Upload
others
View
14
Download
0
Embed Size (px)
Citation preview
METHOD STATEMENT CLIENT AND PROJECT NAME: Caprari Pumps
SUBMISSION DATE: 14th July 2016
STATEMENT TITLE: JDB Method statement
REFERENCE NO: JDBQ
REV: COMMENT NOTES
1. P R O J ECT DI R E C T ORY
SITE CON T A C T
Peter McGrath – 07836 517375 Caprari PumpsGilbert Millar – 07920 876798 JDB Roofing Ltd
OFF SITE C O N T A C T S
Paul Allaway – 07768 212228 H&S AdvisorJim Bevin – 07748 663577 JDB MD
2 . 1 B R I E F D E S C R I PT ION OF WO R K TO BE C A RR I ED O U T.
The scope of this method statement is as result of a comprehensive site survey by JDBIndustrial Roofing Ltd at Caprari Pumps, Bakewell Road, Peterborough, PE2 6XU to ensure a safe System of work is sufficiently developed to make sure that all risks associated within the scope of works are adequately managed in accordance with legislation (Regulation 3 MHWR & WAH)
2 . 2 SEQ U E N C E OF O PE R A T IO N S.
1. Erect safety netting
Safety netting will be erected to the warehouse underneath the rooflights and secured to the internal roof structure by trained and competent third party FASET trained operatives who will be in receipt of training records, competency certificates and their own RAMS. Work will be carried out to BS1263. Access to the underside of the roof will be via Mobile Elevated Work Platform. All operators will be IPAF trained and competencies given to Site Manager.
2. Erect edge protection
Scaffold edge protection will be erected to the perimeter of the roof as detailed on the plan by third party scaffolder’s who will be in receipt of training records, competency certificates and their own RAMS. Scaffolders will gain access to the roof via tower with materials to construct a triple handrail edge protection system to the perimeter of the roof. Handrails and intermediate rails will be set at a height as deemed appropriate by TG20:2013. 1 no.access tower is to be erected on each building. Running lines are to be installed to the office roof.
3. Machinery / Materials Delivery
All materials to be delivered to site and put in the areas agreed with JDB and Caprari Pumps A 17M telehandler will be delivered to site to facilitate material handling to the roof
METHOD STATEMENT CLIENT AND PROJECT NAME: Caprari Pumps
4. Demarcation of areas
Operatives are to access the roof via the access tower and demarcate the working area with cones & ticker tape on both roofs. This is to ensure operatives do not go beyond the working area.
5. Edge Lap Treatment
Access to the roof for operatives shall be via the access tower. Operatives to jet washthe roof, the corrosion is to be removed from the roof sheet laps with a sanding hand tool, cleaned with giromax approved cleaner, sheet laps are to be treated with an application of mastic sealant prior to base coat followed by topcoat to the end-laps.
5. Replace Ridge, Hip Flashings & Fillers The existing ridge and hip flashings to be removed and replaced with new flashings andweathered. Existing fillers to be removed and replaced with new profiled foam fillers
6. Plygene Gutters
Plygene liner shall be fitted into gutters together with appropriate flashing as per Manufacturers guidelines, ends shall be tucked between eaves of sheeting and existing fillers to ensure water- tightness within buildings. Weldable outlets shall be heat-welded to plygene liner within existing downpipes and stopends shall be formed to suit existing dimensions at existing stopends 7. Area beneath the works is to be cordoned off during works. Staff shall be made aware of progress throughout the works on a regular basis.
8. Remove nets and strike scaffold handrail & tower
The removal of equipment will be in the reverse order of the installation
2 . 3 T I MIN G .
1. Erect safety netting – 1 day2. Erect scaffolding- 2 days3. Edge lap treatment – 5 days4. Replace Ridge, Hip Flashings & Fillers – 2 days5. Plygene Gutters – 3 days6. Strike scaffolding – 2 day7. Strike nets – 1 day
Please note some of the above works will be carried out simultaneously. Significant effects will be due to weather constraints. 2. 4 L OCAT IO N.
Caprari Pumps, Bakewell Road, Peterborough, PE2 6XU
2 . 5 ME T H OD S .
All construction related activities will be compliant with HSG150 and HSG33 Documentation in the form of BS8460 may be used to regarding the safe use of MEWPS
METHOD STATEMENT CLIENT AND PROJECT NAME: Caprari Pumps
2. 6 DURAT IO N.
14 days
2.7 DETAILS OF WASTE CONTROL.
Off-site waste disposal
3 RE SOURCE S REQU IRED.
Secure storage area, Electricity, running water, general welfare facilities i.e. WC.,
3 . 1 JDB IND U STR I AL ROOFING L T D - O P E R A T IVE S .
TBC
3. 2 P LANT A ND EQU IP MEN T T O BE USE D.
Power tools Mobile elevated work platform Telehandler
3 . 3 TR A I N I NG CERT I FICATE S .
IPAF – Mewp , CSCS Construction Site Operative, UKATA Working with Asbestos Certificate, NPORS Telehandler, SSSTS – Site Supervisor Safety Training Scheme
3.4 SUPERVISION.
Jim Bevin – MD (off site) Gilbert Millar – Contracts Manager (off site)TBC (on site)
3 . 5 MA T ERIA L S US E D.
Seamsil 100 Plygene Plastisol Coated Steel Fixings
4. A CCE SS/ E GRESS, LOAD ING/ U NLO ADI NG.
4 . 1 A C CESS INTO SITE.
Via road
4. 2 A CCESS TO ARE A ON H ARDST ANDING FRO M SIT E ENTRANCE .
Loading/access point to be confirmed by site foreman and JDB fixer and cordoned off to prevent public access
METHOD STATEMENT CLIENT AND PROJECT NAME: Caprari Pumps
4 . 3 MA T ERIALS STORED W I T H I N SITE
Materials & plant to be stored internally overnight
5 CONT ROL MEASURES.
5.1 C. O . S. H . H. IN F O RMATION.
N/A
5. 2 IN DUCT IO NS, T OOL BOX TALKS .
To be carried out by site foreman 5.3 SE CURIT Y.
Secure storage for materials and plant within building during works
5 .4 P E RM I T S TO WORK.
n/a – unless site specific
5.5 MAN UAL HANDL ING IN FOR MATION .
General knowledge & experience of operatives
5 . 6 P R OTECTION OF OT H ERS.
Scaffold handrail edge protection, running lines and safety netting underneath the rooflights.
5. 8 P ROT ECTI ON FROM FA LLS .
Scaffold handrail edge protection to the perimeter of the roof Safety nets underneath the rooflights on warehouseRunning lines on Office
IN ACCORDANCE WITH HSG 33 ALL WORK WILL BE CARRIED OUT WHEN WEATHER IS WITHIN PERMIT / ADVISED CONDITIONS. WORK MAY BE STOPPED DUE TO HIGH WIND, DRIVING RAIN & FROSTY CONDITIONS
METHOD STATEMENT CLIENT AND PROJECT NAME: Caprari Pumps
METHOD STATEMENT CLIENT AND PROJECT NAME: Caprari Pumps
5 . 9 PPE T H A T M UST BE U S ED.
Hi-viz, & Safety footwear.
5. 10 PPE T O BE USED WHERE REQU IRED
Gloves, Safety Glasses and Hard Hat
6 SP E C I A L IST I N VO L V E M E NT. 6. 1 DET AILS OF AN Y TE MP ORARY WO RKS/ S CAF FOLD DES IGN , ET C.
6.2 REF E R E NCE TO OTH E R DOC U M E N T S.
Work at Height in accordance with the Work at Height Regulations 2005. Equipment to be used under Provision and Use of Work Equipment Regulations 1998 Health and safety in construction - HSG150 - 2006 Health & safety in roof work – HSG33 - 2008
7. E M ERGE N CY ARRANG E M E N T S . 7. 1 RESCUE I NFORMAT ION .
Emergency services to be called when required, Mewp onsite to be used for removing injured personnel from roof to floor level.
7.2 SP E C I AL FI R ST A I D RE Q U I R E M E N T S.
None
7.3 FI RE EVA CUAT IO N PROCEDURES .
Foreman to assign assembly point on site
7.4 T E M P O R A RY A M E N D E D S Y S TE M S.
None
9. IN FOR MATION SUB MITT ED. 9.1 CHE C K I N G, R E V I E W A ND UP D ATING P R O V I S IONS.
Site foreman carries out daily review of systems and updates rams via office as and when required.
9.2 CHANGE REQUIRE MEN TS.
To be liaised with Site Manager
9 . 3 CONFIRMA T I ON OF O P ERATIVES BRIEF. Sign and return page below
METHOD STATEMENT CLIENT AND PROJECT NAME: Caprari Pumps
10 MONITORING AND CO MPLIA NCE .
10.1 RISK AS SESSME N T , CON T R OL ME A S U RES A N D E X I S T I NG H AZ A R DS.
A work at height risk assessment will be conducted to Regulation 3 of the Management of Health and Safety at WorkRegulations 1999.
1. Identify hazards (see 2.2)2. Decide who might be harmed and how3. Evaluate the risks4. Record findings (including controls, see below)5. Review when onsite and where changes occur a hierarchy of controls will be put into place as per the Work at Height Regulations 2005. Where possible, work at height will be avoided. If avoidance to work at height is not possible, then access equipment is to be selected using the most suitable and safest form of access equipment.Note collective protection measures have been/will be given priority over personal protection measures. Although it may be that a combination of the two will be used.As work at height cannot be avoided, suitable scaffolding will be erected by qualified and competent scaffold erectors6. To get to the roof, access equipment will be used7. This will be in the form of an scissor lift to facilitate netting8. A scaffold handrail shall be erected to the gable of the roof where necessary.9. All access equipment shall only be erected by qualified personnel10. All access equipment shall be suitable for purpose11. All access equipment shall be inspected before use12. Personal Protective Equipment
The correct PPE will be selected in accordance with the Personal Protective Equipment at Work Regulations 1992. All roofers shall wear applicable PPE including:
Gloves to protect skin from abrasions and skin irritation Hi-vis vests so that individuals can be seen by moving vehicles Safety footwear to protect the feet from falling objects. Hard hats (site policy)
Plant and EquipmentAll equipment shall be selected and used in line with the Provision & Use of WorkEquipment Regulations 1998.All equipment shall be suitable for purposeAll equipment shall be fit for useAll equipment shall be inspected prior to useAll equipment shall have a certificate or means of proof that it has been inspectedAll plant and equipment shall only be used by qualified personnel
10.2 M ON I T O R I NG B Y WHOM A N D W H E N . Site Foreman – Daily basis
10.3 ENFORCEMENT – H O W – B Y W H O M . Site Foreman on daily inspectionMD at regular intervals
This method statement must be explained to the workforce before any work commences.
METHOD STATEMENT CLIENT AND PROJECT NAME: Caprari Pumps
I have checked the method statement and comment as above:
Project Manager: Name Signed
Date
JDB Industrial Roofing Ltd Foreman: Name Signed
Date
Two of the above must sign before work commences
Site operatives Signature for receiving briefing of this method statement:
1
2
3
4
5
6
7
8
9
10
METHOD STATEMENT CLIENT AND PROJECT NAME: Caprari Pumps