Upload
srikanth-chandra
View
486
Download
2
Embed Size (px)
Citation preview
PLM - PPR PROCESS
PRODUCTION PART APPROVAL PROCESS PRODUCTION PART APPROVAL PROCESS
TRAININGTRAINING
It is designed to provide comprehensive knowledge to
the participants on understanding the requirements of
PPAP Manual & Implementation Guideline.
.
INTRODUCTIONINTRODUCTION
•• PurposePurpose is tois to ensure that all customer Engg. ensure that all customer Engg.
requirements are understood, and to demonstrate requirements are understood, and to demonstrate
the capability of supplier to meet the requirements, the capability of supplier to meet the requirements,
initially & during actual production run at quoted initially & during actual production run at quoted
production rate.production rate.
•• To validate that the products made from production To validate that the products made from production
tools and processes meet the Engg. Requirementstools and processes meet the Engg. Requirements
PURPOSEPURPOSE
APQP INTRODUCTIONAPQP INTRODUCTION
Expansion of APQP is Advanced Product Quality Planning
A structured method of defining and establishing the steps
necessary to ensure that a product satisfies the customer.
Originator of APQP- AIAG
(Automotive Industry Action Group
of Engineers from 3 Giants)
BENEFITS OF APQP
Changes required are identified early
Changes after production launch are avoided
Quality product is provided on-time at the lowest cost
APQP INTRODUCTIONAPQP INTRODUCTION
4 PHASES OF APQP
1. Plan and Define the program
2. Product Design and Development
3. Process Design and Development
4. Production Part Approval Process (PPAP)
* There are 19 requirements for PPAP
* PPAP Submission in 5 Levels
APQP INTRODUCTIONAPQP INTRODUCTION
5 Levels of PPAP
Level -1 Warrant Only
Level -2 Warrant, Product Samples, Limited Data
Level- 3 Warrant, Product Samples, Complete data submitted
Level -4 Warrant, Other requirements as defined by the Customer. All other PPAP Documents)
Level -5 Warrant, Product samples, Complete Data reviewed at
Supplier End.
PPAP REQUIREMENTS
1. Design Records of Saleable Product
- for proprietary components / details
- for all other components / details
2. Engineering Change Documents, if any
3. Customer Engineering Approval, if required
4. Design FMEA
5. Process Flow Diagrams
6. Process FMEA
7. Control Plan
8. Material / Performance Test Results
9. Dimensional Results
10. Initial Process Study
11. Measurement System Analysis Studies
12. Qualified Laboratory Documentation
13. Part Submission Warrant (PSW)
14. Appearance Approval Report (AAR), if applicable
15. Bulk Material Requirements Checklist (for bulk material
PPAP only)
16. Sample Product
17. Master Sample
18. Checking Aids
19. Records of Compliance with Customer Specific
requirements
R*SRRDesign FMEA4
R*SRRCustomer Engineering Approval, if reqd3
R*SSREngineering Change Documents, if any2
R*SSRfor all other components / details1.2
R*RRRfor proprietary components / details1.1
R*SSRDesign Records of Saleable Product1
54321
Submission LevelRequirementsSl.No
PPAP SUBMISSION LEVELS
R*SSSAppearance Approval Report (AAR), if
applicable
14
RSSSSPart Submission Warrant (PSW)13
R*SRRQualified Laboratory Documentation12
R*SSRMeasurement System Analysis Studies11
R*SRRInitial Process Study10
R*SRRDimensional Results9
R*SSRMaterial, Performance, Test Results8
R*SSRControl Plan7
R*SRRProcess FMEA6
R*SRRProcess Flow Diagrams5
Submission LevelRequirementsSl.No
R*SRRRecords of Compliance with Customer
Specific requirements
19
R*SRRChecking Aids18
R*RRRMaster Sample 17
R*RSRSample Product16
R*RRRBulk Material Requirements Checklist
(for bulk material PPAP only)
15
Submission LevelRequirementsSl.No.
• S – The supplier shall submit to designated customer product approval activity and retain a copy of records or documentation items at appropriate locations, including manufacturing
• R – The supplier shall retain at appropriate locations, including manufacturing, and make readily available to the customer representative upon request
• * - The supplier shall retain at appropriate locations, and submit to customer upon request
• Level 3 as default level
• For Bulk materials, Level 1 as default level
• This is carried out as per APQP timing plan
- Any one or more of the following as appropriate shall satisfy the
intent
• Min. Of 1 hr to 1 shift production with specific production
quantity to a total of min.300 consecutive parts
• Quantity specified by customer quality representative
• Produced from production site using tooling, gauging, process ,
material, operators from the production environment
• Parts from unique tools, lines, cavity, mould, pattern are
measured and representative parts tested
SIGNIFICANT PRODUCTION RUNSIGNIFICANT PRODUCTION RUN
• Part drawings, specifications, CAD data or any
documents referenced
• If it is electronic format, hard copy to identify
measurements taken
• for bulk materials
- Raw material identification
- Formulations
- Processing steps & parameters
- Final product specifications & acceptance criteria
1. DESIGN RECORDS
• Authorized change documents provided by customer
incorporated in the part not incorporated in the drawing
3. ENGINEERING APPROVAL
• As required by design record
• For bulk materials, signature of customer on bulk material
approval check list or inclusion of supplier’s name in
customer list of approved materials
2. ANY AUTHORISED ENGG. CHANGE DOCUMENT
Applicable to design responsible suppliers
for bulk materials, Design Matrix & Design FMEA are
prepared as required by bulk material requirements
checklist
for bulk materials, Design FMEA ratings for SEV, OCC,
DET specified in PPAP manual can be used
4. DESIGN FMEA
Purpose of Process Flow Diagram
To understand all the processes involved from the Incoming stage to
the final product despatch.
BENEFITS
1) Can able to see at once all the processes
2) Allows each operation to questioned
3) Exposes source variations
4) Highlights Non Value Added activities involved in the process
5. PROCESS FLOW DIAGRAM
Inputs for Process Flow Diagram
1) Customer Drawings
2) In-process Drawings
3) Plant Layout
4) Design FMEA outputs
5) FMEA for Similar Products
PFD
How to prepare the PFD
1) Operation sequences
2) What is the output of each process/operation
3) What are the Input characters which affect the output of the
process/operation
4) What are the Process characters which affect the output of the
process/operation
5) What is the symbols to be used for Process Flow Diagram
PFD
1st 2nd3rd 4th5th
PFD
OPERATI0N No & DESCRIPTION
Following guide line shall be followed to provide the Operation nos for the processes.
Category Operation Nos.
1 One Machine-One operation OP 10, OP 20,
OP 30…
2
One Machine- Multi Operations in this
Component cannot be checked stage wise by
Manually or automatically till the operation
Completed.
OP 10, OP 20, OP 30..
3
One Machine-Multi Operations in this
Component can be checked stage wise by
Manually or automatically.
OP 10, OP 10A,
OP 10B, OP 10C,…,
OP 20, OP 30,…
PFD
Incoming Source Variations (ISV)
This could be due to
Raw Material:
If it is due to Raw Material Variation Check the Supplier FMEA, Process
Flow, etc.
Any Previous Operation’s out comes:
If it is due to any Previous operations, clearly specify the operation/machine
from where this Variation occurred.
PFD
Product Characteristics/Desired OutcomeThese are the characters which to be obtained from the particular operation.
This Desired outcome shall be one or more of the Below mentioned.
a) Blue Print (BP)a) Dimensions
b) Engineering Specification (ES)
a) Test procedures b) Reliable checks c) Material specification
c) In process Characteristics (IP)
a) Rough turn ID
d) Process Characteristics (PC)
a) Temperature b) Time c) Pressure d) Speed
e) Functional characteristics (FC)
a) Visual b) Operational c) Fit d) Assembly guidelines
f) Regulatory
a) Safety b) Noise c) Environmental d) Emissions
PFD
Process Characteristics
These are also the Characters which affects the Desired outcome
during the particular operation.
These can be from one or more of the below Mentioned
a) Man
b) Machine
c) Method
d) Process Materials
e) Environment
PFD
Process Flow Diagram identifies
a) Where the inspection is carried out
b) Where the Operator involvement is required
c) Where the Delay is occurred during the process
This process flow Diagram (with the symbols) indicates,Where ever the Non Value added
actives are there in the process
Transportation
Operation or
Machine
Operation with self /Auto inspection
Inspection
Storage
Operation with Multiple Product
streams inspection
Delay
Decision
Primary Path
Alternate Path
Operator
Partial operator
--------------
PFD
1.Casting Variation 1) Reference Dimension - BP 1.Tool Wear 2.Material Hardness Variation 2) Seal Bore Diameter - BP 2.Speed & Feed
3) Seal Bore Surface Finish - BP 3.Operator Skill 4) Seal Face Depth - BP 4. Machine Repeatability 5) Seal Face Chamfer - BP
6) Seal face Surface Finish - BP
7) Seal Face Perpendicularity wrt Seal Bore -BP
8) Spigot Diameter - BP
9) Spigot Diameter Chamfer - BP
10)Spigot Diameter Surface Finish - BP
11) Spigot Face to MTG Face Depth - BP
12) Spigot Diameter Position - BP
13) Mtg Face Perpendicularity wrt Seal Bore - BP
14) Mtg Face Surface Finish - BP
15) Groove Diameter - BP
16) Groove Diameter Position - BP
17) Groove Diameter Suface Finish - BP
18) Groove Depth - BP
19) Chamfer - BP
20) Radius - BP
1.Seal Bore Variation 1) Bearing Bore - BP
2) Bearing Bore Chamfer - BP 1.Tool Wear
3) Bearing Bore Concentricity wrt Seal Bore - BP 2.Speed & Feed
4) Bearing Bore Surface Finish - BP 3.Operator Skill 5) Total Height - BP 4. Machine Repeatability 6) Bearing Face Surface Finish - BP
Bearing Bore
Process
Characteristics
Incoming Source of
VariationPFD
Product Characteristics /
Desired Outcome
OP 10 Seal Bore
Operation
Number
Operation
Description
OP 20
PFD
WHY FMEA
Tool for 6 Sigma
Catch the cause before the problem occurs
Prevent the failure
Easy understanding of Process
Reducing the cost of poor quality
Customer Satification
Optimize the controls
6. Process Failure Mode Effective Analysis
Process Flow of PFMEA
PFMEA
PFMEA
Example
Process function / description
- Machining of outer diameter
� Specify the description and
Function of the process
Potential
Failure
Mode
RequirementsProcess Step
/ Function
PFMEA
Example
Outer diameter, run-out, free from tool
mark
� List out Outputs of the Process
Potential
Effect(s)
of Failure
Potential
Failure
ModeRequirements
PFMEA
Example
Bent, Diameter oversize, Diameter undersize, Cracked,
Deformed, Open Circuited, Burred
Two Assumptions are
1. Consider all inputs are acceptable
2. Consider the Design is acceptable
� List the failure modes those are possible to occur
against the requirements specified in the previous
column.
� Apart from Engg. Specification, what would a
customer consider objectionable
1) No Function, 2) Partial / Over,
3) Degraded Function (after sometime failure),
4) Intermittent, 5)Un Intended Function.
SevPotential Effect(s)
of FailurePotential Failure Mode
PFMEA
Example
Cannot locate, Cannot face, Does not fit, Does not match Scrap,
re-work, Vehicle / item inoperable, Loss of primary function,
Customer dissatisfaction
� List the effects of failure in
1) Next operation,
2) Subsequent operations / Down Stream,
3) Operator Safety,
4) Machine / Equipment,
5) Customer / End User,
6) Vehicle,
7) Govt Regulation.
� For each failure mode, more than one effect can be listed
ClassSevPotential Effect(s) of Failure
PFMEA
� Assess the seriousness of the effect in a 1-10 scale
� This rating applies to EFFECT only
(i.e. previous column)
� Consider the Design FMEA
� Consult subsequent Mfg./ Assembly plant
� Safety related effects should be rated in Nos.9 or 10
� While giving ranking consider only the required
criteria (i.e. next opn. / vehicle)
Potential Cause(s)
/ Mechanism
(s) of Failure
ClassSeverity
PFMEA
Hazardous without warning
Very high severity ranking when a potential failure mode affects safe vehicle operation and/or involves noncompliance with government regulation without warning
May endanger operator (machine or assembly) without warning
10
Hazardous
without warning
Very high severity ranking when a potential failure mode
affects safe vehicle operation and/or involves noncompliance with government regulation without warning
May endanger operator (machine or assembly) without warning
9
Very High Vehicle/item inoperable (loss of primary function) 100% of product may have to be scrapped, or vehicle/item
repaired in repair department with a repair time greater than one hour.
8
High Vehicle/ item operable but at a reduced level of performance. Customer very dissatisfied.
product may have to be sorted and a portion (less than
100%) scrapped, or vehicle/item repaired in repair
department with a repair time between a half-hour and an hour.
7
Moderate Vehicle/ item operable but Comfort/Convenience item(s) inoperable.Customer dissatisfied.
A portion (less than 100%) of the product may have to scrapped with no sorting, or vehicle/item repaired in repair department with a repair time less than a half-hour.
6
Low Vehicle/Item operable but Comfort/Convenience item(s) operable at a reduced level of performance.
100% of product may have to be reworked, or vehicle/item repaired off-line but does not go to repair department.
5
Very Low Fit and Finish/Squeak and Rattle item does not conform. Defect noticed by most customers (greater than75%)
The product may have to be sorted, with no scrap, and a portion (less than 100%) reworked.
4
Minor Fit and Finish/Squeak and Rattle item does conform. Defect noticed by 50% of customers.
A portion (less than 100%) of the product may have to be reworked, with no scrap, on-line but out-of-station.
3
Very Minor Fit and Finish/Squeak and Rattle item does not conform.. Defect noticed by discriminating customers (less than 25%)
A portion (less than 100%)0f the product may have to be reworked, with no scrap, on-line but in-station.
2
None No discernible effect. Slight inconvenience to operation or operator, or no effect. 1
Effect Severity of Effect on Product
(Customer Effect)
Severity of Effect on Process
(MFG/ASSY Effect)
Rank
Severity Ranking PFMEA
� Classify special process
characteristics (e.g. critical, key,
major)
Current
Process
Control
prevention
Potential
Cause(s) /
Mechanis
m (s) of
Failure
Classification
PFMEA
� List the first level potential causes such as
man, machine, tool, process parameter, fixture etc.
� List the root causes under the first level causes
using WHY? WHY? analysis
� Describe the causes in such a way that can be
eliminated or controlled
� Don’t use statements such as operator mal-
functioning, fixture problem etc.
� Use the cause and effect diagram, if required
� consider input materials in last iteration of cause
analysis
Continued……
Occur
Current Process
Control
prevention
Potential Cause(s) / Mechanism (s) of
Failure
PFMEA
Example
Under Man
Fails to clean, Fails to assemble, Fails to tight, Mis-
locate
Under machine
inadequate lubrication, excessive vibration, excessive
spindle run-out
Under process
improper time / temperature, inadequate gating / venting
Under design
Symmetric design, Difficult to assemble
Under Raw Material,
Mixed material, New source, Alternate material,
Excessive hardness
Occur
Current Process
Control
preventionPotential Cause(s) / Mechanism (s) of Failure
PFMEA
•List the existing controls, which can detect the causes or failure mode
Type Examples Prevention of causes Mistake proofing,
Check Sheet,
SPC chart,
On-line monitoring
Auto-control of temperature,
Current
Process
Control
Prevention
OccurCurrent Process Control prevention
PFMEA
� Estimate the probability of occurrence on a 1-10 scale
� Rate against each causes
� Use existing or past data as a basis rejection data for ranking
� Document the basis of occurrence ranking
� For a new processes, if there is no previous experience, use team judgement
Don’t consider failure detecting measures while giving ranking (100%
inspection)
GUIDELINES FOR OCCURRENCE NUMBER
1) Occurrence number is to be calculated for causes based upon actual data
2) If data is not there related to cause, calculated the occurrence no. of the failure mode data and same occurance number has to be transferred to the causes using engineering judgement
3) If you don’t have data related failure mode & causes, calculate occurrence number based on the Cpk Value
4) If the above 3 is not available, use the occurrence number from similar product
5) None of these are available, use the “GUT FEEL
Current
Process
Control
Prevention
Occurrence
PFMEA
Occurrence of Cause - Ranking
Probability Likely failure Rates Ranking
Very High:Persistent
Failures
> 100 per thousand pieces
>100000 PPM
10
50 per thousand pieces
50000 PPM
9
High: Frequent Failure 20 per thousand pieces
20000 PPM
8
10 per thousand pieces
10000 PPM
7
Moderate: Occasional Failures 5 per thousand pieces
5000 PPM
6
2 per thousand pieces
2000 PPM
5
1 per thousand pieces
1000 PPM
4
Low: Relatively Few Failures 0.5 per thousand pieces
500 PPM
3
0.1 per thousand pieces
100 PPM
2
Remote: Failure is Unlikely < 0.01 per thousand pieces
10 PPM
1
PFMEA
ϖAssess the probability of controls listed in the
previous column, which will detect the cause or
failure mode
ϖWhile giving ranking, assume the failure is
occurred
ϖDon’t assume ranking is low because the
occurrence is low
ϖRandom controls should not influence detection
ranking
ϖOne detection ranking can be assigned to multiple
controls
ϖWhile listing, specify the frequency of detection
measures
RP/NDetectCurrent Process Control Detection
PFMEA
Detection Crieteria Inspection types Suggested Range of Detection Methods Ranking
1 2 3
Almost
Impossible
Absolute certainty of non-
detection x
Cannot detect or is not checked 10
Very Remote Controls will
Probably not detect x
Control is achieved with indirect or random
checks only
9
Remote Controls have poor chance of
detection x
Control is achieved with visual inspection
only
8
Very low Control have poor chance of
detection x
Control is achieved with double visual
inspection only
7
Low Controls may detect x x Control is achieved with charting
method,such as SPC (Statistical Process Control)
6
Moderate Controls may detect x Control is based on variable gauging after
parts have left the station, or Go/No Go
gauging performed on 100% of the parts after parts have left the station.
5
Moderately High Controls have a good chance to detect. x x
Error detection in subsequent operations, or gauging performed on setup and first-piece
check(for setup cause only)
4
High Controls have a good chance
to detect. x x
Error detection in-station,or error detection in
subsequent operation by multiple layers of
acceptance: supply, select, install, verify.Cannot accept discrepant part.
3
Very High Controls almost certain to detect. x x
Error detection in-station (automatic gauging with automatic stop feature). Cannot pass
discrepant part.
2
Very High Controls certain to detect.
x
Discrepant parts cannot be made because
item has been error proofed by process/product design.
1
Detection - Ranking
Inspection Types: 1-Error-proof, 2-Gauging, 3-Manual Inspection
PFMEA
� Risk Priority Number is the
multiplication of S O D
severity x occurrence x Detection.
� While calculating RPN,
First consider only highest severity
rating of each failure mode
Alternatively (Different Scenarios)
S O - severity x occurrence
S D - severity x Detection
Responsibility &
Target
Completion
Date
Recommended
ActionRPN
PFMEA
�Policy for RPN to take action
-define a target RPN and anything above that can be
considered for action. Ex. It can be 50. Considering 95%
of the failures are attended
-consider only high priority no. for take action and
review periodically
�As a first priority, take action on causes to reduce
occurrence ranking
�The next priority is to consider action on controls to
reduce detection ranking
�severity ranking can be reduced by
-elimination of failure mode by change in processes or
design
Action
Results
Responsibilit
y
& Target
Completion
DateRecommended Action
PFMEA
�Specify the responsibility and target
completion date for every actions identified
�During APQP, the FMEA completion dates
should be prior to production run
RPN
D
e
t
Oc
cSev
Actions
Taken
Responsibility & Target
Completion Date
PFMEA
�Describe the verification results
�Where effectiveness measure is required,
specify the target date accordingly
�After the assessment of the actions taken, re-
assess the values of severity, occurrence,
detection and RPN
RPNDetOccSevActions Taken
Action Results
PFMEA
Opn No.Operation
Description
Potential
Failure modePotential Effect
Sev.
NoClass Potential Cause
Occur.
No.
Current
Process
Control Prev.
Current
Proces
Control Det.
Dectection
No.RPN
Recommended
ActionsS O D RPN
OP 20 Bearing BoreBearing
Bore Dia u/s
8 SC 3 Inprocess
Inspection
4 96
Next Process
NilHardness out of
spec.3
Receiving
Inspection4 96
Assy
Tight Fit 5 un skilled operator 3Work
instruction 96
Customer
Bearing Failure 7 M/c not repeatable 2 P.M 64
Field
Engine Failure 8 Insert wear 2
Operator
self 64
Inspection
Bearing
Bore Dia o/s
8 SC 3 Inprocess
Inspection
4 96
Next Processun skilled operator 3
Work
instruction 96
Nil 6
Assy M/c not repeatable 2 P.M 64
Loose fit
Customer 7
Bearing play
Field 7 Improper feed & 2 C.P 64
Pump poor
performance 7
PFMEA
Follow up actions The Process - responsible engineer is responsible for ensuring that all actions
recommended have been implemented or adequately addressed .
FMEA is a living document and should always reflect the latest design level as
well as the latest relevant actions.
The Process responsible engineer has several means of ensuring that concerns
are identified and that recommended actions are implemented . they includes but
not limited to followings :
1) Ensuring design requirements are achieved
2) Reviewing engineering drawings & specifications
3) Conforming incorporation in assembly / manufacturing documentation &
4) Reviewing process FMEA & Control plans
PFMEA
What is Control Plan
Is a written summary of the system for controlling the variation
of all product and process characteristics, important quality and
engineering requirements
Is a contract between the supplier and the customer
Is used as the basis for development of process work instruction
Identifies all customer and supplier specified special
characteristics.
7. Control Plan
Control Plan
CONTROL PLAN COLUMN DESCRIPTIONS
1 Header information Enter the header information as required.
2 Part/Process NumberThis item number is usually referenced from the Process Flow Chart. If multiple part numbers exist
(assembly), list the individual part numbers and their processes accordingly.
3Process Name/
Operation Description
All steps in the manufacturing of a component are described in a process flow diagram. Identify the
process/operation name from the flow diagram that best describes the activity being addressed.
4Machine, Device, Jig,
Tools for ManufacturingFor each operation that is described, name the processing equipment as appropriate.
5 NumberEnter a cross reference number from all applicable documents such as, but not limited to, process flow
diagram, numbered blue print, FMEAs, and sketches (computer generated or otherwise), if required.
6 Product
Product Characteristics are the features or properties of a part, component or assembly that are described on
drawings or other primary engineering information. The Core Team should identify the Special Product
Characteristics that are a compilation of im
7 Process
Process Characteristics are the process variable (input variables) that have a cause and effect relationship
with the identified Product Characteristic. A Process Characteristic can only be measured at the time it
occurs. The Core Team should identify Pro
Control Plan
CONTROL PLAN COLUMN DESCRIPTIONS
8Special Characteristic
Classification
Use the appropriate classification to designate the type of special characteristic or this field can be left blank
for other undesignated characteristics. Please refer to the Danaher Motion Quality Manual to see the
descriptive terms and symbols.
9Product/ Process/
Specification/ ToleranceSpecification/tolerance may be obtained from the engineering documents.
10Evaluation/
Measurement Technique
This columns identifies the measurement system being used. This could include gages, fixtures, tools, and/or
test equipment required to measure the part/process/manufacturing equipment. An analysis of the
reproducibility, repeatability and accuracy of the
11 Sample Size/Frequency When sampling is required list the corresponding sample size and frequency.
12 Control Method
This column contains a brief description of how the operation will be controlled, including procedure numbers
where applicable. The control method utilized should be based on effective analysis of the process. The
control method is determined by the type
13 Reaction Plan
The reaction plan specifies the corrective actions necessary to avoid producing nonconforming products or
operating out of control. The actions should normally be the responsibility of the people closest to the
process, the operator, jobsetter, or supervi
Control Plan
CONTROL PLAN COLUMN DESCRIPTIONS Control Plan
CONTROL PLAN COLUMN DESCRIPTIONS Control Plan
• Compliance to design record / control plan
• Record of qty. tested on each tests
• Engg. Change level or authorized engg. Change
• Date of testing
• Material sub contractor’s name and their code (from
customer approved List)
8. MATERIAL / PERFORMANCE TEST RESULTS
• Compliance to control plan & Design Record and all
characteristics (except ref. Dimensions)
• Dimensional results for each production lines, each
cavities, molds, patterns, dies
• Indicate design record, change level, authorized engg.
Change document ref. On all reports
• Identify master sample which is measured
• Tracing is required when optical comparator is required
• Appendix C can be used
9. DIMENSIONAL RESULTS
• Prior to submission, acceptable level of initial process
capability or performance shall be determined with
customer
• MSA prior to initial process studies
• For special Characteristics of variable data
• Cpk or Ppk can be as per customer agreement
• Control charts are preferred, if X bar – R charts used, Min.
25 sub groups, min 100 nos. from significant production
run.
10. INITIAL PROCESS STUDIES
• Use Cpk or Ppk
• Where historical Cpk data is available for similar parts of same
process, Cpk can be captured
• For chronically unstable processes (within specification) use
Ppk
• For bulk material, customer agreement on usage of
techniques
• Index value > 1.67, Else CA plan is reqd.
• For Unstable processes, notify customer & submit CA plan
• One sided specification or non normal data
• E.g. F/O, R/O, concentricity, twist, effort, surface finish,
uniformity, etc.,
10.1 QUALITY INDICES
�Alternate method of calculation & acceptance criteria with
customer agreement
�For bulk materials, if Ppk/Cpk is not achieved 100%
inspection of a sample (s) from a continuous process or
homogeneous batch, which represents online production run.
Part Variation Measurement system Variation
Why MSA ?Why MSA ?
11. MEASUREMENT SYSTEMS ANALYSIS STUDIES
Measurement system analysis (MSA) is an experimental
and mathematical method of determining how much
variation within the measurement process
contributes to overall process variability.
11. MEASUREMENT SYSTEMS ANALYSIS STUDIES
• if in house laboratory is only used for testing / calibration
- Add laboratory scope
• If outside laboratory is used for testing / calibration
• Add NABL certificate or equivalent of that laboratory
• Add scope of accreditation of that lab
12. QUALIFIED LABORATORY
DOCUMENTATION
13. PART SUBMISSION WARRANT
� Separate PSW for each part no.
� Identify Mould / cavity / line no. in PSW
� Part weight shall be rounded off to four decimals derived out
of 10 randomly selected parts
� 10 parts represent all moulds, cavities, lines as appropriate
14. APPEARANCE APPROVAL REPORT
• As required in Design Record
15 . BULK MATERIAL REQUIREMENT
CHECKLIST (Appendix F)
• Jointly agreed by customer during early stage of APQP
• Completion of all agreed activities
16. SAMPLE PRODUCTION PARTS
• As per customer request
17. MASTER SAMPLE
• Retain till new master sample is produced or as per design record
requirement for inspection criteria
• For each position of a multiple cavity, die, tool, mould or pattern, line.
• Retention period can be waived or modified by customer
18. CHECKING AIDS
• Inspection Fixtures, gages, models, templates, etc. specific to the part
• If more than one , prepare & refer the list in PSW including its change
level
• Submit if required by customer
• Certification of checking aid w.r.t part dimensions
• Demonstration of engg. Change in gauge change
• Appropriate MSA studies
19. CUSTOMER SPECIFIC REQUIREMENTS
• compliance records to all specific requirements of customer (Sec. II)
SITUATIONS WHEN PPAP VALIDAITON
& SUBMISSION REQUIRED
• SITUATIONS WHERE SUBMISSION TO CUSTOMER IS
REQUIRED ( Unless waived by customer)
For bulk materials, Process technology new to the supplier, not previously
used for this product4
Engg. Change to design records, specifications, or materials 3
Correction of a discrepancy on a previously submitted part2
A new part or product1
RequirementsSl.
No
• SITUATIONS WHERE NOTIFICATION & SUBMISSION TO
CUSTOMER IS REQUIRED
Production from tooling and equipment transferred to a different plant location or
from an additional plant location
4
Production following refurbishment or rearrangement of existing tooling or
equipment
3
Production from new ort modified tools (Except perishable tools)2
Use of other construction or material than was used in the previously approved part
or product
1
RequirementsSl.
No.
Change in test / inspection method – new technique 8
Product and process changes related to components of the production
manufactured internally or manufactured by s/c
7
Product produced after the tooling has been inactive for volume production
for twelve months or more
6
Change of subcontractor for parts, non-equivalent materials, or services (e.g.
Heat – treating, plating) that affects customer fit, form, function,
durability or performance requirements.
5
RequirementsSl.
No
For bulk materials,
- new source of raw material with spl. Characteristics from new or
existing s/c
- change in production appearance attributes where there is no
appearance specifications
- Revised parameters in the same process
- Change outside of DFMEA of the approved product
9
RequirementsSl.
No
5.2 SITUATIONS WHERE CUSTOMER NOTIFICATION IS NOT
REQUIRED (Track changes & Update any PPAP documents)
Identical gage replacement4
Changes in equipment3
Tool / Equipment movement within the same plant2
Changes to component level drawings1
RequirementsSl.
No
For bulk materials,
- changes within the DFMEA of the approved product
- Changes within PFMEA
- Changes which do not affect the spl. Characteristics
- Changes in approved commodity ingredients
- Change in s/c producing location of a R/M that has no spl. char.
- New sources of R/M that has no spl. Char.
- Tightening of customer/sales acceptance tol. Limits
7
Changes resulting in reduced RPN or PFMEA (with no changes in process
flow)
6
Rebalance of operator job content with no change in process flow5
RequirementsSl.
No