Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Page 1 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 1 of 93
Minutes of the 475th meeting of the State Level Expert Appraisal Committee held on 22/01/2019
at Geer Foundation, Sector 9, Indroda Park, Gandhinagar.
The 475th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 22nd January
2019 at Geer Foundation, Sector 9, Indroda Park, Gandhinagar. Following members attended the
meeting:
1. Dr. Dinesh Misra, Chairman, SEAC
2. Shri V. N. Patel, Member, SEAC
3. Shri R. J. Shah, Member, SEAC
4. Dr. V.K. Jain, Member, SEAC
5. Shri A.K. Muley, Member, SEAC
The agenda of TOR/Scoping cases and Appraisal was taken up. The applicants made presentations on
the activities to be carried out along with other details furnished in the Form-1, PFR, EIA-EMP reports
and other reports.
7 SIA/GJ/IND2/21319/2017 M/s. Hindusthan M-I Swaco Ltd.
Plot No. Z/109/A , Dahej SEZ, Phase-II,
Tal: Vagra, Dist: Bharuch – 392 130,
Gujarat.
Appraisal
Category of the unit : 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/21319/2017 dated 12/01/2018 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated 31/07/2018.
• Project proponent has submitted EIA Report prepared by M/s. Aqua Air Environmental Engineering Pvt Ltd.
based on the TOR issued by SEIAA
• This is an existing unit engaged in Synthetic Organic Chemicals and now proposes for expansion as tabulated
below:
Sr. No.
Name of the Products CAS no. /CI no.
Quantity MT/Month End-use of products Existing Proposed Total
1 Carboxy Methyl Cellulose-Sodium Salt (CMC-Na)
9004-32-4 300 300 600 Oil Drilling
2 Micro Crystalline Cellulose Powder (MCCP)
9004-34-6 200 - 200
3 Hydroxy Ethyl Cellulose (HEC)
9004-62-0 100 - 100
4 Hydroxy Propyl Methyl Cellulose (HPMC)
9004-65-3 25 - 25
5 Methyl Cellulose 9004-67-5 100 - 100
6 Ethyl Cellulose 9004-57-3 25 - 25
7 Fibroseal (MIX II) FINE, 9004-34-6 2000 - 2000
Page 2 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 2 of 93
MEDIUM, COARSE
8 Liquid Based Products
Surfactants 68585-34-2
Emulsifiers 9016-45-9
Lubricants 72623-86-0
Biocides 25314-61-8
Corrosion Inhibitors --
De-Emulsifiers --
Flow Improvers --
9 Carboxy Methyl Starch -Sodium Salt (CMS-Na)
9057-06-1 - 600 600
10 Pregelatinised Starch 9057-07-2 -
11 Bentonite Derivatives 1302-78-9 - 2500 2500
12 Lignite Based Products 129521-66-0 - 4200 4200
13 Lignite / Humic Acid base Product - (Blending / Reprocessing)
1415-93-6 - 2500 2500
14 Carboxy Methyl Cellulose-Sodium Salt (CMC-Na) - (Blending / Reprocessing)
9004-32-4 1400 1400
Total 2,750 11,500 14,250
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 22/01/2019.
• Salient features of the project are as under:
Sr.
no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Existing: 66.65
Proposed: 36.45
Total: 103.1
B Total Plot area
( sq. meter)
Existing: 54368.65 Sq. m.
Proposed: 0 Sq. m.
Total: 54368.65 Sq. m.
Green belt area
( sq. meter)
Existing: 20558.38 Sq. m.
Proposed: 0 Sq. m.
Total: 20558.38 Sq. m.
C Employment generation Existing: 45
Proposed: 20
Total: 65
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
SEZ/ GIDC Water Supply
Status of permission from the concern authority. Unit has obtained permission from GIDC
Page 3 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 3 of 93
for water supply vide letter no
GIDC/BRH/WS/661 dated 27/10/2016.
ii Water consumption (KLD)
Existing KLD
Proposed (Additional) KLD
Total after Expansion KLD
Remarks
(A) Domestic 15 5 20 (B) Gardening 50 0 50 (C) Industrial
Process 115.5 84.5 200
Washing 29 1 30
Boiler 22.9 -2.9 20
Cooling 25.8 4.2 30
Others Nil Nil Nil
Industrial Total 193.2 86.8 280
Grand Total (A+B+C)
258.2 91.8 350
1) Total water requirement for the project: 350 KLD
2) Quantity to be recycled: 12 KLD
3) Total fresh water requirement: 338 KLD
iii Waste water generation (KLD)
Category Existing KLD
Proposed (Additional) KLD
Total after Expansion KLD
Remarks
(A) Domestic 13 4 17 (B) Industrial
Process 67.5 12.5 80
Washing 28 0 28
Boiler 2 3 5
Cooling 2 3 5
Others 4.5 0 4.5 Softening & DM plant reject
Total Industrial waste water
104 18.5 122.5
iv Treatment facility within premises with capacity [For existing and Proposed]
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
M/s. Hindusthan M-I Swaco Ltd., have an Effluent treatment plant consisting of primary, secondary,
tertiary and advanced treatment units. The details of ETP are as follows.
First blowdown from Boiler, Cooling and Softening& DM plant (Stream I) reject shall be collected in
Collection Tank-1(CT-1). Thereafter, the wastewater shall be pumped to Pressure Sand Filter-1 (PSF-
1) to remove any TSS and Activated Carbon Filter-1 (ACF-1) for polishing. Then effluent is collected in
RO feed Tank before sent to RO treatment in RO Unit. RO permeate shall be reuse in process and RO
Page 4 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 4 of 93
reject shall be sent to ME Feed Tank for further treatment.
First all high TDS streams (Process and washing) (Stream II) of wastewater shall pass through Screen
Chamber (SC-01) where floating material shall be removed with help of Screen (S-01). Then effluent
shall be passed through Oil & Grease Removal Trap (OGRT-01) where floating oil and grease shall be
removed manually from the Tank. Then effluent shall be collected in Collection Tank-2(CT-02). Then
effluent is overflowed to Equalization cum Neutralization Tank (ENTs-01) where soda ash shall be
added from Soda Ash Dosing Tank (SADT-01). Agitators are provided in ENTs to keep all suspended
solids in suspension and for proper mixing.
Then after, equalized wastewater shall be pumped to Primary Settling Tank (PST) where poly shall be
added from Poly Dosing Tank (PDT). Solids are allowed to settle in PST and clear supernatant is
collected in Holding Tank.
Sludge settled at bottom shall be sent to Sludge Sump (SS-01). Then effluent shall be pumped to
Stripper (ST-01) for removal of solvent. After that effluent shall collected in MEE Feed Tank (MFT-01).
Then effluent shall be sent to four stages Evaporator followed by Centrifuge (CTF-01). Condensate
from MEE shall be collected in Condensate Storage Tank (CST-01) before sent to Aeration Tank for
further treatment. Solid from Centrifuge (CTF-01) shall be collected and stored in HWSA for ultimate
disposal to TSDF.
MEE condensate shall be mixed with sanitary waste in Aeration tank (AT-01). Here, biodegradation of
organic matter of the wastewater shall be carried out by bacteria (suspended growth) in the AT and for
that oxygen shall be supplied by 2 nos. of air blowers (B-01) through diffusers. Air blowers also keep
MLSS in suspension. Nutrients will be added from NDTs to Aeration Tank for growth of Bacteria.
Then after, wastewater shall go to Secondary Settling Tank (SST-01) from AT. Here, the suspended
solids shall be settled. Sludge shall be removed from bottom of SST and pumped to AT to maintain
MLSS and excess activated sludge shall be sent to Sludge Sump (SS-01). Clear effluent is the
collected in of Intermediate Sump (IS-01) by gravity. Hypo is mixed here in IS for disinfection from
Hypo Dosing Tank (HDT-01).
Thereafter, the wastewater shall be passed through Pressure Sand Filter-2 (PSF-02) to remove left out
TSS and Activated Carbon Filter (ACF-02) for final effluent polishing. Treated effluent is then collected
in Treated Effluent Sump (TES-01) before sent to GIDC drain.
Page 5 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 5 of 93
Sludge settled in PTS and excess sludge from SST-01 shall be collected in Sludge Sump then sludge
shall be pumped to Filter Press (FP)/Sludge Drying Beds (SDBs-01) where, dewatering shall be carried
out before storage in HWSA and ultimate disposal to TSDF. Leachate from FP-01 and SDBs shall be
sent back to MEFT-01 for further treatment.
v Mode of Disposal & Final meeting point
Domestic:
17 KL/Day domestic wastewater will be mixed with condensate released from
MEE and then treated in Effluent Treatment Plant and discharged into deep sea
via GIDC drain.
Industrial:
108 KL/day Industrial (from Process & Washing) & 2.5 KL/day of (RO Reject
Stream) wastewater will be sent to MEE and condensate released from MEE
(i.e. 103.5 KL/day) will be mixed with 17 KL/day (Domestic Wastewater), so total
120.5 KL/day will be then treated in Effluent Treatment Plant and discharged into
deep sea via GIDC drain.
14.5 KL/day industrial (from Boiler, Cooling, DM & Softening Plants) waste water
will be sent to RO for treatment and reuse.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE, CHWIF etc.
Name of Common facility
CHWIF membership of M/s. Saurashtra Enviro Projects Pvt. Ltd.
Membership of Common facility (CF)
Unit has obtained membership of CHWIF membership of M/s. Saurashtra Enviro Projects Pvt. Ltd.
dated 05/04/2018.
vii Simplified water balance diagram with reuse / recycle of waste water
Page 6 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 6 of 93
GIDC WATER
350 KL/ day
DOMESTIC
20 KL/ day
PROCESS
200 KL/ day
WASHING
30 KL/ day
BOILER
20 KL/ day
120.5 KL/ day
ETP
17 KL/ day
80 KL/ day
28 KL/ day
5 KL/ day
COOLING
30 KL/ day
5 KL/ day
Deep sea via
GIDC drain
120.5 KL/ day
110.5 KL/ day
MEE Plant
SOFTENING & DM PLANT
4.5 KL/ day
Reject from
Softening &
DM Plant
GARDENING
50 KL/ day
Nil
MEE Condensate
103.5 KL/ day
14.5 KL/ day
RO Plant
RO Permeate
12 KL/ day Reuse
RO Reject
2.5 KL/ day
108 KL/ day
vii Reuse/Recycle details (KLD)
[Source of reuse & application area]
Total reuse 14.5 KLD
Source of waste water for
reuse with quantity in KLD
Application area
with quantity in
KLD
Remarks regarding feasibility
to reuse i.e. w/w
characteristics (COD, BOD,
TDS etc.)
14.5 KL/day industrial (from
Boiler, Cooling, DM & Softening
14.5 KL/day in
Cooling tower
COD: 50 mg/L
BOD: 10 mg/L
Page 7 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 7 of 93
Plants) waste water will be sent
to RO for treatment
TDS: 200 mg/L
-
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Existing & Proposed
-
Sr.
no.
Source of
emission
With Capacity
Stack
Height
(meter)
Type of
Fuel
Quantity of
Fuel
MT/Day
Type of
emissions
i.e. Air
Pollutants
Air Pollution
Control
Measures
(APCM)
1 Boiler (4.5 TPH & 2TPH) (Existing)
30.5 Natural
Gas/ FO
2500 SCM/ day / 4 MT/Day
SPM SO2 NOx
NG/FO and adequate stack height
2 DG Set (500 KVA) (stand by) (Existing)
11 Diesel 2000 Lit/Day
SPM SO2 NOx
Adequate Stack Height
3 Thermic Fluid Heater (6 Lac Kcal/Hr.) (Proposed)
30 Natural
Gas/ FO
5000 SCM/ day / 20 MT/
Day
SPM SO2 NOx
NG/FO/HSD and adequate stack height
-
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Existing & Proposed
- No process gas emissions from the proposed expansion project.
iii Fugitive emission details with its mitigation measures.
Following measures will be adopted to prevent and control fugitive emissionsC
1. Airborne dust at all transfers operations/ points will be controlled either by spraying water or
providing enclosures.
2. Care will be taken to store construction material properly to prevent fugitive emissions, if any.
3. Regular maintenance of valves, pumps, flanges, joints and other equipment will be done to
prevent leakages and thus minimizing the fugitive emissions of VOCs.
4. Entire process will be carried out in the closed reactors with proper maintenance of pressure
and temperature.
5. Periodic monitoring of work area will be carried out to check the fugitive emission.
6. To eliminate chances of leakages from glands of pumps, mechanical seal will be provided at all
solvent pumps.
Page 8 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 8 of 93
7. Close feeding system will be provided for centrifuges. Centrifuge and filtrate tank vents will be
connected to vent chillers.
8. Minimum number of flanges, joints and valves in pipelines.
9. Enclosures to chemical storage area, collection of emission from loading of raw materials in particular
solvents through hoods and ducts by induced draft, and control by scrubber / dust collector to be
ensured.
10. Adequate ventilation will be provided.
11. Periodic monitoring of work area will be carried out to check the fugitive emission as per the norms of
Gujarat Factory Rules.
12. Emphasis has been given to solvent management / solvent loss prevention as shown in the solvent
management plan.
F Hazardous waste
(as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016.
Existing & Proposed
i
Sr.
no.
Type/Nam
e of
Hazardou
s waste
Source
of
generati
on
Category
and
Schedule
as per HW
Rules.
Quantity
(MT/Annum)
Disposal Method
Existing Propos
ed
Total
1 ETP Sludge
ETP Sch-I/ 35.3
60 336
396
Collection, Storage, Transportation & Disposed at TSDF of M/s. SEPPL
2 Used Oil Equipment &
Machinery
Sch-I/ 5.1
2100 Lit. 11892 Lit.
13992 Lit.
Collection, Storage, Transportation& Disposal By selling to GPCB Registered Reprocessors
3 Discarded Bags & Liners
Raw material
& storage
Sch-I/ 33.1
36000 Nos.
21.6 MT
204000 Nos. 122.4 MT
240000 Nos.
144 MT
Collection, Storage, Decontamination, Transportation & Disposal by either return to supplier or selling to registered vendors
Used Drums & Bags
Raw material
& storage
Sch-I/ 33.1
96000 Nos.
57.6 MT
120000 Nos.
72 MT
216000 Nos. 129.6 MT
Collection, Storage, Transportation and sell to GPCB registered vendor or returned to manufacturer as per terms of purchase
4 MEE Salt MEE Sch-I/ 35.3
1560 1632
3192
Collection, Storage, Transportation & Disposed at TSDF of M/s. SEPPL
5 Spent Carbon
From utility
Sch-I/ 36.2
- 0.12 0.12 Collection, Storage, Transportation & Disposed at Common Incineration or co-processing in cement
Page 9 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 9 of 93
industries.
6 InorganicProcess sludge
Process Sch-I/ 28.1
- 27 27 Collection, Storage, Transportation & Disposed at TSDF of M/s. SEPPL
-
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Company has membership of TSDF of M/s. SEPPL
dated 05/04/2018.
iii Details of Non-Hazardous waste & its
disposal(MSW and others)
No such waste will be generated.
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
Name of Solvent
Total Input (Kg)
Qty. of Recovered
Solvent (Kg)
Qty. of Losses (Kg)
% Recovery
% Losses
Ethanol 2880 2736 144 95 5
Methanol 18720 17970 750 96 4
ii VOC emission sources and its mitigation measures
During operation stage, leakage through valves/pumps, leakage and emission from open drum containing chemicals, open feeding, storage tanks, etc. will be major sources of fugitive emissions and VOCs. Excess use of solvent/s may also results fugitive emission from the process vessels.
• Solid raw material charging will be done through closed system.
• Entire process will be carried out in the closed reactors with proper maintenance of pressure and
temperature.
• Emphasis will be given to solvent management/solvent loss prevention.
• Control by having proper scrubbing system.
• Condenser to trap VOC.
• Proper maintenance schedule will be adhered to avoid emissions through flange joints, pump seals
etc.
• Minimum number of flanges, joints and valves in pipelines.
• Proper gland packing will be maintained for pumps and valves and to the extent possible pumps
with mechanical seal.
• A regular preventive maintenance schedule will be in place to replace or rectify all gaskets and
joints etc. as a part of ISO systems to ensure no fugitive emissions take place.
• Periodic monitoring of work area will be carried out to check the fugitive emission.
• Solvent tank vents will be connected to vent chillers.
• Adequate ventilation will be provided.
• Airborne dust at all transfers operations/ points will be controlled either by spraying water or
providing enclosures.
• Breather valves will be provided on solvent tanks.
Page 10 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 10 of 93
• During the meeting dated 08/01/2019, technical presentation made during the meeting by project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report, various
issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted for
the study area of 10 km radial distance from project site for the period October 2016 to December 2016.
Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2, NO2, NH3, CO, O3, Pb, C6H6, BaP,
As, Ni, HC & VOC at seven locations, including the project site. Values conform to the prescribed standards for
Ambient Air Quality. The incremental Ground Level Concentration (GLC) has been computed using ISCST3.
The resultant concentrations are within the NAAQS. The ambient air quality around the proposed project site
will remain within the National Ambient Air Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• During SEAC meeting on 22/01/2019, committee noted that the proposal is for expansion. This unit has valid
CC&A for existing unit. Copy of CC&A, its compliance report is submitted. Unit has submitted Certified
Compliance Report from RO-Bhopal. PP ensured that there are no court cases pending and no public
complaints against the project. Source of water is GIDC. PP mentioned that w/w generated from boiler blow
down, cooling, DM & Softening will be passed to RO, RO permeate will be used in process and reject will be
sent to MEE. PP also mentioned that w/w generated from process and washing will be sent to MEE along with
RO reject and MEE condensate will be sent to ETP consisting of primary, secondary & tertiary treatment along
with STP w/w and after treatment, treated effluent will be discharged into deep sea via GIDC drain. PP has
proposed one TFH. Fuel used will be Natural Gas/FO. PP addressed Hazardous Waste as per HWR – 2016.
PP addressed EMP, CER with details of budgetary provisions was found satisfactory.
• Compliance of the ToR was found satisfactory.
After detail deliberation the committee unanimously decided to recommend the proposal for grant of EC to
SEIAA with following specific conditions
Ample Plantation shall be carried out in the premises and along the periphery with the species suitable in that
area.
• Reuse treated w/w quality in Cooling Tower shall be conforming to the above mentioned standards (COD – 50
mg/l, BOD – 10 mg/l, TDS – 200 mg/l).
• Storage of solvent shall be as per PESO standards for flammable material.
• Unit shall explore the possibilities for environment friendly methods for disposal of ETP waste instead of
sending to TSDF site.
• All measures shall be taken to prevent soil and ground water contamination.
Page 11 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 11 of 93
• Leak Detection and Repair (LDAR) program shall be prepared and implemented as per the CPCB guidelines.
9 SIA/GJ/IND2/19729/2017 Sabari Chemicals Pvt. Ltd. Plot no. A2/236, GIDC, Nandesari, Vadodara – 391340.
Appraisal
Category of the unit : 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/19729/2017 dated 10/1/2019 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated 20/01/2018.
• Project proponent has submitted EIA Report prepared by RAAS Envirocare based on the TOR issued by
SEIAA
• This is an existing unit engaged in Synthetic organic chemicals and now proposes for expansion as tabulated
below:
Sr.
no.
Name of
the
Products
CAS no. /
CI no.
Quantity
MT/Month
End-use of
the products
Existing
Proposed Total
1
Benzyl
Benzoate
120-51-4 20 30
50
Used in
Pharmaceutical
Industry/
Organic
Chemical
Manufacturing
2 Benzyl
Alcohol
100-51-6 30 30 60
3 Benzyl
Cyanide
140-29-4 15 35 50
4 Phenyl
Acetic Acid
103-82-2 5 45 50
5 Benzyl
Salicylate
118-58-1 5 45 50
6 Naphthalene
Acetic Acid
(Tech) and
Sodium Salt
81872-10-
8
20 0 20
7 Para
Methoxy
Phenyl
Acetonitrile
104-47-2 27 33 60
Page 12 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 12 of 93
8 Para
Methoxy
Phenyl
Acetic Acid
104-01-8 0 20 20
9 Naphthalene
Acetamide
86-86-2 0 10 10
10 Dibenzyl
Ether (High
boiler of
Benzyl
Alcohol)
103-50-4 0 70 70
11 High boiler
of Benzyl
Benzoate
0 25 25
12 Trading
(Repacking)
0 150 150
Benzyl
Acetone
2550-26-7
1 Acetyl
Naphthalene
941-98-0
Benzyl
Acetate
140-11-4
Total 122 493 615
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 22/01/2019.
• Salient features of the project are as under:
Sr.
no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Existing: Rs. 2.85 Cr
Proposed: Rs. 2.0 Cr
Total: Rs. 4.85 Cr
B Total Plot area
( sq. meter)
Existing: 3000 Sq. m.
Page 13 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 13 of 93
Proposed: Nil .Sq. m.
Total: : 3000 Sq. m.
Green belt area
( sq. meter)
Existing: K350 Sq. m. Proposed: 600.Sq. m. Total: 660 Sq. m.
C Employment generation Existing: 63
Proposed: 50
Total: 113
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC Water Supply Scheme
Status of permission from the concern authority.
Permission has been obtained
ii
Water consumption (KLD)
Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(D) Domestic 2.0 8.0 10.0
(E) Gardening
1.0 1.0 2.0
(F) Industrial
Process 31.0 99.0 130.0
Washing 1.0 24.0 25.0
Boiler 2.0 13.0 15.0
Cooling 2.0 18.0 20.0
Others -- -- --
Industrial Total
36.0 154.0 190.0
Grand Total
39.0 163.0 202.0
Page 14 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 14 of 93
(A+B+C)
4) Total water requirement for the project: 202..KLD
5) Quantity to be recycled: 0.0.KLD
6) Total fresh water requirement:202.KLD
iii
Waste water generation (KLD)
Category Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(C) Domestic
1.0 7.0 8.0
(D) Industrial
Process 17.0 66.0 83.0
Washing 1.0 24.0 25.0
Boiler 0.5 4.5 5.0
Cooling 0.5 6.5 7.0
Others -- 40.0 40.0
Total Industrial
waste water
19.0 141.0 160.0
iv Treatment facility within premises with capacity [For existing and Proposed]
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
� Capacity of the ETP – 160 KL/day
v Mode of Disposal & Final meeting point
Domestic:
Soak pit/ CETP
Industrial:
CETP
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE,
CHWIF etc.
Page 15 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 15 of 93
Name of Common facility
� TSDF – Nandesari Environment Control Ltd.
Membership of Common facility (CF):Membership taken
(For waste water treatment)
� CETP – Nandesari Industries Association
vii Simplified water balance diagram with reuse / recycle of waste water
vii Reuse/Recycle details (KLD) : 7 KL/day
[Source of reuse & application area] :
Total reuse : 20.KLD
Source of waste
water for reuse
with quantity in
KLD
Application area with
quantity in KLD
Remarks
regarding
feasibility to
reuse i.e. w/w
characteristics
(COD, BOD,
TDS etc.)
RO Reject – 20
KL/day
Preparation of Lime doser COD- 50 mg/L
-
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr,
Page 16 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 16 of 93
KVA etc.
Existing & Proposed
-
Sr.
no.
Source
of
emission
With
Capacity
Stack
Height
(meter)
Type of
Fuel
Quantity
of Fuel
MT/Day
Type of
emissions
i.e. Air
Pollutants
Air
Pollution
Control
Measures
(APCM)
1
Existing
TFH (4
Lac Kcal /
hr) will be
used as
standby
after
expansion
11 mts Natural
gas
350
SCM/day
NOx, PM Adequate
stack
height is
provided
2 Existing TFH
(4 Lac
KCal/hr)
11 mts Agrowaste/
briquette/
wood
15
MT/day
SO2, NOx,
PM
Built in PM
control
Mechanism
3. Existing Boiler (2 MT/hr)
11 mts briquette/
wood
15
MT/day
SO2, NOx,
PM
Cyclone
4. Proposed Boiler (1.5 MT/hr)
30 mts briquette/
agrowaste
12
MT/day
SO2, NOx,
PM
Cyclone
5. DG Set (250 kva)
3 mts HSD 400
Lts/Mont
h
SO2, NOx,
PM
Adequate
stack
height is
provided
-
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Existing & Proposed
-
Sr.
no.
Specific
Source of
emission
(Name of
Type of
emission
Stack/Vent
Height
(meter)
Air Pollution
Control
Measures
(APCM)
Page 17 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 17 of 93
the
Product &
Process)
1 Scrubber
attached
to reactor
HCl 15 mts 2 stage
scrubber
2 Scrubber
(proposed)
attached
to reactor
HCl 15 mts 3 stage
scrubber
3 Scrubber
(proposed)
attached
to reactor
SO2, HCl 15 mts 2 stage
scrubber
4 Scrubber
(proposed)
attached
to reactor
NH3 15 mts 2 stage
scrubber
-
iii Fugitive emission details with its mitigation measures.
Chilled Water condensers provided to the reaction vessels and storage tanks
F Hazardous waste
(as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
Existing & Proposed
i
Sr.
no
.
Type/Nam
e of
Hazardou
s waste
Specific
Source of
generatio
n
(Name of
the
Activity,
Product
etc.)
Categor
y and
Schedul
e as per
HW
Rules.
Quantity
(MT/Annum)
Manageme
nt of HW
Existin
g
Propose
d
Total
Page 18 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 18 of 93
1 ETP
Sludge
ETP 35.3 800 400 1200 Collection,
Storage,
transportatio
n and
disposal at
TSDF,
NECL for
landfilling
2 Waste
Residue
Process 26.1 18 12 30 Collection,
Storage,
transportatio
n and
disposal at
TSDF,
NECL
3 Used Oil Pumps,
Gearbox
etc
5.1 0.5 0.5 1.0 Applied on
MS
structure for
corrosion
control or
will be sent
to NECL for
incineration
4 Liner
Bags &
discarded
container
Raw /
Inprocess
Material
33.3 1.0 1.0 2.0 Collection,
Storage,
decontamin
ation within
factory
premises
and sold to
authorized
scrap
dealers
-
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Membership has been obtained from TSDF
of NECL, GIDC, Nandesari
Page 19 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 19 of 93
iii Details of Non-Hazardous waste & its
disposal(MSW and others)
Domestic Waste generated by the unit is
picked up daily by truck organized by NIA
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered
Solvents
Solvents (N-Hexane, Trimethyl Amine, Toulene) are used up in the reaction
ii VOC emission sources and its mitigation measures
� From storage area, tank farm – Vent gas condenser with chilled water circulation will be
provided
• During the meeting dated 22/01/2019, technical presentation made during the meeting by project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report, various
issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted for
the study area of 10 km radial distance from project site for the period November 2016 to February 2017.
Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2, NOx, Chlorine, Ammonia & VOC at ten
locations, including the project site. Values conform to the prescribed standards for Ambient Air Quality. The
incremental Ground Level Concentration (GLC) has been computed using ISCST3. The resultant
concentrations are within the NAAQS. The ambient air quality around the proposed project site will remain
within the National Ambient Air Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• During SEAC meeting on 22/01/2019,
• After deliberation, SEAC unanimously decided to consider the proposal after submission of the
following details.
1. To carry out detailed study on all the process having cyanide bearing stream and mentioned the same in
EIA report along with the Quality & Quantity of the waste bearing stream and its treatment methods &
Feasibility.
2. To address scrubber media in waste stream and water balance diagram as per the TOR granted and
submit the revised details accordingly.
3. To submit the revised product profile as per the TOR granted by SEIAA dated 20/01/2018.
4. To eliminate wood as fuel in existing TFH & Boiler and address the APCM in proposed and existing boiler
as per guidelines of GPCB for usage of solid fuel.
5. Properly address Recycle/Reuse of treated w/w along with quantity and quality.
Page 20 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 20 of 93
9 SIA/GJ/IND2/19545/2017 Anil Colour Industries P Ltd. Plot no. 125/1, GIDC, Nandesari, Vadodara – 391340.
Appraisal
Category of the unit : 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/19545/2017 dated 22/09/2017 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated
20/01/2018.
• Project proponent has submitted EIA Report prepared by RAAS Envirocare based on the TOR issued by
SEIAA
• This is an existing unit engaged in Synthetic organic chemicals and now proposes for expansion as
tabulated below:
Sr.
no.
Name of the
Products
CAS no. /
CI no.
Quantity
MT/Month
End-use of
the
products
Existing
Proposed Total
1.
4- Nitro 2-
Amino
Phenol OR
99-57-0 2
48/47 50 Dye and Dye
intermediates
2 Pyridone
Carbonyl
Amide
29097-12-9 3
2 Meta Ureido
Aniline 59690-88-9 15 125 140
Total 20 190
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 22/01/2019.
• Salient features of the project are as under:
Sr.
no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Existing: Rs. 0.43 Cr
Proposed: Rs. 2.5 Cr
Page 21 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 21 of 93
Total: Rs. 2.93 Cr
B Total Plot area
( sq. meter)
Existing: 2994.4 Sq. m.
Proposed: Nil .Sq. m.
Total: : 2994.4 Sq. m.
Green belt area
( sq. meter)
Existing: K300 Sq. m. Proposed: 360.Sq. m. Total: 660 Sq. m.
C Employment generation Existing: 15
Proposed: 50
Total: 65
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC Water Supply Scheme
Status of permission from the concern authority.
Permission has been obtained
ii
Water consumption (KLD)
Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(G) Domestic 3.0 7.0 10.0
(H) Gardening
1.0 1.0 2.0
(I) Industrial
Process 19.4 90.6 110.0
Washing -- -- --
Boiler 2.0 10.0 12.0
Cooling 2.5 12.5 15.0
Others -- -- --
Page 22 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 22 of 93
Industrial Total
23.9 113.1 137
Grand Total
(A+B+C)
27.9 121.1 149.0
7) Total water requirement for the project: 149..KLD
8) Quantity to be recycled: 0.0.KLD
9) Total fresh water requirement:149.KLD
iii
Waste water generation (KLD)
Category Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(E) Domestic
3.0 5.0 8.0
(F) Industrial
Process 17.1 92.9 110.0
Washing -- --
Boiler 0.2 4.3 4.5
Cooling 0.3 2.2 2.5
Others -- --
Total Industrial
waste water
17.6 99.4 117.0
iv Treatment facility within premises with capacity [For existing and Proposed]
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
� Capacity of the ETP – 120 KL/day
v Mode of Disposal & Final meeting point
Domestic:
Soak pit/ CETP
Page 23 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 23 of 93
Industrial:
Soak pit/ CETP
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE,
CHWIF etc.
Name of Common facility
� TSDF – Nandesari Environment Control Ltd.
Membership of Common facility (CF):Membership taken
(For waste water treatment)
� CETP – Nandesari Industries Association
vii Simplified water balance diagram with reuse / recycle of waste water
vii Reuse/Recycle details (KLD) : 7 KL/day
[Source of reuse & application area] :
Total reuse : 20.KLD
Source of waste
water for reuse
with quantity in
KLD
Application area with
quantity in KLD
Remarks
regarding
feasibility to
reuse i.e. w/w
characteristics
(COD, BOD,
TDS etc.)
Page 24 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 24 of 93
Boiler Blowdown –
4.5 KL/day
Preparation of Lime doser COD- 50 mg/L
Cooling tower
blowdown – 2.5
KL/day
Preparation of Lime doser COD- 150 mg/L
-
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr,
KVA etc.
Existing & Proposed
-
Sr.
no.
Source
of
emission
With
Capacity
Stack
Height
(meter)
Type
of
Fuel
Quantity
of Fuel
MT/Day
Type of
emissions
i.e. Air
Pollutants
Air
Pollution
Control
Measures
(APCM)
1
Existing
Boiler
(0.6
MT/hr)
20 mts Natural
gas
25
Nm3/hr
NOx, PM Adequate
stack
height
provided
2 Proposed Boiler (1 MT/hr)
20 mts Natural
gas
75
Nm3/hr
NOx, PM Adequate
stack
height
provided
-
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Existing & Proposed
-
Sr.
no.
Specific
Source of
emission
(Name of
the
Product &
Type of
emission
Stack/Vent
Height
(meter)
Air Pollution
Control
Measures
(APCM)
Page 25 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 25 of 93
Process)
1 No Process gas emissions
-
iii Fugitive emission details with its mitigation measures.
Vent gas condenser with chilled water circulation will be provided during expansion
F Hazardous waste
(as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
Existing & Proposed
i
Sr.
no
.
Type/Nam
e of
Hazardou
s waste
Specific
Source of
generatio
n
(Name of
the
Activity,
Product
etc.)
Categor
y and
Schedul
e as per
HW
Rules.
Quantity
(MT/Annum)
Manageme
nt of HW
Existin
g
Propose
d
Total
1 ETP
Sludge
ETP 35.3 90 1110 1200 Collection,
Storage,
transportatio
n and
disposal at
TSDF,
NECL for
landfilling
2 Process
waste
Sludge
Process 26.1 90 -40 50 Collection,
Storage,
transportatio
n and
disposal at
Page 26 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 26 of 93
TSDF,
NECL
3 Used Oil Pumps,
Gearbox
etc
5.1 0.1 0.4 0.5 Applied on
MS
structure for
corrosion
control or
will be sent
to NECL for
incineration
4 Liner
Bags &
discarded
container
Raw /
Inprocess
Material
33.3 12 8 20 Collection,
Storage,
decontamin
ation within
factory
premises
and sold to
authorized
scrap
dealers
-
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Membership has been obtained from TSDF
of NECL, GIDC, Nandesari
iii Details of Non-Hazardous waste & its
disposal(MSW and others)
Domestic Waste generated by the unit is
picked up daily by truck organized by NIA
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered
Solvents
Solvents (Mono ethyl amine ) is used up in the reaction
ii VOC emission sources and its mitigation measures
� From storage area, tank farm – Vent gas condenser with chilled water circulation will be
provided
• During the meeting dated 22/01/2019, technical presentation made during the meeting by project
Page 27 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 27 of 93
proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report,
various issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted
for the study area of 10 km radial distance from project site for the period November 2016 to February
2017. Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2, NOx, Chlorine, Ammonia,
Cl2, NH3 & VOC at ten locations, including the project site. Values conform to the prescribed standards for
Ambient Air Quality. The incremental Ground Level Concentration (GLC) has been computed using
ISCST3. The resultant concentrations are within the NAAQS. The ambient air quality around the proposed
project site will remain within the National Ambient Air Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency
Plan has been covered in the RA report.
• During SEAC meeting on 22/01/2019,
• After deliberation, SEAC unanimously decided to consider the proposal after submission of the
following details.
1. To carry out detailed study on process water consumption and Effluent generation in Existing stage
and Expansion stage.
2. Technical Justification of Non Increase in water consumption & Effluent Generation in proportion
with Expansion of Production.
3. Properly address Hazardous Waste and its disposal as per HWR – 2016.
4. Properly address Recycle/Reuse of treated w/w along with quantity and quality.
11 SIA/GJ/IND2/22661/2017 M/s. Sagar Life Sciences Pvt. Ltd. Plot No. 3124, 3125 & 3045 GIDC Estate Panoli- 394116, Dist. Bharuch, State - Gujarat, India
EC-Amendment
Category of the unit : 5(f)
Project status: Amendment
• PP has submitted online application vide no. SIA/GJ/IND2/22661/2017 dated 26/11/2018 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated 25/07/2017.
• Project proponent has submitted EIA Report prepared by Siddhi Green Excellence Pvt Ltd based on the TOR
issued by SEIAA.
• This is an existing unit engaged in Synthetic organic chemicals and now proposes for expansion as tabulated
below:
Sr. Name of Products CAS No. Capacity MT/Month
Page 28 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 28 of 93
No. CTO available
Sagar Life Sciences Pvt. Ltd.
CTEAvailable (After EC) Sagar Life
Sciences Pvt. Ltd.
CTO Available for Rajeev Chloride
& Carbonics Pvt. Ltd.
CTO Amendment
Applied (Total both units after
merge)
1. Calcium Chloride 10043-52-4
100 100 250 350
2. Repackaging & formulation of agrochemicals liquid products
-- 250 250 -- 250
3. Repackaging & formulation of agrochemicals Powder products
-- 250 250 -- 250
4. Soil Conditioner (Powder & Granules)
-- 5000 5000 -- 5000
5. Iodobenzene Di acetate
3240-34-4 -- 2 --
2
6. Tert Butyl Carbazate 870-46-2
7. 2 Hydroxy Decanoic Acid
5393-81-7
8. 4- Hydroxy Benzyl Alcohol
623-05-2
9. Ammonium Acetate 631-61- 8 25 -- 25
10. 4- Chloro Butyryl Chloride
4635-59-0 75 --
75
11. 2,5-Diamino Toluene Sulphate
615-50-9
12. Tri Methyl Silyl Triflate 27607-77-8
5 --
5
13. Triflic Anhydride 358-23-6
14. Tri Fluoro Acetic Anhydride
407-25-0
15. 1- Ethyl 3 -(3-dimethyl amino propyl) Carbodimide.HCl
25952-53-8
5 -- 5
16. Hydrogenation of Aldehyde & Nitro Compounds (Meta Phenoxy Benzyl Alcohal or Meta Bromo Aniline)
13826-35-2 / 591-19-
5
50 -- 50
17. Methyl Triflate 333-27-7 1 -- 1
18. Penta Methyl Bromo Benzene
5153-40-2 1 -- 1
19. 4-OCTYNE 1-OL 4-OCTYN 1-OL
34126-19-7
15 --
15
20. 7-OCTYN 1-OL 871-91-0
21. 1-bromo,6 methyl heptane
52648-04-1
22. Bottling of CO2 gas -- -- -- 50.00 50.00
Page 29 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 29 of 93
from CaCl2
23. Potassium Nitrate 7757-79-1 -- -- 250.00 250.00
24. Zinc Chloride 7646-85-7 -- -- 50.00 50.00
25. Potassium Chloride 7447-40-7 -- -- 200.00 200.00
26. Ammonium Chloride
12125-02-9
-- -- 200.00 200.00
• The project falls under the Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 22/01/2019.
• Salient features of the project are as under:
Sr. no.
Particulars Details
A Total cost of Proposed Project (Rs. in Crores):
Total- 663.85 Lac
B Total Plot area ( sq. meter)
Total: 4500 Sq. m. (Plot No. 3124, 3125 & 3045)
Green belt area ( sq. meter)
Approximately ~15% Green belt is proposed inside the plant premises. Remaining Green belt area shall be developed in area allotted from GIDC.
C Employment generation
Existing Man power: 27 + Contract labour Proposed additional Man power: 50 + Contract based labour Total: 77 +Contract based labour
D Water
i
Source of Water Supply (GIDC Bore well, Surface water, Tanker supply etc...)
GIDC
Status of permission from the concern authority.
- As per CTO of M/s. Sagar Life Sciences Pvt. Ltd., Industrial = 12.0 KL/day Domestic = 4.0 KL/day
Gardening = 3.0 KL/day - As per CTO of M/s. Rajeev Chloride & Carbonics Pvt. Ltd.
Industrial = 7.5 KL/day Domestic = 2.0 KL/day
Gardening = 0.5 KL/day
ii
Water consumption (KLD)
Existing KLD
Proposed (Additional) KLD
Total after Expansion KLD
Remarks
(J) Domestic 6.0 6.0 12.0 -- (K) Gardening 3.5 5.0 8.5 -- (L) Industrial
Process
18.5 14.0 32.5
APCM water is added in proposed water requirement
Page 30 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 30 of 93
as it shall be used in scrubbing of process emission.
Washing -- -- -- --
Boiler -- 2.0 2.0 --
Cooling 1.0 29.0 30.0 --
Industrial Total 23.0 50.0 73.0 --
Grand Total (A+B+C)
29.0 56.0 85.0 --
# There is no APCM water in existing water requirement as there is no process gas emission in existing operation. APCM water is added in proposed water requirement as it shall be used in scrubbing of process emission. * Utility blow down is reused for washing purpose.
10) Total water requirement for the project: 85 KLD 11) Quantity to be recycled: 5 KLD 12) Total fresh water requirement: 56 KLD
iii
Waste water generation (KLD)
Category Existing KLD
Proposed (Additional) KLD
Total after Expansion KLD
Remarks
(G) Domestic 3.6 3.0 6.6 To soak pit via septic tank
(H) Industrial
Process -- 8.81 8.81 To be treated in ETP & then to CMEE plant
Washing -- 5.0 5.0 To be treated in ETP & then to CMEE
plant
Boiler -- * -- Reuse for washing
Cooling -- * -- Reuse for washing
Others -- -- --
Total Industrial waste water
3.6 16.81 20.41
iv Treatment facility within premises with capacity [For existing and Proposed] [In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
Existing Scenario: In existing, there is no industrial effluent generation. Domestic sewage is disposed through soak pit via septic tank.
Proposed treatment facility: Treated in ETP and sent to CMEE Domestic sewage is disposed through soak pit via septic tank and same will continue after expansion.
v Mode of Disposal & Final meeting point
Domestic:
Disposed off through soak pit via septic tank
Industrial:
Primary treated effluent shall be sent to Common Multi-Effect Evaporation facility (CMEE) of M/s. Bharuch Enviro Infrastructure Limited (BEIL), Ankleshwar.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE, CHWIF etc.
Page 31 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 31 of 93
Name of Common facility
Common Multi-effect Evaporator (CMEE) Facility of M/s. Bharuch Enviro Infrastructure Ltd. (BEIL), Ankleshwar.
Membership of Common facility (CF)
Unit has membership of Common Multi-Effect Evaporation (CMEE) facility of M/s. Bharuch Enviro Infrastructure Ltd. (BEIL), Ankleshwar.
vii Simplified water balance diagram with reuse / recycle of waste water
vii Reuse/Recycle details (KLD) [Source of reuse & application area]
Total reuseCC.KLD
Source of waste water for reuse with quantity in KLD
Application area with quantity in KLD
Remarks regarding feasibility to reuse i.e. w/w characteristics (COD, BOD, TDS etc.)
Boiler blowdown: 1.0 KLD
Boiler blowdown of 1.0 KLD & Cooling tower blowdown of 4.0 KLD shall be reused for Washing purpose.
COD: <100 BOD: <30 TDS: <500
Cooling tower blowdown: 4 KLD
-
E Air
i Flue gas emission details No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Page 32 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 32 of 93
Existing & Proposed
Sr. No.
Stack ID / Stack
Attached to
Capacity / Remarks
Name of fuel
Quantity of fuel
used
Air Pollution Control
Measures (APCM)
Stack Height
in Meter (From G.L.)
Parameters
Permissible
Limits
Unit
Existing
1
10350-Furnace - to
be discontinue
d after expansion
Furnace (Cap. : 5
LacKcal/h)
Wood/Briquette
800 kg/day
Bag filter 13 PM SO2 NOx
150 100 50
mg/Nm3
ppm ppm
2 10237 - Furnace
15 KL water evaporation
/ Day
Wood OR
Natural Gas
2 MT/Day
OR 100
Nm3/Day
Bag Filter 13 PM SO2 NOx
150 100 50
mg/Nm3
ppm ppm
Proposed Additional
1
97091- Multi Fuel Boiler
Multi Fuel Boiler (1 No.,
Capacity: 2 TPH)
Wood/Briquette
4 MT/Day
Multi Cyclone + Bag filter
15
PM SO2 NOx
150 100 50
mg/Nm3
ppm ppm
97092- Thermic
Fluid Heater
Thermic Fluid Heater
(1 No., Capacity: 10 Lakh Kcal/h)
Wood/Briquette
4 MT/Day
Multi Cyclone + Bag filter
PM SO2 NOx
150 100 50
mg/Nm3
ppm ppm
2 97093- D.
G. Set
D. G. Set (1 No., 250
KVA) (Stand-by)
Diesel 1440 L/Day
-- 7 PM SO2 NOx
150 100 50
mg/Nm3
ppm ppm
The existing Furnace shall be discontinued after proposed expansion
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.) Existing & Proposed
Page 33 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 33 of 93
-
Stack No.
Stack Attached to
Air Pollution Control System
Height (m)
Air Emission
From process Pollutant
Permissible Limit
CTO available Sagar Life Sciences Pvt. Ltd.
1
43830- Blender for
powder formulation
Bag filter 9 PM SO2
NOX
150 mg/Nm3
40 mg/Nm3
25 mg/Nm3
--
2 47740 -
Reaction Vessel
Alkali Scrubber
(1 no.) 11
SO2 NOx HCl Cl2
NH3
40 mg/Nm3
25 mg/Nm3
20 mg/Nm3
9 mg/Nm3
175 mg/Nm3
--
Proposed Additional
3
97094- Reactor
vent for HCl emissions
at proposed new
production area
Water Scrubber (1
set) 9
PM SO2
NOX
150 mg/Nm3
40 mg/Nm3
25 mg/Nm3
Tri Methyl Silyl Triflate (New
product), 1- Ethyl 3 -(3-
dimethyl amino propyl)
Carbodimide. HCl (New product),
Methyl Triflate (New product)
4
97095- Reactor
vent for HBr emissions
at proposed new
production area
Caustic Scrubber (1
Set) 20 HCl
20 mg/Nm3
2 Hydroxy Decanoic Acid (New product), Penta Methyl
Bromo Benzene (New product)
5
97097- Reactor
vent for SO2 emissions
at proposed new
production area
Water + Caustic
Scrubber (1 Set)
20 HBr 30
mg/Nm3
4 Chloro Butyryl Chloride (New
product)
Page 34 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 34 of 93
6
97098- Reactor
vent for NH3
emissions at proposed
new production
area
Water Scrubber (1
set) 20 SO2
40 mg/Nm3
Ammonium Acetate (New product),
4-OCTYNE 1-OL (New product)
Final solutions obtained from scrubbers and their disposal:
Quantity of 30-35% HCl Solution generated from scrubbing of HCl after proposed expansion shall be self consumed as far as possible and sold to actual users and if total quantity is not sold, it shall be converted partially or totally to 30% Calcium chloride (CaCl2) solution OR Calcium chloride (CaCl2) Solid by reacting with either slaked lime or calcium carbonate.
CaCl2 solution OR CaCl2 solid so obtained shall be sold to authorized actual users.
About 30 % Sodium Bromide solution obtained from scrubbing of HBr shall be sold as by-product to authorized actual users.
About 25 % sodium sulfate obtained from scrubbing of SO2 shall be sold as by-product to authorized actual users or shall be dried and sent to TSDF site.
About 20-25% Ammonia solution obtained from scrubbing of NH3 shall be sold as by-product to authorized actual users.
iii Fugitive emission details with its mitigation measures.
Sr. No.
Probable sources Proposed Control measures
1. Pump glands and seals
All pumps handling HAP chemicals with low V.Ps will be with mechanical seals ensuring no emissions.
2. During reactions & Solvent recovery systems
All reactors shall be closed and provided with main condenser with cooling water circulation and vent condensers with chilled water circulation for maximum vapor recovery Solvent recovery of minimum 95% is achieved Temperature and pressure conditions shall be stringently controlled as per the process requirement and optimized with low temperature and vacuum conditions wherever feasible.
3. Release from Sampling Lines
Shall be carried out using a closed loop sampling system.
4. Valves, Flanges, plugs and instrument connections
Welded pipes to be used wherever feasible Suitable gasket material to be used Suitable gland packing to be used in valves Periodic inspection and maintenance of pipes and pipe fittings
5. Chemical vapors during filtration and
Covered systems to be adopted, workers shall be provided PPE, dust extraction systems, local exhausts and roof top
Page 35 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 35 of 93
drying process ventilators, wherever required
6. Drum filling machinery
Covered systems to be adopted, workers shall be provided PPEs, minimum manual operations, local exhausts and roof top ventilators
7. Warehouse storing drums and bags
Spillages shall be strictly prevented by providing drip pans, proper handling equipment, Spill control procedures and equipment shall be provided
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016. Existing & Proposed
i
Sr. No.
Type of Waste
Category (As Per
Sc)-2016
Quantity Per Annum
Source of Generation
Mode of storage
Mode of Treatment &
Disposal
CTO available
Sagar Life
Sciences Pvt. Ltd.
NOC Availab
le (After EC)
Sagar Life
Sciences Pvt.
Ltd.
CTO Available for
Rajeev Chlorid
e &
Carbonics Pvt.
Ltd.
CTO Amendment
Applied
(Total both units after
merge)
1.
Neutralized
Process Sludge
35.3 250 MT -- -- 250 MT
Manufacturing process
Stored in drums / bags in
separate place (Shed with RCC
flooring)
Collection, storage,
transportation and disposal at common
TSDF site of M/s. BEIL,
Ankleshwar
2.
Discarded
Container
Bags/ Liners
33.1 650 Nos.
10 MT 120 MT
Discarded
bags - 2400 Nos. (1.20 MT) & Drums - 180 Nos. (3.60 MT)
784.8 MT
Raw material
container
s / bags
Stored in covered
shed with RCC
flooring
Collection, storage,
decontamination and reuse
3. Used
Oil 5.1 -- 0.1 MT
10.00 MT
10.1 MT
From
machiner
y
Stored in drums
separate area (shed with RCC
flooring)
Collection, Storage,
Transportation & sale to MoEF&CC authorized
reprocessor
Page 36 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 36 of 93
4. Spent
Catalyst 28.2 -- 12 MT -- 12 MT
Manufacturing process
Stored in drums / bags in
separate place (Shed with RCC
flooring)
Collection, storage,
transportation and sent to supplier for
regeneration or
Incineration at CHWIF of M/s. BEIL -Ankleshwar
5.
Distillation
residue 20.3 --
139 MT
-- 139 MT
Manufacturing process
Stored in drums in separate
place (Shed with RCC
flooring)
Collection, storage,
transportation and sent for
co-processing or Incineration at CHWIF of M/s. BEIL -Ankleshwar
6.
Inorganic Salt/
Inorganic Waste
28.1 -- 52 MT
/ 32 MT
-- 52 MT / 32 MT
Manufacturing process
Stored in drums / bags in
separate place (Shed with RCC
flooring)
Collection, storage,
transportation and disposal at common
TSDF site of M/s. BEIL, Ankleshwar
7.
30 % HCl / 30
% CaCl2
Solution / CaCl2 Solid
B15/B10 --
43.2 MT /
66 MT/ 20 MT
--
43.2 MT /
66 MT/ 20 MT
Manufacturing process
Stored in drums / bags in
separate place (Shed with RCC
flooring)
Collection, storage
Error! Reference source not
found.
8.
30% NaBr
Solution -- --
698.4 MT
-- 698.4 MT
Manufacturing process
Stored in drums in separate
place (Shed with RCC
flooring)
Collection, storage,
transportation and sell to authorized
actual users.
Page 37 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 37 of 93
9.
Methyl Benzoat
e -- --
9.96 MT
-- 9.96 MT
Manufacturing process
Stored in drums / bags in
separate place (Shed with RCC
flooring)
Collection, storage,
transportation and sell to authorized
actual users.
10.
P4O10/ Phosph
oric Acid
B15 -- 170.4 MT
-- 170.4 MT
Manufacturing process
Stored in drums in separate
place (Shed with RCC
flooring)
Collection, storage,
transportation and sell to authorized
actual users.
11. Na2SO4 Solution
-- -- 7071 MT
-- 7071 MT
Manufacturing process
Stored in drums in separate
place (Shed with RCC
flooring)
Collection, storage,
transportation and sell to authorized
actual users.
12.
20-25% Ammoni
a solution
A10 -- 151.66
MT --
151.66 MT
Manufacturing process
Stored in drums in separate
place (Shed with RCC
flooring)
Collection, storage,
transportation and sell to authorized
actual users.
13. Lime Stone
-- -- -- 20.00 MT
20.00 MT
From
Process
Collection,
Generation,
Disposal, Storage Transpor
tation
Sent to common
TSDF of M/s. BEIL,
Ankleshwar
14.
Sludge containing Zinc
6.1 -- -- 2.00 MT
2.00 MT
From
Process
Collection,
Generation,
Disposal,
Storage, Transpor
tation
Sent to common
TSDF of M/s. BEIL,
Ankleshwar
Page 38 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 38 of 93
15.
20% Sodium Nitrate
Solution
C13 -- -- 15.00 MT
15.00 MT
From
Process
Collection,
Generation,
Disposal,
Storage, Transpor
tation
Sodium Nitrate
Solution (20%) -
Disposal by sale out to authorized users who are having
authorization with valid CCA and
Rule 9 permission to receive this
waste
ii Membership details of TSDF, CHWIF etc. (For HW management)
Unit has membership of M/s. Bharuch Enviro Infrastructure Ltd. (BEIL) – Ankleshwar TSDF site for disposal. NOC is obtained for additional quantities of land filling wastes to be generated after proposed expansion. NOC is also obtained for incinerable waste disposal at CHWIF of M/s. BEIL. M/s. Sagar Life Science Pvt. Ltd. will try to send maximum waste to co-processing and / or recycling and / or recovery and balance quantity will be sent to common disposal or incineration facility. Unit will obtain membership of M/s. BEIL, Ankleshwar for co-processing.
iii Details of Non-Hazardous waste & its disposal(MSW and others)
Fly ash: 300 MT/Annum shall be sold to brick manufacturers or manufacturers of Cement articles or products
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
• Solvent recovery shall be done by distillation assembly provided on reaction vessels. After the reaction the un-reacted solvent shall be recovered by distillation and reused in next batch. Distillation assembly comprises of packed column, condensers with cooling water and chilled water circulation to obtain minimum 95% recovery. The plant shall be provided with adequate instrumentation to control distillation process and minimize solvent losses.
ii VOC emission sources and its mitigation measures
Handling of chemicals will be in closed system. Primary and secondary condensers are proposed.
• During the meeting dated 22/01/2019, technical presentation made during the meeting by project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report, various
issues raised during the public hearing and details presented during the meeting.
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
Page 39 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 39 of 93
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• During SEAC meeting on 22/01/2019, committee noted that the proposal is for amendment. PP mentioned that
EC amendment is for merger of M/s. Sagar Life Sciences Pvt. Ltd. (Plot No. 3045) and M/s. Sagar Life
Sciences Pvt. Ltd. (Earlier known as Rajeev Chlorides & Carbonics Pvt. Ltd. (Plot No. 3124 & 3125)). This unit
has valid CC&A for existing unit. Copy of CC&A, its compliance report is submitted. Unit has submitted
Certified Compliance Report from RO-Bhopal. PP ensured that there are no court cases pending and no public
complaints against the project. PP mentioned that there is no change in water consumption or waste water
generation. PP mentioned that there is no any change in process or flue gas stack or Hazardous waste.
After detail deliberation the committee unanimously decided to recommend the proposal for grant of EC –
Amendment to SEIAA.
12 SIA/GJ/IND2/200005/2017 M/s. Sahaj Industries
Plot No. 99/B, GIDC, Nandesari, Vadodara
– 391340.
Appraisal
Category of the unit : 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/200005/2017 dated 19/1/2018 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated 31/1/2018.
• Project proponent has submitted EIA Report prepared by RAAS Envirocare based on the TOR issued by
SEIAA.
• This is a new unit proposes manufacturing of synthetic organic chemicals as tabulated below:
Sr.
No.
Name of the
Products
CAS no. /CI no. Quantity
MT/Month
End-use of products
1 4- Nitro 2- Amino
Phenol OR 99-57-0
50
Dye and Dye
intermediates
2 Pyridone
Carbonyl Amide 29097-12-9
2 Meta Ureido
Aniline
59690-88-9 105
Total 155
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 22/01/2019.
• Salient features of the project are as under:
Page 40 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 40 of 93
Sr.
no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Rs. 2.9 Crores
B Total Plot area ( sq. meter)
2341 Sq. m.
Green belt area
( sq. meter)
600 Sq. m.
C Employment generation
65
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC Water Supply
Status of permission from the concern authority.
Permission has been
obtained
ii
Water consumption (KLD)
Category
Quantity
KLD
Remarks
(M) Domestic 12.0
(N) Gardening 4.0
(O) Industrial
Process 100.0
Washing --
Boiler 14.0
Cooling 20.0
Others --
Industrial Total 134.0
Total (A + B + C) 150.0
13) Total water requirement for the project: 150 KLD
14) Quantity to be recycled: 0.0 KLD
Page 41 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 41 of 93
15) Total fresh water requirement: 150.KLD
iii
Waste water generation (KLD)
Category Waste water
KLD
Remarks
(I) Domestic 10.0
(J) Industrial
Process 96.0
Washing --
Boiler 1.5
Cooling 2.5
Others --
Total Industrial
waste water
100
Total [A + B] 110
-
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP
etc..
The Waste water will treated in in-house ETP. The treatment scheme is based on the
treatment process provided by the CETP authorities of NIA. The treatment is based on
hydrodynamic cavitation based treatment. The Capacity of the treatment plant is to treat 125
KL/day.
v Mode of Disposal & Final meeting point
Domestic:
Soak Pit or CETP
Industrial:
The waste water after treatment in inhouse ETP is sent to the CETP of
NIA as per the CETP Norms
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE
etc. , Name of CF
CETP, Nandesari Industries Association
Membership of Common facility (CF)
Page 42 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 42 of 93
(For waste water treatment)
Membership taken
vii Simplified water balance diagram with reuse / recycle of waste water
viii Reuse/Recycle details (KLD) : No Recycle
Total reuseCC.KLD
Source of waste
water for reuse
with quantity in
KLD
Application area with
quantity in KLD
Remarks
regarding
feasibility to
reuse i.e. w/w
characteristics
(COD, BOD,
TDS etc.)
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr,
KVA etc.
-
Page 43 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 43 of 93
Sr.
no.
Source
of
emission
With
Capacity
Stack
Height
(meter)
Type
of
Fuel
Quantity
of Fuel
MT/Day
Type of
emissions
i.e. Air
Pollutants
Air
Pollution
Control
Measures
(APCM)
1 Proposed Boiler (1 MT/hr)
20 mts Natur
al gas
75
Nm3/hr
NOx, PM Adequate
Stack
height will
be
provided
-
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
-
Sr.
no.
Specific
Source of
emission
(Name of
the
Product &
Process)
Type of
emission
Stack/Vent
Height
(meter)
Air Pollution
Control
Measures
(APCM)
1 There are no Process Emissions
-
iii Fugitive emission details with its mitigation measures.
As below:
Vent gas condenser with chilled water circulation will be provided
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
i
Page 44 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 44 of 93
Sr.
no.
Type/Name
of
Hazardous
waste
Specific
Source of
generation
(Name of
the
Activity,
Product
etc.)
Category
and
Schedule
as per HW
Rules.
Quantity
(MT/Annum)
Management
of HW
1 ETP Sludge ETP 35.3 1200 MT/Yr Collection,
Storage,
transportatio
n and
disposal at
TSDF, NECL
for landfilling
2 Process
waste Sludge
Process 26.1 50 MT/Yr Collection,
Storage,
transportatio
n and
disposal at
TSDF, NECL
3 Used Oil Pumps,
Gearbox
etc
5.1 0.5 MT/Yr Applied on
MS structure
for corrosion
control or will
be sent to
NECL for
incineration
4 Liner Bags &
discarded
container
Raw /
Inprocess
Material
33.3 20 MT/Yr Collection,
Storage,deco
ntamination
within factory
premises and
sold to
authorized
scrap dealers
Page 45 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 45 of 93
-
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Membership of TSDF of
NECL, Nanadesari has
been taken
iii Details of Non-Hazardous waste & its disposal
(MSW and others)
Domestic Waste generated
by the unit is picked up
daily by truck organized by
NIA and sent to common
domestic waste disposal
site.
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered
Solvents
• Mono ethyl amine – used as reactant
ii VOC emission sources and its mitigation measures
• From storage area, tank farm – Vent gas condenser with chilled water circulation
will be provided
• Technical presentation was made by the project proponent dated 22/01/2019.
• During the meeting, the project was appraised based on the information furnished in the EIA Report, various
issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted for
the study area of 10 km radial distance from project site for the period March 2017 to May 2017. Ambient Air
Quality monitoring was carried out for PM10, PM2.5, SO2, NOx, Cl2, NH3 & VOC at ten locations, including
the project site. Values conform to the prescribed standards for Ambient Air Quality. The incremental Ground
Level Concentration (GLC) has been computed using ISCST3. The resultant concentrations are within the
NAAQS. The ambient air quality around the proposed project site will remain within the National Ambient Air
Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• During SEAC meeting on 22/01/2019,
After deliberation, SEAC unanimously decided to consider the proposal after submission of the following
details.
Page 46 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 46 of 93
1. To carry out detailed study on process water consumption and Effluent generation in Existing stage and
Expansion stage.
2. Technical Justification of Non Increase in water consumption & Effluent Generation in proportion with
Expansion of Production.
3. Properly address Hazardous Waste and its disposal as per HWR – 2016.
4. Properly address Recycle/Reuse of treated w/w along with quantity and quality.
13 SIA/GJ/IND2/30158/2018 M/s. Maitri Pharma
Plot 25/10, GIDC, Nr. Pepsico India Pvt.
Ltd. Industrial Estate, Dist. Bharuch -
Gujarat.
Screening & Scoping
Category of the unit : 5(f)
Project status: New
• This office has received an application vide their online proposal no. SIA/GJ/IND2/30158/2018 dated
09/01/2019 made by project proponent (PP) regarding grant of Terms of Reference [ToR] for preparation of
EIA/EMP report.
• This is a new unit proposes manufacturing of synthetic organic chemicals as tabulated below:
Sr.
No.
Name of the
Products
CAS no. /CI no. Quantity
MT/Month
End-use of products
1 Pharma
Intermediates
--- 5
Cinnamyl aldehyde
104-55-2 Either / OR Flavouring agent agent
inchewing gum, beverages
m-Phenoxy benzyl alcohol
13826-35-2 used as active in pharmaceutical products
P-anisaldehyde/ 4-methoxy benzaldehyde
123-11-5 fragrance and flavor industry.
4-Chlorobenzophenone
134-85-0 UV curing type coating, printing ink, medical
2-[4-(4-cyclopropyl carbonyl phenyl]-2-methyl propionic acid cyclohexyl amine salt
153439-40-8 Fexofenadine Intermediate API (anti allergic )
N-(2-chloro-4-methyl-3-pyridinyl)2-(cyclopropyl amine)-3-pyridinecarboxamide
133627-46-0 Nevirapine API ( anti HIV drug)
Page 47 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 47 of 93
Trans-4-(2-amino-3,5-dibromobenzylamino)cyclohexanol hydrochloride
27489-62-9 Ambroxole Hydrochloride API ( for respiratory disease)
2 Fine Chemical 20
Benzyl alcohol 100-51-6 Used as bacteriostatic in
medications, cosmetics
and topical drugs
3 Anti allergic 1
2-[4-[4-
chlorophenyl)phe
nyl methyl [1-
piperazinyl]
ethoxy] acetic
303-26-4
Cetrizine API (anti allergic )
4 Dye
Intermediates
5
4-chlorophthalic acid mono sodium salt
56047-23-5 Either / OR Dyes intermediate
Phenyl peri acid magnasium salt
18108-68-4 Dyes intermediate
Total 31
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 22/01/2019.
• Salient features of the project are as under:
Sr
.
n
o.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
0.97 Crores
B Total Plot area ( sq. meter)
2139.68 Sq. m.
Green belt area
( sq. meter)
753 Sq. m.
C Employment generation 20
Page 48 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 48 of 93
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC Jhagadia
Status of permission from the concern authority.
80 KLD water permission
given by GIDC Jhagadia
Unit will use only 20.5
KLD
ii
Water consumption (KLD)
Category
Quantity
KLD
Remarks
(P) Domestic 5
(Q) Gardening 3
(R) Industrial
Process 5.5
1.8 KLD will be recycle in
process
Washing 2.5
Boiler 1
Cooling 2.5
Others 1 Water use for Scrubbing
Industrial Total 12.5
Total (A + B + C)
20.5
Total Fresh Water -18.7
KLD & Recycled Water –
1.8 KLD
16) Total water requirement for the project: 20.5 KLD
17) Quantity to be recycled: 1.8 KLD (Internal Recycled)
18) Total fresh water requirement: 18.7 KLD
iii
Waste water generation (KLD)
-
Category Waste water
KLD
Remarks
Page 49 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 49 of 93
(K) Domestic 4 Disposed through
Soak pit
(L) Industrial
Process 6.9 Treated in to VOC
removal reactor &
Single stage
evaporator then
send to ETP
Washing 2.5
Boiler 0.02
Cooling 0.1
Others 1.4 Scrub Solution HCl
, Na2SO4 &
Ammonium
Sulphate will be
generated and
treated in to in
house ETP
Total Industrial
waste water
10.92
Total [A + B] 14.92
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
ETP capacity 20 KLD followed by Sand filter and Activated Carbon filter & VOC
removal reactor followed by Single stage Evaporator having 10 KLD capacity.
v Mode of Disposal & Final meeting point
Domestic:
Dispose in Soak pit
Industrial:
Concentrated effluent will be treated in to VOC
removal reactor and pass through Single stage
Evaporator then it will be collected in to collection cum
equalization tank plus waste water from washing,
scrubber, cooling tower blow down, boiler blow down
will also collected in to same cum equalization tank
and treated in to in house ETP followed by sand filter
and Activated carbon filter after that 10 KLD waste
water send to NCT
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. ,
Name of CF
Page 50 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 50 of 93
Narmada Clean Tech
Membership of Common facility (CF)
(For waste water treatment)
vi
i
Simplified water balance diagram with reuse / recycle of waste water
Page 51 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 51 of 93
Note:
*Scrub solution will be Na2SO4 , HCl & Ammonium sulphate
vii
i
Reuse/Recycle details (KLD)
Total reuse 1.8 KLD
Source of waste water for
reuse with quantity in
KLD
Application
area with
quantity in
KLD
Remarks regarding feasibility to
reuse i.e. w/w characteristics (COD,
BOD, TDS etc.)
In production process of
Benzyl alcohol - 1.8
(Distilled water)
In same
product
Water recover from distillation process
it will be distilled water.
(BOD- Nil, COD-Nil, TDS -10-15 mg/l)
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr,
KVA etc.
-Sr.
no.
Source of
emission
With
Capacity
Stack
Height
(meter)
Type
of Fuel
Quantity
of Fuel
MT/Day
Type of
emissions
i.e. Air
Pollutants
Air
Pollution
Control
Measures
(APCM)
01 Steam
Boiler
12 Bio Coal
1 MT /day
PM SO2 NOX
Bag Filter
Page 52 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 52 of 93
1 TPH
02 Thermic Fluid Heater 2 Nos. (0.5 lac Kg Cal/hr.)
Natural Gas
1080 Nm3/day
Adequate Stack Height
03 DG Set
125 KVA
09 Diesel
3.120 KL/ day
Adequate Stack Height
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
-
Sr.
no.
Specific Source of emission
(Name of the Product &
Process)
Type of
emission
Stack/Vent
Height
(meter)
Air Pollution
Control
Measures
(APCM)
1
4-Chlorobenzophenone,
Trans-4-(2-amino-3,5-
dibromobenzylamino)cyclohexanol
hydrochloride
SO2
HCl 17
Water
Scrubber
Followed by
Alkali
Scrubber 2
2-[4-(4-cyclopropyl carbonyl
phenyl]-2-methyl propionic acid
cyclohexyl amine salt,
HCl 17
3 Phenyl peri acid magnasium salt Ammonia 17 Acid
Scrubber
-
iii Fugitive emission details with its mitigation measures.
As below:
Sr. No.
Source Probable Pollutant
Emission
Control Measures/ APCM
FUGITIVE EMISSION
1 Solvent recovery system
Air pollutant (VOC)
• Solvent recovery system with steam condensation system.
• Pumps & motors are mechanical seal type.
2 Handling of raw material bags in storage area
Air pollutant (PM)
• Provision of exhaust ventilation
• Provision of PPE.
Page 53 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 53 of 93
• Provision of Job rotation to reduce exposure.
3 Flange joints of pipeline, pump & motors
Air pollutant (VOC)
• Routine &periodic inspection to check leakage.
• Preventive maintenance, Follow SOP for maintenance.
• Pumps & motors will be mechanical seal type.
• LDAR program will be followed.
• Provision of Flange guard.
4 Solid raw material transferring to reactor
Air pollutant (PM)
Hopper will be provided with powder transfer system.
5 Liquid raw material transferring to reactor
Air pollutant (VOC)
• Feeding of liquid raw material will be carried out by closed pipeline and mechanical seal pump.
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
Page 54 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 54 of 93
i
Sr. no.
Type/Name of
Hazardous waste
Specific Source of
generation
(Name of the Activity, Product
etc.)
Category and
Schedule as per
HW Rules.
Quantity
(MT/Annum)
Management of HW
1 Effluent Treatment Plant Sludge
From ETP 35.3 305 Collection, Storage & Send to TSDF for landfilling
2 Evaporator Salt
From Single stage Evaporator
35.3 4 Collection, Storage & Send to TSDF for landfilling
3 Used Oil From Lubrication 5.1 0.6 Collection, Storage, Sold to MoEF Approved Vendors.
4 Empty Barrels/ Containers/ Liners Contaminated with hazardous chemicals/ wastes
From Packing Material
33.1 14 Collection, Storage, decontamination, Sold to GPCB, approved Vendors
5 Process
Residue and
wastes
/ Distillation
Residue
Production process
of m-Phenoxy
benzyl alcohol
28.1 4 Collection,
Storage, Send
for co-
processing /
Incineration
6 NaCl Salt Generated from
manufacturing of
benzyl alcohol
28.1 148 Collection,
Storage &
Send to TSDF
for landfilling
7 Spent Carbon (From ETP )
Activated Carbon filter
28.3 1 Collection,
Storage, Send
for co-
processing /
Incineration
8 Spent Carbon Solvent Recovery System
Carbon tower of Solvent recovery System
28.3 1 Collection,
Storage, Send
for co-
processing /
Incineration
9 Spent Solvent
From Production process & VOC
28.6 35 Collection,
Page 55 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 55 of 93
removal reactor Storage, Send
for co-
processing /
Incineration
Date-expired products
From premises 28.5 50 Collection,
Storage, Send
for co-
processing /
Incineration
10 Off specification products
Production process 28.4 50
Collection,
Storage, Send
for co-
processing /
Incineration
11 Spent catalyst
Production process of Benzyl alcohol and or 4-Chlorobenzophenone
28.2 4 Collection, Storage, Send for authorised regenerator
12 Scrubbed Solution Na2SO4 10% to 20 %
Scrub solution will be generates from 4-Chlorobenzophenone
C2 200 Send to ETP for treatment.
13 Scrubbed Solution HCl 10% to 20 %
Scrub solution will be generates from 4-Chlorobenzophenone
C2 160 Send to ETP for treatment.
14 Scrubbed Solution HCl 30%
Scrub solution generates from 2-[4-(4-cyclopropyl carbonyl phenyl]-2-methyl propaonic acid cyclohexylamine salt
C2 252 Recycle in same product process
15 Scrubbed Solution Ammonium sulphate 10% to 20 %
Scrub solution generates from Phenyl peri acid magnasium salt
C2 160 Send to ETP for treatment
16 Spent Sulphuric acid 25% to 30%
Scrub solution generates from P-anisaldehyde/ 4-methoxy benzaldehyde
C2 250 Send to Actual end user under Rule-9 / use in ETP for treatment
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Unit will apply for
membership for
Page 56 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 56 of 93
membership of TSDF
and incineration.
iii Details of Non-Hazardous waste & its disposal
(MSW and others)
MSW waste will be collected by notified authority of GIDC
Sr. No.
Waste Quantity Mode Of Disposal
1. Glass Waste ( Z 13) 0.1 MT/month To TSDF.
2. Paper waste (Z44) 0.5 MT/month At notified area facility.
3. Bio-Medical Waste 0.05 MT/month
Will be disposed off as per Bio Medical Waste Rules.
4. Wooden Waste 2 MT/month Authorized Scrap Vendors.
5. Used Batteries 0.1 MT / month Authorized Scrap Vendors.
6 Fly Ash 3 MT / Month Send to authorize Brick manufactures
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered
Solvents
• Unit will recover more than 96 % solvent. Unit will also follow solvent recovery
guideline.
ii VOC emission sources and its mitigation measures
• Provision of mechanical seal in pump.
• Regular inspection of tank roof seals.
• Adequate measures for the minimization/prevention of the fugitive emission.
• Regular maintenance of valves, pumps and other equipment to prevent leakage.
• Entire process to be carried out in the closed reactors with proper maintenance of
temperature.
• Regular periodic monitoring of work area to check the fugitive emission.
• Adequate stack heights as per the CPCB estimation will be provides at all locations to
reduce GLCs of pollutants.
• Air Pollution Control System will be installed in the plant.
• Technical presentation was made by the project proponent dated 22/01/2019.
• Committee noted that proposal is new in GIDC Jagadia. Source of water is GIDC. PP informed that Process
Effluent generated will be passed through VOC Removal Reactor followed by single stage evaporator,
Condensate water will be treated in in-house ETP consisting of primary & tertiary treatment and salt will be
sent to TSDF. Effluent generated from washing, scrubber (Bleed Liquor), boiler blow down & cooling tower will
Page 57 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 57 of 93
be treated in in-house ETP along with condensate, finally all the treated w/w will be disposed of into deep sea
via NCT pipeline of Jagadia Pipeline Project. PP has proposed one steam boiler & TFH. Fuel used will be Bio-
Coal/Natural Gas respectively. PP has satisfactorily addressed adequate measures for hazardous waste
management.
• Considering the above project details, after detailed discussion, the terms of reference (ToR) were prescribed
as below and as per the standard TOR for the Synthetic Organic Chemical projects recommended by SEAC
vide letter no. EIA-10-GEN-21/1480 dated 14/09/2017 and approved by SEIAA in its 12th meeting dated
16/09/2017 for the EIA study to be done covering 10 Km radial distance from the project boundary.
1. Compliance of MoEFCC’s OM dated 01/05/2018 regarding “Corporate Environment Responsibility”
(CER). Fund allocation for Corporate Environment Responsibility (CER) shall be made as per
MoEFCC’s O.M. No. 22-65/2017-IA.III dated 01/05/2018 for various activities therein. The details of
fund allocation and activities for CER shall be incorporated in EIA/EMP report.
2. Explore the use of renewable energy to the maximum extent possible. Details of provisions to make the
project energy-efficient through energy efficient devices and adoption of modes of alternative eco-
friendly sources of energy like solar water heater, solar lighting etc. Measures proposed for energy
conservation.
3. PP shall address spent solvent with details of storage, handling and re-use under the Hazardous and
other Waste (Management and Transboundary Movement) Rules 2016.
4. Leak Detection and Repairing Programme (LDAR) for all the volatile organic solvent proposed for use
in-house with detailed chemical properties including vapor pressure. LDAR shall endeavor prevention
of losses of solvents to the best minimum extent.
5. PP shall furnish status of all the applicable rules, acts, regulation, clearances in a tabular form
6. Safety precautions including flame proof electric fittings to be taken to avoid fire hazard during
unloading, storage, transportation, handling and processing of Solvents
7. Segregation of waste water streams based on characteristics and its proper management keeping in
view direction under section 18 (1) (b) of the Water (Prevention and Control of Pollution) act, 1974
issued by CPCB regarding compliance of CETP.
8. Treatability & adequacy report for complete ZLD for additional waste water. Feasibility report for
complete reuse condensate waste water for industrial purpose.
9. Adequacy of in house utilization of dilute HCl, in house recovery and management of spent solvent
shall be addressed
• The TOR prescribed as above and as per the standard TOR approved by SEIAA and the model ToRs
available in the MoEFCC’s sector specific EIA Manual for ‘Synthetic Organic Chemical Industry’ shall be
considered as generic TORs for preparation of the EIA report in addition to all the relevant information as per
the generic structure of EIA given in Appendix III in the EIA Notification, 2006.
Page 58 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 58 of 93
• The project proponent shall have to apply for Environmental clearance through online portal
http://environmentclearance.nic.in/ along with final EIA report.
14 SIA/GJ/IND2/30492/2018 M/s. Multi Colour chem
PLOT NO. A- 2/410, Phase No. – II,
Vatva, Ahmedabad.
Screening & Scoping
Category of the unit : 5(f)
Project status: Expansion
• This office has received an application vide their online proposal no. SIA/GJ/IND2/30492/2018 dated
09/01/2019made by project proponent (PP) regarding grant of Terms of Reference [ToR] for preparation of
EIA/EMP report.
• This is a new unit proposes manufacturing of synthetic organic chemicals as tabulated below:
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 22/01/2019.
• Salient features of the project are as under:
Sr. no.
Particulars Details
A Total cost of Proposed Project (Rs. in Crores):
Existing: 1.0 Cr. Proposed: 1.0 Cr. Total: 2.0 Cr.
B Total Plot area ( sq. meter)
Existing: 1919 Sq. m.
Green belt area ( sq. meter)
Proposed: 50 Sq. m
C Employment generation 20
D Water
i
Source of Water Supply (GIDC Bore well, Surface water, Tanker supply etc...)
GIDC Water
Status of permission from the concern authority.
ii Water consumption (KLD)
Category Existing Additional Total
SR. NO
PRODUCT NAME CI Name/CAS
No.
Quantity MT/Month End-use of the
products Existing Proposed Total
1. Reactive Black B 17095-24-8
NIL 120 120
Textile and Colour
Industries 2. Reactive Orange 3R 20262-58-2 3. Reactive Red CD ---
4. Reactive Yellow FG 12226-63-0
5. Job work of spray drying -- 20 -- 20
TOTAL 20 120 140
Page 59 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 59 of 93
(A) Domestic Purpose 0.3 NIL 0.3
(B) INDUSTRIAL
Process NIL 7.2 7.2
Washing 2.5 1.0 3.5
Boiler NIL 2.0 2.0
Cooling NIL 2.0 2.0
Total water Consumption (Industrial )
2.5 12.2 14.7
Grand Total (A+B) 2.8 12.2 15.0
19) Total water requirement for the project: 15.0 KLD 20) Quantity to be recycle: NIL 21) Total fresh water requirement: 15.0 KLD
iii Waste water generation (KLD)
Category Existing Additional Total
(A) Domestic Purpose 0.2 NIL 0.2
(B) INDUSTRIAL
Process water NIL NIL NIL
Washing 2.3 1.0 3.3
Boiler NIL 0.2 0.2
Cooling NIL 0.2 0.2
Total Waste water Generation (Industrial)
2.3 1.4 3.7
iv Treatment facility within premises with capacity [For existing and Proposed] [In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc. Existing
Sr. No.
Name of Unit Capacity
1 Collection Tank 2 Nos. 6 m3
2 Neutralization Tank 10 m3
3 Settling Tank 10 m3
4 Holding Sump 10 m3
5 C.E.T.P Overhead Tank 30 m3
6. R. O. Plant Proposed 4 KLD
7 Sludge Drying Bed 1.5×1.5 (4 Nos.)
Proposed
Sr. No.
Name of Unit Capacity
1 Collection Tank 2 Nos. 6 m3 and 10m
2 Neutralization Tank 10 m3
3 Settling Tank 25 m3 and 10 m
4 Holding Sump 7.5 m3 and 10 m
5 C.E.T.P Overhead Tank 30 m3
Page 60 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 60 of 93
6. R. O. Plant Proposed 4 KLD
7 Sludge Drying Bed 1.5×1.5 (4 Nos.)
v Mode of Disposal & Final meeting point
Domestic: The generated sewage will be disposed through soak pit/septic tank.
Industrial: The Total Industrial 3.7 KLD Waste Water Generation From Manufacturing Process and Other Ancillary Operation, In Which 1.4 KLD Waste Water Discharge Though In House Spray Dryer and Remaining 2.3 KLD Waste Water Treated in Primary and Secondary Effluent Treatment Plant and send to CETP For their Treatment.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE, CHWIF etc. Name of Common facility
-Not Applicable
Membership of Common facility (CF)
(For waste water treatment)
vii Simplified water balance diagram with reuse / recycle of waste water
Exisiting
After Expansion Water Balance Diagram
Page 61 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 61 of 93
vii Reuse/Recycle details (KLD) [Source of reuse & application area]
Total reuse NIL
E Air
i Flue gas emission details No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc. Existing & Proposed
Sr.
no
Stack attached
to
Stack heigh
t in meter
Type of Fuel
Consumption
Type of emissio
n APCM
Remarks
1 Steam
Boiler (1 TPH)
11 Imported Coal
5 MT/Day
PM SOx NOx
Cyclone separato
r
Proposed
2
Hot Air Generato
r-1 (8 Lac
KCl/hr)
11 Imported Coal
5 MT/Day
Multi cyclone
Dust Collecto
r and Bag Filter
Existing
3
Hot Air Generato
r -2 (8 Lac
KCl/hr)
11 Imported Coal
PM SOx NOx
Multi cyclone
Dust Collecto
r and Bag Filter
Existing
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Page 62 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 62 of 93
Existing & Proposed
-
Sr no
Stack attached to
Stack height in
meter APCM
Type of Emission
Remarks
1. Spray Dryer (500 LPH)
15.0 Cyclone
separator Followed By ventury type
Water Scrubber
PM Existing 2.
Spray Dryer (700 LPH)
15.0
iii Fugitive emission details with its mitigation measures.
� The entire manufacturing activities will be carried out in the closed reactors and regular checking and maintenance of reactors will be carried out to avoid any leakages.
� The tank vents will be equipped with either a carbon filter or an oil trap to prevent water vapor from entering the tank as it breathes.
� Control of all parameters on a continuous basis will be done by adequate control valves, pressure release valves and safety valves etc.
� All the flange joints of the pipe lines will be covered with flange guards. � All the raw materials will be stored in isolated storage area and containers tightly
closed. � There will also be provision of adequate ventilation system in process plant and
hazardous chemical storage area
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016:
i Sr. No
Types of Hazardo
us Waste
Specific Source
of generati
on
Category
Existing
MT/Year
Additional
MT/Year
Total MT/Ye
ar
Management of HW
1 ETP
Sludge ETP Area
35.3 6.00 5.00 11.00
Collection, storage,
Transportation and
Dispose to TSDF
2 Used Oil Plant
Machinery
5.1 0.05 0.45 0.5
Collection, storage,
Reuse within premises.
3
Discarded
Container and Bag
Material Storage
and Handling
33.1 NIL 200.00 200.00
Collection, storage,
Transportation and
Reuse/Dispose to
Authorized Reprocessor
ii Membership details of TSDF, CHWIF etc. (For HW management)
Yes
iii Details of Non-Hazardous waste & its disposal(MSW and others)
No
G Solvent management, VOC emissions etc.
Page 63 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 63 of 93
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
� There is no any type of solvent required
ii VOC emission sources and its mitigation measures
• Sources of fugitive emissions include storage of chemicals, solvents storage, loading and unloading section, raw material handling and, hazardous waste storage area
Measures : • The fugitive emissions in terms of handling losses will get reduced by proper storage
and handling.
• Hazardous chemicals will be stored as per standard criteria. • Periodically monitoring will be carried out as per the post project monitoring plan.
• All materials must be stored in suitable packing to prevent contamination of air.
• Enclosed system & efficient procedures for materials charging shall be ensured.
• During the meeting dated 22/01/2019, technical presentation made by project proponent.
• Committee noted that unit has valid CC&A for existing unit. Unit is complying conditions of CC&A. PP informed
that there are no court cases pending and no public complaints against the project. It is noted that after
expansion existing treated waste water will be sent to CETP with no change in quality and proposed additional
waste water will be sent to in-house existing spray dryer. Committee noted that PP has proposed one steam
boiler. Fuel used will be imported coal. PP has satisfactorily addressed adequate measures for hazardous
waste management.
• Considering the above project details, after detailed discussion, the terms of reference (ToR) were prescribed
as below and as per the standard TOR for the Synthetic Organic Chemical projects recommended by SEAC
vide letter no. EIA-10-GEN-21/1480 dated 14/09/2017 and approved by SEIAA in its 12th meeting dated
16/09/2017 for the EIA study to be done covering 10 Km radial distance from the project boundary.
1. Compliance of MoEFCC’s OM dated 01/05/2018 regarding “Corporate Environment Responsibility”
(CER). Fund allocation for Corporate Environment Responsibility (CER) shall be made as per
MoEFCC’s O.M. No. 22-65/2017-IA.III dated 01/05/2018 for various activities therein. The details of
fund allocation and activities for CER shall be incorporated in EIA/EMP report.
2. Explore the use of renewable energy to the maximum extent possible. Details of provisions to make the
project energy-efficient through energy efficient devices and adoption of modes of alternative eco-
friendly sources of energy like solar water heater, solar lighting etc. Measures proposed for energy
conservation.
3. PP shall address spent solvent with details of storage, handling and re-use under the Hazardous and
other Waste (Management and Transboundary Movement) Rules 2016.
4. Leak Detection and Repairing Programme (LDAR) for all the volatile organic solvent proposed for use
in-house with detailed chemical properties including vapor pressure. LDAR shall endeavor prevention
of losses of solvents to the best minimum extent.
5. PP shall furnish status of all the applicable rules, acts, regulation, clearances in a tabular form
6. Safety precautions including flame proof electric fittings to be taken to avoid fire hazard during
unloading, storage, transportation, handling and processing of Solvents
Page 64 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 64 of 93
7. Segregation of waste water streams based on characteristics and its proper management keeping in
view direction under section 18 (1) (b) of the Water (Prevention and Control of Pollution) act, 1974
issued by CPCB regarding compliance of CETP.
8. Treatability & adequacy report for complete ZLD for additional waste water. Feasibility report for
complete reuse condensate waste water for industrial purpose.
9. Adequacy of in house utilization of dilute HCl, in house recovery and management of spent solvent
shall be addressed
• The TOR prescribed as above and as per the standard TOR approved by SEIAA and the model ToRs
available in the MoEFCC’s sector specific EIA Manual for ‘Synthetic Organic Chemical Industry’ shall be
considered as generic TORs for preparation of the EIA report in addition to all the relevant information as per
the generic structure of EIA given in Appendix III in the EIA Notification, 2006.
• The project proponent shall have to apply for Environmental clearance through online portal
http://environmentclearance.nic.in/ along with final EIA report.
15 SIA/GJ/IND2/30398/2018 M/s. Halcyon Labs Pvt. Ltd.
D-2/CH: 335, 336, 337, GIDC Dahej-2,
Bharuch, Gujarat-392130.
Screening & Scoping
Category of the unit : 5(f)
Project status: New
• This office has received an application vide their online proposal no. SIA/GJ/IND2/30398/2018 dated
09/01/2019 made by project proponent (PP) regarding grant of Terms of Reference [ToR] for preparation of
EIA/EMP report.
• This is a new unit proposes manufacturing of synthetic organic chemicals as tabulated below:
Sr. No.
Product Group
Products Name CAS no. /CI
no. Quantity in MT/Month
End-use of Products
1
A
Betamethasone Dipropionate 5593-20-4
0.83
Used as Pharma
intermediate in pharmaceutical
industries.
2 Beclomethasone Dipropionate 4419-39-0
3 Betamethasone Sodium Phosphate 151-73-5
4 Betamethasone Valerate 2152-44-5
5 Clobetasol Propionate 25122-46-7
6 Dexamethasone Sodium Phosphate 2392-39-4
7 Mometasone Furoate 105102-22-5
8 Clobetasone Butyrate 25122-57-0
9 Triamcinolone Acetonide 76-25-5
Page 65 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 65 of 93
10 Halobetasol Propionate 66852-54-8
11 Fluocinolone Acetonide 67-73-2
12 Betamethasone 378-44-9
13 Dexamethasone 50-02-2
14 Dexamethasone valerate 33755-46-3
15 Dexamethasone tert-butyl acetate 24668-75-5
16 Dexamethasone pivalate 1926-94-9
17 Dexamethasone 21-linolate 14899-36-6
18 Dexamethasone 21-isonicotinate 2265-64-7
19 Betamethasone benzoate 22298-29-9
20 Betamethasone admantoate 5593-20-4
21 Betamethasone acetate 987-24-6
22 Prednisolone 53-03-2
23 Fluticasone 80474-14-2
24 Difluprednate 23674-86-4
25 Budesonide 51333-22-3
26 Deflazacort 14484-47-0
27 Fluocinolone 67-73-2
28
B
Erythromycin Base 114-07-8
20.83
29 Erythromycin Estolate 3521-62-8
30 Erythromycin Ethyl Succinate 1264-62-6
31 Erythromycin Stearate 643-22-1
32 Clotrimazole 23593-75-1
33 Ketoconazole 65277-42-1
34 Fluconazole 86386-73-4
35 Posaconazole 171228-49-2
36 Efinaconazole 164650-44-6
37 Luliconazole 187164-19-8
38 Voriconazole 137234-62-9
39 Sertaconazole 99592-32-2
40 Ravuconazole 182760-06-1
41 Isavuconazole 241479-67-4
42 Itraconazole 84625-61-6
43 Tavaborole 174671-46-6
44 Crisaborole 906673-24-3
45 Fosravuconazole 351227-64-0
46 Betrixaban 330942-05-7
47 Tenofovir 147127-20-6
48 Lamivudine 134678-17-4
Page 66 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 66 of 93
49 Ticagrelor 274693-27-5
50 Apixaban 503612-47-3
51
C
Carbamazepine 503612-47-3
8.33
52 Oxcarbazepine 28721-07-5
53 Eslicarbazepine 236395-14-5
54 Dexchlorpheniramine Maleate 2438-32-6
55 Chlorpheniramine Maleate/Base 113-92-8
56
D
Pamoic Acid 130-85-8
8.33 57 Disodium Pamoate 6640-22-8
58 Pyrantel Pamoate 22204-24-6
59 E 2 CTC ( 2 Chlorotrityl chloride ) 42074-68-0 8.33
Total 46.65
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 22/01/2019.
• Salient features of the project are as under:
Sr.
no.
Particulars Details
A Total cost of Proposed Project (Rs. in Crores): Rs. 22.60 Crores
B Total Plot area ( sq. meter) 14861.20 Sq. m.
Green belt area ( sq. meter) @ 4948 Sq. m.
C Employment generation @ 50 persons
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC water supply
Status of permission from the concern authority.
Already obtain from GIDC for
water supply
ii Water consumption (KLD)
Category Quantity in KLD Remarks
(A) Domestic 8.00
70 KLD Fresh water from GIDC Water Supply and remaining reuse from ETP RO
(B) Gardening 10.0
(C) Industrial
Process 54.0
Washing 2.0
Boiler 25.0
Cooling 5.0
Others(RO/DM Reject) 20.0
Industrial Total 106.0
Page 67 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 67 of 93
Grand Total (A+B+C) 124.0
22) Total water requirement for the project: 124 KLD
23) Quantity to be recycled: 54 KLD
24) Total fresh water requirement: 70 KLD
iii Waste water generation (KLD)
Category Quantity in KLD Remarks
(A) Domestic 6.4 Septic Tank, Soak Pit
(B) Industrial
Process 58.0 � Wastewater will be treated and then subjected to RO and its product will be reused
� ETP RO reject will be sent to be subjected to MEE.
Washing 2.0
Boiler 2.5
Cooling 1.0
Others(RO/DM Reject) 20.0
Total Industrial waste water 83.5
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
In-house ETP - 95 KLD (Primary, Secondary, Tertiary) and MEE(1.5 KL/Hr.)
v Mode of Disposal & Final meeting point
Domestic: � Septic Tank/Soak pit tank
Industrial: � ETP RO reject will be subjected to In - House MEE.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. ,
Name of CF
No. (ETP RO reject will be subjected to In - House MEE.)
Membership of Common facility (CF)
(For waste water treatment)
No.
Page 68 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 68 of 93
vii Simplified water balance diagram with reuse / recycle of waste water
viii Reuse/Recycle details (KLD)
Total reuse : 54 KLD
Source of waste water for
reuse with quantity in
KLD
Application area with
quantity in KLD
Remarks regarding
feasibility to reuse i.e.
w/w characteristics
(COD, BOD, TDS etc.)
ETP - Secondary treated
wastewater followed by
ACF,PSF & RO - 54 KLD
To be mixed with fresh water
being received from GIDC for
various uses in manufacturing
process, Washing, Boiler and
Cooling and Gardening - 54
KLD
COD:70-100 mg/l
BOD: 10-20 mg/l
TDS:100-200 mg/L
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Sr. No.
Source of emission
With Capacity
Stack Height (meter)
Type of Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
1 Boiler -1 (2 TPH)
13 Coal
And/Or PNG
8.0 MT/Day And/Or 2456
SCM/Day
SPM
SO2
NOx
Multi-Cyclone Followed Bag
Filter
2 Boiler -2 (1.5 TPH)
13 Coal
And/Or PNG
5.9 MT/Day And/Or 2456
SCM/Day
Multi-Cyclone Followed Bag
Filter
Page 69 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 69 of 93
3 D.G. set-1 Nos. (750 KVA)
9 Diesel 0.6 MT/Day --
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Sr. No.
Specific Source of emission(Name of
the Product & Process)
Type of emission
Stack/Vent Height (meter)
Air Pollution Control Measures (APCM)
1 Reactor (2-CTC) HCL 9 Two Stage Alkali
Scrubber
iii Fugitive emission details with its mitigation measures.As below:
Normally, fugitive emissions are envisaged from the handling of chemicals and
manufacturing operations. The chemical handling & feed systems are automated &
pneumatic, and moreover the reactions take place in closed vessels, hence the fugitive
emissions will not be significant. Additionally, the unit has adopted effective engineering
practices to mitigate the fugitive emissions.
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Transboundary Movement)
Rules 2016.
i
Sr. no.
Type/Name of Hazardous
waste
Specific Source of generation (Name of
the Activity, Product
etc.)
Category and Schedule as
per HW Rules.
Quantity (MT/Annu
m) Management of HW
1 Used oil From Plant machinery
5.1 0.05
Collection, storage, transportation and sold out to the registeredRecyclers.
2 ETP Sludge From
ETPPlant 35.3 260.00
Collection, storage, transportation and disposal to authorized TSDF facility.
3 MEE Sludge From MEE
Plant 35.3 400.00
Collection, storage, transportation and disposal to authorized TSDF facility.
4 Process sludge From
manufacturing process
28.1 30.00
Collection, storage, transportation and disposal to authorized CHWI facility.
5 Discarded containers / liners/barrels
From Raw material
33.1 180.00
Collection, storage and reused for disposal of waste to sold to recyclers.
Page 70 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 70 of 93
6 Spent carbon or filter medium
From Process
28.3 15.00
Collection, storage, transportation and disposal to authorized TSDF facility.
7 Distillation/stripper Residue
From distillation/str
ipper 36.1 5.00
Collection, storage, transportation and disposal to authorized CHWI facility or sold to recyclers.
8
Spent Solvent from Solvent Stripperand Distillation
From Distillation/St
ripper 28.6 97.00
Collection, storage, transportation and disposal through sale to authorized recyclers.
9 HCL Solution (~15-20 %)
From Production ( 2 Chloro
trityle chloride)
26.3 780.00
Collection, storage andtransportation and soldto actual users as perRule-9 of HAZ Rules.
10 Aluminum chloride (@20 %)
From Production ( 2 Chloro
trityle chloride)
Sch. II B(15)
280.00
Collection, storage andtransportation and soldToactual users as perRule-9 of HAZ Rules.
ii Membership details of TSDF, CHWIF etc.
(For HW management)
The membership of GPCB
authorized TSDF as well as GPCB
authorized decontamination facility
will be obtained prior to
commencement of the production
iii Details of Non-Hazardous waste & its disposal(MSW
and others)
--
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
• Solvents namely Methanol,Acetone, Ethyl acetate, Dimethylformamide, MDC, DMF,
Pyridine, Toluene, lPA, Butanol, Dioxane and Ethanol are being used in
manufacturing processes of different products. The solvents are recovered through
distillation, about 95 % are being recovered and used. Details solvent recovery
system and % recovery of solvent will be covered in EIA report.
ii VOC emission sources and its mitigation measures
• VOC emission sources and its mitigation's measures will be covered in final EIA
report.
• During the meeting dated 22/01/2019, technical presentation made by project proponent.
Page 71 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 71 of 93
• Committee noted that proposal is new in GIDC Jagadia. Source of water is GIDC Jagadia. PP mentioned that
effluent generated will be treated in provided ETP consisting of primary, secondary & tertiary units followed by
RO, RO permeate will be reused while RO reject will be sent to MEE. MEE condensate will be sent to ETP
while salt will be disposed at approved TSDF. PP has proposed two steam boiler. Fuel used will be coal/PNG.
PP has satisfactorily addressed adequate measures for hazardous waste management.
• Considering the above project details, after detailed discussion, the terms of reference (ToR) were prescribed
as below and as per the standard TOR for the Synthetic Organic Chemical projects recommended by SEAC
vide letter no. EIA-10-GEN-21/1480 dated 14/09/2017 and approved by SEIAA in its 12th meeting dated
16/09/2017 for the EIA study to be done covering 10 Km radial distance from the project boundary.
1. Compliance of MoEFCC’s OM dated 01/05/2018 regarding “Corporate Environment Responsibility”
(CER). Fund allocation for Corporate Environment Responsibility (CER) shall be made as per
MoEFCC’s O.M. No. 22-65/2017-IA.III dated 01/05/2018 for various activities therein. The details of
fund allocation and activities for CER shall be incorporated in EIA/EMP report.
2. Explore the use of renewable energy to the maximum extent possible. Details of provisions to make the
project energy-efficient through energy efficient devices and adoption of modes of alternative eco-
friendly sources of energy like solar water heater, solar lighting etc. Measures proposed for energy
conservation.
3. PP shall address spent solvent with details of storage, handling and re-use under the Hazardous and
other Waste (Management and Transboundary Movement) Rules 2016.
4. Leak Detection and Repairing Programme (LDAR) for all the volatile organic solvent proposed for use
in-house with detailed chemical properties including vapor pressure. LDAR shall endeavor prevention
of losses of solvents to the best minimum extent.
5. PP shall furnish status of all the applicable rules, acts, regulation, clearances in a tabular form
6. Safety precautions including flame proof electric fittings to be taken to avoid fire hazard during
unloading, storage, transportation, handling and processing of Solvents
7. Segregation of waste water streams based on characteristics and its proper management keeping in
view direction under section 18 (1) (b) of the Water (Prevention and Control of Pollution) act, 1974
issued by CPCB regarding compliance of CETP.
8. Treatability & adequacy report for complete ZLD for additional waste water. Feasibility report for
complete reuse condensate waste water for industrial purpose.
9. Adequacy of in house utilization of dilute HCl, in house recovery and management of spent solvent
shall be addressed
• The TOR prescribed as above and as per the standard TOR approved by SEIAA and the model ToRs
available in the MoEFCC’s sector specific EIA Manual for ‘Synthetic Organic Chemical Industry’ shall be
considered as generic TORs for preparation of the EIA report in addition to all the relevant information as per
Page 72 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 72 of 93
the generic structure of EIA given in Appendix III in the EIA Notification, 2006.
• The project proponent shall have to apply for Environmental clearance through online portal
http://environmentclearance.nic.in/ along with final EIA report.
16 SIA/GJ/IND2/29916/2018 Associated Dyestuff Pvt Ltd. (Unit-I)
Plot No. A-1/5-B, A-1/4,Phase I, GIDC Estate, Vatva, Ahmedabad
Screening & Scoping
Category of the unit : 5(f)
Project status: Expansion
• This office has received an application vide their online proposal no. SIA/GJ/IND2/29916/2018 dated
09/01/2019 made by project proponent (PP) regarding grant of Terms of Reference [ToR] for preparation of
EIA/EMP report.
• This is a new unit proposes manufacturing of synthetic organic chemicals as tabulated below:
Sr. no.
Name of the Products CAS No. / CI no.
Quantity, MT/Month End-use of the
products Existing Proposed Total
1. Reactive Black 5 12225-25-1 5.0 +25 30 For dyeing & printing 2. Reactive Black HFGR 2580-78-0
3. Reactive Red 195 93050-79-4
4. Reactive Yellow FG 12226-63-0
5. Reactive Blue 222 93051-44-6
6. Reactive Blue 194 93050-78-3
7. Direct Black 22 6473-13-8
8. Direct Black 210 99576-15-5
9. Reactive Blue 160 71872-76-9 00 +10 10
10. Reactive Blue 198 124448-55-1
11. Reactive Blue 220 128416-19-3
12. Reactive Blue 19 2580-78-1
13. Reactive Blue 221 93051-41-3
14. Reactive Turquoise
Blue 21
12236-86-1 0.0 +10 10
Total 5.0 45.0 50.0
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 11/01/2019.
• Salient features of the project including Water, Air and Hazardous waste management:
Sr. no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Existing: 1.5Crores Proposed: 2.5Crores Total: 4.0Crores
B Total Plot area Existing: 523 Sq. m. (Plot No. A-1/5-B)
Page 73 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 73 of 93
( sq. meter) Proposed: 751 Sq. m. (Plot no. A-1/4) Total: 1274 Sq. m.
Green belt area,/Tree Plantation area
( sq. meter)
Existing: 00 Sq. m. Proposed: 382 Sq. m. Total: 382 Sq. m.
C Employment generation Existing: 10 Proposed: 10 Total: 20
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC water supply
Status of permission from the concern authority. Permission is obtained from GIDC.
ii Water consumption (KLD)
Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(S) Domestic 0.4 1.1 1.5 Fresh
(T) Gardening 0.0 0.7 0.7 Fresh
(U) Industrial
Process 2.3 5.2 7.5 Fresh
Washing 1.8 6.2 8.0 Reuse
Boiler 0.5 7.0 7.5 Reuse
+ Fresh
Cooling 00 00 00 --
Others (Scrubber) 1.2 0.8 2.0 --
Industrial Total 5.8 19.2 25.0 --
Grand Total (A+B+C) 6.2 21.0 27.2 --
25) Total water requirement for the project: 27.2K LD
26) Quantity to be recycle: 14.05 KLD (RO permeate 8.0 KLD will be reuse in washing and
6.05 KLD in utilities)
27) Total fresh water requirement: 13.15 KLD
iii Waste water generation (KLD)
Category Existing KLD
Proposed (Additional)
KLD
Total after Expansion
KLD
Remarks
(M) Domestic 0.35 0.85 1.20
(N) Industrial
Process 0.7 7.3 8.0
Washing 1.8 6.2 8.0
Boiler 0.05 0.70 0.75
Cooling 00 00 00
Others (Scrubber) 1.15 -0.15 1.0
Page 74 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 74 of 93
Total Industrial waste
water
3.7 14.05 17.75
Note: 8.0 KLD Close loop recycling of Process-RO Permeates will be utilized for washing
and 6.05 KLD ETP-RO permeate will be reused for boiler.
iv Treatment facility within premises with capacity [For existing and Proposed]
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
In-house ETP (Primary & Tertiary Treatment)
v Mode of Disposal & Final meeting point
Domestic: Soak pit
Industrial:
Main source of wastewater generation is Process, washing, scrubber and utilities. Total wastewater generation is 17.75 KLD, which will be treated in ETP followed by RO. After treatment, 8.0 KLD Process-RO permeate will be reused for washing and 6.05 KLD ETP-RO permeate will be reused for utilities and RO reject 3.7 KLD will be sent for final treatment and final disposal to CETP-GESCSL, Vatva(which is not exceed the sanction quantity of consent i.e. 3.0 KLD).
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE,
CHWIF etc. Name of Common facility.
CETP membership of GESCSL-Vatva and for common evaporation facility membership
of Society for Clean Earth.
Membership of Common facility (CF)
(For waste water treatment)
Attached as Annexure- III.
vii Simplified water balance diagram with reuse / recycle of waste water
Page 75 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 75 of 93
vii Reuse/Recycle details (KLD)
(Source of reuse & application area)
Total reuse: 14.05 KLD [8.0 KLD Process-RO permeate reuse for washing + 6.05 KLD
ETP-RO permeate will be reused in utility]
Source of waste water for reuse with quantity
in KLD
Application area with quantity in KLD
Remarks regarding feasibility to reuse i.e. w/w characteristics (COD, BOD,
TDS etc.)
Process-RO permeate – 8 KLD
Washing – 8 KLD Quality of reuse water is given in following table. Mention quality easily use for washing, utilities and process without any adverse impact on product quality.
ETP-RO permeate – 6.05 KLD
Utility – 6.05 KLD
Parameter Unit Process W/w
after RO RO permeates
after ETP
pH pH unit 7.5-8.0 7.5-8.0
Color mg/L 100-200 30-50
SS mg/L 20-30 20-30
TDS mg/L 500-700 250-300
Page 76 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 76 of 93
COD mg/L 50-70 < 50
BOD mg/L 20-25 < 10
Oil & Grease mg/L -- --
Ammonical Nitrogen
mg/L - -
Volume -- 8.0 KLD 6.05 KLD
E Air
i Flue gas emission details No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc. Existing & Proposed
Sr. no.
Source of emission
With Capacity
Stack Height (meter)
Type of
Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
Existing
Current steam requirement is accomplish from boiler of sister concern unit M/s. Associated Dyestuff Pvt. Ltd. (Unit-2)
Proposed
1. Steam Boiler (0.5 TPH)
11 PNG 500 SCM/day
PM, SO2, NOx
--
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.) Existing & Proposed
Sr. no.
Specific Source of emission
(Name of the Product & Process)
Type of emission
Stack/ Vent
Height (meter)
Air Pollution Control Measures
(APCM)
Existing
No process gas emission, spay drying of liquid dyes is out sourced
Proposed
1. Process reactor of Turquoise Dyes
HCl, Cl2 15 Water scrubber followed by alkali
scrubber
2. Spray Dryer (500 Kg/hr.) PNG-1500 SCM/day
PM, SO2, NOX 21 Cyclone separator followed by water
scrubber
iii Fugitive emission details with its mitigation measures.
There are chances of the fugitive emission due to handling of raw materials, from process and hazardous chemicals.
Mitigation Measures: • Entire process will be carried out in closed reactors.
• Pneumatically transfer of liquid raw material in rector.
• Raw material will be stored in the covered structure.
• Greenbelt will be developed around the plant to arrest the fugitive emission.
• Frequent work area monitoring will be done ensure fugitive emissions level.
• Internal road will be concreted or paved to reduce the fugitive emission during vehicular movement.
• Water sprinkling will be done to control air borne dust.
F Hazardous waste (as per the Hazardous and Other Wastes (Management and
Page 77 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 77 of 93
Transboundary Movement) Rules 2016.
Existing & Proposed
i Sr. no.
Type/ Name of Hazardous
waste
Specific Source of generation (Name of
the Activity, Product
etc.)
Category and
Schedule as per HW Rules
Quantity (MT/Annum)
Management of HW
Existing Proposed Total
1. ETP Sludge ETP 35.3 0.8
Mt/month
2.2
Mt/month
3.0
Mt/month
Collection,
storage,
transportation &
disposal at
TSDF site
approved by
GPCB.
2. Discarded
containers/
barrels/liners
Product & Raw
material storage
33.1 100
Nos./month
---
400 Nos./
month
0.2
Mt/month
500
Nos./
month
0.2
Mt/month
Collection,
storage,
transportation &
sell to
registered
recycler/re-
processer.
3. Spent Oil Plant & machineries
5.1 5.0
Lit/month
5.0
Lit/month
10.0
Lit/month
Collection,
storage,
transportation &
use within
premises as a
lubricant/sell to
registered
recycler.
4. Dilute HCl
(18-20%)
Scrubber 26.3 0.0 26.0
Kl/month
26.0
Kl/month
Collection,
storage, re-use
in process
within premises.
5. Spent H2SO4
(30-32%)
Process 26.3 0.0 31.0
Kl/month
31.0
Kl/month
Collection,
storage, and
sell to actual
users under
Rule-9.
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Membership of Saurashtra Enviro
Projects Pvt. Ltd. is attached as
Annexure IV.
iii Details of Non-Hazardous waste & its disposal(MSW and others)
---
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
--
ii VOC emission sources and its mitigation measures
--
• Technical presentation was made by the project proponent dated 22/01/2019.
Page 78 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 78 of 93
• Committee noted that unit has valid CC&A for existing unit. Unit is complying conditions of CC&A. PP informed
that there are no court cases pending and no public complaints against the project. It is noted that after
expansion existing treated waste water will be sent to CETP of GESCSL, Vatva with no change in quality and
proposed waste water of process will be treated in proposed ETP followed by RO-1, RO permeate will be
reused in washing and RO reject will be sent to in-house spray dryer for product recovery. Additional Effluent
generated from washing, scrubber & boiler blow down will be treated in ETP followed by RO, RO permeate will
be reused in utilities and RO reject will be sent to CETP of GESCSL, Vatva for final treatment and disposal. PP
has proposed one steam boiler. Fuel used will be PNG. PP has satisfactorily addressed adequate measures
for hazardous waste management.
• Considering the above project details, after detailed discussion, the terms of reference (ToR) were prescribed
as below and as per the standard TOR for the Synthetic Organic Chemical projects recommended by SEAC
vide letter no. EIA-10-GEN-21/1480 dated 14/09/2017 and approved by SEIAA in its 12th meeting dated
16/09/2017 for the EIA study to be done covering 10 Km radial distance from the project boundary.
10. Compliance of MoEFCC’s OM dated 01/05/2018 regarding “Corporate Environment Responsibility”
(CER). Fund allocation for Corporate Environment Responsibility (CER) shall be made as per
MoEFCC’s O.M. No. 22-65/2017-IA.III dated 01/05/2018 for various activities therein. The details of
fund allocation and activities for CER shall be incorporated in EIA/EMP report.
11. Explore the use of renewable energy to the maximum extent possible. Details of provisions to make the
project energy-efficient through energy efficient devices and adoption of modes of alternative eco-
friendly sources of energy like solar water heater, solar lighting etc. Measures proposed for energy
conservation.
12. PP shall address spent solvent with details of storage, handling and re-use under the Hazardous and
other Waste (Management and Transboundary Movement) Rules 2016.
13. Leak Detection and Repairing Programme (LDAR) for all the volatile organic solvent proposed for use
in-house with detailed chemical properties including vapor pressure. LDAR shall endeavor prevention
of losses of solvents to the best minimum extent.
14. PP shall furnish status of all the applicable rules, acts, regulation, clearances in a tabular form
15. Safety precautions including flame proof electric fittings to be taken to avoid fire hazard during
unloading, storage, transportation, handling and processing of Solvents
16. Segregation of waste water streams based on characteristics and its proper management keeping in
view direction under section 18 (1) (b) of the Water (Prevention and Control of Pollution) act, 1974
issued by CPCB regarding compliance of CETP.
17. Treatability & adequacy report for complete ZLD for additional waste water. Feasibility report for
complete reuse condensate waste water for industrial purpose.
18. Adequacy of in house utilization of dilute HCl, in house recovery and management of spent solvent
shall be addressed
Page 79 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 79 of 93
• The TOR prescribed as above and as per the standard TOR approved by SEIAA and the model ToRs
available in the MoEFCC’s sector specific EIA Manual for ‘Synthetic Organic Chemical Industry’ shall be
considered as generic TORs for preparation of the EIA report in addition to all the relevant information as per
the generic structure of EIA given in Appendix III in the EIA Notification, 2006.
• The project proponent shall have to apply for Environmental clearance through online portal
http://environmentclearance.nic.in/ along with final EIA report.
17 SIA/GJ/IND2/30542/2018 M/s. Solvay Specialities India Private Limited Plot No. 3526-27, GIDC Industrial Estate, Panoli-394116, Dist: Bharuch (Guj.)
Screening & Scoping
Category of the unit : 5(f)
Project status: New
• This office has received an application vide their online proposal no. SIA/GJ/IND2/30542/2018 dated
09/01/2019 made by project proponent (PP) regarding grant of Terms of Reference [ToR] for preparation of
EIA/EMP report.
• This is a new unit proposes manufacturing of synthetic organic chemicals as tabulated below:
Sr.
no.
Name of the
Products
CAS no. /
CI no.
Quantity
MT/Month End-use of
the products Existing Proposed Total
1
SULPHONE
POLYMERS
Poly Ether Sulphone (PES) OR
25608-63-3
630 2000 2630 High Performance Polymer
Poly Sulphone (PSU) OR
25154-01-2
Poly Phenylene Sulphone (PPSU) OR
25608-64-4
Diamino Macromer of Sulphone (DAMS) OR
37768-08-4
Sulphone Co Polymer OR
--
Poly Super Sulphone (EPISPIRE)
--
2 DI Chloro Di Phenyl Sulphone (DCDPS)
80-07-9 450 850 1300 Intermediate to Polymer
Page 80 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 80 of 93
3 DI Hydroxy DI Phenyl Sulphone (DHDPS)
80-09-1 250 250 500 Intermediate to Polymer
4 Acrylic Polymer 9063-87-0 10 -- 10 Polymer
5
KETONE POLYMERS
Poly Ether Ether Ketone (PEEK) OR
29658-26-2
100 400 500 High Performance Polymer
Poly Aryl Ether Ketone (PAEK) OR
55088-54-5
Poly Ether Diphenyl Ether Ketone (PPEK-PEDEK COPOLYMERS) OR
104570-14-1
Poly Phenylene Sulphone Ketone (PPSK) OR
103696-74-8
Poly Ether Ketone Ketone (PEKK) OR
121115-58-0
Poly Ether Ketone Ether Ketone Ketone (PEKEKK) OR
105451-79-4
Poly Ether Ketone (PEK) OR
27380-274
6 Captive Power Plant
-- 15500 KVA
-- 15500 KVA
--
Total (1-5) 1440 3500 4940
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 22/01/2019.
• Salient features of the project are as under:
Sr.
no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Existing:600
Proposed:2100
Total: 2700
B Total Plot area
( sq. meter)
Existing: 2,06,816 Sq. m.
Proposed: 0 Sq. m.
Total: 2,06,816 Sq. m.
Green belt area
( sq. meter)
Existing: 60,000 Sq. m.
Proposed: 5599.67 Sq. m.
Total: 65599.67Sq. m.
C Employment generation Existing:550
Page 81 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 81 of 93
Proposed:500
Total:1050
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC water supply
Status of permission from the concern authority. Unit has obtained permission
for water supply
ii Water consumption (KLD)
Existing
KLD
Proposed
Additional
KLD
Total after
Expansion
KLD
Remarks
(V) Domestic 105 369 474
(W) Gardening 100 0 100
(X) Industrial
Process 544 1340 1884
Washing 131 423 554
Boiler 341 1199 1540
Cooling 609 2140 2749
Industrial Total 1625 5102 6727
Grand Total
(A+B+C)
1830 5471 7301
28) Total water requirement for the project: 7301 KLD
29) Quantity to be recycled: 3200 KLD
30) Total fresh water requirement: 4101 KLD
iii Waste water generation (KLD)
Category Existing
KLD
Proposed
Additional
KLD
Total after
Expansion
KLD
Remarks
(O) Domestic 87 305 392 Treated in
STP and then
reused in
gardening or
irrigation
(P) Industrial
Process 459 1276 1735
Washing 202 403 605
Boiler 109 383 492
Cooling 243 854 1097
Total Industrial
waste water 1013 2916 3929
iv Treatment facility within premises with capacity [For existing and Proposed]
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
� Existing ETP: 650 KLD
� Existing RO: 570 KLD
� Existing MEE: 225 KLD
� Proposed ETP: 1700 KLD
� Proposed RO: 3000 KLD
Page 82 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 82 of 93
� Proposed MEE: 750 KLD
v Mode of Disposal & Final meeting point
Domestic:
Domestic Waste water will be treated in STP and then reused in
gardening or irrigation purpose.
Industrial: • Existing load of effluent will be treated in ETP then 638 KLD will be
sent to M/s. NCTL for further treatment and disposal.
• 3291 KLD of treated effluent will be recycled by RO + MEE.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE,
CHWIF etc.
Name of Common facility
� FETP of M/s. NCTL
Membership of Common facility (CF)
(For waste water treatment)
Unit is already member of the FETP of M/s. NCTL
vii Simplified water balance diagram with reuse / recycle of waste water
vii Reuse/Recycle details (KLD)
[Source of reuse & application area]
Total reuse 3200 KLD
Page 83 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 83 of 93
Source of waste
water for reuse with
quantity in KLD
Application area with
quantity in KLD
Remarks
regarding
feasibility to
reuse i.e. w/w
characteristics
(COD, BOD,
TDS etc.)
RO Permeate: 2000
KLD
Cooling: 2000 KLD TDS: 100-150
mg/L
MEE Condensate:
1200 KLD
Boiler: 1200 KLD TDS: 350-400
mg/L
-
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr,
KVA etc.
Existing & Proposed
-
S
R.
N
O.
Stacks
attached to
Heigh
t from
groun
d
level
(m)
Type of fuel Quantity of
fuel
Air
Pollutio
n
Control
Measur
es
(APCM)
Expect
ed
Polluta
nts
EXISTING
1 DGSet@250KV
A
9 HSD/SKO/SL
DO
45 Lit/Hr.
Adequat
e Stack
Height
SPM-
150
mg/Nm
3 Sox -
100
ppm
Nox -50
ppm
2 Boiler-12 TPH
(smoke tube
type boiler)
48 Furnace Oil/
Natural Gas
761 kg/hr /
824 SM3/Hr
3 DG Set-
CPP@1000KV
Ax 2 Nos
12 HSD/SKO/SL
DO
210 Lit/Hr
Natural Gas
+ SKO
(250 X 2
SM3/Hr) (for
2 nos.)
+ 84 lit/Hr
4 Thermicfluidhea
ter–2nos.(1.5
Mkcal)
36 Furnace Oil/
Natural Gas
180 kg/hrx2 /
195
SM3x2/Hr
5 Thermicfluidhea
ter–
1nos.(DASH -
1.0 Mkcal)
36 Furnace Oil/
Natural Gas
120 kg/hr/
130 SM3/Hr
6 DG Set -CPP 12 Natural Gas 250 SM3/Hr
Page 84 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 84 of 93
2000KVA x2
Nos
* 2 (for 2
Nos.)
7 DG Set -CPP
5750KVA x2
Nos
18 Natural Gas/
LDO/ HSD
1635 SM3/Hr
/
1410 kg/hr
8 Boiler-10 TPH 48 Furnace Oil/
Natural Gas
634 kg/hr/
687 SM3/Hr
9 Boiler-25x2 Nos
TPH (one stand
by)
48 Natural Gas
/LDO/HSD
1648 kg/hr/
1522 SM3/Hr
10 Hot Oil Unit (4.0
MCal/hr)
30 LDO /HSD/
Natural Gas
510 kg/hr/
560 SM3/Hr
11 Thermic fluid
heater 1.0
36 Furnace Oil 140 kg/hr
12 Extra fuel for
existing boiler
Furnace Oil
Natural Gas
HSD
21 kg/hr/
65 SM3/Hr
500 Liter/Day
PROPOSED
13 New Boiler- 25
TPH x 6 Nos.
(Total 3 no. of
stack)
30 HSD/Na
tural
Gas
7610 kg/hr/
8240 SM3/Hr
Adequat
e Stack
Height
SPM-
150
mg/Nm
3
Sox -
100
ppm
Nox -50
ppm
14 TFH Hot Oil
Unit - 4x5
MKcal
(Total 4 no. of
stack)
36 HSD /
Natural Gas
2550
Kg/hr/2800
SM3/Hr
15 DG Set /CPP
5750 kVA x 3
Nos
18 Natural Gas/
HSD/
2452
SM3/hr/1897
Lit/Hr.
-
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Existing & Proposed
-
PROCESS STACK
EXISTING
Sr. No
Process Stack attached to
Height from ground level
(m)
Air Pollution Control
Measures (APCM)
Expected Pollutants
1 DMS Vent with DMS scrubber
20
Single Stage Alkali
Scrubber (Packed bed
type)
Hydrocarbon 15 mg/Nm3
Page 85 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 85 of 93
2 Spin Flash Dryer (PES Plant) Reactor
20 Bag Filter PM - 150 mg/Nm3
3
PEEK Plant with Caustic Scrubber Ventury Scrubber OR Reactor Vent Column Type Scrubber& Alkali Circulating system
20
Single Stage Alkali
Scrubber (Spray type)
S02-40 mg / Nm3 HCL-20 mg/Nm3 HF-6
mg / Nm 3
4
Polymer Reactor of
PES Not Applicable
Process
20 Adequate
Stack Height
CO2:150
mg/NM3
5 S03 Vent with S03
Scrubber 20
Single stage
Acidic
scrubber
(Packed bed
type)
S03:40 mg/NM3
6
Hood of Solidfication Dust Collector, Bag & grinding steps of PEEK Filter polymer with Bag Filter Fugitive dust collector
11 Bag Filter PM - 150 mg/Nm3
7 Polymer Ribbon Dryer - I
11 Bag Filter PM - 150 mg/Nm3
8 Hydrochloric Acid Storage tank
11
Two Stage Water + Alkali
scrubber (Venturi with packed bed
type)
HCL-40 mg/Nm3
9 Salt cooler Dust Collector
10 Bag Filter PM-150 mg/Nm3
10 Packing hood Dust Collector
10 Bag Filter PM-150 mg/Nm3
11 Polymer Ribbon Dryer - II
11 Bag Filter PM - 150 mg/Nm3
12 Extraction wash tank 11 Bag Filter PM - 150 mg/Nm3
13
TOx (Thermal Oxidizer) Alkali Scrubber (Addl para. TOC: 15 mg/NM3, HCl+Cl2 40 mg/Nm3) (Natural Gas: 90 NM3/hr)
30 Single Stage
Alkali Scrubber
PM-150 mg/ Nm3 NOX-50
mg/Nm3
14 Polymer dryer 10 Dust Collector PM - 150 mg/Nm3
15
Polymer reactor
(Addlpara. CO2: 150
mg/NM3)
22 Adequate
Stack Height
CO2: 150
mg/NM3
16 Polymer Blender 10 Dust Collector PM-150 mg/
Page 86 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 86 of 93
(Ware House) Nm3
17 Packing Silo
10 Dust Collector PM-1 50 mg/
Nm3
18 Polymer Hood (Ware House)
10 Dust Collector PM-150 mg /
Nm3
PROPOSED
1 DMS Vent with DMS scrubber
20
Single Stage Alkali
Scrubber (Packed bed
type)
Hydrocarbon 15 mg/Nm3
2 Spin Flash Dryer (PES Plant) Reactor
20 Bag Filter PM - 150 mg/Nm3
3
PEEK Plant with Caustic Scrubber Ventury Scrubber OR Reactor Vent Column Type Scrubber& Alkali Circulating system
20
Single Stage Alkali
Scrubber (Spray type)
S02-40 mg / Nm3 HCL-20 mg/Nm3 HF-6
mg / Nm 3
4 Reactor of PES Not
Applicable Process 20
Adequate
Stack Height
CO2:150
mg/NM3
5 S03 Vent with S03
Scrubber Scrubber 20
Single Stage
Acidic
Scrubber
(Packed bed
type)
S03:40 mg/NM3
6
Hood of Solidfication Dust Collector, Bag & grinding steps of PEEK Filter polymer with Bag Filter Fugitive dust collector
11 Bag Filter PM - 150 mg/Nm3
7
Hydrochloric Acid with Scrubber Scrubbing System &Caustic Scrubbing system
11
Two stage Water + Alkali
scrubber (Venturi with packed bed
type)
HCL-40 mg/Nm3
8 Salt cooler Dust Collector
10 Bag Filter PM-1 50 mg /
Nm 3
9 Packing hood Dust Collector
10 Bag Filter PM-1 50 mg /
Nm 3
10
Extraction wash tank with Dust Collector Dust Collection system of extraction vessel
11 Bag Filter PM - 150 mg/Nm3
11
Process Emission Vessel TOx (Thermal Oxidizer) Alkali Scrubber (ddl para. TOC: 15 mg/NM3,
30 Single Stage
Alkali Scrubber
PM-150 mg/ Nm3 NOX-50
mg/Nm3
Page 87 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 87 of 93
HCl+Cl2 40 mg/Nm3) (Natural Gas: 90 NM3/hr)
12 Polymer dryer 10 Dust Collector PM - 150 mg/Nm3
13 Polymer reactor 22 Adequate
Stack Height
CO2: 150
mg/NM3
14 Polymer Blender (Ware House)
10 Dust Collector PM-150 mg/
Nm3
15 Packing Silo 10 Dust Collector PM-150 mg/
Nm3
16 Polymer Hood (Ware House)
10 Dust Collector PM-150 mg /
Nm3
-
iii Fugitive emission details with its mitigation measures.
Following measures will be adopted to prevent and control fugitive emissionsC
1. Airborne dust at all transfers operations/ points will be controlled either by
spraying water or providing enclosures.
2. Care will be taken to store construction material properly to prevent fugitive
emissions, if any.
3. Regular maintenance of valves, pumps, flanges, joints and other equipment
will be done to prevent leakages and thus minimizing the fugitive emissions of
VOCs.
4. Entire process will be carried out in the closed reactors with proper
maintenance of pressure and temperature.
5. Periodic monitoring of work area will be carried out to check the fugitive
emission.
6. Breather valves will be provided on solvent tanks.
7. Solvent tank vents will be connected to vent chillers.
8. To eliminate chances of leakages from glands of pumps, mechanical seal will
be provided at all solvent pumps.
9. Close feeding system will be provided for centrifuges. Centrifuge and filtrate
tank vents will be connected to vent chillers.
10. Minimum number of flanges, joints and valves in pipelines.
11. Enclosures to chemical storage area, collection of emission from loading of raw
materials in particular solvents through hoods and ducts by induced draft, and
control by scrubber / dust collector to be ensured.
12. Nitrogen blanketing will be provided, besides special care needs to be taken for
control in respect of odorous chemicals.
F Hazardous waste
(as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
Existing & Proposed
i SR NO
.
TYPE OF WASTE
SOURCE OF
GENERATION
CAT. NO.
EXISTING QUANTIT
Y
PROPOSED QUANTITY
TOTAL QUANTIT
Y DISPOSAL FACILITY
(MT/Month)
1 ETP Sludge
Effluent Treatment Plant
Sch-I-34.3
710 2492 3202 Collection, storage, transportation, disposal at TSDF,
Page 88 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 88 of 93
BEIL/SEPPL/GSPL
2 Distillation Residue
Solvent Distillati
on in Process
Plant
Sch-I-20.3
90 315 405
Collection, storage, transportation & First priority at Co-processing at RSPL/ Cement Industries or incineration at BEIL/ SEPPL/ GSPL.
3 Oily Waste
Process &
Maintenance of Equipm
ent
Sch-I-34.4
24.2 85 109
4 Spent Carbon
Process & ETP
Sch-I-35.3
12 48 60
5 Other waste
contaminated dust, cotton waste
Process and
Maintenance of equipment and plants.
Sch-I-33.1
2 7 9
6 Waste & Residue
Manufacturing
Process
Sch-I-21.1
12 42 54
Collection, storage, transportation, disposal at TSDF, BEIL/SEPPL/GSPL
7 Industrial Salt
Manufacturing
Process
175 560 735
8 Spent Sulfuric Acid (30
%)
Manufacturing
Process &
Scrubber
Sch-II-D2
575 1090 1665 Collections, storage, transportation & sell to end users having Rule 9 Permission.
9 Spent Oil Process &
Maintenance of Equipm
ent
Sch-I-5.1
7.2 25.2 32 Collections, storage, transportation, sell to registered re-processor.
10 Gunny Bags/Plastic Liners
Process &
Maintenance of Equipm
ent
Sch-I-33.3
925 3237 4163 Collections, storage, decontamination, transportation & sell to authorized traders.
11 Glass wool, waste
insulation
Process &
Maintenance of Equipm
ent
7.5 26.5 34
Collection, storage, transportation, disposal at TSDF, BEIL/SEPPL/GSPL
12 Used contamina
ted personal protective equipment
s
From departm
ent
0.2 0.7 1
13 Non Manufac 15 52.5 68
Page 89 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 89 of 93
Recyclable Plastic
waste
turing Process
14 Drums/carboys/Glass bottles
Process &
Maintenance of Equipm
ent
300 1050 1350
Collections, storage, decontamination, transportation & sell to authorized traders.
15 Discarded container
Process &
Maintenance of Equipm
ent
0.62 2.17 3
16 Asbestos waste
----- Sch-I-15.2
0.4 0 0.4 Collection, storage, transportation, disposal at TSDF, BEIL/SEPPL/GSPL
17 Used filter media from
lubrication system D
Set
Process &
Maintenance of Equipm
ent
Sch-I-35.1
0.45 1.575 2 Collection, storage, transportation & First priority at Co-processing at RSPL/ Cement Industries or incineration at BEIL/ SEPPL/ GSPL.
18 Spent Solvent
Manufacturing
Process
Sch-I-21.2
-- 40500 40500 Collection, storage, transportation, recovered by solvent distillation Plan
19 12% HCl Solution
Scrubber
Sch-II-B-15
-- 30 30
Collection, storage and sent to ETP for further treatment
20 15% NaCl Solution
Scrubber
Sch-II-B-36
-- 10 10
21 12 % of Potassium Hydrosulfit
e& Potassium Chloride & Potassium Hydrofura
n
Scrubber
-- 120 120
-
ii Membership details of TSDF, CHWIF etc.
(For HW management)
Company is member of M/s. Ambuja
Cements Limited, M/s. RSPL, M/s.
GSPL.
Details of Non-Hazardous waste & its
disposal(MSW and others)
No non hazardous waste will be
generated.
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered
Solvents
Details of Solvent recovery
Page 90 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 90 of 93
Atmospheric Distillation of Solvents:
Primary Condenser HE-01: Cooling Tower water will be used to condense the
solvents and the non condensed vapors will be condensed in a Secondary
Condenser.
Secondary Condenser HE-02: Chilled water at 6 0C will be used to condense the
non condensed vapors in the Secondary Condenser.
Vacuum distillation of Solvent:
Primary Condenser HE-01: Cooling Tower water or Chilled water will be used to
condense the solvents depend on the vapor pressure at its operating conditions
and the non condensed vapors will be condensed in a Secondary Condenser.
Secondary Condenser HE-02: Chilled water at 60C will be used to condense the
non condensed vapors in the Secondary Condenser.
96 % of Spent Solvent will be recovered by In-house distillation of Solvent.
ii VOC emission sources and its mitigation measures
• All the solvents are directly distillate from product mix and purified in packed column
with the help of reflux and therefore there is no generation of any distillation residue
from the solvent distillation.
• The solvent distillation system is designed so as to achieve minimum 95% recovery of
solvent.
• Pure solvent, crude solvent and distilled (recovered) solvent shall be stored only in
storage tanks and we shall not be using drums at any stage in the Solvent
Management System.
• Wherever required, the solvents shall be directly pumped into day tanks from the
storage tanks and shall be charged into the reactors without involving any manual
handling.
• All the pumps shall be mechanical seal type to avoid any leakage of solvent.
• All necessary fire fighting systems shall be provided with alarm system. Flame proof
wiring and flame proof electrical accessories shall be provided to avoid any mishap.
• All the storage tank and day tank shall be connected to a vent system through chilled
water condensers to prevent loss of solvents in the atmosphere.
• All the distillation column vents are also connected to chilled water condensers for
maximum possible recovery of the solvents.
• During the meeting dated 22/01/2019, technical presentation made by project proponent.
• Committee noted that unit has valid CC&A for existing unit. Unit is complying conditions of CC&A. Committee
noted that unit has submitted certified compliance report of RO-Bhopal for compliance of existing EC. PP
informed that there are no court cases pending and no public complaints against the project. It is noted that
after expansion existing treated waste water will be sent to CETP with no change in quality and proposed
additional waste water of process and washing will be treated in proposed ETP followed by RO, RO permeate
will be reused and RO reject will be sent to MEE. Additional Effluent generated from cooling & boiler will
directly passed through RO, RO permeate will be reused and RO reject will be sent to MEE. MEE condensate
will be reused back and salt/residue will be disposed at approved TSDF. PP has proposed 6 steam boiler, 4
TFH & 3 DG sets. Fuel used will be Natural Gas/HSD. PP has satisfactorily addressed adequate measures for
Page 91 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 91 of 93
hazardous waste management.
• Considering the above project details, after detailed discussion, the terms of reference (ToR) were prescribed
as below and as per the standard TOR for the Synthetic Organic Chemical projects recommended by SEAC
vide letter no. EIA-10-GEN-21/1480 dated 14/09/2017 and approved by SEIAA in its 12th meeting dated
16/09/2017 for the EIA study to be done covering 10 Km radial distance from the project boundary.
1. Compliance of MoEFCC’s OM dated 01/05/2018 regarding “Corporate Environment Responsibility”
(CER). Fund allocation for Corporate Environment Responsibility (CER) shall be made as per
MoEFCC’s O.M. No. 22-65/2017-IA.III dated 01/05/2018 for various activities therein. The details of
fund allocation and activities for CER shall be incorporated in EIA/EMP report.
2. Explore the use of renewable energy to the maximum extent possible. Details of provisions to make the
project energy-efficient through energy efficient devices and adoption of modes of alternative eco-
friendly sources of energy like solar water heater, solar lighting etc. Measures proposed for energy
conservation.
3. PP shall address spent solvent with details of storage, handling and re-use under the Hazardous and
other Waste (Management and Transboundary Movement) Rules 2016.
4. Leak Detection and Repairing Programme (LDAR) for all the volatile organic solvent proposed for use
in-house with detailed chemical properties including vapor pressure. LDAR shall endeavor prevention
of losses of solvents to the best minimum extent.
5. PP shall furnish status of all the applicable rules, acts, regulation, clearances in a tabular form
6. Safety precautions including flame proof electric fittings to be taken to avoid fire hazard during
unloading, storage, transportation, handling and processing of Solvents
7. Segregation of waste water streams based on characteristics and its proper management keeping in
view direction under section 18 (1) (b) of the Water (Prevention and Control of Pollution) act, 1974
issued by CPCB regarding compliance of CETP.
8. Treatability & adequacy report for complete ZLD for additional waste water. Feasibility report for
complete reuse condensate waste water for industrial purpose.
9. Adequacy of in house utilization of dilute HCl, in house recovery and management of spent solvent
shall be addressed
• The TOR prescribed as above and as per the standard TOR approved by SEIAA and the model ToRs
available in the MoEFCC’s sector specific EIA Manual for ‘Synthetic Organic Chemical Industry’ shall be
considered as generic TORs for preparation of the EIA report in addition to all the relevant information as per
the generic structure of EIA given in Appendix III in the EIA Notification, 2006.
• The project proponent shall have to apply for Environmental clearance through online portal
http://environmentclearance.nic.in/ along with final EIA report.
Page 92 of 93
475th meeting of SEAC-Gujarat, Dated 22.01.2019
Page 92 of 93
Meeting ended with thanks to the Chair.
Minutes approved by:
1. Dr. Dinesh Misra, Chairman, SEAC 2. Shri V. N. Patel, Member, SEAC
3. Shri. R. J. Shah, Member, SEAC
4. Dr. V. K. Jain, Member, SEAC
5. Shri A.K. Muley, Member, SEAC