Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Opening the Southern Gas Corridor
EU Energy Policy in Transition Brussels, 16 April 2013
Michael Hoffmann, External Affairs Director
15.04.2013 TAP's Corporate Presentation
Southern Gas Corridor Projects
Diversity and security of energy supply for Europe
• The EU’s initiative to enhance Europe’s energy security by connecting to new
sources of natural gas in the Caspian Sea
• Two pipeline projects pre-selected by Shah Deniz Consortium
• 10 bcm/a initially available from Shah Deniz will be able to supply 7 million
households in South Eastern and Western Europe
What is Involved?
3
Total investment of approx. USD 45 billion
1. Drilling of wells
2. Offshore production
3. Onshore procession Sangachal Terminal
4. SCP
5. TANAP
6. TAP
7. Expansion of Italian network (SRG)
8. Further transport to western Europe
and the Balkans
SDC Schedule
Experts doing things the right way, at the right time
1. Submission of RFP to Shah Deniz Consortium (SDC) 1 Oct 2011
2. Selection of Southern and Northern export options (Feb & June 2012 )
3. Decision Support Package to SDC – end of March 2013
4. Shah Deniz final decision on export route in June 2013
5. SDC members to take up equity option one month after selection
6. TAP to take Resolution to Construct (RTC) in Sept 2013
7. Shah Deniz Final Investment Decision (FID) in Oct 2013
8. Construction of TAP to start early 2015
9. Ready to receive first gas from Shah Deniz 2019
TAP submits final transportation bid on 28th March 2013
Shah Deniz Requirements
Commerciality
Project Deliverability
Financial Deliverability
Engineering Design
Excellent cooperation between TAP and Shah Deniz
March 2013
TAP submitted Decision Support Package (gas transportation bid) to Shah Deniz
November 2012
TAP’s shareholders conclude Shareholder Agreement with SOCAR, Total and BP
August 2012
TAP’s shareholders sign Funding and Equity Agreement with SOCAR, Total and BP with an option to take 50% equity in project
June 2012
TAP signs Cooperation Agreement with Shah Deniz Consortium
February 2012
Shah Deniz Consortium selects TAP as priority route to southern Europe
Alignment & Transparency
Operabiltiy
Scalability
Public Policy Considerations
TAP's Key Features
Alignment with EC policy objectives • Designed to expand from 10 to 20 bcm (plus) per year
• Up to 80% of physical reverse flow and potential gas storage
• Connecting directly to TANAP on the Turkish-Greek border
• Interconnection with various existing and proposed pipelines providing energy security in SE Europe
• Providing Bulgaria with a new source of gas through IGB or the Kula-Sidirokastro Interconnector
• Delivering gas and interconnecting to multiple markets in Western and Central Europe
• Bringing major foreign direct investment and employment: Greece – Euro 1.5 bln,- supporting economic
recovery in the Eurozone
6
?
?
?
TAP can connect SD/new gas to Europe
1. TAP will connect to the Italian
natural gas grid to provide firm
capacity at the Italian virtual trading
point (PSV)), from which all Italian
gas exit points can be reached
2. TAP can reach Baumgarten via
TAG pipeline to have similar
transportation capacity as other
planned pipelines, e.g.:
• 6 bcm/a reverse technical capacity
• 25 bcm/a average swap potential (2011)
3. TAP can reach Germany and
France via Transitgas pipeline
through Switzerland, e.g.:
• virtual backhaul of approx 10 bcm/a
• planned physical backhaul of 15 bcm/a
4. Baumgarten: Despite developed
pipeline infrastructure, grid extension
is necessary to reach markets of
western Germany from Baumgarten
TAP will have an option to link to
Baumgarten, and moreover, it will reach
Germany & France via Switzerland and
will have access to the Italian PSV
trading hub
TAP can deliver to the UK and more….
Grid operators Snam Rete Gas and Fluxys
signed Memorandum of Understanding in
August 2012 to develop physical reverse
flow capacities between Italy and the UK:
• Managing Director of FluxSwiss announced
that the company is ‘committed to investing
in the project to enable south-to-north
flows“
Objective: interconnect gas markets of Italy,
Switzerland, Germany, Netherlands and
Belgium
Volume: up to 15 bcm/a physical reverse flow
by 2018
This will create a new natural gas supply
route directly to the UK in the future.
TAP’s Connection to the Balkans TAP can provide Bulgaria with a new source of gas through existing and planned
infrastructure
Reverse flow on Kula/Sidirokastro
Interconnection point exporting Russian gas from Bulgaria
into Greece.
Existing capacity (Bulgaria-to-Greece direction): 4.3 bcm/y
at a minimum pressure at Sidirokastro MS of 47,74 barg.
Reverse Flow capacity: up to 4.3 bcm/y
IGB
IGB – is designed to connect Greece (Komotini) to Bulgaria
(Stara Zagora).
Planned Capacity: up to 3 bcm/y (option for capacity
increase to 5 bcm/y)
Int. BG
-Serbia* SERBIA
FYROM
*operations scheduled to start in 2015 9
Supported by Strong Partners
42.5% • Swiss energy company with
European focus
• Together with its partners, supplies
electricity to around 3 million
people
10 TAP's Corporate Presentation
42.5%
• Second largest gas supplier to
Europe
• The world’s largest deepwater
operator (8,000 km of subsea
pipelines)
• Partner and commercial operator
of the Shah Deniz consortium
15%
• Europe’s largest private utility
supplying 53 billion m³ of gas
yearly
• Own supply system comprises
11,600 km of gas pipelines
• Operates gas fired power plants
in Italy
TAP’s shareholders are the
world’s leading specialists
in the implementation of
pipeline projects having
developed over 20,000 km
of onshore and offshore
pipelines around the globe
“A” rated companies with a combined market capitalisation of over one hundred billion Euros
Massive Effort in Developing TAP
11
Front-end engineering design completed
Key Features:
• FEED completed March 2013
• Full ESIA submitted in Italy (March 2012), Albania (January 2013), full ESIA to be submitted in Greece (2Q
2013)
• Pre-qualification for steel pipe producers (January 2013)
• Frame agreements with major suppliers
Technical Excellence Mobilised:
• World class engineering expertise of Statoil and E.ON mobilized – 2 TSPs, approx. 40 subcontractors, 200
specialists working for TAP every day
• Analyzed 10,000 km of terrain in detail to identify TAP route of approx. 870 km
• Organised 150 technical field missions, offshore and onshore surveys
TAP's Corporate Presentation
Robust and creditworthy shareholders support a strong and solid business case, thus
enabling greater flexibility of financing conditions.
• Liquidity in very difficult & challenging economic climate
• No reliance on public funding to succeed
• Lower CAPEX compared to other projects in Southern Gas Corridor
• TAP initiated discussions with International Financing Institutions including EBRD & EIB as
well as various Export Credit Guarantee Agencies
• Banks signalled willingness of the market to provide financing
15.04.2013 12
Sound Financing Approach
Investment confidence
March 2013
TAP and members of the Shah Deniz Consortium
selected Société Générale Corporate & Investment
Banking to provide financial guidance to the project
during its preparatory and construction phases.
• finance strategy
• bankability review
• credible and deliverable
funding plan for TAP
TAP’s Advanced Status
Political / Agreements
• Intergovernmental Agreement (IGA) signed (February 2013), Ratifed in Albania 25th March, and
Greece 10th April
• Host Government Agreement signed and ratified with Albania (15th April 2013)
• Host Government Agreement with Greece planned to be concluded (April 2013)
• TAP and TANAP Cooperation Agreement signed (December 2012)
• TAP becomes “project of national importance” in Albania (December 2012)
• Memorandum of Understanding (MoU) between Albania, Greece, Italy signed (September 2012)
• MoUs in South Eastern Europe on interconnection with IAP (Plinacro Ltd, Croatia; BH-Gas, Bosnia;
the government of Montenegro; the government of Albania; Geoplin Plinovodi, Slovenia)
Technical
• Front-end engineering design (FEED) completed (March 2013)
• 10,000 km of terrain analyzed, world class engineering expertise of Statoil and E.ON mobilised
• Full ESIA submitted in Italy (March 2012), Albania (January 2013, approved in April), ESIA Greece
(1Q 2013)
• Pre-qualification for steel pipe producers (January 2013)
• Environmental permit received in Albania (March 2013)
Cooperation with
Shah Deniz (SOCAR,
BP, Total) /
Commercial
• Decision Support Packages submitted to Shah Deniz (28 March 2013)
• Shareholder Agreement concluded with Shah Deniz (November 2012)
• Funding and Equity Option Agreement signed with Shah Deniz (August 2012)
• Cooperation Agreement signed with Shah Deniz (June 2012)
• TAP selected as priority southern route by Shah Deniz (February 2012)
• Third Party Exemptions approved by three National Energy Regulators (4th March 2013), submitted
to European Commission
Finance
• TAP initiated discussions with International Financing Institutions including EBRD & EIB
• Financial Advisor selected (Société Générale)
• No reliance on subsidies or grants
Key Political Milestone
On 13 of February 2013 the governments of Italy, Greece and Albania signed
Intergovernmental Agreement on TAP in Athens, Greece. The IGA has now been ratified by
the Albanian and Greek Parliaments.
IGA signed in Athens by
Dimitris Avramopoulos, Greek
Foreign Minister, Edmond
Haxhinasto, the Deputy Prime
Minister and Energy Minister of
Albania, and Corrado Passera,
Italian Development Minister.
IGA solidifies a range of key commitments by
Greece, Italy and Albania to the forward
development, construction and operation of
the TAP pipeline
Conclusion - SD is just the start….
15
• Azerbaijan’s role as a stable supplier of gas
contributing to Europe’s energy security will
continue to grow in the next decades
• Production from gas fields in the Caspian
could increase Azerbaijan’s natural gas
production to c.40 bcm/a by 2030
• The giant Caspian gas and condensate field
Shah Deniz – 1.2 tcm
• SOCAR’s current exploration of the Umid
field and Babek along with Total’s
exploration of Absheron,
• Other fields including ACG Deep,
Nakhchivan, Shafag-Asiman, and Zafar-
Mashal resulting in overall proven reserves
of approximately 2.5tcm
• TANAP IGAs and HGAs signed and ratified
by Azerbaijani and Turkish parliaments
represents a clear export route to the border
with the EU
Source: Gulmira Rzayeva, Center for Strategic Studies under the President of Azerbaijan
Azerbaijan: reliable & growing supplier of gas to Europe
Thank you!
Find out more about TAP at:
www.trans-adriatic-pipeline.com
15.04.2013 16 TAP's Corporate Presentation