36
COMPANY PROFILE All of the information and presentation material, including text, images and usage of logos , is either the property of, or used with permission by MAJU INTEGRATED ENGINEERS SDN BHD (ENERGY DIV.) The information may not be distributed, modified, displayed or reproduced without the prior written permission from MIE. MAJU INTEGRATED ENGINEERS SDN BHD (MIE - ENERGY DIVISION) 491172 -T ENERGY DIV. MAJU INTEGRATED ENGINEERS WWW.MIE-ENERGY.COM

MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

COMPANY

PROFILE

All of the information and presentation material, including text, images and usage of logos , is either the property of, or used with permission by MAJU INTEGRATED ENGINEERS

SDN BHD (ENERGY DIV.) The information may not be distributed, modified, displayed or reproduced without the prior written permission from MIE.

MAJU INTEGRATED ENGINEERS SDN BHD

(MIE - ENERGY DIVISION)

491172 -T

ENERGY DIV.MAJU INTEGRATED ENGINEERS

WWW.MIE-ENERGY.COM

Page 2: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one

of Malaysia’s premier Civil, Structural, Mechanical and Electrical works for buildings and

infrastructures services.

In 2014, MIE set up a new division known as MIE-Energy Div. (MIE-Energy) towards diversifying

the business to penetrate energy sector, such as Oil & Gas (Upstream and Downstream),

Renewable Energy, Subsea, Power Plant and R&D/Technology industries, apart from boosting

young local talent in creating a multi-disciplinary engineering services in these industries.

Serving the sector for more than a decade, MIE-Energy proudly stands as a local unique

MALAYSIAN company that provides project efficiency delivery across project lifecycles, from

concept to final project delivery engineering solutions.

With integrated local expertise, joint-venturing, partnership as well as collaboration with

international partners, it drives us to become one of the comprehensive superiors to deliver

practical performance solutions to our clients for their asset reliability, quality, safety and

economics.

INTRODUCTION

WWW.MIE-ENERGY.COM

2017

TECHNOLOGY AND

PRODUCT DIVISION

350k manhours within 3

years of establishment

(Energy Division) and

expanded to more than 60

employees

2014

MIE – ENERGY DIV.

New division setup called as

MAJU INTEGRATED

ENGINEERS – ENERGY

DIVISION, with a vision to

boost the oil and gas market

sector

1999

INCEPTION INTO

MARKET

Incorporated in 1999 and

started as Malaysia’s Premier

Civil, Structural, Mechanical

& Electrical for Buildings &

Infrastructure

2015

INTERNATIONAL

Secured international

projects in Thailand and

Singapore

2021

PRESENT

• Securing major contracts

from reputable clients and

has grown up to over 200

employees

• Established footprint in

South East Asia (SEA) i.e.

Thailand, Indonesia,

Singapore and Vietnam

TO-DATE

WITHOUT LOST-TIME INJURY

1.8MILLION

SAFE

MANHOURS

OUR

VALUES & BELIEF

Empowering the excellentUnleash the true potential of our talent in

delivering exceptional result.

Mutual RespectEnables our people to work across functions and

at all levels in unlocking and maximizing

opportunities.

IntegrityUphold the values of integrity in innovating

creative solutions without compromising people,

environment, assets and reputation.

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 3: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

ABOUT US – OUR GROUP

WWW.MIE-ENERGY.COM

PARTNERSHIP

UNIVERSITY INDUSTRIAL PARTNERTHAILAND & MYANMAR

ENERGY DIV.MAJU INTEGRATED ENGINEERS

MAJU INTEGRATED ENGINEERS SDN BHD (MIE)

MIE OFFSHORE SOLUTIONS SDN BHD (MOFS)

• ENGINEERING SERVICES FOR ONSHORE & OFFSHORE

(Feasibility Study, Concept Select, Conceptual Study, FEED/Basic Engineering, Detailed

Engineering , Specialized Study, As-Builting)

• BROWNFIELD & GREENFIELD PROJECTS

ENERGY DIV.

• ENGINEERING & CONSTRUCTION (E&C), R&D/TECHNOLOGY, TRANSPORTATION &

INSTALLATION, ASSET INTEGRITY MANAGEMENT, MANPOWER SUPPLY AND MOBILE

OFFSHORE DRILLING UNIT (MODU)

• ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION & HOOK-UP &

COMMISSIONING, 3D LASER SCANNING, PROVISION OF CHOKE VALVE SUPPLY & R&D/

TECHNOLOGYMIE ENGINEERING SOLUTIONS CO., LTD.

(THAILAND REGISTERED COMPANY)

TUAH ENERGY SDN BHD (TESB)

• PROJECT MANAGEMENT, PROCUREMENT, FABRICATION, CONSTRUCTION &

COMMISSIONING, TECHNOLOGY & SOLUTIONS PROVIDER, PRODUCTS, INSPECTION &

MAINTENANCE AND SPECIALIST MANPOWER SUPPLY

Page 4: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

Jack-Up Rig Services

Engineering Services (Feasibility Study / Conceptual / FEED / Detailed Design/ Specialized Study / As-Builting)

Procurement / Fabrication

Installation / Hook Up & Commissioning / Decommissioning

Asset Integrity Management

Laser Scanning Services

Products

OUR SERVICES

WWW.MIE-ENERGY.COM

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Topside Substructure Subsea Floaters Petrochemical Refinery Power Plant

Strategic Thinking & PlanningInnovative Design, Supplied & Project SolutionsCreative & Cost Effective SolutionsQuality DeliverablesHighest Safety Requirement

R&D / Technology

Page 5: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

OFFICE LOCATIONHeadquarters & MIE Design Offices

HEADQUARTERS

BANDAR TASIK SELATAN

T4-2-2, TOWER 4, MAJU LINK, JALAN LINGKARAN TENGAH 2 (MRR2), 57100 BANDAR TASIK SELATAN, KUALA LUMPUR(MIE ENERGY HQ)

150

KERTEH

LOT 50080, TINGKAT ATAS,JALAN KEMAMAN-DUNGUN, KAMPUNG BARU,24300 KERTEH, KEMAMANTERENGGANU(KERTEH OFFICE)

20

LOT 1463&1464, JALAN MACHINDA, LUTONG, 98100, MIRI,SARAWAK(MIRI OFFICE)

MIRI

20KOTA KINABALU

BLOCK NO. F, LOT 1,1ST FLOOR, LINTAS JAYA SHOP LOT,88300 DISTRICT OF PENAMPANGSABAH(KK OFFICE)

10

BINTULU

LOT 7668, 3RD FLOOR, BLOCK 31, KEMENA LAND DISTRICT, 97000, BINTULU, SARAWAK(BINTULU OFFICE)

15

THAILAND

5

10/7, MOO 2, SUKHUMVIT ROAD, T.BANGLAMUNG, ABANGLAMUNG, CHONBURI 20150 THAILAND(THAILAND OFFICE)

WWW.MIEOFFSHORE.COM.MY

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 6: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

CORPORATE TEAM

WWW.MIE-ENERGY.COM

ENERGY DIV.MAJU INTEGRATED ENGINEERS

HEAD OF PROJECTS & ENGINEERING

Ir. AZAN ZAINUDDIN

FINANCE DEPARTMENT

MOHD HAFIZ MOHD SHUIB

HR/ADMIN DEPARTMENT

SAZREEN MOHAMED HUSSEIN

MIE ENGINEERING SOLUTIONS CO. LTD

(THAILAND)

SUPAPON SAE-BE

ENGINEERING DEPARTMENT

Ir. MOHD FADHIR AKHKAR ALI

CHIEF OPERATING OFFICER

Ir. AHMAD NAZWAN MAT ZIN

MANAGING DIRECTOR

Ir. MAT JUSOH MAMAT

PROJECT MANAGEMENT DEPARTMENT

Ir. MOHAMAD SETH FARABI ISMAIL

PROJECT SERVICES DEPARTMENT

SAIFUL ADLI MOHAMAD

COMMERCIAL, CONTRACT & PROPOSAL DEPARTMENT

RAINANI JAMALODIN

QHSSE DEPARTMENT

REZA SYAHRUZZAMAN MOHAMED

BUSINESS DEVELOPMENT DIRECTOR

BAIZURI JUSOH

IT DEPARTMENT

SYUKRI HAKIM ABDUL RAHMAN

SATELLITE OFFICE(DOMESTIC – MALAYSIA)

KERTEH

MIRI

BINTULU

KOTA KINABALU

MIE OFFSHORE SOLUTIONS SDN BHD

Ir. AHMAD NAZWAN MAT ZIN

PLANNING DEPARTMENT

WAN MOHD IFTITAHWAN KAMAL

TUAH ENERGY SDN BHD

SAIFUL ADLI MOHAMAD

CORPORATE & BUSINESS SUPPORT

JANISA ALDEAN

Page 7: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

PROJECT EXPERIENCES

CLIENTELE

More than 30

International Market Penetration

Through partnership, collaboration & joint-venture

CONTRACTSAWARDED

Brownfield & Greenfield

368

Onshore & Offshore

More than

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 8: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

OUR CLIENTELE

WWW.MIE-ENERGY.COM

HALLIBURTON BAYAN PETROLEUM

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 9: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

OUR LICENSE & CERTIFICATE

WWW.MIE-ENERGY.COM

STANDARDISED WORK AND EQUIPMENT CATEGORIES (SWECs)

ISO 9001:2015

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 10: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

ENERGY DIV.MAJU INTEGRATED ENGINEERSOUR SOFTWARE

WWW.MIE-ENERGY.COM

Discipline Software

• Process Engineering

HYSIS ICON Petronas

PIPESIM

FlareNet

• Piping Engineering

AVEVA PDMS Naviswork

CAESAR II SmarPlant 3D

AutoCAD

ZWCAD

• Mechanical Engineering

TANK SolidWorks

PVelite AnSYS

HTRI

• Electrical EngineeringETAP

EDSA

• Instrumentation

Engineering

Instrument Calculation (InstruCalcs)

Intools (Smart Plant Instrumentation)

• Structural / Naval

Architecture Engineering

/ Civil

SACS Executive Bentley Openroad

BOCAD Tedds

MOSES Orion

STAAD Pro Prota

Tedds S-Frame

MX Road Profesional Bentley Power Civil

Miduss 98

• Pipeline EngineeringAutoPIPE Mathcad

Orcaflex Offpipe

• Project ManagementMicrosoft Project 2016

Primavera Enterprise P3e

Page 11: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

CASE STUDY 1

Strength & Fatigue Analyses Assessment Of Flare Stack Structure

WWW.MIE-ENERGY.COM

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Case Study Background and Problem Statement

• Client has identified a partly damaged and severely corroded flare tower. It has become aconcern to Client to ensure normal operability of this flare tower without compromisingthe structural integrity of the structure, loss of live, damage to the environment and lossof reputation.

• The study split in two phase as below:

• The flare tower not fit for service and is not recommended for furtherstrengthening or repair.

• For long term, it’s suggested to change the entire flare tower with a new one oras minimum to replace the lower part flare tower with new fabricated section.

• Due to this, Phase 2 is activated by implement the replacing of lower part offlare tower.

Our Proposed Design

Phase 1 Phase 2

• To identify the weak points and

compromising areas subject to normal

operation

• If the finding indicating sound and fit for

Operation, the Flare will not be assessed

in Phase 2. However, if the assessment

strongly suggests strengthening /

demolishment / replacement then Phase 2

is required.

• To provide options for strengthening

and possibility to completely re-

design a new flare tower structure.

• To come out with constructability

and construction scope of work

• To report the strength, fatigue and vortex shedding of the Flare Tower:Strength➢ Two structural components are found to be over-utilised. The locations are the lower flare

tower structure and the blower duct side reinforcements.Fatigue➢ The entire flare tower structure is noted to be free from fatigue damages. This in short

means that the flare tower structure is not influenced to wind induced fatigue damages.Vortex Shedding➢ Although the flare tower structure has relatively a larger D/t ratio, it is observed to be fairly

stiffened, due to the presence of platform supports, baffle plate, nozzles, openings andblower duct inlet. In short, the flare tower not influenced by the vortex induced vibration.

Page 12: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

CASE STUDY 2

Life Boat 2 DAVIT – Permanent Repair

WWW.MIE-ENERGY.COM

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Case Study Background &Problem Statement

• After conducting 1.1 Dynamic Load test on LB 2 Davit, crack onweld was found at leg 1 (AFT) and crack on parent metal on Leg 2(FWD) by using MPI technique. EMA only can detect crack depthuntil 2mm due to certain limitation.

• Further grinding off AFT leg, it was found the crack length increasesfrom 80mm to 200mm.

• To present preliminary assessment finding of the cracks foundafter lifeboat davit testing.

• To provide results of manual calculations of foundation stressesand unity checks before and after modification.

• To present load reactions of the davit structure from thesimplified SACS analysis.

• To highlight results for Finite Element (FE) verification analysis.• Conclusion and recommendation for lifeboat 1 davit modification.

Our Proposed Design

• The comparison of stresses shows good correlation between manual calculations and FE results.• The stresses at the hotspot area reduced significantly (up to 90%) after modification.• The design of the proposed modification strengthening can be considered very effective in

solving the crack issue. This is further evidence by no cracks found after the re-test.

1

2

3

Figure 1.0 : Davit leg-Foundation Footprint (Before and After Modification)

Figure 2.0: Loads Acting on Davit Structure

Table 2.0: Summary of Reactions at Davit Leg Foundation

Figure 3.0: Davit Leg-Foundation FE Models

(Before and After Modification)

Table 3.0: Comparison of Combined Stresses

• In order to obtain the more accurate reactions at davitfoundation subjected to applied load during lifeboat testing, asimplified SACS analysis has been performed.

• List of loads considered acting on davit structure are as below:✓ Design weights of lifeboat✓ Dynamic Factors considered✓ Davit self weight✓ Lateral reactions from pulley on top of davit✓ Wind was considered to be negligible during

lifeboat testing

• Manual calculations have been performed to obtain estimationof the stresses and unity checks at weld and steel at davit leg-foundation interface (see Figure 2c below).

• A FE analysis has been performed to verify the reactionsand results obtained earlier. Details of the foundation as-built and strengthening have been carefully considered inthe FE model. Load reactions considered were from thesimplified SACS analysis

Manual Calculation of Stresses at Foundation

Simplified SACS Analysis

Finite Element (FE) Analysis

Page 13: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

CASE STUDY 3

Test Separator Optimization

WWW.MIE-ENERGY.COM

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Existing Test Separator DesignCase Study Background and Problem Statement

• D21JT-A infill drilling was performed in 2017 under SIPROD campaign• The infill wells topside facility was designed based on individual well maximum flowrate

of 1500 BPD oil plus minimum watercut• However, during well completion and unloading, it came to surprise that one of the infill

well is capable of producing maximum 3000 BPD oil instead• To cope with the increased oil production rate, ROC requested MIE to assess the

feasibility of using the existing Test Separator by allocating the water leg for oil collection

Test Separator Capacity Assessment

Modified Test Separator

Advantages of the Proposed Design

• No changes to existing dimension of the vessel and its inlet/outlet nozzles is required• However, following modification is anticipated:

• Water weir and the back weir of the oil bucket are to be removed• Water related level instruments isolation valve is to be closed• Level setpoints adjustment are required• Changes of setpoints to be reflected in PMCS

Page 14: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

GREENFIELD EXPERIENCEONSHORE

WWW.MIE-ENERGY.COM

BASIC ENGINEERING DESIGN FOR EFFLUENT MANAGEMENT AT SOURCE (EMAS) PROJECT

• EMBARK ON A DEVELOPMENT OF BASIC ENGINEERING DESIGN FOR EFFLUENT MANAGEMENT AT SOURCE PROJECT TO TREAT OILY

WATER AND MEET REGULATORY LIMIT TO IER 2009 STANDARD “A”

• SG. UDANG, MELAKA

• YEAR 2019

• 45,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 15: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

GREENFIELD EXPERIENCEONSHORE

WWW.MIE-ENERGY.COM

ENGINEERING DESIGN SERVICES FOR PROPOSED

MODIFICATION TO EXISTING EXPANDABLE POLYSTRYENE

(EPS) AND TAMOL PLANT

• TOTAL CONVERSION FROM EXISTING EPS PLANT INTO

POLYMER DISPERSION PLANT

• PASIR GUDANG, JOHOR, MALAYSIA

• REACTOR, VESSEL, AGITATORS, TANK FARMS AND NEW

DELUGE SYSTEM

• YEAR 2014

• 35,000 MANHOURS

ENGINEERING OF GASIFIER STEAM BOILER

RENEWABLE ENERGY PLANT

• NEW BUILD DESIGN FOR GASIFIER STEAM

BOILER RENEWABLE ENERGY POLYMER

PLASTIC PARK

• KERTEH, MALAYSIA

• YEAR 2014

• 55,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 16: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

GREENFIELD EXPERIENCEOFFSHORE

WWW.MIE-ENERGY.COM

PROVISION OF CONCEPTUAL & PRE-FEED

STUDY FOR LARAK & BAKONG WHP FOR

SK408 FIELD DEVELOPMENT

• UNMANNED WELLHEAD PLATFORM

• SARAWAK, MALAYSIA

• TOPSIDE : 475 MT

• SUBSTRUCTURE : 1,100 MT

• 80 MTRS WATER DEPTH

• YEAR 2015

PROVISION OF CONCEPTUAL FOR BAKONG

PRODUCTION PLATFORM FOR SK408 FIELD

DEVELOPMENT

• 6-LEGGED CPP

• SARAWAK, MALAYSIA

• TOPSIDE : 3,500 MT

• SUBSTRUCTURE : 1,800 MT

• 85 MTRS WATER DEPTH

• YEAR 2015

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 17: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

BROWNFIELD EXPERIENCEOFFSHORE & ONSHORE

WWW.MIE-ENERGY.COM

UMBRELLA CONTRACT ENGINEERING SERVICES FOR FACILITIES IMPROVEMENT PROPOSAL (FIP) & PLANT CHANGE

• 3 YEARS + 1 YEARS (OPTIONAL) EXTENSION : YEAR 2018 TILL 2022

• COVERAGE LOCATION : KL/MELAKA/KERTEH/KEMAMAN/GEBENG/GURUN/MIRI/BINTULU/ KOTA KINABALU

• ANY OF BROWNFIELD ENGINEERING SERVICES FOR ALL PETRONAS ASSET FOR PROJECT SERVICES, FEASIBILITY STUDY/BASIC, FEED,

DETAILED DESIGN AND OTHER SPECIALIZED ENGINEERING (FOR ONSHORE & OFFSHORE)

• ESTIMATED MORE THAN 2.0M MANHOURS THROUGHOUT CONTRACT DURATION

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 18: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

BROWNFIELD EXPERIENCEONSHORE

WWW.MIE-ENERGY.COM

PROVISION FOR ENGINEERING SERVICES FOR PLANT MODIFICATION AND IMPROVEMENT PROJECT FOR

PETRONAS GAS BERHAD, PETRONAS CHECMICAL ETHLYNE SDN BHD, PETRONAS CHEMICAL POLYETHYLENE SDN BHD &

PETRONAS PENAPISAN (TERENGGANU) SDN BHD.

• 3 YEARS + 2 YEARS (OPTIONAL) EXTENSION : YEAR 2015 TILL 2020

• COVERAGE LOCATION : KERTEH/KEMAMAN/GEBENG (TERENGGANU/PAHANG)

• ANY OF BROWNFIELD ENGINEERING SERVICES FOR ALL PETRONAS ASSET FOR PROJECT SERVICES, FEASIBILITY STUDY/BASIC, FEED,

DETAILED DESIGN AND OTHER SPECIALIZED ENGINEERING (FOR ONSHORE)

• ESTIMATED MORE THAN 1.0M MANHOURS THROUGHOUT CONTRACT DURATION

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 19: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

BROWNFIELD EXPERIENCEONSHORE

WWW.MIE-ENERGY.COM

PROVISION OF ENGINEERING DESIGN

TECHNOLOGY FOR SPENT CAUSTIC TREATMENT

UNIT PROJECT.

• DETAILED ENGINEERING DESIGN AND

TECHNOLOGY LIAISON (MERICHEM, USA)

• RAYONG, THAILAND

• YEAR 2016

• 20,000 MANHOURS

ENGINEERING DESIGN FOR SELECTIVE CATALYST

REDUCTION (SCR) SYSTEM FOR WHRU 3508-F01

PROJECT

• REDUCE NOx EMISSION FROM EXISTING WHRU 3502F01

LOCATED IN PTT RAYONG GAS SEPARATION GAS

SEPARATION. (100PPM@7% O2 (existing value) to

40PPM @7% O2 DUE TO LAW REGULATION

• RAYONG, THAILAND

• YEAR 2017

• 10,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 20: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

BROWNFIELD EXPERIENCEOFFSHORE

WWW.MIE-ENERGY.COM

ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION AND COMMISIONING FOR BENTARA WELLHEAD PLATFORM

REINSTATEMENT

• PLATFORM RE-INSTATEMENT/RE-ACTIVATION

• MIE HAD CARRIED OUT ALL SERVICES (PMT, Engineering, Laser Scanning, Procurement, Construction Engineering, Offshore

Hook-Up & Commissioning) IN-HOUSE

• SARAWAK, MALAYSIA

• AUG 2017 TO AUG 2018

• 150,000 MANHOURS (W/O LTI FOR ALL SCOPES)

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 21: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

BROWNFIELD EXPERIENCEOFFSHORE

WWW.MIE-ENERGY.COM

PROVISION OF STRUCTURAL ENGINEERING

SERVICES

• STRUCTURAL BROWNFIELD ENGINEERING

WORKS FOR ALL REPSOL PM-3 ASSET

• TERENGGANU, MALAYSIA

• 1-YEAR CONTRACT (2018 – 2019)

• 150,000 MANHOURS

UMBRELLA CONTRACT FOR PROVISION OF DESIGN,

ENGINEERING AND CONSULTANCY SERVICE FOR D35,

D21 AND J4 FIELDS

• BROWNFIELD & GREENFIELD ENGINEERING DESIGN

CONTRACT

• SARAWAK, MALAYSIA

• 2 YEARS + 1 YEARS (OPTIONAL): (2019 TO 2021)

• 500,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 22: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

BROWNFIELD EXPERIENCEOFFSHORE

WWW.MIE-ENERGY.COM

PROVISION OF ENGINEERING & DETAILED

DESIGN FOR J4 & D21 SIMULTANEOUS

PRODUCTION DRILLING (SIPROD)

• D21JT-A:3 SLOT, J4DP-A:11 SLOT INFILL

DRILLING ENGINEERING

• SARAWAK, MALAYSIA

• YEAR 2016

• 40,000 MANHOURS

PROVISION OF ENGINEERING FOR D35DP-A

FACILITIES MODIFICATION AND WELL TIE-IN FOR

CTU DRILLING ACTIVITIES

• WELL WORKOVER ON D35DP-A FOR PHASE 1

PROJECT DEVELOPMENT, SIPROD INFILL

ENGINEERING

• SARAWAK, MALAYSIA

• YEAR 2015

• 25,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 23: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

BROWNFIELD EXPERIENCEOFFSHORE

WWW.MIE-ENERGY.COM

PROVISION OF ENGINEERING SERVICES FOR

EAST BELUMUT INFILL DRILLING PROJECT

• 7 NOS OF INFILL DRILLING WELLS WITH DECK

EXTENSION

• TERENGGANU, MALAYSIA

• YEAR 2015

• 15,000 MANHOURS

PROVISION FOR PIPELINE REHABILITATION WITH IN-

FIELD (IFL) TECHNOLOGY FOR PETRONAS CARIGALI

(PL-234)

• NON-METALLIC PIPELINE REHABILITATION

(RTP/TCP/IFL) IS CHOSEN FOR CAPEX AND TOTAL

LIFE CYCLE COST COMPARED TO CARBON STEEL

REQUIREMENT

• SARAWAK, MALAYSIA

• YEAR 2018

• 8,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 24: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

BROWNFIELD EXPERIENCEOFFSHORE

WWW.MIE-ENERGY.COM

PROVISION OF AS-BUILTING EXERCISE AND

STRUCTURAL GLOBAL ANALYSIS FOR PM323 AND

PM329

• AS-BUILT FOR ALL DISCIPLINE AND STRUCTURAL

GLOBAL ANALYSIS

• TERENGGANU, MALAYSIA

• PM323: BEL-A, CHR-A, WB-A, TG-A

• PM329: EPA-CPP, EPA-WHP

• 2 YEAR CONTRACT (2015 – 2017)

• 300,000 MANHOURS

PROVISION FOR CONCEPTUAL OF SAND REMOVAL

AND DISPOSAL SYSTEM AT DUYONG FOR PETRONAS

CARIGALI SDN BHD

• SAND REMOVAL TECHNOLOGIES FOR COMPARATIVE

ASSESSMENT BETWEEN THE OPTIONS

• TERENGGANU, MALAYSIA

• YEAR 2015

• 5,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 25: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

BROWNFIELD EXPERIENCEOFFSHORE

WWW.MIE-ENERGY.COM

EPCIC OF DEEP DRAWN BOOSTER

COMPRESSION PILOT PROJECT AT ARTHIT

PLATFORM

• BOOSTER COMPRESSOR FOR AWP3 PLATFORM

• THAILAND

• YEAR 2014

• 15,000 MANHOURS

PROVISION OF ENGINEERING MODIFICATION

UPGRADE FOR EARLY PRODUCTION VESSEL

(EPV) AT BALAI CLUSTER

• FACILITIES UPGRADE MODIFICATION DUE TO

RELOCATION OF EPV BALAI MUTIARA TO

BENTARA CLUSTER FROM BALAI CLUSTER

• SARAWAK, MALAYSIA

• YEAR 2014

• 15,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 26: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

MARINE & NAVAL ARCHITECH EXPERIENCEOFFSHORE

WWW.MIE-ENERGY.COM

PROVISION OF DEMOBILISATION SERVICES FOR MOPU-SATU AND MOPU-DUA

• DECOMMISSIONING/DEMOBILISATION OF MOPU-SATU & MOPU-DUA TO APPROVED LAYING AREA IN JOHORE DUE TO

PLATFORM ABANDONMENT BY CLIENT

• TERENGGANU, MALAYSIA

• YEAR 2016

• PREPARATION OF DECOMMISSIONING ENGINEERING & PROCEDURE INCLUDING OPERATION SUPPORT

• 7,500 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 27: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

MARINE & NAVAL ARCHITECH EXPERIENCEOFFSHORE

WWW.MIE-ENERGY.COM

PROVISION OF MOORING ENGINEERING SERVICES

FOR TEMBIKAI OILFIELD

• MOORING ENGINEERING SERVICES FOR

PLATFORM SUPPORT VESSEL (PSV) AT TEMBIKAI

PLATFORM DURING HUC CAMPAIGN

• TERENGGANU, MALAYSIA

• YEAR 2015

• 5,000 MANHOURS

PROVISION OF ENGINEERING FOR BELIDA FPSO

PROJECT

• BELIDA FPSO PROJECT INSTALLATION ENGINEERING

• INDONESIA

• YEAR 2017

• 6,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 28: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

CONSTRUCTION ENGINEERING EXPERIENCE

OFFSHORE

WWW.MIE-ENERGY.COM

PROVISION OF FABRICATION ENGINEERING

AND AS-BUILT FOR HOST TIE-IN AT KNDP-A

• STRUCTURAL FABRICATION / SHOP DRAWING

(IFC), MTO, NDE, GA, ERECTION DRAWING,

NESTING & CUTTING PLAN

• SABAH, MALAYSIA

• 2015

• 12,000 MANHOURS

PROVISION OF FABRICATION SUPPORT (SHOP

DRAWING) FOR CONSTRUCTION OF NEW LAB

AND MATERIALMAN ROOM AT BEKOK-A

PLATFORM

• ALL DISCIPLINES SHOP DRAWING /(IFC) FOR

MATERIALMAN LABS AT BEKOK-A

• TERENGGANU, MALAYSIA

• YEAR 2014

• 4,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 29: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

3D LASER SCANNINGOFFSHORE & ONSHORE

WWW.MIE-ENERGY.COM

3D LASER SCANNING & CONSTRUCTION

DRAWINGS FOR MEP-A AND SAP-A NAG

• 3D LASER SCANNING & CONSTRUCTION

ENGINEERING

• SARAWAK, MALAYSIA

• YEAR 2016

• 15,000 MANHOURS

3D LASER SCANNING & 3D MODEL UPDATE FOR

SHELL BUKOM PLANT

• 3D LASER SCANNING & SP3D MODEL

COMPLETE (INTELLIGENT 3D MODEL)

• SINGAPORE

• YEAR 2017

• 8,000 MANHOURS

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 30: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

SPECIALIZED ENGINEERING

WWW.MIE-ENERGY.COM

FLOW ASSURANCE STUDY FOR TEMBIKAI GAS

DEVELOPMENT

• PIPELINE TRANSIENT ANALYSIS FOR 12” X

58KM FWS PIPELINE FROM TEMBIKAI WHP TO

BERANTAI FPSO

• TERENGGANU, MALAYSIA

• YEAR 2017

PROVISION OF FEA ANALYSIS FOR FLARE STACK

ASSESSMENT STUDY

• DAMAGED FROM SEVERE CORRODED FLARE TOWERS FOR

3 NOS OF FLARE STACK

• TERENGGANU, MALAYSIA

• ANSYS SOFTWARE

• YEAR 2015

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 31: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

SPECIALIZED ENGINEERING

WWW.MIE-ENERGY.COM

ENGINEERING ANALYSIS FOR STEAM TURBINE

INDUCE VORTEX STUDY

• INDUCE VORTEX STUDY FOR FEA & CFD

ANALYSIS

• TERENGGANU, MALAYSIA

• ANSYS & SOLIDWORK SOFTWARE

• YEAR 2017

PROVISION OF CFD ANALYSIS FOR STEAM INLET

DISTRIBUTOR

• CFD & FEA ANALYSIS FOR STEAM INLET DISTRIBUTOR

• TERENGGANU, MALAYSIA

• ANSYS SOFTWARE

• YEAR 2016

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 32: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

OTHER PROJECT EXPERIENCE LISTNo Project List Client Duration/Status

1PROVISION OF ENGINEERING AND DETAILED DESIGN FOR BAYAN GAS DEVELOPMENT PROJECT PHASE 2 (BROWNFIELD

WORKS)DIALOG E&C SDN BHD FEB 2021 - ONGOING

2PROVISION OF DETAILED ENGINEERING DESIGN FOR M1 TOPSIDE MODIFICATION IN PREPARATION FOR PL-395/396

DEPRESSURISING AND FLUSHING.PETRONAS CARIGALI SDN BHD JAN 2020 - ONGOING

3 PROVISION OF DETAILS ENGINEERING DESIGN FOR PFLNG2 TROPO ANTENNA STRUCTURE PETRA RESOURCSES SDN BHD JAN 2020 - ONGOING

4 MECHANICAL PE ENDORSEMENT FOR CHIMNEY TRAY SUPPORT VEKTHOR SDN BHD DEC 2020 - COMPLETED

5 PROVISION OF ENGINEERING DESIGN FOR BERANTAI GAS DEVELOPMENT STUDY INFILL DRILLING EPIC OG SDN BHD OCT 2020 - NOV 2020

6 PROVISION OF DE-CONSTRUCTION AND REMOVAL OF BIF REDUNDANT EQUIPMENT DH TECHNICAL SERVICES SDN BHD OCT 2020 - ONGOING

7 DETAILS ENGINEERING DESIGN FOR MCOT CULVERT BRIDGE PL106 MGV ENERGY SDN. BHD. SEPT 2020 - OCT 2020

8 BAKONG PIPELINE LEAK DETECTION SAPURAOMV UPSTREAM (SARAWAK)

INC.JUL 2020 - AUG 2020

9 PROVISION OF MANPOWER SUPPLY OF PIPELINE DESIGNERPETROFAC RNZ INTEGRATED (M)

SDN BHDJUNE 2020 - JUNE 2021

10 PROVISION OF ENGINEERING SERVICES FOR MRCSB REFINERY ASSET REJUVENATION TIGA (RESET) PROJECT - CATEGORY EMALAYSIAN REFINING COMPANY

SDN BHDMAY 2020 - SEPT 2020

11 PROVISION OF ENGINEERING SERVICES FOR IPC MALAYSIA B.V. IPC MALAYSIA B.V. FEB 2020 – FEB 2021

12 PROVISION OF FEED OF SK408W JERUN GAS FIELD DEVELOPMENT PROJECT - 3D MODEL VERIFICATIONPETROFAC RNZ INTEGRATED (M)

SDN BHDFEB 2020 - APR 2020

13 PROVISION OF ENGINEERING SERVICES FOR BENTARA A SIPROD - INFILL WELL DAYANG ENTERPRISE SDN BHD FEB 2020 - APR 2020

14 PROVISION OF ENGINEERING STUDY FOR SELIGI A COMPRESSOR TRAIN D REJUVENATION PROJECTENQUEST PETROLEUM PRODUCTION

MALAYSIA LTDNOV 2019 - APR 2020

15 PROVISION OF ENGINEERING SUPPORT FOR RE-DESIGN OF JACKET FOR A SUBSTATION RAMBOLL DANMARK A/S OCT 2019 - FEB 2020

WWW.MIE-ENERGY.COM

ENERGY DIV.MAJU INTEGRATED ENGINEERSOTHER PROJECT EXPERIENCE LIST

Page 33: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

No Project List Client Duration/Status

16UMBRELLA CONTRACT FOR PROVISION OF ENGINEERING SUPPORT SERVICES FOR NORTH MALAY BASIN

(NMB), FULL FIELD DEVELOPMENT PROJECTS

HESS EXPLORATION & PRODUCTION

MALAYSIA B.V

OCT 2019

(2 + 1 YEARS)

17UMBRELLA CONTRACT FOR PROVISION OF TECHNICAL SERVICES AGREEMENT (TSA) FOR ENGINEERING

SERVICES FOR VESTIGO PETROLEUMVESTIGO PETROLEUM SDN BHD

SEPT 2019

(2 + 1 YEARS)

18PROVISION OF ENGINEERING SERVICES FOR THE SAND TECHNOLOGY PILOT IMPLEMENTATION AT BARAM

FIELDPETRONAS RESEACH SDN BHD JUN 2019 - AUG 2020

19PROVISION OF ENGINEERING ADEQUACY CHECK FOR SK310 B15 PLATFORM RAMPING UP PRODUCTION

FOR SAPURAOMV UPSTREAM (SARAWAK) INC.

SAPURAOMV UPSTREAM (SARAWAK)

INC.MAY 2019 - NOV 2019

20 FPSO BERANTAI FOR TEMBIKAI NON ASSIOCIATED GAS (TNAG) SAUJANA MARINE SDN BHD MAY 2019 – SEPT 2019

21 PROVISION OF ENGINEERING CALL-OUT SERVICES FOR BLOCK B-17 & C-19 AND B-17-01CARIGALI-PTTEPI OPERATING

COMPANY SDN BHD

APR 2019

(3 + 1 YEARS)

22PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION AND COMMISIONING

(EPCIC) FOR BAYAN REDEVELOPMENT PROJECT PHASE 2B & 2C DIALOG ENERGY SDN BHD FEB 2019 - FEB 2020

23FINATE ELEMENT ANALYSIS (FEA) AND DESIGN CHECK - PHASE 1 & PHASE 2 AT C-109 DEERTHANIZER

COLUMN SHELL REPAIR AT PPTSBEPIC OG SDN BHD JAN 2019 - APR 2019

24

UMBRELLA CONTRACT FOR PROVISION OF DESIGN, ENGINEERING AND CONSULTANCY SERVICES FOR D35,

D21 AND J4 FIELDS ROC OIL (SARAWAK) SDN BHDDEC 2018

(3 + 1 YEARS)

25PROVISION OF DETAIL ENGINEERING SUPPORT FOR NOVEL OFFSHORE SAND DISPOSAL SYSTEM (NOSDS)

(IN-SKID AND OFF-SKID) PILOTPETRONAS RESEACH SDN BHD NOV 2018 - DEC 2019

26PRELIMINARY DESIGN ENGINEERING OF LIQUID RECOVERY SYSTEM (LRS) AT BINTULU ADDITIONAL GAS

SALES FACILITIES (BAGSF)

PETRONAS TECHNOLOGY VENTURES

SDN BHDNOV 2018 - APR 2020

27PROVISION OF FEASIBILITY AND CONCEPTUAL DESIGN SERVICES FOR LIQUID RECOVERY SYSTEM (LRS)

SKID & TIE-IN

PETROLIAM NASIONAL BERHAD

(PETRONAS)NOV 2018 - DEC 2019

28 UMBRELLA CONTRACT FOR DESIGN ENGINEERING AND CONSULTANCY SERVICES (2 + 1 YEARS)REPSOL OIL&GAS MALAYSIA LTD /

PETROVIETNAM ENGINEERING J.S.CNOV 2018 - NOV 2020

29UMBRELLA CONTRACT ENGINEERING FOR FACILITIES IMPROVEMENT PROPOSAL (FIP) & PLANT CHANGE

( PACKAGE E - MIRI )

PETROLIAM NASIONAL BERHAD

(PETRONAS)

AUG 2018

(3 + 1 YEARS)

30UMBRELLA CONTRACT ENGINEERING FOR FACILITIES IMPROVEMENT PROPOSAL (FIP) & PLANT CHANGE

( PACKAGE D - KUALA LUMPUR/MELAKA )

PETROLIAM NASIONAL BERHAD

(PETRONAS)

AUG 2018

(3 + 1 YEARS)

OTHER PROJECT EXPERIENCE LIST – CONT.

WWW.MIE-ENERGY.COM

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 34: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

No Project List Client Duration/Status

31UMBRELLA CONTRACT ENGINEERING FOR FACILITIES IMPROVEMENT PROPOSAL (FIP) & PLANT CHANGE

( PACKAGE C - KERTEH )

PETROLIAM NASIONAL BERHAD

(PETRONAS)

AUG 2018

(3 + 1 YEARS)

32UMBRELLA CONTRACT ENGINEERING FOR FACILITIES IMPROVEMENT PROPOSAL (FIP) & PLANT CHANGE

( PACKAGE B - BINTULU )

PETROLIAM NASIONAL BERHAD

(PETRONAS)

AUG 2018

(3 + 1 YEARS)

33UMBRELLA CONTRACT ENGINEERING FOR FACILITIES IMPROVEMENT PROPOSAL (FIP) & PLANT CHANGE

( PACKAGE A - KOTA KINABALU)

PETROLIAM NASIONAL BERHAD

(PETRONAS)

AUG 2018

(3 + 1 YEARS)

34 PROVISION OF ENGINEERING SERVICES (STRUCTURAL ENGINEERING)REPSOL OIL&GAS MALAYSIA

LTDFEB 2018 - DEC 2019

35 DETAIL ENGINEERING DESIGN FOR HYPROCHLORITE SKID UPGRADINGSAPURA EXPLORATION AND

PRODUCTIONAUG 2018

36DETAIL ENGINEERING SERVICES FOR STRUCTURAL ANALYSIS EAST BELUMUT-A / WEST BELUMUT-A FOR

SICKLINE CAMPAIGN

SAPURA EXPLORATION AND

PRODUCTIONJUN 2018 - JUL 2018

37PROVISISON OF FACILITIES IMPROVEMENT, REJUVENATION AND MODIFICATION FOR VESTIGO FLOW ASSURANCE

FOR TEMBIKAI GAS DEVELOPMENTSAUJANA MARINE SDN BHD JUL 2018 - OCT 2018

38 PROVISION OF FACILITIES IMPROVEMENT, REJUVENATION AND MODIFICATION FOR VESTIGO-BENTARA PROJECT

SEMARAK PETRO SDN BHD /

VESTIGO PETROLEUM SDN

BHD

SEPT 2017 - AUG 2018

39PROVISION OF DETAILED ENGINEERING DESIGN FOR HEAT SHIELD/BARRIER AT EAST BELUMUT-A (BEL-A)

PLATFORM

SAPURAKENCANA ENERGY

INC.MAY 2017 - JUN 2017

40 PROVISION OF DETAIL ENGINEERING DESIGN FOR CASING BLEEDLINE AT EAST PIATU PLATFORMSAPURAKENCANA ENERGY

INC.MAY 2017 - JUN 2017

41 PROVISION FOR DETAILED ENGINEERING DESIGN TO REPLACE EXISTING FLEXIBLE HOSESAPURAKENCANA ENERGY

INC.FEB 2017 - MAY 2017

42 PROVISION OF ENGINEERING AND DETAILED DESIGN FOR J4 SIMULTANEOUS PRODUCTION & DRILLING (SIPROD) ROC OIL (SARAWAK) SDN BHD NOV 2016 - JUN 2018

43PROVISION OF ENGINEERING AND DETAILED DESIGN FOR D21 SIMULTANEOUS PRODUCTION & DRILLING

(SIPROD)ROC OIL (SARAWAK) SDN BHD OCT 2016 - MAR 2018

44PROVISION OF ENGINEERING SERVICES FOR PLANT MODIFICATION AND IMPROVEMENT PROJECT AT PETRONAS

PENAPISAN (TERENGGANU) SDN BHD (1 ½ + 2 YEARS TERM CONTRACT)

PETRONAS PENAPISAN

TERENGGANU SDN BHDOCT 2016 - MAR 2020

45 PROVISION OF INFILL WELL TIE IN FOR ANJUNG KECILVESTIGO PETROLEUM SDN

BHDJUN 2016 - AUG 2016

OTHER PROJECT EXPERIENCE LIST – CONT.

WWW.MIE-ENERGY.COM

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 35: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

No Project List Client Duration/Status

46 TOPSIDE AS-BUILT FOR ANJUNG KECIL VESTIGO PETROLEUM SDN BHD MAY 2016 - AUG 2016

47 PROVISION OF ENGINEERING STUDY FOR WELL REMOTE SHUT IN PROJECT SAPURAKENCANA ENERGY INC. DEC 2015 - MAR 2016

48 PROVISION OF FABRICATION ENGINEERING AND AS-BUILT FOR HOST TIE-INS AT KNDP-A PBJV GROUP SDN BHD OCT 2015 - FEB 2016

49 PROVISION OF ENGINEERING SERVICES FOR EAST BELUMUT INFILL DRILLING PROJECT SAPURAKENCANA ENERGY INC. AUG 2015 - FEB 2016

50

PROVISION OF MANPOWER SUPPLY FOR ENGINEERING SERVICES FOR PLANT MODIFICATION AND

IMPROVEMENT PROJECT AT PETRONAS CHEMICALS ETHYLENE SDN BHD AND PETRONAS

CHEMICALS POLYETHYLENE SDN BHD

PETRONAS CHEMICALS

ETHYLENE SDN BHD &

PETRONAS CHEMICALS

POLYETHYLENE SDN BHD

JUN 2015 – MAR 2020

(3 + 2 YEARS TERM CONTRACT)

51PROVISION OF AS-BUILTING EXERCISE AND STRUCTURAL GLOBAL ANALYSIS FOR PM323 AND

PM329SAPURAKENCANA ENERGY INC. APR 2015 - ONGOING

52

PROVISION OF ENGINEERING SERVICES FOR PLANT MODIFICATION AND IMPROVEMENT PROJECT

AT GAS PROCESSING & UTILITIES (GPU), PETRONAS GAS BHD PETRONAS GAS BERHADMAR 2015 - MAR 2020

(3 + 2 YEARS TERM CONTRACT)

OTHER PROJECT EXPERIENCE LIST – CONT.

WWW.MIE-ENERGY.COM

ENERGY DIV.MAJU INTEGRATED ENGINEERS

Page 36: MIE-ENERGY - MAJU INTEGRATED ENGINEERS SDN BHD ......MAJU INTEGRATED ENGINEERS SDN BHD (MIE) was incorporated in 1999 and started as one of Malaysia’spremier Civil, Structural, Mechanical

WWW.MIE-ENERGY.COM

ENERGY DIV.MAJU INTEGRATED ENGINEERS

MAJU INTEGRATED ENGINEERS SDN BHD(ENERGY DIVISION)

T4-2-2, Tower 4, Level 2, Maju Link,

Jalan Lingkaran Tengah 2 (MRR2),

57100 Bandar Tasik Selatan, Kuala Lumpur.

MALAYSIA

TEL: +603-9054 5701

FAX: +603-9054 4302

Email: [email protected]

www.mie-energy.com