Upload
anonymous-bldg7qjdka
View
9
Download
0
Embed Size (px)
DESCRIPTION
production of CO2
Citation preview
Chemical Properties
Chemical names
Carbon dioxide Carbonic anhydride Dry ice Carbonic acid gas Carbonic acid anhydride
Molecular weight(lb/mol) 44.01
Specific gravity 1.555
Molecular formula C02
Molecular structure
Critical temperature(psia) 1071.0
Melting point -69.9 °F
Boiling Point -109.2 °F
Liquid Density @ 70°F (lb/ft3) 47.64
Gas Density @ 70°F 1 atm
(lb/ft3)
0.1144
Physical properties of 1-Tetradecene
State Colourless
Odor Odorless
Solubility in water Soluble
APPLICATIONSAPPLICATIONS
• Multi – industry uses for Carbon Dioxide (CO2)• Metal Industry
• Manufacturing and Construction• Chemical, Pharmaceuticals and Petroleum
• Food and Beverages• Environmental uses
PROCESS DESCRIPTION
Production of Carbon Dioxide using from Biomass
Advantages :Renewable sourcesDisadvantage:Research is needed to reduce the costs of Biomass based on fuelLand used for energy crops maybe in demand for other purposes such as farming, conservation, housing, resort and agriculture use.Produce harmful air pollution
Production of Carbon Dioxide from Water Gas Shift (WGS)
Advantages :Easy to operateMore efficient, resulting in a reaction yield greater than that achieved with existing catalysts.Can process at medium temperature (250-350ºC)Can achieve a complete CO conversion
PROCESS SELECTION
PROCESS DESCRIPTIONPROCESS DESCRIPTION
• The raw material that involved in this process is carbon monoxide (CO) and the water (H2O) that to produce carbon
dioxide (CO2) and hydrogen (H2). • This process involve water- gas shift(WGS) reaction that has
been traditionally used to produce hydrogen from the syngas, which is comprises CO and H2.
• The reaction is mildly in the exothermic and the equilibrium limited.
• When the temperature increases along the length of the reactor the extent of reaction will becomes limited. To achieve the desired extent reaction the two-stage process interstage
cooling needed.
STREAM TABLE
MARKET ANALYSIS
1. The current global CO2 demand is estimated to be 80M tonnes per annum, of which 50M tonnes per annum is used for EOR in North America.
3. The future potential demand for CO2 that could eventuate 2020 is estimated to be 140M tonnes per annum
2. The remaining 30M tonnes per annum represents the global demand of all uses, predominantly the mature industries of beverage carbonation and food industry uses
4. Based on Global CCS Institute, in 2009 Dakota Gasification Company’s Great Plains Synfuels Plant sold US$53.2m worth of CO2, whilst it produced 2.8M tonnes per annum, suggesting a price of US$19 per metric tonne produced, incorporating the cost of transportation
Figure 1: Approximate proportion of current CO2 demand by end use
MASS BALANCE:
REACTOR R-1301
SEPARATOR
hkmolnL OH /70.5992.6098.02
hkmolV
V
LVF
/3.13070.59190
70.59190
98% of the water leaving at the bottom product.
2% of the water leaving at the upper product
hkmol
n OH
/22.1
92.6002.02
Overall mass balance:
Inlet Outlet
Subtances ṅ(mol/h) Ĥ(kJ/mol) ṅ(mol/h) Ĥ(kJ/mol)
CH4 1050.6 Ĥ1 - -
O2 3151.9 Ĥ2 1050.7 Ĥ4
N2 7716.8 Ĥ3 7716.9 Ĥ5
CO2 - 1050.7 Ĥ6
H2O - 2101.3 Ĥ7
ENERGY BALANCE:
FIRED HEATER H-1301
CH4 (25ºC) : Ĥ1 =(∆Ĥf)= -74.85kJ/mol
O2 (25ºC) , N2 (25ºC) : Ĥ2=Ĥ3 = 0 O2 (417ºC) : Ĥ4 = 12.28 kJ/molN2 (417ºC) : Ĥ5 = 11.68 kJ/molCO2 (417ºC) : Ĥ6 = ∆Ĥf + Ĥ(417ºC)
= (-393.5 + 17.20) kJ/mol=-376.3 kJ/mol
H2O (417ºC) : Ĥ7 = ∆Ĥf + Ĥ(417ºC)= (-241.83 + 13.87) kJ/mol= -227.96 kJ/mol
Inlet Outlet
Subtances ṅ(mol/h) Ĥ(kJ/mol) ṅ(mol/h) Ĥ(kJ/mol)
CH4 1050.6 -74.85 - -
O2 3151.9 0 1050.7 12.28
N2 7716.8 0 7716.9 11.68
CO2 - - 1050.7 -376.3
H2O - - 2101.3 -227.96
hkJ
Q
HQout
/36.692717
)41.78637()77.771354(
nH-nHin
Inlet Outlet
Subtances ṅ(mol/h) Ĥ(kJ/mol) ṅ(mol/h) Ĥ(kJ/mol)
CO 33200 Ĥ1 13280 Ĥ5
H2 40800 Ĥ2 60720 Ĥ6
CO2 25200 Ĥ3 45120 Ĥ7
H2O 90800 Ĥ4 70880 Ĥ8
hkmolnn
CO
inCOoutCO /1992013320013280)()(
molkJ
HHHHH
HH
OfHfCOfHfCOr
fr
/81.524
)83.241)(1()5.393)(1()0)(1()52.110)(1(
))(1())(1())(1())(1(222
REACTOR R-1301References: CO(g), H2(g), CO2(g), H2O(g) at 25ºC and 1 atm.
Extent of reaction
Standard Heat of Reaction
hkJnH
molkJTTTH
molkJTTTH
molkJTTTH
molkJTTTH
in
C
C
C
C
/22.1927294)3017.1090800()5511.825200()7884.840800()5857.1233200(
/3017.1010593.3107604.0106880.003346.0
/5511.810464.710887.210233.403611.0
/7884.8108698.0103288.01000765.002884.0
/5857.1210220.2103548.0104110.002095.0
2.320
25
3122854
2.320
25
3122853
2.320
25
3122852
2.320
25
3122851
hkJ
nH
molkJTTTH
molkJTTTH
molkJTTTH
molkJTTTH
out
C
C
C
C
C
C
C
C
/13.2528066
)3635.1470880()7728.1145120()1847.1260720()9922.1713280(
/3635.1410593.3107604.0106880.003346.0
/7728.1110464.710887.210233.403611.0
/1847.12108698.0103288.01000765.002884.0
/9922.1710220.2103548.0104110.0020905.0
2.430
25
3122858
2.430
25
3122857
2.430
25
3122856
2.430
25
3122855
Inlet enthaply
Outlet Enthalpies
hkJ
molkJhkJmolkJhmolQ
nHnHHHQout in
r
/78.9773510
/22.1893214/64.2206551)/81.524)(/19220(
Energy balance for others equipment are shown in table below:
Equipment Q (kJ/h)
Heat exchanger E-1302 510693.2
Heat exchanger E-1303 8740796
Reactor R-1302 257068.61
HEAT INTEGRATION
Stream Conditions ṁ(kg/s)
Cp
(kJ/kg·ºC)Tin (ºC) Tout (ºC)
1 Hot 1.043 Cp1 430 203
2 Hot 1.043 Cp2 260.7 185
3 Hot 1.043 Cp3 185 50
CmolkJC
CmolkJC
CmolkJC
CmolkJC
pCO
pH
pCO
pCO
/0375.0)2.430(10593.3)2.430(107604.0)2.430(106880.01046.33
/0294.0)2.430(108698.0)2.430(103288.0)2.430(1000765.01084.28
/0312.0)2.430(10220.2)2.430(103548.0)2.430(104110.01095.28
/0507.0)2.430(10464.7)2.430(10887.2)2.430(10233.41011.36
3122853
3122853
3122853
3122853
2
2
2
32 dTcTbTaCP Calculation Cp every components :
Stream 1:T=430.2ºC
Components Cp (kJ/mol·ºC) MW Cp (kJ/kg·ºC) Mole Fraction, X
Cpi X
CO2 0.0507 44.01 1.1515 0.2375 0.2735
CO 0.0312 28.01 1.1138 0.0699 0.0779
H2 0.0294 2.016 14.5894 0.3196 4.6628
H2O 0.0375 18.016 2.0838 0.3731 0.7775
Total 5.7916
Components Cp (kJ/mol·ºC) MW Cp (kJ/kg·ºC) Mole Fraction, X
Cpi X
CO2 0.0436 44.01 0.9903 0.2375 0.2352
CO 0.0299 28.01 1.0691 0.0699 0.0747
H2 0.0290 2.016 14.3943 0.3196 4.6004
H2O 0.0352 18.016 1.9547 0.3731 0.7293
Total 5.6396
T=230ºC
CkgkJC p /152.06396.57916.51
CskJCm p
/16.0152.0043.1
Stream Conditions ṁCp
(kJ/s·ºC)Tin (ºC) Tout (ºC)
1 Hot 0.16 430 203
2 Hot 0.052 260.7 185
3 Hot 0.077 185 50
For stream 1:
Repeat the same method for stream 2 and stream 3 .
Step 1 : Minimum approach temperature ∆Tmin
The value 10 ºC is chosen in this system.
Step 2: Temperature Interval Diagram
Streams 1 2 3
ṁCp
(kW/ºC)0.16 0.052 0.077
430.2 420.2
260.7 250.7
203 193
185 175
50 40
kWQ
kWQ
kWQ
kWQ
TCmQ
D
C
B
A
p
40.10)50185(077.0
32.2)185203(077.0)185203(052.0
23.12)2037.260(052.0)2037.260(16.0
12.27)7.2602.430(16.0
Step 3: Cascade Diagram
Cascade diagram
It can be shown in this system it does not have pinch because heat is only cascade downward and rejected to cold utility.
In this system, there is no need to supply energy from the hot utility to the process.
This case is refer as threshold problem with respectively no cold utility or hot utility and without pinch point.
Threshold problems only need a single thermal utility either hot or cold but no both and over a range of minimum temperature difference ranging from zero to threshold temperature.
HEAT EXCHANGER(E-1303)
From table 11.11, the following heuristics is used:
Rule 1 - F=0.9 for shell and tube heat exchanger, there is no phase change.
Rule 6 - ∆T = 10 ⁰C
Rule 7 - cooling water inlet is 30˚C and maximum outlet 40˚C
Rule 8: Heat transfer coefficient, for water to liquid, U= 850 W/m2 ⁰C
The cold outlet is 50⁰C
The hot inlet is 185⁰C
∆T hot = 185⁰C - 40˚C = 145 ⁰C ∆T cold = 50⁰C - 30˚C = 20 ⁰C ∆Tlm = ∆T hot - ∆T cold / ln [∆T hot / ∆T cold] ∆Tlm = (145⁰C) – (20 ⁰C ) / ln [145 ⁰C /20 ⁰C]= 63.01˚C
Q= 242800 W Q=UAF∆Tlm
242800W = (850 W/m2.˚C) A (0.9) (63.01)
A = 5.04 m2
FURNACE (H-1301)
From table 11.11, use the following heuristic :
Rule 13 – Equal heat transfer in radiant and convective sections
Radiant rate = 37. 6 kW/ m2, Convective rate = 12.5 kW/ m2
Duty =192.42 kW
Area radiant section = (0.5)(192.42)/(37.6) = 2.56 m2
Area convective section = (0.5)(192.42)/(12.5) = 7.70 m2
REACTOR
From table 11.11, the following heuristics is used:
Rule 1 – The rate of reaction in very instance is established on the laboratory
Rule 2 – Dimensions of catalyst in packed bed 2 – 5 mm (powder)
Rule 13- The value of a catalyst may improve the selectivity.
-r carbon dioxide = ko exp ( −EaRT )P methanol
-r carbon dioxide = 296.81 exp ( −40.739ሺ8.314ሻ(698.1)) 1
-r carbon dioxide= 296.51
V= 𝐹𝑎𝑜−𝑟 𝑐𝑎𝑟𝑏𝑜𝑛 𝑑𝑖𝑜𝑥𝑖𝑑𝑒 1𝑑𝑥0.60
V = 190000ሺ44ሻ1.98296.51 (0.6− 0)
V=8486L
VESSEL (V-1301)
From table 11.6, the following heuristics is used:
Rule 3 – Gas-liquid phase separators are usually vertical vessel
Rule 4 – L/D between 2.5 and 5 with optimum at 3.0
Rule 5 – Liquid holdup time is 5 min based on ½ volume of vessel
Rule 9 – Gas velocity in gas/liquid separators, u=√𝑝𝑙𝑝𝑣 − 1 , k=0.0305
Rule 12 – Good performance can be expected at velocities of 30% - 100% of those calculated
with given k, with 75% is popular.
From the stream table
Vapor flow = Stream 9 =2680.98 kg/h P=12.7 bar T = 50°C
Liquid flow = Stream 10 = 1075.50 kg/h P= 11.7 bar T = 50°C
ρv = 0.630 kg/m3 ρl = 958 kg/m3
From the rule 9
u = 1.18 m/s
uact = (0.75)(1.18m/s) = 0.885 m/s
mass flow rate of vapor = uρvπD2/4 = 2680.98/h x 1h/3600s = 0.744kg/s
solving for D , D= 1.33 m
From the rule 5
Volume of liquid = 0.5LπD2/4 = 0.895L
5min of liquid flow = [(5)(60)(1075.50)]/[958/3600] = 0.094m3
Equating the two results above, L= 0.11 m3
From the rule 4
L/D should be in the range 2.5 to 5 but in this case L/D = 0.08 (not in ranged)
So change L=2.5D = 3.33 m.
Therefore, V-1301 should be vertical vessel with D = 1.33m, L= 3.33 m
Bare Module Cost of EquipmentBare Module Cost of EquipmentEquipment
Cp˚ (2001)
($)
CBM (2001)
($)
CBM ˚ (2001)
($)
Heat Exchanger
E-1301
E-1302
E-1303
57 650.9
28 133.8
57 777.6
196 160.0
95 725.3
196 588.3
189 671.5
92 560.2
190 088.3
Fired Heater
H-1301
169 572
440 289.3
440 289.3
Vessel
V-1301
4 618.8
24 307.8
18 798.5
Reactor
R-1301
R-1302
91 891.0
69517.1
367 564.0
278 068.4
367 564.0
278 068.4
Total 479 161.2 1 598703.1 1 577 040.2
CEPCI 2014 = 576.1
CBM (2014) = CBM (2001) (576.1/394)
CBM (2014) = (1 598703.1) (576.1/394) = $ 2 337 596.08
•VESSELV-1301Vertical
Carbon steelL = 1.83 m D = 0.61 m
Maximum pressure rating of 19 bar From Table A.4;Volume = 0.5348 m3 B1 = 2.25
B2 = 1.82CBM = Cp˚ [ B1 + B2 FP FM ]
From Appendix A Cp˚/ V = $ 8 636.4 / m3
Cp˚(2001) = x 0.5348 m3 = $ 4 618.8
Equation A.2: From Table A.3;FP = for P>-0.5 barg FM = 1
FP = = 1.6554
CBM (2001) = Cp˚ (2001) [ B1 + B2 FP FM ] = $ 4 618.8 [ 2.25 + 1.82 (1.6554)(1)]
= $ 24 307.7CBM (2014) = CBM ˚ (2001) (576.1/394) = $ 24 307.7 (576.1/394)
= $ 35 542.3
• HEAT EXCHANGERE-1301
Floating head, carbon steel, shell and tube designProcess stream in tubes
A = 67.2 m2
Q = 1580 MJ/hMaximum pressure rating of 19 bar
CBM = Cp˚ [ B1 + B2 FP FM ] From Table A.4;From Appendix A Cp˚/ A = $ 857.9 / m2 B1 = 1.63Cp˚(2001) = x 67.2 m2 = $ 57 650.9 B2 = 1.66
Equation A.3: From Table A.3;
log FP = C1 + C2 log P + C3 (log P)2 FM = 1From Table A.2;
C1 = 0.03881, C2 = -0.11272, C3 = 0.08183log FP = 0.03881 - 0.11272 log 19 + 0.08183 (log 19)2
FP = 1.0678
CBM (2001) = Cp˚ (2001) [ B1 + B2 FP FM ] = $ 57 650.9 [ 1.63 + 1.66 (1.0678)(1)]
= $ 196 160CBM (2014) = CBM ˚ (2001) (576.1/394) = $ 196 160 (576.1/394)
= $ 286 821.77
•Fixed Capital Investment (FCI)
CTM = 1.18 = 1.18 ($ 1 598 703.1) (576.1/394)
= $ 2 758 363.4
CGR = CTM + 0.50 = $ 2 758 363.4 + 0.50 ($1 577 040.2) (576.1/394)
= $ 3 911 323.9
•Cost of Operating Labor (COL)
NOL = ( 6.29 + 31.7P2 + 0.23Nnp )0.5
P = 0, because no handling particulate solid NOL = ( 6.29 + 31.7(0)2 + 0.23(6) )0.5
= 2.77The number of operations required per shift = 2.77
Operating labor = 4.5(2.77) = 12.5 (round to the nearest integer yields 13 operators)
Labor Cost = 13 x $ 59 580 = $ 774 540/year
Equipment No of equipment Nnp
Reactors
Heaters
Exchangers
Vessels
2
1
3
1
2
1
3
-
Total 6
No Types Description Price Price/year
1. High pressure steamP – 19 bar
Q – 1580 MJ/h $ 17.70 /GJ $ 232 846.5
2. High pressure steamP – 19 bar
Q – 3764 MJ/h$ 17.70 /GJ $ 67 021.2
3. High pressure steamP – 19 bar
Q – 455 MJ/h$ 17.70 /GJ $ 554 434.9
4. Natural gasP – 19 bar
Thermal efficiency – 80%$ 13.88 /GJ $ 92 407.5
Total = $ 946 728.1 / year
•Fired Heater H-1301Duty = 800 MJ/h Cost = $ 13.88 / GJ
Thermal efficiency = 75% t = 0.95
Yearly Cost = Q Csteam t = x x x x x 0.95 = $ 92 407.5 / year
•Heat Exchanger E-1301
Duty = 1 580 MJ/h Cost = $ 17.70 / GJt = 0.95
Yearly Cost = Q Csteam t = x x x x x 0.95
= $ 232 864.5 / year
•Cost of Waste Treatment (CWT)Assume the waste treatment primary (filtration)
Component of water = 1059.1 kg/h Density = 988.04 kg/m3
Yearly Cost = (Yearly flowrate)(Cost per unit mass)(Density) = x x x x x 0.95
= $ 365.7 / year
•Cost of Raw MaterialsComponent
Mass Flowrate
(kg/h)
Cost of Material
($/kg)
Yearly Cost
($/year)
CO 929.93 0.028 294 077.3
CO2 1109.05 0.16 1 476 722.3
H2 82.42 0.0025 1 714.7
H2O 1621.35 5.7x10-3 76 909.4
Total = $ 1 849 423.7 / year
•Cost of Manufacturing (COMd)COMd = 0.18FCI + 2.73COL + 1.23 (CUT + CWT + CRW)
= 0.18($ 3 911 323.9/year) + 2.73($ 774 450/year) + 1.23 ($ 946 728.1/year + $ 365.7/year + $ 1 849
423.7 /year) = $ 6 258 249.03 / year
•Cost of LandLand Cost = 10 acres x = $ 10 000 000
•Working CapitalWorking Capital (WC) = x FCI = 0.2 x $ 3 911 323.9
= $782 264.8
•Assumptions: Land cost, L = $ 10 000 000
Total Fixed Capital Investment, FCIL = $ 3 911 323.9Fixed Capital Investment during year 1 = $ 2 058 823.9Fixed Capital Investment during year 2 = $ 1 852 500
Plant start-up at end year 2Working Capital = $782 264.8
Yearly Sales Revenue, R = $ 10 000 000Cost of Manufacture without Depreciation, COMd = $ 6 258
249.03Taxation rate = 25% = 0.25
Interest rate = 2.96% = 0.0296Plant salvage value, S = $ 0
Depreciation by 5 year MACRSPlant life = 10 years
Year Investment dkFCI - ∑dk R COMd
(R -COMd -
dK) (1-t) + dkCash Flow
Cumulative Cash
Flow
0 -10000000.0 - 3911323.9 - - - -10000000.0 -10000000.0
1 -2058823.9 - 3911323.9 - - - -2058823.9 -12058823.9
2 -2634764.8 - 3911323.9 - - - -2634764.8 -14693588.7
3 - 782264.8 3129059.1 10000000 6258249.03 3001879.4 3001879.4 -11691709.3
4 - 1251623.6 1877435.5 10000000 6258249.03 3119219.1 3119219.1 -8572490.2
5 - 750974.2 1126461.3 10000000 6258249.03 2994056.8 2994056.8 -5578433.4
6 - 450584.5 675876.8 10000000 6258249.03 2918959.4 2918959.4 -2659474.0
7 - 450584.5 225292.3 10000000 6258249.03 2918959.4 2918959.4 259485.4
8 - 225292.3 0.0 10000000 6258249.03 2862636.3 2862636.3 3122121.7
9 - 0.0 0.0 10000000 6258249.03 2806313.2 2862636.3 5984758.0
10 - 0.0 0.0 10000000 6258249.03 2806313.2 2862636.3 8847394.3
11 - 0.0 0.0 10000000 6258249.03 2806313.2 2862636.3 11710030.6
12 2282264.8 0.0 0.0 10000000 6258249.03 2806313.2 5088578.0 16798608.6
Payback Period (PBP) = 1 years
Cumulative Cash Position (CCP) = $ 16.8M
Cumulative Cash Ratio (CCR) = 2.14
Rate of Return on Investment (ROROI) = 43%
Non-discounted After-Tax Cash Flows
Year Non-discounted Cash Flow Discounted Cash Flow Cumulative Cash Flow
0 -10000000.0 -10000000.0 -10000000.0
1 -2058823.9 -1999634.7 -11999634.7
2 -2634764.8 -2485448.6 -14485083.3
3 3001879.4 2750347.9 -11734735.4
4 3119219.1 2775695.0 -8959040.3
5 2994056.8 2587720.5 -6371319.9
6 2918959.4 2450286.4 -3921033.4
7 2918959.4 2379843.1 -1541190.4
8 2862636.3 2266824.5 725634.1
9 2862636.3 2201655.5 2927289.7
10 2862636.3 2138360.1 5065649.7
11 2862636.3 2076884.3 7142534.0
12 5088578.0 3585700.7 10728234.7
Discounted Payback Period (DPBP) = 1.3 years
Net Present Value (NPV) = $ 10.73M
Present Value Ratio (PVR) = 1.74
Discounted Cash Flow Rate of Return (DCFROR) = 12.15%
Discounted After-Tax Cash Flows
The value of discounted cash flow rate of return (DCFROR) found at NPV = $ 0. Therefore, interpolation method was used.
DCFROR = 10.00 + 5(0.43) = 12.15 %
Interest or Discount Rate (%) NPV ($ M)
0
2.96
10.00
15.00
20.00
16.80
10.73
1.62
-2.15
-4.67
62.115.262.10
00.1000.1500.10
DCFROR
Conclusion Conclusion
•In term of the time basis, the payback period increases as the discount rate increases. It shows that the payback period increases from 1 to 1.3 years.
•In term of the cash basis, when replacing the cash flow with the discounted cash flow decreases the value at the end of the project. It shows that the
value at the end of the project dropped from $ 16.80M to $ 10.73M.•In term of the cash ratios, discounting the cash flow gives a lower ratio. It
shows that the ratio dropped from 2.14 to 1.74.
Comparison Non-discounted Cash Flow Discounted Cash Flow
PBP / DPBP
CCP / NPV
CCR / PVR
ROROI / DCFROR
1 year
$16.80M
2.14
43%
1.3 years
$10.73M
1.74
12.15%