Microsoft Office Project - PEBBLE PARK

Embed Size (px)

Citation preview

  • 7/28/2019 Microsoft Office Project - PEBBLE PARK

    1/2

    ID Task Name Predecessors Duration

    1 PROJECT "PEBBLE PARK" 95 days?

    2 General works 35 days?

    3 Obtain building permits 30 days?

    4 Install temporary power 3SS 2 days?

    5 Install temporary water se 3SS 2 days?

    6 Set up site office 8 2 days?

    7 Prepare site - lay down ya 3SS 2 days?

    8 Clear the site 3 3 days?

    9 Lineout 8 2 days?

    10 Substructure 30 days?

    11 Foundations 15 days?

    12 Excavations of found9 7 days?

    13 Excavations of elevat12SS 1 day?

    14 P.C.C. for all footings 12,13 2 days?

    15 Reinforcement Cuttin 12SS 7 days?

    16 Formwork for footing 14 3 days?

    17 Prepare and pour co 15,16 3 days?

    18 Basement (RCC) 15 days?

    19 Casting of columns u 17 12 days?

    20 Casting of lift wall upt19SS+2 days 5 days?

    21 Casting of staircase u19SS+2 days 7 days?22 Shuttering work for sl 19SS+7 days 7 days?

    23 Slab casting 19,20,21,22 1 day?

    24 Superstructure 30 days?

    25 Ground Floor (RCC) 15 days?

    26 Casting of columns u 23 12 days?

    27 Casting of lift wall upt26SS+2 days 5 days?

    28 Casting of staircase u26SS+2 days 7 days?

    29 Shuttering work for sl 26SS+7 days 7 days?

    30 Slab casting 26,27,28,29 1 day?

    31 First Floor (RCC) 15 days?

    32 Casting of columns u 30 12 days?

    33 Casting of lift wall upt32SS+2 days 5 days?

    34 Casting of staircase u32SS+2 days 7 days?

    3 Obtain building permits30 days?

    4 Install temporary power

    5 Install temporary water service

    6 Set up site off ice

    7 Prepare site - lay down yard and temporary fencing

    8 Clear the site

    9 Lineout

    12 Excavations of f oundations7 da

    13 Excavations of elevator pit

    14 P.C.C. for all footings

    15 Reinforcement Cutting works for footings and columns7 da

    16 Formwork for footings

    17 Prepare and pour concrete for basement floor

    19 Casting of columns upto l intel level upto l intel level12 days?

    20 Casting of lift wall upto lintel level5

    21 Casting of staircase upto mid landingl7 d22 Shuttering work for slab7 da

    23 Slab cast ing

    26 Cast ing of columns upto l intel level upto l intel l12 days

    27 Casting of lift wall upto lintel level5 d

    28 Casting of staircase upto mid landingl7 da

    29 Shuttering work for slab7 d

    30 Slab casting

    32 Casting of columns upto lintel level12 day

    33 Casting of lif t wall upto lintel level5

    34 Casting of staircase upto mid landingl7 d

    15

    22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11May '14 Jun '14 Jul '14 Aug '14 Sep '14 Oct '14 Nov '14

    Task

    Critical Task

    Progress

    Milestone

    Summary

    Rolled Up Task

    Rolled Up Critical Task

    Rolled Up Milestone

    Rolled Up Progress

    Split

    External Tasks

    Project Summary

    Group By Summary

    Deadline

    Page 1

    Project: PEBBLE PARK.mppDate: Wed 10-04-13

  • 7/28/2019 Microsoft Office Project - PEBBLE PARK

    2/2

    ID Task Name Predecessors Duration

    35 Shuttering work for sl 32SS+7 days 7 days?

    36 Slab casting 32,33,34,35 1 day?

    35 Shuttering work for slab7 d

    36 Slab casting

    15

    22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11May '14 Jun '14 Jul '14 Aug '14 Sep '14 Oct '14 Nov '14

    Task

    Critical Task

    Progress

    Milestone

    Summary

    Rolled Up Task

    Rolled Up Critical Task

    Rolled Up Milestone

    Rolled Up Progress

    Split

    External Tasks

    Project Summary

    Group By Summary

    Deadline

    Page 2

    Project: PEBBLE PARK.mppDate: Wed 10-04-13