3

Click here to load reader

Method Statement (Roadways)

Embed Size (px)

Citation preview

Page 1: Method Statement (Roadways)

Method Statement

Method Statement for the Construction of Keadue WWTP

Roadways

Background Information

Company Details:

Company Name:

Address:

Tel.:

Fax:

e-mail:

Site Address: Contact Name:

Address:

Contact No.:

Activity Work safely and efficiently in the construction of

Keadue WWTP roadways

Safety Safety during construction:

Where undertaking any part of the work, it is the responsibilities of the applicant/Engineer to seek

competent advice to ensure the stability of excavations, superstructure, stanchion foundations, wall

foundations and to avoid any other foreseeable risk

Power Lines:

Keadue WWTP buildings shall not be constructed under or nearer than 10m to an overhead power

supply.

If advice is required, or if power lines need to be diverted, it is the applicant’s responsibility to contact,

in writing, the local ESB supervisor before construction commences and then to follow the ESB

conditions.

Site Preparation Keadue WWTP roadways should be laid in good weather when soil conditions are dry.

All topsoil and soft material shall be excavated to a minimum depth of 150mm or down to a solid

stratum.

The excavated material shall be suitably disposed of.

Where slopes are unavoidable they should be kept to a minimum and be as uniform as possible.

Provisions shall be made for drainage of the site. In the case of roads, such culverts and drains as may

be required for the stability of the roadway or the drainage of adjacent land shall be provided.

Width of Roadways All internal Keadue WWTP roadways shall be constructed 4.5m wide, with the width of roadways being

increased to 5m for the final 50m leading to the milking parlour

Foundations The foundation shall consist of 150mm of well-compacted hard-core gravel or dry filling, laid to

produce a smooth surface, with gradients corresponding closely to those required in the finished

roadway

Road Surface The roadway should be completed with about 50-75mm (2-3 inches) of a fine material

This surface layer or wearing course needs to be laid evenly and compacted. Spread it out to the

gradient formed in the foundation layer

Page 2: Method Statement (Roadways)

Method Statement

The material used should ideally have only a very low proportion of pebbles and plenty of very fine and

dusty material into which the small pebbles can embed. Any pebbles should be no bigger than 5 or

6mm. It will bind and compact better if it is laid and rolled when wet

The finished surface is impermeable to water; hence the importance of having a fall to one or both sides

of the roadway.

Camber To remove water quickly from roadways they should slope to one or both sides

A roadway that slopes to one side is easier to construct and machinery runs better on it

All roadways shall be constructed with a cross fall of between 1 in 20 and 1 in 30

Water must not be trapped at the edge of the roadway; it must be shed completely and allowed to soak

away in the soil.

The 1 in 20-30 cross fall should be enough to divert water to the sides even on ground that is from

steeply sloping ground

Plant Required

Vibrating unit

Hand Tools

PPE

Tracked Excavator

Lorry

Tractor and dump trailer

MATERIALS REQUIRED:

Well-graded hardcore

Fine dust

Bitumen

Release Agent

Reinforcing bars & mesh reinforcement

MAIN HAZARDS:

Uncontrolled use plant and equipment

Overhead power lines

Required Personal Protectice Equipment

Other Informations and Comments

Page 3: Method Statement (Roadways)

Method Statement

Items Attcahed Yes No

Shetches

Certification of Plant etc.

Programme of Work

Risk Assessments

Method Statement Briefing Record

Briefing delivered by:

Position

Date:

We (the undersigned have read and understood the attached method statement and will

comply with the specified requirements and control measures. If the work activity

changes or deviates from the originally envisaged, we will seek further advice and

request an amended method statement.

Name (Print) Signature Date