22
Project time management according to standard guidelines for project management Project Time Management Fachhochschule Dortmund Fachhochschule Dortmund Fachhochschule Dortmund Fachhochschule Dortmund University of Applied Sciences and Arts University of Applied Sciences and Arts University of Applied Sciences and Arts University of Applied Sciences and Arts 8th January 2008 8th January 2008 8th January 2008 8th January 2008 Christoph Johann Szczecina Henrique Adolfo Lima de Faria Supervision: Prof. Dr. Dr. h.c. mult. Peter J. A. Reusch

Microsoft PowerPoint - Project time management according to

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Microsoft PowerPoint - Project time management according to

Project time management according to standard guidelines for project management

Project Time Management

Fachhochschule DortmundFachhochschule DortmundFachhochschule DortmundFachhochschule Dortmund

University of Applied Sciences and ArtsUniversity of Applied Sciences and ArtsUniversity of Applied Sciences and ArtsUniversity of Applied Sciences and Arts

8th January 20088th January 20088th January 20088th January 2008

Christoph Johann Szczecina

Henrique Adolfo Lima de Faria

Supervision: Prof. Dr. Dr. h.c. mult. Peter J. A. Reusch

Page 2: Microsoft PowerPoint - Project time management according to

Contents

• General introduction to PM guidelines� Project Management Body of Knowledge

� IPMA Competence Baseline

� ISO 10006:2003 – TenStep – PRINCE2

• Comparison of selected standards (shortcut)� PMBOK® – IPMA Competence Baseline

� PMBOK® – ISO 10006:2003

• PMBOK® – Time Management – Specialities

• PMBOK® – Activity Sequencing

2Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 3: Microsoft PowerPoint - Project time management according to

• Process oriented in 5 groups among

9 knowledge areas•Integration – Scope – Time – Cost – Quality

•Human Resources – Communications – Risk - Procurement

• Started by PMI in 1987, now 3rd edition

• Set up by to identify common PM practices

• International standard, IEEE 1490-2003

• Detailed description - gives input, output and

techniques for each process

3Project Time Management - Henrique Faria, Christoph Szczecina © 2008

General introduction – Project Management Body of Knowledge

Page 4: Microsoft PowerPoint - Project time management according to

General introduction – IPMA Competence Baseline

• Competence oriented in 3 groups• Technical – Behavioural – Contextual

• Set up by IPMA for personnel certification

• Strong focus on managerial skills

• 4 levels of certification• Certified Projects Director

• Certified Senior Project Manager

• Certified Project Manager

• Certified Project Management Associate

4Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 5: Microsoft PowerPoint - Project time management according to

General introduction – ISO 10006:2003

• Process oriented with 6 process groups• Planning – Organising – Monitoring – Controlling

• Reporting - On-going corrective actions

• Guideline for quality management in projects

• Evaluation of customer/stakeholder needs

• Assures organisational qualities are met

• Not for certification/accreditation

• Initial structure based on PMBOK®

5Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 6: Microsoft PowerPoint - Project time management according to

General introduction – TenStep

• Process oriented with 10 steps•Define the work - Build the schedule and budget

•Manage schedule and budget - Manage Issues

•Manage change -Manage communication - Manage risk

•Manage human resources - Manage quality - Manage metrics

• Incorporated by a consulting company

• No sequential progression besides planning• Higher step →more attention

6Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 7: Microsoft PowerPoint - Project time management according to

General introduction – PRINCE2

• Process oriented approach with 8 processes

and 45 sub-processes•Starting Up a Project - Planning - Initiating a Project

•Directing a Project - Controlling a Stage - Managing Product Delivery

•Managing Stage Boundaries - Closing a Project

• Started in 1989 as UK standard for IT PM

• Most practical approach

• Special techniques� Product Based Planning (PBS)

� Quality Review (Chairman – Reviewer - Scribe)

� Change Control (Change means Project Issue)

7Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 8: Microsoft PowerPoint - Project time management according to

General introduction – PRINCE2 – Change Control

8

Set priorityCategorize

Project Issue

Categorize in the List of

open Issues

Analyze impact (Plans,

BC, Risks)

Evaluate suitable actions

Update Risk and Issue Log

Add actions to plan or create Exception plan

Close Issue in Issue Log

Project Issue

Issue Log

Copy of Issue Log entry to

author

Inform author about

next steps

InformAuthorAboutactions

Confirm entry of issue into

system to author or reply to question

and close IssueRegularly and concerning all Open Issues(CS4: Examining Project Issues)

After the decision of the measurement

Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 9: Microsoft PowerPoint - Project time management according to

Comparison of selected standards – PMBOK® and ICB

9Project Time Management - Henrique Faria, Christoph Szczecina © 2008

6 Project time management

6.1 Activity Definition 14. Time schedules

6.2 Activity Sequencing 14. Time schedules

6.3 Activity Resource Estimating 15. Resources

6.4 Activity Duration Estimating 14. Time schedules

6.5 Schedule Development 14. Time schedules

6.6 Schedule Control 20. Controlling

ICB does not want to include the detailed

specific description of the PMBOK Guide

Based on KNÖPFEL, Hans

Page 10: Microsoft PowerPoint - Project time management according to

Comparison of selected standards – PMBOK® and ICB

• ICB only proposes steps, no direct definition

• Time related processes spread around

competences• Finance

• Personnel Management

• Efficiency

• Control and reports

• Based on Soft Skills – competences • Contextual competences

• Technical competences

• Behavioural competences

10Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 11: Microsoft PowerPoint - Project time management according to

Comparison of selected standards – PMBOK® and ICB

• Possible processing steps could be:

• Define and sequence the activities and/or work packages

• Estimation duration

• Schedule the project or phase

• Allocate and balance resources

• Compare target, planned and actual dates and update

forecast as necessary

• Control the time schedule with respect to changes

• Document the lessons learned and apply to future projects

11Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 12: Microsoft PowerPoint - Project time management according to

Comparison of selected standards – PMBOK® and ISO 10006:2003

12Project Time Management - Henrique Faria, Christoph Szczecina © 2008

6 Project Time Management 7.4 Time-related processes

6.1 Activity Definition 7.3.4 Definition of activities

6.2 Activity Sequencing 7.4.2 Planning of activity dependencies

6.3 Activity Resource Estimating 6.1.2 Resource planning

6.4 Activity Duration Estimating 7.4.3 Estimation of duration

6.5 Schedule Development 7.4.4 Schedule development

6.6 Schedule Control 7.4.5 Schedule control

Page 13: Microsoft PowerPoint - Project time management according to

Comparison of selected standards – PMBOK® and ISO 10006:2003

• No introduction of possible techniques

• Activities directly and only related to time• No activity definition and activity resource estimation

• No direct definition of inputs/outputs

→ No direct link between processes

• Much higher abstraction level

→ Better scalability, “at owner's risk“

• No misleading security

13Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 14: Microsoft PowerPoint - Project time management according to

PMBOK® – Time Management – Tools & Techniques

• Expert� Visualized schedule activities and logical connections

• Activity List� Updated Activity List after possible change requests

• Activity Attributes� Updated with leads and lags, containing logical connections

• Milestone List•Updated with leads and lags, containing logical connections

• Change Request•Updated with leads and lags, containing logical connections

14Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 15: Microsoft PowerPoint - Project time management according to

PMBOK® – Time Management - Specialities

• Rolling Wave Planning•Decomposition of WBS abstraction level on time

• Templates•Activity Lists for former projects

• Crashing• Higher costs, higher compression of the schedule

• Fast tracking• Increase on costs, compression of the schedule

15Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 16: Microsoft PowerPoint - Project time management according to

PMBOK® - Activity Sequencing - Inputs

• Project Scope Statement•Common description of deliverables for team and stakeholders

• Activity List•Decomposed WBS

• Activity Attributes•Resource requirements, logical relationships, activity identifiers

• Milestone List•Schedule control points, sub-deliverables of the project

• Approved Change Request•New requirements to project scope

16Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 17: Microsoft PowerPoint - Project time management according to

PMBOK® - Activity Sequencing - Outputs

• Project Schedule Network Diagrams� Visualized schedule activities and logical connections

• Activity List� Updated Activity List after possible change requests

• Activity Attributes� Updated with leads and lags, containing logical connections

• Milestone List•Updated with leads and lags, containing logical connections

• Change Request•Updated with leads and lags, containing logical connections

17Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 18: Microsoft PowerPoint - Project time management according to

PMBOK® - Activity Sequencing - Tools & Techniques

• Schedule Network Templates� Used to accelerate the preparation of networks of project

schedule activities

• Dependency Determination� Mandatory dependencies

� Discretionary dependencies

� External dependencies

• Applying Leads and Lags� Leads – acceleration of the successor activity

� Lags – delay in the successor activity

•Expert Judgment• Also called Lessons learned by other methods

18Project Time Management - Henrique Faria, Christoph Szczecina © 2008

Page 19: Microsoft PowerPoint - Project time management according to

PMBOK® - Activity Sequencing – Tools & Techniques

Project Time Management - Henrique Faria, Christoph Szczecina © 2008

• Critical Chain Method

� Modify the project schedule

� Focuses on managing the buffer activity duration

� Focuses on managing the resources applied to planned

schedule activities

� Deterministic and probabilistic approaches

� Add buffers to critical milestones

Page 20: Microsoft PowerPoint - Project time management according to

PMBOK® - Activity Sequencing – Tools & Techniques

20Project Time Management - Henrique Faria, Christoph Szczecina © 2008

ACTIVITY1

ACTIVITY2

CONSTRAINT

ACTIVITY1

ACTIVITY2

CONSTRAINT

ACTIVITY1

ACTIVITY2

CONSTRAINT

ACTIVITY1

ACTIVITY2

CONSTRAINT

ACTIVITY1

ACTIVITY2

FINISH

START

FINISH

FINISH

START

START

50%

20%

(A) FINISH-TO-START

(B) START-TO-START

(C) FINISH-TO-FINISH

(D) START-TO-FINISH

(E) PERCENT COMPLETE

ActivityActivityActivityActivity----OnOnOnOn----Node (AON) or Node (AON) or Node (AON) or Node (AON) or Precedence Diagramming Precedence Diagramming Precedence Diagramming Precedence Diagramming Method (PDM)Method (PDM)Method (PDM)Method (PDM)

� Scheduling activities

� Between milestones

� Start before the former ends

� Consist of five types:

•finish-to-start

•start-to-start

•finish-to-finish

•start-to-finish

•percent complete

Page 21: Microsoft PowerPoint - Project time management according to

PMBOK® - Activity Sequencing – Tools & Techniques

Activity-On-Arrow (AOA)

• PERT • Finish-to-start• Three scenarios• Use dummies

Project Time Management - Henrique Faria, Christoph Szczecina © 2008

• ADM or CPM• Finish-to-start• One scenario• Use dummies

Page 22: Microsoft PowerPoint - Project time management according to

Thank YouThank YouThank YouThank Youfor your attention..

Questions Left ??