1
To minimize the impact of the work on the lake bed, crews installed silt curtains to keep debris from spreading and water quality was tested daily. To make the repair, divers first removed a 3-to 4-inch-thick coating of concrete from the pipeline, and then bolted on a specialized clamp to reinforce the 0.345-inch-thick steel walls of the pipeline. A team of experienced divers equipped with video cameras and live audio feeds worked in murky underwater conditions to repair the pipe. PIPELINE INTEGRITY UNDER WATER WATER TESTING MAKING THE REPAIR UNDERWATER WORK The project team anchored a barge in Lake Oologah to use as a working platform for crews, close to where the integrity work was taking place on the lake bed. MID-LAKE BASE

MID-LAKE BASE WATER TESTING/media/6A990892735A47C0888FCB3...To minimize the impact of the work on the lake bed, crews installed silt curtains to keep debris from spreading and water

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MID-LAKE BASE WATER TESTING/media/6A990892735A47C0888FCB3...To minimize the impact of the work on the lake bed, crews installed silt curtains to keep debris from spreading and water

To minimize the impact of the work on the lake bed, crews installed silt curtains to keep debris from spreading and water quality was tested daily.

To make the repair, divers first removed a 3-to 4-inch-thick coating of concrete from the pipeline, and then bolted on a specialized clamp to reinforce the 0.345-inch-thick steel walls of the pipeline.

A team of experienced divers equipped with video cameras and live audio feeds worked in murky underwater conditions to repair the pipe.

PIPELINE INTEGRITY UNDER WATER

WATER TESTING

MAKING THE REPAIRUNDERWATER WORK

The project team anchored a barge in Lake Oologah to use as a working platform for crews, close to where the integrity work was taking place on the lake bed.

MID-LAKE BASE