47
Evaluation of the Development Account Project “Strengthening the Capacity of African Countries to Use Mobile Technologies to Collect Data for Effective Policy and Decision Making” Midterm evaluation report Submitted by: Alexandre Diouf September 2016

Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

Evaluation of the Development Account Project

“Strengthening the Capacity of African Countries to Use Mobile

Technologies to Collect Data for Effective Policy and Decision

Making”

Midterm evaluation report

Submitted by: Alexandre Diouf

September 2016

Page 2: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

i

Disclaimer: This report is prepared for the United Nations Economic Commission for Africa (ECA). It was written by Alexandre Diouf. The

author’s views expressed in this report do not necessarily reflect those of the ECA.

Page 3: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report i

TABLE OF CONTENTS

Abbreviations .............................................................................................................................................. ii

executive summary ..................................................................................................................................... iii

PROJECT BACKGROUND............................................................................................................................ III

THE EVALUATION ..................................................................................................................................... III

RESULTS ................................................................................................................................................... III

RECOMMENDATIONS ................................................................................................................................ IV

1. Introduction ............................................................................................................................................ 1

1.1 PILOT PROJECT OVERVIEW .............................................................................................................. 1

1.2 GEOGRAPHIC SCOPE AND SELECTION CRITERIA ............................................................................. 2

1.3 KEY PERFORMANCE INDICATORS .................................................................................................... 3

1.4 EVALUATION FRAMEWORK ............................................................................................................. 4

1.5 EVALUATION CRITERIA ................................................................................................................... 5

2. Methodology ........................................................................................................................................... 5

2.1 PHASE 1: PREPARATION ................................................................................................................... 5

2.2 PHASE 2: COUNTRY DATA COLLECTION AND SYNTHESIS ............................................................... 6

2.3 PHASE 3: DRAFT AND FINAL REPORTING ........................................................................................ 7

3. Results and discussions .......................................................................................................................... 7

3.1 RELEVANCE...................................................................................................................................... 7

3.2 EFFECTIVENESS .............................................................................................................................. 10

3.3 EFFICIENCY .................................................................................................................................... 13

3.4 PROGRESS TOWARDS IMPACT ........................................................................................................ 17

3.5 SUSTAINABILITY ............................................................................................................................ 21

4. Major issues and problems at the country level ................................................................................ 24

5. Lessons learned .................................................................................................................................... 25

6. Recommendations ................................................................................................................................ 26

Annexes ........................................................................................................................................................ 1

1. DATA COLLECTION TOOLS .................................................................................................................... 1

2. EVALUATION TIMELINE ........................................................................................................................ 5

3. PEOPLE INTERVIEWED AND CONTACTS ................................................................................................. 6

4. EVALUATION TOR ................................................................................................................................ 9

Page 4: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report ii

ABBREVIATIONS

ACS African Centre for Statistics

CAPI Computer-assisted personnel interview

CEA Commission Économique des Nations Unies pour l’Afrique

CPI Consumer Price Index

CSA Central Statistical Agency

CSPro Census and Survey Processing

DA Development Account

ECA Economic Commission for Africa

ESA Ethiopian Statistical Association

GBoS The Gambia Bureau of Statistics

GPS Global Positioning System

ICT Information and communication technology

INS Institut National de la Statistique

KNBS Kenya National Bureau of Statistics

M&E Monitoring and evaluation

MoHCC Ministry of Health and Child Care

MTBDC Mobile technology-based data collection

NGO Non-governmental organisation

NSO National Statistic Office

NSI National Statistical Institute

PDA Personal digital assistant

SOM School of Mathematics

TRI Training and Research Institute

UoN University of Nairobi

ZIMSTAT Zimbabwe National Statistics Agency

Page 5: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report iii

EXECUTIVE SUMMARY

PROJECT BACKGROUND

This is the Final Report of a Midterm evaluation of the Development Account Project “Strengthening the

Capacity of African Countries to Use Mobile Technologies to Collect Data for Effective Policy and

Decision Making” (DA project). The project was implemented by the United Nations Economic

Commission for Africa (ECA). The Development Account project was launched in 2013 with the aim of

enabling the National Statistical Offices (NSOs) to develop technological bases for the mobile data

collection in a partnership with Training and Research Institutes (TRIs) within the country. Cameroon,

Gambia, Kenya, Zimbabwe, Ethiopia and Tunisia were selected as pilot countries where NSO and TRI of

each country established the implementation program in a collaboration.

THE EVALUATION

The rationale for the evaluation is threefold:

Assess the achievement of the DA project to date from the standpoint of its overall

performance, coverage and outreach approach, relevance, efficiency, effectiveness, impact

and sustainability.

Verify and ground-truth, to the extent feasible, DA results reported by country teams.

Generate data and information to allow ECA to make informed decisions concerning the

best use of DA resources for the second phase of the project.

The evaluation employed the following data collection methods:

Document review: Soon after being awarded the contract, the team of consultants conducted a

literature review focused on the performance of the DA project. Documents reviewed included

project proposal, performance reports provided by ECA, project design documents, and other

relevant documents.

Primary Research. A national consultant was contracted in each of the beneficiary countries. The

work of the national consultants was coordinated by an international team leader. The team leader

developed the evaluation tools and procedures and coached the national consultants during the

evaluation process. National consultants were in charge of data collection, processing and reporting

as indicated by the team lead at the national level.

Focus Group Discussions and Key Informant Interviews: Focus Group Discussions (FGDs) were

organized and key informant interviews were organized in each country and at ECA level. National

consultants were able to interview the ECA focal points, the staff of the NSOs and TRIs involved

in the development of the software as well as the enumerators who were the ultimate users of the

software.

RESULTS

Regarding relevance, all participating countries had their long term development plans that required timely

provision of more statistics with better quality. For example, in the case of The Gambia, the project was

particularly relevant as the government aims to boost the economic development by incorporating IT

technologies. The project was also found very pertinent in Zimbabwe where in-house staff capacity already

existed but needed support in providing training and purchasing equipment.

Page 6: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report iv

About Effectiveness, across all six countries, in terms of reporting, the ECA coordination team had

developed an M&E mechanism to guide the implementation of the DA project. As a result, there is evidence

to support the rate of implementation. Reporting can range from essential short-/midterm reports (e.g.

national situation analysis, national workshop reports, hardware procurement, etc.) to ECA focal points

reporting to DA project headquarters every 1–2 months on project status in the countries according to the

work plan. In all but one country, the NSOs were able to develop and pilot a geo-enabled mobile data

collection system for the CPS, successfully enhancing the reliability of the data as they can track the

authenticity of the data collected. But since it was a pilot project with a limited budget, the NSOs were not

always able to test the software at national level. In Tunisia particularly, however, respondents felt at times

that the NSO chose the ESSAI as its TRI more to meet an administrative requirement of the agreement with

the ECA than to develop a real technological partnership. And indeed, this TRI’s lack of participation at

the design phase of the project, and the absence of a specific budget assigned to the ESSAI, weakened its

commitment to the project. Under the effectiveness criteria, then, the project is deemed satisfactory because

it achieved most of its intended results by the end of its first phase.

For efficiency, in general, the project was highly efficient across the six countries. The project was highly

valued by the interviewees because it facilitated the processes used by the NSO to collect, process and

report on price information. The project built the capacity of both the TRIs and the NSOs, which was a key

achievement. The software seemed to have integrated geo-referencing information and were said to be very

user-friendly and are actually being used to collect and report on price information.

With regard to impact, the DA project, although piloted in six countries, had several impacts at country

level. The most important of those impacts are: the reduced data entry errors, the reduced workload, the

real time data collection and transmission and the easy way to detect anomalies. Most importantly the time

needed to generate critical information related to prices was cut by about 20 to 40% depending on the

country. The software made it possible to detect at an early stage any error, typo that happen during the

process of data collection, entry and processing which was found to be instrumental for it widespread

adoption by key actors.

For sustainability, at the time of the midterm evaluation, the TRIs and NSOs which have been involved

in the implementation of the project had the capacity to continue to use the software and generate useful

price-related information using mobile technologies. Critical capacity has been generated and is available

at country level, should similar project need to be replicated. No plan seemed to be put in place for the

project to continue critical activities beyond its lifetime though. Going forward it will be necessary to think

about that to maintain the project achievements and perpetuate its impacts.

RECOMMENDATIONS

At the end of this evaluation, the following recommendations are made to help sort out the problems

encountered by the DA project and facilitate design and implementation of similar projects in the future:

It is important for ECA’s future projects that the NSO receives assistance in the TRI

selection methodology, through the provision of a TRI assessment grid prior to signing the

agreement between the ECA and NSO. At the same time, the agreement must clearly define

Page 7: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report v

the TRI as well as the TRI’s expected activities and its budget for those activities.

Otherwise, there is a risk that the NSO will work alone in order to retain the entire budget.

The ECA should take into account the time it needs to complete its administrative processes

before the funds can be accessed by their partners. A proper planning will reduce delays

suffered by similar projects in the future.

It is important to have local or regional cloud servers to guarantee the security of data

collected via the newly-developed platforms.

The choice of a TRI and the theme of the DA project needs to be consultative and

exhaustive in order to ensure project success.

The CSA should carry out further pilot testing with large geographic coverage of urban

and rural areas of the country. This would promote better appreciation for the efficiency

and effectiveness of the MTBDC system for price data collection, including the presence

or absence of power, internet connectivity, and other essential factors.

Page 8: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 1

1. INTRODUCTION

Statistics increasingly play a crucial role in the design of monitoring and evaluation (M&E)

systems for development policies, by drawing out and clarifying priorities and objectives to be

attained. This finding, confirmed during the 2012 UN Conference on Sustainable Development

(Rio+20), also highlighted the need to make statistics available and accessible to all users—at

local, national, and international levels. In some African countries, however, statistical data are

not always collected, nor are their quality, reliability, and timeliness always assured.

The Economic Commission for Africa (ECA) has cited several reasons why statistics in some parts

of Africa are not being collected, compiled, and made available to national and global users.

Financial constraints, lack of appreciation for how data can be used for evidence-based decision

making and monitoring of implementation, low awareness of the advantage data being shared with

the international community are a few of the obstacles noted. But inadequate human capacity and

low technology base are the obstacles deemed the most critical to national statistical systems

preparing to shift from manual, paper-based data collection methods to those that increasingly rely

on information and communication technologies (ICTs), mobile technology-based data collection

(MTBDC) systems in particular.

ICT initiatives have the ability to support unprecedented changes in leveraging limited resources

for those committed to overcoming such core challenges as low levels of ‘digital literacy’ and

internet connectivity. They offer an opportunity to intervene and narrow the digital divide. The use

of mobile technologies to collect data and disseminate information would reduce the cost and time

associated with these tasks and lead to the following additional benefits:

Higher quality and more complete data availability

Use of real- or near real-time trend spotting with visualisation tools. Real-time data enable

better decision-making, adaptive management, and improved allocation of limited

resources.

Greater data security and archiving, which are especially important for ensuring data

transparency and conducting data audits.

The African region is witnessing one of the strongest increases in mobile data use in the world. It

is predicted that mobile internet traffic across Africa is expected to increase dramatically by 2018,

and will possibly see a 20-fold increase by the end of the decade (Lange et al. 2014).1

1.1 PILOT PROJECT OVERVIEW

In many African countries, several factors prevent statistics from being collected, compiled, and

made available to national and global users. These include financial constraints, poor appreciation

for the use of data for evidence-based decision-making and monitoring of implementation, and

1 Africa mobile broadband market. Lange et al. 2014. (Available at: http://www.budde.com.au/Research/2014-Africa-

Mobile-Broadband-Market.html?r=51)

Page 9: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 2

low awareness of the advantage of broadening the international community’s access to the data.

But of these factors, it is low human capacity and a low technology base that most limit the full

potential of ICT tools—mobile devices in particular—to improve how statistical data are being

collected, disseminated, and used.

To target the problems associated with data collection, particularly the technology and human

capacity issues, the ECA launched the Development Account (DA) project, “Strengthening the

Capacity of African Countries to Use Mobile Technologies to Collect Data for Effective Policy

and Decision Making”. Begun in 2013, this two-phase, two-year pilot project aimed to strengthen

data collection through the use of mobile technologies. It focused on building capacities of national

statistical offices (NSOs) and government departments in a number of African countries for

effective policy and decision-making. The expected outcomes centred on increased capacity in

two critical areas—namely, NSOs would partner with training and research institutions (TRIs) to

develop methodologies and systems for mobile data collection, and project countries would

develop geo-enabled data collection systems running on mobile devices.

1.2 GEOGRAPHIC SCOPE AND SELECTION CRITERIA

For phase 1 of the DA project, five pilot beneficiary countries were selected based on several criteria,

including:

Level of commitment and readiness to implement the DA project

Geographical placement, language, and manageable size of the country

Level of development of ICT tools/mobile devices and willingness to use them for data

collection

Security level/sustainable institutions in the country

Relevance to the work of the NSO.

As part of the situation analysis, a consultant was engaged to review potential countries based on

these criteria, and put forward those that met them, to inform the selection. The consultant’s

proposal was presented to a joint meeting of the technical and steering committees, which was

held during a regional workshop in Praia, Cape Verde, in March 2014. Cameroon (Central Africa)

and Kenya (East Africa) were selected based on the consultant’s recommendation in the situation

analysis report; both countries confirmed their willingness and readiness to participate. The

Gambia and Tunisia were selected from West and North Africa based on presentations by their

respective NSOs during the workshop and meeting. Zimbabwe was selected after presentations by

Research and Information Services (which later became the TRI for the Zimbabwe pilot project).

The presentations demonstrated both the suitability of the countries for the project as well as their

strong commitment to the project’s implementation. The DA project subsequently expanded to

include a sixth country, Ethiopia, after the Embassy of Ireland in Ethiopia expressed interest in

supporting the project.

Page 10: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 3

1.3 KEY PERFORMANCE INDICATORS

To measure progress towards the achievement of the project objectives, five key performance

indicators were developed, all based on the number of:

1. Geo-enabled mobile data collection systems adapted or developed through partnerships

with training and research institutions established and functional

2. Countries that have adapted project methodology and work-flow for data collection and

processing

3. Pilot countries using mobile devices to collect and analyse data

4. Data collection campaigns undertaken as part of the project

5. Publications and reports attributing their data sources in the pilot countries to national and

regional data collected by the project.

Brief, country-specific highlights of the DA project are given below.

Cameroon

Implementation of the DA project related to data collection aimed at designing consumer price

indices is a routine operation of the National Statistical Institute (NSI). It is articulated around four

main initiatives: the organisation by the NSI of a national training workshop for the data collection

on price; using mobile devices to collect data on producer prices at 3,702 points of sale across the

country; the calculation of price indices; and conducting a satisfaction survey.

Ethiopia

Only in Ethiopia was the project funded by the Government of Ireland. The Central Statistical

Agency (CSA), in partnership with the Ethiopian Statistical Association (ESA), implemented the

pilot project. Field testing and pilot mobile data collection were carried out for the monthly retail

and producer prices in the Tigray region of northern Ethiopia, in order to build synergies with other

programmes that the Irish government is funding in that part of Ethiopia.

The Gambia

The project was implemented by The Gambia Bureau of Statistics (GBoS) as the NSO, in

collaboration with the University of The Gambia as the TRI. Implementation of the DA project,

which sought to collect and disseminate data on price indices, ended in March 2015.

Kenya

The project was implemented by the Kenya National Bureau of Statistics (KNBS), in partnership

with the School of Mathematics (SOM)–University of Nairobi (UoN). Following a presentation

by the KNBS on areas where it collects, the Consumer Price Index (CPI) was selected for the pilot.

Tunisia

Page 11: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 4

The project was planned to be implemented by the Institut National de la Statistique (INS), in

collaboration with the Ecole Supérieure de la Statistique et de l'Analyse de l'Information (ESSAI)

as the TRI.

Zimbabwe

The Zimbabwe National Statistics Agency (ZIMSTAT), in partnership with Research and

Information Services, initially implemented a DA pilot project. It focused on the revival and

maintenance of electronic village/area registers as a tool for collecting, using, and disseminating

data for development. The project, however, was not completed as the TRI ran into problems with

the government over its registration. As a result, and with the approval of the ECA, ZIMSTAT

implemented an alternative project, the Consumer Price Survey (CPS), to achieve the objectives

of the DA pilot project in Zimbabwe without a TRI.2

1.4 EVALUATION FRAMEWORK

An independent midterm evaluation (MTE) of the DA project was carried out in the six target

countries from June to July 2016. The MTE will enable the ECA to assess the validity of the

project’s design and assumptions, and its performance. The findings will specifically inform the

design and implementation of upscaling the intervention into additional countries across the

African continent. The specific objectives of the assignment are to:

Make an overall independent assessment of the first phase of the DA project’s

performance, paying particular attention to the relevance, effectiveness, efficiency,

sustainability, and impact of project actions against results and objectives.

Identify key lessons learned and propose practical recommendations that guide the design

of the project’s second phase.

The MTE was based on an iterative design aimed at capturing the perspectives of all stakeholders

and assessing the DA project’s overall performance against ECA’s evaluation criteria. This

approach enables a ‘360 degree evaluation’, incorporating the views and perspectives of the ECA

and its country-level partners (NSOs, TRIs) as well as enumerators who have been using the

software developed in each participating country. These multiple lines of evidence provided the

considerable length and breadth of data needed to assess the capacity-building, software quality,

and the data quality improvement components as well as the potential sustainability of the project.

These data will also inform possible programmatic decisions for the DA’s second phase for both

the ECA and partners.

2 Even though there was some progress and expenditure related to the uncompleted project, including some outputs in

terms of reports, the midterm evaluation focuses on the latter project implemented by ZIMSTAT on the CPS.

Page 12: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 5

1.5 EVALUATION CRITERIA

The MTE formulated a set of broad strategic questions, with relevant sub-questions, to provide

information on the extent to which the project has been implemented. Organised around five

components (i.e. ‘project implementation dimensions’), the evaluation sought to determine:

Relevance: The extent to which the objectives pursued by the DA project are consistent

with the country context, needs, and priorities of the member States and institutions in

collecting, analysing, and reporting on macro-level statistics.

Effectiveness: The extent to which the DA project is on track to attain its intended targets,

and whether these targets have been transformed into the results anticipated at the project’s

design stage. More specifically, the MTE assessed the extent to which the project has

enhanced the capacity of mobile data collection at NSO and TRI levels, the quality of the

software, and the extent to which it is being used by NSOs and TRIs.

Efficiency: The extent to which the DA project, implemented at country level, transformed

the available resources into the expected results in terms of quantity, quality, and

timeliness. The evaluation assessed the extent to which the software developed during the

project is user-friendly and complete. The evaluation has identified the factors that explain

(or contribute to) the level of use of the software. Under this component, the evaluation

also looked at the capacity of the software to integrate geo-referenced information.

Impact: The extent to which the results achieved through the DA project have contributed

(or will contribute) to increasing the quality and reducing the time needed to collect and

report country-level statistics. It also assessed the extent to which the project has improved

the quality of data in NSOs.

Sustainability: The extent to which the positive results of the DA project will continue

after it is completed. The evaluation specifically looked at the capacity of the NSOs and

TRIs to continue to use and improve the software. It examined both the working

arrangements and plans that have been put in place so as to continue critical activities of

the project beyond its lifetime, as well as the financial plan that has been set up to support

the implementation of those activities.

2. METHODOLOGY

Operationally, the MTE was conducted in three complementary phases as discussed below.

2.1 PHASE 1: PREPARATION

Page 13: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 6

Phase 1 began following contract award. It included extensive communication between the

consultant and ECA’s focal point from the African Centre for Statistics (ACS) and its Evaluation

Section. During this phase, all the DA documents were shared with the consultant, who reviewed

them and then developed a work plan for the evaluation. Also during phase 1, the consultant held

Skype conversations with the ACS focal point and the Evaluation Section. The purpose of the

communication was to discuss and clarify ECA’s expectations from the exercise and its results in

order to achieve consensus and develop a common understanding of the MTE’s overall schedule

and approach. The consultant submitted an inception report detailing the methodology and the

evaluation tools. At the end of phase 1, he had a detailed evaluation methodology that included the

revised list of evaluation questions and assumptions to be tested, refined data collection and

analysis tools, and an agreed timeline (see Annexes 1 and 2).

2.2 PHASE 2: COUNTRY DATA COLLECTION AND SYNTHESIS

The development of the inception report followed an initial document review of the project

proposal, including documents related to the project in each country, project monitoring reports,

and country situation analysis reports. National data collectors were contracted in each of the six

countries; they led the enumeration and analysis work at country levels. The lead consultant held

one-on-one Skype meetings with each of the national data collectors to explain the methodology

and expectations regarding data collection, analysis, and information reporting. The data collectors

then interviewed representatives of the NSOs, TRIs, and enumerators in their respective countries,

using the methodology and data collection tools in the inception report.

At the NSO level, the data collector identified and interviewed at least three people who have been

involved in the implementation/management of the DA project, which represents between 20 and

50% of the people who have been involved in the implementation of the project. Similarly, at least

three people were interviewed at the TRI level and at least five enumerators who have used the

software. A set of questions that specifically shed light on the evaluation questions has been

developed for each group of interviewees. Annex 3 presents a list of those interviewed and their

contact information.

To ensure that the process used for the evaluation was as thorough and reliable as possible, the

different data collection tools to be employed (semi-structured interview guides, focus group

discussion guides, key informant interview guides, etc.) were approved by the ECA, along with

the other tools and procedures used during this evaluation, prior to the fieldwork phase.

An important element of the MTE was the breadth of data sources used and the multiplicity of

stakeholder perspectives sought. Data collected from each country was analysed separately and

reported in a specific document. The synthesis stage of the project evaluation involves an

overarching analysis of all the different types of data collected on thematic and country bases,

using the evaluation criteria set forth in the terms of reference (Annex 4). This analysis compares,

contrasts, and synthesises perspectives and experiences across the different data sources and

stakeholders.

Page 14: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 7

2.3 PHASE 3: DRAFT AND FINAL REPORTING

After collecting the data in phase 2, country-level data collectors submitted a draft of the country

reports to the lead consultant and the ECA for their review. The reports were reviewed in

compliance with the guidelines laid down in the inception report. Following the submission of

revised reports by the national data collectors, the lead consultant drafted the consolidated the

present MTE report.

3. RESULTS AND DISCUSSIONS

3.1 RELEVANCE

The main area of evaluation under this section focused on the relevance and applicability of the

DA project activities as well as the anticipated benefits and problems that the project could help

to solve. It examined whether the project approach and objectives were relevant and appropriate

to the achievement of expected outcomes, given national and regional priorities.

Cameroon

For Cameroon, the activities were relevant and consistent with the national development plan in

relation to statistics. The DA project helped to build the capacities not only of NSI staff but also

those in the national statistics system (i.e. Ministère de l’Agriculture et du Développement Rural

and Ministère de l’Élevage, des Pèches et des Industries Animale) to use MTBDC methods. In

June 2015, the NSI carried out a diagnostic study that identified needs in relation to this.

Ethiopia

In Ethiopia, in-depth discussions with relevant representatives from each of the CSA and ESA

show that the project approach and objectives are highly relevant to national and regional priorities.

Representatives of the CSA (formerly the Central Statistical Authority) and ESA enumerators both

agree that the logical framework of the DA project has been very helpful in the implementation of

project activities. Similarly, the ECA reported that the key performance indicators in the logical

framework were also appropriate and of sufficient quality to assess performance.

The CSA and ESA considered project activities at country level to be well designed and to fit the

framework of national and regional strategies for development in the area of intervention. In this

respect, the strategic plan of the CSA (i.e. the National Statistics System) emphasises use of

technology to improve supply of data and quality of data, as opposed to the traditional paper-based

system.

The mandate of the CSA is twofold: (1) to collect, process, analyse, and disseminate statistical

data, and (2) to provide technical guidance and assistance to government agencies and institutions

in building administrative systems and registers. This includes building capacity and providing

directives for database creation and proper management of administrative records. The current

second 5-year national development plan of Ethiopia, the Growth and Transformation Plan II, also

Page 15: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 8

requires massive data for M&E of the national growth and development process, including demand

for statistical data in areas or issues which have not been covered by formal surveys/census

activities of the CSA. Regarding the gender dimension of the DA project, proper data collection,

dissemination, and use and by policymakers at macro- and micro-levels do help to address gender

gaps and challenges in national development. Designing data collection forms in a gender-

disaggregated manner is central for development policy decision-making. So too are collecting

and disseminating gender-disaggregated data and analysed information. The use of MTBDC

technologies can better facilitate and improve the quality, quantity, and timely generation of

gender-disaggregated data, further catalysing gender-friendly and gender-inclusive development

activities at national, regional, and local levels.

The data collected through the project’s MTBDC systems have all been fully geo-referenced. The

enumerators already had Global Positioning System (GPS) software loaded on their tablets. They

also had a Garmin (external GPS) coordinate reader to help ensure that they took proper geo-

referencing of the retail and producer price market places. The respondents for this evaluation from

the CSA and ESA stated that the project’s objectives remained valid and relevant throughout its

implementation.

The Gambia

In The Gambia, almost every stakeholder met during the evaluation rated the project as very

relevant, especially in the context of demand for timely provision of statistical data for informed

policy decisions. Furthermore, respondents expressed that the project’s targets are well defined

and have strong linkages with the Gambia’s VISION 2020 (and by extension, its Medium

Development Plan known as the ‘Programme for Accelerated Growth and Employment’).

The GBoS plays a crucial role in the country’s overall development and policymaking process by

providing the evidence for setting policy objectives, targets, and priorities for the government and

the international community. The manual form of data collection used by the GBoS remains a

challenge as it is neither a speedy nor efficient way to process data. To overcome this problem, it

is crucial to introduce emerging technologies if the GBoS is to have an efficient and cost-effective

method of collecting data for use by NSOs elsewhere in Africa. The DA project is quite relevant

and will continue to be so in The Gambia. The government aims to make the country’s ICT

infrastructure ‘e-ready’ and so boost economic development by focusing on telecommunications,

information technology, and media. The project, as revealed during the interviews, was perfectly

designed for this as it facilitated a collaborative approach between the GBoS as an implementing

partner and the School of Information, Technology and Communication of the University of The

Gambia as a TRI. This is a mutually reinforcing partnership; each party has a comparative

advantage during project implementation.

Kenya

For Kenya, the CPI and corresponding inflation statistics are compiled and disseminated every

month as one of the key statistical outputs of the KNBS. As noted during the evaluation, KNBS

Page 16: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 9

staff were satisfied with the approach used during implementation of the DA project. To them, the

selection of the CPI for the pilot was affirmed following a presentation on areas where it collects

data. Both the KNBS and SOM-UoN felt that the project’s activities are quite relevant. They

observed that the collection, transmission, validation, analysis, dissemination, and storage of

survey data needed to be more efficient and cost-effective, while utilising scalable and suitable

technologies.

Retail prices to be used in the compilation of the CPI is currently collected every month in 25 data

collection zones in 13 urban centres. Each of these 25 zones is manned by a price collector and

supervised by a county statistical officer. Nationally, more than 12,000 price observations are

made every month from a sample of more than 4,000 outlets. According to the interviewees, the

CPI is used in a number of ways. These include deflation of monetary values; as an indicator of

macroeconomic performance; to determine supplier/debtor price variations; to determine

employer/ employee wage negotiations; and to index pension benefits. All these have to do with

the value of money. Hence, it is imperative that the KNBS collects, compiles, and disseminates

CPI data timely and with a high degree of accuracy so that it remains a credible source of this

important statistic. Besides, quality CPI data are crucial for informing policymakers, investors,

and the general public on inflation trends in Kenya. Prior to February 2009, prices collected from

the outlets were written on paper and posted to the CPI office, at the KNBS headquarters. This

process was discontinued because it cost money for courier services and every month it was common

for some field returns to be late.

The logical framework indicators were also considered appropriate and of sufficient quality to

assess the performance of CPI data collection. What is more, the DA project activities in Kenya

were well designed and fit into the framework of national and regional strategies.

Tunisia

According to INS officials, at the beginning of the DA project Tunisia had no available expertise

in mobile technology for data collection, neither at universities nor in private sector (telecoms or

information technology development companies). The INS therefore needed to develop in-house

skills to be able to quickly implement technical solutions, partly due to the urgent need to carry out

the CPI survey. INS officials are satisfied with the activities formulated during the project, which

have enabled them to achieve their objectives.

Zimbabwe

In Zimbabwe, the DA project was relevant for a number of reasons. Although the Agency’s staff

had capacity to implement mobile systems to collect data, they needed to build relevant, supporting

capacities in training (how to implement Android-based systems) and equipment (server and

tablets provided by the project). The project was also relevant because it showed the NSO and its

stakeholders that it is possible to improve data quality and cut costs when mobile data collection

systems are implemented. As well, the conventional paper-based CPS uses too much paper and

generates processes that make having data available for decision-making unnecessarily

Page 17: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 10

complicated and delayed. The survey managed to use geo-referencing, thus reducing the likelihood

that enumerators and their supervisors would manipulate data since the application could confirm

whether enumerators had actually collected the data from the field.

The project was piloted in only 3 of Zimbabwe’s 10 provinces. Evidence from the pilot results

suggests that implementation of MTBDC systems in all 10 provinces would have reduced the

administrative burden of printing questionnaires, the cost of transporting the questionnaires to and

from the field, and the rigorous process of data entry and cleaning for analysis. It has been

estimated that the use of mobile data collection would reduce the time for a given survey by about

45 days. Furthermore, had the project been implemented in all the provinces, data quality would

be very high as the likelihood of mistakes was reduced at the point when data were collected. The

manual paper system was less efficient, as the information takes a long time to reach the head

office, where it must then be entered. Any errors would merely serve to prolong this process. With

the DA project, the information would be delivered instantly for analysis after a quick supervisory

check. The project was relevant to ZIMSTAT as it also helped to build capacity of its staff and

enhanced its ability to handle statistical data within the government. As a result of the project,

many government departments are seeking support for a similar system for their work. ZIMSTAT

staff felt that the logical framework indicators were appropriate and of sufficient quality to assess

project performance.

Conclusion

For many of those consulted, the project was highly relevant to the needs of their respective

country. All the NSOs were handling a lot of data, and the support the project provided was

instrumental in demonstrating that they could improve the way they handled and processed their

datasets.

3.2 EFFECTIVENESS

To measure the DA project’s effectiveness, the MTE focused on determining project targets at

proposal level and how and whether they transformed into expected results. Further, the evaluation

looked at whether the project has enhanced the capacity for mobile data collection at NSO and

TRI levels, as well as the generation of knowledge to be shared across the network of NSOs and

TRIs.

Cameroon

In Cameroon, the DA project was able to strengthen NSI’s existing capacity in MTBDC as it has

been using this technology since 2010. At the launch of the project, the NSI had already carried

out four statistical operations using MTBDC methods, but none of them had used tablets to collect

price data. The project conducted a training workshop from 29 July to 1 August 2015, to build

NSI’s capacities in the use of tablets. It also enabled the NSI to take ownership of the development

of data collection applications using tablets, and to experiment with the transfer of data directly

Page 18: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 11

onto a server. Under the project, the NSI acquired equipment (i.e. 60 electronic tablets with wallets;

10 power-banks; six laptop computers, one server, one 3-kva inverter, and Windows 2008 business

software) for 200 posts.

Ethiopia

In Ethiopia, the implementation tools and mechanisms applied were found to be very appropriate

and helpful at ensuring the effectiveness of the DA project. This included, importantly, the NSI

arrangement mechanisms that cover the project advisory board (consisting of ESA board chairman

and ESA president, head of Addis Ababa University statistics department, and two deputy director

generals of the CSA) and a technical working group of five from the CSA and ESA.

The CSA and ESA respondents also cited the other valuable implementation tools and mechanisms

that were critical to project performance. These included the initial project design and planning

approach, strategies, the agreement letters and memorandum of association signed between and

among implementing partners, as well as the logical framework. Respondents also mentioned as

critical the project work plan, its timeline, and budgeting; fund transfers (85%) from the ECA to

CSA and then ESA; expertise/human resources staffing and management arrangements;

stakeholder participation; and the monitoring and reporting system put in place to enable better

follow-up among implementing partners.

The CSA, ESA, and the enumerators’ response unanimously shows that in Ethiopia, the project

attained its intended targets (e.g. national and regional workshops and trainings, software

development, and field testing). MTBDC systems were used on retail and producer prices in North

Ethiopia (Tigray region), and internal generation of a mobile price collection report that meets

CSA’s statistical data quality. A lag in procuring the tablets caused the CSA and ESA to borrow

some from the government’s Agricultural Transformation Agency. The respondents also noted

that the project enhanced the capacity for MTBDC at CSA and ESA levels. During the project’s

mobile price data collection in Ethiopia’s Tigray region, the field assistants who were deployed

with the enumerators experienced first-hand how useful both personal data assistants (PDAs) and

mobile phones are in collecting data, especially compared with paper-based methods.

The Gambia

The development of the software by the TRI in The Gambia was timely, and enumerators were

trained for five days on how to use and operate it. After the training, pre-testing was conducted at

the field; the outcome was very satisfactory. Officers of the GBoS, enumerators, and system

developers all rated the performance of the software as very good and described it as user-friendly.

The Android application developed by the TRI is used primarily to collect and tabulate data. The

GBoS uses the application to collect both the CPI and producer price index in conjunction with an

SQL database for analysis. But the Android application installed in a tablet can also be used as a

sole programme for processing the collected information if the cloud or server functionalities are

not available for any given period. For example, GBoS enumerators can collect market price

Page 19: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 12

indices using handheld tablet devices, and store the information with both the GPS and time stamp

of where the data are collected. The information can be further synchronised to the server in the

GBoS cloud platform when network connectivity is available.

Kenya

In Kenya, the KNBS, in partnership with SON-UoN, have been able to develop and pilot a geo-

enabled mobile data collection system for CPI data collection (at present it is not being

implemented). Drawing upon the DA project methodology, the KNBS is using MTBDC to conduct

the Kenya Integrated Household Budget Survey (KIHBS) and the Micro and Small Medium

Enterprises (MSME) survey (completed). It is worth noting that even though the KIHBS and

MSME are independent surveys, their use of MTBDC methods was informed by the DA CPI pilot

project. Overall, Kenyan respondents noted an improvement in the capacity of the KNBS and

SOM-UoN to use MTBDC tools because of their participation in the project. They observed that

the project also enhance the role of the KNBS to provide national statistics. Development of the

software and the collection of data benefit students at the SOM-UoN, because an agreement with

the KNBS permits data collected for CPI and other surveys to be used as training materials by the

university.

Tunisia

In Tunisia, the project exceeded its objective to strengthen national capacity to develop geo-active

data collection systems using mobile technologies). The INS now has the resources to improve the

software application developed through the project, as well as the capability to develop other

applications for the variety of surveys carried out by the NSO. These resources facilitated the

acquisition of new skills within the project, which today develops systems to disseminate surveys,

as well as the implementation of a private cloud that can potentially spread these technologies

within Tunisia and abroad. Since the beginning of January 2016, 100% of the CPI data is collected

solely through tablets, and the application is now used by all enumerators in Tunisia.

Zimbabwe

As noted earlier, the DA project was implemented in 10 provinces in Zimbabwe; financial

constraints prevented it from being rolled out to the other 7. The main objective of project was to

recommend the use of mobile devices in conducting the CPS and other surveys carried out by the

NSO. This was achieved, as the project not only managed to show the utility of tablets, but also

built the capacity of NSO staff and increased their efficiency to process the collected data in a

timely manner. Some branches of the government, such as the Ministry of Lands and Rural

Resettlement and the Ministry of Health and Child Care (MoHCC), have started to rely on the

expertise of ZIMSTAT in collecting data using mobile devices after the success of the project. The

ministries approached ZIMSTAT about conducting their own surveys using the electronic data

collection system that was piloted and established during the project, for several reasons.

Page 20: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 13

ZIMSTAT has the necessary hardware (tablets); the technical expertise to develop data collection

software; and the capacity to design the studies, manage the data collection process, and provide

technical backstopping. The MoHCC has already been carrying out a Malaria Indicator Survey,

and the Ministry of Lands and Rural Resettlement has proposed to do a land audit which is waiting

to be launched. And although the present surveys the Agency is doing for other line ministries are

one-off, the MoHCC has expressed interest in a long-term partnership because it does conduct

different surveys at regular intervals. At present, ZIMSTAT can do more to conduct its own

surveys using the electronic system. But the Agency cannot purchase the technology it needs to

carry out national surveys electronically, as the government is unable to finance the technology.

Conclusion

Across all six countries, in terms of reporting, the ECA coordination team had developed an M&E

mechanism to guide the implementation of the DA project. As a result, there is evidence to support

the rate of implementation. Reporting can range from essential short-/midterm reports (e.g.

national situation analysis, national workshop reports, hardware procurement, etc.) to ECA focal

points reporting to DA project headquarters every 1–2 months on project status in the countries

according to the work plan. From experience, however, such reports mostly focus on measuring

the process of project implementation, with emphasis on upward financial accountability.

Admittedly, this monitoring of project activities is an important management function, and the

information is certainly useful in attributing impact to a given intervention. Yet such monitoring

data rarely reveal much about a project’s real impact.

In all but one country, the NSOs were able to develop and pilot a geo-enabled mobile data

collection system for the CPS, successfully enhancing the reliability of the data as they can track

the authenticity of the data collected. But since it was a pilot project with a limited budget, the

NSOs were not always able to test the software at national level. Under the effectiveness criteria,

then, the project is deemed satisfactory because it achieved most of its intended results by the end

of its first phase.

3.3 EFFICIENCY

Under the efficiency component, the MTE sought to determine the extent to which the available

resources were transformed into results. Key evaluation aspects included:

The value added by the project to the role of NSOs and TRIs

The extent to which the resources allocated enabled the project to achieve results in terms

of quantity, quality, and timeliness

User-friendliness of the software developed compared with other software currently being

used in data collection and reporting

Page 21: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 14

The extent to which management, decision-making, and relationship structures of the

project support the successful implementation of the project

The level of use of the software, with an explanation of the key drivers and the extent to

which the software is able to integrate geo-referenced information.

Cameroon

For Cameroon, the satisfaction survey was carried out by the NSI amongst 23 users about the

application developed by the DA project. The survey revealed that 82.6% had never used an

application before the project, so this was their first experience. Some 73.9% of the users stated

that they were satisfied with the application. In terms of difficulty, 17.4% of respondents

highlighted problems with the application throughout the data collection phase; 56.5%

encountered malfunctioning of the application at the beginning of data collection; and 26.1%

experienced no difficulties using the application. That nearly 40% of the respondents had never

used a tablet before could explain some of the difficulties they encountered. The level of use of

this application for surveys in Cameroon is still relatively low, however, and it needs to be made

more user-friendly to facilitate its dissemination. Many surveys are still carried out on paper, and

there are financial and logistical constraints in the purchase of tablets.

Ethiopia

In Ethiopia, the DA project’s use of MTBDC significantly reduced time across all major activity

chains: data collection, transfer, coding, analysis, and reporting. Respondents reported that the

software developed was very user-friendly and the devices easy to use, especially compared with

other software currently being used to collect and report data. Mobile devices also greatly reduced

the logistical arrangements from field sites to branch offices in the different regions. The tablets

prompt enumerators to save data onto tablets, and periodically to upload and synchronize daily

collected data onto the server at the CSA. Consequently, collected data do not need to be emailed

to CSA’s head office, and the search for specific items for data collection is easier. Tremendous

savings in time and resources are realised as MTBDC technologies replace paper-based

questionnaires, eliminating or streamlining many of the laborious and costly steps associated with

manual systems. The effect of such time reductions has broader implications for the CSA as it

collects, analyses, and reports other data sought by national development, or to expand the scope

and coverage of specific statistical data surveys. The CSA is now well positioned to carry out in-

depth data collection on price, and can expand to other types of demand-driven surveys/ censuses.

It can provide highly relevant, well-analysed, and informative data to the public/private sectors

and regional and international institutions. Cumulative reductions in time to collect and process

data, and parallel increases in the efficiency and cost-effectiveness of processing and sharing the

data, enable the scope and coverage of specific statistical data surveys to expand, not only for the

CSA but also for other stakeholders who collect data for their organisational activities.

MTBDC methods, along with a PDAs/CAPI (computer-assisted personnel interview) system,

helped to reduce the time and increase the quality for mobile price data collection, analysis, and

Page 22: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 15

reporting. Field testing of the software, and the feedback received, was quite helpful in improving

the user-friendliness of the software (it has both English and Amharic features). The enumerators

identified additional significant increases in the volume of data collected in a relatively short time

(a few days). They remarked how they were able to imagine that mobile technologies, if

mainstreamed, could significantly transform data quality, quantity, and timeliness in order to

produce and disseminate statistically rich publications to different users. These project

interventions, along with critical capacity and knowledge created and utilised in MTBDC systems

among implementing partners and stakeholders, are helping to increase data quality, security, and

reliability.

In all instances, the software developed was able to fully integrate geo-referenced information.

Initial problems faced by enumerators in taking GPS coordinates after entering the market were

quickly resolved. In this regard, enumerators used both the external Garmin device and the GPS

incorporated into the software in the tablet device they use for mobile data collection.

The Gambia

In The Gambia, because all the project activities were implemented within four months, targets

were met far sooner than anticipated. During implementation, TRI’s collaboration with the GBoS

allowed for knowledge-sharing and the smooth transition of project development phases. All key

deliverables and milestones have been successfully completed on time and within budget. While

the software uses a simple graphical interface, the Android application also contains a

sophisticated programming language that can be used to create highly customized applications.

The application can also use simple quality control checks, and advanced users can use the

enhanced features using SQL query. The programme’s user manual also contains rich

documentation describing the language, the Android features, and the step-by-step user functions.

Kenya

For Kenya, all respondents considered the main areas where the DA project added value were data

collection, transmission, and validation. In the short time that the KNBS has used MTBDC for

CPI, several advantages have been noted (e.g. integration of specification aspects in the data

collection software and geo-referencing, minimising errors in calculations; real-time transmission

of data; and elimination of data entry, thus saving time). CPI data collection using manual systems

used to take about three weeks after the end of the month before compilation and reporting. When

MTBDC systems are fully implemented, this process should be reduced by up to one week.

KNBS staff noted that the project added value to its provision of national statistics. Compared with

other software currently being used to collect and report data, E-Survey CPI software is user-

friendly, efficient, and does not need third-party software to operate. (It was customised from

software already developed by the KNBS.) It has a user manual detailing all the steps, and each

interface has captions properly labelled with clear instructions.

The KNBS and SOM-UoN tried different measures to ensure cost-effectiveness during the

project’s implementation. As targeted, 40 Techno tablets were procured and installed with the

Page 23: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 16

software. And although a Samsung tablet, when compared with a Techno device, proved more

user-friendly, it is far more expensive ($600) than a Techno’s tablet ($300). Piloting was carried

out over three months, and the issues identified were shared with the software developer during

the training and review workshop. According to the KNBS, the money allocated was sufficient

only for the data collection component and not for compilation and analysis, which are equally

important. As a result, during piloting, only relevant personnel were involved to ensure continuity

and achieve more for less cost.

The E-Survey CPI software is not being fully utilised at present, likely because the trained KNBS

CPI enumerators are few and overwhelmed by the various data collection exercises. As such, the

KNBS sorely needs capacity in this respect, coupled with continuous capacity building in order to

continue the project objectives. To improve its quality, the software will be continuously modified,

tested, and reviewed for 12 months, after August 2016. As noted during the evaluation, Kenya’s

internet connectivity is stable, and geo-referencing is able to confirm whether actual observations

were made. Respondents noted that geo-referencing, coupled with a record of actual time periods

when prices are observed, is very instrumental in instilling professionalism in retail price

collection. The E-Survey CPI software geo-referencing capability was appreciated.

Tunisia

The project achieved the first objective which allowed the NSO to effectively start data collection

with mobile technologies for the CPI survey. The soon-to-come employment survey will also be

done with the tablets. However the other objective (development of a partnership between the

NSO and TRI) was not achieved. This partnership was however important because it was meant

to support the development of skills and expertise within the TRI so that the development of mobile

technologies for data collection becomes sustainable either through the adaptation of these

technologies for other surveys to be done by the NSO or the replication of the tool by other actors.

Part of this has to do with the fact that the start of the project was delayed due to administrative

issues on ECA side. The budget for the project in Tunisia was 212,518.20 USD. This budget was

enough to build the capacity of the NSO and TRI to develop the tool that was used in the CPI

survey. To date, all CPI surveys are using the mobile data collection platform which is said to be

very user-friendly and has helped the NSO to reduce the time to collect and report price

information by 50% of the time it needed before the adoption of this system.

Zimbabwe

Zimbabwe was a singular case, given the issues of deregistration of the TRI and delays in starting

the alternative project (i.e. CPS) that affected the entire project’s timeliness and cost-effectiveness.

Resources were spent on the earlier project, which had to be abandoned. But there are some

positives that were taken from the new project. For example, ZIMSTAT was able to receive

support in linking their server to mobile networks, which is an important issue when conducting

data collection using mobile devices.

Page 24: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 17

Value for money was evident in that the project collected data more efficiently by eliminating data

entry processes, the transportation of papers, and timely submission after data collection. The

initial cost of setting up the systems is high; but once systems are in place it is cheaper. Although

the project was only piloted in three provinces, it has put ZIMSTAT in the limelight as it

demonstrated that the Agency can keep up with the times and lead the paperless revolution in the

country’s collection of vital statistics. Other departments have since been using the same software

on different projects.

The software used for the DA project was user-friendly and clearly labelled. The screen transition

was very smooth, although some enumerators complained about some of the machines freezing

whilst in use. Even though there are too many categories as required in this type of survey, CSPro

was appropriate for the pilot project. ZIMSTAT needed to invest more time in training the

enumerators, but this was limited by the availability of funds. In terms of cost effectiveness, the

NSO bought Android tablets that were fit for the job and not fancy. The alternative, CPI project

managed to achieve its set targets in a short time (Aug.–Dec. 2015), adding value for money as the

project managed to promote the use of MTBDC in surveys. Other ministries, too, have come to

appreciate the role of the NSO due to this short-term project. The collection and quality of data

would have benefitted even more had the project been implemented over a longer period.

Nonetheless, the project was cost-effective, considering the time and resources used to implement

it. In the end, the NSO managed to develop and implement a geo-enabled mobile data collection

system (including software and hand-held devices, such as techno tablets) for collecting CPI data.

Conclusion

In general, the project was highly efficient across the six countries. The project was highly valued

by the interviewees because it facilitated the processes used by the NSO to collect, process and

report on price information. The project built the capacity of both the TRIs and the NSOs, which

was a key achievement. The software seemed to have integrated geo-referencing information and

were said to be very user-friendly and are actually being used to collect and report on price

information.

3.4 PROGRESS TOWARDS IMPACT

The fourth dimension of the evaluation looked at the extent to which the results achieved through

the DA project helped to reduce the time needed to collect and report statistics across the six

countries and improve their quality in the NSOs. The MTE also tried to assess any progress

towards impact that the project may yield in the foreseeable future.

Cameroon

Page 25: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 18

For Cameroon, the DA project set up more efficient complementary modules for real-time central

processing. The project has also made data collected available to the NSI on a daily basis, which

limits the risk of loss of data and reduces delays in data processing. Furthermore, the DA project

has reduced data collection times, and set up a platform for collaboration with the École Nationale

Supérieure Polytechnique for the management and transfer of data. Nonetheless, the mode of

collaboration between these two institutions needs to be improved. The project has improved real-

time quality control of data collected in the field. One improvement is the fact that data are

transferred directly to the server.

Ethiopia

In addition, other important outcomes of the DA project for Ethiopia are the partnership,

knowledge, and capacity created at national level; and the institutional arrangement and

partnerships created and strengthened during the project period, which will serve as a reliable basis

for magnification and scale-up of the project’s approaches and systems. The exemplary partnership

between the CSA and ESA, beside boosting both institutions’ capacity, knowledge, and experience

in MTBDC project management and implementation, has created the opportunity for the CSA to

identify and access senior academicians (such as statisticians) for their professional consultancy

and advisory services. The favourable enabling environment created as a result of the project

enhanced capacity of the CSA on MTBDC, will enable the CSA to better discharge its legally set

duties and responsibilities (as enshrined in its establishment proclamation), and spearhead/lead the

National Statistical System towards utilisation of MTBDC systems. Yet, subsequent to the project,

an overriding outcome has been the inspiration created by the project on mobile data collection on

the activities of the CSA, ESA, and potentially other stakeholder institutions.

The introduction and use of MTBDC in other institutions in the country are expected to be another

outcome of the project. (The respondents did indicate that some international and a few national

institutions do use smart phones/tablets for some of their data collection needs.) Moreover, with

the increased capacity of the CSA to use MTBDC systems also comes its capacity to support and

guide mobile data collection activities nationally. This will result in multiplier effects of the project

to be effectively utilised.

All respondents from the CSA, ESA, and the enumerators expressed their confidence that the

project has improved the quality of data in the NSO. This is because the MTBDC activity has

significantly reduced human errors that could occur along the data collection–entry–editing

process. It has also enabled more data to be collected reliably and in a very short time than actually

needed for doing the same work using paper-based or PDAs methods. (Noteworthy, too, is the

significant reduction in the number of enumerators, supervisors, budget, logistics, transport, paper,

etc. that could fairly be expected from adopting MTBDC systems). Comparative/experimental

research on quality, quantity, and timeliness of the different methods of data collection (e.g.

MTBDC, PDAs, and CAPI, paper-based) has yet to be done by either the CSA or ESA.

Representatives of both institutions commented that such research be done first as soon as possible

before any mobile data collection activity.

Page 26: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 19

The Gambia

The results of project implementation have been positive despite some challenges. The TRI noted

a number of indicators of achievement. For example, MTBDC ensures that prices are verified as

they are entered directly from the collection point and transferred to the server, reducing both the

use of manual data collection and the time it takes. Besides network connectivity issues

experienced in some parts of the country, the data collection survey has been conducted

successfully across the country. All supervisors of the respective teams were able to synchronise

price data with the tablet devices to the central server from the selected markets nationwide.

The use of MTBDC ensures that data are readily available upon collection and up-load. There were

no problems or data entry errors; and access to content by staff of the ‘GBoS Price Statistics Unit’

has been problem free. GBoS research analysts very much appreciated the analytical tool they used

for its ability to generate the index with a click of a button. GBoS price statisticians thoroughly

observed the process and have been satisfied with the results.

Kenya

In Kenya, through MTBDC, the quality of data has improved tremendously, not only for CPI but

also for the KIHBS. Hence, the KNBS, as the sole producer of national statistics, will not have to

use additional resources to correct data; improved quality will enhance stakeholder confidence and

support. Overall, respondents maintained that there is increased adoption of MTBDC methods

since DA support in Kenya. The SOM-UoN, for example, has been involved in other research/data

collection exercises using MTBDC, such as a recent survey in partnership with the Kenya

Meteorological Department. Currently, the KNBS is collecting data for the KIHBS and the Micro

and Small Medium Enterprises (MSME) Survey (completed). Both surveys had a component on

data collection using mobile technology. However, even though the KIHBS and MSME are

independent surveys, their use of MTBDC techniques was informed by the DA CPI pilot project.

Tunisia

For Tunisia, the data collected by enumerators in the field are uploaded daily by email to the

internet platform, compared with 10 days or so by fax. As a result, the NIS is now able to reduce

the time it takes to publish its monthly report, from M+4 to M+1 (1 day after the end of the month

instead of 4 days after the end of the month). The quality of data collected has greatly improved,

although officials were unable to quantify this. This improvement is due to features of the

application that bring to the attention of the enumerator whenever there is a significant price

difference compared with the previous month. The amount of missing data also is reduced, as the

platform manager can track near real-time data collection, and can identify points of sale that have

not yet been visited and thus have personalised follow-up with each enumerator in each

governorate of the country. There is now the possibility to identify products by photo and make

Page 27: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 20

audio recordings in order to obtain information in situations where it is not possible to use the

tablet (e.g. in case a vendor refuses, or because of risk of theft).

Zimbabwe

In Zimbabwe, the CPS is a very important exercise for the government. It is carried out by

ZIMSTAT as part of its mandate, and benefitted from the piloting of mobile technology during its

implementation. The pilot project demonstrated that mobile technology can enhance the data

collection process, data quality, and the timely publishing of results from the survey. Some of the

impacts of the pilot project include the following:

Reduction of costs currently being spent on printing and transporting of questionnaires

Reduction of costs and time for data entry

Real-time data collection and transmission

Timely production of statistics

Improvement in data quality

Overall reduction in the cost of producing statistics

Saving of storage space as questionnaires need to be stored

Solved the problem of enumerators running out of questionnaire

Improved data quality as they were able to prove the authenticity of data collected as the

tablets collected geo-referenced data

Lowered resistance within ZIMSTAT to move from paper to mobile system, and afforded

people within the NSO to see the usefulness of the system and helped to pre-test both the

software and tablets

Helped build the capacity of ZIMSTAT to deploy mobile devices in data collection, which

are now a viable option for doing business

Capacity building of ZIMSTAT staff in terms of training on the use of CSPro on Android

devices using the tablets in data collection and the purchase of the server

Positioned ZIMSTAT in the limelight because other line ministries appreciate its role in

collecting statistics.

Overall, the project has demonstrated the capacity of ZIMSTAT to collect statistics using mobile

technology in Zimbabwe. This has been shown by line ministries (e.g. Ministry of Health)

approaching the NSO to design electronic data collection systems for their own surveys. The only

missing link is funding for the procurement of more tablets for use in large national surveys.

Conclusion

The DA project, although piloted in six countries, had several impacts at country level. The most

important of those impacts are: the reduced data entry errors, the reduced workload, the real time

Page 28: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 21

data collection and transmission and the easy way to detect anomalies. Most importantly the time

needed to generate critical information related to prices was cut by about 20 to 40% depending on

the country. The software made it possible to detect at an early stage any error, typo that happen

during the process of data collection, entry and processing which was found to be instrumental for

its widespread adoption by key actors.

3.5 SUSTAINABILITY

The sustainability component dealt with the critical measures that needed to be put in place to

ascertain whether the results of the DA project would continue after its completion. The evaluation

looked at whether the TRIs and NSOs have the capacity to continue to use and improve the

software. It considered whether there are appropriate working arrangements and plans in order to

continue the project’s critical activities beyond its lifetime. The MTE also examined whether a

financial plan had been set up to support the implementation of those activities, as well as whether

the project led to policy reforms at national or regional level.

Cameroon

For Cameroon, this application was developed with CSPro, a software that the NSI has used for

more than 20 years. Moreover, the Institute played a major role in the development of this

application. As part of its partnership with the World Bank for its social safety net projects, the

NSI uses MTBDC systems. Several operations have already been carried out, including the Proxy

Mean Test , the field test, data collection and the final evaluation for the social safety net project.

But there is no clear funding plan to finance the planned activities, however, and the NSI is

working on action plans within available funding models. It plans to carry out production of a final

household CPI based on data collected through mobile technologies.

Ethiopia

In Ethiopia, there are emerging trends in the CSA in using the knowledge and capacity created

through the DA project on mobile data collection towards sustainability. Importantly, the major

inspiration and immediate impact of the project will be on the upcoming National Population and

Housing Census of Ethiopia in 2017. In this respect, respondents indicated that questionnaires for

collecting Census data with mobile-based technologies have been developed using CSPro. At

present, the questionnaires are being field-tested in one of the regions in Ethiopia (Oromia region).

This Census is estimated to require about 140,000 enumerators, hence a similar number or more

of tablets are needed, including reserves. These tablets, or other resources (in-kind or financing),

are expected to be secured through cooperation with international partners, such as the United

Nations Population Fund.

Ultimately, the CSA is making major efforts to raise awareness on and promote the idea of mobile

data collection among government offices, and is finalising the Census tools and instruments. It is

working to secure the government’s endorsement to train mobile data collection enumerators,

Page 29: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 22

supervisors, and others, with goal of launching the first-ever use of MTBDC to gather national

Census data in 2017. The CSA is currently carrying out preparatory activities and experimentation

on introducing MTBDC methods for industrial producer prices and quarterly medium and large

industries surveys. Through a network created under the ECA and ESA, the CSA hopes to

coordinate and share experiences on the use of MTBDC, with other African countries or sub-

regional and regional institutions. The partnership between the CSA and the US Census Bureau

will also continue to be key to further improvement and utilisation of the software for MTBDC

systems.

Since the DA project was completed, there has been no major intervention or plan to engage in

further MTBDC activities, or in committing funds and financial resources for such an intervention.

The Gambia

The application developed by the DA project was fully embraced by project users eager to test the

capability of a system, network, or process to handle a growing amount of work, or its potential to

be enlarged in order to accommodate growth. Such high regard should not be underestimated, as

it is a reliable predictor for early adoption of MTBDC methods and the commitment to build and

strengthen human capacity for their continued use. After application development and

maintenance, new features might be requested or bugs might be detected. The ability to quickly

add new features, fix bugs, and deploy changes is also very important.

To determine the best priced index, it is imperative that features that are strictly essential for any

price data collection be considered for deployment. Given the relative strengths and weaknesses

identified in digital and manual platforms, decisions as to which platform to use will depend solely

on user preference and data collection requirements. MTBDC systems save costs and increase

speed, accuracy, functionality, and security. In this sense, they are the future.

Kenya

To sustain DA project activities in Kenya, 100% of respondents thought that it was crucial to

continue to encourage buy-in by different government officials and sharpen the focus on

developing capacity and skills within the KNBS, SOM-UoN, and other research institutions.

Respondents underscored the importance of data validity and reliability, and the benefits that

accrue, stressing the need for continued operationalisation of the E-Survey CPI software. They

highlighted the need to inculcate the culture of knowledge generation and sharing for the benefit

of the entire country. During the evaluation, it was established that the KNBS has re-engaged an

earlier consultant (see Section 3.3) to incorporate the current software issues identified and to train

staff for internal support and continuity. Other sustainability measures include plans by the KNBS

and SOM-UoN to finalise the implementation report by the end of June 2016. This would enable

them to receive the remaining 15% of the project’s funds meant for procuring hardware for safe

storage of CPI data. The KNBS also plans to recruit and train more enumerators to bridge the

current capacity gaps. As noted during the evaluation, most of the enumerators are aging (50 years

Page 30: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 23

and older); hence the pressing need for continuity. Additionally, the KIHBS and MSME’ 400

Samsung tablets will revert to the KNBS once the surveys are completed.

As to funding, the KNBS, through the Medium Term Expenditure Framework, has earmarked

resources to continue project activities and its core functions. Overall, the pilot project has not

resulted in any policy reforms at national or regional level. Regionally, the KNBS and other NSOs

have only harmonised concepts and compilation methods—not data collection techniques. The

main successes have been the project’s contribution to raising awareness about mobile data

collection in Kenya. By making strategic use of this baseline information and activity appraisals,

the KNBS and SOM-UoN should be able to develop targeted strategies for implementation to

further the ECA’s aspirations. Interviews with respondents showed that the project’s approach was

widely applicable, and that there was a potential for wide learning across/between countries and

organisations, locally and internationally.

Tunisia

For Tunisia, the sustainability of the project within the NSO is guaranteed to the extent that

the use of tablets is now part of its standard working procedure. The CPI has since abandoned

paper-based data collection, including the 2017 Employment survey, as the NSO plans to gradually

introduce digital data collection methods for all surveys. The NSO is now positioned to further

develop the application as shown by the new development currently on-going.The TRI, however,

did not develop capacities to use or develop the application because of its limited involvement in

the project.

Zimbabwe

ZIMSTAT in Zimbabwe now has the capacity to continue with the project and use MBTDC

systems. A huge bonus too is that the Agency can develop its own needed software, eliminating

the high cost of hiring outside software developers. Although the DA project was initiated,

implemented, and completed in just 5 months (Aug.–Dec. 2015), ZIMSTAT has shown that it has

the capacity to continue using the skills gained from the project by setting up other governmental

line ministries (i.e. MoHCC, Ministry of Lands) to carry out their own surveys. There has been

buy-in within ZIMSTAT as the use of MBTDC is now an option as part of its mandate. Initially,

there was resistance on whether migration from paper to the use of mobile devices was viable, but

the project managed to dispel those doubts. Overcoming these early misgivings is crucial to

consolidating the gains realised by the project. Moreover, collecting statistics on mobile devices

enhanced data validity and reliability by improving the quality of data and ensuring that CPS data

is geo-referenced.

And yet, despite the project’s many positives, the government cannot afford to purchase and

maintain new equipment, or to train enumerators in order to expand the process beyond the three

provinces where the tablets were piloted. At the moment, ZIMSTAT has not achieved the threshold

needed for collection of statistics at the national level with the same mobile devices, and has no

financial plan for acquiring more MTBDC equipment. But development partners have expressed

Page 31: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 24

interest in supporting the government, although nothing has been confirmed to date. An important

measure that needs to be in place to ensure the sustainability of the project is the allocation of

funds needed to maintain mobile devices/ servers, update/develop software, and train staff. (The

initial cost of purchasing mobile devices and servers, which is usually the most burdensome factor

for NSOs, was covered by the DA project.) No doubt, all of these measures that have direct

influences are important. Equally so are the indirect factors, such as commitment at senior level in

the organisation and awareness of the use of new MTBDC systems. These form the basis of support

for introducing direct measures and fostering innovation.

Conclusion

At the time of the midterm evaluation, the TRIs and NSOs which have been involved in the

implementation of the project had the capacity to continue to use the software and generate useful

price-related information using mobile technologies. Critical capacity has been generated and is

available at country level, should similar project need to be replicated. No plan seemed to be put

in place for the project to continue critical activities beyond its lifetime though. Going forward it

will be necessary to think about that to maintain the project achievements and perpetuate its

impacts.

4. MAJOR ISSUES AND PROBLEMS AT THE COUNTRY LEVEL

Across all six countries, evidence shows that the implementation of project activities was

substantially complete, though some challenges remained unresolved.

For example, in Zimbabwe, apart from issues related to the deregistration of the TRI, there were

critical issues around the inability of the government to provide funds to support the expansion of

the project beyond the three provinces where it had been piloted. There were also issues relating

to inadequate time for testing of the system and training of the enumerators, but these were

resolved by close follow-up and technical support during the data collection phase.

In Kenya, project implementation was hampered by lack of expertise within the KNBS and SOM-

UoN in software development, which forced them to bring in external consultants to support the

process. ‘Teething’ problems were also noted as both institutions had never worked together prior

to the DA project. They are different entities altogether—SOM-UoN is a research institution, the

KNBS a semi-autonomous government agency—with entirely different modus operandi.

In Ethiopia and Tunisia, the enumerators at times could not receive the GPS coordinates easily.

Ultimately, they did overcome this by making sure that they first took proper GPS readings before

starting to collect their price data at marketplaces. Enumerators also faced a problem with network

connectivity when trying to upload their data to the servers.

In Tunisia, having the ESSAI be the designated TRI may indeed not have been the most

appropriate choice, as it had not been selected objectively. The project would have benefitted from

a more thorough assessment of the ESSAI and its existing capacities and limitations before the

project got started. This would have made a public or private school or university a better choice,

Page 32: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 25

especially one that specialised in information technology, particularly in mobile applications. To

meet ECA’s requirement, the NIS instead opted for the easiest solution: a TRI it already knew and

had collaborated with (e.g. the recruitment of ESSAI graduates, mentoring of students during final

year projects, etc.). The better alternative, one that would have enabled the two to develop a real

technological partnership, would have been to choose a TRI with real capabilities in MTBDC

systems.

In Cameroon, the process was less smooth. Implementation was impeded by the delay to receive

the funds from ECA at the start of the project, the lack of clarity on the characteristics of the

software to be developed by the TRI (ENSP) and the insufficient participation in the process of

key factors such as INS/prix, MINEPIA, and MINADER.

In the Gambia, several other problems came up: first, the tablets used in the survey were high-

status items in The Gambia, making them a theft risk. Keeping the tablets secured at day time and

hidden while walking to interviews was a priority for the enumerators. Second, safe data storage

depends on uploading the day’s interviews via the Internet, and where WiFi of GSM signals are

not available at the end of each day, the risks go up of a lost or damaged of the tablet compromising

the survey sample. Third, during the interviews, respondents often sat side-by-side with the

enumerators so they could see how the tablet worked. This could influence the answers.

Respondents tend to choose the last answer given if they are hearing the questions or the first

answer given if they are reading the question (the primacy effect).

5. LESSONS LEARNED

Several lessons learned have emerged from the evaluation of the DA project:

Pilot projects are necessary to demonstrate the utility of systems where there is resistance

to changing data collection systems from paper to digital.

Mobile data collection systems can both reduce the cost of producing statistics and improve

data quality.

Integration of specification aspects of data collection software such as geo-referencing

minimises bias and enhances the reliability and validity of data.

Building the capacity of NSOs is key to the financial sustainability of MTBDC surveys, as

shown by the ability of ZIMSTAT to develop its own software—a costly component when

outsourced.

The DA project has sparked a veritable technological revolution, including in the NSOs

approach to its work. It demonstrated that it is possible to collect data in a user-friendly

and much more rapid way, while also ensuring better quality data. Enumerators are more

motivated to carry out their work by raising their profile and recognition, and the reputation

of the NIS as a progressive institution that produces high-quality, reliable products is

Page 33: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 26

enhanced. The involvement of NSO staff in the project, either at management level or

through the training of enumerators, was essential to the project’s success.

Although NIS’s development of a tablet application was an undeniable success, the

cultivation of the partnership between the NSO and the TRI—in Tunisia particularly—was

key to guaranteeing the dissemination of mobile technologies and to ensuring that these

reach the largest possible number of organisations that carry out field surveys. It is

essential, then, that the two parties work to develop a real partnership for the benefit of the

NSO as well as for the whole country.

Proper collaboration between the NSOs and TRIs is beneficial in the long run as it

generates knowledge that can be shared across the network, resulting in improved validity

and reliability of country data. The TRI, however, needs to develop a track record in the

area that it is supporting to ensure that the mandate and skills gained through the project

can continue beyond the pilot phase.

It is important to clearly identify the characteristics of the software when partnering the

NSO with the TRI in order to be certain the final product includes all the features needed

to achieve its purpose.

In general such project are very relevant to the needs of the NSOs at country level hence

the high level of utilization. It is nonetheless important to both start the contracting and

administrative process well ahead of time to prevent delays and involve all the actors in

the design process to fully benefit from their participation.

6. RECOMMENDATIONS

At the end of this evaluation, the following recommendations are made to help sort out the

problems encountered by the DA project and facilitate design and implementation of similar

projects in the future:

It is important for ECA’s future projects that the NSO receives assistance in the TRI

selection methodology, through the provision of a TRI assessment grid prior to signing the

agreement between the ECA and NSO. At the same time, the agreement must clearly define

the TRI as well as the TRI’s expected activities and its budget for those activities.

Otherwise, there is a risk that the NSO will work alone in order to retain the entire budget.

The ECA should take into account the time it needs to complete its administrative processes

before the funds can be accessed by their partners. A proper planning will reduce delays

suffered by similar projects in the future.

A feature of the CSPro software is that it can capture the geo-code of the enumeration area

in combination with outlet codes. This can provide quite detailed geographic information

that may be linked to/analysed with price information. In addition, the software has a

function for GPS reading (longitude/latitude), although this largely depends on network

availability. It would appear from the interviews that this geo-information was not

Page 34: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE

Report 27

thoroughly explored across all the six countries. But having this functionality would enable

the NSO not only to conduct spatial analysis of the statistical data it collects with mobile

devices, but also to link these data with other socio-economic information that is beyond

the scope of DA project.

The choice of a TRI and the theme of the DA project needs to be consultative and

exhaustive in order to ensure project success.

Outsourcing software development work is expensive. These pilot projects should

therefore build the capacity of the NSOs’ own staff in order to set up mobile data collection

systems themselves.

The NSOs should carry out further pilot testing with large geographic coverage of urban

and rural areas of their countries. This would promote better appreciation for the efficiency

and effectiveness of the MTBDC system for price data collection, including the presence

or absence of power, internet connectivity, and other essential factors.

Page 35: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

1

ANNEXES

1. DATA COLLECTION TOOLS

Interview guide with NSO and TRI staff

Date:

Country:

Institution:

Respondent:

Title of the respondent:

Contact of the respondent:

1. Are the project approach and objectives relevant to the achievement of expected outcomes, given

national and regional priorities?

2. What process did you follow to develop the software?

3. Did you receive all the support you needed to finalise the development of your software? If not

what was lacking?

4. How many times did you get to use the software since it was finalised?

5. How did you find it?

6. If you have not used it since its finalisation, what are the reasons behind?

7. Was the logical framework indicators appropriate and of sufficient quality to assess performance?

8. Were the project activities at country level well designed and do they fit the framework of national

and regional strategies for development in the area of intervention?

9. Has a ‘gender approach’ been considered in the project implementation?

10. Have the objectives remained valid and relevant throughout implementation?

11. What are the implementation tools and mechanisms? Are they appropriate for the smooth and

timely implementation of key outputs?

12. Has the DA project attained its intended targets as set forth in the project proposal?

13. Has the DA enhanced the capacity of mobile data collection at NSO and TRI levels?

14. To what extent did the DA project generate knowledge that has been shared across the network of

NSOs and TRIs?

15. To what extent did the DA project achieve its expected results, in terms of quantity, quality, and

timeliness at country level?

Page 36: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

2

16. How user-friendly is the software developed during the DA project as opposed to the other software

currently being used in data collection and reporting?

17. To what extent is the software able to integrate geo-referenced information?

18. To what extent do the results achieved through the DA project contribute to increasing the quality

and reducing the time needed to collect and report country level statistics?

19. To what extent has the DA project improved the quality of data in NSOs?

20. What is the value added of the DA project with regard to the role of the NSOs?

21. What are the critical measures that need to be put in place to ascertain that the results of the DA

project continue after its completion?

22. Do the NSO and TRIs have the capacity to continue to use and improve the software?

23. Have appropriate working arrangements and plans been put in place to continue critical activities

of the project beyond its lifetime?

24. Has a financial plan been set up to support the implementation of those activities is there clear

commitment to fund it?

Interview guide with DA project focal persons in ECA

Date:

Department:

Respondent:

Title of the respondent:

Contact of the respondent:

1. Are the project approach and objectives relevant to the achievement of expected outcomes, given

national and regional priorities?

2. How did you identify the beneficiary countries? And the beneficiary institutions at country level?

3. Was gender a focus area during the development of the DA project? If yes what was done to ensure

that gender was mainstreamed? If not why?

4. Were the key performance indicators in the logical framework appropriate and of sufficient quality

to assess performance?

5. Were the project activities at country level well designed and do they fit the framework of national

and regional strategies and priorities for development in the area of intervention?

6. Have the objectives remained valid and relevant throughout implementation?

7. What are the implementation tools and mechanisms? Are they appropriate for the smooth and

timely implementation of key outputs?

Page 37: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

3

8. Has the DA project attained its intended targets as set forth in the project proposal?

9. To what extent did the DA project generate knowledge that has been shared across the network of

NSOs and TRIs?

10. To what extent did the DA project achieve its expected results, in terms of quantity, quality, and

timeliness at country level?

11. How can the level of utilisation be explained? What are the key drivers of that utilisation?

12. How did you undertake monitoring and reporting regarding the project activities in your country

of responsibility?

13. What were the main issues/challenges that you had to face during project implementation?

14. To what extent is the software able to integrate geo-referenced information?

15. What are the critical measures that need to be put in place to ascertain that the results of the DA

project continue after its completion?

16. Do the NSO and TRIs have the capacity to continue to use and improve the software?

17. Have appropriate working arrangements and plans been put in place to continue critical activities

of the project beyond its lifetime?

18. Has a financial plan been set up to support the implementation of those activities?

Interview questions with enumerators

Date:

Country:

Institution:

Respondent:

Title of the respondent:

Contact of the respondent:

1. How many times did you use the software that was developed with the DA project to collect data?

2. How was the training that you had to take to be able to use the software?

3. After your experience using the software, what are the top three issues/challenges that you had with

the software?

4. How were they addressed?

5. Has the DA enhanced the capacity of mobile data collection at NSO and TRI levels?

6. How user-friendly is the software developed during the DA project as opposed to the other software

currently being used in data collection and reporting?

Page 38: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

4

7. What is the level of utilisation of the software at country level?

8. How can the level of utilisation be explained? What are the key drivers of that utilisation?

9. To what extent is the software able to integrate geo-referenced information?

10. To what extent do the results achieved through the DA project contribute to increasing the quality

and reducing the time needed to collect and report country level statistics?

11. To what extent has the DA project improved the quality of data in NSOs?

12. What is the value added of the DA project with regard to the role of the NSOs?

13. What are the critical measures that need to be put in place to ascertain that the results of the DA

project continue after its completion?

Page 39: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

5

2. EVALUATION TIMELINE

The following timeline was proposed for the evaluation.

# Activity From To

1 Development of the evaluation inception report which will include

the methodology, tools, and procedures that will be used by the

national data collectors and lead evaluator

April 18th May 6th

2 Finalise the inception report based on the comments from the ECA May 8th May

17th

3 Skype teleconference with each of the national data collectors to

explain the methodology and the tools that will be used

May 18th May

21th

4 Data collection at the national level May 22th May

30th

5 Report writing at the national level May 30 June 5th

6 Interviews with additional stakeholders June 5th June

10th

Country reports received from national data collectors June 15th

7 Improve the reports at the national levels through discussions with

the national data collectors

June 15th June 18th

8 Summarise the data and write up the MTE report June 18th June 25th

9 Submit draft of the MTE report June 27th

10 Comments of the first draft by the ECA June 30

11 Revise the draft and submit a final MTE report by incorporating

comments received from the ECA

June 30th July 2nd

12 Submit final report July 5th

Page 40: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

6

3. PEOPLE INTERVIEWED AND CONTACTS

S/No. Name Institution Email

Zimbabwe

1. Mr Rodgers Sango ZIMSTAT [email protected]

2. Mr Wish Chipiro ZIMSTAT [email protected]

3. Ms Esnat Mutumbure ZIMSTAT -

4. Mr Elias Fushai ZIMSTAT [email protected]

5. Mr Shepherd Mandi ZIMSTAT [email protected]

m

6. Mr Emmanuel Gwenzi ZIMSTAT [email protected]

7. Mr Aubrita Gweshe ZIMSTAT [email protected]

8. Mr Salisio Budakuvaka ZIMSTAT [email protected]

m

9. Mr Z. Mabire ZIMSTAT [email protected]

10. Ms Inkyung Choi ECA [email protected]

Kenya

11. Mr Cleophas Kiio KNBS [email protected]

12. Mr Robert Nderitu KNBS [email protected]

13. Mr Simon Gaitho KNBS [email protected]

14. Mr Evans Munene KNBS [email protected]

15. Prof. Moses Manene SOM-UoN [email protected]

16. Prof. Patrick Weke SOM-UoN [email protected]

17. Mr Ndubi Arun KNBS -

18. Mr Silas Mulwa KNBS -

Ethiopia

19. Mr Kifle Gebre CSA 251-911409817

20. Mr Abdulaziz Shiffa

Yimam

CSA/ESA 251-912199550

21. Mr Zelalem Destaw ESA 251-912035205

22. Mr Didimos Ayele CSA 251-911418341

23. Mr Ermyas Arega CSA/ESA 251-911303646

24. Mr Abel Tesfaye CSA 251-911070790

25. Mr Yabebal Ayalew Addis Ababa University 251-913559036

26. Mr Gezahegn Getahun Private consultant 251-921794541

27. Mr Bekalu Mehari CSA 251-911027207

28. Mr Taddesse Kasahun Addis Ababa University 251-911835082

29. Mr Temesgen Abera Addis Ababa University 251-921467143

Cameroon

30. Léandre Ngongang CEA [email protected]

31. Martin Mba INS [email protected]

32. Guy Ndeffo INS [email protected]

33. Eric Jazet Kengap INS [email protected]

Page 41: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

7

34. Jean Alogo Samba INS [email protected]

35. Clément Eyem Georges INS [email protected]

36. Romain Tchakoute INS [email protected]

37. Thomas B. Bouetou École Nationale Supérieure

Polytechnique

[email protected]

38. Peggy Kuinze K. Alvine INS [email protected]

39. Brice-Muriel Tientcheu INS [email protected]

40. Joel Nkouagnou Calin INS [email protected]

41. Marthe Ngo Lihep Ministère de l’Élevage, des Pèches et

des Industries Animales

[email protected]

42. Jules Cheumetou Ministère de l’Élevage, des Pèches et

des Industries Animales

[email protected]

The Gambia

43. Mr Léandre Ngogang

Wandji

ECA [email protected]

44. Mr Nyakassi M.B.

Sanyang

The GBoS (NSO) Tel: +(220) 9969821

45. Mr Ousman Dibba The GBoS (NSO) Tel: +220 9969981

46. Dr Momodou Jain University of The Gambia (TRI) [email protected]

47. Mbemba Hydra University of The Gambia (TRI) [email protected]

48. Pa Safiong Kebbeh University of The Gambia (TRI) [email protected]

49. Mr Molamin Fadia The GBoS (NSO) [email protected]

50. Mr Morro Sanyang The GBoS (NSO) [email protected]

51. Mr Sainey Jallow The GBoS (NSO) [email protected]

52. Mr Tumbulou Drammeh The GBoS (NSO) Tel:- +(220) 6575535

53. Mr Ebrima Keita The GBoS (NSO) [email protected]

Tunisia

54. Mme Mouna Zgoulli INS [email protected]

55. M. Néjib Khlifi INS [email protected]

56. M. Hatem Sedghiani INS [email protected]

57. Mme Samira Chihi INS

58. Mme Saloua Khemiri INS

59. Mme Wissem Sellam INS

60. Mme Rim Lahmandi

Ayed

ESSAI [email protected]

om

61. Ms Meriem Aït Ouyahia ECA [email protected]

Page 42: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

8

Page 43: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

9

4. EVALUATION TOR

Midterm Evaluation of the Development Account Project “Strengthening the Capacity of

African Countries to Use Mobile Technologies to Collect Data for Effective Policy and

Decision Making”

1. Background and Context

Project number 2920

Project title Strengthening the Capacity of African Countries to Use Mobile

Technologies to Collect Data for Effective Policy and Decision

Making (Phase I)

Duration 2013–2015

Location Inter-regional project with 6 pilot countries (Cameroon, Ethiopia,

The Gambia, Kenya, Tunisia, and Zimbabwe)

Executing agency

(implementing entities)

Economic Commission for Africa (ECA)

Department of Economic and Social Affairs (DESA)—United

Nations Statistics Division (UNSD)

Partner Organizations National Statistics Offices (NSOs) and Training and Research

Institutes (TRIs) in 6 pilot countries

Total approved budget US $1,845,000

Donors Development Account fund

The Government of Ireland for implementing a pilot project in

Ethiopia

Division/IDEP/SRO/Section African Centre for Statistics (ACS)/Data Technology Section

(DTS)

SRO - Central Africa

SRO – Eastern Africa

SRO – North Africa

SRO – Southern Africa

SRO – West Africa

Programme/Project

Manager

ACS/DTS

Statistics play a crucial role in the overall development policy making process of countries by providing

the evidence for setting objectives, targets and priorities. However, the statistics on which such evidence

would be based are not always available in a timely manner in many African countries and their reliability

is not always assured. Most African national statistical systems often use manual, paper-based data

collection methods whose lengthy process not only delays the production of data for decision making, but

also requires a lot of personnel for data collection, thereby exacerbating the financial constraints. Computer

Assisted Interviewing (CAI) methods are increasingly replacing pen-and-paper methods of survey data

Page 44: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

10

collection but due to the low technology base, CAI methods are not yet as widely used in Africa as in other

parts of the world.

The Development Account (DA) project on “Strengthening the Capacity of African Countries to Use

Mobile Technologies to Collect Data for Effective Policy and Decision Making” (DA project hereafter)

was launched in 2013 with aim of enabling the National Statistical Offices (NSOs) to develop technological

bases for the mobile data collection in a partnership with Training and Research Institutes (TRIs) within

the country. Cameroon, Gambia, Kenya, Zimbabwe, Ethiopia and Tunisia were selected as pilot countries

where NSO and TRI of each country established the implementation program in a collaboration.

2. Disbursement History

Total Approved Budget

(US$) 2013–2015

Expenditure (US$)

(2013–2015)

Expenditure

(%)

(2013–2015)

Remarks

1,845,000.00 1,724,200.15 93.45% Main DA (five countries)

163,224.00

(Exclusive of programme

support cost)

139,361.04 85.38% Parallel pilot project

(Ethiopia) funded by the Irish

Government

3. Purpose of the Evaluation

The evaluation will assess the quality and viability of the mobile data collection system established in the

region through DA project.

The global evaluation for the DA project as a whole will be carried out by an international evaluator (see

also Section 6. Evaluation Methodology) who will be recruited separately. The national evaluator will

collect detailed data for the international evaluator to collate into the comprehensive mid-term evaluation

report for the project.

The evaluation result will also be used for designing Phase 2 of DA project.

4. Scope of the Evaluation

Type of evaluation Midterm evaluation for DA project

Time period covered by the

evaluation

Entire project implementation period

Geographical coverage of the

evaluation

Regional with focus on 6 pilot countries

5. Evaluation Criteria And Key Evaluation Questions

Relevance: Were the objectives as stated in the result frameworks consistent with member state-specific

policies, strategies, and plans?

Page 45: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

11

Sample questions:

Objective/ rationale / logical framework: are they relevant to the achievement of expected

outcomes, given national and regional priorities? Was the logical framework indicators appropriate

and of sufficient quality to assess performance?

Was the programmes well designed and do they fit the framework of national and regional

strategies for development in the area of intervention?

Has a “gender approach” been considered in the programme design?

Have the objectives remained valid and relevant throughout implementation?

What are the implementation tools and mechanisms? Are they appropriate for the smooth and

timely implementation of key outputs?

Effectiveness: How effective have the interventions carried out been in terms of achieving the targeted

results?

Sample questions:

To what extent have the objectives been achieved?

What have been the (quantitative and qualitative) effects of the intervention?

To what extent do the observed effects correspond to the objectives?

To what extent can these changes/effects be credited to the intervention?

What factors influenced the achievements observed?

To what extent did different factors influence the achievements observed?

How user-friendly and easy the developed software is judged by consultant himself/herself

How user-friendly and easy the developed software is judged by enumerators and self-enumerators,

if applicable

Whether user manual of the software is available

Whether developer manual of the software is available

Whether the developed software have a functionality to record and send geospatial information of

the data

Efficiency: How efficient has the overall effort been in terms of management of resources, time committed

vis – a- vis results achieved?

Sample questions:

Were activities cost-efficient?

Were objectives achieved at the least cost?

Were the interventions implemented in the most efficient way compared to alternative ways?

Impact: To the extent possible, assess how the impact of the interventions funded under can reasonably be

attributed to or be associated with the support of the Commission. While ECA aims for specific social and

economic impacts, a range of intermediate changes will be instrumental to achieving these impacts. The

Page 46: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

12

evaluation will attempt to measure such changes, which include influence, leverage, and learning, as

evidence of progress towards impacts.

Sustainability (potential for scalability): How sustainable has been the overall efforts, how well suited

was the initiative to the members’ states respective structures and to the overall goal and strategies of the

program at national and regional level? How sustainable will be the results if the support comes to an end?

- How much viable the working arrangements are to incorporate the developed program into the NSO’s

regular work (if applicable) How much viable the working arrangements are for the self-enumerators to

continue reporting data?

Sample questions:

To what extent and in what ways have national capacities been enhanced in the government

To what extent is there potential for replication and scaling up of innovative or catalytic approaches

Have complementarities, collaboration and / or synergies fostered by ECA contributed to greater

sustainability of results at the country/regional level

6. Evaluation Methodology

To allow more comprehensive analysis in the pilot countries, six national evaluators will be recruited for

the pilot countries who will collect data based on following activities:

Review of reports and documents prepared by NSO and TRI regarding the project conducted in the

respective country

in-person interviews with NSO, TRI and enumerator

hands-on experience with mobile application developed by NSO and TRI

and write a national evaluation report for the consolidated midterm report.

The consultants will design the evaluation methodology. They are also expected to propose refined and

specific evaluation questions to be included in the Inception Report. The evaluation should go beyond

questioning whether the indicators as set out in the original log frame have been achieved and should aim

to question the contribution of the programme to the outcomes and to assess the unplanned and unintended

results of the programme (positive and negative), and to learn how and why the change happened. The lead

consultant is expected to propose a suitable evaluation design and methodology for addressing the

evaluation questions, with justification.

Desk Review/secondary data collection will involve A thorough review of the Logframe, progress

reports, final reports and assessments.

Document review including analysis of previous reviews and evaluations and key reports and

reference documents.

Field work/Primary data collection: This will be conducted to the national data collectors, with

substantive support and oversight from the lead consultant

Selecting respondents. Criteria for selecting respondents will include, but not limited to:

Focal points from selected countries – ministries and institutions.

Develop Data collection protocols

Define data collection techniques to be used for different respondents.

Page 47: Midterm evaluation report · 2017-03-30 · Midterm evaluation report Submitted by: Alexandre Diouf ... MoHCC Ministry of Health and Child Care MTBDC Mobile technology-based data

DA Project MTE Report A-

13

7. Timeframe and Deliverables

The evaluator will be working for one month in total which would be divided into two parts:

1. Approximate 1~2 week(s) before national evaluation begins to provide guideline for national

evaluators and communicate it with them and

2. The remaining period after national evaluations end to compile reports, evaluate the DA project

and write the final report.

During the consultancy period, the evaluator should deliver:

a work plan within one week of the beginning of contract

an evaluation guideline/template for the national evaluators within two weeks of the beginning of

contract

an evaluation report by the end of contract

8. Evaluation Team Composition

Following people will be involved in the evaluation process:

National evaluator, in charge of collecting data from the pilot country and writing a national

evaluation report for the country

International evaluator (team leader; will be recruited with a separate TOR), in charge of

coordinating the six national evaluations, providing general guidelines for national evaluators and

writing the consolidated evaluation report for the project as a whole.

Management of Evaluation Process

The evaluation section will provide the norms, tools and templates for the different stages of the evaluation

process. It will advise on evaluation matters and quality review the deliverables

Evaluation section in consultation with ACS will clear the final TORs, the inception report and the draft

evaluation report and the final report. The section will support the process of issuing a management

response, and post the report and/or key findings over evaluation section. The section will provide technical

back stopping to the whole evaluation process and will be a part of the committee to select the service

provider

ACS will ensure that all necessary documentation, including project details and data are timely available to

the evaluators, arrange in-house appointments and with key stakeholders that are to be interviewed.