
saving
methods
(in kWh)
1 External Lighting load 19958.40 13970.88
2 Lift load 1190246.40 833172.48
3 Pump load 324959.04 227471.33
4 Common area Load 157784.04 84151.49
5 Hospital Load 782992.80 417596.16
6 Solar Boiler for hot water 642816.00 214272.00
7 Total 3118756.68 1790634.34
8 Total Savings in power /
Annum (in Kwh)
1328122.34
9 Energy Consumed / Annum
in the absence of energy
savings method (in Kwh)
7432349.00
10 Total Energy Consumption /
Annum (in Kwh) with
energy saving method
6104226.00
11 Total savings in power
because of power saving
methods
42.58%
Traffic Management � 6 m Wide Internal Roads
� Parking Type: Stilt, Open spaces
� Total No. of Parking : 447 Cars, 550 Scooters
Green Belt
Development
400 shrubs and bushes on the elevated RG and 200 nos. of the large
and medium trees on the ground RG and along the boundary of the
plots
List of Trees
Sr Botanical Name Name
1 Caroyota Urens Fishtail Palm
2 Spathoda Campanulata Fountain Tree, Pichkari
Details Area in m2
Provided R.G. 5145.28
RG1 (Elevated) 3297.04
RG2 (Ground) (Paved RG) 669.19
RG3 (Ground) (Unpaved RG) 906.33
Total RG on ground 32.33 %
Chairman
84
3 Butea Monosperma Palas
4 Bombax Ceiba Katesvar
5 Cassia Fistula Bahawa
6 Tabebula Argentia Tabebuia
7 Alstonia Scholaris Satwin
List of shrubs
Sr Botanical Name Common Name
1 Melaleuca golden crest Golden bottle brush
2 Hibiscus rosea sinesis Hibiscus pink regular
3 Tabernaemontana coronaria
variegated
Variegated tagar
4 Ixora chinesis Chinese Ixora
5 Stachytarpheta Indica Stachytarpheta Red
6 Euphorbia leucocephala Polnsettla moutan snow
7 Belloperone gutta Shrimp plant red
8 Ficus Benjamin black Ficus black
9 Alpinia speclosa Alpinia yelow variegated
10 Euphorbia carcasana Euphorbia
11 Ficus benjamina Ficus prestige
12 Acalypha wikesiana Acalypha marble pink
13 Murraya exotica Kamini
14 Allamanda nerfolla Allamanda miniature
15 Ceasalpinia pulchirima Shankasur
16 Bougainvillea glabra Bougainvillea deep purple
17 Canna species (yellow) Canna dwarf yellow
18 Callandra emarginata Powder puff dwarf
19 Cassla biflora Cassla biflora
20 Ixora duffl red Ixora deep red
21 Lagerstormia indica Lagerstormia indica
22 Lantana camara Tantani
23 Eranthemum laxiflorum Tagar blue
24 Galphimia glauca Canara bush Environment
Management Plan
Capital cost: 359 lakhs
O & M Cost: 25.05 lakhs/annum
Decision:
The case was discussed on the basis of the presentation made by the proponent. SEAC decided to
recommend the proposal for Environmental Clearance only after complying with following
conditions:
Chairman
85
1. As agreed during the presentation, PP shall undertake that he will not commission the
project until water supply and drainage facility are made available by TMC.
2. OC will be issued subject to condition that fresh water supply and drainage facility
connections are provided by TMC.
3. UGT for treated waste water shall be located away from fresh water UGTs.
4. Submit a note on the existing trees, trees to be cut, trees to be transplanted and trees to be
planted (nos., size, age, species and locations) as per MoEF guidelines.
5. Revised drawings without RO system shall be submitted.
6. Submit original copies of all the letters issued by TMC regarding water supply and
drainage facility for verification.
Chairman
86
Item No. 33
Subject: Environmental clearance for proposed MMRDA Rental housing project
“Mahavir Square” located at Chitalsar, Manpada, Thane by M/s. Square Feet
Builders.
(File No.:SEAC2010/CR 678/ TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : MMRDA Rental housing “Mahavir Square”
Project Proponent : M/s. Square Feet Builders.
Consultant M/s. Enviro Analysts & Engineers Pvt. Ltd.
Location of the project : S. No. 59A/2A, 59A/16A/1/1 at Chitalsar, Manpada, Thane.
Type of Project : Construction project
Total Plot Area : 5767.00 m2
Proposed Total built up
area
: FSI area : Sale =16,739.44 m2, MMRDA = 5763.86 m
2
Non FSI area : Sale = 13,760.70 m2, MMRDA = 2790.26 m
2
Total construction area (FSI + Non FSI): 39,054.26 m2
Ground Coverage area 67.50 %
Estimated cost of the
project
: 77 Crores
No. of Buildings : Sale Bldg : 1 No. constituting 2 wings (1B+St+1P+29 fl)
MMRDA : 1 No. ( Gr/St + 25 fl)
Height of Building : Sale Bldg : 91.35 m
MMRDA : 72.5 m
Total Water Requirement : Total water requirement: 379 KLD (Fresh Water: 162 KLD
from TMC)
Sewage Generation : 304 m3/day
STP capacity : Two STP 1 x 220KLD for Gray water and 1 x 95 KLD for
black water
Rain water Harvesting : 2 tanks of 74 m3 and 39 m
3, 7 percolation tanks.
Solid waste generation : Biodegradable waste: 680.65 Kg/day
Non biodegradable waste: 450.85 Kg/day
STP Sludge: 76 Kg/day
Solid waste management : Biodegradable waste will be handed over to local garbage
collecting vehicle of TMC for further treatment.
Green Belt Development RG area on ground: 434.44 m2 ( 7.5 % of the plot)
Elevated RG area: 984 m2.
Trees to be cut are 54 nos. & trees to be planted are 150 nos.
Chairman
87
Energy Requirement Source: MSEB, Maximum demand: 2.2 MW
1 x 630 KVA for sale building, 1 x 250 KVA for Residential
housing.
Traffic Management Four-wheelers: 382 nos.
Two wheelers: 225 nos.
Energy Conservation
measures
Use of CFL, T5 lamps.
Solar energy proposed.
Environmental
Management Plan
Capital cost: 188 lakhs
O & M cost: 20 lakhs /Y
Decision:
The case was discussed on the basis of the presentation made by the proponent. PP has not
complied with most of the queries raised during the last meeting. It was noted that the major
concern of the Committee was tenement density and PP has not committed to reduce the same
close to 1000/ha during the presentation. This has constrained SEAC to recommend rejection of
the proposal.
Chairman
88
Item No. 34
Subject: Environmental clearance for the proposed Cement Grinding Unit (2.0 MTPA)
with DG Set (12 MW), At Village: Tarsa, Ashti, Tehsil: Mauda, District: Nagpur
by M/s Ultratech Cement Ltd.
(File No.: SEAC 2011/CR956/TC2) (TOR case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : Proposed Cement Grinding Unit (2.0 MTPA) with DG Set (12
MW), by M/s Ultratech Cement Ltd.
Category : 3(b) and 1(d) – B1
Project Proponent : M/s UltraTech Cement Ltd.
Consultant M/s J.M. EnviroNet Pvt. Ltd.
Location of the project : At Village: Tarsa, Ashti, Tehsil: Mauda, Dist: Nagpur
Latitude: 21° 15' 20.57"N- 21° 14' 38.99"N
Longitude: 79°22' 15.98"E- 79°22' 1.56"E
Elevation above Mean Sea Level: 279 m
Type of Project : Proposed Cement Grinding Unit (2.0 MTPA) with DG Set (12 MW)
Total Plot Area : 76.76 ha
Project cost : Project Cost:160 crore
Products : Cement = 2 MTPA
Raw materials : Clinker (4000-4450 TPD), Fly ash (1350-1850 TPD), Gypsum (300-
500TPD), Water
Water Requirement : 400KLD, Source: - River/Groundwater/ Industrial Area
(i) Process : 35 KLD
(ii) Cooling water : 130 KLD, for D.G. Set :150 KLD
(iii) DM Water: Nil
(iv) Dust Suppression: 20KLD
(v) Drinking: 10 KLD
(vi) Green belt : 35 KLD
(vii) Fire service : Nil
(viii) Others: 20KLD
Effluent Generation : Clinker Grinding is based on dry process technology so total water
will be recycled and reused as a result effluent will not be generated.
Domestic Effluent: Quantity & Disposal: 8KLD will be treated
through soak pit via septic tank
Solid waste management : No domestic solid waste will be generated. Small quantity of
commercial waste generated will be recycled through authorized
Chairman
89
dealers.
Air Pollution Control : 1 Bag House and 14 Bag Filters will be installed to control emissions.
Green Belt Development : Green belt area : 25.33 ha
Area will be covered at the rate of 1000 trees per hectare, with 20
m thickness around the plant boundary.
Existing plantation - Nil
Proposed no. of plant species = 25,000 trees
Number trees being cut/replanted or compensated- Nil
Energy Requirement : Total Power Requirement (MW); 12 MW
Source of Power: D.G. Sets / State Grid Supply
Environmental
Management Plan
: Capital Cost of environmental protection measures =Rs. 80 Lac Recurring cost: 6 lac/annum
Decision:
The case was discussed on the basis of the presentation made by the proponent. PP requested
to treat the project as B2 and submitted documents showing other such projects treated as B2
by MoEF.SEAC deliberated the issue and noted that proposed total land is not in possession
of PP and some portion of it is under agriculture use.Considering this ,the project proponent
has been advised to carry out the EIA study considering the various comments ( viz.
conversion to landuse pattern to non-agricultural (NA) purpose, satellite imagaery, drawal of
water etc.) made by the committee and the model TORs prescribed both for Cement and
Power Plant (Page No 104 & 119 ) and Public consultation as per MoEF guideline. A QCI
accredited consultant and MOEF/NABL accredited lab shall be used for the preparation of
EIA Report.
Chairman
90
Item No. 35
Subject: Environmental clearance for the expansion of industrial project [Expansion of
power plant] at plot No. E 1, E 2, E 3 MIDC Waluj, Aurangabad by M/s. Sterlite
Technologies Limited
(File No.: SEAC 2011/CR895/TC2) (TOR case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : M/s. Sterlite Technologies Limited
Category : 1(d) – B1
Project Proponent : M/s. Sterlite Technologies Limited
Consultant M/s SMS Envocare ltd
Location of the project : Plot No. E 1, E 2, E 3 MIDC Waluj, Aurangabad
Latitude : 190 50’ 24.57” N
Longitude : 750 13’ 46.27” E
Elevation above Mean Sea Level : 513 m
Type of Project : Expansion of power plant - Power generation on Furnace Oil based
Total Plot Area : Total plot area: 34788 m2
Built up: 22978 m2
Project cost : 9.19 Cr (Expansion)
Products : Existing 6 MW Captive Power Plant Expansion by 7.88 MW (6 +
7.88) Captive Power plant, Total Capacity = 13.88 MW Power
generation on Furnace Oil based
Raw materials : Furnace Oil (Liquid) = 2000 MT/Month
HSD (Liquid) = 6 MT/Month
Lube Oil (Liquid) = 8.5 MT/Month
Boiler Chemical (Solid) = 350 KG/Month
Cooling Tower Chemical (Solid) = 350 KG/Month
Water Requirement : Source: MIDC water Supply
Total Water Requirement After Expansion : 91 CMD
(i) Process : Nil
(ii) Cooling water : 55 CMD (Existing 20 + Proposed 35 CMD)
(iii) Drinking : 1 CMD (Existing 0.2 CMD + Proposed 0.8 CMD)
(iv) Green belt : 20 CMD
(v) Fire service: - Make up
(vi) Boiler : 15 CMD (Existing 15 CMD + Proposed Nil )
Effluent Generation : Total Effluent generation : 7.8 CMD
Domestic Effluent = 0.3 CMD
Chairman
91
Trade Effluent: 7.5 CMD
ETP / STP capacity : Capacity of ETP: Existing ETP -55 CMD
Rain water Harvesting : Proposed
Storm Water Drainage : Storm water drains will be constructed. Storm water from the entire
plot will be collected through network of storm drains. Storm water
from plot area will be collected in the rainwater harvesting pits
provided for this purpose. The overflow from these pits, if any, will
be then discharged in the nalla.
Solid waste management : No solid wastes are generated during the operation phase. The liquid
waste generated during the operation phase is Spent Oil (EXISTING
-100 KG/Day) (Proposed - 660 KG/Day) Total = 760 KG/Day – will
be sent to authorized Reprocessor
Air Pollution Control : The pollutants envisaged from the project activity are Suspended
Particulate Matter (SPM), Oxides of Nitrogen (NOx), Carbon mono-
oxide (CO) and CO2. Scrubber (existing) installed.
Green Belt Development : Green belt area : 33% will be provided
Area in Sq. meter- 11810 m2
Energy Requirement : DG Sets: 1No, Capacity :- 200 KVA
Environmental
Management Plan
: Cost of environmental protection measures = Rs. 86.5 Lakhs
Recurring Cost = Rs. 12 Lakhs / Yr
Decision:
The case was discussed on the basis of the presentation made by the proponent. The project
proponent has been advised to carry out the EIA study considering the various comments made
by the committee and the model TOR prescribed (Page No 119) and then approach the
committee for the appraisal. A QCI accredited consultant and MOEF/NABL accredited lab shall
be used for the preparation of EIA Report.
Chairman
92
Item No. 36
Subject: Environmental clearance for the proposed Sponge iron 180 TPD, 30 MW power
plant, MS Billets Mini Steel plant 525 TPD and Re-Rolling Mill 500 TPD at Mul
MIDC area, Chandrapur Dist by Rajuri steels and Alloys Pvt. Ltd.
(File No.: SEAC2011/CR683/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted
project details furnished by the Project Proponent as:
Name of the Project : Sponge iron 180 TPD, Power plant 30 MW, Billet plant 525 TPD and
Re rolling mill 500 TPD
Project Proponent : M/s. Rajuri steels and Alloys Pvt. Ltd.
Consultant M/s. Pollution and Ecology control services, Nagpur
Category 3 (a) and 1(d), B1
Previous
consideration/s
: 26th meeting of the State Level Expert Appraisal Committee (SEAC)
held on 17th April, 2010
Location Plot No. B-6, 7, and 8 MIDC, Mul, District Chandrapur.
Plant Metallurgical industry and power plant
Products Sponge iron: 180 TPD
M.S. Billet plant: 525 TPD
Re rolling mill: 500 TPD
Power plant: 30 MW
Raw material Sponge iron plant:
Iron ore: 288 TPD
Coal: 216 TPD
Dolomite: 1.8 TPD
CPP:
Coal: 374 TPD
Char: 49 TPD by product
Rolling Mill: Coal in Gasifier: 45TPD
Total plot area 24 ha.
Estimated cost of the
project
Rs. 15,775 Lakhs.
Total water
requirement
Total water requirement: 210 m3/day, Source: MIDC
Sponge iron plant: 50 m3/day
Captive power plant: 100 m3/day
MS Billets: 40 m3/day
Domestic: 20 m3/day
Chairman
93
Waste water
generation
110 m3/day
Green belt area 30 % of the plot area
Power generation 30 MW
Air pollution control
measures
Sponge iron: bag filters / ESP
Captive power plant: ESP
M.S.Billets: Ventury scrubbers
Rolling mill: bag filters and ecupraetors
Dry fog type dust suppression system to control the secondary
fugitive emission.
Air pollution control
measures
• M/S RSAPL shall provide dust suction system which will
control fugitive emission due to raw material handling.
• Dust suppression system will be provided in the form of water
sprinklers. All vibrating screens and weigh feeders below the
hopper, day bins etc are totally covered to prevent leakages of
dust. All bins are totally packed and covered so that there is
no chance of dust leakage. All material transfer points are
connected with dust suppression water nozzles to avoid air
pollution. From Sponge iron plant fugitive emission will be
envisaged due to accumulation of ash on finished product
surface.
• Ventury scrubbers will be provided for the extraction of dust
particles. The continuous casting operation is selected for the
production of billets in induction furnace.
Water pollution
control measures
• The waste water generated from the proposed power plant
with captive power plant will be suitably treated in effluent
treatment plant. The effluent generation mostly from captive
power plant consists of cooling tower down boiler blow
down, service water and sanitary waste. Effluent from the DM
plant will be neutralized.
• The treated effluent will be recycled to rolling mill as make
up water for cooling and the remaining will be used in the ash
pond, dust suppression and green belt development.
• Treated waste water will be recycled 100 %. No waste water
will discharged outside the plant boundary.
Noise pollution
control measures
• Providing padding at various locations to avoid sharp noise
due to vibration.
• Encasement of noise generating equipment where otherwise
noise cannot be controlled
• Providing noise proof cabins to operators where remote
control for operating noise generating equipment is feasible.
• In all the design/installation precautions are taken as specified
Chairman
94
by the manufacturers with respect to noise control will be
strictly adhered to; High noise generating sources will be
insulated adequately by providing suitable enclosures;
• Use of lagging with attenuation properties on plant
components / installation of sound attenuation panels around
the equipment
• Other than the regular maintenance of the various equipment,
ear plugs/muffs are recommended for the personnel working
close to the noise generating units;
• All the openings like covers, partitions will be designed
properly
• Inlet and outlet mufflers will be provided which are easy to
design and construct.
• All rotating items will be well lubricated and provided with
enclosures as far as possible to reduce noise transmission.
Extensive vibration monitoring system will be provided to
check and reduce vibrations. Vibration isolators will be
provided.
Solid waste
management
• Char: 49 TPD will be utilized Fluidized Bed Combustion
Boilers after washing.
• Fly Ash 127 TPD; 100% shall be used in the brick unit.
Temporary storage of unused ash in ash pond.
Decision :
The case was discussed on the basis of the presentation made by the proponent. The PP has
submitted the report on flora & fauna and CSR during the presentation.As SEAC needed some
time to go through the documents it is decided to consider the case in next meeting.
Chairman
95
Item No. 37
Subject: Environmental clearance for the proposed Pharma SEZ at village Krushnoor,
District Nanded M/s Parsvnath MIDC Pharma SEZ Pvt Ltd.
(File No.: SEAC 2011/CR 960/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : Proposd pharma SEZ at village Krushnoor, Dist Nanded
Project Proponent : M/s Parsvnath MIDC Pharma SEZ Pvt Ltd.
Consultant : M/s Voyents Solution Ltd
Category : 7(c) 7 (d) B1
Location of the
project
: village Krushnoor, Hyderabad Road, adjacent to State Highway
MSH-3, Nanded hydrabad state highway, Dist Nanded
Type of Project : Area development - Pharma SEZ
Total Area : 150 Hectors
Estimated cost of the
project
: Rs. 52.44 Cr
Water Requirement : Total Water Requirement: 8.11 MLD
Processing area: 6.55 MLD
Non processing area: 1.56 MLD
Rain water harvesting : 80 nos. of recharge pits are proposed.
Sewage and waste
water
: • MLD of domestic water will be treated in STP (SAFF
Technology).
• 3.46 MLD of trade effluent will be treated in CETP.
• Treated water from STP and CETP will be used for gardening and
cooling.
Solid Waste
Generation
: • Spent oil will be sent to the authorized recyclers.
• Sludge from CETP will be sent to the authorized recycler.
Energy : 85.26 MVA
Green Belt
Development
: • RG on the ground: 1,29,150 Sq.m
• Existing trees: 50 nos. and 150 nos. of trees will be replanted or
compensated.
Environment
Management Plan
: Capital Cost: 1595 lakhs
O&M Cost: 175lakhs / annum
Decision:
Chairman
96
The case was discussed on the basis of the presentation made by the proponent. SEAC noted
letter submitted by PP dated 30.03.2012 having provision of Captive Power Plant and CETP
during the area development. However, during presentation, PP clarified that no Captive Power
Plant is proposed and only CETP is proposed during the area development. In view of this SEAC
decided that the project will be appraised under the Category No. 7(C) [i.e SEZ] and
7(d)[i.e.CETP].
The proponent is directed to comply with the following observations:
1. Submit undertaking regarding withdrawal of Captive Power Plant from the proposed area
development and submit revised Forms accordingly.
2. Carry out the EIA study considering the various comments made by the committee and the
model TORs prescribed both for SEZ and CETP (Page No136 & 111) and then approach the
committee for the appraisal. A QCI accredited consultant and MOEF/NABL accredited lab
shall be used for the preparation of EIA Report.
3. It is not clear whether the project site falls in a notified industrial area.This may be clarified
with necessary documents. If it be outside notified industrial area, then public consultation
will be necessary.
4. The layout of the plots has been done without considering the very undulating topography of
the site and needs to be modified.
5. PP needs to do indivisual plot development so that all necessary infrastructures like surface
run-off drains, internal roads, STP and sewerage etc. are provided in the proposed scheme.
6. Details as to how the capacity of CETP,STP,etc. are worked out be furnished.
Chairman
97
Item No. 38
Subject: Environmental clearance for the proposed Adegaon Dolomite and Limestone
Mine (35.87 Ha), Tehsil Zarijamni, District Yavatmal by M/s. Linkson Coals &
Minerals Pvt. Ltd
(File No.: SEAC3511/CR964/TC2) (Compliance case)
The project proponent was absent.
Chairman
98
Item No. 39
Subject: Environmental clearance for the proposed expansion of sugar unit from 5,000 TCD
to 8,000 TCD along with cogeneration unit of 18.585 MW at Mahatma Phule Nagar,
village Bijwadi Tal-Indapur, Dist-Pune by M/s. Karmayogi Shankarraoji Patil
Sahakari Sakhar Karkhana Limited
(File No.: SEAC2012/CR 001/TC2) (Compliance case)
The Project Proponent explained the proposal before the committee and committee noted project
details furnished by the Project Proponent as:
Name of the Project : Expansion of sugar unit from 5,000 TCD to 8,000 TCD along with
cogeneration unit of 18.585 MW.
Category : 5(J) and 1(d), B1
Project Proponent : M/s. Karmayogi Shankarraoji Patil Sahakari Sakhar Karkhana
Limited
Consultant M/s. Vasantdada Sugar Institute, Pune
Location of the project : Mahatma Phule Nagar, village Bijwadi Tal-Indapur
Type of Project : Sugar unit along with cogeneration plant.
Total Plot Area : 18 Acres built up area, 6 acres provided for green belt development
Estimated cost of the
project
: Rs. 12103.48 lakhs
Products : Name of
Products,
Byproducts
Existing Proposed activity
(new/
modernization/e
xpansion)
Total
A. Main
Products
White Sugar:
467 MT/Day
White Sugar:
920 MT/Day
Power: (18.585
MW electricity)
White Sugar
920 MT/Day,
18.585 MW
Electricity
B. By-
Products
Molasses : 163
MT/Day
Bagasse : 1300
MT/Day
Press mud:
173MT / Day
Molasses : 320
MT/Day
Bagasse : 2240
MT/Day
Press mud: 320
MT / Day
Molasses :
320MT/Day
Bagasse :
2240MT/Day
Press mud:
320MT/Day
Chairman
99
Raw material Sugar Cane: 8,000 MT/Day
Lime : 9.8MT/Day
Sulfur: 4.64 MT/Day
Bagasse (Fuel): 106.875 TPH ( 76,950TPM)
Water Requirement : Total Water Requirement: 2835 m3/day
Recycled water: 1975 m3/day
Power Generation : Total Power Requirement (MW): 10.925( Sugar Factory, ETP,
Office, Colony, Workshop, Other)
Solid waste
management
Raw water Treatment Plant: 3.0 TPM; Land filling in own
gardening area
ETP: 85 TPM; Utilized for composting along with press mud
Process Ash: 1014 TPM; Utilized for composting along with press
mud
Effluent Generation Total Effluent generation: 856 m3/day,
Effluent treated in ETP of 1,700 m3/day ; will be used for irrigation
purpose.
Pollution control
measures
Aspect Existing Proposed
Air Mechanical Dust
collector Wet scrubber
Water Effluent Treatment
Plant
Existing ETP at sugar factory is
of 1700m3 which is adequate to
treat the additional effluent
from cogeneration unit.
Noise Regular
maintenance of
machinery and
greenbelt
Boiler and power house in
closed area
Greenbelt development for
proposed unit
Solid
Waste
Bio-compost unit Adequate for disposal of
additional ash
due to cogeneration unit Green belt area Green belt area: 24281.13 Sq. m
Existing nos. of trees: 10,000 nos.
Proposed nos. of trees with plant species: 5,000 nos.
Environmental
Management Plan
: Capital cost: 450 Crores
Recurring cost: Rs. 17 Lakhs
Decision:
The case was discussed on the basis of the presentation made by the proponent. The
project proponent submitted Minutes of the Public hearing and EIA report. SEAC decided to
recommend the proposal for Environmental Clearance only after complying with following
conditions:
Chairman
100
1. Submit a note on the existing trees, trees to be cut, trees to be transplanted and trees to be
planted (nos., size, age, species and locations) as per MoEF guidelines.
2. Submit detailed note on RWH.
3. Submit detailed note on ETP along with effluent characteristics.
4. The project proponent shall draw up a sustainable model with appropriate EMP, as the
proposed EMP (O&M) is inadequate.
Chairman
101
Item No. 40
Subject: Environmental clearance for the Proposed residential building at land bearing Sr.
No. 127/175, Waked Chinchwad road, waked Mulshi, Pune by M/s. Manav
Promoters Pvt. Ltd. (New case)
SEAC noted that the PP has not furnished the projects details. The proponent is directed to
comply with the following preliminary observations:
1. Submit plot history and chronological developmental details of Phase I, II and III.
2. Submit site photographs from different corners of the plot for poposed phase.
3. Dimensioned Master plan layout explaining the STPs, RWH, storage water tank for the
fire fighting etc. should be submitted
4. Submit the consent for drainage facility and additional required water supply from
competent authority.
5. Submit copy of Conveyance Deed.
6. Submit a note on the existing trees, trees to be cut, trees to be transplanted and trees to be
planted (nos., size, age, species and locations) as per MoEF guidelines.
7. Non FSI area on account of covered parking is catering only to Phase-II. Ensure that it is
not loaded to Phase-III.
Comprehensive assessment will be done after studying the proposal.
Chairman
102
Item No. 41
Subject: Environmental clearance for the proposed Residential Project on plot bearing
S.No.112,112/1 to 4,113/1, 113/2,114 to 118,118/1 to 5,119,119/1 to 11 of village
Goregaon(West), Mumbai by M/s.Skystar Buildcon Private Limited (New Case)
SEAC noted that the PP has not furnished the projects details The proponent is directed to
comply with the following preliminary observations:
1. Ground Coverage is very high (76%).
2. Per car parking area is very high.
3. Consent for drainage facility and required water supply from competent authority was
not available.
4. Non FSI-area is very high.
5. No confirmation that PP has fully adopted new DCR.
6. Details of RG on groundand podium not available.
7. RG area ground seems to be inadequate.
Comprehensive assessment will be done after studying the proposal.
Chairman
103
Item No. 42
Subject: Environmental clearance for the Proposed residential project at Undri, Pune by
M/s. Nyati Builders Pvt Ltd (New Case)
SEAC noted that the PP has not furnished the projects details The proponent is directed to
comply with the following preliminary observations:
1. PP informed that he has formed a joint venture with other party and accordingly name of
the project is changed. Undertaking regarding the same is not submitted.
2. Location of the plot is beyond PMC limits, therefore amenities like water supply and
drainage facilities are not available. PP has not clarified the status and postion of the
same.
3. As the plot has many steep areas, cutting into steep slopes for development of plot is not
advisable. Such steep area can be conveniently used for development of green spots. The
nayout needs to be accordingly modified.
4. Detailed layout map showing storm water outfall was not available.
5. The ground coverage calculation needs revision by eliminating the amenity area to be
handed over.
Comprehensive assessment will be done after studying the proposal.
Chairman
104
Term of Reference
TOR for Cement Industry
For the limestone mine captive to cement plants, separate ToRs specified for cement and as well as mining
are required to be considered. ToR for EIA studies for cement plants may include, but not limited to the
following:
1 Executive summary of the project – giving a prima facie idea of the objectives of the proposal, use of
resources, justification, etc. In addition, it should provide a compilation of EIA report, including EMP
and the post-project monitoring plan in brief.
Project description:
2 Justification for selecting the proposed product and unit size.
3 Land requirement for the project including its break up for various purposes, its availability and
optimization.
4 Details of proposed layout clearly demarcating various units/industries within the plant.
5 Complete process flow diagram describing each unit, its processes and operations, along with
material and energy inputs and outputs (material and energy balance).
6 Details of proposed source-specific pollution control schemes and equipments to meet the national
standards.
7 Details on requirement of raw materials, its source and storage at the plant.
8 Details on locating the residential colonies on upwind direction.
9 Details of the proposed methods of water conservation and recharging.
10 Management plan for solid/hazardous waste generation, storage, utilization and disposal.
11 In case, hazardous waste is proposed to be charged in kilns, details on type of waste, its
characteristics and monitoring of emissions of gases, heavy metals, VOCs, dioxins and furans.
12 Scheme of proper storage of fly ash, gypsum, clinker.
13 Analysis report of Sulphur content in fuels and Sulphur balance data.
14 Details of heat and noise emission sources from the proposed project and proposed measures.
15 Details of CO2 emissions including its quantum per tonne of cement.
16 Details regarding infrastructure facilities such as sanitation, fuel storage, restroom, etc. to the workers
during construction and operation phase.
Chairman
105
17 In case of expansion of existing industries, remediation measures adopted to restore the
environmental quality if the groundwater, soil, crop, air, etc., are affected and a detailed compliance
to the prior environmental clearance/consent conditions.
18 Any litigation pending against the project and /or any direction /order passed by any
Court of Law related to the environmental pollution and impacts in the last two years,
if so, details thereof.
Description of the environment:
19 The study area shall be up to a distance of 10 km from the boundary of the proposed project site.
20 Location of the project site and nearest habitats with distances from the project site to be demarcated
on a toposheet (1: 50000 scale).
21 Land-use based on satellite imagery including location specific sensitivities such as national parks /
wildlife sanctuary, villages, industries, etc. for the study area.
22 Demography details of all the villages falling within the study area.
23 Topography details of the project area.
24 The baseline data to be collected from the study area w.r.t. different components of environment viz.
air, noise, water, land, and biology and socio-economic.
25 Details of geological features of the study area and mine area. Hydrological regime plan shall be
prepared and incorporated. Interception of mining with the groundwater, if any.
26 Surface water quality of nearby water sources and other surface drains.
27 Details on ground water quality.
28 Details on existing ambient air quality and expected, stack and fugitive emissions for PM10, PM 2.5,
SO2* and other sulphur compounds, NOx* and other nitrogen compounds, carbon oxides (CO and
CO2) etc., and evaluation of the adequacy of the proposed pollution control devices to meet standards
for point sources and to meet AAQ standards. (* - As applicable)
29 Details on other pollutants also to be considered in relation to the production of cement, especially
with secondary fuels are VOC, polychlorinated dibenzodioxins and dibenzofurans (PCDDs and
PCDFs), metals and their compounds, Hydrogen Fluoride, Hydrochloric Acid (HCl), etc.
30 The air quality contours may be plotted on a location map showing the location of project site,
habitation nearby, sensitive receptors, if any and wind roses.
31 Chemical characterization of RSPM data.
32 Details on baseline data on silicosis in buffer and core zone.
33 Details on noise levels at sensitive/commercial receptors.
34 Site-specific micro-meteorological data including mixing height.
35 One season site-specific data excluding monsoon season.
36 Proposed baseline monitoring network for the consideration and approval of the Competent
Chairman
106
Authority.
37 Ecological status (terrestrial and aquatic) of the study area such as habitat type and quality, species,
diversity, rarity, fragmentation, ecological linkage, age, abundance, etc.
If any incompatible land-use attributes fall within the project area, proponent shall describe the
sensitivity (distance, area and significance) and propose the additional points based on significance
for review and acceptance by the SEAC. Incompatible land-use attributes include:
a. Public water supply areas from rivers/surface water bodies, from ground water
b. Scenic areas/tourism areas/hill resorts
c. Religious places, pilgrim centers that attract over 10 lakh pilgrims a year
d. Protected tribal settlements (notified tribal areas where industrial activity is not permitted)
e. CRZ
f. Monuments of national significance, World Heritage Sites
g. Cyclone, Tsunami-prone areas (based on last 25 years)
h. Airport areas
i. Any other feature as specified by the State or local government and other features as locally
applicable, including prime agricultural lands, pastures, migratory corridors, etc.
If ecologically sensitive attributes fall within the project area, proponent shall describe the sensitivity
(distance, area and significance) and propose the additional points based on significance for review
and acceptance by the SEAC. Ecological sensitive attributes include:
a. National parks
b. Wild life sanctuaries, Game reserve
c. Tiger reserve/elephant reserve/turtle nesting ground
d. Mangrove area
e. Wetlands
f. Reserved and Protected forests, etc.
39
g. Any other closed/protected area under the Wild Life (Protection) Act, 1972, any other area
locally applicable
40 If the location falls in a valley, studies on specific issues connected to the natural resources
management.
41 Identification of CRZ area: A CRZ map duly authenticated by one of the authorized agencies
demarcating LTL(Low Tide Level), HTL (High Tide Level), CRZ area, location of the project and
associate facilities w.r.t. CRZ, coastal features such as mangroves, if any. The route of the pipeline,
etc., passing through CRZ, if any, should also be demarcated. Recommendations of the State Coastal
Management Authority for the activities to be taken up in the CRZ.
– Provide the CRZ map in 1:10000 scale in general cases and in 1:5000 scale for specific
observations.
– Proposed site for disposal of dredged material and environmental quality at the point of
Chairman
107
disposal/impact areas.
– Fisheries study should be done w.r.t. Benthos and Marine organic material and coastal fisheries.
Anticipated environmental impacts and mitigation measures :
42 Anticipated generic environmental impacts due to this project may be evaluated for significance and
based on corresponding likely impacts Valued Environmental Components (VECs) may be
identified. Baseline studies may be conducted for all the concerned VECs and likely impacts will
have to be assessed for their magnitude in order to identify mitigation measures.
43 Impact prediction tools used for the appropriate assessment of environmental impacts .
While identifying the likely impacts, also include the following for analysis of significance and
required mitigation measures:
a impacts due to transportation of raw materials and end products on the surrounding environment
b impacts on surface water, soil and groundwater
c impacts due to air pollution
d impacts due to odour pollution
e impacts due to noise
f impacts due to fugitive emissions
44
g impact on health of workers due to proposed project activities
45 Proposed odour control measures
46 Action plan for the greenbelt development – species, width of plantations, planning schedule, etc., in
accordance to CPCB published guidelines.
47 In case of likely impact from the proposed project on the surrounding reserve forests, Plan for the
conservation of wild fauna in consultation with the State Forest Department.
48 Mitigation measures - for source control and treatment.
49 Air quality modeling for the cement plant should be incorporated. Air pollution control system to be
installed should be elaborated upon to control emissions within 50 mg/Nm3.
50 Details on rainwater harvesting at the cement plant site.
Analysis of alternative resources and technologies:
51 Comparison of alternate sites considered and the reasons for selecting the proposed site. Conformity
of the site with the prescribed guidelines in terms of CRZ, river, highways, railways, etc.
52 Details on improved technologies.
Environmental monitoring program:
Chairman
108
53 Specific programme to monitor Nickel and Vanadium emissions be included, incase of use of pet-
coke.
54 An action plan to control and monitor secondary fugitive emissions as per the CPCB guidelines.
55 Monitoring programme for pollution control at source
56 Monitoring pollutants at receiving environment for the appropriate notified parameters – air quality,
groundwater, surface water, gas quality, etc. during operational phase of the project.
57 Specific programme to monitor safety and health protection of workers
58 Appropriate monitoring network has to be designed and proposed, to assess the possible residual
impacts on VECs.
59 Details of in-house monitoring capabilities and the recognized agencies if proposed for conducting
monitoring.
Additional studies:
60 Clearances/approvals from the IBM and State government for the linked mining component.
61 Details on risk assessment and damage control during different phases of the project and proposed
safeguard measures.
62 Details on socio-economic development activities such as commercial property values, generation of
jobs, education, social conflicts, cultural status, accidents, etc.
63 Proposed plan to handle the socio-economic influence on the local community. The plan should
include quantitative dimension as far as possible.
64 Details on compensation package for the people affected by the project, considering the socio-
economic status of the area, homestead oustees, land oustees, and landless labourers.
65 Points identified in the public hearing and commitment of the project proponent to the same. Detailed
action plan addressing the issues raised, and the details of necessary allocation of funds.
66 Administrative and technical organizational structure to ensure proposed post-project monitoring
programme for approved mitigation measures..
67 EMP devised to mitigate the adverse impacts of the project should be provided along
with item-wise cost of its implementation (Capital and recurring costs).
68 Allocation of resources and responsibilities for plan implementation.
69 Details of the emergency preparedness plan and on-site and off-site disaster management plan.
Above points shall be adequately addressed in the EIA report at corresponding chapters, in addition
to the contents given in the reporting structure as below:
Sr. EIA Structure Contents
1 Introduction Purpose of the report
Chairman
109
Identification of project & project proponent
Brief description of nature, size, location of the project and its
importance to the country, region
Scope of the study – details of regulatory scoping carried out
Condensed description of those aspects of the project (based on
project feasibility study), likely to cause environmental effects.
Details should be provided to give clear picture of the following:
Type of project
Need for the project
Location (maps showing general location, specific location,
project boundary & project site layout)
Size or magnitude of operation (incl. Associated activities
required by / for the project)
Proposed schedule for approval and implementation
Technology and process description
Project description including drawings showing project layout,
components of project etc. Schematic representations of
feasibility drawings which give information important for EIA
purpose
Description of mitigation measures incorporated into the project
to meet environmental standards, environmental operating
conditions, or other EIA requirements (as required by the scope)
2 Project Description
Assessment of New & untested technology for the risk of
technological failure
Study area, period, components & methodology
Establishment of baseline for VECs, as identified in the scope
3 Description of the
Environment
Base maps of all environmental components
Details of Investigated Environmental impacts due to project
location, possible accidents, project design, project construction,
regular operations, final decommissioning or rehabilitation of a
completed project
Measures for minimizing and / or offsetting adverse impacts
identified
Irreversible and irretrievable commitments of environmental
components
4 Anticipated
Environmental
Impacts & Mitigation
Measures
Assessment of significance of impacts (Criteria for determining
significance, Assigning significance)
Chairman
110
Mitigation measures
Incase, the scoping exercise results in need for alternatives:
Description of each alternative
Summary of adverse impacts of each alternative
5 Analysis of
Alternatives
(Technology & Site)
Mitigation measures proposed for each alternative and selection
of alternative
6 Environmental
Monitoring Program
Technical aspects of monitoring the effectiveness of mitigation
measures (incl. measurement methodologies, frequency, location,
data analysis, reporting schedules, emergency procedures,
detailed budget & procurement schedules)
Public consultation
Risk assessment
7 Additional Studies
Social impact assessment, R&R action plans
Improvements in physical infrastructure
Improvements in social infrastructure
Employment potential –skilled; semi-skilled and unskilled
8 Project Benefits
Other tangible benefits
9 Environmental Cost
Benefit Analysis
If recommended at the scoping stage
10 EMP Description of the administrative aspects that ensures proper
implementation of mitigative measures and their effectiveness
monitored, after approval of the EIA
Overall justification for implementation of the project
11 Summary &
Conclusion (This
will constitute the
summary of the EIA
Report) Explanation of how, adverse effects have been mitigated
12 Disclosure of
Consultants engaged
Names of the Consultants engaged with their brief resume
and nature of Consultancy rendered
Chairman
111
TOR for Common Effluent Treatment Plant (CETP)
ToR for EIA studies in respect of proposed CETP may include, but not limited to the following:
1 Executive summary of the project – giving a prima facie idea of the objectives of the proposal, use of
resources, justification, etc. In addition, it should provide a compilation of EIA report, including EMP
and the post-project monitoring plan in brief.
Project description:
2 Justification for selecting the proposed product and unit size.
3 Land requirement for the project including its break up for various purposes, its availability and
optimization.
4 Details of proposed layout clearly demarcating various units/industries within the plant.
5 Complete process flow diagram describing each unit, its processes and operations, along with
material and energy inputs and outputs (material and energy balance).
6 Details of the industries for which CETP facility is proposed including raw materials used and
products manufactured.
7 Expected quantity of wastewater from each industry and justification for selecting the proposed
capacity of the treatment plant/modules.
8 Characteristics of effluent and proposed segregation of streams, if any, from individual member
industries.
9 Details of mode of effluent collection system either by tankers and/or pipeline, etc., or proposed
trouble-shooting mechanism.
10 Monitoring protocol in case of collection of effluent through pipeline and/or tankers.
11 Details on physical, chemical and biological characteristics of the combined effluent and its
concentrations and the basis for the same.
12 Details of equalization tank at least for 24 hrs; and guard ponds for holding treated wastewater or
continuous monitoring facilities, if any.
13 Details of the proposed treatment schemes supported by the treatability studies including source
separation of streams for specific mode of collection and treatment either at individual industry or at
CETP (based on economic and operational ease considerations).
14 Built-in flexibility provisions to deal with quantitative and qualitative fluctuations.
Chairman
112
15 Organizational setup for collection of pretreated effluents, treatment and disposal of the treated
effluents, etc. and deployment of qualified/skilled man power.
16 Details of O&M for maximum utilization of the designed capacity of the plant.
17 Proposed monitoring protocol for stage-wise quality control w.r.t. various characteristics and
maintenance schedules followed for all rotating equipment including lubricating/oil fill, operational
chemicals and laboratory chemicals.
18 For any sensitive environmental parameters such as heavy metals, fluorides, etc., details on improved
material of construction of tanks and other equipments such as corrosion resistance, allowance, etc.
19 Details of power consumption and stand-by arrangements like the diesel generator (DG) sets, dual
fuel (gas and oil) for uninterrupted operation of treatment plant.
20 Protocol and mechanism to accept the effluent by tankers only during day time, including the
adequacy of the receiving/holding tanks, etc.
21 Impact of the project on local infrastructure of the study area such as road network, etc. If the study
area requires any additional infrastructure, details of the agency responsible for the same should be
included along with the time frame. Details of the permission from the competent Authority for
conveyor belt crossing the village road.
22 If the ultimate disposal is through a marine outfall then preliminary design of the outfall with
estimated initial dilution.
23 Details of laboratory, workshop, database, library, waste exchange centers, etc. in CETP.
24 Availability of the land for proposed treatment for ultimate capacity and to accommodate required
greenbelt development.
25 Details of the proposed methods of water conservation and recharging.
26 Management plan for solid/hazardous waste generation, storage, utilization and disposal.
27 Detailed plan of treated wastewater disposal/ reuse/ utilization / management.
28 Detailed plan of treated wastewater disposal/ reuse/ utilization / management.
29 In case of expansion of existing industries, remediation measures adopted to restore the
environmental quality if the groundwater, soil, crop, air, etc., are affected and a detailed compliance
to the prior environmental clearance/consent conditions.
30 Details on equity by the member industries/non refundable membership fee to ensure continuity of
membership and financial model, etc.
31 Any litigation pending against the project and /or any direction /order passed by any Court of Law
related to the environmental pollution and impacts in the last two years, if so, details thereof.
Description of the environment:
32 The study area shall be up to a distance of 5 km from the boundary of the proposed site and all along
the collection network/route map of tanker movement, treated wastewater carrying pipe-line and the
Chairman
113
receiving environment at the point of disposal.
33 Location of the project site and nearest habitats with distances from the project site to be demarcated
on a toposheet (1: 50000 scale).
34 Land-use based on satellite imagery including location specific sensitivities such as national parks /
wildlife sanctuary, villages, industries, etc. for the study area.
35 Demography details of all the villages falling within the study area.
36 Topography details of the project area.
37 The baseline data to be collected from the study area w.r.t. different components of environment viz.
air, noise, water, land, and biology and socio-economic.
38 Geological features and geo-hydrological status of the study area.
39 Surface water quality of nearby water sources and other surface drains.
40 Details on ground water quality.
41 Details on water quality parameters such as pH, Temperature (oC), Oil and grease, Cyanide* (as CN),
Ammoniacal nitrogen* (as N), Phenolic compounds* (as C6H5OH), Hexavalent Chromium*, Total
chromium*, Copper*, Nickel*, Lead*, Arsenic*, Mercury*, Cadmium*, Selenium*, Fluoride*,
Boron*, Radioactive materials*, Alfa emitters*, Hc/ml,Beta emitters*, Hc/ml*, etc. (* - as
applicable).
42 Details on existing ambient air quality and expected, stack and fugitive emissions for PM10, PM2.5,
SO2*, NOx*, VOCs*, carbon oxides (CO and CO2) etc., and evaluation of the adequacy of the
proposed pollution control devices to meet standards for point sources and to meet AAQ standards. (*
- As applicable)
43 The air quality contours may be plotted on a location map showing the location of project site,
habitation nearby, sensitive receptors, if any and wind roses.
44 Details on noise levels at sensitive/commercial receptors.
45 Site-specific micro-meteorological data including mixing height.
46 One season site-specific data excluding monsoon season.
47 Proposed baseline monitoring network for the consideration and approval of the Competent
Authority.
48 Ecological status (terrestrial and aquatic) of the study area such as habitat type and quality, species,
diversity, rarity, fragmentation, ecological linkage, age, abundance, etc.
If any incompatible land-use attributes fall within a 5 km radius of the project boundary, proponent
shall describe the sensitivity (distance, area and significance) and propose the additional points based
on significance for review and acceptance by the EAC/SEAC. Incompatible land-use attributes
include:
Public water supply areas from rivers/surface water bodies, from ground water
b. Scenic areas/tourism areas/hill resorts
49
c. Religious places, pilgrim centers that attract over 10 lakh pilgrims a year
Chairman
114
d. Protected tribal settlements (notified tribal areas where industrial activity is not permitted)
e. CRZ
f. Monuments of national significance, World Heritage Sites
g. Cyclone, Tsunami-prone areas (based on last 25 years)
h. Airport areas
i. Any other feature as specified by the State or local government and other features as locally
applicable, including prime agricultural lands, pastures, migratory corridors, etc.
If ecologically sensitive attributes fall within a 5 km radius of the project boundary, proponent shall
describe the sensitivity (distance, area and significance) and propose the additional points based on
significance for review and acceptance by the SEAC. Ecological sensitive attributes include:
a. National parks
b. Wild life sanctuaries, Game reserve
c. Tiger reserve/elephant reserve/turtle nesting ground
d. Mangrove area
e. Wetlands
f. Reserved and Protected forests, etc.
50
g. Any other closed/protected area under the Wild Life (Protection) Act, 1972, any other area
locally applicable
51 If the location falls in a valley, studies on specific issues connected to the natural resources
management.
52 Identification of CRZ area: A CRZ map duly authenticated by one of the authorized agencies
demarcating LTL(Low Tide Level), HTL (High Tide Level), CRZ area, location of the project and
associate facilities w.r.t. CRZ, coastal features such as mangroves, if any. The route of the pipeline,
etc., passing through CRZ, if any, should also be demarcated. Recommendations of the State Coastal
Management Authority for the activities to be taken up in the CRZ.
53 CRZ map in 1:10000 scale in general cases and in 1:5000 scale for specific observations.
54 Environmental parameters – Temperature, sea level pressure, wind speed, mean relative humidity,
visibility, salinity, density, rainfall, fog, frequency and intensity of cyclones, sediment transport,
seismic characteristics, fresh water influx.
55 Details on marine biological parameters – microbiological population, pathogenic bacteria, plankton
distribution, fish spawning grounds in the adjoining waters, commercial fisheries potential,
vegetation including inter tidal, flora and fauna in the marine, benthal quality assessment for
biological species and heavy metals and estuarine environment.
Anticipated environmental impacts and mitigation measures :
56 Anticipated generic environmental impacts due to this project may be evaluated for significance and
Chairman
115
based on corresponding likely impacts Valued Environmental Components (VECs) may be
identified. Baseline studies may be conducted for all the concerned VECs and likely impacts will
have to be assessed for their magnitude in order to identify mitigation measures.
57 Impact prediction tools used for the appropriate assessment of environmental impacts .
While identifying the likely impacts, also include the following for analysis of significance and
required mitigation measures:
a impacts due to transportation of raw materials and end products on the surrounding environment
b impacts on surface water, soil and groundwater
c impacts due to air pollution
d impacts due to odour pollution
e impacts due to noise
F impacts due to fugitive emissions
g impact on health of workers due to proposed project activities
58
h impact on the disposal mode-specific receiving environment
59 Proposed odour control measures
60 Action plan for the greenbelt development – species, width of plantations, planning schedule, etc., in
accordance to CPCB published guidelines.
61 In case of likely impact from the proposed project on the surrounding reserve forests, Plan for the
conservation of wild fauna in consultation with the State Forest Department.
62 Mitigation measures - for source control and treatment.
63 Details in case, if the effluent conveyance system uses pipe lines, details regarding minimum (one
day) storage tank with mixing facility to keep it in aerobic conditions at source industry and
mechanism to ensure compliance with prescribed standards at this storage tank.
64 Details regarding soil and groundwater impacts and regular monitoring protocols suggested for
ensuring no significant impacts, besides preventive measures.
65 Impacts due to laying of pipe lines for effluent collection and for the disposal of the
treated wastewaters.
66 Bathymetric studies need to be conducted and models shall be applied to predict the dispersion
patterns to determine the length of the outfall, if disposal is through a marine outfall.
67 Capital quantity of dredging material, disposal and its impact on aquatic life.
68 Details on fisheries study which are conducted w.r.t. benthos and marine organic
material and coastal fisheries.
69 Details of storm water collection network and utilization plan, etc.
70 Proposed measures for occupational safety and health of the workers.
Analysis of alternative resources and technologies:
Chairman
116
71 Comparison of alternate sites considered and the reasons for selecting the proposed site. Conformity
of the site with the prescribed guidelines in terms of CRZ, river, highways, railways, etc.
72 Drainage area and alterations, if any due to the project.
73 Details on improved technologies.
Environmental monitoring program:
74 Monitoring programme for pollution control at source.
75 Monitoring pollutants at receiving environment for the appropriate notified parameters – air quality,
groundwater, surface water, gas quality, etc. during operational phase of the project.
76 Specific programme to monitor safety and health protection of workers
77 Appropriate monitoring network has to be designed and proposed, to assess the possible residual
impacts on VECs.
78 Details of in-house monitoring capabilities and the recognized agencies if proposed for conducting
monitoring.
Additional studies:
79 Details on risk assessment and damage control during different phases of the project and proposed
safeguard measures.
80 Details on socio-economic development activities such as commercial property values, generation of
jobs, education, social conflicts, cultural status, accidents, etc.
81 Proposed plan to handle the socio-economic influence on the local community. The plan should
include quantitative dimension as far as possible.
82 Details on compensation package for the people affected by the project, considering the socio-
economic status of the area, homestead oustees, land oustees, and landless labourers.
83 Points identified in the public hearing and commitment of the project proponent to the same. Detailed
action plan addressing the issues raised, and the details of necessary allocation of funds.
Above points shall be adequately addressed in the EIA report at corresponding chapters, in addition
to the contents given in the reporting structure as below:
Sr. EIA Structure Contents
Purpose of the report
Identification of project & project proponent
1 Introduction
Brief description of nature, size, location of the project and its
importance to the country, region
Chairman
117
Scope of the study – details of regulatory scoping carried out
Condensed description of those aspects of the project (based on
project feasibility study), likely to cause environmental effects.
Details should be provided to give clear picture of the following:
Type of project
Need for the project
Location (maps showing general location, specific location,
project boundary & project site layout)
Size or magnitude of operation (incl. Associated activities
required by / for the project)
Proposed schedule for approval and implementation
Technology and process description
Project description including drawings showing project layout,
components of project etc. Schematic representations of
feasibility drawings which give information important for EIA
purpose
Description of mitigation measures incorporated into the project
to meet environmental standards, environmental operating
conditions, or other EIA requirements (as required by the scope)
2 Project Description
Assessment of New & untested technology for the risk of
technological failure
Study area, period, components & methodology
Establishment of baseline for VECs, as identified in the scope
3 Description of the
Environment
Base maps of all environmental components
Details of Investigated Environmental impacts due to project
location, possible accidents, project design, project construction,
regular operations, final decommissioning or rehabilitation of a
completed project
Measures for minimizing and / or offsetting adverse impacts
identified
Irreversible and irretrievable commitments of environmental
components
Assessment of significance of impacts (Criteria for determining
significance, Assigning significance)
4 Anticipated
Environmental
Impacts & Mitigation
Measures
Mitigation measures
5 Analysis of Incase, the scoping exercise results in need for alternatives:
Chairman
118
Description of each alternative
Summary of adverse impacts of each alternative
Alternatives
(Technology & Site)
Mitigation measures proposed for each alternative and selection
of alternative
6 Environmental
Monitoring Program
Technical aspects of monitoring the effectiveness of mitigation
measures (incl. measurement methodologies, frequency, location,
data analysis, reporting schedules, emergency procedures,
detailed budget & procurement schedules)
Public consultation
Risk assessment
7 Additional Studies
Social impact assessment, R&R action plans
Improvements in physical infrastructure
Improvements in social infrastructure
Employment potential –skilled; semi-skilled and unskilled
8 Project Benefits
Other tangible benefits
9 Environmental Cost
Benefit Analysis
If recommended at the scoping stage
10 EMP Description of the administrative aspects that ensures proper
implementation of mitigative measures and their effectiveness
monitored, after approval of the EIA
Overall justification for implementation of the project
11 Summary &
Conclusion (This
will constitute the
summary of the EIA
Report) Explanation of how, adverse effects have been mitigated
12 Disclosure of
Consultants engaged
Names of the Consultants engaged with their brief resume
and nature of Consultancy rendered
Chairman
119
TOR for Power Plants
ToR for EIA studies in respect of the Thermal Power Plants include, but not limited to the following:
1 Executive summary of the project – giving a prima facie idea of the objectives of the proposal, use of resources, justification, etc. In addition, it should provide a compilation of EIA report including EMP and post-project monitoring plan in brief.
Project description:
2 Justification for selecting the proposed unit size.
3 Land requirement for the project including its break up for various purposes, its availability and optimization.
4 Details of proposed layout clearly demarcating various units of the plant.
5 Complete process flow diagram describing each unit, its processes and operations, along with material and energy inputs & outputs (material and energy balance).
6 Details on requirement of raw materials, its source and storage at the plant.
7 Fuel analysis report (sulphur, ash content and mercury) including details of auxiliary fuel, if any.
Details like quantity, quality, storage etc.,
8 Quantity of fuel required its source and transportation, a confirmed fuel linkage/ copy of the MoU.
9 Source of water and its availability. Proof regarding availability of requisite quantity of water from the
competent authority.
10 Details on water balance including quantity of effluent generated, recycled & reused. Efforts to
minimize effluent discharge and to maintain quality of receiving water body.
11 Details of effluent treatment plant, inlet and treated water quality with specific efficiency of each
treatment unit in reduction in respect of all concerned/regulated environmental parameters.
12 Location of intake and outfall points (with coordinates) based on modeling studies. Details of modeling
and the results obtained. It may be kept in view that the intake and outfall points are away from the
mangroves.
13 Examine the feasibility of zero discharge. In case of any proposed discharge, its quantity, quality and
point of discharge, users downstream, etc.
14 Explore the possibility of cooling towers installation. Details regarding the same.
15 Details regarding fly ash utilization as per new notification
16 Detailed plan of ash utilization / management.
17 Details of evacuation of ash.
Chairman
120
18 Details regarding ash pond impermeability and whether it would be lined, if so details of the lining etc.
19 Details of desalination plant and disposal of sludge.
20 Details of proposed source-specific pollution control schemes and equipments to meet the national
standards.
21 Details of the proposed methods of water conservation and recharging.
22 Management plan for solid/hazardous waste generation, storage, utilization and disposal.
23 Details regarding infrastructure facilities such as sanitation, fuel storage, restroom, etc. to the workers
during construction and operation phase.
24 In case of expansion of existing industries, remediation measures adopted to restore the environmental
quality if the groundwater, soil, crop, air, etc., are affected and a detailed compliance to the prior
environmental clearance/consent conditions.
25 Any litigation pending against the project and /or any direction /order passed by any Court of Law
related to the environmental pollution and impacts in the last two years, if so, details thereof.
Description of the Environment:
26 The study area shall be up to a distance of 10 km from the boundary of project area for air quality
considerations in view of impacts occurring at distant locations once emitted from a tall stack
particularly in view of absence of source control for SO2 in tail gases whereas for impacts on other
components (such as water, soil quality and noise monitoring, etc.) the study area may be up to a
distance of 5 Km.
27 Location of the project site and nearest habitats with distances from the project site to be demarcated on
a toposheet (1: 50000 scale).
28 Landuse based on satellite imagery including location specific sensitivities such as national parks /
wildlife sanctuary, villages, industries, etc. for the study area.
29 Demography details of all the villages falling within the study area.
30 Topography details of the project area.
31 The baseline data to be collected from the study area w.r.t. different components of environment viz.
air, noise, water, land, and biology and socio-economic.
32 Geological features and geo-hydrological status of the study area.
33 Surface water quality of nearby water sources and other surface drains.
34 Details on ground water quality.
35 Details on water quality parameters such as Temperature, pH*, TOC*, Colour*, TDS*, BOD*, COD*,
N (total)*, Mineral oils*, Free chlorine* , NH3*, Fish*, toxicity*, Sb*, PAH Metals* (Co, Mn, Tl, V,
Sn, Cd, Cr, Ni, Cu, Hg, Pb, Zn , etc.) CN*, S*, SO3*, SO4*, EOX*, Phenol*, PCDD/PCDF*, P (total)
Chairman
121
TSS*, Cl-*, FAs* , BTEX*, etc. (* - as applicable)
36 Details on existing ambient air quality and expected, stack and fugitive emissions for PM10, PM 2.5,
SO2*, NOx*, O3*, VOCs*, Hg*, suspended particulates* etc., and evaluation of the adequacy of the
proposed pollution control devices to meet standards for point sources and to meet AAQ standards. (*
- As applicable)
37 The air quality contours may be plotted on a location map showing the location of project site,
habitation nearby, sensitive receptors, if any and wind roses.
38 Details on noise levels at sensitive/commercial receptors.
39 Site-specific micro-meteorological data including mixing height.
40 One season site-specific data excluding monsoon season.
41 Proposed baseline monitoring network for the consideration and approval of the Competent Authority.
42 Ecological status (terrestrial and aquatic) of the study area such as habitat type and quality, species,
diversity, rarity, fragmentation, ecological linkage, age, abundance, etc.
If any incompatible land use attributes fall within the study area, proponent shall describe the sensitivity (distance, area and significance) and propose the additional points based on significance for review and acceptance by the EAC/SEAC. Incompatible land use attributes include:
A Public water supply areas from rivers/surface water bodies, from ground water
B Scenic areas/tourism areas/hill resorts
C Religious places, pilgrim centers that attract over 10 lakh pilgrims a year
D Protected tribal settlements (notified tribal areas where industrial activity is not permitted)
E Monuments of national significance, World Heritage Sites
F Cyclone, Tsunami prone areas (based on last 25 years)
G Airport areas
43
H Any other feature as specified by the State or local government and other features as locally applicable, including prime agricultural lands, pastures, migratory corridors, etc
If ecologically sensitive attributes fall within the study area, proponent shall describe the sensitivity (distance, area and significance) and propose the additional points based on significance for review and acceptance by the SEAC. Ecological sensitive attributes include:
A National parks
B Wild life sanctuaries Game reserve
C Tiger reserve/elephant reserve/turtle nesting ground
D Mangrove area
44
E Wetlands
Chairman
122
F Reserved and protected forests, etc.
G Any other closed/protected area under the Wild Life (Protection) Act, 1972, any other area locally applicable
45 If the location falls in Valley, specific issues connected to the natural resources management shall be studied and presented.
If the location falls in CRZ area: A CRZ map duly authenticated by one of the authorized agencies demarcating LTL, HTL, CRZ area, location of the project and associate facilities w.r.t. CRZ, coastal features such as mangroves, if any.
a Provide the CRZ map in 1:10000 scale in general cases and in 1:5000 scale for specific observations.
b Proposed site for disposal of dredged material and environmental quality at the point of disposal/impact areas.
46
c Fisheries study should be done w.r.t. Benthos and Marine organic material and coastal fisheries.
Anticipated environmental impacts and Mitigation Measures:
47 Anticipated generic environmental impacts due to this project, which may be evaluated for significance and based on corresponding likely impacts VECs may be identified. Baseline studies may be conducted for all the concerned VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.
48 Tools used for the assessment of environmental impacts.
49 Impact on drainage of the area and the surroundings.
50 Impact of the project on the AAQ of the area. Details of the model used and the input data used for modeling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
51 Impact of the project on local infrastructure of the study area such as road network, etc. In case if the
study area requires any additional infrastructure, details of the agency responsible for the same should
be included along with the time frame. Details of the permission from Competent Authority for
conveyor belt crossing the village road.
52 Impact of the activities to be taken up in the CRZ area including jetty and desalination plant etc.,
should be integrated into the EIA report; however, action should be taken to obtain separate clearance
from the competent authority as may be applicable to such activities.
53 Details of rainwater harvesting and its proposed usage in the plant.
54 Details regarding infrastructure facilities such as sanitation, fuel, restroom, etc., to be provided to the
workers during construction as well as to the casual workers including truck drivers during the
operational phase.
Chairman
123
55 Details of flora and fauna. Conservation plan in case of any scheduled fauna.
56 Proposed measures for occupational safety and health of the workers.
57 Oil spill control planning.
58 Off-shore coastal air dispersion models shall be applied.
59 Capital quantity of dredging material, disposal and its impact on aquatic life.
60 Fisheries study should be done with respect to Benthos and Marine organic material and coastal
fisheries.
61 Proposed odour control measures.
62 Action plan for the greenbelt development – species, width of plantations, planning schedule etc. in
accordance to CPCB published guidelines.
63 In case of likely impact from the proposed project on the surrounding reserve forests, Plan for the
conservation of wild fauna in consultation with the State Forest Department.
64 Identifying the mitigation measures, source control and treatment.
Analysis of alternative resources and technologies
65 Comparison of alternate sites considered and the reasons for selecting the proposed site. Conformity of
the site with the prescribed guidelines in terms of Coastal Regulatory Zone (CRZ), river, highways,
railways etc.
66 Details of alternative sources of energy such as photovoltaic cells use in the plant for various applications.
67 Details on improved technologies.
Environmental monitoring program :
68 Monitoring of pollution control at source
69 Monitoring of pollutants at receiving environment for all the appropriate notified parameters – air quality, groundwater, surface water, etc., during operational phase of the project.
70 Specific programme to monitor occupational safety and health protection of workers.
71 Appropriate monitoring network has to be designed and proposed, to assess the
possible residual impacts on VECs.
72 Details of in-house monitoring capabilities and the recognized agencies if proposed for conducting monitoring.
Additional studies :
73 Details on risk assessment and damage control during different phases of the project and proposed
safeguard measures.
74 Details on socio-economic development activities such as commercial property values, generation of
Chairman
124
jobs, education, social conflicts, cultural status, accidents, etc.
75 Proposed plan to handle the socio-economic influence on the local community. The plan should include
quantitative dimension as far as possible.
76 Details on compensation package for the people affected by the project, considering the socio-
economic status of the area, homestead oustees, land oustees, and landless labourers.
77 Points identified in the public hearing and commitment of the project proponent to the same. Detailed
action plan addressing the issues raised, and the details of necessary allocation of funds.
Environmental management plan:
78 Administrative and technical organizational structure to ensure proposed post-project monitoring programme for approved mitigation measures.
79 EMP devised to mitigate the adverse impacts of the project should be provided along with item-wise cost of its implementation (Capital and recurring costs).
80 Allocation of resources and responsibilities for plan implementation.
81 Details of the emergency preparedness plan and on-site and off-site disaster management plan.
Above points shall be adequately addressed in the EIA report in addition to the contents given in the reporting structure as below:
Sr. EIA Structure Contents
1 Introduction 1. Purpose of the report
2. Identification of project & project proponent
3. Brief description of nature, size, location of the project and its
importance to the country, region
4. Scope of the study – details of regulatory scoping carried out (As per
Terms of Reference)
2 Project
Description
Condensed description of those aspects of the project (based on project
feasibility study), likely to cause environmental effects. Details should be
provided to give clear picture of the following:
1. Type of project
2. Need for the project
3. Location (maps showing general location, specific location, project
boundary & project site layout)
4. Size or magnitude of operation (incl. Associated activities required by
or for the project)
5. Proposed schedule for approval and implementation
6. Technology and process description
7. Project description including drawings showing project layout,
Chairman
125
components of project etc. Schematic representations of the feasibility
drawings which give information important for EIA purpose
8. Description of mitigation measures incorporated into the project to meet
environmental standards, environmental operating conditions, or other
EIA requirements (as required by the scope)
9. Assessment of new & untested technology for the risk of technological
failure
3 Description of
the Environment
1. Study area, period, components & methodology
2. Establishment of baseline for VECs, as identified in the scope
3. Base maps of all environmental components
4 Anticipated
Environmental
Impacts &
Mitigation
Measures
1. Details of Investigated Environmental impacts due to project location,
possible accidents, project design, project construction, regular
operations, final decommissioning or rehabilitation of a completed
project
2. Measures for minimizing and / or offsetting adverse impacts identified
3. Irreversible and irretrievable commitments of environmental
components
4. Assessment of significance of impacts (Criteria for determining
significance, Assigning significance)
5. Mitigation measures
5 Analysis of
Alternatives
(Technology &
Site)
1. Incase, the scoping exercise results in need for alternatives:
2. Description of each alternative
3. Summary of adverse impacts of each alternative
4. Mitigation measures proposed for each alternative and selection of
alternative
6 Environmental
Monitoring
Program
1. Technical aspects of monitoring the effectiveness of mitigation
measures (incl. measurement methodologies, frequency, location, data
analysis, reporting schedules, emergency procedures, detailed budget &
procurement schedules)
7 Additional
Studies
1. Public consultation
2. Risk assessment
3. Social impact assessment, R&R action plans
8 Project Benefits 1. Improvements in physical infrastructure
2. Improvements in social infrastructure
3. Employment potential –skilled; semi-skilled and unskilled
4. Other tangible benefits
9 Environmental 1. If recommended at the scoping stage
Chairman
126
Cost Benefit
Analysis
10 EMP 1. Description of the administrative aspects that ensures proper
implementation of mitigation measures and their effectiveness
monitored, after approval of the EIA.
11 Summary &
Conclusion (This
will constitute
the summary of
the EIA Report)
1. Overall justification for implementation of the project
2. Explanation of how, adverse effects have been mitigated
12 Disclosure of
Consultants
engaged
1. Names of the Consultants engaged with their brief resume and nature of
Consultancy rendered
Chairman
127
TOR for Metallurgical Industry
ToR for EIA studies in respect of metallurgical industry (ferrous and non-ferrous) may include, but not limited to the following:
1 Executive summary of the project – giving a prima facie idea of the objectives of the proposal, use of resources, justification, etc. In addition, it should provide a compilation of EIA report including EMP and post-project monitoring plan in brief.
Project description
2 Justification for selecting the proposed unit size.
3 Land requirement for the project including its break up for various purposes, its availability and optimization.
4 Details of proposed layout clearly demarcating various units of the plant.
5 Complete process flow diagram describing each unit, its processes and operations, along with material and energy inputs & outputs (material and energy balance).
Iron and steel :
a Details of Iron and steel making plant describing details on design and manufacturing process for all the units.
b Details on blast furnace/ open hearth furnace/ basic oxygen furnace/ladle refining, casting and rolling plants etc.
c Details on installation/activation of opacity meters with recording with proper calibration system
d Details on toxic metals including mercury, arsenic and fluoride emissions
6
e Details on stack height requirement for integrated steel
Details on ash disposal and management -Non ferrous metal :
a Complete process flow diagram describing production of lead/zinc/copper/aluminium, etc
b Raw materials substitution or elimination
c Details on smelting, thermal refining, melting, slag fuming, and Waelz kiln operation
d Details on Holding and de-gassing of molten metal from primary and secondary aluminum, materials pre-treatment, and from melting and smelting of secondary aluminum
e Details on solvent recycling, and
7
f Details on precious metals recovery
Chairman
128
8 Details of proposed source-specific pollution control schemes and equipments to meet the national standards.
9 Details on requirement of raw materials, its source and storage at the plant. Also, an agreement for the supply of the iron ore for the proposed plant.
10 Details on requirement of energy and water requirement along with its source and authorization from the concerned department.
11 Details on water balance including quantity of effluent generated, recycled & reused. Efforts to minimize effluent discharge and to maintain quality of receiving water body.
12 Details of effluent treatment plant, inlet and treated water quality with specific efficiency of each treatment unit in reduction in respect of all concerned/regulated environmental parameters.
13 Details of the proposed methods of water conservation, recharging.
14 Water drawl approval from concerned authorities.
15 Details on use of high calorific hazardous wastes in kiln and commitment regarding use of hazardous waste.
16 Details on composition, generation and utilization of waste/fuel gases from coke oven plant and their utilization.
17 Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly char and fly ash.
18 Details on toxic metal content in the waste material and its composition and end use (particularly of slag).
19 Details regarding infrastructure facilities such as sanitation, fuel, restroom, etc., to be provided to the workers during construction as well as to the casual workers including truck drivers during operation phase.
20 In case of expansion of existing industries, remediation measures adopted to restore the environmental quality if the groundwater, soil, crop, air, etc., are affected and a detailed compliance to the prior environmental clearance/consent conditions.
21 Any litigation pending against the project and /or any direction /order passed by any Court of Law against the project, if so, details thereof.
Description of the environment
22 The study area shall be up to a distance of 10 km from the boundary of the proposed project site.
23 Location of the project site, and nearest habitats with distances from the site to be demarcated on a toposheet (1: 50000 scale).
24 Landuse of study area should include data about the residential/ institutional/nearest village/ township/ locality/ housing society, industries, etc., based on the satellite imagery.
Chairman
129
25 Demography details of all the villages falling within the study area
26 Topography of the area clearly indicating the presence of pits deeper than one meter, if any. If these pits require to be filled in, details of filling material to be used, quantity required, its source, mode of transport, etc.
27 The baseline data to be collected from the study area w.r.t. different components of environment viz. air, noise, water, land, and biology and socio-economic.
28 Geological features and Geo-hydrological status of the study area.
29 Surface water quality of nearby water sources and other surface drains.
30 The location map drawn on Survey of India topo sheets with satellite imageries as regards its interference with natural drainage paths.
31 Details on ground water quality near solid waste dump zone.
32 Details on water quality for parameters pH, temperature, COD, Biochemical oxygen demand (27oC, 3 days), TDS*, Suspended solids*, Phenolic compounds (As C6H5OH)*, Cyanides (As CN)*, Oil & grease*, Ammonical nitrogen (As N)*, chlorides*, sulphides*, etc. (* - As applicable)
33 Relevant ambient air quality parameters for monitoring include following:
a Iron & Steel: SO2, NOx, PM10, PM 2.5, O3, Pb, CO, NH3, C6H6, BaP.
b Aluminum: SO2, NOx, PM10, PM 2.5, O3, Pb, CO, NH3, fluoride
c Lead & Zinc: SO2, NOx, PM10, PM 2.5, O3, Pb, CO, NH3, As, Ni.
d Copper: SO2, NOx, PM10, PM 2.5, O3, Pb, CO, As, Ni, Acid mist
e Coke ovens: SO2, NOx, PM10, PM 2.5, O3, Pb, CO, C6H6, BaP.
f Sponge Iron: SO2, NOx, PM10, PM 2.5, O3, Pb, CO.
g Secondary non-ferrous: SO2, NOx, PM10, PM 2.5, O3, Pb, CO, As, Ni, Acid mist.
34 Details on existing ambient air quality and expected, stack and fugitive emissions may be monitored for SPM*, PM10*, PM2.5*, SO2*, NOx*, HC*, CO*, acid mist*, VOC* and Benzopyrenes* (at ground level and at battery top), etc. and evaluation of the adequacy of the proposed pollution control devices to meet gaseous emissions and Dust fall data with heavy metal analysis. (* - as applicable)
35 The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any and wind roses.
36 Proposed pollution control devices for the controlling the releasing of SPM to 50 mg/m3
37 One season site-specific data excluding monsoon season.
38 Site-specific micro-meteorological data including mixing height.
39 Noise levels at sensitive/commercial receptor.
40 Proposed baseline monitoring network for the consideration and approval of the Competent Authority.
Chairman
130
41 Ecological status (terrestrial and aquatic) of the study area such as habitat type and quality, species, diversity, rarity, fragmentation, ecological linkage, age, abundance, etc.
If any incompatible land use attributes fall within the study area, proponent shall describe the sensitivity (distance, area and significance) and propose the additional points based on significance for review and acceptance by the EAC/SEAC. Incompatible land use attributes include:
a Public water supply areas from rivers/surface water bodies, from ground water
b Scenic areas/tourism areas/hill resorts
c Religious places, pilgrim centers that attract over 10 lakh pilgrims a year
d Protected tribal settlements (notified tribal areas where industrial activity is not permitted)
e Monuments of national significance, World Heritage Sites
f Cyclone, Tsunami prone areas (based on last 25 years)
g Airport areas
42
h Any other feature as specified by the State or local government and other features as locally applicable, including prime agricultural lands, pastures, migratory corridors, etc
If ecologically sensitive attributes fall within the study area, proponent shall describe the sensitivity (distance, area and significance) and propose the additional points based on significance for review and acceptance by the EAC/ SEAC. Ecological sensitive attributes include:
a National parks
b Wild life sanctuaries Game reserve
c Tiger reserve/elephant reserve/turtle nesting ground
d Mangrove area
e Wetlands
f Reserved and protected forests
g Any other closed/protected area under the Wild Life (Protection) Act, 1972,
43
h Any other eco-sensitive areas
44 If the location falls in Valley, specific issues connected to the natural resources management shall be studied and presented.
If the location falls in CRZ area: A CRZ map duly authenticated by one of the authorized agencies demarcating LTL, HTL, CRZ area, location of the project and associate facilities w.r.t. CRZ, coastal features such as mangroves, if any.
a Provide the CRZ map in 1:10000 scale in general cases and in 1:5000 scale for specific observations.
45
b Proposed site for disposal of dredged material and environmental quality at the point of
Chairman
131
disposal/impact areas.
c Fisheries study should be done w.r.t. Benthos and Marine organic material and coastal fisheries.
Anticipated environmental impacts and mitigation measures
46 Anticipated generic environmental impacts due to this project, which may be evaluated for significance and based on corresponding likely impacts VECs may be identified. Baseline studies may be conducted for all the concerned VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.
47 Tools used for the assessment of environmental impacts.
48 Air pollution control system to be installed should be elaborated upon to control SPM emissions within 50 mg/Nm3 and leakages from coke oven as per the Notified standards.
49 Sulphur removal from CO gas containing H2S as per the notified standards.
50 Proposed odour control measures
51 Dry quenching of coke/modified wet quenching of coke as per the notified standards.
52 Pushing side emission control as per the notified standards.
53 Impact of the transport of the raw materials and end products on the surrounding environment including agricultural land.
54 Unit-wise air pollution control measures proposed for the control of gaseous emissions from all the sources should be incorporated.
55 Impact of the project on the AAQ of the area. Details of the model used and the input data used for modeling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.
56 Determination of atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack/fugitive emission based on site-specific meteorological features. Air quality modeling for specific pollutants needs to be done.
57 Proper and full utilization of coke oven gases in BOF/BF/Coke oven gas plant and no discharge of gases into the air should be included.
58 Note on treatment of wastewater from different plants, recycle and reuse for different purposes.
59 Efforts made to minimize use of groundwater and impact on the groundwater, if any due the proposed project.
60 Impact of noise and measures taken for its control.
61 Char handling and management
62 Hazard identification taking resources to hazardous indices, inventory analysis, natural hazardous probability, etc., Consequent analysis of failure and accidents resulting in release of hazardous substances.
Chairman
132
63 Impact of toxic metal content in the waste material and its mitigating measures
64 Impact of storm water and mitigating measures.
65 Surface as well as roof top rainwater harvesting and groundwater recharge should be included.
66 Action plan for the greenbelt development – species, width of plantations, planning schedule etc. in accordance to CPCB published guidelines.
67 Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly tar and sludge from by product plant, dust from APCS etc.
68 Assessment report of the impact of transport of raw material and finished product on the transport system.
69 Proposed measures for occupational safety and health of the workers. Indian Factories Act must be referred for values of work zone concentration and other provisions.
70 Identifying the mitigation measures, source control and treatment.
Analysis of alternative resources and technologies:
71 Comparison of alternate sites considered and the reasons for selecting the proposed site. Conformity of the site with the prescribed guidelines in terms of CRZ, river, highways, railways, etc
72 Details of clean technologies or any other improved technologies.
Environmental monitoring program :
73 Monitoring of pollution control at source
74 Monitoring of pollutants at receiving environment for all the appropriate notified parameters – air quality, groundwater, surface water, etc., during operational phase of the project.
75 Specific programme to monitor occupational safety and health protection of workers.
76 Appropriate monitoring network has to be designed and proposed, to assess the possible residual impacts.
77 Monitoring of carbon foot print
78 Details of in-house monitoring capabilities and the recognized agencies if proposed for conducting monitoring.
Additional studies :
79 Impact of the project on local infrastructure of the area such as road network and whether any additional infrastructure would need to be constructed and the agency responsible for the same with timeframe.
Chairman
133
80 Details on risk assessment and damage control during different phases of the project and proposed safeguard measures.
81 Details on socio-economic development activities such as commercial property values, generation of jobs, education, social conflicts, cultural status, accidents, etc.
82 Proposed plan to handle the socio-economic influence on the local community. The plan should include quantitative dimension as far as possible.
83 Details on compensation package for the people affected by the project, considering the socio-economic status of the area, homestead oustees, land oustees, and landless labourers.
84 Points identified in the public hearing and commitment of the project proponent to the same. Detailed action plan addressing the issues raised, and the details of necessary allocation of funds.
85 Details on plan for corporate social responsibility including the villages, population spread, SC/ST/backward communities, upgradation of existing schools, establishing new schools with facilities (such as laboratories, toilets, etc.), link roads, community halls, primary health facilities, health camps, etc.
Environmental management plan:
86 Administrative and technical organizational structure to ensure proposed post-project monitoring programme for approved mitigation measures.
87 EMP devised to mitigate the adverse impacts of the project should be provided along with item-wise cost of its implementation (Capital and recurring costs).
88 Mitigation measures and EMP for construction work camps and slums formed during construction and operation including other induced developments
89 Allocation of resources and responsibilities for plan implementation.
90 Details of the emergency preparedness plan and on-site and off-site disaster management plan.
Above points shall be adequately addressed in the EIA report in addition to the contents given in the reporting structure as below:
Sr. EIA Structure Contents
1 Introduction 1. Purpose of the report
2. Identification of project & project proponent
3. Brief description of nature, size, location of the project and its
importance to the country, region
4. Scope of the study – details of regulatory scoping carried out (As per
Terms of Reference)
2 Project Condensed description of those aspects of the project (based on project
Chairman
134
Description feasibility study), likely to cause environmental effects. Details should be
provided to give clear picture of the following:
1. Type of project
2. Need for the project
3. Location (maps showing general location, specific location, project
boundary & project site layout)
4. Size or magnitude of operation (incl. Associated activities required by
or for the project)
5. Proposed schedule for approval and implementation
6. Technology and process description
7. Project description including drawings showing project layout,
components of project etc. Schematic representations of the feasibility
drawings which give information important for EIA purpose
8. Description of mitigation measures incorporated into the project to meet
environmental standards, environmental operating conditions, or other EIA
requirements (as required by the scope)
9. Assessment of new & untested technology for the risk of technological
failure
3 Description of
the Environment
1. Study area, period, components & methodology
2. Establishment of baseline for VECs, as identified in the scope
3. Base maps of all environmental components
4 Anticipated
Environmental
Impacts &
Mitigation
Measures
1. Details of Investigated Environmental impacts due to project location,
possible accidents, project design, project construction, regular operations,
final decommissioning or rehabilitation of a completed project
2. Measures for minimizing and / or offsetting adverse impacts identified
3. Irreversible and irretrievable commitments of environmental components
4. Assessment of significance of impacts (Criteria for determining
significance, Assigning significance)
5. Mitigation measures
5 Analysis of
Alternatives
(Technology &
1. Incase, the scoping exercise results in need for alternatives:
2. Description of each alternative
3. Summary of adverse impacts of each alternative
Chairman
135
Site) 4. Mitigation measures proposed for each alternative and selection of
alternative
6 Environmental
Monitoring
Program
Technical aspects of monitoring the effectiveness of mitigation measures (incl.
measurement methodologies, frequency, location, data analysis, reporting
schedules, emergency procedures, detailed budget & procurement schedules)
7 Additional
Studies
1. Public consultation
2. Risk assessment
3. Social impact assessment, R&R action plans
8 Project Benefits 1. Improvements in physical infrastructure
2. Improvements in social infrastructure
3. Employment potential –skilled; semi-skilled and unskilled
4. Other tangible benefits
9 Environmental
Cost Benefit
Analysis
If recommended at the scoping stage
10 EMP Description of the administrative aspects that ensures proper implementation of
mitigation measures and their effectiveness monitored, after approval of the
EIA.
11 Summary &
Conclusion (This
will constitute
the summary of
the EIA Report)
1. Overall justification for implementation of the project
2. Explanation of how, adverse effects have been mitigated
12 Disclosure of
Consultants
engaged
Names of the Consultants engaged with their brief resume and nature of
Consultancy rendered
Chairman
136
TOR for Industrial Estates (Pharma SEZ)
ToR for EIA studies in respect of proposed Industrial Estates may include, but not limited to the
following:
1 Executive summary of the project – giving a prima facie idea of the objectives of the proposal, use
of resources, justification, etc. In addition, it should provide a compilation of EIA report including
EMP and post-project monitoring plan in brief.
Project description:
2 Details of the industries, for which the estate is being planned and their proposed capacities of
installation, if available. In the absence of complete details, indicate the type of industries and
capacity being considered.
3 Land requirement for the project including the peripheral greenbelt inside the boundary.
4 Justification for selecting the proposed size of the IEs.
5 Details on strategy being followed for development of IE.
6 Layout map of estate indicating processing zones, admin area, roads, plots, green belt, common
utilities area, etc., shall be shown along with contour map. Landscape plan including open spaces
may be described.
7 Classify the proposed industries based on their pollution potential to the extent possible i.e., A1 to
A4 categories for air pollution and W1 to W4 categories for water pollution - CPCB Guidance may
be referred for classification.
8 Backward and forward linkages of the IEs (availability of input resources and markets for the
products / by-products and anticipated benefits for the regional development).
9 Details of Infrastructure Development within the IE and in the region.
10 Details on known industrial activity-specific proposed processes, resource consumption and rejects
assessment.
11 Details on estimated quantity of fuel required, fuel type, nature, source and transportation.
12 Details on estimated water balance taking into account conservation measures, reuse and recycling
of treated effluents.
13 Individual and/or common facilities for waste collection, treatment, recycling and disposal (all
effluent, emission and refuse including MSW, and hazardous wastes)
14 Commitment from the concerned authorities regarding availability of power, water and sewerage
network.
15 Details of Solid Waste management including arrangements for hazardous waste management and
e-waste.
16 Details on provisions made for safety in storage of materials, products and wastes.
17 Details on use of local building materials. The provisions of fly ash Notification should be kept in
view.
Chairman
137
18 Detailed plan of treated water disposal, reuse and utilization/management.
19 In case of site leveling involving quarrying, details thereof.
20 Any litigation pending against the project and /or any direction /order passed by any Court of Law
related to the environmental pollution and impacts in the last two years, if so, details thereof.
Description of the environment:
21 The project study area for EIA studies shall be up to a distance of 10 km from the boundary of the
proposed IE.
22 Location of the project site and nearest habitats with distances from the project site to be demarcated
on a toposheet (1: 50000 scale).
23 Landuse based on satellite imagery including location specific sensitivities such as national parks /
wildlife sanctuary, villages, industries, etc. for the study area.
24 Demography details of all the villages falling within the study area.
25 Topography details of the project area.
26 Anticipated pollution loads from each of the known composition of industrial units. Cumulative
wastewater quantity and pollution load, point source–specific details for air pollutants and their
loads, total solid/hazardous waste generation etc.
27 Details of rainwater harvesting and how it will be used in the IE & outfall.
28 The baseline data to be collected from the study area w.r.t. different components of environment viz.
air, noise, water, land, and biology and socio-economic.
29 Identification of existing potential sources of pollution in the study area.
30 Present and projected population; present and proposed land use; planned development activities,
issues relating to squatting and relocation, community structure, employment, distribution of
income, goods and services; recreation; public health and safety; cultural peculiarities, aspirations
and attitudes shall be explored in study.
31 Details regarding availability of social infrastructure and future projections, details of facilities such
as sanitation, fuel, restroom etc. to be provided to the labour force during construction as well as to
the casual workers including truck drivers during operation phase.
32 Detailed study of the hydrological and geo-hydrological conditions of the project area including a
contour plan indicating slopes and showing drainage pattern and outfall.
33 Information regarding surface hydrology and water regime and impact of the same, if any due to the
project.
34 Examine soil characteristics, topography, rainfall pattern and soil erosion.
35 Details on surface water quality of nearby water sources and other surface drains.
36 Details of groundwater quality in and around the IE.
37 Examine water quality with reference to Persistent Organic Pollutants, if relevant.
38 Details on water quality for parameters such as pH, Temperature (0C), Oil and grease*, Cyanide* (as
CN), Ammoniacal nitrogen* (as N), Phenolic compounds* (as C6H5OH), Hexavalent Chromium*,
Total chromium*, Copper*, Nickel* , Lead*, Arsenic*, Mercury*, Cadmium*, Selenium*,
Fluoride*, Boron*, Radioactive Materials*, Alfa emitters*, Hc/ml*, Beta emitters*, Hc/ml*, etc. (* -
As applicable). These parameters to be determined depend on the type of industries coming in
industrial estates.
39 Details on existing ambient air quality and expected, stack and fugitive emissions for PM10, PM
Chairman
138
2.5, SO2*, NOx*, O3, suspended particulates, VOC, Mercury, etc., and evaluation of the adequacy of
the proposed pollution control devices to meet standards for point sources and to meet AAQ
standards. (* - As applicable and these parameters to be determined depends on the type of
industries coming in industrial estates)
40 The air quality contours may be plotted on a location map showing the location of project site,
habitation nearby, sensitive receptors, if any and wind roses.
41 Mathematical modeling for calculating the dispersion of air pollutants and ground level
concentration along with emissions from boilers
42 Details on noise levels at sensitive/commercial receptors.
43 Site-specific meteorological data including mixing heights and secondary data for future predictions.
44 One season site-specific data excluding monsoon season.
45 Proposed baseline monitoring network for the consideration and approval of the Competent
Authority.
46 Fuel analysis to be provided (sulphur, ash content and mercury). Details of auxiliary fuel, if any
including its quantity, quality, storage, etc., should also be given.
47 Examine entry/exit of the project including the crossings from the highway and provision of service
roads on the basis of traffic density studies and analysis.
48 Climatic conditions of the study area shall be monitored for hourly wind speed, wind
direction, relative humidity, ambient dry and wet bulb temperatures and precipitation.
49 Ecological status (terrestrial and aquatic) of the study area such as habitat type and quality, species,
diversity, rarity, fragmentation, ecological linkage, age, abundance, etc.
If ecologically sensitive attributes fall within the study area, proponent shall describe the sensitivity
(distance, area and significance) and propose the additional points based on significance for review
and acceptance by the SEAC. Ecological sensitive attributes include:
a. National parks
b. Wild life sanctuaries Game reserve
c. Tiger reserve/elephant reserve/turtle nesting ground
d. Mangrove area
e. Wetlands
f. Reserved and Protected forests, etc.
50
g. Any other closed/protected area under the Wild Life (Protection) Act, 1972, any other area
locally applicable
If any incompatible land use attributes fall within the study area, proponent shall describe the
sensitivity (distance, area and significance) and propose the additional points based on significance
for review and acceptance by the SEAC. Incompatible land use attributes include:
a. Public water supply areas from rivers/surface water bodies, from ground water
b. Scenic areas/tourism areas/hill resorts
c. Religious places, pilgrim centers that attract over 10 lakh pilgrims a year
d. Protected tribal settlements (notified tribal areas where industrial activity is not permitted)
e. Monuments of national significance, World Heritage Sites
f. Cyclone, Tsunami prone areas (based on last 25 years);
51
g. Airport areas
Chairman
139
h. Any other feature as specified by the State or local government and other features as locally
applicable, including prime agricultural lands, pastures, migratory corridors, etc.
52 If the location falls in Valley, specific issues connected to the natural resources management shall be
studied and presented.
If the location falls in CRZ area: A CRZ map duly authenticated by one of the authorized agencies
demarcating LTL, HTL, CRZ area, location of the project and associate facilities w.r.t. CRZ, coastal
features such as mangroves, if any.
a. Provide the CRZ map in 1:10000 scale in general cases and in 1:5000 scale for specific
observations.
b. Proposed site for disposal of dredged material and environmental quality at the point of
disposal/impact areas.
53
c. Fisheries study should be done w.r.t. Benthos and Marine organic material and coastal fisheries.
Anticipated environmental impacts and mitigation measures :
54 Anticipated generic environmental impacts due to this project may be evaluated for significance and
based on corresponding likely impacts valued environmental components (VECs) may be identified.
Baseline studies may be conducted for all the concerned VECs and likely impacts will have to be
assessed for their magnitude in order to identify mitigation measures.
55 Tools used for the appropriate assessment of environmental impacts.
While identifying the likely impacts, also include the following for analysis of significance and
required mitigation measures:
a. impacts due to transportation of raw materials and end products on the surrounding environment
b. impacts on surface water, soil, groundwater, drainage due to project activities
c. impacts due to air pollution
d. impacts due to odour pollution
e. impacts due to noise
f. impacts due to fugitive emissions
56
g. impact on health of workers due to proposed project activities
57 Proposed odour control measures.
58 Examine in detail the proposed site with reference to possible impact of infrastructure covering
water supply, pipelines, roads, storm water drainage, sewerage, power, temporary waste storage
facilities, treated wastewater disposal (land/sewer/surface water bodies), common facilities, etc.
59 Environmental condition scenarios shall be developed based on industrial activities and pollution
potentials.
60 Details of traffic density vis-à-vis impact on the ambient air.
61 Cumulative impact on regional supportive capacity shall be studied in terms of population density,
water supply, sewerage, storm water drainage, power supply, educational facilities, medical
facilities, public transport, traffic, housing for EWS, and community facilities, etc
62 Details on positive and negative impacts, direct and indirect impacts, induced impacts.
63 Project activities and impacts shall be represented in matrix form with separate matrices for pre and
post mitigation scenarios.
64 Traffic management plan including parking and loading/unloading areas may be described. Traffic
survey should be carried out on week days and weekends and also analyze the anticipated traffic
Chairman
140
increase.
65 Odour mitigation plan may be described. Also make provision of green cover as a measure for
mitigation of dust and noise and buffer between habitation and industry.
66 Rain water harvesting proposals should be made with due safeguards for groundwater quality.
Maximize recycling of water and utilization of rain water.
67 Temporary plans for the housing of construction labour within the site with all necessary
infrastructure and facilities such as fuel for cooking, mobile toilets, mobile Sewage Treatment Plant
(STP), safe drinking water, medical health care, crèche, etc.
68 Proposed measures for occupational safety and health of the workers.
69 Impact of the project on local infrastructure of the area such as road network and whether any
additional infrastructure would need to be constructed and the agency responsible for the same with
time frame.
70 Action plan for the greenbelt development – species, width of plantations, planning schedule etc.
within the boundary around the IE in accordance to CPCB published guidelines.
71 In case of likely impact from the proposed project on the surrounding reserve forests, Plan for the
conservation of wild fauna in consultation with the State Forest Department.
72 Identification of mitigation measures, source control and treatment.
Analysis of alternative resources and technologies :
73 Comparison of alternate sites considered and the reasons for selecting the proposed site. Conformity
of the site with the prescribed guidelines in terms of CRZ, river, highways, railways, etc.
74 Evaluate alternative disposal modes of effluent and solid wastes, from the point of view of disposal
points and associated impacts.
75 All kind of resources both renewable and non-renewable shall be taken into account.
76 Details on improved technologies.
Environmental monitoring program :
77 Monitoring programme for pollution control at source.
78 Monitoring pollutants at receiving environment for the appropriate notified parameters – air quality,
groundwater, surface water, etc. during operational phase of the project.
79 Specific programme to monitor safety and health protection of workers.
80 Appropriate monitoring network has to be designed and proposed, to assess the possible residual
impacts on VECs.
81 Details of in-house monitoring capabilities and the recognized agencies if proposed for conducting
monitoring.
Additional studies :
82 Details on risk assessment and damage control during different phases of the project and proposed
safeguard measures
83 Details on socio-economic development activities such as commercial property values, generation of
jobs, education, social conflicts, cultural status, accidents, etc.
84 Proposed plan to handle the socio-economic influence on the local community. The plan should
include quantitative dimension as far as possible.
85 Details on compensation package for the people affected by the project, considering the socio-
economic status of the area, homestead oustees, land oustees, and landless labourers.
Chairman
141
86 Public hearing should be conducted as per the prescribed procedure. Points identified in the public
hearing and commitment of the project proponent to the same. Detailed action plan addressing the
issues raised, and the details of necessary allocation of funds.
87 The historical importance of the area shall also be examined in the study. While this analysis is
being conducted, it is expected that an assessment of public perception of the proposed development
be conducted.
88 Describe the application of industrial ecology concept for planning of IEs. Explore possibility of
utilizing waste of one unit as raw material for the other units.
89 Specific chemical emergency response and proposed rescue system.
90 Details on corporate social responsibility proposal.
Environmental management plan :
91 Administrative and technical organizational structure to ensure proposed post-project monitoring
programme for approved mitigation measures.
92 EMP devised to mitigate the adverse impacts of the project should be provided along with item-wise
cost of its implementation (capital and recurring costs).
93 Allocation of resources and responsibilities for plan implementation.
94 Details of the emergency preparedness plan and on-site and off-site disaster management plan.
Pharma - SEZ specific points:
95 Details of Solvent Recovery Plant to be installed to recover the solvents and its monitoring
mechanism.
96 Mitigation measures to control fugitive measures.
97 Details of STP/CETP to be installed for the treatment of sewage and trade effluent generated to the
prescribed standards and recycling mechanism.
98 Detailed plan for compliance with the provision of rules and guidelines under Manufacture, Storage
and Import of Hazardous Chemicals Rules, 1989 and Hazardous Wastes (Management, Handling
and Transboundary Movement) Rules,2008 as amended from time to time.
99 Plan for occupational health surveillance as per Factories Act.
100 Eco-developmental measures including community welfare measures.
101 Details of MoU with all buyers of the plot to ensure operation and maintenance of the
ETP/STP/CETP/TSDF etc and other assets.
If the location falls in CRZ area: A CRZ map duly authenticated by one of the authorized agencies
demarcating LTL, HTL, CRZ area, location of the project and associate facilities w.r.t. CRZ, coastal
features such as mangroves, if any.
a. Provide the CRZ map in 1:10000 scale in general cases and in 1:5000 scale for specific
observations.
b. Proposed site for disposal of dredged material and environmental quality at the point of
disposal/impact areas.
102
c. Fisheries study should be done w.r.t. Benthos and Marine organic material and coastal
fisheries.
Above points shall be adequately addressed in the EIA report at corresponding chapters, in addition
to the contents given in the reporting structure as below:
Chairman
142
Sr. EIA Structure Contents
Purpose of the report
Identification of project & project proponent
Brief description of nature, size, location of the project and its importance
to the country, region
1 Introduction
Scope of the study – details of regulatory scoping carried out (As per
ToR)
Condensed description of those aspects of the project (based on project
feasibility study), likely to cause environmental effects. Details should be
provided to give clear picture of the following:
a. Type of project
b. Need for the project
c. Location (maps showing general location, specific location, project
boundary & project site layout)
d. Size or magnitude of operation (incl. Associated activities required
by / for the project)
e. Proposed schedule for approval and implementation
f. Technology and process description
g. Project description including drawings showing project layout,
components of project etc. Schematic representations of the
feasibility drawings which give information important for EIA
h. Description of mitigation measures incorporated into the project to
meet environmental standards, environmental operating conditions,
or other EIA requirements (as required by the scope)
2 Project Description
i. Assessment of new & untested technology for the risk of
technological failure
Study area, period, components & methodology
Establishment of baseline for VECs, as identified in the scope
3 Description of the
Environment
Base maps of all environmental components
Details of investigated environmental impacts due to project location,
possible accidents, project design, project construction, regular
operations, final decommissioning or rehabilitation of a completed project
Measures for minimizing and / or offsetting adverse impacts identified
Irreversible and irretrievable commitments of environmental components
Assessment of significance of impacts (Criteria for determining
significance, assigning significance)
4 Anticipated
Environmental
Impacts &
Mitigation Measures
Mitigation measures
In case the scoping exercise results in need for alternatives:
a. Description of each alternative
b. Summary of adverse impacts of each alternative
5 Analysis of
Alternatives
(Technology & Site)
c. Mitigation measures proposed for each alternative and selection of
alternative
Chairman
143
6 Environmental
Monitoring Program
Technical aspects of monitoring the effectiveness of mitigation measures
(incl. measurement methodologies, frequency, location, data analysis,
reporting schedules, emergency procedures, detailed budget &
procurement schedules)
Public consultation
Risk assessment
7 Additional Studies
Social impact assessment, R&R Action Plans
Improvements in physical infrastructure
Improvements in social infrastructure
Employment potential –skilled; semi-skilled and unskilled
8 Project Benefits
Other tangible benefits
9 Environmental Cost
Benefit Analysis
If recommended at the Scoping stage
10 EMP Description of administrative aspects that ensures proper implementation
of mitigative measures and their effectiveness monitored, after approval
of the EIA
Overall justification for implementation of the project 11 Summary &
Conclusion (This
will constitute the
summary of the EIA
Report)
Explanation of how, adverse effects have been mitigated
12 Disclosure of
Consultants engaged
Names of the Consultants engaged with their brief resume and nature of
Consultancy rendered
=o=