Ministry of Irrigation
Department of Irrigation
Irrigation Management Division
System Management and Training Program
FINAL REPORT
On
Functional Status and Performance Evaluation
of
Kankai Irrigation and WUA Systems Under IMT/IWRMP
(IMT process step-13)
Submitted by:
Mannings Consult Pvt.Ltd.
Kupandole, Lalitpur
Contact no-0977-01-5536981
March, 2018
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. ii
Acknowledgements
We express our earnest gratitude to System Management and Training Program (SMTP) for providing
an opportunity to conduct Functional Status and Performance Evaluation of Kankai Irrigation and WUA
Systems under IMT/IWRMP in January 2018.
Many people benefited this study by their acumen and academic contribution. At the outset, we express
our sincere gratitude to Mr. Rajendra Bir Joshi, Chief of SMTP, and Mr. Umesh Kumar Sujakhu, Senior
Divisional Engineer, SMTP who provided both moral and administrative support.
We are grateful to SMTP for entrusting this responsibility and also financing this study. Ms. Sanchita
Kaduwal, Engineer on the SMTP was throughout helpful in supplying us required research materials.
We express our sincere thanks to her.
This study would not have been completed without the active support of officials of Kanai Irrigation
Management Division Office, Jhapa. We express our deep gratitude for providing necessary
information about the project and their kind co-operation regarding this evaluation of the system. The
consultant also expresses its thanks to WUA personnel and key informant farmers who directly and
indirectly cooperating to accomplish this evaluation.
Lastly, the Mannings Consult extends its sincere thanks to the study team for their hard work, sincere
dedication and commitment to accomplish this study.
Mannings Consult Pvt. Ltd.
Kupandole, Lalitpur
March, 2018
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. iii
Table of Contents
Acknowledgements ........................................................................................................................... ii
Table of Contents ............................................................................................................................. iii
List of Tables ................................................................................................................................... vi
List of Figures .................................................................................................................................. vi
List of Acronyms ............................................................................................................................. vii
1 Introduction ............................................................................................................................... 1
1.1 Project Background ............................................................................................................ 1
1.2 Subprojects under Component-B ........................................................................................ 1
1.3 Project Objectives .............................................................................................................. 2
1.4 Indicators of Achievements ................................................................................................ 2
1.5 Project Inputs, Activities, Outputs and Expected Outcomes ................................................ 2
1.5.1 Project budget of Component –B ................................................................................ 2
1.5.2 The Activities of Component–B.................................................................................. 3
1.5.3 The Expected Primary Outputs of Component-B ........................................................ 3
1.5.4 The Expected Out Comes ........................................................................................... 3
2 Context of Functional Performance Evaluation (FPE) of KIS and WUA .................................... 4
2.1 Background Features of KIS .............................................................................................. 4
2.1.1 Canal Inventories ........................................................................................................ 4
2.1.2 Headwork and Settling Basin ...................................................................................... 4
2.1.3 Distribution System .................................................................................................... 6
2.1.4 Improvements Works Done ........................................................................................ 6
2.1.5 WUA Features of KIS ................................................................................................ 6
2.1.6 Water Management (Canal Operation and Maintenance) Features in KIS .................... 8
2.1.7 Canal Operation Plan (COP) Preparation and Implementation ..................................... 8
2.1.8 Asset Management Plan (AMP) .................................................................................. 8
2.2 Purpose of Functional Performance Evaluation (FPE)......................................................... 9
2.3 Objectives of FPE .............................................................................................................. 9
2.4 Scope of FPE ..................................................................................................................... 9
2.5 Features of Evaluation Team ............................................................................................ 10
2.6 Concept Approach and Methodology of Evaluation .......................................................... 10
2.6.1 Concepts .................................................................................................................. 10
2.6.2 Indicators ................................................................................................................. 11
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. iv
2.6.3 Approach and Methodology ..................................................................................... 12
2.6.3.1 Desk Study Approach ............................................................................................... 13
2.6.3.2 Field Study (Primary data collection techniques) ...................................................... 14
2.6.3.3 Data Analysis ........................................................................................................... 14
2.7 Limitations of the Evaluation ........................................................................................... 15
3 Findings and Conclusions ........................................................................................................ 16
3.1 Performance of Canal Rehabilitation ................................................................................ 16
3.1.1 Adequate Water Flow in the Canals .......................................................................... 16
3.1.2 Control Gates and Water Measuring Structures Functionality.................................... 16
3.2 Performance of Main and Secondary Canal Level Water Management ............................. 17
3.2.1 Performance of Main System Water Management ..................................................... 17
3.2.2 Performance of Secondary Level Water Management ............................................... 18
3.2.3 Tail Enders Response on Improved Water Delivery .................................................. 19
3.2.4 Conclusions .............................................................................................................. 19
3.3 Performance of WUA....................................................................................................... 20
3.3.1 WUA Establishment ................................................................................................. 20
3.3.2 Administration and Financial Management ............................................................... 21
3.3.3 Resource Mobilization .............................................................................................. 23
3.3.4 Irrigation Service Delivery to Users .......................................................................... 24
3.3.5 Program Management ............................................................................................... 24
3.3.6 Conflict Management ............................................................................................... 24
3.3.7 Conclusions .............................................................................................................. 25
3.4 Performance of Agriculture .............................................................................................. 25
3.4.1 Crop Yield................................................................................................................ 26
3.4.2 Cropping Intensity .................................................................................................... 27
3.4.3 Cropping Pattern ...................................................................................................... 27
3.4.4 Other Tangible Impacts ............................................................................................ 28
3.4.5 Conclusions .............................................................................................................. 28
4 Lessons Learned ...................................................................................................................... 29
5 Conclusions and Recommendations ......................................................................................... 30
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. v
Annexes .......................................................................................................................................... 32
Annex-1 Data Summary Sheet (KIS) ........................................................................................... 33
Annex-2 Observations of Canal Structures along MC and BC of KIS........................................... 40
Annex-3 List of Key informants (WUA, Office Staff & Farmers) ................................................ 41
Annex-4 Canal Operation Plan (COP) ......................................................................................... 42
Annex 5 List of Training Accomplished in KIS ........................................................................... 49
Annex-6 Field Photographs ......................................................................................................... 53
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. vi
List of Tables
Table 1: Original Scope Subproject information ................................................................................ 1
Table 2: Original Scope Budget Plan ................................................................................................. 2
Table 3: Research indicators ............................................................................................................ 11
Table 4: Sample Design ................................................................................................................... 13
Table 5: Results of COP Implementation in KIS .............................................................................. 17
Table 6: Tail Ender Response on Water Availability ........................................................................ 19
Table 7: Administrative & Financial Records................................................................................... 22
Table 8: Resource collection in various years ................................................................................... 23
Table 9: Yield Data of Main Crops of KIS ....................................................................................... 26
Table 10: Cropping Intensity ........................................................................................................... 27
Table 11: Achieved % Increase of the Major Crops in KIS ............................................................. 28
List of Figures
Figure 1: Canal networks of KIS ........................................................................................................ 5
Figure 2: Organization Chart of KIS WUA ........................................................................................ 7
Figure 3: Bar Graph showing Annual Crop Yield............................................................................. 26
Figure 4: Bar Graph showing Cropping Intensity ............................................................................. 27
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. vii
List of Acronyms
AF : Additional Financing (World Bank loan funds made available in early 2014)
AMIS : Agency-Managed Irrigation System
AMP : Asset Management Plan
AO : Association Organizer (Social Worker)
BC : Branch Canal
BCC : Branch Canal Committee
C/R : Cross Regulator
COP : Canal Operation Plan
DIO : District Irrigation Office
DOA : Department of Agriculture
DOI : Department of Irrigation
ESI : Essential Structure Improvements
HA : Hectare
H/R : Head Regulator
IMD : Irrigation Management Division
IMT : Irrigation Management Transfer
ISF : Irrigation Service Fee
IWRMP : Irrigation and Water Resources Management Project
KIMD : Kankai Irrigation Management Division
KIS : Kankai Irrigation System
LRP : Local Resource Persons
MC : Main Canal
M&E : Monitoring and Evaluation
MIS : Mahakali Irrigation System (also “Management Information System”)
MIMD : Mahakali Irrigation Management Division
MSC : Main Secondary Canal
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. viii
NIS : Narayani Irrigation System
NIMD : Narayani Irrigation Management Division
O&M : Operation and Maintenance
OPD : Office of the Project Director
PAD : Project Appraisal Document
PDO : Project Development Objective
PIM : Project Implementation Manual
SC : Secondary Canal
SCC : Scheme Coordination Committee
SDE : Senior Divisional Engineer
SIS : Sitagunj Irrigation System (also known as “S9”, a sub-system within SMIS)
SMIS : Sunsari Morang Irrigation System
SMU : Sub-project Management Unit
SSC : Sub-Secondary Canal
TA : Technical Assistance
TA B : Technical Assistance of IWRMP Component B
TOT : Training of Trainers
VC : Vice Chairman
WB : World Bank
WUA : Water Users Association
WUCC : Water Users Coordination Committee
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 1
1 Introduction
1.1 Project Background
The Irrigation and Water Resource Management Project (IWRMP) is financed by the World Bank
(WB), the Government of Nepal (GON), and Water User Associations (WUAs), and is being
executed by Department of Irrigation (DOI). The IWRMP comprises four Components, A through
D:
A – Rehabilitation and Modernization of Irrigation Infrastructure
B – Irrigation Management Transfer Reform
C – Institutional and Policy Support for Improved Water Management
D – Integrated Crop Water Management
1.2 Subprojects under Component-B
Component B phase-1 subprojects started in March 2008 and ended in June 2013. Four of the sub-
systems – Kankai Irrigation Sub-system (KIS), Sitagunj Distributary Irrigation System (SIS) of
Sunsary Morang Irrigation System, Block-8 of Narayani Irrigation System (NIS-8) and Phase-I of
Mahakali Irrigation system ( MIS-I) were initiated in the first phase or as Original Scope (OS)
subprojects of the IWRMP and are at the stage of completion of the other follow up activities like
institutional development and water management which were being carried over the IWRMP-AF
period or till June 2018 .These four sub-systems are located within the four AMIS of Kankai, Sunsari
Morang, Narayani, and Mahakali Irrigation system. These subsystems cover about 22,668 ha of the
irrigation command area transferred to four WUAs.
Table 1: Original Scope Subproject information
Irrigation Systems Sub-Projects Command Area,
(ha) No. of WUAs
Original Scope (phase-I) Subprojects
Kankai (KIS) (total area 7,000 ha) Entire System 7,000 1
Sunsari Morang (SMIS) (total system 62,000 ha) Sitagunj SC 7,800 1
Narayani (NIS) (total area 37,000 ha) Block 8 2,768 1
Mahakali (MIS) (total area 10,800 ha) Stage I 5,100 1
Original Scope Sites Sub-Total 4 Schemes 22,668 4
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 2
1.3 Project Objectives
The overall objective of Component B in KIS is to improve irrigation service performance and
service delivery to users through the completion and consolidation of Irrigation Management
Transfer (IMT) to the Water Users Association (WUAs) of KIS. The component is designed to
address problems exhibited in KIS (Agency Managed irrigation Systems or AMIS) of below
capacity performance, poor O&M, low cost recovery, and inadequate maintenance funds.
1.4 Indicators of Achievements
The PAD 2007 provides several indicators for monitoring the achievements of "Outcomes" (at
overall IWRMP level) and "Intermediate Outcomes" (at Component level). Indicators for
"Intermediate Outcomes" for Component-B are:
Percent of tail-enders reporting improved water availability (relative to baseline).
Percent of WUAs holding regular meetings
Percent of WUAs collecting water charges required for adequate O&M.
Percent of WUAs maintaining appropriate accounts and cash registers.
Percent of delivery points receiving proportionate share of water.
Adequate O&M expenditures by DOI and WUA according to agreed Asset Management
Plans (AMP)
1.5 Project Inputs, Activities, Outputs and Expected Outcomes
To achieve the project out comes Component-B in general budgeted and spent $9.53 in all the 4
subprojects. Apart from this there were consultants input and guidance for qualitative achievement
of the project outputs.
1.5.1 Project budget of Component –B
Table 2: Original Scope Budget Plan
Project Cost Amount (US$)
Total Cost $ 9.53 Million (grant)
Grant Assistant of WB (IDA) $7.27 Million
Investment of GON $1.82 Million
WUA Contribution $ 0.44 Million
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 3
1.5.2 The Activities of Component–B
The major headings of the implemented activities in KIS were as follows:
Completion/consolidation of the Management Transfer Plan, including streamlining and
strengthening of WUAs;
Essential structural improvements;
Repair, upgrading, or procurement of buildings, information systems, transportation,
and maintenance and information technology equipment;
Capacity building of WUAs and the DOI.
1.5.3 The Expected Primary Outputs of Component-B
The followings were the intended outputs to be achieved in KIS;
Efficient and equitable service delivery by financially and institutionally sustainable
WUAs;
Financially and institutionally sustainable WUAs.
Improved physical performance of the irrigation schemes;
Reliable bulk water delivery by the DOI, according to the IMT Agreement with the
respective WUAs.
1.5.4 The Expected Out Comes
The component-B of IWRMP aims to achieve the Project Development Indicators in terms of
outcomes indicators as follows:
Improved irrigated agricultural productivity (Percentage increase in yield and cropping
pattern)
Improved irrigation scheme management
a. % of WUAs whose O and M expenditures is as per agreed AMP,
b. % of water users satisfied with WUA O& M
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 4
2 Context of Functional Performance Evaluation (FPE) of KIS
and WUA
2.1 Background Features of KIS
The Kankai irrigation system irrigates 7000 ha of agricultural land in Jhapa, District. The command
area is circled by the Kankai River in the east, the Khrisna River in the west, the Mahendra highway
in the north and the Indian border in the south.A detailed feasibility study was completed in 1970 by
ADB. The construction was completed in two phases: the first phase was initiated in 1973 and
completed in 1981 and the second phase, to irrigate an additional 3 000 ha, started in 1980 and was
completed in 1991. The irrigation infrastructure was developed for a total of 7 000 ha of land with
the total cost of NRs 310 million, 63 percent of which was from Asia Development Bank loan. The
diversion structure is 126m-long, 1.85 m-high weirs. The canal system consists of a three-tier
network of canals. The main canal length is 34 km with 74 km of secondary canals and 110 km of
tertiary canals. The first 11.5 km reach of the main canal is lined with a design capacity of 10.15
m3/s; the other reaches are unlined and their capacity decreases from 7.25 to 1.75 m3/s. Steel gates
have been built at all off-take points from the main canal and at all tertiary off-takes from secondary
canals.
Irrigation Management Transfer Program under Component-B is in operation to address the
problems exhibited in large public irrigation schemes of below capacity performance, poor operation
and maintenance, low cost recovery and inadequate maintenance funds. The program is financed by
the World Bank, the Government of Nepal and involved Water Users Association (WUA). The
program implementation agreement was signed by WUA and DOI in 31st January 2008 and the first
phase of the program was ended in June 2015. Meanwhile, the World Bank and the Government of
Nepal have signed a new agreement for Additional Financing (AF) for the second phase of the
project ending on June 30, 2018 to support unfinished works.
2.1.1 Canal Inventories
The following sub section deal about available information briefly on canal inventories.
2.1.2 Headwork and Settling Basin
Kankai Irrigation head works structure is a conventional type comprised of a weir, under sluice, and
head regulator structure. The span of the vertical fall type weir is 126m, with a vertical fall of 1.85m
in height. The under sluice has three bays with a total span of 16.5 m width. A typical trapping
structure is built just upstream of the head regulating structure to divert the floating debris in the
river. The location of the headworks structure lies at the foothill of the Churia range just upstream
of the outwash to the Terai plain area. At present the structure is intact and sound. The settling basin
to flush the sediment is built at 1.65 km from the headworks site. The flushing of the sediments is
carried out regularly one day a week to the adjacent SardareKhola.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 5
The total canal network (refer figure -1) has been divided in to five reaches of main canals. The
extension main canal is considered as Reach-5, and other four reaches of the main canal are
considered in the Phase-I main canal sections. The total length of the Phase-I main canal is 22.4 km
and that of extension main canal is 13.6 km, giving a total length of 36 km. The two main canals are
bifurcated at chainage 9+886 km from the headworks site on the Phase-I main. The Phase-I main
canal bifurcates further down gradient 14.1 km into Reach–3 and Reach-4 sections.
Figure 1: Canal networks of KIS
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 6
2.1.3 Distribution System
In KIS a total of 22 numbers of secondary canals are built, out of which only 17 nos. have their
tertiary system for water distribution. The remaining 5 nos. have not been developed for its water
distribution structures, S-17 to S19 secondary canal have some structures VRB and others, but the
turnout structures are missing. At the S-20 and S-21 secondary canal the earth works only are
complete and no structures are built. Total 86.69 km. Length of the secondary canals were built, with
54 nos. of sub-secondary canals. Total 199 nos. of tertiary canals were constructed with total length
of 110 km. Density of the distribution canal is 28 m/ha, which is in the low level of water delivery
efficiency. The distribution system comprises of 22 secondary, 54 sub-secondary, and 199 nos. of
tertiary canals. Total 86.69 km length of secondary canal and 110 km length of tertiary canals were
constructed.
2.1.4 Improvements Works Done
Major canal improvement works done under ESI can be categorized into following topics:
Canal conveyance capacity improvement works: Canal desilting & reshaping works,
canal bank strengthening works, canal lining and canal maintenance works.
Improvement of supporting structures: Drain inlet, CD works , pipe culverts , gabion
works etc.
Construction & protection works of different structures (Culverts, CD Works) at
different chainage
Construction of other structures: Dhyngrikhola aquaduct repair
2.1.5 WUA Features of KIS
Kankai Water User Association (refer figure-2), Jhapa, consists of three level organizations: Main
Canal, Secondary Canal committee and Tertiary Canal committee (TCC). The WUA of KIS was
formed and registered in 1st December 1993 under the Water Resources Act (1993). It has three
tiered organizations, which are structured as follows:
Water User's Committee (WUC) at the tertiary canal level.
Secondary Canal Committee (SCC) at the secondary canal level.
Main Canal Committee (MCC) to work at the whole system level.
In Kanakai altogether 181 water user committees (upasakha and prasakha) are formed among the
ISF paid and membership holder farmers of the tertiary. In total the 5777 membership holding
farmers participated in WUA formation process.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 7
Figure 2: Organization Chart of KIS WUA
Water User's Committee (WUC)
The tertiary committee (prasakha and upasakha) is the lowest significant unit of the WUA. These
communities have 7 members having Chairman, Vice-chairman, a secretary, and treasurer and 3
members. There are altogether 225 WUCs.
Secondary Canal Committee (SCC)
WUC tertiary users elect 3 representatives for a BC sabha from each tertiary to form the SCC. 22
SCCs have been formed among the members of the BC sabha. Nine-member BCCs have been
formed for each BC including Chairman, Vice Chairman, Secretary, Treasurer and 5 members.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 8
Main Canal Committee (MCC)
In total 225 GA members have elected the posts of Chairman, Vice Chairman, Secretary, Treasurer,
and 10 members of the MCC. The ex–chairman of the WUA also is selected as a member of the
MCC. This makes a total of 15 WUA members that form the MCC.
General Assembly (GA)
The 225 GA members are the sole authorized body represented by the users from the very lowest
level of WUA. It has full power to make and amend rules and regulations regarding the operation
and maintenance of the system including water management.
2.1.6 Water Management (Canal Operation and Maintenance) Features in KIS
For achieving improved water management practices in KIS under Component-B, the following four
outputs are planned: a) Calibrated main canal off takes b) Measured, controlled and scheduled
seasonal bulk water delivery by DOI to all WUA BCs, c) Standard and qualitative irrigation service
delivery to users by WUA and d) Approved AMPs ready for implementation in main canal and
branch canal. For these targeted outputs, the main activities planned for KIS were:
2.1.7 Canal Operation Plan (COP) Preparation and Implementation
For this the following activities were reported to have been completed.
Crop data collection (crop calendar, cropping pattern and cropped area) for all the crops
grown in the command area
Calibration of flow control structures at strategic locations
Gauge painting for water allocation and distribution as planned
Preparation of COP for all season crops
Knowledge and skill development trainings for WUAs and Government staff for
effective implementation of COP
2.1.8 Asset Management Plan (AMP)
In order to ensures smooth canal operation for target water delivery, timely and effective in KIS is
inevitable. For this, the following activities have been completed in KIS.
Collection of inventory of canal systems/subsystems and other assets owned by WUA
under component-B
Preparation of AMP (Asset Management Plan)
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 9
Dissemination of AMP for knowledge and skill development for WUAs and
Government staff for adoption of efficient maintenance practice
2.2 Purpose of Functional Performance Evaluation (FPE)
The main purpose of this study is to identify the general status and assess the performance of the sub
component tasks under component-B, IWRMP in KIS: Rehabilitation, Water management and
WUA development tasks. Any incompleteness of the status and performance recommended by this
study would be implemented in the follow up or regular program of SMTP/IMD.
2.3 Objectives of FPE
The overall objective of the study is to assess the present status and performance of irrigation and
WUA. The specific objectives are listed as below:
To document available inventory and performance of canal networks and associated
water control structures.
To assess WUA functional status and their performance
To assess COP and AMP implementation status and irrigation service delivery
performance
To document past agricultural yield, cropping pattern and cropping intensity in reference
to project M&E document.
Recommend unfinished activities or most critical constrains To WUA function with
solution for strengthening capacity of WUA.
2.4 Scope of FPE
The scope of evaluation study is limited to Kankai Irrigation Sub System, 7000. The functional
evaluation part of this study was focused on different aspects as listed below
Physical Aspect (Canal and Water management Systems)
This aspect will cover the study of following parameters;
Canals: Functional status of main canals, branch canals and tertiary canals and their
water conveyance performance including available physical inventories also.
Existence and performance of concerned key water control structures in Main canal and
Branch canals.
Water management (Canal Operation (COP) and Maintenance/ Asset Management Plan
(AMP) status
COP and AMP development, dissemination and adoption; Water allocation and distribution
procedure at main, secondary and tertiary level; Water availability and extent of water accessibility
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 10
to tail end users; Operation and maintenance practice followed at different level of canals according
to Asset Management Plan.
Institutional aspect
It will cover following parameters: WUA establishment, norms and rules established, Key functions
of WUA and their performance status’; WUA capacity development efforts and status; Extent of
efforts of WUA in resource mobilization; Communication aspects and methods in WUA; Extent of
responsibilities sharing between DOI, WUA and the farmers; Organization, hierarchy and functions
of WUA.
Agricultural aspects
Productivity of main Crops, Cropping Intensity cropping pattern and increase households for
vegetable growers
2.5 Features of Evaluation Team
A three – member team of evaluators a team leader, a sociologist / rural development specialist and
one irrigation management engineer conducted evaluation from January 2018. There were four
elements of evaluation methodology: initial meetings, desk review / study of pre – existing
secondary data and project documents, field visit for primary data collection through interview and
discussion and additional information collection through Technical Assistant Team.
2.6 Concept Approach and Methodology of Evaluation
2.6.1 Concepts
In Irrigation management transfer program under IWRMP three components tasks are of primary
concerned to make project success as follows;
Rehabilitation task
Water management task
WUA development task
When tasks are completed an expected output or a state of completeness is achieved. This state
drives into a certain functions with expected performance or a preset standard. In project logical
frame work, we call it intermediate outcomes also. There are definite functions (output) that
rehabilitation tasks and WUA development tasks should enable irrigation system and WUA perform
defined functions. The performance standards associated to the key functions of these two unit tasks
are considered in this study as ‘functional performance’ and are measured by the defined attributes
of each function. Whether these achievements have been achieved or still have to be achieved are
the subjects of assessment to SMTP of IMD.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 11
2.6.2 Indicators
Table 3: Research indicators
Key Functional
Components (Concepts)
Functional Performance (Concept
Indicator Dimensions)
Attributes to be Assessed (Indicators of
Measurements)
Physical-: Canal
rehabilitation
Canal network
improvement
Canal water controlled
structure improvement
Adequate water flow reaching head
to tail.
Canal reshaped to the original section
Canal section improved by… %
controlled & measured water
delivery
Water control structures are complete
and functional.
Adequate water control and measuring
structures built.
Percent of tail Enders reporting
improved water availability. From M&E report.
Water management
(Effective O&M)
Canal operation
Canal maintenance
Controlled and measured bulk
water delivery by project to BC
WUAs.
Calibration at main canal off takes
complete and stations functional.
Cop complete, disseminated and used.
Main system canal operation staff
trained.
DOI /project office maintaining
canal according to main system
AMP.
AMP developed, Approved and
implemented.
Staff trained on AMP
Branch canal WUA maintaining
BC and TC canals according to
BC level AMP.
AMP developed, disseminated and
used.
WUA members trained on canal
maintenance.
WUA is maintaining TC canals.
Institutional (WUA
Development)
1. Established WUA
Office space is available
WUA democratically elected and registered
WUA has logical supports
WUA has rules, constitution and norms.
WUA is organized with their hydraulic
boundary.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 12
2. Effective administration and financial management of WUA
.
Meeting held regularly.
Decision made collectively.
WAU maintaining financial records.
WUA holds general assembly meeting.
WUA does annual auditing.
WUA resource mobilization is
effective.
WUA is collecting ISF & membership fee
with defined target
WUA mobilized labor for canal
maintenance.
WUA is delivering irrigation
service to users equitably, timely and reliably.
COP is developed.
WUA members are trained on COP.
AMP is developed disseminated and used by
BC WUA.
Increase response of user’s satisfaction on
water availability.
Effective WUA program management
WUA has annual plan for activities.
WUA consists of M&E committee for
program monitoring and evaluation.
Effective conflict management A member or committee is responsible for
conflict management.
Observed cases of resolved conflicts.
Agricultural Aspect Crop production Crop yield t/ha
Cropping Intensity %.
2.6.3 Approach and Methodology
Team Management Approach:
In order to complete the study in line and with quality the following team management approach
was adopted:
Team orientation on concept, indicators, objective and methods of functional evaluation.
Assignment of roles responsibility and tasks
Adherence on work activity plan and schedule.
Submission of draft sectoral report as instructed by team leader.
Discipline wise contribution for check list preparation.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 13
2.6.3.1 Desk Study Approach
During desk study period several meetings, documents review, secondary data collection, design of
research and check list were completed as explained below.
Table 4: Sample Design
Sampling units Size of sample Characteristics Parameters of interest
1.Project office 5- members
(SDE, Engineers, AO)
Homogeneous Finite Physical aspect &
Water management
aspect
2.WUA 10- members or more
Executive -4
Members-6
From head, Middle & Tail.
Homogeneous Finite Indicators of WUA
functions
3. Branch level users 3 Branch –H-M-T
Respondents accidental
Homogeneous among Branch Canal Finite
Key informant question
4.Observation
a. Canal MC
4 sample, random
Middle-2
Tail-2
Homogeneous Finite
Universe
Condition of water
control structures/
canals of main supply
b. Canal Branch 3 BC –H-M-T
3 Points – H-M-T
In each BC
Homogeneous Finite
Purpose stratified
Functional status and
performance structures in BC
Initial meetings: Several initial introduction and consultation meetings were held among SMTP,
IWRMP and Technical Assistant staff in order to have project overview knowledge and locations of
project documents and information.
Desk Review and study design: The evaluation started with the comprehensive study of important
project documents provided by WRMP. Many secondary information and data such as project
objectives, plan, implementation arrangements, irrigation management transfer process, M&E result
frame work and project component progress were gathered (Annex- for reviewed documents)
Review and collection of pre – existing data: Baseline data, time line data and end line data were
collected from project M&E result frame work attached in progress reports of IWRMP
Sampling design and sample for data collection: Because of the homogenous nature of the WUA
main committee and branch committee respondents as well as that of office staff a non-probability
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 14
sampling or a convenience sampling for population representativeness and for element selection a
purposive sampling technique with restriction is adopted. For the study purpose the following
sampling units with following characteristics are chosen as data source for the study.
Checklists/Questionnaires preparation: After thorough study of the project documents and the
requirement of the performance study objectives a check list was developed after consultation with
the specialist and clients. The check list consisted of Questionnaires on four aspects namely, A:
physical performance aspects: water management performance aspects: WUA performance aspects
and D: agricultural performance aspects. The check list is attached in Annex I.
2.6.3.2 Field Study (Primary data collection techniques)
Field evaluation team collected primary data through different technique such as key informants
(project staff, WUA executives) interviews, focus group discussion, open ended interviews and
discussions.
Key Informants Interviews: Ten questions were asked to Branch WUAs located at head middle
and tail. These answers were analyzed to validate and complement the report.
Focus Group Discussion (FGD): It was held with –WUA main committee, branch committee and
project system management unit staff. Field visits for conformation of data found in project reports
and key information / interviews were made along the canals and WUA office. In order to triangulate
findings, the evaluations team reviewed secondary data collected in the field.
Field Observation: Water management engineer visited main and branch canal for confirmation of
operational conditions of canal structures and canals. Similarly, Sociologist visited WUA offices to
observe office operation facilities, records and logistics used by WUA. Site visits allowed the
evaluation team to confirm data found in project reports and/or from key information interviews.
2.6.3.3 Data Analysis
After editing, sorting and tabulating qualitative and quantitative data, it was tried to generalize to
identify the functional status (outputs) and performance status of the three components of irrigation
management transfer as mentioned earlier. The overall data analysis approach followed was
qualitative methods and quantitative method for deriving information and theories.
Qualitative Method: The analysis focused on the facts and situation of the project, relations
between causes& effects, implementation process and input, output and outcomes, WUA functions
and performance level and attributes relation with indicators.
Quantitative Method: Simple comparison, trend line graph and simple statistic such as mean and
average for agricultural data were used for evaluation and conclusion.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 15
2.7 Limitations of the Evaluation
The following limitations are realized by the evaluation team
Study period is not sufficient for the required indicator assessment.
Descriptive or qualitative research concept in survey and fact finding enquiries of WUA
functional performance indicators assessment and analysis was applied.
Some degrees of simple quantitative analysis using simple statistics were used for
agricultural and other data.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 16
3 Findings and Conclusions
3.1 Performance of Canal Rehabilitation
The major works accomplished in system improvement in KIS consists of canal conveyance capacity
improvement and rehabilitation of water control and measuring structures. Upper part of main canal
is lined and lower reach of the canal is earthen where section improvement works were done. Canal
conveyance capacity of S0 to S16 branch canals and head regulators and cross regulators built in
them were completely repaired and made functional. Later during phase-ii part of component- B,
branch canals S17-S12 were improved in shape and for structures up to tertiary canals. Major
activities of ESI works done in these canals were canal lining, disilting , canal cleaning gate
maintenance , tertiary canal extension (S17-S21) and Dhyangri aqueduct rehabilitation. The new
reshaping works of canals S17-S12 was by 100% and in old canals (S0-S16) it was by 20-30%,
Tertiary canal reshaping was not included in the project cost. Respective farmers of the tertiary canal
clean them. There is 110km of tertiary canal having average length of 500meter and discharge of
20- 30lit/sec (Details have been given in section 2.1). After completion of rehabilitation of canal
networks, head regulators, cross regulators, full discharge was available in all secondary canals and
tertiary canals in all seasons. But 4 tertiary canals of S12 are blocked and dis-functional where water
does not pass.
3.1.1 Adequate Water Flow in the Canals
As reported by KIMD staff and WUA main committee members since the start of canal rehabilitation
works in 2010, there was regular canal section improvement, desilting works and canal bank
improvement works in S0-S16 canals. Additionally, secondary canals from S17-S21 also were
repaired and maintained in the second phase of IWRMP. All these activities facilitated uninterrupted
water flow from head to tail in MC, SCs and TCs in KIS. Designed flow easily reaches in all canals
except in 4 tertiary canals of S12.
3.1.2 Control Gates and Water Measuring Structures Functionality
All water control and water measurement structures were
adequately repaired and made functional. A total of 41
numbers of head regulator, 7 cross regulators and around
200 tertiary head regulators were maintained. All water
measuring stations at 22 locations including gauge plates
were cleaned and made readable. Sample checks on HR-
1 and CR-1 at S-1, similar structures at S-9 and S-21
along the main canal conformed the findings from project
staff. Similarly observation at nine location along
secondary canals such as at S-1-T1, S-1-T5, S-1-T8, S9-
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 17
T1, S9-T3,S9-T5,S21-T3,S21-T5 and S21-T8 also validated the responses obtained from WUA
executive committee and project staff. The observations are attached in data summery sheet (Annex-
2).
3.2 Performance of Main and Secondary Canal Level Water Management
The quality of irrigation service committed by the government to provide to users is governed by
the effectiveness of main and secondary level management effectiveness. Therefore, performance
of main system and secondary system is separately discussed in the following sections
3.2.1 Performance of Main System Water Management
The overall results of main system management is reflected by how KIMD delivers irrigation
quantity to SCCs and how well functional the main canal and associated canal control structures
have been maintained. Regarding this, the findings are discussed in the following two subsections
3.2.1.1 Controlled and Measured Bulk Water Delivery by KIMD to BCCs
In order to assess this indicator, three elements such as calibration at BC off takes, COP development
and project staff training are considered for analysis.
Secondary off takes at 22 places have been calibrated. New measured canal discharge delivery is
possible from 22 canal off takes. At Sardare intake, there is calibration station for main canal intake
discharge. In order to deliver bulk water to BCCs, one main canal COP has been developed. COP
has been tried in last year spring and monsoon season. There has been a notable change that occurred
in the crop yields and satisfaction of the farmers. This is shown below:
Table 5: Results of COP Implementation in KIS
S.N Branch
Canals Chairperson Remarks in Water Availability
Remarks on Paddy
Yield
1 Branch
Canal-5
Bhim Prasad Tajpuriya,
Chair Person
(9804924729),
Panchgachhi VDC,
Ward -8
Due to rotation system of 4:4 (4
days on & 4 days off), branch
canals received water in needed
quantity and time. Controlled &
measured water delivery was
applied in our branch
Paddy yield was
better than last years.
this year we
harvested more than
4.5 t/ha
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 18
2 Branch
Canal-6
Gendra Prasad
Rajbansi
(9817969002),
Chairpersons, users of
tertiary canal -5,
Panchgachhi ward -3
Farmers are happy with the
rotation system & scheduling (4:4)
in my branch canal because they
got water in time adequately. We
want this schedule for future also
This year spring
paddy yield
increased more than
4.8 t/ha unlike last
years
3 Branch
Canal-11
Narayan Dhungel
(9815917339)
Chairperson & user of
tertiary canal -11
Though we are at tail, we got better
irrigation service this year four
drafts rotation is good. Our farmers
are satisfied with it. I hope this
system would continue in the fully
years also.
Before IMT spring,
paddy, yield was 3-
3.5 t/ha, after rehab it
increased to 4-4.8
t/ha and with this 4:4
rotation schedule I
harvested 6.3 t/ha in
my field.
Success Story – KIS
Jaya Narayan Dhungel is a farmer of tail-end tertiary branch
canal no. 11 that experienced leakage every year. Five such
KIS tertiary canals never received water adequately. Dhungel
says, “Because of this problem we use to harvest only around
3 to 3.5 t/ha. But after the IMT rehabilitated 50 meters of this
canal by lining, last year I harvested 4.8 t/ha.”(Source: Ninth
Quarterly Report, Sep, Nov, 2017) The trained gate operators of
KIMD operate each BC gates and keep records of water
delivery. Thus, equitable bulk water delivery practice exists in
KIS.
3.2.1.2 Main Canal Maintenance with AMP
KIMD has prepared one main canal AMP with the help of Technical Assistant. The purpose of this
AMP is to ensure annual flow of budged Rs. 25 Million to 30 Million (including head works repair
and staff salary) from DOI so that main canal is maintenance annually to sustainable in quantity.
The budget plan and AMP has been submitted to OPD for approval. It is in the process of approval.
3.2.2 Performance of Secondary Level Water Management
According to irrigation management Transfer Agreement, secondary canal level canal operation and
maintenance lies on the accountability of KIS-WUA (Irrigation Management Agreement Document
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 19
signed between WUA and DOI, 2010). According to the agreement, secondary level WUA has to
deliver received irrigation quantity of water from main canal to users timely, equitably and reliably
by operating and maintaining BCs and TCs effectively and efficiently. To achieve this quality of
irrigation service, WUA- KIS has been assisted in developing secondary level COPs (22) and AMPs
(22). In each branch, canal BCC has formed a technical core committee of three members who will
receive COP and AMP training in order to assist BCC in implementing irrigation and maintenance
schedule to meet irrigation quality service to users. At present, AMP training is not yet given to BCC
technical committee members, although, all 22 CMP is already planned. According to KIMD, this
training will be provided during February or March, 2018. The impact of primary level water
management has been shown in section 3.2.1 and the overall impact of water availability is explained
through the water availability response explained in section 3.4.
3.2.3 Tail Enders Response on Improved Water Delivery
To reflect overall result of KIS rehabilitation and improvement, one of the intermediate indicators
proposed in PAD, WB, 2007 is the water availability percent response of the tail Enders located
along the main canal. Before the start of the project at 2010, tail ender’s water availability response
level was recorded as bench mark was 30% after response analysis house hold survey. IWRMP
continually is surveying the changes on these values annually in order to record probable causes for
the changes through established M&E result frame work report. Based on this report of the past
years, the recorded values are shown in the following table
Table 6: Tail Ender Response on Water Availability
Years Tail ender response in % Benchmark
(%)
Target
2016 60 30% 60%
2017 62
2018 62
3.2.4 Conclusions
After data analysis on each attributes of respective indicators the following conclusions are derived
for canal rehabilitation and water management performance of KIS.
Design discharge can pass from head to tail of MC 22-BCCs and 200-TCCs in accordance to their
respective sectional conveyance capacity. Due to section improvement water control gates (head
regulators, cross regulators, under sluice gates) are in complete and functional status because of
complete maintenance and repair works.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 20
Main canal water management status and performance is adequate and satisfactory. There is COP
and AMP developed and disseminated. AMP needs to be approved for regular budget flow. There
is measured and control water delivery to each BCCs. BCCs performance on irrigation service
delivery is being elevated intensively after dissemination of 22COPs developed and given to each
BCC. However, already developed BC level AMP has not been disseminated yet. BCC members
and trained 3 persons of water management sub -committee are well aware of the quality of irrigation
delivery service to users.
After proper sectional and conveyance capacity improvement, rehabilitation of canal control
structures and application of main system COP, tail Enders response in % increased from 30% to
60% in 2017-2018.
3.3 Performance of WUA
In order to have comprehensive impressions and facts on performance status and level of WUA and
Kankai Irrigation System, the following major concepts with their indicators and inherent associated
attributes were studied.
WUA establishment
Administration and financial management
Resource mobilization
Irrigation service delivery to users
Program management
Conflict management
3.3.1 WUA Establishment
The associated attributes such as office space, decision
making, democratic election, logistic supports, working norms
and rules and their pattern of organization (hydraulically based
or village based) are assessed in detail under this sub- heading.
Kankai WUA is working in a two-story building with 4 big
rooms with training hall at ground floor. It has other 3
buildings with single story. Altogether, it has 5 Bigha of lland
for work space. The office is located at JanataChowk, ward
no-5, Shirasatari Municipality. WUA main committee has
adequate furniture and office support provided by IWRMP. It
has: steel shelves-25, Table-5 (with computer table), Wooden chair-6, Plastic chair-234, Computer
-1, Xerox-2, Brother printer-1, Acer laptop -1. There is one office secretary employed by WUA for
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 21
office support. WUA has bank account in Excel Nepal Bank, Rastriya Banijya Bank and Nepal
Bank. There is big sign board of WUA in front wall of the office building. WUA has its own letter
pad and stamp for correspondence.
KIS – WUA have been practicing democratic election process based on constitution and WUA
election rules established earlier and hence, continued from the past years. Election starts from the
tertiary level and gradually goes up through branch canal up to main canal level. At tertiary, the
tertiary committee of 7 members are elected by 2/3rd majority of ISF paid general formers. There is
one reserved position for female. Gradually the same procedure is followed up to MCC formation
(refer section 2.4.1 for detail democratic process and representation of women, Dalit and Janajati).
After election first registration of WUA was complete on 2050-08-16 B.S.
KIS-WUA has adequate logistic supports to manage its day to functions. It has motorbike -2,
excavator-1, tractor-1, reaper-1, Xerox machine-1 and one thresher. WUA has mobilized these
equipment for its own users’ purpose and for generating incomes for WUA fund. Excavator is used
for cleaning the canals and tractor is leased on rent for income generation.
WUA has developed adequate rules and norms for institutional sustainability and day to day works.
It has constitution, election rule, finance management rule, administration rule and canal operation
and maintenance rules. The last amendment of the constitution was on 2072 (5thamendment). WUA
has developed norms for leasing and hiring equipment.
There is a norms for ISF un-payers also as follows: A fine of 25 % of ISF due amount charged for
one year delay, 50% fine for 2 years delay payment and validity of membership expires after two
years of delay in payment.
WUA is organized within the hydrological boundary in KIS. Constitution and WUA Organization
and Operation Procedures 2072 guided the process of WUA election. WUA holds election for the
committee organizations such as Tertiary canal Committee (TCC), Secondary or Branch Canal
Committee (BCC) and Main Canal Committee (MCC) within the reach of respective command area
or hydrological boundary.
3.3.2 Administration and Financial Management
In KIS WUA- MCC and BCC meeting is regularly held on the 9th day and 2-7th day of every month
at MCC and BCC offices. Based on the needs, WUA organizes meeting even more than 2-3 times
also. Meeting is held at WUA office and members are invited by phone call or letter or individual
contacts. At TCC level meeting is held as and when needed.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 22
A democratic and participative decision making
process is followed in WUA. First, agenda for
meeting is prepared at MCC/BCC/TCC and it is
circulated to the participating members by office
secretary. Then, agenda is discussed in the
meeting and decision is kept in minute in the
presence of all members. The minute is circulated
to each concerned committee members. Just it
follows a process chain of agenda preparation -
communication of agenda – discussion on agenda
– decision – keep minute then communication. Generally the chairperson calls the meeting.
In MCC of KIS a subcommittee is formed for annual plan and budget preparation before the fiscal
year. This sub-committee after detail study of requirements and previous records, and discussion
and agreement with other members prepares the plan and submit in MCC for discussion. Then, MCC
put the plan in GA meeting for approval. Finally all budget and plan are passed in GA for the coming
fiscal year. The main budget expenditures headings consists of the following items: staff salary, cost,
electricity fee, election cost and so on. WUA has maintained the following types of financial records
Table 7: Administrative & Financial Records
Administrative Records Financial records
Main committee meeting record Income expenditure records
.Letter outgoing records ISF collection records
.Letters incoming records Membership income records.
Bank records Machine income records
Users Inventory records Subsidiary records
Store stock record Labor contribution records
- Advance payment record
- Audit records
A general assembly of KIS WUA comprised of 225 members. Generally GA meeting is held on
Ashwin to Kartik. But last year it was held on 22th of Poush 2074 B.S. In general assembly, subject
on income and expenditure, next year’s plan, construction completion reports, income statements
and management status of physical assets are put for approval.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 23
A sound practice of annual auditing exists in WUA. Internal audit committee of three members
selects an experienced auditor. A notice of auditor requirement is posted in public place for auditor
invitation. After receiving application and completing selection process, he/she is appointed by
MCC for 15-30 days. After completing auditing, the report received from auditor is put in MCC and
GA meeting for implementation.
3.3.3 Resource Mobilization
WUA of KIS seems very energetic with high level of WUA functions performer specifically in
resource collection and management. It has identified following source with norms of collecting
them: Irrigation service fee (ISF) at the rate of Rs450/ha/crop except of maize and wheat, tractor
leasing @ Rs 1500/hour to their WUA and Rs 1800/hour for outsiders, excavator leasing @
Rs1800/hour and membership fee of Rs.50/MH and Rs10 for renewal The total target of resource
collection is Rs4300000.00 (ISF +Equipment earning +Labor mobilization).
The main accountability of ISF and other resource collection lies on the accountability of chairperson
of Tertiary and Main canal committee. The main constraints for ISF collection is less water supply
to tail end tertiary canals, might is right policy exerted by rich farmers and no assigned persons for
water distribution at tail specifically in S16-S21 branch canals.
There is an excellent ISF sharing mechanism and norms established in WUA as follows: Tax 10%,
after deducting tax out of remaining 90% amount, ISF collector fee 5%, out of remaining 85% and
assuming it as 100% MCC gets 40%, BCC-20% and TCC- 20%. A norms of penalty to ISF non-
payers are imposed as 25% of total due ISF for one year delay, 50% of ISF for two year delay and
membership validity of such defaulters expires after two years and his membership is not renewed
by WUA. The resource collection status of WUA for the past four year is as shown in the following
table:
Table 8: Resource collection in various years
Years Cash amount (ISF+
others)
Cash and kind
mobilize
% of Target
Rs.4300000
2070/71 2572000 5186000 119%
2071/72 3114000 5423000 125%
2072/73 2474000 5260000 121%
2073/74 2154000 NA
Generally users contribute household labor in the same branch canal that belong to them, but mostly
farmers pay cash to BCC instead of labor at the rate of Rs10/ha on the basis of land ,and then the
BCC maintains the canal. According to the process, the total volume of work is estimated in Rupees
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 24
first; then this amount is divided by the total land of the households, and contribution share per unit
area is assessed.
3.3.4 Irrigation Service Delivery to Users
Branch level committees of KIS – WUA changed traditional practice of water scheduling. According
to one respondent, last year they followed one irrigation schedule of 4-days off and 4-days on
rotation according to COP instead of 6-days off and 6-days on rotation along the main canal reach
rotation. The new practice tested in spring season eased farmers to get more water reliably. To
implement new COP each BCC has kept a committee of three members for COP implement. These
members have been trained on COP. About 156 persons from S0- S11 branch canal committee
members have got training so far on COP. Although, COP at branch canal has not been yet fully
implemented with standards of irrigation service delivery, however, WUA intends to provide
irrigation service timely, reliably and equitably to users. Although, 22 COPs have been developed
and 12 BCC have already received COPs planning is there to train the remaining BCC members
also.
To replace old practice of asset management process a new concept of Assets management plan has
been introduced in KIS - WUA. For this, one AMP for main canal and 22 AMP for 22 BCCs have
been developed. But it is in the process of implementation. An accidental survey with tail ender
farmers revealed that there is increased satisfaction among users compared to before the project
situation on COP implementation practices and water availability in KIS.
3.3.5 Program Management
WUA of KIS prepares a very sound and clear annual work plan once in a year before the Fiscal year
in MCC meeting. After agreement with all the members, the program is passed and is subrritted in
the general assembly meeting which is mostly held in Aswin to Kartik. The important component of
the plan is canal operation and canal maintenance. WUA has a committee of 4 trained members for
program monitoring and evaluation. Generally, this committee monitors main canal water delivery
to BCC in conjunction with Kankai Irrigation Management Division (KIMD) staff. Apart from this
regular canal maintenance, new construction and water delivery activities also are monitored by this
committee. It was reported in the discussion that such program development and M&E practice do
not exist in all most all BCCs. Due to this reasons, effective water distribution and adequate amount
of ISF collection have not been yet achieved as expected through these BCCs.
3.3.6 Conflict Management
This indicator was assessed with four elements: assigned persons or committee for conflict
assessment, types of conflict faced by WUA, process of conflict settlement and evidences of conflict
settlements. During the discussion it was noted that MCC has established a sound system of conflict
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 25
settlement practice. A committee of 4 members including one committee president, one farmer,
specialist (Budhijibi) and one member of BCC.
Generally three types of conflict occurs in KIS – WUA: Conflict in canal bank encroachment ,
mismatch in original canal layout map of canal alignment and field office building belonging to
individual farmers ownership. Once the application for the conflict is received the settlement process
starts with first consolation, negotiation and then it is handled by main committee level with
prescribed WUA norms. No practical evidences were reported except one in one of the BCCs during
land acquisition issue for canal service road widening.
3.3.7 Conclusions
Analyzing all attributes regarding Kankai WUA functional status and performance the following
conclusions are derived:
WUA is well established, perfect and performing satisfactorily in utilizing office buildings and
equipment and other logistic supports in performing its day to day tasks.
Resource mobilization process, practices and effort is at its maximum level generating
maximum cash collection of Rs.3114000 in 2071/72 and cash and kind mobilization by 125%
of the required target of Rs430000.
For equitable and reliable water distribution, MC level one and BC level 22 COPs are ready and
being disseminated. The water delivery performance at main canal is satisfactory and producing
impact on increased response of tail Enders on water availability.
WUA of KIS has established process, committees and tasks assignment to committee in
program planning and monitoring. This committee has monitored construction works and main
canal water delivery work satisfactory, however, there is no such practice in branch canal level
committees.
A committee of 4 persons comprising chairpersons is formed for conflict management.
Consolation, negotiation and settlement by established committee is the basic process of conflict
management in WUA. It is managing conflict through its TCCs and BCCs. In general, WUA of
KIS is at complete functional status and is performing satisfactorily all WUA functions.
However, BCCs are week in program management tasks.
3.4 Performance of Agriculture
During the IWRMP project Initiation period (2007), the poverty reduction strategy plan (PRSP) was
the guiding course for WRMP. PRSP, then recognized that robust agricultural growth is required for
poverty reduction in Nepal. In this context, component B of WRMP was chosen as a mean for
increasing agricultural productivity and reducing rural poverty. The goal set of component- B,
IWRMP is to increase agricultural production and cropping intensity through improved irrigation
scheme management. The goal achievement indicators set in term of outcome indicators as written
in Result Frame Work (PAD, 2007), IWRMP are listed below:
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 26
Percent increase in productivity of Paddy, wheat, Maize and Potato crops.
Percent increase in cropping intensity.
Crops yield and cropping intensity data have been regularly reported through M&E result frame
work by components- B /IWRMP. These data were collected from M&E report of IWRMP and
tabulated for analysis as follows:
3.4.1 Crop Yield
IWRMP has considered the main crop (Monsoon and Spring Paddy, Wheat, Maize and Potato grown
in KIS) yields and cropping intensity as prime outcome indicators to measure the Project
Development Objective. Data are analyzed and interpreted with the following tables.
Table 9: Yield Data of Main Crops of KIS
Crop Years Paddy(t/ha) Wheat(t/ha) Maize(t/ha) Potato(t/ha)
Target 3.5 2.8 3.2 14
Benchmark 2.9 2 2.1 10
2014/15 3.7 2-1 3.6 6.8
2015/16 4.7 2.7 4.2 14.3
2016/17 4.8 2.8 4.5 14.3
2017/18 5 2.9 4.7 15.1
Figure 3: Bar Graph showing Annual Crop Yield
As seen in the above chart and table, crop- yields increased gradually against bench mark yield data
in KIS where Irrigation Management Transfer program started in December 2009. Paddy yield
increase from 2.9 ton/ha to 5 ton/ha or the yield increase was even more than the target yield (3.5
ton/ha). Also the Wheat increased from 2ton/ha (benchmark yield) to 2.9ton/ha and Maize increased
0
2
4
6
8
10
12
14
16
Target Benchmark 2014/15 2015/16 2016/17 2017/18
T
o
n
/
h
a
Year
Annual Crop Yield of KIS
Paddy
Wheat
Maize
Potato
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 27
from 2.1 ton/ha (benchmark yield) 4.7 ton/ha double of the target yield. Potato yield (15.1 ton/ha)
also increased over benchmark yield (10 ton/ha).
3.4.2 Cropping Intensity
Cropping intensity of four consecutive years are tabulated for analysis as shown in Table-10
Table 10: Cropping Intensity
Crop Year Cropping Intensity %
Target(2018) 205
Bench mark2008 168
2014/15 200
2015/16 247
2016/17 253
2017/18 262
Figure 4: Bar Graph showing Cropping Intensity
The above table and bar chart shows cropping intensity in KIS command area gradually increases to
262% over bench mark cropping intensity data (168%).
One of the major reasons of increase of cropping intensity is due to the gradual increase in the water
delivery in measured and controlled way to branch canals. Farmer response (60%) on water
availability also justifies the reasons of increase in the cropping intensity.
3.4.3 Cropping Pattern
The following types of cropping pattern is reported in KIS
“Paddy-Wheat-Maize/Oilseed/Potato-spring paddy”
0
50
100
150
200
250
300
Tgt 2018 B M 2008 2014/15 2015/16 2016/17 2017/18
%
Years
Cropping Intensity %
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 28
3.4.4 Other Tangible Impacts
As reported by the farmers of BCCs vegetable grower households are increasing year by year. At
present the number has reached around 400 households.
3.4.5 Conclusions
Agricultural productivity indicators which increased gradually meeting the target indicators are the
project development objective (PDO) outcome indicator of component – B, WRMP. Percent
increase over targeted %of increase is quite encouraging in KIS. The main reasons for the increase
in productivity can be attribution to application of Canal Operation Plan (COP), Asset Management
Plan (AMP) and irrigation canal network rehabilitation activities. The % increase over bench mark
data as reported from M&E report and PAD, 2007 is as shown in the following Table;
Table 11: Achieved % Increase of the Major Crops in KIS
Crops Target Yield(t/ha)
Target % increase over
bench mark
Achieved % over bench
mark
Bench mark yield t/ha
Paddy 3.5 31 72 2.9
Wheat 2.8 40 45 2
Maize 3.2 52 106 2.1
Potato 14 40 51 10
In KIS % increase on cropping intensity over bench mark is 56 % and over the target cropping
intensity (2008, PAD 2007) is 34 %. The contributing factors for this increase are; Scheduled
irrigation practice according to (COP), trained WUA members and reshaped canal conveyance
capacity. Thus, the agricultural project development outcome indicators have been achieved in KIS.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 29
4 Lessons Learned
The following lessons and best practice are derived from this study from KIS.
a. Main canal system management with an objective of equity and reliably of buck water
delivery to branch canal committee contributes to increase water availability to tail Enders.
For this, main system off takes is calibrated, COP and AMP are used and operating staff are
trained.
b. Application of COP and AMP in secondary level followed with training to BCC members
adequately on irrigation and maintenance schedule contributes to water saving and changes
the traditional attitude of farmers over existing irrigation practices.
c. For institutional sustainability of WUA, the best practice is to establish WUA with adequate
office space, furniture and office accessories, logistics and heavy equipment support for
canal maintenance, unanimously developed constitution, working rules and norms.
d. For financially sustainable WUA, ISF, Equipment lease and membership fee are the reliable
sources of income. More and more users’ financial supports are obtained if financial
transaction is made transparent to users and quality of irrigation service to users are ensured.
e. Equipment management with internal control and leasing norms can be economic source for
raising WUA income.
f. A committee of 3 to 5 trained members with established process and penalty norms is basic
requirements for effective irrigation conflict management.
For the increase percentage of main crop productivity and cropping intensity in KIS, the following
attributes can be accounted for or in other words for an effective irrigation management transfer
program with an outcome/goal of crop productivity increase the following elements should not be
avoided.
a. Canal network conveyance capacity improvement through reshaping and rehabilitation.
b. Repair or rehabilitation of water control and measuring structures making functional.
c. Application of COP and CMP at main and secondary system management.
d. Strengthening adequately WUA and project staff capacity for irrigation management
functions.
e. A clear and transparent objectives setting of irrigation service quality and standard of
irrigation service to users.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 30
5 Conclusions and Recommendations
a. Rehabilitation of Canals and Structure:
Main canal and branch canals (S0-S22) of KIS were reshaped, disilted and lined in order to improve
canal conveyance capacity that resulted to adequate discharge flow in the canals. All nonfunctional
water control gates were repaired and made functional.
b. Main System Water Management:
Kankai irrigation management division staff are operating main canal using main canal COP to
achieve equitable and controlled bulk water delivery to BCC. Trained gate operators maintain water
measurement through calibrated stations. AMP is developed but not implemented yet. Therefore, it
is recommend that MC level AMP budget recommended is approved by DOI and implemented from
this year.
c. Secondary Level Water Management:
Each BCC through its trained water distribution committee members intends to distribute water
timely, reliably and equitably .For this, 22 BCCs have one COP in hand provided by KIMD. There
is also 22 AMPs developed but not used yet. Therefore, it is recommended that it should be
disseminated to BCC members and its sub-committee members as soon as possible for
implementation.
d. WUA Establishment and Administrative Functions:
WUA main office is adequately established for performing required WUA functions. It has adequate
office space, logistics, working institutional rules and norms, stationaries, stamp, letter pad and
WUA employed office secretary, office and an excavator driver with helper.
e. Program Management:
Very satisfactory program planning process exists in WUA main committee. The subcommittee
consults members, past planning effects and results, and identifies requirements to be included in
the plan. However, such program management activities including M&E activities were not reported
in BCC. Therefore it is recommended that program planning and M&E capacity development
training need to be provided to BCC members.
f. Resource Mobilization:
Irrigation service fee, equipment leasing, membership collection are the key source for cash
resource. Equally, labor contribution and cash contribution separately from users in BCC are quite
prevailing practice for branch canal maintenance. WUA has established a norms for sharing the
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 31
amount collected form ISF. The cash collection in 2070/71 was Rs.3114000 against the target of
Rs.4300000 and the cash and kind mobilization was worth Rs540000 about 125% of the target.
g. Irrigation Service Delivery to Users:
BCC level members and its sub-committee members have acquired capacity for applying COP
which is already developed for each BCC. The members know that objective quality of irrigation
service delivery timely, reliably and equitable to users. AMP also is ready, but it has not been
available to BCC yet.
h. Conflict Management:
Very effective conflict management system exists in KIS-WUA. A committee of 4 persons chaired
by committee chairperson has been formed. Although conflicts like canal bank encroachment, wrong
canal alignment and conflicts over government owned building occurred, the WUA became able to
settle with the process of consolation, negotiation and committee settlement.
The committee members who were trained on conflict settlement process lost election. New
members are there in the committee. Therefore, a refresher conflict management training for this
committee members including 22 vice-chairman is recommended
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 32
Annexes
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 33
Annex-1 Data Summary Sheet (KIS)
Part -1 Physical Performance
Performance
Indicators
Response Summary
Adequate water flow
Adequate water flow reaching head to tail.
100% flow during monsoon reaches tail part of Main ,Secondary and Tertiary
canals
In winter and spring also water reach up to the tertiary levels.
4 tertiary of S-12 are damaged and blocked, hence water doesn’t flow in those
canals
S17-S21 is fully reshaped and 100% functional and flow reaches there
a. Canal reshaped to
the original section
S17-S21 are fully reshaped including its tertiary
Main canal is lined so has not got any notable reshaping work.
Lining, desilting, c anal cleaning , gate maintenance, tertiary extension were all
relevant activities were carried out in S17-S21
DhyangriKholaaquaduct rehabilitation
b. Canal section
improved by…
%
Almost improved by 100% in S17-S21 and by 20-30% in S0-S16
Satisfactory improvements in other sub secondary canals where rehabilitation
was carried out
2. Water control structures and water measurement structures functional
Schedule wise delivery according to COP
Canal or gate operator distribute water following the scheduled routine.
Water is distributed on equity basis in measured way.
Water control
structures are
complete and
functional.
structure Number status
HR 41 (rehabilitated) ALL good and
functional
CR 7 (rehabilitated) ALL good and
functional
Other HR Equal to number of branches
and tertiary
All good and
functional
Other HR Equal to number of branches and tertiary
Adequate water
control and
measuring structures
built.
1.9 require number of HR,CR and flumes are built in S17-S21 branches and in
their tertiary canals
1.10 SAMPLE OBSERVATION (Annex-2)
Percent of tail Enders
reporting improved
water availability.
(from the M and E
report)
Years % response of the farmers
May, 2016 60 %
May, 2017 62 %
January,2018 62 %
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 34
Controlled and measured bulk water delivery by project to BC WUAs.
Yes, according to COP and the norms.
Calibration at main
canal off takes
complete and stations
functional.
All 33 stations (main and branches ) are well calibrated and completely functional
Tertiary of S-12 are damaged and blocked by local people and hence not gauged.
Trained gatekeepers keep BC water delivery records.
COP complete,
disseminated and
used.
MC level COP is complete , well disseminated to all the project staff
MWUA=MCC
Cop is effective, it was tested in monsoon and spring season paddy
All users are satisfied with COP results of water availability and schedule
Main system canal
operation staff
trained
ALL 12 canal operator are well trained according to Main canal COP for water
delivery.
Other WUA members of the MCC and some members of BCCs are also trained
2 SMU engineers also are trained
DOI /project office maintaining canal according to main system AMP.
Maintenance as per required in the Intake & main canal according to exiting practices
Large scale maintenance and repairmen is carried out by office
AMP developed,
Approved and
implemented.
AMP has been developed but not yet implemented by project asit has not been
approved yet.
So it is not implemented yet. It is with OPD in the center and is in the process of
approval
Annual budget proposed is Rs……..
Staff trained on AMP
Developed and hence training is carried out for gate operators and main WUA
members
Branch canal WUA Operating and maintaining BC and TC canals according to BC level COP and AMP.
Irrigation Service
Delivery by WUA to
users
COP application is being initiated in all MCC,BCC and TCC
Almost all BCC Members are trained on COP
Delivery concept is equity, timely as sufficient water is available in the source
Delivery is completely with COP and user are totally satisfied with COP schedule.
BC Subcommittee of 3 members are formed for service delivery from BCs
according to COP.
AMP developed,
disseminated and
used.
AMP is developed well but not disseminated yet
WUA members
trained on canal
maintenance.
SMU is in the process of organizing AMP dissemination trainings At BC level
A 3 days training on COP was held once for MCC members.
At BC level it is not disseminated yet
WUA is maintaining
TC canals.
TCC and SCC of WUA and individual farmer jointly carryout maintenance work.
Each SCC mange BC level maintenance themselves.
Larger scale TC maintenance is done by TCC and minor are carried out by farmers
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 35
Part -2 WUA performance
Indicators Response Summary
WUA Establishment
Office space is
available
Sufficient space is available for office as they have in total of 5kattha land
Location: Shivasatasi Metropolitan, ward no.5, janata chok.
Total 4 buildings: Two story building (1 No) for office with 4 rooms, other 3 are
1- story buildings. Steel shelves- 25 out of which 6-7 are frequently used, Table -
5 including computer table, wooden chair 6,plastic chair-234, computer-1,Xerox-
2,brother printer -1,Acer laptop-1
Bank account in i)Excel dev. Bank ii)RBB and iii)Nepal Bank Ltd.
WUA democratically
elected and
registered WUA has logical supports
WUA registration date- 2050/08/16
All election are fully with Democratic election process.
At tertiary: for election minimum of 66% user must involve in election.
1 women(usually treasurer) is compulsory in any committee
Membership to participate in election is provided to only ISF payer.
Only general member and ISF payer can vote.
225 GA member vote for MCC executives
Logistic supports: motorbike-2 (old), excavator-1, tractor-1 (sonalika), reaper-1,
zero tillage machine-1, thresher-1
WUA has rules,
constitution and
norms.
WUA has rules and norms (constitution 2072), Last amendment on 2072(5th
amendment).
Rules on election, planning exists
WUA administration and all WUA members are responsible to follow constitution
Penalty system for late payer exists: 25% of ISF for 1 year delay, 50% of ISF up
to 2 years, validity expires after two years and membership has to be renewed.
Norms are developed after serious discussion in WUA and are based on needs.
WUA is organized with their hydraulic
boundary
Boundary is fixed in accordance with constitution and irrigation area
b. Boundary is separated according to designed command area, only respective
users are allowed to use the water from that Tertiary
BC level boundary is also fixed according to design service command area
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 36
Indicators Response Summary
Effective administration and financial management of WUA.
Meeting held regularly.
At least 1 meeting per month usually 9thday of particular month
BCC meeting usually 2-7th of the month all regular
TCC meeting is held as per required
2-3 meetings may be organized according to need
Meeting is announced by either secretory or president of respective committee
Self-attendance is compulsory of user on specified date of meeting
Invitation for meeting is through phone call, letter and individual information
whatever is easiest.
Decision made
collectively.
Agenda is prepared in the meeting of MCC, meeting is called by chairperson
Agenda is discussed in all MCC,BCC & TCC and finally approved
Minuting is done in the presence of all the member of each committee and their
agreement, discussed in MCC then sent to GA
Decision- final decision after every one agree.
WAU maintaining
financial records.
Financial planning is prepared by planning sub -committee after detail study of
requirement and previous records in the agreement with the agreement of all
respondents
If any amendment required, it is through GA.
All budget are passed through GA
Staff salary, vehicle maintenance cost, meeting expenditure, transportation cost,
agricultural equipment buying cost, electricity fees, election cost etc. are
included in financial planning.
WUA holds general assembly meeting.
GA meeting is held annually
Total 225 GA member
Last GA meeting of 22th of Poush 2074 BS.,usually in Ashwin or Kartik
ISF collection, future planning for financial resources management, repair and
maintenance, physical infrastructure, resources management etc. are put in GA
WUA does annual
Auditing.
Auditing every year by hiring the experienced auditor by Internal audit
committee.
Internal audit committee is established with 3 member
Auditor is hired for 15-20 days based on experience
All the recommendation are implemented as much as possible.
Recommendations are put in GA and implemented after discussion
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 37
Part 3 WUA resource mobilization
Indicators Response Summary
Effective Resource Mobilization
WUA is collecting ISF
& membership fee with
target
Rs.450/ha/crop except maize and wheat is ISF rates
Tractor lease @Rs.1500/hr for SCCs and for other @Rs 1800/hr
Excavator lease @1800/hr
Membership fees @Rs.50/member and Rs10/year for its Renovation
ISF target – Rs.4300000.00
Highest ISF collection – 16lakhs 52 thousand /year in fiscal year 073/74
Other years satisfactory ISF collection
Resource sharing: Tax-10%,Out of remaining 90% ,ISF collector fees-15%, Out
of remaining 85%assuming it as 100%, MCC-40%, BCC-20%, TCC-20%
Penalty for not payers or delayed payers exists : 25% of ISF for 1 year delay,50%
of ISF up to 2 years, validity expires after two years and membership has to be
renewed as penalty
Main accountability of ISF collection –chairperson of respected committee or
member to whom responsibility is given
WUA mobilized labor
for canal maintenance.
Insufficient maintenance amount is equally divided to all users according to their
land size.
The cash is paid by farmers @ Rs 10/Katha for maintenance
Users are mobilized in cleaning tertiary canals
WUA is delivering irrigation service to users equitably, timely and reliably.
Irrigation service delivery in accordance with BC level COP
Service quality in terms of equity, timeliness and reliability
COP is developed.
22 COPs are developed, are effective are preferred by users
COPs are for Up to all BCC and TCC
Training is being conducted for BCC and TCC members.
WUA members are
trained on COP.
BCC members already trained for S0-S11
Planning is done to train remaining BCC in February 2018
AMP is developed
disseminated and used by BC WUA.
One AMP is developed only for MCC
22 BCC level AMPs have been developed but not disseminated yet.
No BCC and TCC member are trained on AMP
Increased response of user’s satisfaction on
water availability.
Increased satisfaction
All users’ satisfaction level is raised compared to past
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 38
Effective WUA program management
Annual plan is prepared by MCC members with project staff
Meeting is held for annual plan
Approved in the agreement of all MCC members.
BCC members do not have program planning system
WUA has annual
plan for activities.
Staff salary, vehicle maintenance cost, meeting expenditure, transportation cost,
agricultural equipment buying cost, electricity fees, election cost etc. are included in
financial planning,
Plan for Canal operation and maintenance, water delivery system
Are included.
WUA consists of
M&E committee for program
monitoring and
evaluation
M&E committee of 4 members consists
Other members are well trained in this committee
Canal maintenance, construction works and water delivery is monitored by the
committee,
Effective conflict management.
A member or
committee is
responsible for conflict
management.
Conflict management committee exists. It consists of 1 committee president,1
farmer, 1 specialist (Buddhijibi) and other few member of BCC
But new members are not provided with training
Conflict in the issue of land: as design map and existing alignment at various section
don’t match.
Conflicts arise when farmers plough land up to edge of bank and canal gets narrowed
Conflict in the name of BCC office building, as people claimed that building as
private property. Previously the land had been donated and the building was
constructed with the cost of KIS project.
Process of settlement: Individual consolation, negotiation or otherwise evaluation by
MCC and settlement is according to norms
Observed cases of resolved conflicts.
Not available
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 39
Part 4 Agricultural Performance
Main crop yields (From M and E
report)
Crop Years Paddy(t/ha) Wheat(t/ha)
Target 3.5 2.8
Benchmark 2.9 2
2014/15 3.7 1-Feb
2015/16 4.7 2.7
2016/17 4.8 2.8
2017/18 5 2.9
Cropping Intensity
(From M & E report)
Crop Year Cropping Intensity %
Target(2018) 205
Bench mark2008 168
2014/15 200
2015/16 247
2016/17 253
2017/18 262
Cropping Pattern Paddy-wheat-maize/oil seed/potato-spring paddy
Ashwin month -potato mostly
Increase in vegetable growers
About 400 HHs grow vegetables in the system
Highly attracted towards vegetable farming due to water availability
and increased yield in winter.
Key informants Responses (BC level WUA)
Water is sufficient up to tail of tertiary in monsoon but, during winter and spring,the tail reach
receive -insufficient water.
Almost all tertiary of branch canal are functional and almost all can flow water efficiently.
But there is problem of illegal taping of water by head users.
Little but not sufficiently getting irrigation water in spring. Spring paddy is also cultivated in
the field but its yield is low comparatively.
Well known about COP and its importance. (4-4 ) days routine of water delivery in each
branch is managed in COP but implemented effectively.
Maintenance work is carried out jointly by farmers and TCC.
The yield of almost all crop has increased in all seasons
huge change in water availability, timely available but not sufficient throughout the year
WUA main committee prepares carryout major co-ordination between the branch committee
and monitor the equity water delivery.
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 40
Annex-2 Observations of Canal Structures along MC and BC of KIS
Canals/
Locations
Structures
assessed Functional Status (complete and functional)
Main-1(S-9) INTAKE Complete and well functional, good painting, well gauged, no rusting
Head(-S-1 ) HR1 complete and functional, little rusted, gauged, good greasing, painting is old,
CR1 with 2 control gates, well gauged, painting is old,debris deposition
Middle(S-9) HR complete and functional, little rusted, well gauge reading, paint is faded and old
CR Complete and functional, well paint and good gauged
Tail(S-21) HR complete and functional, good gauged, Good paint, good greasing
CR complete and functional, no painting, no greasing, rust affected
Branches-3 Nos.
1. S1
Head (S1-T1) tert.HR complete and functional, no gauge, corrosive ,no greasing, poor paint
Middle(S-1-
T5) tert.HR
Functional & complete, but has no gauge, no proper greasing, no paint, high rust,
high debris deposition, small wear in gate with small holes appearance.
Tail(S-1-T8) tert.HR functional, complete, no gauge, no greasing, no paint, high rust, high debris
deposition ,no water flow
2. S9
Head (S-9-
T1) tert.HR
only satisfactory functioning, highly rusted, poor and blur gauge, no greasing, poor
paint ,little wear in the gate plate
Middle(S-9-T3)
tert.HR functional, poor greasing and painting ,blur gauge, debris deposition, high rusting
Tail(S-9-T5) tert.HR functional, poor greasing and painting, blur gauge, vegetative disturbance
3. S21
Head(S21 -
T3) tert.HR Highly rusted, blur gauge, no greasing, just functional only and complete
Middle (S21-T5)
tert.HR well functional, poor greasing and painting, blur gauge, debris deposition
tail(S21-T8) tert.HR complete and functional, old painting and poor greasing
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 41
Annex-3 List of Key informants (WUA, Office Staff & Farmers)
KIS WUA Government staffs Key Informant farmers
NAME DESIGNATION NAME DESIGNATION NAME DESIGNATION
Kamal Pd. Bhandari president Mr. Birendra Yadav SDE. Manton Chaudhary Head Reach farmer
Namkal Man limbu vice-president Mr. Lalan Baitha Engineer Gopal Phuyal Middle Reach farmer
Netrapati Pokhrel secretary Mr. Gopal Poudel A.O Kamala Goutam Tail Reach farmer
Suryanarayan Shingh member
Anjana khadka member
UttarkumariDhungel member
Laya pd. Chapagain member
BhishmaBdr.Luintel president- BCC19
Bhakti Pd. Bhandari office manager
Bhawani Pd. Dhungel office staff
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 42
Annex-4 Canal Operation Plan (COP)
Main Canal Operational Schedule at Sardare Intake for winter Crops in KIS. For Monsoon period it is Continuous Flow
Parent canal Sardare Intake Command Area, Ha 6950
Chainage 0+000 Cropped Area, Ha 3764
Name of canal offtake Main Irrigation Canal, MIC Irrigated Area, Ha 3764
Name of Chairperson Suryanarayan Singh Tajpuriya Operational Group
Name of Gateoperator Santa Lawati Design Discharge, l/s 10150
Start of Irrigation Dose End of Irrigation Dose Dose Period Discharge per dose U/S head underflow
SIC Groups
Date Day Date Day Days l/s cm
2015/12/06 6:00 AM Sunday 2015/12/11 6:00 PM Friday 5.50 586.5 32 S0 to S12
2015/12/11 6:00 PM Friday 2015/12/13 6:00 AM Sunday 1.50
2015/12/13 6:00 AM Sunday 2015/12/18 6:00 PM Friday 5.50 769.9 38 S13 to S21
2015/12/18 6:00 PM Friday 2015/12/27 6:00 AM Sunday 8.50
2015/12/27 6:00 AM Sunday 2016/01/01 6:00 PM Friday 5.50 586.5 32 S0 to S12
2016/01/01 6:00 PM Friday 2016/01/03 6:00 AM Sunday 1.50
2016/01/03 6:00 AM Sunday 2016/01/08 6:00 PM Friday 5.50 769.9 38 S13 to S21
2016/01/08 6:00 PM Friday 2016/01/17 6:00 AM Sunday 8.50
2016/01/17 6:00 AM Sunday 2016/01/22 6:00 PM Friday 5.50 1456.2 56 S0 to S12
2016/01/22 6:00 PM Friday 2016/01/24 6:00 AM Sunday 1.50
2016/01/24 6:00 AM Sunday 2016/01/29 6:00 PM Friday 5.50 1674.6 61 S13 to S21
2016/01/29 6:00 PM Friday 2016/02/07 6:00 AM Sunday 8.50
2016/02/07 6:00 AM Sunday 2016/02/12 6:00 PM Friday 5.50 1456.2 56 S0 to S12
2016/02/12 6:00 PM Friday 2016/02/14 6:00 AM Sunday 1.50
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 43
Start of Irrigation Dose
End of Irrigation Dose
Dose Period Discharge per dose
U/S head underflow
SIC Groups Start of
Irrigation Dose
End of Irrigation Dose
Day Date Day Days l/s cm Day Date
2016/02/14 6:00 AM Sunday 2016/02/19 6:00 PM Friday 5.50 1674.6 61 S13 to S21
2016/02/19 6:00 PM Friday 2016/02/21 6:00 AM Sunday 1.50
2016/02/21 6:00 AM Sunday 2016/02/26 6:00 PM Friday 5.50 1156.9 49 S0 to S12
2016/02/26 6:00 PM Friday 2016/02/28 6:00 AM Sunday 1.50
2016/02/28 6:00 AM Sunday 2016/03/04 6:00 PM Friday 5.50 1348.5 54 S13 to S21
2016/03/04 6:00 PM Friday 2016/03/06 6:00 AM Sunday 1.50
2016/03/06 6:00 AM Sunday 2016/03/09 6:00 PM Wednesday 3.50 1156.9 49 S0 to S12
2016/03/09 6:00 PM Wednesday 2016/03/11 6:00 PM Friday 2.00 1348.5 54 S13 to S21
2016/03/11 6:00 PM Friday 2016/03/13 6:00 AM Sunday 1.50
2016/03/13 6:00 AM Sunday 2016/03/16 6:00 PM Wednesday 3.50 3313.1 93 S0 to S4
2016/03/16 6:00 PM Wednesday 2016/03/18 6:00 PM Friday 2.00 2935.3 86 S5 to S21
2016/03/18 6:00 PM Friday 2016/03/20 6:00 AM Sunday 1.50
2016/03/20 6:00 AM Sunday 2016/03/23 6:00 PM Wednesday 3.50 3313.1 93 S0 to S4
2016/03/23 6:00 PM Wednesday 2016/03/25 6:00 PM Friday 2.00 2935.3 86 S5 to S21
2016/03/25 6:00 PM Friday 2016/03/27 6:00 AM Sunday 1.50
2016/03/27 6:00 AM Sunday 2016/03/30 6:00 PM Wednesday 3.50 3313.1 93 S0 to S4
2016/03/30 6:00 PM Wednesday 2016/04/01 6:00 PM Friday 2.00 2935.3 86 S5 to S21
2016/04/01 6:00 PM Friday 2016/04/03 6:00 AM Sunday 1.50
2016/04/03 6:00 AM Sunday 2016/04/08 6:00 PM Friday 5.50 3313.1 93 S0 to S4
2016/04/08 6:00 PM Friday 2016/04/10 6:00 AM Sunday 1.50
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 44
Branch (BS1) Canal level Canal Operation Schedule Plan, KIS
sGsfO{ l;+rfO{ k|0ffnL (KIS), u}F8], emfkf
d'n l;+rfO{ gx/ (MIC) k|0ffnL
cf=j=: 2074÷75
-aiff{ ck'u_ gx/ ;+rfng tflnsf- wfg afnL -k|yd kl/If0f_
Kof/]G6 Sofgn M MIC l/r 1 sdf08 If]q, x]= 460
Rofg]h M 5+650 afnL If]q, x]=
gx/sf] gfd S1 l;+rfO{ If]q, x]=
zfvf÷pkzfvf cWoIfsf] gfd M emlgGb| e6\6/fO{ ;+rfng ;d'x
u]6 ck/]6/sf] gfd M ;Togf/fo0f rf}w/L
l8hfOg axfj,
ln=÷;]= 851
l;+rfO{ kfnf] ;'? ldtL l;+rfO{ kfnf] clGtd ldtL
l;+rfO{
cjwL jxfj k|lt l;+rfO{
u]6
dfyLsf]
kfgLsf]
x]8
zfvf gx/
;d'x
zfvf Ans
axfj k|lt
l;+rfO{
ldtL lbg ldtL lbg lbg ln=÷;]= ;]=dL= ln=÷;]=
@)&$÷)!÷#! ^M)) ljxfg cfO{taf/ @)&$÷)@÷)% ^M)) ckx|fGg z'qmaf/ 5.25 59 v'Nnf
T1-1~T1-7; T1-8~T1-11 67
@)&$÷)@÷)% ^M)) ckx|fGg z'qmaf/ @)&$÷)@÷)& ^M)) laxfg cfO{taf/ 1.75 aGb
@)&$÷)@÷)& ^M)) laxfg cfO{taf/ @)&$÷)@÷!@ ^M)) ckx|fGg z'qmaf/ 5.25 59 v'Nnf
T1-1~T1-7; T1-8~T1-11 67
@)&$÷)@÷!@ ^M)) ckx|fGg z'qmaf/ @)&$÷)@÷!$ ^M)) laxfg cfO{taf/ 1.75 aGb
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 45
@)&$÷)@÷!$ ^M)) laxfg cfO{taf/ @)&$÷)@÷!& ^M)) ckx|fGg a'waf/ 3.50 59 v'Nnf
T1-1~T1-7; T1-8~T1-11 67
@)&$÷)@÷!& ^M)) ckx|fGg a'waf/ @)&$÷)@÷@! ^M)) laxfg cfOtaf/ 3.50 aGb
@)&$÷)@÷@! ^M)) laxfg cfO{taf/ @)&$÷)@÷@$ ^M)) ckx|fGg a'waf/ 3.50 691 v'Nnf
T0-1~T0-7; T0-8~T0-11 785
@)&$÷)@÷@$ ^M)) ckx|fGg a'waf/ @)&$÷)@÷@* ^M)) laxfg cfO{af/ 3.50 aGb
@)&$÷)@÷@* ^M)) laxfg cfO{taf/ @)&$÷)@÷#! ^M)) ckx|fGg a'waf/ 3.50 691 v'Nnf
T0-1~T0-7; T0-8~T0-11 785
@)&$÷)@÷#! ^M)) ckx|fGg a'waf/ @)&$÷)#÷)$ ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)#÷)$ ^M)) laxfg cfO{taf/ @)&$÷)#÷)& ^M)) ckx|fGg a'waf/ 3.50 691 v'Nnf
T0-1~T0-7; T0-8~T0-11 785
@)&$÷)#÷)& ^M)) ckx|fGg a'waf/ @)&$÷)#÷!! ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)#÷!! ^M)) laxfg cfO{taf/ @)&$÷)#÷!$ ^M)) ckx|fGg a'waf/ 3.50 691 v'Nnf
T0-1~T0-7; T0-8~T0-11 785
@)&$÷)#÷!$ ^M)) ckx|fGg a'waf/ @)&$÷)#÷!* ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)#÷!* ^M)) laxfg cfO{taf/ @)&$÷)#÷@! ^M)) ckx|fGg a'waf/ 3.50 449 v'Nnf
T0-1~T0-7; T0-8~T0-11 510
@)&$÷)#÷@! ^M)) ckx|fGg a'waf/ @)&$÷)#÷@% ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)#÷@% ^M)) laxfg cfO{taf/ @)&$÷)#÷@* ^M)) ckx|fGg a'waf/ 3.50 449 v'Nnf
T0-1~T0-7; T0-8~T0-11 510
@)&$÷)#÷@* ^M)) ckx|fGg a'waf/ @)&$÷)$÷)! ^M)) laxfg cfO{taf/ 3.50 aGb
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 46
@)&$÷)$÷)! ^M)) laxfg cfO{taf/ @)&$÷)$÷)$ ^M)) ckx|fGg a'waf/ 3.50 449 v'Nnf
T0-1~T0-7; T0-8~T0-11 510
@)&$÷)$÷)$ ^M)) ckx|fGg a'waf/ @)&$÷)$÷)* ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)$÷)* ^M)) laxfg cfO{taf/ @)&$÷)$÷!! ^M)) ckx|fGg a'waf/ 3.50 449 v'Nnf
T0-1~T0-7; T0-8~T0-11 510
@)&$÷)$÷!! ^M)) ckx|fGg a'waf/ @)&$÷)$÷!% ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)$÷!% ^M)) laxfg cfO{taf/ @)&$÷)$÷!* ^M)) ckx|fGg a'waf/ 3.50 449 v'Nnf
T0-1~T0-7; T0-8~T0-11 510
@)&$÷)$÷!* ^M)) ckx|fGg a'waf/ @)&$÷)$÷@@ ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)$÷@@ ^M)) laxfg cfO{taf/ @)&$÷)$÷@% ^M)) ckx|fGg a'waf/ 3.50 361 v'Nnf
T0-1~T0-7; T0-8~T0-11 410
@)&$÷)$÷@% ^M)) ckx|fGg a'waf/ @)&$÷)$÷@* ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)$÷@* ^M)) laxfg cfO{taf/ @)&$÷)$÷#@ ^M)) ckx|fGg a'waf/ 3.50 361 v'Nnf
T0-1~T0-7; T0-8~T0-11 410
@)&$÷)$÷#@ ^M)) ckx|fGg a'waf/ @)&$÷)%÷)$ ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)%÷)$ ^M)) laxfg cfO{taf/ @)&$÷)%÷)& ^M)) ckx|fGg a'waf/ 3.50 361 v'Nnf
T0-1~T0-7; T0-8~T0-11 410
@)&$÷)%÷)& ^M)) ckx|fGg a'waf/ @)&$÷)%÷!! ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)%÷!! ^M)) laxfg cfO{taf/ @)&$÷)%÷!$ ^M)) ckx|fGg a'waf/ 3.50 361 v'Nnf
T0-1~T0-7; T0-8~T0-11 410
@)&$÷)%÷!$ ^M)) ckx|fGg a'waf/ @)&$÷)%÷!* ^M)) laxfg cfO{taf/ 3.50 aGb
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 47
@)&$÷)%÷!* ^M)) ckx|fGg cfO{taf/ @)&$÷)%÷@! ^M)) laxfg a'waf/ 3.50 361 v'Nnf
T0-1~T0-7; T0-8~T0-11 410
@)&$÷)%÷@! ^M)) laxfg a'waf/ @)&$÷)%÷@% ^M)) ckx|fGg cfO{taf/ 3.50 aGb
@)&$÷)%÷@% ^M)) ckx|fGg cfO{taf/ @)&$÷)%÷@* ^M)) laxfg a'waf/ 3.50 361 v'Nnf
T0-1~T0-7; T0-8~T0-11 410
@)&$÷)%÷@* ^M)) ckx|fGg a'waf/ @)&$÷)^÷)! ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)^÷)! ^M)) laxfg cfO{taf/ @)&$÷)^÷)$ ^M)) ckx|fGg a'waf/ 3.50 361 v'Nnf
T0-1~T0-7; T0-8~T0-11 410
@)&$÷)^÷)$ ^M)) ckx|fGg a'waf/ @)&$÷)^÷)* ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)^÷)* ^M)) ckx|fGg cfO{taf/ @)&$÷)^÷!! ^M)) laxfg a'waf/ 3.50 361 v'Nnf
T0-1~T0-7; T0-8~T0-11 410
@)&$÷)^÷!! ^M)) laxfg a'waf/ @)&$÷)^÷!% ^M)) ckx|fGg cfO{taf/ 3.50 aGb
@)&$÷)^÷!% ^M)) ckx|fGg cfO{taf/ @)&$÷)^÷!* ^M)) laxfg a'waf/ 3.50 373 v'Nnf
T0-1~T0-7; T0-8~T0-11 424
@)&$÷)^÷!* ^M)) ckx|fGg a'waf/ @)&$÷)^÷@@ ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)^÷@@ ^M)) laxfg cfO{taf/ @)&$÷)^÷@% ^M)) ckx|fGg a'waf/ 3.50 373 v'Nnf
T0-1~T0-7; T0-8~T0-11 424
@)&$÷)^÷@% ^M)) ckx|fGg a'waf/ @)&$÷)^÷@( ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)^÷@( ^M)) ckx|fGg cfO{taf/ @)&$÷)&÷)! ^M)) laxfg a'waf/ 3.50 373 v'Nnf
T0-1~T0-7; T0-8~T0-11 424
@)&$÷)&÷)! ^M)) laxfg a'waf/ @)&$÷)&÷)% ^M)) ckx|fGg cfO{taf/ 3.50 aGb
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 48
@)&$÷)&÷)% ^M)) ckx|fGg cfO{taf/ @)&$÷)&÷)* ^M)) laxfg a'waf/ 3.50 373 v'Nnf
T0-1~T0-7; T0-8~T0-11 424
@)&$÷)&÷)* ^M)) ckx|fGg a'waf/ @)&$÷)&÷!@ ^M)) laxfg cfO{taf/ 3.50 aGb
@)&$÷)&÷!@ ^M)) laxfg cfO{taf/ @)&$÷)&÷!% ^M)) ckx|fGg a'waf/ 3.50 373 v'Nnf
T0-1~T0-7; T0-8~T0-11 424
@)&$÷)&÷!% ^M)) ckx|fGg a'waf/ @)&$÷)&÷!( ^M)) laxfg cfO{taf/ 3.50 aGb
S1 Ans sf] nflu MIC af6 zfvf÷pkzfvf gx/x?sf] ;d"x
d"n gx/
l/r ckm6]s Rofg]h
gx/sf]
gfd
sdf08
If]q,
x]S6/ l8hfOg axfj
1 5+650 S1 460 851
1 6+619 T0-1 63 83
hDDff 523
gf]6 M olb slDtdf ! xKtf ;Dd !) ld=ld= eGbf a9L lg/~t/ aiff{ ePdf gx/df x'g] axfjnfO{ 9f]s] ;+/rfgfaf6 lgoGq0f ul/G5 .
;DalGwt zfvf gx/x?sf] pkzfvf cfp6n]6x?sf] kfnf] / axfj ;DalGwt zfvf gx/xdf x'g] sdf08 If]qsf] cg'kftdf x'g]5 .
;DalGwt zfvf gx/sf] axfjnfO{ To; cGtu{t k|zfvf gx/x?sf] em'08 agfO{ ;dosf] kfnf]df afF8kmfF8 ug'{kg]{5 .
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 49
Annex 5 List of Training Accomplished in KIS
S.N. Subjects Target/ Groups Participants Venue Date Resource Persons
Female Male Total
KIS: Training Activities
1. Orientation workshop on IMTP (II pkgs) WUA, SMU 0 660 660 Panchgachhi, other sites 2009/10 OPD, SMU, SAHARA
2. Office management and record keeping training (4 pkgs)
WUA 0 100 100 Panchgachhi, other sites 2009/10
3. Orientation on ISF collection, Inventory collection (7 pkgs)
WUA 0 175 175 Panchgachhi, other sites 2009/10
4. Participatory M&E (2 days)
WUA NA NA NA- Panchgachhi, other sites 2009/10
5. Orientation on IMT program (WUA S0 to S16) WUA, Div. staff NA NA NA Panchgachhi 2010/11
6. Resource collection and mobilization (6 pkgs) WUA 0 180 180 Panchgachhi, Topgachi& others
2010/11
7. Study and observation tour program WUA 4 26 30 MIS & Panchakanya 2010/11
8. Constr. Mgmt.. & quality control (3 pkgs) WUA 8 79 87 Panchgachhi 2010/11
9. Office and record management (2 pkgs) WUA 4 50 54 Panchgachhi 2010/11
10. Computer basic training WUA 1 7 8 Shivgunj 2010/11
11. Basic account record keeping (4 pkgs), 2 days WUA 11 89 100 Panchgachhi& other places 19-26/4/2011 Sr. Accountant, WUA member
12. ISF collection and management (4 pkgs), 3 days
WUAs 19 83 102 Panchgachhi& other places 4-21/5/2011 AE, AE, TA-B
13. Mid-term progress review workshop WUA 02 44 46 Panchgachhi 19/5/2011 A, AEs
14. Women empowerment WUA 22 0 22 Panchgachhi 19-21/4/2011 NGO, WDO, TA-B, AO
15. Workshop training on income generation women members of WUA
WUA 35 0 35 Panchgachhi 12-14/4/2011 NGO, WDO, TA-B, AO
16. Gender awareness & women's participation (3 pkgs)
WUA 75 0 75 Lumle, Pokhara 12-14/6/2011 NGO, WDO, TA-B, AO
17. Study & exposure visit WUA 5 25 30 ChhattishMauja, Rupandehi 19-22/6/2011 AE, AO
18. Structure calibration training SMU – 7
WUA - 10
0 17 17 KIS, Jhapa 14-18/7/2010 TA-B (esp. Dr. KC Prasad)
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 50
S.N. Subjects Target/ Groups Participants Venue Date Resource Persons
Female Male Total
19. Study and exposure visit (4 days) WUA female members
30 0 30 ChhattishMauja, Rupandehi 19-22 June,2011 SMU
20. Parcellary map preparation & review training SMU 0 4 4 KIS, Jhapa 25-27/7/2010 TA-B (esp. Dr. KC Prasad)
21. Account record keeping (5 pkgs) WUA – TC 18 104 122 Panchgachhi, Mahabhara &Topgachhi
14-26/3/2012 Acc. officer, EIDD, TA-B
22. Off season vegetables farming (4 pkgs) WUA, female 105 0 105 Panchgachhi 18-21/1/2012 DAD staff, TA-B
23. Construction management and quality control (2 pkgs& 3 days for each pkgs)
WUA members 9 48 57 Panchgachhi and Baigundhara
07-09 & 27-29 Feb, 2012
Irrigation engineer, SMU & TA-B
24. Two days Workshop on WUA Capacity Development and Orientation Related to Irrigation Management Transfer (IMT)
WUA executive members
8 32 40 Panchgachhi 27-28 Jan, 2012 OPD & SMU
25 SEMP preparation and review SMU - - - KIS, Jhapa Jan 2010 - Jan 2011
OPD and subject matter experts
26. One day training of fertilizer management WUA and farmers
184 176 360 WUA office & field May 28 - June 10, 2012
AO, Agriculture – staff trainings from
ICWMP 27. Irrigation Service Fee collection WUA – Sec –
TC – Level 10 64 74 WUA Office 11 – 16 June
2012 TA, AO, SMU staff
28. Training of Trainers (TOT) Training WUA 4 20 24 Bhojpur Hotel, DamakJhapa
15 -27 June 2012
IMD, SMU, OPD, TA-B
29. Study Tour (Central WUA) WUA 4 24 28 Different Districts 5 – 8 July, 2012 Study Tour Guide - AO
30. “Review and Interaction” workshop on Present Status of IWRMP/IMT and WUA of KIS
WUA 4 25 29 Bhojpur Hotel, DamakJhapa
5-6, Dec, 2012 OPD, EIDD #1 Jhapa, TA-B
31. “On and Off Farm Water Management”
Gate Operators, Dhalpas, and Supervisors
3 21 24 Panchgachi, Jhapa 26-28 Dec, 2012 WUA, SMU, TA-B
32. “Water Users Organization Management, Resource Collection & Mobilization”
WUA 4 25 29 Panchgachi, Jhapa 1-2, Jan, 2013, 2012
WUA TOT Trainees, SMU, TA-
B
33. “On and Off Farm Water Management”
WUA main committee
4 27 31 Panchgachi, Jhapa 11-13 January, 2013
SMU, TA-B
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 51
S.N. Subjects Target/ Groups Participants Venue Date Resource Persons
Female Male Total
34. “On and Off Farm Water Management”
WUA branch committees
1 21 22 Panchgachi, Jhapa 5-7 February, 2013
SMU, TA-B
35. “ISF Collection and Management”
WUA branch & tertiary com.
13 68 81 Panchgachi, Jhapa 25 April-03 May, 2013
WUA TOT Trainees
36. “Increasing Awareness” (Chetana Abhibridhi)
WUA branch & tertiary com.
87 153 240 8 packages at various locations within KIS
07-16 May, 2013 WUA TOT Trainees
37
ISF collection and management (Two pkgs) WUA branch & tertiary com.
21 29 50 Baigundhura, Jhapa 01-02 June, 2013
WUA TOT Trainees
38 On-the-job training by TA-B staff
SMU and WUA many many many various locations various and ongoing
TA-B National and International staff
39 Study Tour (Central WUA) WUA members 5 25 30 Mahakali Irrigation Systems 30 May-4 June, 2014
SMU staff and WUA members of MIS
40 Structural calibration and water scheduling / COP for monsoon crop season (4 pkgs)
WUA BC/TC members &
dhalpas
13 100 113 Panchgachi, Jhapa 22 - 26 May, 2014
SMU staff and TA
41 Leadership development (3 pkgs) WUA branch committees
12 78 90 Panchgachi, Jhapa 3-11 February, 2015
WUA TOT Trainees
42 Canal repair, maintenance and construction management
WUA branch committees
2 28 30 Panchgachi, Jhapa 5-6 February, 2015
WUA TOT Trainees
43 Canal operation schedule development WUA branch committees
4 26 30 Panchgachi, Jhapa 7-8 February, 2015
WUA TOT Trainees
44 Leadership development (2 pkgs) WUA branch & tertiary com
14 47 61 Panchgachi, Jhapa 14-19 April, 2015
WUA TOT Trainees
45 Basic account record keeping (8 Packages)
WUA branch & tertiary com.
58 182 240 Panchgachi, Jhapa 17 May-04 June, 2015
WUA TOT Trainees & account officer
46 Leadership and Good Governance Training WUA Members All Chairmen
3 21 24 Panchigachi, Jhapa 22 Dec to 25 Dec
WUA, TOT Padam Poudel ,Dev Kumar
Basent and Bed NidhiAdhakari,
SAO-GopalPoudel, TA-IDS-2
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 52
S.N. Subjects Target/ Groups Participants Venue Date Resource Persons
Female Male Total
47 Conflict Management Training WUA Vice Chairmen
4 23 27 Panchigachi,Jhapa 27 Dec-29 Dec WUA, TOT- Padam Poudel, Dev Kumar
Basnet , SAO GopalPoudel and
TA-IDS
48 IMT Review Workshop Kankai IS 0 22 22 Panchigachi, Jhapa 25 Nov 2015 OPD, SMU, TA-B
49 M&E Training Kankai IS 0 25 25 Panchigachi, Jhapa April 3 to 4, 2016
SMU, TA-B
50 Observation Tour Kankai IS 5 27 32 KIS to Different Irrigation System
May 15 to 21, 2016
SMU, WUA
51 ISF collection administration, 24 events TC committee members newly
elected
24 84 108 Panchigachi, Jhapa Feb19-22, 2017 And SMU TA staff
52 ISF collection and management, 3 events Branch and sub branch level
SEC
7 65 72 Panchigachi, Jhapa April 2-4, 2017 TOT and SAO
53 Irrigation Schedule development 35 80 115 Panchigachi, Jhapa March 24-April 2, 2017
TOT ,IWRMO staff
54 BC COP dissemination BC WUA s (1-11) 156
members
37 114 156 Panchigachi, Jhapa Nov 19-24, 2017 TA/SMU
55 ISF collection and Management WUA Branch committee members
35 215 240 Panchigachi, Jhapa Feb 3-15, 2018 TA/SMU
56 Branch canal level COP dissemination training WUA Branch committee members
51 205 256 Panchigachi, Jhapa Nov 19, 2017- Feb 02,2018
TA/SMU
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 53
Annex-6 Field Photographs
HR of S1 canal
HR of S9 canal Diversion gate of main canal
Functional Status and Performance Evaluation of Kankai Irrigation and WUA Systems Under IMT/IWRMP
FINAL REPORT
Mannings Consult Pvt. Ltd. 54
Key interview with farmers FGD with WUAs & office staff