Upload
others
View
12
Download
1
Embed Size (px)
Citation preview
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 1 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
RISK ASSESSMENTS & METHOD STATEMENT 04
FOR
INSTALLATION OF SURFACE WATER V DITCHES AND HEADWALLS TO ALLOW DISCHARGE OF PLANNING CONDITION 21.
C2278
OMEGA WARRINGTON – Zone 7 Phase 1
NAME POSITION APPROVED (signature required)
DATE
Ian Byrne Director
Ed McDonald Contracts Manager
Darren Fowles Project Manager (Author)
This document MUST be SIGNED OFF by at least 2 of the ABOVE BEFORE USE when working at height, deep drainage or other high risk activities
Adam Onyett SHEQ Coordinator
IF SITE CONDITIONS CHANGE OUT WITH THE RISK AND METHOD STATEMENT
SCOPE WORKS WILL STOP BE REASSESSED FOR RISK AND METHOD RE-AGREED INDUCTED AND IMPLEMENTED
Revision: 02 Date: 07.10.13
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 2 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
(No. 04)
Contract: Omega Warrington
Description of Works: Cut / fill to main works / Installation of Permanent Drainage Systems and Silt Mitigation Measures
Prepared by: Darren Fowles Date: 07/10/13
Approved By: Date:
Distribution: Site,
Client : Omega Warrington Ltd
RECORD OF ATTENDANCE
I have read the above method statement and fully understand its contents. I agree to carry out the work in compliance with this document and will not change from the agreed system of work without prior notification to the site supervisor.
Date Full Name Company Signature
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 3 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
KEY RISKS OF THIS METHOD STATEMENT:
Plant and machinery movements and operation
Adverse weather conditions
Excavations
Contaminated ground On site re-fuelling
Pollution of water courses
Environmental Impact
o Disruption of habitats
1.0 SCOPE OF WORKS If site conditions change, out with the method and risk assessment scope, work shall stop, be re-assessed for risk, with methods re-agreed, inducted and implemented. 1.1 Install level control 1.2 Cut and fill operations 1.3 Excavation of V Ditches
2.0 RISK ASSESSMENTS / COSHH
2.1 Risk assessments have been carried out and the operations on the following
pages have been identified as the most significant risks. Additional assessments are located within the D Morgan PLC Occupational Health & Safety System and copy of which is available on site via the Site Manager.
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 4 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
PROJECT: Omega South Zone 7 Phase 1 - Warrington
GRUB UP EXISTING HARDSTANDINGS
Person at Risk
Initial
Evaluation of Risk
High
Medium Low
(HML)
CONTROLLED MEASURES
Final
Evaluation of Risk
High
Medium Low
(HML)
AC
TIO
N B
Y
Item No.
SIGNIFICANT RISKS / HAZARDS
Site
Per
sonn
el
Pub
lic
Sub
cont
ract
or
Oth
ers
1. Noise – Hearing loss H 1. Wear ear protection when working near to the machine L Site
Ops
2. Dust H
1. If working close to excavator wear dust mask to prevent inhalation of dust.
2. Materials will be damped down where necessary to prevent the generation of dust.
L Site Ops
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 5 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
PROJECT: Omega South Zone 7 Phase 1 - Warrington
SURVEYING / SETTING OUT
Person at Risk
Initial
Evaluation of Risk
High
Medium Low
(HML)
FURTHER ACTIONS REQUIRED
Final
Evaluation of Risk
High
Medium Low
(HML)
AC
TIO
N B
Y
Item No.
SIGNIFICANT RISKS / HAZARDS
Site
Per
sonn
el
Pub
lic
Sub
cont
ract
or
Oth
ers
1 Underground Services M
1. Review contract drawings for position of known services 2. Contact Stats to obtain all known info on existing services 3. Confirm actual position of known services from surrounding features and by use of cable detectors/ trial holes and mark on site 4. Scan for underground services in advance and mark clearly on the ground 5. If in doubt use alternative methods (i.e. standing profiles, etc)
L Site Ops
2 Contact with O/H Services M
1. As (1&2) above 2. Establish approved crossing points / goal post Protection / exclusion zones in tandem with service owner 3. Prohibit use of levelling staves beneath O/H electrical services
L
Site Ops
3 Hidden trip hazards i.e. open manholes/ natural sink holes M
1. Pre-survey to establish potential trip hazards and cover/ mark / fence or fill in advance, as appropriate 2. Maintain personal vigilance at all times 3. Wear safety boots and safety helmet at all times
L Site Ops
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 6 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
PROJECT: Omega South Zone 7 Phase 1 - Warrington
SURVEYING / SETTING OUT
Person at Risk
Initial
Evaluation of Risk
High
Medium Low
(HML)
FURTHER ACTIONS REQUIRED
Final
Evaluation of Risk
High
Medium Low
(HML)
AC
TIO
N B
Y
Item No.
SIGNIFICANT RISKS / HAZARDS
Site
Per
sonn
el
Pub
lic
Sub
cont
ract
or
Oth
ers
4 Falling into excavation, Falling over steep/ shear inclines and edges of ex. Structures
M
1. All excavations shall be fenced and backfilled as soon as practical 2. A readily accessible means of access will be maintained at all times (i.e. ladder / ramp/ steps) 3. Do not survey at unprotected edge remain 1.5m min from edge
L Site Ops
5 Contamination from Contaminated Land See Excavation & Filling Risk Assessment
6 Personnel Hit by Traffic/ Plant – on Highway
1. Set up traffic management measures where necessary 2. Where necessary, have an extra operative available to act
as a lookout 3. Avoid working on live carriageways unless absolutely
necessary and undertake works outside of busy times
L Site Ops
7 Personnel Struck by Plant and Vehicles M
1. Workforce to stay within vision of driver 2. Ensure good visibility at all times 3. All personnel to wear Hi-Viz PPE 4. Work in authorised areas only
L Site Ops
8 Slip / trip / fall M Site Ops L
Site Ops
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 7 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
PROJECT: Omega South Zone 7 Phase 1 - Warrington
SURVEYING / SETTING OUT
Person at Risk
Initial Evaluation
of Risk
High Medium
Low
(HML)
FURTHER ACTIONS REQUIRED
Final
Evaluation of Risk
High
Medium Low
(HML)
AC
TIO
N B
Y:
Item No.
SIGNIFICANT RISKS / HAZARDS
Site
Per
sonn
el
Pub
lic
Sub
cont
ract
or
Oth
ers
9 Inhalation of fumes and Particulates M
1. Use in well ventilated environment 2. Check wind direction to avoid ‘blow back’ 3. dispose of empty can at designated disposal
locations only
L Site
Ops
10 Explosions / Fire M 1. Store paint as manufacturer’s instructions 2. Keep out of direct sunlight and away from heat
sources
L Site
Ops
11 Eye Injury – Installation of Hiliti Nails M
1. Wear class 1 eye protection at all times 2. Trained personnel only to use percussion tools 3. Personnel not trained as (2) should use
lightweight hand hammer only
L Site
Ops
12 Hand Injury M
1. Wear thick protective gloves 2. Hold item to be driven away from impact area 3. Use weight of hammer appropriate o the task
and the strength of the user 4. ‘Both striker’ and ‘holder’ should keep their eye
on the job at all times
L
Site Ops
13 Eye Injury – Use of Laser Level M 1. Engineer only to use Laser equipment
2. Do not look directly into laser
L Site Ops
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 8 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
PROJECT: Omega South Zone 7 Phase 1 - Warrington
FORWARD TIPPING DUMPERS
Person at Risk
Initial Evaluation of Risk
High Medium
Low
(HML)
FURTHER ACTIONS REQUIRED
Final
Evaluation of Risk
High
Medium Low
(HML)
ACTI
ON
BY
Item No.
SIGNIFICANT RISKS / HAZARDS S
ite P
erso
nnel
Pub
lic
Sub
cont
ract
or
Oth
ers
1 Overturning on Slopes and Rough Ground at the Edges of Excavations, Embankments, Etc
H
1. Maintain haul routes to minimize potholes, ruts, debris and other obstructions 2. Avoid slopes, including slopes in the direction of travel. If slopes cannot be avoided, check with the vehicle manufacturer that the dumper can negotiate the slopes safely 3. Dumper overturns often occur due to a combination of slope and rough ground so manufacturers guidance on the capability of a vehicle to negotiate a slope should be reduced where rough ground must be negotiated 4. Speed should be kept to a minimum on rough ground 5. Where traffic routes pass close to the edge of a roadway, embankment or other drop, make sure the edge of the roadway is suitably supported and a barrier in place to prevent vehicles running off the roadway (either stop blocks or bunded) 6. Undertake regular maintenance and vehicle checks in accordance with manufactures recommendations 7. Stop blocks or safe bunding edges of haul roads / slopes
L Site Ops
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 9 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
PROJECT: Omega South Zone 7 Phase 1 - Warrington
FORWARD TIPPING DUMPERS
Person at Risk
Initial Evaluation of Risk
High Medium
Low
(HML)
FURTHER ACTIONS REQUIRED
Final
Evaluation of Risk
High
Medium Low
(HML)
ACTI
ON
BY
Item No.
SIGNIFICANT RISKS / HAZARDS
Site
Per
sonn
el
Pub
lic
Sub
cont
ract
or
Oth
ers
And protection to excavations. And adequate designed temp works to trenches 8. Only trained and competent drivers to operate dumpers
2 Travelling when high lift skip is in raised position M
1. Stability of high lift dumpers is greatly reduced when the skip is in the elevated position 2. Where dumpers need to have skips raised ensure ground level is level and free of debris
L Site Ops
3 Pedestrians Struck by Dumpers H
1. All pedestrians to wear Hi-Viz clothing 2. Site speed limit to be established and reduced to 5mph (walking pace) where dumpers and pedestrians are in close proximity 3. Keep dumpers and pedestrians apart wherever possible by creating designated walkways 4. Ensure dumpers are not overloaded, restricting drivers vision
L Site Ops
4 Driver Error due to Lack of Experience and Training e.g. accidental operation of controls
M
1. Drivers to familiarise themselves with vehicle controls prior to moving 2. Only allow authorised drivers to hold vehicle keys 3. Instruct drivers to turn off engine and remove key whenever leaving the vehicle
L Site Ops
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 10 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
PROJECT: Omega South Zone 7 Phase 1 - Warrington
LOAD AND TIP
Person at Risk
Initial
Evaluation of Risk
High
Medium Low
(HML)
FURTHER ACTIONS REQUIRED
Final
Evaluation of Risk
High
Medium Low
(HML)
AC
TIO
N B
Y
Item No.
SIGNIFICANT RISKS / HAZARDS
Site
Per
sonn
el
Pub
lic
Sub
cont
ract
or
Oth
ers
1. Overhead Services Contact with H
1. Inspect site for position of known services 2. Contact Stats. To obtain all known info. on ex services 3. Notify relevant authorities of construction work and agree working restrictions / minimum clearances / controlled crossing points 4. Establish approved crossing points / goal post Protection / exclusion zones in tandem with service owner
L Site Ops
2. Striking Operatives - Loading M
1. All operatives shall stay outside turning circle of excavator 2. All operatives to wear fluorescent PPE/ hard hats and boots 3. All wagon movements are to be under plant driver instructions and on level ground 4. No wagons / plant movements until operatives visible to driver 5. HGV driver to remain in cab when being loaded
L Site Ops
3. Striking Vehicles - Loading M 1. All wagon movements are to be under plant driver instruction 2. Due care and attention to be paid by plant driver
L Site Ops
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 11 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
PROJECT: Omega South Zone 7 Phase 1 - Warrington
LOAD AND TIP
Person at Risk
Initial
Evaluation of Risk
High
Medium Low
(HML)
FURTHER ACTIONS REQUIRED
Final
Evaluation of Risk
High
Medium Low
(HML)
AC
TIO
N B
Y
Item No.
SIGNIFICANT RISKS / HAZARDS
Site
Per
sonn
el
Pub
lic
Sub
cont
ract
or
Oth
ers
when loading 3. Never load over cab of wagon
4. Striking Operatives – Placing M
1. All wagon tipping movements are to be under banksman or P/operative control on level ground 2. All operatives to wear florescent PPE/ hard hats and boots 3. All operatives to keep clear of mechanical movements 4. No wagons/ plant movements until ground operatives visible to driver/s
L Site Ops
5. Striking Vehicles – Placing M 1. All wagon movements are to be under plant driver instruction 2. Due care and attention to be paid by HGV driver when tipping
L Site Ops
6. Overhead services Contact with – Placing H
1. Inspect site for position of known services 2. Contact Stats. To obtain all known info. on ex, services 3. Notify relevant authorities of construction work and Agree working restrictions / minimum clearances / Controlled crossing points 4. Establish approved crossing points / goal post protection/exclusion zones
L Site Ops
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 12 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
1.
Plant and machinery movements Parking of Plant and Machinery Plant Overturning Accessing machine cabs and engine compartments.
H
All plant must have 360 degree all round vision (cameras or mirrors). All plant ops must hold valid CPCS cards and provide up to date competency records to prove familiarisation with machines. All plant must have operational reversing bleepers checked daily by operators. Excavator cabs must be facing direction of travel. No operatives to enter the swing area of any excavator whilst machine is operational. All keys to be removed and cab door locked when machine is left unattended. All personnel will be inducted into the D Morgan “Say Hello, Wave Goodbye” protocol. Should any members of the public enter the site all operations must cease until the pedestrians have been escorted to a safe distance away from operational areas.
Avoid, where possible, parking on inclines. Always keep steps clear of debris build up. Always use handrails when accessing engine compartment.
Keep windows and mirrors clean at all times. Ground conditions to be continually monitored by site supervisors and ground personnel.
When mounting or dismounting machines always face machine and use climbing steps.
Never jump from machines ADT’s must be loaded evenly and only to safe carrying weight/volume
M
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 13 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
ADT’s must only deposit loads on firm even ground
When tipping ADT’s cab and body must be in line
Handbrake must be applied and neutral gear selected prior to tipping. .
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 14 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
PROJECT: Omega South Zone 7 Phase 1 - Warrington
OPERATED PLANT MOVEMENT
Person at Risk
Initial
Evaluation of Risk
High
Medium Low
(HML)
CONTROLLED MEASURES
Final
Evaluation of Risk
High
Medium Low
(HML)
AC
TIO
N B
Y
Item No.
SIGNIFICANT RISKS / HAZARDS
Site
Per
sonn
el
Pub
lic
Sub
cont
ract
or
Oth
ers
1. Tracking M
1. Operator to check for clearance prior to moving (min clearance 600mm)
2. Ensure good 360 degree visibility at all times 3. Banksman or operator must do a full all round check prior
to movement 4. Banksman or operator must ensure no pedestrians, plant
or equipment within working area 5. Ensure nothing is left close to machine operation (e.g.
small tools) 6. Cab must be facing direction of travel
L Site Ops
2. Slewing M
1. Operator to check for clearance before moving (min. 600mm)
2. Workforce to stay within vision of driver at all times 3. Slewing to be undertaken under trained banks man
supervision only 4. Barriers to be used when machine works in confined area 5. Ground operatives and members of the public to be
excluded from fenced working area 6. Ensure nothing is left close to machine operation (e.g.
small tools)
L Site Ops
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 15 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
PROJECT: Omega South Zone 7 Phase 1 - Warrington
OPERATED PLANT MOVEMENT
Person at Risk
Initial
Evaluation of Risk
High
Medium Low
(HML)
CONTROLLED MEASURES
Final
Evaluation of Risk
High
Medium Low
(HML)
AC
TIO
N B
Y
Item No.
SIGNIFICANT RISKS / HAZARDS
Site
Per
sonn
el
Pub
lic
Sub
cont
ract
or
Oth
ers
1. Pollution of Watercourses M
1. All plant to be parked a min of 30m from any watercourses 2. No re-fuelling within 10m of water courses but 30m as best practice. 3. Any spills or leaks must be cleaned up immediately and reported to the Site Management and BAE Systems 4. Discharge points must be formally agreed prior to any works commencing. 5. Silt traps, catch pits and drainage ditches must be checked and cleaned at least daily and more if needed. 6. Discharged water must be as clean as possible at discharge point
L Site Ops
2. Disruption of Habitats M
1. Proposal to be accepted, area to be scanned and valid permit to work issued prior to any works taking place. 2. All operatives must be advised of all sensitive areas with regard to wildlife habitats
L Site Ops
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 16 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
3.0 SITE ACCESS & EGRESS
The site is situated off Burtonwood Road, Westbrook; Warrington. Access will be via extg steel gates off the roundabout on Burtonwood Road. The existing gates will be kept shut and locked at all times when not in use.
Access to the work area and water course will be via existing hard standings/ roads where available, when unavailable routes will be defined within the Miller Red line boundary to avoid unnecessary trampling of the wider area.
Route definition will take into account proximity to bank edges for both stability and safety implications. As mentioned in the site CEMP plan –
To mitigate any conflict with GCN in hibernation we will install the outfall head wall by Nov 2013, all stockpiles/ arising’s from ditch excavations will be moved or loaded immediately so as not to attract wildlife.
To further mitigate / discourage GCN’s plant machinery and materials will not be stored in close proximity to the water course. It is our aim to prevent GCN’s from seeking shelter or protection within our materials storage area. If storage is necessary, blocks will be used to keep items off ground.
4.0 RESOURCES AND RESPONSIBILITIES
Labour Project Manager – Darren Fowles Engineer – Dan Wilkinson
Plant Operatives
Plant/Tools Tracked Excavators D65 / 61Dozers
Dump Trucks Ride on Vibratory Roller
Materials Site won material T
PPE Safety Helmet Hi-viz vest/jackets Safety footwear (steel toe & sole) Gloves Hearing Protection (as specified by risk assessment)
Dust masks (as specified by risk assessment)
4.1 All operatives and operators will produce valid CSCS / CPCS cards or Certificates of Competency, prior to starting work.
4.2 All plant shall have valid safety certificates and will be produced prior to starting
work. All plant operators should fill in daily check sheets for submission to the site manager at the end of the week.
4.3 All work will be undertaken in accordance with the D Morgan Health & Safety
Policy, the Project Health & Safety Plan and Site Rules, taking particular notice of the hazards associated with working on site.
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 17 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
4.4 Operatives will be suitably inducted and given regular toolbox talks on the
hazards involved and the precautions required.
4.5 The on-going operations will be monitored by our Project Manager Darren Fowles (Tel: - 07771847473) to ensure that they comply with the restrictions outlined.
4.6 Smoking is not permitted on site, except in designated areas.
4.7 No work is to proceed until a valid excavation permit to work has been issued
by the site Engineer.
5.0 PHASING & SEQUENCE OF THE WORKS
5.1 Upon arrival on site a full CAT and generator survey will be carried out by the site engineer to locate all known services within the work area, with the services being marked out.
5.2 A ‘Permit to Dig’ will then be issued to all machine operatives and banksman
detailing all known services on an attached drawing.
5.3 The D6 Dozer will push the topsoil off the proposed route of the swale into an agreed location and stockpiled for future use on the batters.
5.4 Excavation works will commence with a 360 tracked excavator using a V shaped bucket.
5.5 Arising’s will be loaded directly onto an ADT or forward tipping dump truck for disposal in the tip or for reuse elsewhere on site.
5.6 Site won clay will be used to form the batters of the swales; this will be transported from point of loading to tipping point by ADT’s under guidance of a banks man.
5.7 When site won material is being moved all trucks / ADT’s will adhere to site speed limits and banks man’s instructions. When loading the dump trucks will reverse towards the loading excavator, with the aid of mirrors and reversing camera, until a suitable loading place has been achieved. The excavator driver will signal the ADT driver at this point. The dump truck driver will then apply the handbrake and select neutral gear. The excavator will then load the skips of the ADT’s to practical carrying weight/volume. The truck will be signalled when the load is ready. The operator will drive the truck towards the fill area and select his tipping location ensuring the truck can tip safely on firm and even ground. The truck driver will then turn the cab of the truck away from the selected tipping location and drive forwards until the cab and body are in line. The driver will then select reverse gear and travel backwards until the desired tipping location is achieved, apply the handbrake and select neutral gear. The operator will then raise the body of the ADT and deposit the load. Once the skip is fully raised the operator will select forward gear and release the handbrake. The
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 18 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
truck will then drive forward until the truck is clear of the deposited load. Once this is achieved the truck will return to the loading excavator and repeat this operation until completion. Turning circles will be formed beyond the fill area for the trucks to turn and head back to the loading excavator(s).
5.8
Compaction in areas of the swale requiring fill will be carried out using ride on vibratory roller. The compaction plant will observe the correct number of passes for the materials being placed according to Table 6/4 of the ‘Specification for Highway Works’.
5.9 In the instance of surface water run-off from existing roads and haul routes, areas will be identified to install catch pits initially. Silt nets will then be installed at the discharge points in a half moon shape and nailed to engineering pegs. All run off will then be channelled towards the catch pits with a series of v-ditches. Should the flow be too great for the catch pits to function efficiently check dams will be installed using pipe bedding material, at regular intervals.
5.10 All catch pits, v-ditches, silt nets and settlement ponds will be proactively
monitored by the site supervisor, always assuming the worst case scenario.
5.11 As mentioned in section 3.0 –
To mitigate any conflict with GCN in hibernation we will install the outfall head wall by Nov 2013, all stockpiles/ arising’s from ditch excavations will be moved or loaded immediately so as not to attract wildlife.
6.0 CONTROL MEASURES
6.1 All personnel to attend the D. Morgan Site Inductions and will be required to hold passes for access to the site. All personnel must stay within the designated working area at all times.
6.2 Site inductions are to be carried out by the D Morgan site supervisors; this
will include the site rules, emergency procedures, site specific hazards. Regular tool box talks and daily task briefings will be held to discuss further safety issues relevant to the works in progress.
6.3 Dust monitoring will be carried out visually, by the site management team
whilst works are under way
6.4 Stockpiles will be in designated, agreed areas controlled by DM staff.
6.5 All plant/wagons will have operational flashing beacons.
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 19 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
6.6 All machines using vibratory equipment (crusher, breaker etc) will be assessed for noise and vibration exposure limits.
6.7 Regular Occupational Health Screening is carried out on all Operatives.
6.8 Dust and Particulate Suppression All D Morgan haul routes will be damped
down as necessary by the D Morgan tractor and bowser.
6.9 Surface Water / Rain Water run-off will be channelled to the constructed drainage system where it will pass through check dams constructed of pipe bedding.
6.10 Refuelling Plant will be refuelled using onsite tank. The excavator within the
will be refuelled using a towable bowser with spill kits available. All ADT’s will be refuelled away from any watercourse
Control recommendations within Arnott Mann Ecological Impact Assessment.
No animals have been recorded within Omega South. The various water features that are found within the immediate vicinity of the site are not considered to have potential for great crested newts to occupy. The site, including the location where a new attenuation pond is planned, and the route defined for installation of a new drainage ditch in the south east, is not considered to be great crested newt terrestrial habitat. The entire area is short, open, mown/grazed improved grassland and will offer no shelter or foraging opportunities for amphibians. Stockpiles to be moved so as not to attract GCN’s Visual search for GCN’s prior to commencement of topsoil strip / excavation works.
6.11 The above control measures along with controlled access / egress procedures mentioned in Section 3.0 form the basis of our environmental mitigation measures, this is a live document and will be updated accordingly should circumstances / environments change.
7.0 TEMPORARY AMMENDMENTS
7.1 No changes to working methods are accepted on site unless contained in a revised method statement agreed by D Morgan
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 20 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
8.0 EMERGENCY PROCEDURES
Follow normal site rules (displayed in site office) and make immediate contact with the site supervisor below if any accident or dangerous occurrence happens whilst on site. If any damage occurs to services, no matter how minor it may appear, this must be reported to the site supervisor immediately. The Site Supervisor is responsible for ensuring that all staff and operatives are alerted to the emergency, in the event that an evacuation is required. This will be carried out using an air horn.
DM Project Manager Darren Fowles 07771 847473
DM Site Engineer Dan Wilkinson 07803 291618 DM Operations Manager Ian Banks 07803 291632
DM Contracts Director Ian Byrne 07803 291614 Following contact of any of the above emergency numbers, it may be necessary to contact one or more of the following:
In the event of an accident notify your supervisor or the nearest first aider. The qualified and certificated first Aider is Daniel Wilkinson.
The nearest A&E hospital is approximately 4 miles from the site, address below: Warrington Hospital Lovely Lane Warrington WA5 1QG Tel - 01925 635911 If absolutely necessary call the emergency services on 999.
METHOD STATEMENT
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 21 of 21
SHEQ / DM / P9.R3 / REV02 Oct 2013
9.0 INFORMATION ISSUE & MONITORING
It is a requirement that all operative and supervisory staff; are aware of the contents of this method statement and the working procedure to be followed. This is achieved by signing the cover sheet. If works can be carried out in a more efficient/safer manner then the working procedure may be altered providing the site supervisor has authorised the change in working procedure. The site supervisor is the person responsible for the ongoing review of the works being carried out and the carrying out of on site risk assessments should the work differ from those described above.
PROJECT ENVIRONMENTAL PLAN ADDENDUM
Treatment of suspended solids / Surface water run-off Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 1 of 7
SHEQ / DM/ R1C9/REV03 Oct 13
ADDENDUM
FOR
OMEGA ZONE 7 PHASE 1 SOUTH INFRASTRUCTURE WORKS
TREATMENT OF SUSPENDED SOLIDS FROM SURFACE WATER RUN OFF
TO ALLOW DISCHARGE OF PLANNING CONDITION 22.
C2278
For
OMEGA WARRINGTON
NAME POSITION APPROVED
(signature required) DATE
Ian Byrne Contracts Director
Ed McDonald Contracts Manager
Adam Onyett SHEQ Coordinator
Environmental Plan MUST be SIGNED OFF by at least 2 of the ABOVE BEFORE USE
Darren Fowles Project Manager
Revision Comments Date Rev 1 For Comment 07/10/13
Document Ref: R1.C9 (Revised Oct 2013)
PROJECT ENVIRONMENTAL PLAN ADDENDUM
Treatment of suspended solids / Surface water run-off Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 2 of 7
SHEQ / DM/ R1C9/REV03 Oct 13
AUTHORISATION AND ISSUE RECORD The following Addendum relating to the treatment of suspended solids has been prepared in accordance with the Environmental Management System (EMS) Procedure C9 – Operational Control. I authorise the use of this plan as the main control element of the EMS on the above contract. This should be read with the ‘Electronic’ access to the Documented Environment Management System and Manual. Name Adam Onyett Signature Date 07.10.13 Job Title SHEQ Coordinator
The Project Environmental Plan is to be issued to the Project Team, listed below, who shall agree to comply with its contents at site level and maintain the necessary documentation listed within it. The working copy of the plan is to be held on site and updated when applicable.
Name of Recipient Job Title Signature Date
The Site Manager, supported by the Contracts Manager and SHEQ Coordinator, is the key person within this system and shall be responsible for the following;
Method of work undertaken on the project matches the client and regulatory authorities’ requirements and minimises the effect of our works on the environment.
Verification that approved working procedures and regular inspections are implemented and all personnel are compliant.
Ensuring that all personnel on the project are aware of their responsibilities within the EMS, arranging training where necessary (via the SHEQ Coordinator).
Holding the current version of the EMS and advising the project team of the relevant procedures and records to be kept.
PROJECT ENVIRONMENTAL PLAN ADDENDUM
Treatment of suspended solids / Surface water run-off Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 3 of 7
SHEQ / DM/ R1C9/REV03 Oct 13
1. DESCRIPTION OF PROJECT
The project is described in the Tender Information Pack issued by WSP and summarised in the Health & Safety Plan. This includes, but is not limited to, the following activities;
Mobilisation and Set up Trial Holes Unexploded Ordnance Survey Breaking up of Concrete Slabs if req Earthworks Installation of Sub Station Installation of Utility Services Installation of Drainage Construction of Site Access Road Traffic & Materials Management
Risk Assessments with an associated Method Statement will be produced for each of these activities prior to the commencement of any element of the works. This addendum should be read in conjunction with MS04 Rev3 07/10/12
The Works is estimated to be a 40 week project to commence 19th August 2013.
2. RESPONSIBILITES WITHIN PROJECT TEAM
Specific environmental site responsibilities on this project are outlined in documents P4.R1.1 (for Contracts Manager) and P4.R1.2 (for Site Manager) of the OHSMS. These documents will be included in Section 1 of the Health & Safety ‘As Built’ File. Please read with the site staff structure and the roles and responsibilities for your position as designated or agreed. Agree your specific role on this project with the Contracts Manager (see Appendix C of the ‘C2278 - Health and Safety Plan’). Site notice boards must be established as the company standard for the site office and welfare unit, with all emergency details clearly displayed.
Specific Procedures and Responsibilities
Procedure
Description of Task Documents Generated Who
C9 Operational Control R1.C9 - Project Environmental Plan SC/CM C1 Legal & Other Requirements R1.C1 – Legal Requirements SC/CM C7 Communication R1.C7 – External Communication CM/SM C11 Emergency Planning R1.C11 – Emergency Plan
R2.C11 – Emergency Contacts CM/SM
C14 Legal Compliance R1.C1 – Legal Requirements SC/CM C15 Non Conformance Control R1.C15 – Non Conformance &
Corrective Action Record SC/CM/SM/G
C16 Control of Records R1.C16 – Control of Documents SM/E C17 Internal Audits R2.C17 – Internal Audit Record
R3.C17 – Site Review/Inspection SC SM
E1 Environment Aspects and R1.E1 – Significant Aspects and SC/CM/
PROJECT ENVIRONMENTAL PLAN ADDENDUM
Treatment of suspended solids / Surface water run-off Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 4 of 7
SHEQ / DM/ R1C9/REV03 Oct 13
Risk Assessment Impacts Summary R2.E1 – Aspect Significance
Assessment (Pollution) R3.E1 – Aspect Significance
Assessment (Resources) R4.E1 – Significant Aspects Impact
Control Sheet
SM
H&S Standard
Site Specific Environmental Information for Site
Workers/Visitors
Method Statements & Induction SM
SC - SHEQ COORDINATOR CM - CONTRACTS MANAGER SM - SITE MANAGER G – GANGER
SITE ACCESS & EGRESS
The site is situated off Burton wood Road, Westbrook; Warrington. Access will be via ext. steel gates off the roundabout on Burton wood Road. The existing gates will be kept shut and locked at all times when not in use.
Access to the work area and water course will be via existing hard standings/ roads where available, when unavailable routes will be defined within the Miller Red line boundary to avoid unnecessary trampling of the wider area.
Route definition will take into account proximity to bank edges for both stability and safety implications.
3. MONITORING AND AWARENESS
3.1 The Site Management Team is required to carry out regular monitoring of the system
and will complete a detailed checklist as part of an Environmental Site Review (detailed above). It is important that all established procedures are followed and that any problems are reported immediately. The site will also be subjected to a formal internal audit to assess the operation of the EMS.
3.2 Environmental awareness will be continually promoted and further improvements
discussed by carrying out Toolbox Talks on a regular basis to ensure that all operations are carried out to minimise the risk of pollution and reduce the volume of waste produced on site. All site personnel and sub-contractors will be required to sign the attendance record for these talks.
3.1 Environmental considerations will form part of the initial site induction, where the contents of this management plan will be disseminated to all personnel to ensure the awareness of its contents to all persons on site.
3.2 There is a requirement to carry out water sampling on 4 watercourses around site. 4. CONTROL OF WORKS
4.1 All incidents, no matter how minor, are to be reported to D. Morgan Site Manager and Client team (see organisational chart Appendix A). External parties will be contacted if required by D Morgan Site Management.
4.2 Refuelling / Fuel Storage - will be stored on site in limited quantities in a COSHH store
which will be bunded, with a collection tray for spill prevention and control. Refuelling
PROJECT ENVIRONMENTAL PLAN ADDENDUM
Treatment of suspended solids / Surface water run-off Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 5 of 7
SHEQ / DM/ R1C9/REV03 Oct 13
operations will be undertaken by daily visits from a mobile bowser and will take place in designated areas where drip trays will be utilised to catch any potential spillages. No refuelling will take place within 50M of any watercourse. To further mitigate any potential contamination to ground or watercourses, the bowser is equipped with a quick release fuel nozzle and all operated plant will be equipped with spill kits to tackle any spillages which may occur (no matter how minor).
4.3 All site fitters will be inducted to site rules. Any waste arising from maintenance / fitting
work shall be removed from site by the fitter and disposed of via either the D Morgan main office fitting service waste agreements (i.e. waste oils, grease cartridges, rags) or by our sub-contractor’s waste streams.
4.4 Plant, particularly articulated dump trucks, will have designated haul routes and
permitted areas for parking. These vehicles are to avoid causing any undue damage to flora and fauna which is not to be cleared in this phase of the works. Every effort will be made to reduce the impact of these works on the local ecology onsite.
4.5 Wherever possible materials will be reused locally not only to reduce waste, but also to
reduce emissions with localised rather than long haul movement of materials. It is also intended to maximise ‘dig once, place once’ options, minimising double handling of materials (saving both noise and emissions pollution).
4.6 Water management will be a high priority on this project. Localised bunding and lagoons
may be required to prevent surface water adversely affecting the works. It may also be necessary to excavate ‘grips’ or ‘v’ ditches to capture water and channel towards a holding area (lagoon), preferably the permanent works swales.
4.7 The spine road embankment will be constructed to allow surface water and solids to run into the works and on to the sand fill layer thus acting as a sponge for all surface water run-off. Either side of the fill area there will be bunds located to prevent surface water leaving the works.
4.8 Where water has collected in excavations or sump holes and is required to be pumped
clear, the water will be recharged to the sand fill in order to prevent its release into any watercourse. If any is suspected to be contaminated (it has oily residues apparent, odour or discolouration) then it must not be pumped until verified.
4.9 During the works all personnel shall remain vigilant to the potential of contaminated
materials. If any materials are suspected to contain contamination (oily residues, odour or discolouration), then works will stop and samples will be taken to determine whether or not the materials are contaminated.
4.10 It is believed that asbestos containing materials may be found on site. During the clearance works all personnel shall be briefed as to the likely presence and on finding such materials they will be fenced off and a plan for dealing with them put in place. This will be to confirm that the materials contain asbestos; if notifiable then a specialist sub-contractor will be procured (if not, then trained D Morgan personnel will undertake the works); the materials will be double bagged in asbestos bags and placed in an enclosed skip for offsite disposal to a licensed site to accept asbestos waste.
4.11 In order to maintain a high standard of good practice, Omega Warrington Limited has requested that the works are registered to the Considerate Constructors Scheme (CCS) and adhere to the scheme’s code of practice. In accordance with BREEAM requirements, a CCS score between 32 and 40 will be achieved and all sections within
PROJECT ENVIRONMENTAL PLAN ADDENDUM
Treatment of suspended solids / Surface water run-off Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 6 of 7
SHEQ / DM/ R1C9/REV03 Oct 13
the scheme will achieve a score more than or equal to 3. The scheme will be implemented through each sub-contractor.
4.12 The contents of the WSP document ‘Construction Environmental Management Plan’ will
be considered throughout the works and the relevant parts adhered to, with most of its requirements being addressed within this document. All plant to be parked a min of 50m from any watercourses No re-fuelling within 50m of water courses but 100m as best practice. Any spills or leaks must be cleaned up immediately and reported to the Site Management Discharge points must be formally agreed prior to any works commencing. Silt traps, catch pits and drainage ditches must be checked and cleaned at least daily and more regular if needed. Discharged water must be as clean as possible at discharge point In the instance of surface water run-off from existing roads and haul routes, areas will be identified to install catch pits initially. Silt nets will then be installed at the discharge points in a half moon shape and nailed to engineering pegs. All run off will then be channelled towards the catch pits with a series of v-ditches. Should the flow be too great for the catch pits to function efficiently check dams will be installed using pipe bedding material, at regular intervals.
All catch pits, v-ditches, silt nets and settlement ponds will be proactively monitored by the site supervisor, always assuming the worst case scenario.
4.1 Wheel Wash Facilities - To prevent mud etc. from entering the public highway a wheel wash is located 100M inside the main gate at Burton wood Road, the condition of the water will be monitored to ensure site going vehicle wheel are optimally cleaned prior to leaving site.
PROJECT ENVIRONMENTAL PLAN ADDENDUM
Treatment of suspended solids / Surface water run-off Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 7 of 7
SHEQ / DM/ R1C9/REV03 Oct 13
5. EMERGENCY PROCEDURES
5.1 Fuel/Oil (or other potentially damaging substance) Spillage
In the event of a spillage incident the following procedure must be followed;
Eliminate sources of ignition and cordon off area. Attempt to contain the spillage without risk to personal health and safety. Inform a member of the Site Supervisory Team of the approximate volume of the
spillage, location and measures taken at present. Where necessary, use plant from the locality to form bunds, excavate to Dump
Trucks or any other action which may contain/mitigate the spillage. Use spill kits from the plant to clean up or if necessary use adjacent soils. Do not allow the spillage to enter a watercourse. Site Manager to inform WSP staff and, if necessary, contact the following;
o Fire 999 o Environment Agency 0800 807060 o United Utilities 0845 746 2200
Site Manager to liaise with the above and agree measures to remediate area. Site Manager to complete an ‘Incident Report Form’ or NCR.
5.2 Surface Water Release
In the event of surface water release the following procedure must be followed;
Attempt to contain the release without risk to personal health and safety. Inform a member of the Site Supervisory Team of the approximate volume of
water released, location and measures taken at present. Where necessary/possible, use plant from the locality to form bunds or excavate
a sump (remembering to check Permit to Dig prior to breaking ground). Site Supervisory Team to call in bowser or pumps to ensure that the release is
contained in the bund/sump and does not overflow. Site Manager to inform WSP staff and, if necessary, contact the following;
o Environment Agency 0800 807060 o United Utilities 0845 746 2200
Site Manager to liaise with the above and agree further/improved mitigation measures.
Site Manager to complete an ‘Incident Report Form’ or NCR.
5.3 Emergency Preparedness These emergency procedures should be brought to the attention of all site personnel and, at a suitable time during the works, drills should be carried out to ensure that the emergency arrangements are effective and understood by all personnel.
| Tate Consulting
Bericote Properties
Omega,
Warrington
External Lighting Statement
February 2013
Document Validation Contract title Omega, Warrington Contract No
C1067
Document title
External Lighting Statement Doc/File ref
2PL001
Revision Date Filename External Lighting Statement Initial Issue 13/02/2013 Description External Lighting Statement prepared to support the
planning application.
Prepared by Checked by Approved by Name A McGregor S Tate
Signature
Revision Date Filename Description
Prepared by Checked by Approved by Name
Signature
Revision Date Filename Description
Prepared by Checked by Approved by Name
Signature
Tate Consulting Osborne House 20 Victoria Avenue Harrogate HG1 5QY T: +44 (0) 1423 538 020 W: www.tateconsulting.eu This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this
report, or any part thereof, is made known. Any such party relies on the report at their own risk.
Omega, Warrington – External Lighting Statement
Tate Consulting 3
Executive Summary
This External Lighting Statement has been prepared to support the planning application
submitted by Bericote Properties Limited for a proposed new Automated Distribution
Centre at the Omega South Business Centre in Warrington; and sets out the building
external lighting strategy as aligned with local planning policy.
The proposed development will comply fully with Warrington Borough Council
Supplementary Planning Document: Environmental Protection Supplementary Planning
Document: 5 Light pollution.
Omega, Warrington – External Lighting Statement
Tate Consulting 4
Contents
Executive Summary .............................................................................................. 3
Introduction ........................................................................................................... 5
1.0 Context ........................................................................................................ 5
2.0 The Development Site ................................................................................. 7
3.0 Assessment of the Need for Lighting .......................................................... 8
4.0 Lighting Standards ...................................................................................... 9
6.0 Control Measures .......................................................................................14
7.0 Design Measures for Biodiversity ...............................................................15
Appendix A – Proposed External Lighting Isolux Plots ........................................16
Omega, Warrington – External Lighting Statement
Tate Consulting 5
Introduction
This external lighting statement has been prepared to support the planning application
submitted by Bericote Properties Limited for a proposed new Automated Distribution Centre
at the Omega South Business Centre in Warrington; and sets out the building external
lighting strategy as aligned with local planning policy.
The proposed development will comply fully with Warrington Borough Council
Supplementary Planning Document: Environmental Protection Supplementary Planning
Document: 5 Light pollution.
1.0 Context
1.1 (5) Light Pollution
(5.1.1) What is Light Pollution?
Light pollution is the term used to describe unwanted light from artificial light sources. Light
pollution can occur as:
• Sky Glow - the orange glow visible around urban areas resulting from the scattering
of artificial light by dust particles and water droplets in the sky;
• Glare - the uncomfortable brightness of a light source when viewed against a dark
sky;
• Light Trespass - light spillage beyond the boundary of the property on which a light is
located.
(5.5.1) Proper Design and Planning
It is possible to reduce many of the negative effects of lighting through proper design and
planning. This can be achieved by using lighting only where and when necessary; using an
appropriate strength of light; and by adjusting light fittings to direct the light to where it is
required. Luminance should be appropriate to the surroundings and character of the area as
a whole. 'Over lighting' should be avoided and shields, reflectors and baffles used to help
reduce light spill to a minimum. Use specifically designed equipment that once installed,
minimises the spread of light above the horizontal should also be considered.
Omega, Warrington – External Lighting Statement
Tate Consulting 6
(5.3.1) Requirements for Specific Lighting Schemes - C. Commercial & Industrial
Developments
• Avoid use of lights simply to create a 'presence' at night;
• Concentrate lights where they are needed and establish a clear hierarchy, with
minimum lighting around the outer, perimeter of the complex.
Omega, Warrington – External Lighting Statement
Tate Consulting 7
2.0 The Development Site
2.1 This document has been prepared following consultation with the Local Planning
Officer to support the planning application for the proposed new project Omega Distribution
centre, Warrington; and sets out the External lighting strategy.
2.2 To the Southern, western and Eastern boundaries of the proposed development site,
there will be predominantly storage and distribution, commercial development buildings and
connector roads. The proposed lighting installations will have to take account of nearby
connector roads to minimize glare and minimize light spillage onto adjacent plots/buildings.
2.3 To the northern boundary of the proposed development site is the M62 motorway.
The proposed lighting installations will have to take account of the nearby motorway to
ensure that glare to oncoming motorists is eliminated.
Omega, Warrington – External Lighting Statement
Tate Consulting 8
3.0 Assessment of the Need for Lighting
3.1 Not withstanding the legislative requirements to provide adequate means of
illumination to prevent the occurrence of dangerous incidents. The external lighting is an
integral requirement of Bericote’s loss prevention policy and a requirement to prevent
vehicular and pedestrian incidences.
3.2 The three key issues that drive the requirement for artificial lighting in Bericote’s
service yards are:
• safety of vehicular and pedestrian movement;
• security of property and goods; and
• extension of working practices;
3.3 Bericote will not operate the development without external lighting because the
perceived operational risks are too high. External service yards are sometimes at their
busiest during the hours of darkness. The risk to personal injury or property damage from
vehicular or product movement is high.
3.4 The safety and loss prevention benefits of providing external lighting outweigh any
negatives for not providing external lighting.
3.5 Lighting in itself is not a problem; it only becomes a problem where it is excessive,
poorly designed or badly installed1. Additional control measures for providing artificial
external lighting have been considered, and will be incorporated into the external lighting
design, where required. Refer to control measures for a list of the control measures to be
incorporated into the lighting design.
1 Lighting in the Countryside, Towards Good Practice: 2006
Omega, Warrington – External Lighting Statement
Tate Consulting 9
4.0 Lighting Standards
4.1 The following external lighting standards and guidance documents will form the basis
for assessment of the minimum lighting design standard to be provided for the development:
British Standards:
BS 5489, 1:2003 Code of Practice for the design of road lighting – Part 1: Lighting of roads
and public amenity areas
BS EN 13201, 2:2003 Road lighting – Part 2: Performance requirements
Countryside Commission/DOE:
Lighting in the Countryside: Towards good practice
CIBSE Lighting Guides:
LG1, The Industrial Environment (1989)
LG6, The Exterior Environment (1992)
CIE Publications:
92, Guide for floodlighting (1992)
126, Guidelines for minimizing Skyglow (1997)
ILP/CIBSE:
GP09: Lighting the Environment - A guide to good urban lighting (1995)
GN01: Guidance Notes for the Reduction of Obtrusive Light (2011)
Omega, Warrington – External Lighting Statement
Tate Consulting 10
5.0 Design Standards
5.1 The whole of the Lighting shall be designed to achieve the following maintained
illuminances at floor level:
Loading docks (exc. Side of loading canopy) 20 lux
Loading canopy 20 lux
Access roadways BS 5489
Carparks 15 lux
Hardstanding areas 15 lux
Main entrances 15 lux
HGV parking areas 15 lux
Gatehouse area 20 lux
Transfer areas 20 lux
5.2 The whole of the external lighting installation shall achieve a minimum light level of 5
lux.
5.3 The uniformity ratio of the whole of the lighting installation shall be 0.30.
5.4 Floodlighting to the service yards will comprise a combination of lighting columns
around the site perimeter, at a height not to exceed 12m mounting height; and preferably be
8m high, and building mounted floodlights, mounted along the elevations at a height not to
exceed 10m; and preferably be mounted at 8m high.
5.5 The proposed external lighting installation will be designed in accordance with the
environmental zone classification E3 that is set out within ILP Guidance Notes for the
Reduction of Obtrusive Light2. The table below is an extract from the ILP guidance note and
sets out the environmental zone classifications for different environmental conditions. We
2 The Institution of Lighting Professionals (ILP) - Notes for the Reduction of Obtrusive Light
GN01:2011
Omega, Warrington – External Lighting Statement
Tate Consulting 11
have adopted the obtrusive light limitations for this external lighting installation as prescribed
for a E3 classification.
Notes:
ULR = Upward Light Ratio of the Installation - the maximum permitted percentage of
luminaire flux that goes directly into the sky.
Ev = Vertical Illuminance in Lux - measured flat on the glazing at the centre of the window.
I = Light Intensity in Candelas (cd)
L = Luminance in Candelas per Square Metre (cd/m2)
Curfew = the time after which stricter requirements (for the control of obtrusive light) will
apply - this often a condition of use of lighting applied by the local planning authority. If not
otherwise stated - 23.00hrs is suggested.
Omega, Warrington – External Lighting Statement
Tate Consulting 12
* = Permitted only from Public road lighting installations
(1) Upward Light Ratio – Some lighting schemes will require the deliberate and careful use
of upward light, e.g. ground recessed luminaires, ground mounted floodlights, festive lighting,
to which these limits cannot apply. However, care should always be taken to minimise any
upward waste light by the proper application of suitably directional luminaires and light
controlling attachments.
(2) Light Intrusion (into Windows) – These values are suggested maxima and need to take
account of existing light intrusion at the point of measurement. In the case of road lighting on
public highways where building facades are adjacent to the lit highway, these levels may not
be obtainable. In such cases where a specific complaint has been received, the Highway
Authority should endeavour to reduce the light intrusion into the window down to the post
curfew value by fitting a shield, replacing the luminaire, or by varying the lighting level.
(3) Luminaire Intensity – This applies to each luminaire in the potentially obtrusive direction,
outside of the area being lit. The figures given are for general guidance only and for some
sports lighting applications with limited mounting heights, may be difficult to achieve.
(4) Building Luminance – This should be limited to avoid over lighting, and related to the
general district brightness. In this reference building luminance is applicable to buildings
directly illuminated as a night-time feature as against the illumination of a building caused by
spill light from adjacent luminaires or luminaires fixed to the building but used to light an
adjacent area.
Omega, Warrington – External Lighting Statement
Tate Consulting 13
5.6 The CIBSE recommendation for illuminating loading bay canopies is 150 Lux.
However, Bericote have agreed to reduce this requirement for this site to 20 Lux. The
diagram below indicates the position of luminaires placed on canopies above loading bays
for safety purposes.
Diagram 1: Correct positioning of canopy loading bay lighting
Omega, Warrington – External Lighting Statement
Tate Consulting 14
6.0 Control Measures
6.1 This section describes the particular control measures that this site will incorporate to
minimize light spillage, trespass and pollution:
6.2 The external lighting shall be time controlled to ensure that the lighting installation
only operates within the specified operating hours, and to provide a facility to switch part of
the external lighting installation off during periods of low activity.
6.3 In addition, the external lighting installation shall incorporate a photo- electric cell
control, to prevent the lighting installation operating during the hours of daylight, thus
conserving energy and minimizing carbon emissions. The photo-electric cell set-point
threshold shall be set at 50 lux.
6.4 A manual override control facility will be provided for testing and maintenance
purposes only.
6.5 The whole of the external lighting installation will comply with the performance
requirements set out within the ILP guidance note for reduction of obtrusive light.
6.6 The external lighting design will not incorporate any luminaires that have aiming
angles beyond the horizontal working plane.
6.7 Measures shall be taken to eliminate light spillage onto adjacent land from luminaires
positioned on the development site.
6.8 Illuminance levels will be reduced to the absolute legal minimum to conserve energy
and to minimize light pollution.
6.9 The design shall incorporate measures to prevent light spillage onto adjacent land.
6.10 Where practically possible, all luminaires facing out of the development will be
positioned to minimize direct visual contact with the lamp source.
Omega, Warrington – External Lighting Statement
Tate Consulting 15
7.0 Design Measures for Biodiversity
Refer to the ecology report prepared by Arnott & Mann Ecology Consultants and the relevant
extracts relating to the operational mitigation of the spill of the external lighting and the
potential impact to the local habitat to the site.
Omega, Warrington – External Lighting Statement
Tate Consulting 16
Appendix A – Proposed External Lighting Isolux Plots
PROJECT ENVIRONMENTAL ADDENDUM
WASTE MANAGEMENT PLAN Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 1 of 10
SHEQ / DM/ R1C9/REV01 Oct 13
ADDENDUM
FOR
OMEGA ZONE 7 PHASE 1 SOUTH INFRASTRUCTURE WORKS
WASTE MANAGEMENT PLAN
TO ALLOW DISCHARGE OF PLANNING CONDITION 23.
C2278
For
OMEGA WARRINGTON
NAME POSITION APPROVED
(signature required) DATE
Ian Byrne Contracts Director
Ed McDonald Contracts Manager
Adam Onyett SHEQ Coordinator
Environmental Plan MUST be SIGNED OFF by at least 2 of the ABOVE BEFORE USE
Darren Fowles Project Manager
Revision Comments Date Rev 1 For Comment 07/10/13
Document Ref: R1.C9 (Revised Oct 2013)
PROJECT ENVIRONMENTAL ADDENDUM
WASTE MANAGEMENT PLAN Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 2 of 10
SHEQ / DM/ R1C9/REV01 Oct 13
AUTHORISATION AND ISSUE RECORD The following Addendum relating to waste management has been prepared in accordance with the Environmental Management System (EMS) Procedure C9 – Operational Control. I authorise the use of this plan as the main control element of the EMS on the above contract. This should be read with the ‘Electronic’ access to the Documented Environment Management System and Manual. Name Adam Onyett Signature Date 07.10.13 Job Title SHEQ Coordinator
The Project Environmental Plan is to be issued to the Project Team, listed below, who shall agree to comply with its contents at site level and maintain the necessary documentation listed within it. The working copy of the plan is to be held on site and updated when applicable.
Name of Recipient Job Title Signature Date
The Site Manager, supported by the Contracts Manager and SHEQ Coordinator, is the key person within this system and shall be responsible for the following;
Method of work undertaken on the project matches the client and regulatory authorities’ requirements and minimises the effect of our works on the environment.
Verification that approved working procedures and regular inspections are implemented and all personnel are compliant.
Ensuring that all personnel on the project are aware of their responsibilities within the EMS, arranging training where necessary (via the SHEQ Coordinator).
Holding the current version of the EMS and advising the project team of the relevant procedures and records to be kept.
PROJECT ENVIRONMENTAL ADDENDUM
WASTE MANAGEMENT PLAN Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 3 of 10
SHEQ / DM/ R1C9/REV01 Oct 13
1. DESCRIPTION OF PROJECT
The project is described in the Tender Information Pack issued by WSP and summarised in this Health & Safety Plan. This includes, but is not limited to, the following activities;
Mobilisation and Set up Trial Holes Unexploded Ordnance Survey Breaking up of Concrete Slabs if req Earthworks Installation of Sub Station Installation of Utility Services Installation of Drainage Construction of Site Access Road Traffic & Materials Management
Risk Assessments with an associated Method Statement will be produced for each of these activities prior to the commencement of any element of the works.
The Works is estimated to be a 40 week project to commence 19th August 2013.
2. RESPONSIBILITES WITHIN PROJECT TEAM
Specific environmental site responsibilities on this project are outlined in documents P4.R1.1 (for Contracts Manager) and P4.R1.2 (for Site Manager) of the OHSMS. These documents will be included in Section 1 of the Health & Safety ‘As Built’ File. Please read with the site staff structure and the roles and responsibilities for your position as designated or agreed. Agree your specific role on this project with the Contracts Manager (see Appendix C of the ‘C2278 - Health and Safety Plan’). Site notice boards must be established as the company standard for the site office and welfare unit, with all emergency details clearly displayed.
Specific Procedures and Responsibilities
Procedure
Description of Task Documents Generated Who
C9 Operational Control R1.C9 - Project Environmental Plan SC/CM C1 Legal & Other Requirements R1.C1 – Legal Requirements SC/CM C7 Communication R1.C7 – External Communication CM/SM C11 Emergency Planning R1.C11 – Emergency Plan
R2.C11 – Emergency Contacts CM/SM
C14 Legal Compliance R1.C1 – Legal Requirements SC/CM C15 Non Conformance Control R1.C15 – Non Conformance &
Corrective Action Record SC/CM/SM/G
C16 Control of Records R1.C16 – Control of Documents SM/E C17 Internal Audits R2.C17 – Internal Audit Record
R3.C17 – Site Review/Inspection SC SM
E1 Environment Aspects and Risk Assessment
R1.E1 – Significant Aspects and Impacts Summary
R2.E1 – Aspect Significance
SC/CM/SM
PROJECT ENVIRONMENTAL ADDENDUM
WASTE MANAGEMENT PLAN Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 4 of 10
SHEQ / DM/ R1C9/REV01 Oct 13
Assessment (Pollution) R3.E1 – Aspect Significance
Assessment (Resources) R4.E1 – Significant Aspects Impact
Control Sheet H&S
Standard Site Specific Environmental
Information for Site Workers/Visitors
Method Statements & Induction SM
SC - SHEQ COORDINATOR CM - CONTRACTS MANAGER SM - SITE MANAGER G – GANGER
SITE ACCESS & EGRESS
The site is situated off Burton wood Road, Westbrook; Warrington. Access will be via ext. steel gates off the roundabout on Burton wood Road. The existing gates will be kept shut and locked at all times when not in use.
STORAGE OF PLANT AND MATERIALS
3. MONITORING AND AWARENESS
3.1 The Site Management Team is required to carry out regular monitoring of the system
and will complete a detailed checklist as part of an Environmental Site Review (detailed above). It is important that all established procedures are followed and that any problems are reported immediately. The site will also be subjected to a formal internal audit to assess the operation of the EMS.
3.2 Environmental awareness will be continually promoted and further improvements
discussed by carrying out Toolbox Talks on a regular basis to ensure that all operations
PROJECT ENVIRONMENTAL ADDENDUM
WASTE MANAGEMENT PLAN Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 5 of 10
SHEQ / DM/ R1C9/REV01 Oct 13
are carried out to minimise the risk of pollution and reduce the volume of waste produced on site. All site personnel and sub-contractors will be required to sign the attendance record for these talks.
3.1 Environmental considerations will form part of the initial site induction, where the contents of this management plan will be disseminated to all personnel to ensure the awareness of its contents to all persons on site.
4. CONTROL OF WORKS
4.1 All incidents, no matter how minor, are to be reported to D. Morgan Site Manager and Client team (see organisational chart Appendix A). External parties will be contacted if required by D Morgan Site Management.
4.2 Wherever possible materials will be reused locally not only to reduce waste, but also to
reduce emissions with localised rather than long haul movement of materials. It is also intended to maximise ‘dig once, place once’ options, minimising double handling of materials (saving both noise and emissions pollution).
4.3 Any hydraulic breaking operations will be kept to a minimum and within the agreed site
working hours. These operations, wherever possible, will be undertaken away from the site boundary and local residences.
4.4 Water management will be a high priority on this project. Localised bunding and lagoons
may be required to prevent surface water adversely affecting the works. It may also be necessary to excavate ‘grips’ or ‘v’ ditches to capture water and channel towards a holding area (lagoon), preferably the permanent works swales.
4.5 Wherever possible all breakable materials on site will be processed to engineering
materials and used within the works. This will reduce the number of vehicular movements on the local roads and limit nuisance to the local community.
4.6 During the works all personnel shall remain vigilant to the potential of contaminated materials. If any materials are suspected to contain contamination (oily residues, odour or discolouration), then works will stop and samples will be taken to determine whether or not the materials are contaminated.
4.7 It is believed that asbestos containing materials may be found on site. During the clearance works all personnel shall be briefed as to the likely presence and on finding such materials they will be fenced off and a plan for dealing with them put in place. This will be to confirm that the materials contain asbestos; if notifiable then a specialist sub-contractor will be procured (if not, then trained D Morgan personnel will undertake the works); the materials will be double bagged in asbestos bags and placed in an enclosed skip for offsite disposal to a licensed site to accept asbestos waste.
4.8 In order to maintain a high standard of good practice, Omega Warrington Limited has requested that the works are registered to the Considerate Constructors Scheme (CCS) and adhere to the scheme’s code of practice. In accordance with BREEAM requirements, a CCS score between 32 and 40 will be achieved and all sections within the scheme will achieve a score more than or equal to 3. The scheme will be implemented through each sub-contractor.
PROJECT ENVIRONMENTAL ADDENDUM
WASTE MANAGEMENT PLAN Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 6 of 10
SHEQ / DM/ R1C9/REV01 Oct 13
4.9 Additionally, all office staff must ensure they adopt the D Morgan ‘print both sides policy’ wherever possible and reduce the use of paper and printer ink as far as practicable. All personnel will be required to follow the ‘switch me off’ policy when leaving a room and switch off any electrical appliances which do not need to be consuming electricity.
4.10 Every effort must be made to segregate office, canteen and packaging waste and place in the relevant receptacles for recycling. There will be separate bins for paper, cardboard, plastics, cans and general waste.
4.11 The contents of the WSP document ‘Construction Environmental Management Plan’ will be considered throughout the works and the relevant parts adhered to, with most of its requirements being addressed within this document.
4.12 Wheel Wash Facilities - To prevent mud etc. from entering the public highway a wheel wash is located 100M inside the main gate at Burton wood Road, the condition of the water will be monitored to ensure site going vehicle wheel are optimally cleaned prior to leaving site.
5. EMERGENCY PROCEDURES
5.1 Fuel/Oil (or other potentially damaging substance) Spillage
In the event of a spillage incident the following procedure must be followed;
Eliminate sources of ignition and cordon off area. Attempt to contain the spillage without risk to personal health and safety. Inform a member of the Site Supervisory Team of the approximate volume of the
spillage, location and measures taken at present. Where necessary, use plant from the locality to form bunds, excavate to Dump
Trucks or any other action which may contain/mitigate the spillage. Use spill kits from the plant to clean up or if necessary use adjacent soils. Do not allow the spillage to enter a watercourse. Site Manager to inform WSP staff and, if necessary, contact the following;
o Fire 999 o Environment Agency 0800 807060 o United Utilities 0845 746 2200
Site Manager to liaise with the above and agree measures to remediate area. Site Manager to complete an ‘Incident Report Form’ or NCR.
5.2 Surface Water Release
In the event of surface water release the following procedure must be followed;
Attempt to contain the release without risk to personal health and safety. Inform a member of the Site Supervisory Team of the approximate volume of
water released, location and measures taken at present. Where necessary/possible, use plant from the locality to form bunds or excavate
a sump (remembering to check Permit to Dig prior to breaking ground). Site Supervisory Team to call in bowser or pumps to ensure that the release is
contained in the bund/sump and does not overflow. Site Manager to inform WSP staff and, if necessary, contact the following;
o Environment Agency 0800 807060 o United Utilities 0845 746 2200
PROJECT ENVIRONMENTAL ADDENDUM
WASTE MANAGEMENT PLAN Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 7 of 10
SHEQ / DM/ R1C9/REV01 Oct 13
Site Manager to liaise with the above and agree further/improved mitigation measures.
Site Manager to complete an ‘Incident Report Form’ or NCR.
5.3 Emergency Preparedness These emergency procedures should be brought to the attention of all site personnel and, at a suitable time during the works, drills should be carried out to ensure that the emergency arrangements are effective and understood by all personnel.
6. RECYCLING AND WASTE DISPOSAL:
In line with the CL:AIRE Development Industry Code of Practice (2008) and under the objectives of the Site Waste Management Plan Regulations (England) 2008, the client and contractor shall provide a Site Waste Management Plan.
All materials will be separated/segregated as far as reasonably practicable in order to minimise the quantities of mixed materials. The waste hierarchy will be considered at all times.
The site arising materials are detailed in the tender documents and site method statements. The materials have been identified as soils, brick & concrete, vegetation, trees & hedges and general waste.
The fate of all materials will be tracked and recorded within the tables on the following pages of this Plan.
Typically; Soils Suitable engineering materials will be used for cut to fill operations. Unsuitable inert materials will be used within the landform. Brick and/or Concrete Any brick and/or concrete arising from the works will be processed (crushed) to produce engineering materials. Concrete will be crushed to 6F2 specification and brick will be used for hardcore purposes. Any tarmac arising from the works will be incorporated into the processed materials in quantities not exceeding those from the ‘Specification for Highway Works’, Series 600, Table 6/1 for the type of aggregate being produced. Vegetation, Trees & Hedges All vegetation, trees and hedges will be dealt with in the Site Clearance; chipped and cut up as necessary. Chippings will remain on site, with cuts and stumps being removed from site. General Waste All general waste will be separated into the following categories and recycled as far as possible; paper, cardboard, plastics, cans and general waste. The estimated quantities of these wastes is very low, but will be tracked throughout the works.
PROJECT ENVIRONMENTAL ADDENDUM
WASTE MANAGEMENT PLAN Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 8 of 10
SHEQ / DM/ R1C9/REV01 Oct 13
WASTE RECORDS
Date removed
Quantity (m3)
Waste type Waste Carrier Waste Management
Facility taken to
Confirmation of delivery
Waste management route (reused on/off site, recycled on/off site, recovery, landfill,
otherwise disposed)
Transfer records received and filed
PROJECT ENVIRONMENTAL ADDENDUM
WASTE MANAGEMENT PLAN Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 9 of 10
SHEQ / DM/ R1C9/REV01 Oct 13
ACTUAL QUANTITIES m3 / tonnes (delete as required) Waste Type
Waste Materials EWC Waste minimisation methods used
Volume re-used Volume recycled Volume recovered in other ways
Volume sent to landfill
on-site off-site on-site off-site
Iner
t
Concrete 17-01-01 Brick 17-01-02 Tiles / ceramics 17-01-03 Rubble (mix of concrete, brick, tiles etc)
17-01-07
Non
-haz
ardo
us
Soils 17-05-04 Metal 17-04-07 Timber 17-02-01 Plasterboard Cable & wiring 17-04-11 Office/canteen 20-01-01
(paper)
20-01-08 (canteen)
Glass 17-02-02 Plastic 17-02-03 Mixed waste
Haz
ardo
us Asbestos 17-06-05
Contaminated soil 17-05-03
Other
PROJECT ENVIRONMENTAL ADDENDUM
WASTE MANAGEMENT PLAN Omega South Zone 7 Phase 1
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 10 of 10
SHEQ / DM/ R1C9/REV01 Oct 13
WASTE QUANTITY COMPARISON
Waste type
Waste Materials EWC Estimated Quantity Actual Quantity Difference (+/-) Reason for variance (m3 / tonnes) –
delete as appropriate (m3 / tonnes) - delete
as appropriate
Iner
t
Concrete 17-01-01 Brick 17-01-02 Tiles / ceramics 17-01-03 Rubble (mix of concrete, brick, tiles etc)
17-01-07
Non
-haz
ardo
us
Soils 17-05-04 Metal 17-04-07 Timber 17-02-01 Cable & wiring 17-04-11 Office/canteen 20-01-01
(paper)
20-01-08 (canteen)
Glass 17-02-02 Plastic 17-02-03 Mixed waste
Haz
ardo
us Asbestos 17-06-05
Contaminated soil 17-05-03
Other