Milestones and Key Dates
Milestone Meeting Input Output
Sketch Review
BoardsGraphic and textile artInspiration SamplesMarket Intelligence / Comp Analysis
Direction for ADM SampleProduct StrategyHigh Level ProjectionsCost Expectations / TargetsCapacity Reservation
Assortment Definition Meeting
(ADM)
SamplesBest CostGeneric TNAs / Early Booking Request (if needed)
Direction for ADM SamplingCost Feedback at Program levelProjections at program levelGreige Commitments Capacity Booking
Assortment Finalization
Meeting (AFM)
Updated samples reflective of final productFinal CostConfirmed Vendor and Factory Allocation (with ID and Ethical Rating)
Final Cost ApprovalFormal WM CommitmentADSFinal TNA and Delivery Confirmation
Spring 2015 Generic TNA
Key Milestones DateSketch Review 2/24/2014Cost Request from SourcingWith Target Costs, Fabric Cots, Projections and TNA - YY Available (3/7-3/14)
3/4-3/7
Costing Due to LT Sourcing(Cost meetings during March Trip)
3/11-3/25
Assortment Definition Meeting (ADM) 4/7-4/30
Feedback from ADM Meeting(Cost / Projections / Product)
4/15-5/1
Final Costs due for AFM 4/22-5/7Capacity Reservation with Mills and Factories
5/1-5/15
Greige / Yarn Bookings (SP+SU) 5/1-5/15AFM Meetings 5/15-5/30WM Final Program Confirmation 6/5-6/20ADS Due 6/12-6/30Spring Colors Booked 6/12-6/30Fabric X Mill 7/30-8/15Fabric in Factory 8/15-9/15Sewing Months (Spring - Summer) 9/27-1/28
X Factory Dates
Spring: 10/27-12/27 (Initial thru replenishments)Summer: 1/28-2/28 (Initial and Replenishment)
Walmart Product S.O.P.
Pre-productionFabric and color approval
(Lab dip, shadeband)Fit ApprovalAE Visual Approval CTL Testing
ProductionPP TestingTOP TestingTOP Visual ApprovalDupro Testing