59
Method Statement for the Asbestos Removal and demolition of former student accommodation block Located at Pembridge Gardens W2 4DX Elvanite Client: The Brennan Group (De Grey Management) Document Reference No. EL/CC/RB2813 Author : CRAIG CHAPLIN COTC Date: 9 th June , 2015 This document is the copyright of Elvanite Ltd and is formatted for the exclusive use of Elvanite

Method Statement for the Elvanite Gardens Client

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Method Statement for the Elvanite Gardens Client

 

   

 

Method Statement for the 

Asbestos Removal and 

demolition of former 

student accommodation 

block Located at Pembridge 

Gardens W2 4DX   

Elvanite

 

Client:  The Brennan Group (De Grey Management) 

 

Document Reference No. 

 

 

EL/CC/RB2813 

 

Author 

 

CRAIG CHAPLIN COTC 

 

Date: 

 

 

9th June , 2015 

 

This document is the copyright of Elvanite Ltd and is formatted for the exclusive use of Elvanite 

 

 

 

 

 

 

Page 2: Method Statement for the Elvanite Gardens Client

 

 

Rev 

 

Date 

 

Status 

 

Revision Details 

 

Originator 

 

Review 

 

00 

 

9/6/2015 

 

FA 

   

Craig Chaplin 

 

Brennan 

Group 

 

01 

 

9/6/2015 

 

FA 

   

Craig Chaplin 

Brennan 

Group 

 

03 

 

9/6/2015 

 

FC 

   

Craig Chaplin 

 

Brennan 

Group 

 

04 

 

9/6/2015 

 

 

FC 

   

Craig Chaplin 

 

Brennan 

Group 

 

 

         

 

D = Draft   FI = For Information   FC = For Construction   FA = For Acceptance    P = Preliminary 

 

 

Comments: 

 

 

Signature of Originator: Craig Chaplin 

 

 

 

Page 3: Method Statement for the Elvanite Gardens Client

 

Date of Method: 

9th June 2015 

Start Date of Work: 

12th July 2015 

Estimated Date of Completion 

28th August 2015 

Principal Contractor: Brennan Construction 

(De Grey Management)  

7 De Grey Square,  

De Grey Road,  

Colchester,  

Essex,  

CO4 5YQ  

                                    

            

Demolition Contractor: Elvanite Recycling Unit 8  Haven Road Haven Quay Colchester CO2 8HT   

Site Address: Student Accommodation Block 

Pembridge Gardens 

Nottinghill 

London 

W2 4DX 

 

      

  

Asbestos Contractor: ARCS Environmental Alton, Harrow Road,  North Benfleet,  Wickford, Essex. SS12 9JW 

 Tel: 01268 725477   Fax: 01268 725460 

     

CDM Coordinator:TBC 

 

 

Position:  Manager 

 

Name:  Craig Chaplin 

 

 

Telephone:  07894 692498 

 

Position: Site Supervisor 

 

Name: Matthew Atkinson 

 

 

Telephone :  07793 132142 

 

Page 4: Method Statement for the Elvanite Gardens Client

 

  PROJECT OVERVIEW 

Elvanite recycling have been awarded the contract for the Asbestos Removal and demolition of a 3 storey 

former  student  accommodation  block  located  at  Pembridge  Gardens  Nottinghill  London.  It  is  the 

intention to totally strip back to bare wall in readiness for structural demolition. 

 

The works will be carried out two phases. 

Phase 1 – Asbestos removal and soft strip 

Phase 2 – Demolition, slab and foundation removal with crushing on site 

Structural  surveys  have  indicated  that  building  is  constructed  on  strip  footings  down  to  approx.  1.5m 

deep, with cast floors, there are service ducts located within the building and drain runs that will need to 

be identified and protected at the manhole exiting the site. 

 

Load Sheer  load bearing walls have  then been constructed  throughout,  supporting concrete  floors,  the 

roof is expected to be constructed with felt screed and straw board laid to a concrete roof. 

 

The  eastern  gable  end  is  abutted  up  to  a  listed  building,  it  has  been  previously  identified  that  the 

accommodation block  is  independent  to  the adjoining residential property,  there  is a cavity wall gap of 

approx...  150mm  between  the  two  buildings  however  due  to  very  close  proximity  of  the  residential 

property great care will be needed when dismantling  this  last section of  the accommodation block and 

the removal of any footings close to the building. 

 

A  protective  scaffold with  full  debris  netting will  be  erected  along  the western  elevation;  a working 

platform will be  installed  to the  last 4m run  to enable the careful hand demolition to be carried out as 

described within this method statement. 

 

Progressive piece meal methodology will be used at all times utilizing hydraulic attachments to minimize 

noise whilst ensuring a greater degree of control at the structure at all times, due to the close proximity of 

residential buildings and public thoroughfare dust suppression will be applied at all times through a fine 

droplet water cannon and pin point locations to the attachment to minimize any dust.  

An Asbestos  survey has been carried out,  the  survey has  indicated  significant m2 of Asbestos  textured 

coating to all areas within the building, it is the intention to run the soft strip and Asbestos removal insitu. 

 

This will require pre‐planning and coordination from both parties. 

 

It will be the intention to soft strip in a top down sequence enabling the Asbestos removal to run in situ 

with  soft  strip  operations,  due  to Asbestos  being  located  to  the majority  of  all  ceilings  no  fixtures  or 

fittings will be removed from the ceiling areas, this will be carried out by the asbestos operatives. 

 

Site access is very tight and pre planning of all logistical movements will be required, the excavators will 

need to be delivered on a drop bed enabling side dismount, the crusher will need to be delivered out of 

peak hours with the necessity for road to be boarded out. 

Page 5: Method Statement for the Elvanite Gardens Client

 Duties of Site Management 

Operations  Director  –  Site  Operations  and  logistics,  site  visit  as  required/approval  of  changes  to 

Method Statement. 

Health &  Safety Advisor  – H&S Management,  Site Audits, Method  Statement  Checking/Approval  of 

changes to Method Statement. 

Contracts Manager  –  Pre‐start  paperwork/notices/meetings,  liaising  with  statutory  authorities,  Co‐ordinating Method Statements/Risk Assessments, progress meetings, completion of site H&S  Duties of Site Management 

Operations  Director  –  Site  Operations  and  logistics,  site  visit  as  required/approval  of  changes  to 

Method Statement. 

Health &  Safety Advisor  – H&S Management,  Site Audits, Method  Statement  Checking/Approval  of 

changes to Method Statement. 

 The Health & Safety at Work etc Act 1974 is a UK act of parliament that defines the fundamental structure and authority for the encouragement, regulation and enforcement of workplace, health, safety and welfare in the United Kingdom. Cascading from this important piece of legislation are the workplace regulations, codes of practice and industry guidance. Most notably and of direct concern for work within a demolition environment are the following statutory regulations. 

 

The Construction (Design and Management) Regulations 2015 

The Provision and Use of Work Equipment Regulations 1998 (PUWER) 

The Lifting Operations, Lifting Equipment Regulations 1998 (LOLER) 

The Workplace (Health, Safety & Welfare) Regulations 1992 

The Management of Health, Safety & Welfare Regulations 1999 (MHSWR) 

Personal Protective Equipment Regulations 1992 (PPE) 

The Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 1995 (RIDDOR) 

The Supply of Machinery (Safety) Regulations 2008  The Control of Substances Hazardous to Health Regulations 2002 (COSHH) 

Health and safety at work act 1974 etc. 1974 

Health and Safety (consultation with employees) Regulations 1999 

Health and Safety (Enforcing Authority) Regulations 1989 

Health and Safety (First aid Regulations) 1981 

Health and Safety (Information for Employees) Regulations 1989 

Health and Safety (Miscellaneous provisions) Regulations 1992 

Health and Safety (Safety signs and signals) Regulations 1992 

Health and Safety (Training for Employment) Regulations 1990            

Page 6: Method Statement for the Elvanite Gardens Client

 

  

Health and Safety (Offences) Act 2008  

Workplace (Health and Safety and Welfare) Regulations 1992 

Confined spaces Regulations 1997 

Control of Asbestos Regulations 2012 

Control of lead at work Regulations 2002 

Control of Major Accident Hazards 1999 

Control of Noise at Work Regulations 2005 

Working at Height Regulations 2005 

Low voltage Electrical Equipment (Safety) Regulations 

Manual Handling Operations 1992 

Control of Vibration at Work Regulations 2005 

Electricity at Work Regulations 1989 

Corporate manslaughter and Corporate Homicide Act 2007  The  above  list  contains  a  number  of  legal  requirements  for  any  employer  to  implement,  and manage,  at  all  times.  Consultation,  training  and  available  information  is  of  paramount importance  for  any  employer,  and  employee,  to  receive  and  adhere  to.    It  is  also  vital  that employers/employees respect these regulations and legislative requirements.    ENVIRONMENTAL LEGISLATION 

The purpose of  this document  is  to outline  the  framework and measures by which  the Company controls environmental issues for which we have responsibility. It has been developed to provide direction to specific procedures that control activities that have, or have the potential to have, an environmental impact. It also addresses the roles, responsibilities and authorities of the Project Management Team who ensure  that the policy  is carried out effectively the Environmental Legislation applicable  to  the works required for the Demolition process of the Project at Nottinghill are listed below.   

Collection and Disposal of Waste Regulations 1988(amended 1988) 

Control of Pollution Act 1974 

Control of Pollution (Amendment) Act 1989 

Control of Pollution (Oil Storage England) Regulations 2001 

Environment Act 1992 

Controlled Waste Regulations 1992(amended 1993) 

Site Waste Management Regulations 2008 

Waste Electrical and Electronic Equipment Regulations 2006 

Waste Management (Miscellaneous Provisions) Regulations 1997 

Waste management Regulations 1996 

Waste Regulations 2011 (England and wales) 

Environment Protection Act 1990 

Environmental act 1995 

Environmental Protection (Duty of Care) Regulations 1991 

Pollution Prevention and Control Act 1999 

Pollution Prevention and Control Regulations 2000 

Page 7: Method Statement for the Elvanite Gardens Client

  Hazardous Waste Regulations 2005 

List of Wastes Regulations 2005 

Noise and statutory Nuisance Act 1993  

Clean Air Act 1993     Site Health, Safety & Environmental Objectives Elvanite Recycling have established a safety strategy for the works with a target of zero harm of any type and  in addition, we will set a benchmark standard  for the monitoring of health and safety standards of this project by means of a system of monitoring of accident/incident frequency rates, using both active and reactive monitoring procedures prior to the commencement of the works.  Any contractors working on the site will be expected to achieve a similar minimum standard and provide outline procedures  for inspecting and auditing during the project  

Zero RIDDOR reportable accidents or incidents 

Zero enforcement notices from the Health & Safety Executive 

Zero environmental impacts and enforcement notices from the Environmental Agency 

All Elvanite Recycling operatives are required to attend site specific health & safety inductions 

All Elvanite Recycling operatives working on this project hold current CSCS/CCDO cards and have the relevant training to enable them to complete their job in a safe manner 

All health and safety related incidents will be fully investigated and the relevant reports produced for agreement/compliance from all parties. 

Full commitment to BBCL Zero Harm policy  

Meetings Elvanite  Recycling  will  co‐ordinate  and  liaise  with  any  sub‐contractors  via  inductions,  toolbox  talks, informal  discussions  and  weekly  site  meetings.    The  Client  Brennan  Construction  will  be  informed regarding any activities that are deemed to be a threat to the health and safety of the project.  Monitoring & Review of Site H&S Performance The Risk Assessments and Method Statements have been carried out by CRAIG CHAPLIN and approved by a member of the Institute of Demolition Engineers (IDE)  

Consultation with Operatives 

Upon award of the contract, a Site Management hierarchy will be identitied in the form of a Site specific 

Organogram and approperiate resources will be allocated to the contract.   As planning  is a vital part of 

the  demolition  process,  the  senior  staff  team will  visit  the  site  and  evaluate  the  complexities  of  the 

contract.  Before any site operations commence all parties will sign the Method Statement and agree the 

demolition and Stripout  sequence  through out  the  contract.   All operatives will be made aware of  the 

demolition  and  stripout  sequence  by means  of  pre‐start  commencement workshops  and  site  specific 

Toolbox Talks, which will be carried out and signed off by all operatives.  A brief pictorial representation of 

the sequence of works will be demonstrated  to all operatives at site  inductions and  in addition, will be 

posted within the Brennan Construction site cabins for the use of new site employees and visitors alike.  

All employees/visitors will be inducted and logged within the site Method Statement.   

End of day checklists will be undertaken by Elvanite’s Site Supervisor and all Hot Works ceased one hour 

prior to the end of shifts as recommended by the RRFSO 2005 & HSE Fire Safety Risk Assessment checklist 

(FSRA)‐5‐step‐checklist. 

 

Page 8: Method Statement for the Elvanite Gardens Client

  

Management Liaison 

We  intend  to  instruct  experienced  and  recognised  personnel  in  the  field  of  demolition  and  stripout 

operations  and health and safety.  These will assist the demolition engineering and remediation process.  

We  also  intend  to  produce  an  easy  and  efficient managment  and  communication  channel  between 

ourselves and the Client.  A specific Quantity Surveyor will be appointed to assist both ourselvbes and the 

Client with commercial aspects of the contract.   This  form of communication will be greatly assisted by 

the fact that the QS will spend at least one day per week on site and is based less than 90mins away from 

the contract. 

As  previously  demonstrated,  Elvanite  Recycling  have  always  given  a  speedy  response  to  queries  and 

within our CV site file, the Client will have all office mobile and email addresses. 

With  the addition of Health and Safety audits, demolition audits and structural engineers  input, a  tight 

procedure  incorportated within our Quality Assurance and Quality Management Systems.   Should there 

be any queries arising which were not identified at tender or interview stage, we will communicate to you 

in a  timely and professional manner and will not proceed with any work until a written agreement has 

been sought. 

 

 

1.   DESCRIPTION OF WORKS 

       Establish a secure Hoarding/Herras perimeter to the boundry Brennan Construction 

       Place appropriate warning signs around site perimeter Brennan Construction 

       Locate any remaining live services and record on site drawings 

       Ensure termination of redundant services with relevant certification available on‐site 

       Soft Stripping and Demolition to all pre identified floors to drawings including suspended   

       Ceilings, false partion walls, skirtings, M&E fixtures and fittings, floor coverings and   

       Redundant furniture all as indicated on the drawings.  

       Non Licensed Asbestso Removal to all parts of the building as indicated on the R&D Survey 

       Scaffold Erection nand protection to East elevation 

       Mechanical Demolition to main super structure 

       Back propping if required  

       Full dust suppression at all times 

       Careful hand demolition to rear elevation where buildings are within parti wall agreement.  

       Waste segregation and disposal 

       Slab and foundation removal 

       Crushing of all materials on site for future re‐use on site within the pile mat. 

       Careful Demolition of boundary wall to enable new hoarding to be erected 

Site  establishment/cabins  and  welfare  will  be  provided  by  Brennan  Construction  to  be 

intially located and relocated to suite site requirments as the work activities progress. 

 

    

  

Page 9: Method Statement for the Elvanite Gardens Client

  

2. SEQUENCE OF DEMOLITION OPERATIONS  

 1. ERECT HOARDING/FENCING & SIGNAGE BY BRENNAN CONSTRUCTION 2. ENSURE SERVICE DISCONNECTIONS 3. PRE  IDENTIFY  AREAS  OF  BUILDING/FLOORS  TO  BE  STRIPPED  OF  NON  LIOCENSED 

ASBESTOS 4. COMMENCE  SOFT  STRIP  TO  ALL  INTERNAL  WASTE  STREAMS  IN  ROOM  BY  ROOM 

SEQUENCE WORKING IN TOP DOWN METHODOLOGY 5. FOLLOW IN SEQUENCE ASBESTOS REMOVAL 6. CAREFUL DEMOLITION TO EXISTING SITE BOUNDRY WALL 7. PRE IDENTIFY LOCATION OF BINS FOR LOADING 8. COMPLETE SOFT STRIP AND ASBESTSOS REMOVAL 9. ERECT SCAFFOLD PROTECTION 10. COMMENCE MECHANICAL DEMOLITION IN PROGRESSIVE METHODOLOGY 11. CAREFUL HAND DEMOLITION AND ROBOTIC DEMOLITION TO EASTERN GABLE END WITH 

TEMPOARY PROPPING IF REQUIRED. 12. STOCKPILE ARISINGS IN READINESS FOR CRUSHING 13. BREAK OUT CONCRETE SLAB AND FOUNDATIONS 14. CRUSH ALL MATERIAL TO CLIENTS SPECIFICATION 15. LEAVE SITE CLEAN,TIDY AND LEVEL 

  

 2. Logistical Identification   The Following Resources Will Be Required   

 LABOUR 

 1 X Contracts Manager 

 1 X Site supervisor 

 5 x Site operative’s 

 5 X Asbestos operatives 

 2 X Machine operatives 

  

 

 PLANT & EQUIPMENT 

       Multi Processing Attachments 

       Fire Extinguishers 

       1 x Lorry Driver 

              2 X Scaffold towers 

       Small Hand tools/Crobars/Hammers etc 

                   110v demolition tools/Breakers/Rip saws etc 

       110v extension leads 

                   110v transformer 

 

 

 

Page 10: Method Statement for the Elvanite Gardens Client

 

       23t Demolition spec excavtor 

                  13t Demolition Spec excavator 

      Kleeman Concrete Crusher 

                  Multi processing attachements 

                  Dust Suppression unit 

 

 

 

 

                   PPE REQUIREMENTS (minimum) 

                   Steel toe cap boots 

                   Hard Hat, Hi Viz,Gloves 

                   Safety Glasses 

                   Ear defenders 

                   Dust Masks (fp3) 

 

 

 

3. ACCESS TO SITE (HSE guidance notes HSG 136 Workplace Transport Safety) 

 

The  emegency  plan  will  managed  and  implemented    as  suggested  by  current  industry  best 

practice HSE HSG 136 Work Place Tansport Safety. 

 

Access /Egress point to the site will be via the designated entrance gate off Pembridge Gardens 

London W2 4DX, this is to be installed on completion of boundry wall being carefully demolished. 

Due  to  the  continuous  changes on  site, an on‐site  traffic management plan will be devised by 

Brennan Construction site manager, the site will be very tight for  logistical movements and  it  is 

anticipated  that any  lorry movements will need  to be pre organised and  reversed off  the main 

road,  this will  be  ammended &  relayed  to  all  site  operatives  throughout  the  duration  of  the 

contract as the logistical operations will continuely change throughout the projects entirety.  

 

A designated access/egress gate will be  installed by Brennan Construction with a  fully qualified 

and certified vehicle marshall who will  take  responsibility of deliveries and vehicles  leaving  the 

site. During a pre site visit we have identified acess and egress will be required during the hours of 

07.30.00‐16.00 daily. 

It  is Elvanite  intention  to undertake consultaion as part of a pre‐commencemment objective  to 

remain compliant to the Considerate Constructors Scheme to the  local populous of  its guises by 

inviting  reidents  and  buisness  owners  to  co‐ordinated  discussions  to  be  held  within  the  the 

confines of the Brennan site office to address any concerns with any of the sites activities. 

Furthermore,Elvanites  accreditation  of  ISO  14001:2004  requires  innovative  techniques  to  be 

employed in regard to minimising the environmental impact of cradle to grave, by considering the 

locale and the ‘4R’s and the D as part of Elvanite’s continuing contribution towards sustainability 

of  resources  in  all  of  its merits  and  compliance with  current  best  practice  in  regard  to WRAP 

protocol.  

Page 11: Method Statement for the Elvanite Gardens Client

  

Pedestrian Management (HSE Guidelin HSG 151 Protection of the Public) 

Where any of the sites operations require diversion of pedestrians along  Pembridge Road it will be the 

responsibility of Brennan Construction to accommodate these works, these shall be undertaken via safe 

accessible means  and  implemented  through  display  of  signage  and  installation  and maintenance  of 

suitable  barriers  as  instructed  by  Brennan  Construction.    All  pedestrian  diversion  routes  will 

accommodate DDA requirements where reasonably practicable. A vehicle marshall will monitor traffic 

movement at all times.   

 

 

 

Site Parking/Traffic Management 

Site parking will be strictly within the site confines provided by Brennan Construction, utilising areas a 

safe  distance  from  the  works  with  clearly  defined  segregtaed  pedestrian  access  and  site  traffic 

management routes using suitable barriers and adequate signage. All access to the site will be via the 

main entrance off Pembridge Gardens, at no point will any site operations impare emergency routes to 

the site all any exsiting surround buisness or  residential properties or  the busy  inter‐juction at Forest  

Road.  To ensure that vehicles are restricted to a minimum, operatives will travel to site in a mini‐bus, or 

directly by tube thus minimising site traffic. 

Access will be maintaintained at all times for emergency vehicles to gain access to the building located 

within the college grounds and any surrounding college properties/buisnesses. 

A trained vehicle marshall will have responsibility to control all site traffic through any access and egress 

gates. Two way radio communication will be available for all logistical operations on site. 

 

 

Site Deliveries/Collections 

All  site movements will be  controlled  by  the  Elvanite  Site  Supervisor Matthew Atkinson,  all  relevant 

certification will be  checked and hire  companies will be vetted by our  subcontract quality process  to 

ensure compliance. 

The  unloading  and  loading  of  Elvanite  plant  and  equipment will  be  carried  out  by  Elvanite  trained 

employees, any hired equipment brought to site  i.e. generators/rollers will be unloaded/loaded by the 

hire company.  Familiarisation training documentation to be issued to the client. 

 

Elvanite will manage all deliveries and collections from their area and a Vehical Marshall will be in use at 

all  times  to control  the  traffic.   Vehicle Marshalls are  to wear PPE  in  line with Brennan Constructions 

Health & Safety requirements. 

 

Elvanite will ensure that any hired materials or hire companies have been given the site paramenters in 

relation to vehicle movements and times of operation.   Due to the confines and locale of the contract, 

we  intend  to  limit  vehicle movements  between  08.00  and  16.30.    This  will  reduce  any  impact  on 

prescribed rush hour traffic and school routes. 

 

 

 

 

Page 12: Method Statement for the Elvanite Gardens Client

  

4. SERVICE DISCONNECTIONS 

It  is  the  responsibility  of  the  client  Brennan  Construction  to  ensure  that  any  relevant  service 

disconnections  including heating, BT, gas, electricity and water  to  the area within  the  scope of 

works  have  been  disconnected  and  severed  and  that  Elvanite  are  issued  with  written 

confirmation of disconnections. 

 

Elvanite will be provided with a services removal permit prior to any Stripout works commencing 

and the building sign off document from the client. 

 

Each area of the Building along with any areas of electrical equipment that is to be removed will 

be checked prior and permits  issued prior  to works commencing.;  if any remaining  live services 

are identified, Elvanite will inform Brennan Construction site representative and take the relevant 

precautions necessary to ensure safety to operatives and the public.    In particular regard to the 

locations  of  any  services  identified  during  the  course  of  the works  that  are  not  identified  on 

current copies of utility service mappings will be recorded as best as reasonably practicable by the 

Site Supervisor. 

 

If an unmarked service is found, work will be stopped immediately and the near miss reported to 

the client. 

 

A  Pre‐start  Survey  will  be  carried  out  using  the  information  available  by  the  client  Brennan 

Construction to assess and locate all terminated services which are within the proposed scope of 

works.  The findings of these surveys will be identified and drawn onto a site service map and will 

be  issued  to  all  staff  and operatives.    The  findings will be  conveyed back  to  the management 

liaison  and  also  the  clients  representative.    Protection  of  services will  be  undertaken  using  a 

variety  of  methods  indcluding  ,  physical  barriers,  signage,  location  drawings  and  computer 

generated mapping.                         

 

NOTE  

NO DEMOLITION WORKS WORKS WILL TAKE PLACE BEFORE THE NECESSARY ISOLATIONS HAVE 

BEEN CARRIED OUT WITH CERTIFICATION ISSUED. 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 13: Method Statement for the Elvanite Gardens Client

 

  

5. ENVIRONMENTAL  ISSUES  (Environmental  Protection  Act  1990  and  the  Duty  of  Care 

Regulations 2011, Section 34) 

         

   

 

All Environmental controls will be implemented to satisfy Brennan Construction, the Environment 

Agency and the HSE requirements. 

 

The  location of any  fuel bowser must not be within 10m of a watercourse or 50m of a well or 

borehole. In addition the bowser would ideally be located upon an impermeable surface such as 

concrete. 

In any event a suitable spill kit of adequate capacity shall be  located adjacent to any and all fuel 

bowsers as suggested by current industry best practice.   

 

All Elvanite fuel bunds are double bunded to 110% of the inner capacity of the tank and are fitted 

with  padlocks  which  will  be  kept  locked  at  all  times  except  during  the  refuelling  process.  

Emergency spill kits will be positioned adjacent to the bowsers and any accidental spillages dealt 

with  by  the  plant  operative  concerned,  a  copy  of  the  ‘Spill  Response  Procedure’  is  contained 

within the site file which contains details of how the used spill kit will be disposed of and where 

to.  A copy of the Elvanite Spill Response Procedure’ will be supplied to Brennan Construction on 

arrival at site.  A copy of the Elvanite organogram for environmental issued has been supplied to 

the client. 

 

Fuel bowsers will be stored away  from water courses at all  times.   Gloves and all other PPE as 

identified within the refuelling risk assessment will be worn by operatives refuelling the plant and 

the company’s ‘no smoking’ policy enforced at all times (refer to COSHH Risk Assessment, diesel 

fuel).  All Elvanite COSHH assessments are in the site file and a copy of the COSHH assessment for 

the diesel will be provided to the client on arrival at site. 

 

Elvanite’s  operatives  will  only  park  plant  and  re‐fuel  in  the  designated  area  which  has  been 

agreed as being the site compound area. 

 

 

 

 

 

 

 

 

 

 

 

Page 14: Method Statement for the Elvanite Gardens Client

  

Dust  suppression measures will be  implemented during dry periods and as  required during  the 

sites  activities  as  deemed  necessarry  by  the  site  supervisor,  considerations will  be  taken  into 

account for wind direction, material composition and general site conditions.. 

 

All surplus/waste materials from the sites operations will be re‐cycled where practicable. 

.  

A copy of the Elvanite’s organogram for environmental issues will be supplied to the client. 

 

All materials that are generated from the sites activities that are not required for re‐use will be 

suitably segregated and stored in appropriate 20 yard skips for transporation off site to registered 

waste management  facilities.: 

 

All brickwork/blockwork and concrete from the demolition and stripout  process will be removed 

from site to a registered waste management facility. 

All steelwork and reinforcement/metals will be salvaged and recycled 

Hazardous  materials  including  asbestos  will  be  stored  in  lockable  containers    Removal  to  a 

licensed recycling facility will be arranged where necessary and the appropriate duty of care notes 

will be  stored  in  the  site  file with  copies  issued  to  the  client on  completion of  sections of  the 

works  in accordance with  the  requirements of  the Environmental Protection Act 1990 and  the 

Duty of Care Regulations 2011, Section 34. 

ALL works will run in conjuction with the  2 Phase  Method Statement. 

 

 

Dust Suppression for works covered by this method statement

Cleaning  of  construction  vehicles  prior  to  leaving  the  confines  of  the  site  by means  of wheel 

washing/steam cleaning. 

A materials management plan will be prepared to any excavation to regulate the treatment and 

movement of contaminated soils to facilitate the prevention of cross contamination. 

Where  practicable,  materials  generated  on  site  will  be  subjected  to  the  clients 

requirements/specifications  and  re‐used  or  recycled  for  the  backfilling  phase  and  pile  mat 

engineering works, all materials that are generated from the sites activities that are not required 

for re‐use will be suitably segregated and stored in appropriate 40 yard skips for transporation off 

site to registered waste management  facilities.: 

All surplus/waste materials from the sites operations will be re‐cycled where practicable. 

All  imported materials  to  site must meet  the  criteria  as  specified with  the  relevant  laboratory 

analyst test reports to ensure compliance to the remediation stratergy.  

A copy of the Elvanite’s organogram for environmental issues will be supplied to the client.     

The  location of  the  stockpile area and  segregated  skip  location has been considered  in  specific   

regard  to  the specific site  location providing a natural means of screening offered by  the reduced  level 

relative to the works as well as  it providing a  level of dust screening thus the noise at work regulations 

require that no person shall be exposed to noise levels which are likely to lead to long term hearing loss. 

 

Page 15: Method Statement for the Elvanite Gardens Client

 6. Noise 

Prior  to any works commencing,  it  is our  intention  for  the contacts manager Craig Chaplin  to visit site, 

who will undertake a number of external readings from the hoarding line of the contract.  These readings 

will provide background noise monitoring and the levels we must achieve to prevent any noise pollution 

above the agreed parameters. 

 

All plant and machinery are fitted with the  latest attachments and are designed to reach no more than 

the maximum upper exposure limits.  As noise dissipates over a linear meterage. 

Lower exposure action level 80db(A) 

Upper exposure action level 85db(A) 

 

A  noise  survey will  be  carried  out  on  site  by  the  Health  and  Safety Manager/Site  Supervisor, who  is 

familiar with the recording equipment and trained in its use, to determine suitable hearing protection to 

be  worn  and  noise  levels  at  the  boundaries  prior  to  and  during  the  demoltion  works.    All  Elvanite 

Supervisors have been  issued with, and have received training  in, the use of a Maplin Electronics Sound 

Level Meter, which measures sound outputs to an accuracy of +/‐ 3.5db.  These instruments will be used 

to record noise levels on a daily basis to ensure that we are within agreed levels. 

 

Copies of the noise survey and records will be provided to the client and the trust. 

 

All  Elvanite personnel will wear hard hat mounted  ear protectors where practicable or disposable  ear 

plugs. 

 

Refer to Section 10 below in relation to dust monitoring and suppression measures 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 16: Method Statement for the Elvanite Gardens Client

 7. SAFETY REGULATIONS 

All work where practicable will be carried out in accordance with BS 6187.2014 and the guidelines 

set out by the CITB’s current issue of GE700. 

 

Before any work commences on the site, all operatives will be given a safety induction course by 

the  Site  Foreman  and  by  Brennan  Construction  Site Manager  and  will  be  required  to  sign  a 

‘Confirmation  of  Methodology’  sheet  (see  appendix  1),  which  means  they  have  read  and 

understood  this  Method  Statement  and  Risk  Assessments.    If  there  is  a  requirement  for 

subcontractors, health and safety information will be relayed to operatives during their induction. 

 

Weekly tool box talks will be carried out and the content and list of attendees will be supplied to 

the client on the day of completion of the talk. 

 

A  copy  of  Elvanit’s  ‘Zero Harm’  action  plan will  be  forwarded  to  the  clients  for  their  records 

following award of the contract.  A copy of the weekly safety audits will be provided to the client 

on the day of the audit. 

 

The Elvanite Supervisor will undertake morning briefings to all of the team and members of the 

client site team are free to attend these briefings. 

 

Elvanite will not be employing  any  apprentices or  young persons on  this project  and  a  ‘buddy 

system’ of working will not, therefore, be required. 

 

8. WELFARE AND SITE SERVICES (HASAWA 1974 etc. and the MHSW Regs 1999) 

All  site  facilities  and  services will  be  provided  by  Brennan  Construction  for  the  period  of  the 

Asbestsos removal and demolition operations, these will be used by site operatives and visitors 

alike. 

Elvanite will ensure that any facilities used will be kept in a clean condition. 

Hygiene is of high importance in ensuring the welfare of operatives.  Therefore and suggetsed by 

CDM 2007 REGULATIONS 

 barrier creams and hand washing facilities will be available at all times. 

A designated clean area will be provided for the purposes of eating and drinking with running hot 

water, separate drying room and adequate facilities to warm food and to dry clothes. 

A designated smoking area will be implemented on site by the site supervisor. 

 

 

 

 

 

 

 

 

 

 

Page 17: Method Statement for the Elvanite Gardens Client

 9. SITE SECURITY AND SAFETY 

The site will be hoarded to all boundrys in its entirety by Brennan construction prior to the main 

structural demolition commencing, however part of the 1st phase works  is to carefully demolish 

the boundry wall that runs along Pembridge Road. It is paramount that when a section of wall is 

removed a suitable and suffcient security fence is installed immediately with appropriate signage 

to minimise any risk of children or the general public being able to gain access at any point.  

Specific work areas within  the  floors  that will undertake  the  softstrip operations will be clearly 

defined using heras fence panel fencing as erected by Elvanite Recycling depending on where the 

work is situated.  Works within any high risk areas that require demarcation will be separated by a 

suitable  barrier  system.   Operatives will  receive  a  site‐specific  induction  and  toolbox  talks  on 

relevant safety issues that may arise on site.  The Site Supervisor will carry these out and details 

of the talks will be recroded. 

Designated parking  areas will be discussed  and  approved by  the Brennan Constrcution 

site manager and the contracts manager Craig Chaplin prior to works commencing.   The 

identified areas will not impede on any site activities. 

Regular  liaison between relevant parties will be co‐ordinated on a daily basis by the Site 

Foreman.  If a weekly meeting is required, the Contract Manager Craig Chaplin will attend 

and the details will be recorded.  Any relevant paperwork/information will be collated by 

the  Site  Foreman  and  distributed  to  all  parties  (where  required),  copies  of  this 

information will be stored in a site file which is returned to Head Office at the end of the 

project. 

On arrival to site, all operatives will sign in on the Elvanite daily log and on departure, sign 

out. 

As  a minimum,  all  operatives must wear  the  following  PPE, Hi‐Viz Vest,  hardhat,  steel 

toecap and mid sole boots, gloves and safety glasses.  All other job specific PPE and safety 

equipment will be provided on a task basis. 

Areas of Demolition will be  left  secure during working hours and each evening prior  to 

leaving site. 

No  unauthorised  persons will  be  allowed within  the  demolition  areas  unless  requests 

have been made from the client to the Elvanite Site Foreman and visitors are supervised 

and escorted at all times. 

Elvanite operatives on site have the right to participate, be consulted and represented on 

health  and  safety  issues.    Craig  Chaplin  holds  the  position  of  Elvanite  Safety 

representative. 

Should there be a need to make any amendments to the methodology the Site Foreman 

can hand write the changes onto the Method Statement amendment sheet attached, he 

will contact Craig Chaplin for approval.  The client will be consulted on all matters relating 

to the change in method of work. 

Elvanite have established a safety strategy for the works with a target of zero accidents of 

any type and in additrion, we will set a benchmark standard for the monitoring of health 

and  safety  standards  on  this  project  by  means  of  a  system  of  monitoring  of 

accident/incident frequency rates, using both active and reactive monitoring procedures 

prior to the commencement of the works.  

 

 

Page 18: Method Statement for the Elvanite Gardens Client

 

 

  

Elvanite have established a safety strategy for the works with a target of zero accidents of 

any type and in additrion, we will set a benchmark standard for the monitoring of health 

and  safety  standards  on  this  project  by  means  of  a  system  of  monitoring  of 

accident/incident frequency rates, using both active and reactive monitoring procedures 

prior to the commencement of the works.  Any contractors working on the site will be  

expected  to  achieve  a  similar minimum  standard  and  provide  outline  procedures  for 

inspecting and auditing during the project.   

Subcontractors are required to complete a pre‐qualification questionnaire; if they do not 

meet  the Elvanite  criteria,  they will not be offered work on  this project.   A  copy of an 

example subcontractor questionnaire is available from the Head Office. 

Site Foremen are responsible for carrying out a tool box talk, set out in the GE700 and the 

NDTG tool box talks. 

Elvanite plant  is serviced on a regular basis and the equipment  is checked by the driver 

every morning prior to works commencing and the check recorded on the Elvanite driver 

check report form, a copy of which will be supplied to the client on request.  Should any 

macihinery require a site  repair, a member of our service  team will attend site  to carry 

out the works.   Copies of machine certificates are held by the Site Supervisor or can be 

requested from Head Office.  The Elvanite Plant Manager is Brett Hampson. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 19: Method Statement for the Elvanite Gardens Client

 

  

10. FIRE PROCEDURES (RRFSO 2005 AND THE ‘FSRA‐5‐Step‐Risk Assessment’) 

Elvanite will be  issued a detailed  fire plan by Brennan Construction which  indicates access,  fire 

escapes,  fire  alarms, muster  points,  etc.    This  plan  is  subject  to  regular  review  as  the  project 

progresses and Elvanite will be issued any future amendments. 

For  purposes  of  this  plan,  any  person  discovering  a  fire  should  follow  specific  emergency 

procedures laid down by Brennan Construction & Elvanite, this will be discussed prior to works 

commencing and during inductions. 

The following actions should be carried out: 

 

1. Raise the alarm 

2. Site Manager to notify the client 

3. Site Manager to ring the emergency services – 999 

4. If trained and can do so safely, tackle the fire using the fire appliances provided 

5. Leave the site via the nearest available exit 

6. Vehicle Marshalls will inform plant operative of the emergency procedure to be adopted 

7. Report  to  the designated  assembly point  (this will be detailed on  the  site plan  and  clearly 

displayed in the welfare facilities and in the building). 

 

Elvanite will provide water  fire extinguishers during  the demolition process, as  soft  stripping produces 

wood and paper.  Foam fire extinguishers will be provided  at the fuel bowser;  other extinguishers  will be 

position at various points around the perimater of the buildings, as agreed with the client and only used 

by trained operatives in the event of an emergancy. 

 

SMOKING is only allowed in designated areas on site. 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 20: Method Statement for the Elvanite Gardens Client

  

11. FIRST AID 

In the event of an accident on site, details will be recorded on the accident form within the site 

file and telephoned through to Head Office and the client, if the accident is severe.  The first aider  

who  is  identified by  a  green  cross on his helmet, will  ensure  that  the  emergency  services  are            

notified immediately and the casualty receives immediate medical attention. 

In the event of the accident being reportable under RIDDOR, then the office will complete F2508 

and forward it to the relevant authorities.  A fully qualified first aider will be present on site at all 

times  and  the  first  aid  facilities will  be  located  in  the  site  office.    This  is  in  line with  current 

legislation.   All accidents will be reported  to and  investiaged by  the client and Elvanite’s Health 

and Safety Representative.  Firs aid kit(s) will be kept in the welfare unit. 

The accident book is located within the main Elvanite site office. 

A  location  plan,  complete with  clear  directions  and map  showing  the  route  to  the  local  A&E 

Hospital will also be displayed  in  the Elvanite site welfare office and  first aid points around  the 

site.  Elvanite  Recyclings  first  aider  is  Matthew  Atkinson. 

    

 

NEAREST HOSPITAL DETAILS:   St Marys Hospital, Praed Street, London, W2 1NY – 020 3312 6666

         

 

 

 

 

 

Page 21: Method Statement for the Elvanite Gardens Client

  

Note:  Should there be a requirement for an emergency rescue, a copy of the emergency vehicle 

access routes “Blue Route” will be displayed within Brennan Constructions/ Elvanite’s site office 

and welfare cabins.   Elvanite will appoint the Site Foreman and designated Operative to contact 

the  emergency  services  in  the  event  of  an  uncontrolled  incident,  await  arrival  of  emergency 

services,  guide  them  to  the  scene  and  form  a perimeter  to  zone off  the  area etc.   Emergency 

rescue details, muster points and designated operatives will be discussed and identified at the site 

induction. 

 

A copy of the Risk Assessment for uncontrolled collapse will be provided to the client on arrival at 

site.   This emergency plan will be monitored and reviewd/updated by Elvanite and the client as 

required on a monthly basis or as the site’s requirements change. 

12. TRAINING 

 

100% of  Elvanite’s plant  operators  are  in  receipt  of  their CPCS/CSCS/CCDO  card  in  association 

with the CITB card system. 

 

A copy of all CSCS/CPCS/CCDO cards will be taken to the site induction and they can also be found 

in the Elvanite Head Office, where copies are held.  Copies of all competencies shall be provided 

to the client on award of the Contract. 

 

Regarding  underpinning  knowledge,  all  operatives  have  also  completed  their  NVQ  level  2  in 

specialised plant operation. 

 

Demolition  operatives  are  also  accredited  for  the  Certification  of  Competence  of  Demolition 

Operatives  (CCDO) which  consists of Demolition Operative 1, Demolition Operative 2,  Topman 

and Demolition Supervisor.  All operatives have NVQ and Craig Chaplin carries the accreditation of 

CCDO Gold card as well as a NEBOSH GENERAL CERTIFICATE, WAMITAB Level 4 Diploma  in  the 

management, Handling, Treatment and Disposal of Hazardous waste whilst also holding   a COTC 

site operators licence.  

 

All  demolition  and  plant  operatives  also  undergo  regular  in‐house  refresher  training  schemes, 

including demolition safety awareness, working at heights, asbestos awareness, abrasive wheels, 

reciprocating saws, tower scaffold use and behaviour training.   Copies of all certificates are held 

at Head Office. 

 

Should  there  be  a  need  for  subcontractors,  any  relevant  paperwork  will  be  submitted  and 

checked by the Site Foreman prior to works commencing. 

 

A copy of Elvanite’s site management team and site organogram will be made available following 

the award of the Contract. 

 

 

Page 22: Method Statement for the Elvanite Gardens Client

  

13. SAFETY EQUIPMENT  PPE Equipment  All  Elvanite  Recycling  Ltd  site  personnel  are  to  be  in  pocession  of  the  correct  Personnel  Protective Equipment  (PPE)  at  all  times  during work  on  site.    All mandatory  equipment  requirements  are  to  be obeyed by site personnel.   Elvanite personnel are at all times to wear as a minimum, a Hi‐Vis vest, Hard hat with  identifying  logo  and  Safety  footwear with a  steel  toe and mid‐sole protection.   As and when safety glasses and ear defence are required they are to be made available.  Where there is a requirement for  specialised  safety  equipment  such  as  fall  arrest  harnesses,  they  should  be  accompanied  by  the relevant up  to date  check  certificates.   Where operators are  required  to use  items of RPE,  the  correct paperwork will be held on file by the Site Supervisor and the client Brennan Constrcuction.   Should they be requested, copies are also held at Elvanites head office.  The Site Supervisor will  insure that he has all relevant documentation  in regards to PPE & RPE for each member of the demolition work force.  This is to include any demolition worker employed through agency means.    Further  items of PPE not  identified during  the pre‐start meetings  should be held on  stock  as required for immediate issue.  All working operatives and visitors must obey the site rules with regard to protective clothing.  

13 . METHODOLOGY 

 

The method of demolition has been designed  in  accordance with  standard demolition  techniques,  the 

Demolition Code of Practice BS6187:2011.  

 

DUST SUPPRESSION FOR ALL WORKS IN ALL AREAS COVERED BY THIS METHOD STATEMENT 

 

In addition, dust  levels will generally be monitored and suppressed with use of hoses and fire hydrants, 

the  water  supply  will  be  from  metered  standpipes  fitted  with  non  return  valves  (RPZ)  at  point  of 

connection to the water supply from the mains supply to our works. 

Attached to the standpipe will be a section of hose fitted with a non return valve, this will be utilised to 

supply a direct feed for the sites dusty operations. 

A mobile  dust  cannon will  be  utilised when  deemed  necessary,  the  cannon will  disperse  a  fine water 

droplet mist to any immediate areas that require quickfire heavy suppression. 

Environmental  influences will be taking  into consideration, such as wind direction, all operations will be 

taken into consideration to ensure the best placement of cold water droplets to cover the immediate area 

of work to suppress the dust.A the 25t excavator will have a direct watermains feed to the attachment for 

additional soaking during the progressive demolition works, there will be a fine droplect nozzle located to 

beak of all hydraulic attachments. 

In addition  there will also be a mobile self powered nurse  tank on site  for any extra volumes of water 

required during the site operations. 

Due care and monitoring of these operations  is paramount to ensure any one particular area becoming 

over dampened resulting in excessice surface water or residual run off to local  drainage systems. 

Should water run off be a potential issue, bunds/trenches shall be formed to allow a natrual soak away for 

excessive water. 

Page 23: Method Statement for the Elvanite Gardens Client

 

  

 

 

 

 

 

.  Any  site  activities  requiring  point  accuracy,  e.g  lorry  loading/processing  a  second  hosepipe  will  be 

utilised 

 

 

SOFT STRIPPING OPERATIONS TO ALL 3 FLOORS OF THE BUILDING 

 

PRIOR  TO  ANY  SOFT  STRIPPING  COMMENCING  ALL  ASBESTOS  MATERIALS  WILL  BE  SUITABLY 

IDENTIFIED AND REMOVED UNDER CAR2012 WITH THE ASBNW1/ABS5 NOTIFICATION  IN PLACE. THE 

SITE WILL BE REGISTERED WITH  THE  ENVIRONMENT AGENCY WITH A  SITE  SPECIFIC PREMISES CODE 

BEING AVAILABLE FOR THE REMOVAL OF ANY HAZARDOUS WAST STREAMS. 

 

Due to the short programme, it will be the intention to carryout all noisy operations within the 1st week 

to minimise any disruption to the college during tutorial times.  

All  materials  from  the  redundant  floors  to  the  building  will  be  soft  stripped  by  use  of  demolition 

operatives  utilising  hand  held  tools  such  as  pinch  bars,  sledgehammers  and  assorted  non mechanical 

demolition  equipment,  any  identified  block  walls  will  be  removed  using  low  percussive  hand  held 

breakers. 

 

Where ever possible and reasonbly practicable waste streams will be seperated at source and  in situ to 

ensure  minimal  cross  contamination  which  could  result  in  non  conmpliances  at  licensed  waste 

management facilities. 

This will allow all working areas to run efficiently through an un‐obstructed access whilst keeping waste 

streams seperated reducing the potential of any harm arising to operatives as well as greatly reducing the 

possibility of fire hazards occuring with an overall effect of improved well being within the sites confines. 

EXCLUSIONS ZONES WILL BE PRE‐IDENTIFIED BEFORE SOFT STRIPPING COMMENCES. 

 

 

 

Page 24: Method Statement for the Elvanite Gardens Client

  

 

Identified Hazards & Risks 

1. Asbestos  products  are  present  within  certain  areas  &  the  building.  (Control  of  Asbestos 

Regulations 2012) 

2. Services may  be  live  to  area  (HSE  guidelines  HSG  47  Avoiding  Danger  from  Underground 

Services) 

3. Unauthorised access to work area (MHSW Regulations 1999) 

4. Operative cuts and grazes (HSG17 Safety in the use of Abrasive Wheels publication, Training, 

Inductions and Toolbox Talks) 

5. Asbestos fibre release (HSG 264 Asbestos: The Survey Guide) 

6. Waste  disposal  (The  Environmental  Protection Act  1990  and  the Duty  of  Care  Regulations 

2011) 

7. Vehicular access to site (HSG 136 Workplace Transport Safety) 

8. Pedestrian access to site (MHSW Regulations 1999 and SG 151 Protection of the Public) 

9. Welfare facilities (HASAWA 1974 etc., MHSW Regulations 1999, CDM 2015) 

10. Interaction with employees and members of the public on foot and in vehicles 

11. Machine operation (LOLER 1998, PUWER 1998) 

12. Dust  (Environmental  Protection  Act  1990,  HSG  151  Protection  of  the  Public,  COSHH 

Regulations 2002 (as amended) 

13. Noise (MHSW Regulations 1999, Environments Protection Act 1990) 

14. Working at height  (Working at Height Regulations 2005, HSG65 Successful Health & Safety 

Management Guidance) 

15. Premature collapse 

16. Flame cutting 

17. Fire (RRFSO 2005, FSRA‐5‐Step‐Checklist) 

18. Other structures that remain are in vacinity 

19. Excavations CDM ‐ 2015 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 25: Method Statement for the Elvanite Gardens Client

  

Control Measures 

 

1. An  Asbestos  trained  surveyor  has  carried  out  an  inspection  prior  to  any  site  activities 

commencing and produced  a Demolition & Refurbishment Survey. REPORT 10579.1 

The survey has  indicated and highlighted Asbestos products  located within the 3no floors to 

be  stripped.  The  asbestos will  be  removed  by  a  licensed  contractor,  employed  directly  by 

Elvanite Recycling, all works undertaken will be  in accordance with The Control of Asbestos 

Regulations 2012. Clearance certificates will be issued for any licensed Asbetsos Removal. 

All  of  Elvanite  Recycling  operatives  have  received  Asbestos  Awareness  training,  all works 

undertaken will be carried out with due dilligence. 

Any suspected ACM’S that have not been pre  identified by the Asbestos Survey will result  in 

works for that area being  immediately suspended, with the area being cornered off and the 

Brennan Construction SITE MANAGER being informed. 

Once  identification of  the material has been confirmed Elvanite Recycling will await written 

instruction  from  the  Brennan  Construction  as  how  to  proceed  before  recommencing  any 

further works. 

If  additional  Asbestos  removal  is  required  Brennan  Construction  will  Instruct  a  Licensed 

Contractor for the removal of such materials found to contain Asbestos, upon completion of 

these  works  a  Clean  Air  Certificate    shall  be  issued  to  Elvanite  Recycling  prior  to  works 

commencing again. 

  

2. Services to be terminated by the Client and proof in writing given to Elvanite’s Site Supervisor. 

3. Work area  to be  separated by Heras  fence exclusion zone with warning  signage as Signs & 

Signals  Regulations.    Main  site  entrance  gate  to  be  kept  locked  at  all  times  to  prevent 

trespass. Visitor access  to be arranged via  the  site supervisor who can be  found  in  the  site 

office. 

4. Correct PPE of hard hat, safety boots, hi‐viz vest,  light eye protection, overalls and gloves to 

be worn at all times by operatives.  Ear defenders will be worn if the noise monitoring shows 

that they are required.  Helmet mounted ear defenders are to be used (MHSW Regs 1999) 

5. As  the asbestos has been  removed by  trained operatives under controlled conditions  there 

will be no danger from fibre release. 

6. The hardcore and waste materials will be sorted as work progresses into the designated areas 

for  crushing  to  specified  sizes  on  site.    The  site will  be  registered with  the  Environment 

Agency as a Hazardous waste producer and the Section 62 movement notices will be  issued 

for all waste removed from site with copies supplied to Brennan Construction and the CDM 

Co‐ordinator on completion of  the works  for  inclusion within  the H&S  file  for  the handover 

file to the Client upon completion of the contract. 

7. Site vehicle access will be via the main  site access gtates with the existing vehicle entrances 

being  used  for  access/egress.    Vehicle Marshall(s)  to  be  in  attendance  at  all  times when 

vehicles enter and leave work area.  Operative cars to park on the designmated car park area,  

 

 

 

 

Page 26: Method Statement for the Elvanite Gardens Client

 

  

 

8. accessed  via  separate  gates  from  the  road,  from  where  site  can  be  accessed  on  foot.  

Reversing of vehicles will be reduced to the minimum and where reversing must be carried 

out it will be done under Elvanite’s approved vehicle marshall control. 

 

9. All visits and pedestrians to enter site by clearly designated route from road and to reeport to 

the site office for induction before being allowed on site.  All visitors will comply with the site 

rules. 

10. Brennan  Construction will  provide welfare  facilities  for  their won workforce  (MHSW  Regs 

1999).  Welfare to have flush toilets, hot water and the facility to heat up foot and water all as 

the Construction (Design and Management) Regulations 2007. 

11. Vehcile  marshalls  to  be  in  attendance  in  work  area  at  all  times  and  to  control  vehicle 

movements. 

12. Machines to have current 12 month test certificate (PUWER 1998), (LOLER 1998) & INDG 290, 

have been  inspected within  the  last seven days and have a driver holding a CPCS, CCDO or 

CSCS card to show competence. 

13. Should the works generate dust (Environment Protection Act 1990) and (COSHH Regs 2002) 

to the point it is of a concern, the works will be damped down with water before and during 

demolition to reduce the risk of any dust release. 

14. Any  working  at  height  will  be  carried  out  by  trained  0peratives,  wherever  reasonbly 

practicable scaffod, scaffold towers or Mewps will be utilised, fall arrest systemswill only be 

used as a last resort. A working at height rescue plan will be implemented at all times. 

15. A structural survey has been carried out to enable mechanical demolition to proceed, piece 

meal methodology will used  at  all  times,  any  areas  that  require  tempoary  support will  be 

desinged and calculated by an engineer to suit the projects requirements. 

16. Slab removal to proceed in sections to remove one section at a time.  When section has been 

removed, the debris will be removed before the next section is commenced. 

17. Operatives  to be competent  in use of Oxy‐propane cutting  torch.   Torch, pipes, gauges and 

cylinders to be  in good order and checked by operatives before use and Hot Works Permits 

issued prior to commencement.  Pipes to be fitted with spark arrestors.  Operatives to flame 

cut steels only when the disc cutter will not cut the material.  All hot works are to cease and 

the work area cleared one hour before the end of the shift to enable End of Day Checklists to 

be undertaken so as to illiminate risk of fire related incidents arising resulting from hot works 

as recommended by current industry best pracrtice. 

18. Site is a NO SMOKING OR NAKED FLAME site so hot works to be carried out under a permit to 

work system. 

19. All excavations will be battered back or stepped, no excavtions will left open for any period of 

time, a suitable barrier system will be utilised at all times, backfilling of any open excavtion 

will take place at the earliest opportunity as works proceeds, no excavtions will be  left open 

over night. 

 

    

 

Page 27: Method Statement for the Elvanite Gardens Client

 14. NOTIFICATIONS 

Prior  to any works commencing on site  the project will be registered with  the Environment 

Agency  under  the  Wrap  Protocol  as  a  waste  producing  site,  this  will  enable  the  sites 

operations to have a unique premises code to ensure the Duty of Care Regulations 1991 are 

compliant for all Hazardous and Non Hazardous waste removal from site.  

 

 

Elvanite Recycling currently holds an environmental permit for the crushing, screening storing and loading of raw materials and recycled materials (permit number APA10/92/p4).This permit will be activated for the crushing and screening of all clean validated recyclable materials that are to be used for the encapsulation layers, pile mat areas and re-engineering works. All works will to be undertaken by adhering to best codes of practice as implemented by the Environment Agency’s standard Rules and guidelines SR2008 NO27, Elvanite Recycling operating Permit no is EPR/AB3409FK.

 

 

15. SEQUENCE OF WORKS 

Prior  to any activities  commencing on  site  the  site  supervisor will pre  identfy any Asbestos Containing 

materials within  the  structures  that are  to be demolished  to ensure  these materials are not disturbed 

during the soft strip works. 

 

A  Demolition  &  Refurbishment  Asbestsos  Survey  in  accordance  with  HSG264  has  been  produced  by 

Brennan  Construction,  Elvanite Recycling will manage  the  asbestos  removal works  prior  to  demolition 

stripout works  ensuring  all  the  relevanat  HSE Notifications  are  in  place,  these May  include  the  ASB5 

Notifiable licensed Removal if any Licensed Asbestos is suspected and the ASB NNLW1 Notification of non 

licensed working with Asbestos. 

The site will also be registered with The Environment Agency as a Hazardous Waste Producer with its own 

specific premises code. 

However  unidentified  Abestsos  products  may  be  detected  during  the  soft  stripping  operations(  see 

control measures 1) 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 28: Method Statement for the Elvanite Gardens Client

 16. NOTIFIABLE LICENSED ASBESTOS REMOVAL 

 

The  Asbestos  report  to  accompany  these works  have  not  indicated  any  licensed  products within  the 

building (PDR SURVEY REPORT 10579.1) however due to the age of the building and certain areas being 

unavailable  to  be  surveyed  there  is  a  residual  risk  that  unidentified  Asbetsos  products  may  be 

encountered.  In  the  eventuality  that  any  suspected  unidentified Asbestos  is  discovered,  all works will 

cease  within  that  area,  the  area  will  be  isolated  and  Brennan  Constructions  site  manger  will  be 

immediately inforemed. 

 

A  fully  qualified HSE  licensed  contractor will  undertake  all  aspects  of  Asbestos  removal  as  to  remain 

compliant  to  the  CAR  2012  at  all  times,  a  separate method  staement  and  risk  assessments  will  be 

produced by the spealised as bestos contractor prior to any asbestos removal taking place. 

 

A trained and competent surveyor will have the suspected ACM  analysed to ensure any future works are 

carried out under the correct legislation and notifications whilst ensuring the safety and welfare of all site 

staff and public alike. 

 

Brennan Construction will employ a UKAS  Licensed Asbestos Contractor  for any unidentified Notifiable 

Licensed operations, these works will be carried out under an ASB5 Notification, all relevant notifications 

will  be  in  place  prior  to works  commencing, with  all method  statements  and  risks  assessments  being 

available on site and authorised by the site manager. 

The specialised contractor will issue a final air clearance certificate on completion of works. 

All works will remain compliant to  The Control of Asbestos Regulations 2012. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 29: Method Statement for the Elvanite Gardens Client

  

17. Preventing Falls When working at heights is required, suitable access equipment will be provided, in accordance with the Working At Height Regulations 2005 and will undertake a risk assessment to identify if working at height is  required  and will  ensure  that work  is  not  carried  out  at  height, where  it  can  be  done  safely  from another position.  Where work  is to be carried out at height, Elvanite will take suitable and sufficient measures to prevent any person falling a distance liable to cause personal injury.  Elvanite will: 

Ensure that work, or gaining access or egress, is carried out from an existing place of work or an existing means of access. 

Where this is not practicable: 

Elvanite will provide suitable and sufficient work equipment to prevent a fall occuring. Where the measures do not eliminate the risk of a fall occurring: 

Elvanite will provide suitable work equipment to minimise the distance and consequences of a fall. 

Provide training and instruction 

Take other measures  to  prevent  any  person  falling  a distance  liable  to  cause personal injury. 

 It  is  therefore  planned  that  any work  at  height  internally, will  be  carried  out  by  utilising mobile  alloy towers, correctly assembled by competent persons.  Working  from stepladders may be permitted at  the Site Managers discretion, only  for a short duration and only where the risk assessment shows that a stepladder is a suitable form of access.  Where works are  to be undertaken which could  result  in materials,  tools etc.  falling on persons below, these  areas  are  to  be  clearly  identified  and  cordoned  off  where  reasonably  practicable  in  order  to minimise risks.  Scaffolds where  required, will  be  erected,  adjusted,  altered  and  dismantled  by  a  competent  scaffold company,  who  will  provide  adequate  design  information,  handover  certificates  and  licenses  where necessary.   Scaffolds will be  inspected by a  trained competent person every 7 days and  the  inspection recorded on the site scaffold register.   Tools  Elvanite  Recycling  Ltd  will  follow  the  Regulations  (i.e.  The  Provision  and  Use  of  Work  Equipment Regulations 1998)  that are applicable  to such specified equipment as deemed necessary and any other relevant legislation or industry guidance as issued.  Elvanite is to ensure that all equipment is suitable for it’s planned purpose and will take into account the working conditions and hazards in the workplace, when specifying equipment to be used.  All employees will be provided with adequate information, instruction and training and will be provided with equipment that conforms to both EC product safety directive and UK regulations.  

 

 

 

 

Page 30: Method Statement for the Elvanite Gardens Client

  

 

18. SOFT STRIPPING METHOD OF WORKS 

AN EXPERIENCED BANKSMAN WILL BE  IN ATTENDANCE AT ALL TIMES DURING THE LOADING OF ANY 

RUBBISH BINS 

 

Prior to any soft strip works being undertaken, the site supervisor will identfy the window that needs to 

removed to allow the removal of all waste streams, a suitable and suffcient exclusion zone will be created 

to allow segregated waste streams to loaded directly into an awaiting skip below. Please note the removal 

of windows will be kept  to an absolute minimum untill all  the Asbestos remoal has  take place,  this will 

assist in the necessity when it comes to building air locks within the building. 

 

The building will be  soft  stripped  starting on  the  top  floor and progressing down,  it  is  the  intention  to 

complete a floor allowing the licensed contractor to commence the asbestos removal insitu with the soft 

strip operations. As each floor is cleared of any ACMS demolition operatives will drop back to commence 

the  removal  of  the windows  taking  care when  handling  glass  and  to  ensure  any  breakge  is  kept  to  a 

minimum. 

 

CCDO/CSCS operatives wearing the correct ppe for the tasks to be undertaken, will move into the building 

working in each pre identified room and will remove, using hand tools all items of soft stripping materials 

that  have been pre‐identified  to  the  contract,  all materials will be  seperated methodically  for  loading 

directly  into  designated  skips  by  a  demolition  operatives  for  disposal  off  site  to  a  registered   waste 

management facility.  

These  items will  include doors &  frames, carpets, ceiling  tiles and grids non asbestos only,  light  fittings 

shelves & work surfaces fixtures and any losse items of furniture left by the previous occupier.  

Exclusion zones for for loading areas will be pre identified by the site supervisor and segregated by using 

heras fence panels. Access and Egress will maintained at all times to the building. 

All waste skips will be located adjacent to the works area  and will be manually loaded by site operatives. 

Where walls are of a plasterboard construction all  fittings will be carefully  removed using 12v batterry 

operated equipment. 

 

 

Working at height will be only be carried out by  trained and competent operatives who hold a PASMA 

ticket to erect and dismantle any scaffold towers, all towers will be scaff tagged and inspected daily by the 

site supervisor. 

 

All operatives will be face fit tested on site with a face fit test certificate being produced and available for 

inspection. 

 

 

 

 

 

 

 

Page 31: Method Statement for the Elvanite Gardens Client

  

House keeping will be imperative to site safety, all areas including designated escape routes corridors will 

be kept suitably clear from rubbish/timber, all 110v leads will be either placed above head height or kept 

to a minimal length to avoid the risk of slips/trips and falls. 

Any timber procucts will have nails flattened or stacked in a pre‐identified area in readiness for disposal to 

avoid pucnture wounds. 

 

19. Floor coverings All floor tiles are to be removed from the premises in a logical order throughout each room of the building 

where  reasonbly  praticable.    The  order  of  the  floor  covering  removal  is  at  the  discretion  of  the  Site 

Supervisor based on his current assessment of available free floor space and access to areas within each 

floor.  It is suggested that the floor coverings are removed starting from the furthest area from the access 

point located to the SW corner of the building.  Dependant on the adhesive used to stick the tiles in place, 

operatives may be able to lift the floor coverings away from the underfloor screed by hand provided that 

the correct PPE is worn to prevent skin abrasions.  If the operative has difficulty in removing the coverings 

by hand, a 5 inch carpet mut can be used to start the process and raise the corner of the tiles.  Should the 

floor tiles prove dificult to  lift then hand tools can usually be safely and efficiently removed by scraping, 

either utlising hand tools such as a lino lifter and floor scraper or by using a mechanical floor tile remover.  

The  floor  tiles removed can be stacked  in a  logical  fashion near  to but not blocking  the access / egress 

point.   If required, the tiles can be  loaded  into tonne bags and disposed of at the waste material transit 

point until such time as they can be safely removed off site.  Again, operatives removing waste materials 

between floor levels are advised not to exceed the lifts weight restriction. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 32: Method Statement for the Elvanite Gardens Client

  

20. Internal structures 

 The internal structure of the building mainly comprises of solid blockwork walls; however there are some areas of internal walls that are covered in plasterboard with a fine plaster render.  The inside fascia to the pre‐existing external walls is rendered with approximately 200mm of plaster that when broken at the surface becomes fine powder and is easily stripped back to the brick fascia.  On occasion operatives may have to remove internal blockwork walls.  Dismantling internal wall structures can generate large quantities of dust pm and operatives should at all times wear the correct level of RPE commensurate to the task.  Should dust be generated in large quantities to the point where it becomes a concern, the works will undergo Negative Air treatment before and during any works to reduce the risk of any dust release. Where electrical services run through the partitions, operatives are to ensure that services have been disconnected prior to removal.  A screwdriver with the correct drive can be used to remove all existing electrical services including light switches and plug points.  These fitments are usually of a plastic composition and should be segregated prior to disposal.  It is possible for the operatives to utilize power tools at this stage if they require providing the operating criteria are met.   Internal structure stud walling is to be stripped methodically from the top down and to either side to prevent collapse of any large hung plasterboard.  Operatives should use a combination of hammers, mallets, sledges and pry bars as required to gain a feasible entry point into the wall cavities.  Where reasonably practicable operatives can strip back remaining plaster board using hands to pull the boards free from the wooden partitions. All plasterboard can be broken down by hand into manageable sizes and disposed of in tonne bags prior to removal to the waste material transit location and onto local disposal. All partitions can be removed in a safe and logical manner.  If the partition has infill of a fire retardant nature or other purpose such as sound deadening, this material can be stripped out by hand provided the correct PPE is worn by operatives.  It should be bagged and sealed for further disposal. Studs, head plates and sole plates should be left in situ whilst all other timber noggins are removed.  This can be done utilising power tools and/or manual tools such as a reciprocating saw, dependent on circumstance.  Once the noggins are removed both the head plate and sole plate can be unscrewed from the ceiling and floor.  This will allow the stud frame to be lowered to a height where operatives can easily dismantle it causing minimum disruption.  The waste materials should be disposed of according to the disposal segregation plan. Where the interior of the pre‐existing internal walls requires stripping back to brick the plaster render can be hacked away by operatives using chisels and hammers as and when required.  Where ever possible, operatives should utilise 110v guns and mid‐sized breakers to remove the plaster coverings.  However, restrictions may be in place regarding noise levels at certain periods of the works.  It may be necessary for operatives to remove smaller areas of plaster at a time using hammers to knock to plaster away.  Small areas of plaster work can be removed using a putty knife where practicable.  If areas of the wall require it, the old lath can be removed with a hammer and bundled as needed.  All the plaster can be swept into manageable piles and disposed of in suitable tonne bags prior to waste segregation disposal.  Operatives are advised to check manual handling risk assessments with their supervisor prior to lifting and moving materials as they may be heavy.  If required, the materials may need to be separated into smaller more manageable quantities to assist in their removal from site. If operatives are required to remove any block walls from inside the building they are advised to use the methods already stated to remove plaster render exposing the existing block. Correct PPE should be worn at all times and at least half face dust masks worn to prevent dust inhalation.

Page 33: Method Statement for the Elvanite Gardens Client

Removal of all electrical plates, outlets and switches and if pipes are located within the wall ensure that service disconnection is in place.  If the walls have any trim it can usually be removed with pry bars and hammers.  Using a sledge hammer, a hole can be punched through the block to expose the space beyond and ensure no vital services or access and egress is affected.  Continue removing the block wall in a systematic approach ensuring that the operators work from the top down and to either side as the demolition progresses.  At no time should an operative remove the block from the bottom risking a structural collapse until prior permission is sought and justified.  The remaining block work can be removed continuing to use the top down approach.  If there is increased difficulty in removing the block particularly where it is mortared into pre‐existing structural walls a hammer and chisel can be used to remove the mortar.  Where reasonably practicable, operators can utilise mini‐breakers, rip saws and other power tools as required.  The block should be broken down into manageable sizes and disposed of using the waste material segregation method as previously demonstrated. Greater care should be taken when dismantling all glass partitions throughout the floors.  Where possible, the glass partitions should be dismantled removing any fixtures and fittings as required.  Hand tools such as screwdrivers and allen keys may be required to remove certain items of existing frame work holding the glass partitions in place.  Where necessary, one side of the frame shall be removed ensuring that there are no further obstacles in the way and access and egress is not impaired.  A heavy duty cut and puncture resistant tarpaulin shall be placed on the floor directly below the glassed area big enough to cover the surface area required for the glass.  For ease of cleanliness, boarding should be placed over the DPM Tarpaulin.  This will allow glass shards to be collected quickly and easily.  If the glass panels do not require their integrity to remain operatives in PPE (including safety glasses/goggles) are to smash the glass using lump hammers from the top down to prevent shards falling onto operators.  The glass panels will be methodically broken and allowed to fall naturally into the tarpaulin. Smaller shards can be removed from the frames by hand and placed into the tarpaulin as required.  Any fine shards of glass shall be swept up for collection.  Tarpaulins will be bundled and removed from site according to the waste segregation to ensure minimal cross contamination at licensed waste management facilities.   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 34: Method Statement for the Elvanite Gardens Client

  

21. Door removal  Under current legislation all commercial properties are fitted with fire retardant doors.  These can be removed using the same method as usual for doors but the Site Supervisor may need to ascertain whether the existing doors are to remain damage free.  The door can be screwed free from all hinges using small hand tools or alternatively by using a pry bar to rip the door free dependent on required damage limitations.  The remaining hinge can be prised free from the door frame and segregated as required.  Should there be a requirement; the hinge can be separated by tapping a nail upward through the hinge to remove the pin although this method is time consuming.  Remove the screws holding the door frame in place with hand tools or a drill. If there are any nail heads in the frame that are visible, pry these out with a small pry bar or the end of a claw hammer.  If the nails are too deeply embedded in the frame and can’t be pried out cut through the nails between the house and door frame with a reciprocating saw. Run the saw in the space between the wall and the frame.  If there is no space, run the saw directly along the edge of the door frame and cut all the way around the frame. Hit the edge of the frame with a mallet or lump hammer until it begins to loosen and the trim begins to come away from the wall.  The frame may require several knocks along its length to separate the section from the wall.  Once enough of the surround has been exposed, the frame can be pulled free by hand.  Repeat the process for the other side of the frame and along the top until the frame can be completely removed.  Doing this in one piece, rather than prying out portions of the frame, will limit the damage to the surrounding area.   Ensure that any remaining nails and/or screws are flattened or taken out.  Once the frame is off, the operators will be able to access the seam where the door jamb meets the wall. Starting at the bottom of one side of the door, slip the metal‐cutting blade a jigsaw in between the jamb and the wall, and turn it on. Work your way up the jamb, cutting through all nails and screws that are holding it there, until reaching the top. Depending on how long the jigsaw blade is, it may be necessary to o repeat the process from the other side of the jamb to get all the fasteners and remove the jamb remaining piece. All waste materials can be into smaller pieces and loaded into a tonne bag for removal to the transfer location or directly to available bins.    Ceiling removal‐ Caution must be taken at all times when working on ceiling fixings, only ceilings that have been pre‐identified as Asbestos free are to be removed or have any associated fixings or fittings removed, this is to ensure that no Asbestos is disturbed prior to removal.  All fixtures and fittings for the ceiling are to be removed in a logical and systematic sequence.  Certain areas of the ceilings are composed of ceiling tiles laid across a thin alloy metal grid frame.    Operatives will use safe Working at Heights methods from a small BOSS tower or podiums. If required and for short periods of work provided prior authorisation is given, a step ladder may be utilised if safety procedures are followed.  All equipment is to be checked for serviceability before use and at weekly intervals ensuring any scaf‐tags and supporting documents are up to date.  The Site Supervisor is to ensure that any operatives working with the tower equipment used are correctly certified before work commences.  An area on the perimeter of the tiles should be identified for work to begin, selecting a tile that does not have any fixtures or accessories.  The tiles can be lifted out of place, angled slightly away from the ceiling grid and twisted until it slides easily through the grid.  All border tiles should be removed prior to the field being taken out and stacked in a designated area on each floor.  Once the ceiling tiles are removed the grid frame will be dismantled utilising hand tools such as spanners and socket sets.  Some of the ceiling tiles have fixtures and/or accessories attached which will need to be removed.  Pull up the insulation covering the connection between air conditioning vents and the flex duct attaching them to the air conditioning system. Grab the head of a strap holding the inner flex liner to the vent collar with a pair of pliers. Twist the strap head clockwise until it snaps. Pull the flex off the vent collar. Remove the vent or the tile holding the vent using the method described for the ceiling tiles.  The Site Supervisor is to ensure that all electrical services to the lighting grid are disconnected before removing light fixtures.   

Page 35: Method Statement for the Elvanite Gardens Client

 

  Remove the cover from each light fixture using the appropriate hand tools.  Once all remaining fixtures and accessories are removed from the tiles the remainder of the ceiling tiles can be removed.  To remove the grid, hold one ceiling tee‐grid with your non‐dominant hand and push up on the point the ceiling tee enters the slot of a main support tee. Pull the tee away from the support tee. Remove all tees and set them aside.  Cut the ceiling wires with the pliers or alternatively use spanners and sockets to loosen all bolted suspender rods until finger tight.  Keeping the weight held (which should be minimal); ensure that the end of each support wire sits flush with the bottom of the securing tabs. Lower each main tee to the ground carefully to avoid damage and set them aside.  Remove the screws holding the border angle from the walls by turning each mounting screw counter clockwise with a Phillips screwdriver. Score the underside of the angle with the blade of the utility knife, if the angle is caulked to the wall. Pull the angle away from the wall slowly.  This process should be repeated on each floor and all waste segregated as per the waste disposal plan. Identify all areas of air ducting that requires removal.  All operatives are to be aware of The Working at Height Regulations 2005 and have suitable PPE as the removal of the air ducting is likely to cause large amounts of dust pm to build up if not properly monitored.  The air ducting is pre‐designed as workable sections and should be dismantled a section at a time preferably working from the walls in.  Unbolt or unscrew a section of air ducting utilising the appropriate hand tool until the operative has gained complete separation between sections.  Where the sections have suspender rods fitted, they should be loosened off until finger tight with a spanner or socket set.  Maintain the weight of the section so that it doesn’t drop unnecessarily and undo the securing bolts completely from the section of ducting to be removed.  Once free from the suspender rods allow the section of duct to drop or pass it down to another operative.  Once the section is completely removed the operator will be required to remove all existing suspender rods and bracketing using appropriate hand tools.  Each section of air ducting and its associated bracketing is to be removed in sequence until operatives reach the center of the room being stripped.  All waste metals are to be segregated for removal from site as previously described. All wiring can be removed once a service disconnection certificate has been presented.  Wiring can be traced back to the junction panel and removed at source using pliers and wire cutters to remove in piece meal fashion allowing for it to be handled more easily.  

All windows should be handled with care to prevent accidental damage to the glass panes.  Operators should wear gloves at all times and wear an approved face mask to reduce the risk of exposure from dust pm and lead paint, particularly in old windows.  Old metal windows can be extremely heavy and Site Supervisors are requested to refer to risk assessments on manual handling prior to work commencing.  All glass panes should have masking tape crisscrossed against the diagonal of the pane to hold the glass together should it accidently break.  Where possible, operatives should remove the inside layer of existing              

Page 36: Method Statement for the Elvanite Gardens Client

 Putty to gain access to the glass pane.  By inserting a small pry bar or flathead screwdriver at the side of the glass it may be possible to remove the pane wholly.  If this is not possible the window should be removed as a whole piece where the glass might be removed at a later stage.  Locate the fixing screws around the outer of the existing window and remove if a logical sequence.  It may be necessary to use a flathead screwdriver as the window frames may pre‐date positive screw heads. If the screws are fixed firmly in position (usually due to paint layers) a small hack saw blade with handle can be used or a reciprocating saw if available at the side of the window frame to saw through the screw.  Once all screws are removed the window frame can be lifted out of position and placed onto DPM.  It may be necessary to pry the frame away from the wall using pry bars but this should only be attempted at the side of the frames to prevent the windows falling onto operatives.  All glass panes can then be removed and the frames disposed of in waste materials.  

All methods adopted throughout this method statement may be liable to change at the discretion of the Elvanite Site Supervisor once prior collaboration is sought and the deviation from method justified in keeping with the current works.  Any deviation will be recorded and inserted into this method statement for review and/or used as a lessons learnt reference.  Due to the lack of access to the rear of the building, Elvanite Recycling Ltd shall not amend the method statement to reflect strip out works until such time as Brennan Construction have clearly indicated the structural integrity and composition of all existing load bearing walls through the completion of a detailed survey.  No dismantling and/or demolition soft strips will be undertaken until such time as the necessary permits for work have been issued.  It will be the intention to utilize mechanical methods of dismantling whenever reasonably practicable to minimize the risks associated with manual handling.  

The removal of all waste streams will be critical to the contract programme, any oversized materials will 

be  removed utilising  the existing  stair wells  located at  the end of each  floor  to be  loaded directly  into 

awaiting  skips. This will need  to be  kept  to  a minimum  at  all  times  and  suitable manual handling  risk 

assessments carried out on site as the work proceeds. 

 

All transportation of materials will be pre organised by Elvanites site supervisor to minimise any build up 

of materials with the building. 

 

 

22. HOT WORKS 

All  hot works  if  required will  be  carried  out  to  the  permit  to work  system  implemented  by  Brennan 

Construction. 

It is Elvanite Recyclings intention to keep any hot works to an absolute minimum by utilising cold cutting 

apparatus and rip saws. 

 

 

 

 

 

 

 

 

Page 37: Method Statement for the Elvanite Gardens Client

  

23. Boundry Wall removal 

 

Running parrallel along Pembridge Road  is an existing boundry wall,  the wall will need  to be  carefully 

removed to enable the boundry hoarding to be installed. Working from west to east a temporary herras 

fence line with debris netting will be installed prior to any works commencing. 

The wall will be carefullly removed working from within the existing site boundry in 2m sections at a time, 

demolition operatives will  start at  the  top of  the wall working across  the  face of wall  in a methodical 

manner course by course down to existing path level utilising hand held 110v low percussive breakers, if 

the bond is weak small club hammers will be utilised to minimise the risk of HAVS exposure. Where access 

at  height  is  required  demolition  operatives who  are  suitably  pasma  trained will  erect  a  small  scaffold 

tower, ensuring the ground is level prior to starting work. 

As the works proceeds a suitable security fence will be installed as instructed by Brennans site manger. 

All arisings will stay on site as they will be crushed during the 2nd phase of demolition works for future re‐

use on site. 

 

If at all reasonbly practicable, the wall may be able to be removed by means of mechanical operations. 

A small 1.5t mini digger will be utilised, this will need to authorised and assessed on site by Brennans site 

manager prior to works commencing. 

 

Demolition operatives would place vertical saw cuts down the face of the wall in 2m strips, allowing each 

2m section to become independent, the 1.5t mini digeer would then commence to carefully lay the wall 

over  in piece meal  sections,  a banksman would  be  in  attendance on  the  Pembridge  road  footpath  to 

ensure all works cease whilst any general public wishes to pass the work area. Full dust suppression will 

be applied at all times. 

 

By using mechanical operations the risks associated with the works would ilminate many of the hazardous 

associated with manual handling, working at height and HAVS. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 38: Method Statement for the Elvanite Gardens Client

 

 24. Mechanical Demolition 

Prior  to any mechanical operations commencing  the Protective  scaffold will be erected with  full debris 

netting  to  the  south elevation,  the  scaffold will be  suitably  scaff  tagged and  inspected by a competent 

person every 7days from the scaffold company. 

 

On  completion  of  the  scaffold  the  building will  systematically  checked  to  ensure  that  all  services  are 

disconnected and that no residual hazards are apparent or previously unidentified chambers, basements 

or voids. 

 

An exclusion zone will then be set up with a suitable barrier system and clear signage being displayed. 

 

The Dust boss unit will be  stratigically placed  to allow  for wind direction  regarding  local  residents and 

buisnesses. 

 

The 23t demo spec excavtor will then take position, central to the western gable end, utilising a hydraulic 

multi processor attachement with direct water feed to the attachement to assist with dampening down at 

source, all works will be carried out in top down methodology. 

 

Starting  in  the  center  of  the  rear  gable  end,  the  outer  bick  wall  will  be  removed  in  piece  meal 

methodology, once a sufficient opening has been created the excavtor will proceed to start on the roof 

Construction working horizontaly along the roof construction maintaing an even distrubution of weight at 

all  times  to  the  side  elevations  thus maintaining  structural  intgerity  to  the  building  at  all  times,  the 

processed material will be allowed to fall to the floor below. 

 

Once  approx  2m  of  roof  section  has  been  removed  the  processd material  will  be  cleared  from  the 

concrete  floor below,  the excavtor will  then proceed  to work another 2m of  roof  section  in  the  same 

methodology. 

 

Once  the 4m of  roof  section has been  removed  the excavator will  then proceed  to  remove 2m of  the 

second floor of concrete construction  allowing the material to drop to 1st floor where the material will be 

cleared. 

 

The excavator will then proceed to remove 1m of floor section from the 1st floor, at no point will the side 

elevations be removed at this point. 

 

The  works  will  proceed  in  this  methodolgy  thus  reducing  the  risk  of  over  loading  any  floors  with 

demolition arisings which could possibly cuase an unplanned collapse. 

 

Once the roof section has bee removed up to the 1st set of windows the side elevations will be carefully 

removed by the excavtor down to 1m above second floor. 

 

Works will then progress to remove the lower floors in the same methodology as previously described 

 

Untill a step sequence system is clearly apparent. See diagrams below. 

Page 39: Method Statement for the Elvanite Gardens Client

 All of the demolition arisings will be kept damp at all times and within the footprint of the building.    The size of the exclusion zone will depend on the method selected, the risk of collapse and the risk posed by falling debris in relation to the predicted debris area. This last point will be of greater significance if no sheeted scaffold or screen is in use. Equally, the predicted debris area may be larger when using push/pull pole attachments as opposed to shears and grapples where the degree of control may be enhanced and the amount of debris created is reduced. Refer to figure 1 

   

        

Progressive demolition to 

maintain structural integrity. 

Buttresses to be 

engineered to shear walls 

Page 40: Method Statement for the Elvanite Gardens Client

                                      As  the works proceeds  through  the building  following  the  same methodology, a  second 13t excavator with a hydraulic grab will be  in attendance for secondary operations, this will  include the  loading of any residual materials into 40 yard roll on roll off bins ensuring the site remains clean and tidy at all times, a banksman will be in attendance at with a site operative located to perimeter of site to monitor dust, noise and vibration levels.  There are 2 number  staircases  located  to each end of  the building,  these have been  identified as core strength elements, works will always progress as to ensure the core strength of the building is maintained for as long as reasonably practical.  Due  to  the  building  being  abutted  next  to  a  residential  property  it  will  be  the  intention  to  cease mechanical  operations  prior  to  reaching  the  gable  end,  the  protective  scaffold  will  have  a  working platform  installed  to  the  last  4m,  enabling  demolition  operatives  access  to  this  side  of  building  to  all elevations.  The next phase of works will  involve precise robotic demolition and hand demolition  to enable  the  last section  of  the  building  to  come  down  safely whilst minimizing  any  risk  of  damage  to  the  residential building next door.  Demolition operatives will line the gable end of the residential property with heavy duty marine plywood prior to any hand demolition commencing to offer protection against any residual blockwork striking the gable end of the residential property  A Brock 180 will be lifted on to the second floor by the 23t excavator with testing lifting chains ensuring that  load does not  exceed  the  SWL of  the  excavator, utilizing  a  small hydraulic  cracker  the brock will proceed with  last 4m  in exactly  the same methodology as previously described, the Brock operator will remotely control the Brock 180 from within the man basket of an elevated work platform, the concrete floor sections will be pulverized and processed  in piece meal sections working along the face of  leading edge of roof section, this will maintain even distribution of weight to the load bearing walls. If required a row of temporary acrows supports will be back propped with 1m centers from top down, to minimize any unforeseen collapses.  This  assessment  will  be  made  at  the  earliest  stages  of  the  demolition,  as  the  building  fabric  and construction will become apparent.   The 23t excavator will be attendance at all times to ensure all residual concrete is cleared as not to over load any concrete floor section at any one time.  Once  the  roof  section  has  been  completed  in  its  entirety,  the  side  elevation  walls  will  be  carefully removed in piece methodology by the brokk, the gable end wall will then be taken down course by course by demolition operatives working from a telescopic work platform.  Each floor will follow this methodical sequence of works.  A  full working at height  risk assessment along with a  rescue and evacuation plan will be  implemented prior to these works commencing.  One  the  top  floor  is completed with  this methodology,  the  top  lift of scaffold will be struck, works will then proceed to the second floor and first floor in a repeat sequence of works as described above     

Page 41: Method Statement for the Elvanite Gardens Client

  

    

1.

  Example of Brokk and pulverizer to be used                                                           

1.

Page 42: Method Statement for the Elvanite Gardens Client

 

  The  use  of  robotic  deconstruction  techniques  dramatically  reduces  significant  risks  associated  with demolition works; these include manual handling, HAVS, working at height.  Only trained and qualified operatives will operate plant on site.   Disposal of residual demolition arisings 

 All waste streams generated from the demolition operations will  be suitably segregated due to the piece 

meal methodolgy being implemented by the trained and competent excavator operative. 

 By utilising the roatational selecta grab all waste streams will be loaded directly into 30 yard roll on/bins 

which will be trnasfered with full waste consignment notes to a licensed waste management facility with 

copies available to Brennan site management. 

 All blockworks  is  to be  retained on site  for crushing  for  furure  reuse during  the construction phase, all 

block work wwill be  stockpiled  to  suit  the  logistical  requirements of  the  site, dust  suppression will be 

applied at times when moving materials around site. 

 

Prior to any slab being lifted all blockwork will be cleaned from the slab area in readiness for crushing. 

 

25. Concrete slab and foundation removal 

 Before any mechanical operations commence on site, a site drawing will be explained with all existing live 

services being sufficiently marked on site with designated spray & marker poles to clearly  identfy areas 

where live services are to remain 

 *As precaution the slab and foundation removal area will be suitably CAT scanned with all works being 

undertaken by a permit to dig as authorised by Brennan site manager. 

 *Due  to  the  close  proximity  of  residential  dwellings  hydraulic  breaking will  be  kept  to  an  absolute 

minimum at all times. 

 Starting from the eastern point of the building foot print, the 360° excavator will proceed to  lift and  lay 

the slab  in situ continuously behind the excavator (refered to as haymaking), creating a stockpile as the 

work proceeds, contiuous dust suppression from the dust boss will be utilised at all times when moving 

masonary products on site. 

 

In the event that the slab is to heavily reinforced a ripping hook  will need to be utilsed, however the slab 

will only be broken into managble sized fractions when required to allow the safe loading of the crusher.. 

  

 

 

Page 43: Method Statement for the Elvanite Gardens Client

 26. Foundation removal 

 

Once  the  slab  has  been  processed  and  stockpiled,  the  360  excavtor will  proceed  to  remove  the  strip 

footings,  a  slip  trench will  be  excavated  allowing maximum  leveridge  to  grub  the  footing  out whilst 

minimising disturbance to the underlying ground, all excavtions will be backfilled and compacted as the 

works proceeds thus minimising any risk to open excavtions, no open excavtions will be left overnight.  

 

Works will commence at western end of the building working towards the residential property loacated at 

the eastern end,  it will be  the  intebntion  to  remove  the  footings  in as  large  lumps  from  the ground as 

reasonbly  practicable  to minimise  any  breaking  in  the  ground,  as  the  works  proceeds  closer  to  the 

residential building greta care and due dilligence will be applied as to ensure no risk of undermiming the 

residential building next door. 

 

It will  the  intention  to carry out  some  investigation works  to  the western elevation  to ensure  that  the 

former accomodation block sits on independent footings and to ascertain the foundation construction of 

the residential property. 

 

In  the  eventuality  that  the  last  section of  footings  to be  removed pose  a  risk  to  any  integerity of  the 

residential building next door, Brennan Construction will be  informed  immediately, a revised method of 

works will be issued and authorised by Brennan Construction. 

 

As to minimise the noise and vibration of these works, all large sections of concrete will be processed on 

the existing  concrete/hardcore heap,  thus allowing  the heap  to absorb noise and vibration  from  these 

works, dust suppression will be applied at all times.   

 

 27. Hazardous Waste/Contaminated ground 

 In  the  event  that  any hazardous materials/contaminated  ground  are  identified during  the  slab/footing operations, all works will cease immediately with the relevant parties being informed, whilst also ensuring the correct procedures associated with the hazardous waste/contaminants are carried out under the                  

Page 44: Method Statement for the Elvanite Gardens Client

28. CRUSHING OPERATIONS 

.  

Prior  to  any  crushing  operations  commencing  the  area  adjacent  to  the  stockpile will  be  inspected  to ensure sufficient stability for the tracked mobile crusher during all crushing activities. The Area where all specified material is to be stockpiled will be pre identified by the Brennan Construction site manager; all  stockpiles will be  compliant  to  the  site’s  specific  rules. All works will be  compliant  to Elvanite Recycling Environmental mobile crushing permit. 

 Transport of  the crusher will be pre‐organised  to ensure minimal disruption  to other work activities on site & local residents, due to the large size of the machine a suitable area will be required to enable the low‐loader to release the cab from the trailer bed allowing the crusher to track off hopper end first & then be tracked into position. 

 Once  in position  the  trained crusher operative will  set up & configure  the crusher, ensuring all guards, safety pins & emergency stop buttons are in place & operational. 

 The crusher operative will then carry out a full plant inspection ensuring the crusher and screener is ready for  operation  and  configures  the  jaw  setting  to  produce  the  recycled  aggregate  to  the  client’s specification.   A  direct  water  feed  will  then  be  connected  to  the  crusher’s  dust  suppression  unit  minimizing  any environmental issues. Once the crusher is in position, the Finlay power screen will then be positioned to enable the crusher to discharge  straight  into  the  screeners  loading  hopper,  the  screener will  be  configured  to  produce  the specified material as requested by Brennan Construction at tender stage.     A 28t excavator will load from the central stockpile, feeding the back of the crusher hopper, a secondary 12t excavator will ensure at all times the discharge belts from the crusher are kept clear of the processed material, whilst creating a stockpile in readiness for re‐use for future construction operations.   Dust suppression will be applied to all stockpiles heaps by means of a dusts boss.     

Additional Processing Any material that  is deemed too  large to be crushed by the primary crusher, will need to be processed separately by means of a 360 excavator hydraulically breaking or pulverizing the large lumps to a suitable size, these works will need be carried out  in a suitable area of the recycling area to minimize noise and risk of flying fragments from these operations. The oversized and processed material can then be crushed.                    

Page 45: Method Statement for the Elvanite Gardens Client

 

   

29. MONITORING PROCEDURES IDENTIFIED RECEPTORS & TRIGGER LEVELS During  all mechanical  site  operations    back  ground  reassurance  testing will  be  carried  out  by  a UKAS 

accredited  company  at  the  pre‐identified monitoring  points.  The monitoring  points  have  beeen  pre‐

identified to ensure recordings are site specific to the local receptors identified. 

 

Personal monitoring of the segregation process will also be implemented to assess working exposure 

limits and to ensure all RPE/PPE is adequate for the tasks being under taken. 

Once mechanical operations are ready to commence a monitoring station will be placed in a centralised 

location within the material segregation operations to give an intrusive a reflective recording of any 

possible free air borne concentration of dusts of concern, weather conditions will be taking into 

consideration for all monitoring operations. 

(wind direction)  

IDENTIFIED RECEPTORS

R1) General Public Pembridge Road

R2) Construction Site, Brennans Site Staff, Elvanite Site Staff

R3) Residential Dwellings Pembridge Road

R4) Site Offices Brennan Construction

R5) Site Visitors R6) Student accommodation to northern boundary

 

Identified Monitoring Points  

MP1) Site office accommodation

MP2) Pembridge Road S/E

MP3) Pembridge Road S/W

MP4) Site boundary West (student accommodation) MP5) Site boundary East (residential properties)  

 

 

 

Page 46: Method Statement for the Elvanite Gardens Client

 

     30. Site specific Risk Assessments wthin Demolition and made ground 

 

The site specific risk assessments devised for the projects mechanical operations have been identified  from pre start 

invesigation works, avaible information from historical uses of the land and surrounding areas along with the 

identified mechanical site operations that have been outlined in the devised Demolition strategy and associated 

RAMS. 

Identification of the sources relevant to the sites Demolition operations are listed below. 

Heavy plant operations 

Mechanical segregation 

Asbestos Contaminated Soils 

Fuel & Oil Storage 

Unidentified contaminants  

The pathways that could potentially release mechanisms if the site’s operations are carried out without the control 

measures inplace are listed below. 

On site plant movements 

Ground vibration 

Mechanical Vibration 

Environmental conditions: Wind/Heat dry weather 

Noise from site operations 

Ground water migration/ground contamination 

On site drainage leading to local water ways 

Emmissions from air 

Dust from air 

 

The site is located between local populated dwellings and commercial buisness and shops, the receptors that have 

been identified are listed below. 

Site operatives/sub‐contractors 

Site visitors/clients 

Local dwellings/residents 

Nearby buisnesses 

Flora/fauna 

General Public 

Site office staff 

        

Page 47: Method Statement for the Elvanite Gardens Client

  

 There is a possible risk to other receptors which include sub‐contractors, site office staff, visitors, enforcement officers and lorry drivers.  Full control measures will be implemented at all times  highlighted in the RAMS, in addition to these control measures continuous on site noise monitoring will be carried out at periodic intervals along with UKAS Certified standard air monitoring at designated monitoring stations, this are highlighted on drawing no ELV SP01.  The control limits are specified within the L143 Work with Materials Containing Asbestos. For all types of Asbestos the Limits are:  0.1 Fibres/ ml of air averaged over any 4 hour period 0.6 fibres/ml of air averaged over any 10 minute period  For a sample volume of 480 lires of air, any result of less than 20 fibres/200 graticule areas will give a calculated fibre concentration of less than 0.01/ml of air.  A result of less than (<) 0,01 fibres per ml of air is accepted as indicating: normal uncontaminated air: in clearance and other test situations.  N.B Asbestos fibres cannot be distinguished from non‐asbestos fibres using this method of analysis and the final result is a measure of all respirable fibres present and the air at the time of sampling.    All site operations will be carried out to legislative requirements including site security and designated working envelopes/site segregation and quarantine areas.  

However, potential human exposure routes to receptors have been pre‐identified.  

Dust/soil ingestion – skin contact resulting in ingestion from dirty hands face etc.  

Dermal contact – Exposed areas of unprotected skin from oils/liquids, contaminated soils, atmospheric/airborne particles. 

 

Atmospheric/air inhalation – respiratory inhalation of fibres, emissions, dust particles, fumes and gasses.   

 The conceptual Site Model indicates that further control measures are required to safeguard the operative’s health & welfare for all operations required to undertake the site specific activities.  All PPE will be specific to the tasks under taken and to the relevant legislation (PPE REGS 1992) they fall under to safeguard against the handling, treatment, movement and storage of all associated contaminants identified by the site specific risk assessments.  These include Dusts, fibres, oils and liquids, airborne particles, noise emissions, manual handling.    The control limit for asbestos is 0.1 asbestos fibres per cubic centimetre of air (0.1 f/cm3).   

Page 48: Method Statement for the Elvanite Gardens Client

    

  

 

 

 

INDICATOR  JUSTIFICATION  Trigger Level 

Portland Cement 

products 

Concrete waste 

products and cement 

10mg per m3 of air 

INDICATOR  JUSTIFICATION  Trigger level over 8 

hour time weighted 

Average 

ppm(mg.m3) 

Hydrocarbons 

If detected 

 Diesel wastes buried 

tanks, unidentified 

contaminant 

 

1200 ppm/mgm3 

Aromatic 

Hydrocarbons 

 Diesel waste products  

Fuel tanks engines 

 

5oo ppm/mg,3 

 

 

 

 

 

Page 49: Method Statement for the Elvanite Gardens Client

 Listed below are the parameters for the materials that have been identified that will require monitoring if 

discovered Trigger levels have also so been identified and the justification for why they are being 

monitored. 

 

 

INDICATOR 

 

 

 

JUSTIFICATION 

 

 

 

TRIGGER LEVEL  

 

 

CONTOL MEASURES 

ASBESTOS 

 

 

Associated with building 

products 

 

Demolition/construction 

Waste hard‐core 

 

960litres of air 20 

fibres/200 graticule 

area = 0.01 per ml of 

air. 

0.1wt/wt product 

0.001 wt/wt fibres 

 

 

 

All works to be 

undertaken in 

accordance with CAR 

2012. Licensed 

contractor to be 

employed with UKAS 

reassurance air 

monitoring being 

carried out.  

 

SILICA DUST 

 

Associated with 

concrete and plaster 

products 

 

0.1mg per m3 of air 

 

Dust suppression to be 

applied at all times. 

 

Trigger levels have been concluded from the EH40 Annual Workplace Exposure Limits 

All monitoring points will be clearly indicated prior to works commencing, with adequate protection to 

minimise the risk of damage. 

All points will be securely fixed to ensure change in environmental conditions do not compromise the 

stability and accuracy of the recording instruments. 

The main objective of the back ground monitoring is to ensure the site does not exceed the trigger point 

to the identified receptors. 

The control limit is specified in Regulation 2 of CAR 2012 as 0.1 fibres per cubic centimetre (f/cm3). Due to current weather conditions and dust suppression measures any other air borne dusts will be kept 

to a minimal.  

Page 50: Method Statement for the Elvanite Gardens Client

  

Noise and vibration disturbance will be minimized by:  

1. Ensuring all equipment is serviced and maintained to minimize noise and vibration  2. Utilising mains power instead of generators where feasible  3. Working within agreed hours 4. Disturbance to the local community and third parties will be minimised by:  

5. Only utilising agreed access and egress points 6. Parking in designated areas only 7. Observing good neighbour procedures and reporting any complaints to the QHSE Manager 8. Obeying traffic and pedestrian management schemes 9. Planning deliveries in off peak periods where practicable 10. Ensuring information on disruptive activities is adequately communicated by appropriate means 

including newsletters; site visits, visits to local schools etc. 11. Ensuring maximum noise levels as detailed in the Control of Pollution Act – ‘Schedule of Maximum 

Permissible Site Boundary Noise Levels’ are not exceeded.    

The Site supervisor will check that all plant delivered to site is in good working order and is accompanied by the appropriate test certification, as required by LOLER and PUWER, therefore minimising any nuisance created by noise  

Site controls that will be implemented during the demolition works will be to ensure strict controls of all 

the above. 

All areas of the demolition works will be suitably suppressed with fine water droplets mists as and when 

required; this will include areas of excavations, loading of materials, identified stockpile areas and 

mechanical segregation operations. In the unlikely event of any sustained periods of dry weather or 

failings on air monitoring trigger levels, dust suppression will be increased by deploying a dust boss fine 

droplet water cannon to site.   

Controlled procedures will be implemented at all times with experienced trained and competent 

operatives only being authorised to operate the identified plant for the remediation operations. 

Discharge heights from conveyor systems, excavators will be kept to an absolute minimum at all times 

with no large volumes of materials being double handled. 

Excavators will not be overload buckets to minimise spillage at all times. 

Stockpiles will be adequately managed daily, with all stockpile heaps being kept to a minimum height in 

relation to the sites requirements. Stockpiles will positioned when reasonably practicable to ensure they 

act as a natural sound/vibration and dust barrier to any identified receptors. 

The heaps will be sealed at the end of each working day by an excavator utilising a flat edged grading 

bucket, this will help to retain existing moisture content within the soils. 

Monitoring of dust emissions will be carried out using a UKAS registered company who will monitor for all 

dust emissions resulting from the sites activities. All equipment will be calibrated to UKAS industry 

standards with calibration certificates being available on site, the designated monitoring points have been 

pre‐identified drawing no ELV SP01 to ensure all identified receptors are monitored. 

Page 51: Method Statement for the Elvanite Gardens Client

 

These points have been identified to cover all wind directions and changing environmental conditions. 

Designated vehicular routes will be kept damp at all times to minimise any dust from vehicular 

movements. Vehicle wash down procedures will be implemented if required. A designated road sweeper 

will be in site attendance at all times for local connecting roads. The site supervisor will monitor the 

conditions of all access roads during the sites operations to ensure full controls are being implemented, a 

designated road sweeper will be in attendance/damping down as required to keep roads clean/minimise 

the spread of dust.  

MONITORING AND REVIEW 

 

The Company operates a pro‐active Integrated Management System (IMS), in accordance with the 

requirements of BS EN ISO 9001: 2008, BS EN ISO 14001: 2004 and OHSAS 18001: 2007. 

The Management Systems to be operated for the duration of the contract are those operated on all 

Company’s sites, involving strict compliance with these IMS Procedures. 

The IMS Procedures control all aspects of the safety, health, environmental and quality operations on site.  

The IMS Procedures require generation and retention of Construction Phase Plans, Method Statements, 

Plans of Work, Environmental Plans, assessments, including risk, COSHH, manual handling, PPE, etc., 

clearly defined records (specified pro‐formats) to provide documented controls and objective evidence to 

enable both internal and third party audits to be carried out. The records may also be utilised in the event 

of complaints relating to safety, environmental or operational matters.  

All records are contained in our Management System and are subject to controlled issue. 

The detailed procedures for issue/ retention of records and requirement for internal audits are:  

Document Control  Quality Records  Internal Quality Audits 

 Company records (the SWMP) also identify quantities of materials to waste, to re‐cycle and to re‐use. 

During the course of the works the designated Site Supervisor and Remediation manager will oversee the 

environmental activities on site including the removal and control of waste. 

The Site Supervisor will carry out a weekly review of environmental and safety performance. This will be 

by completion of appropriate Management System documentation. 

The Managing Director, in association with the Technical Director, remediation Manager, Quality Manager 

and Safety Advisor, will review environmental performance on an ongoing basis. 

At the reviews, appropriate corrective action measures will be developed and implemented to ensure 

continuous process improvement is maintained. 

All corrective action measures will be taken in a time period commensurate with the seriousness of the 

deficiency and/or the scope for improvement in environmental performance.  

A review of Company performance, including health and safety, environmental and operational issues, is carried out on an ongoing basis. A formal review is carried out annually – this is documented as required by the Management System.  

Pre start checks of all machinery will take place before any mechanical operations take place, with the 

relevant maintenance/pre start documents being recorded. 

The area of operations will be clearly segregated with the relevant signage being displayed. 

Page 52: Method Statement for the Elvanite Gardens Client

 

  

 Maintenance Any maintenance operations  that may be  required  throughout  the duration of  the project, will only be carried out by trained and certified be personnel, any maintenance works must be authorized by the site manager prior to any maintenance activities taken place to ensure all associated tasks remain compliant to the site rules and permit to work systems at all times. All sub‐contractors used will be vetted prior to being allowed on site. Elvanite Recycling operates a modern fleet of machinery which is maintained by the main dealer.  

NB DUE TO THE SHORT PRGRAMME TIME AND THE LOGISTICAL OPERATIONS REQUIRED ALONG WITH 

THE CLOSE PROXIMITY OF RESIDENTIAL DWELLINGS,  IT  IS OF PARAMOUNT  IMPORTANCE    THAT ALL 

WORKS ADHERE TO THIS METHOD STATEMENT. 

GOOD LINES OF COMMUNICATION MUST BE OPEN AT ALL TIMES BETWEEN ALL PARTIES CONCERNED 

TO ENSURE NO NON COMPLIANCE’S ON  SITE OR  IMPROVEMENT/ PROHIBITION ORDERS  FROM ANY 

REGULATING AUTHORITIES.  

 

 

 

Whilst  every  effort has been made  to  ensure  this method  statement  is  suitable  and  sufficient  for  the 

works to be undertaken on this project, due to unforseen eventualities associated with demolition works 

ammendments to this method satement may need to be made. 

 

At no point will any works deviate untill a  full written ammendment has been made and authorised by 

Craig Chaplin and member of management from the Brennan Group. 

 

 

 

 

Elvanite Recycling will make available any information requested by the CDM‐Co‐ordinator for inclusion in 

the Health & Safety file. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 53: Method Statement for the Elvanite Gardens Client

 

 

      APPENDIX 1  

Confirmation of methodology of project 

 

PROJECT:  

Forman to ensure that Method Statement is read and understood by each operative on the project and 

sign to that effect. 

 

Operative  to sign as having  read and understood  the Method Statement and all  its attachments  (i.e. 

Company H&S Policy, etc.) 

 

 

NAME OF OPERATIVE 

 

SIG 

 

DATE 

 

FOREMAN’S SIG 

 

DATE 

 

 

 

       

 

 

 

       

 

 

 

       

 

 

 

       

 

 

 

       

 

 

 

       

 

 

 

       

 

Foreman to ensure that this document is returned to Head Office once each member of the workforce 

has signed at the start of the contract.  If document is faxed (FAX NO…..) then the original is to be kept 

in the site file for information. 

 

 

 

 

Page 54: Method Statement for the Elvanite Gardens Client

 

 

  

EMERGENCY NUMBERS 

LOCAL A&E 

 020 3312 6666 

FIRE  999 

 

POLICE  999 (101 Non Emergency) 

 

 

GAS (if you smell gas) 

 

0800 111 999 

 

ELECTRIC 

 

0800 328 1111 

 

WATER 

 

0800 783 4444 

 

ELVANITE RECYCLING HEAD OFFICE 

 

01206 791958 

 

 

 

 

 

 

 

 

 

 

 

 

Page 55: Method Statement for the Elvanite Gardens Client

 

  

Method Statement Amendment/Addition Sheet 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Signature of Site Foreman __________________ 

 

 

 

 

 

 

Page 56: Method Statement for the Elvanite Gardens Client

 

 

  

SITE RULES  

Deliberate  contravention  of  these  rules  shall  be  considered  a  break  in  an  employee’s  contract  of 

employment or a breach of contract from that employee’s employer. 

 

It  should  also  be  borne  in mind  that  contravention  of  the Health  and  Safety  Legislation  is  a  criminal 

offence and that a prosecution can be taken against an individual by the Health and Safety Executive. 

 

WORKING PRACTICES 

 

1.No machine, item of plant or equipment is to be operated by any person, unless they have been trained 

and are authorised to do so. 

2. All machine guarding is to be in place and correctly adjusted, prior to machinery being used. 

3. Any fault, defect (including damage) or malfunction in any item of machinery, plant, equipment, tool or 

guard must be reported immediately. 

4. No machine, plant or equipment  is to be  left unattended or cleaned whilst  in motion, unless you are 

authorised to do so. 

5. No repairs, maintenance or adjustments to macnhines, plant or equipment are to be carried out, unless 

you are authorised to do so. 

6. All substances are to be stored  in accordance with the written  instructions and are to be returned to 

the storage after use. 

7. All substances are only to be used in accordance with the written instructions. 

8. All hazard notices or warning signs displayed on the premises are to be obeyed. 

9. All notices displayed  in the workplace are to be read and you are to ensure that you understand the 

instructions. 

10. All  safety  equipment  and  facilities  provided  are  to  be  used  and  are  not  to  be misused  or wilfully 

damaged. 

11. The work area is to be kept clean and tidy at all times. 

12. All waste is to be disposed of in the correct container. 

13. All liquid spills are to be cleaned up immediately. 

14. All emergency procedures relevant to your work area are to be obeyed. 

15. Emergency exits and equipment are not to be obstructed. 

16. Any use of or damage to fire fighting equipment is to be reported immediately. 

17. Prompt medical assistance must be  sought  for any  injury  received at work and  the  injury must be 

reported as soon as possible. 

18.  Operatives  are  advised  of  the  dangers  of  exposure  to  UV  radiation  and  are  advised  to  use  the 

appropriate barrier cream and clothing protection. 

19. No  persons  are  allowed  to work  on  site  if  they  are  under  the  influence  of ALCOHOL  or  consume 

alcohol in the working day. 

20. NO RECREATIONAL DRUGS, RADIO’S nor WALKMAN’s are allowed at any time at the site. 

Page 57: Method Statement for the Elvanite Gardens Client

 

 

MISCONDUCT Any  person  on  site,  found  to  have  acted  in  any  one  of  the  following ways,  shall  be  liable  to  the  site 

disciplinary procedure: 

 

1. Wilfully breaching the safety rules or Safety Policy. 

2. Removing any guard or protective device without permission. 

3. Operating any machine, plant or euqipment without authority. 

4. Misusing items provided for first aid. 

5. Recklessly  interfering  with  or misusing  anything  provided  in  the  interest  of  health,  safety  or 

welfare at work. 

6. Defacing or removing notices, signs, labels or any other warning device. 

7. Misusing any chemical, flammable substance, toxic material, etc. 

8. Smoking in designated “No Smoking” areas or whilst using flammable substances. 

9. Taking part in horseplay or practical jokes. 

 

ACCIDENT/INCIDENT REPORTING PROCEDURE Site Personnel 

All  site  personnel must  report  immediately  any  accident,  dangerous  occurrence  or  near miss  on  site, 

regardless of severity, to the Site Supervisor/Foreman. 

 

Site Supervisor/Foreman 

The Site Supervisor/Foreman will record all accidents, dangerous occurrances and near misses onto the 

Incident Register. 

 

Site Supervisor/Foreman 

Accidents 

The Site Supervisor/Foreman will ensure that in the event of an accident, the following actions are taken 

immediately: 

Report details of the accident to either the Safety Advisor or designated person(s) 

Record details onto the Incident Record 

Generate an Accident Report 

Forward the Accident Report to the Office 

Record details into any other designated Accident Books 

NB:  Details of all accidents, regardless of severity, will be recorded 

Dangerous Occurrences?Near Misses 

The Site Supervisor/Foreman will ensure  that  in  the event of a dangerous occurrence or near miss,  the 

following actions are taken immediately: 

Report verbally details of the dangerous occurrence or near miss to either the Safety Advisor or 

designated person, Contracts Director or Contracrts Manager. 

Record details onto the Incident Record 

Generate a Dangerous Occurrence/Near Miss Record  if  the dangerous occurrence  is detailed  in 

the Table of Occurrences/Near Misses 

Forward the Dangerous Occurrence/Near Miss Record to the Office 

Page 58: Method Statement for the Elvanite Gardens Client

  

Adminsitration 

The recipient of either an Accident Report or Dangerous Occurrence/Near Miss Record must ensure that 

the following actions are taken immediately: 

Accidents 

Generate a copy of the Accident Report 

Issue the original to Safety Advisor or designated person 

File one copy in the employuee’s personnel file 

Dangerous Occurrences/Near Misses 

    Generate a copy of the Dangerous Occurrence/Near Miss Record 

    Issue the original to Safety Advisor or designated person 

    File one copy in the appropriate Project file 

 

Safety Advisor or designated person 

Accidents 

Upon receipt of an Accident Report, the Safety Advisor or designated person will: 

 

Report all accidentrs reportable under the requirements of the Reporting of Injuries, Diseases and 

Dangerous Occurrences Regulations (RIDDOR) to the HSE Incident Contact Centre at Caerphilly 

Record all accident details in the Incidents Register 

Retain the original in the ‘Incident Records and Analysis’ file 

In  the  case  of RIDDOR  reportable  accidents,  generate  an Accidewnt  File  to be  retained  in  the 

‘Incident Records and Analysis’ file 

Issue  copies  of  all documentation  to  the Company  Insurers,  in  the  case of RIDDOR  reportable 

accidents immediately, others at the end of each month 

Dangerous Occurrence/Near Misses 

Upon receipt of a Dangerous Occurrence/Near Miss Record, the Safety Advisor or designated person will: 

Report all dangerous occurrences reportable under the requirements of the Reporting of Injuries, 

Diseases and Dangerous Occurrences Regulations (RIDDOR) to the HSE Incident Contact Centre at 

Caerphilly 

Record all dangerous occurrences in the Incidents Register 

Retain the original in the ‘Incident Records and Analysis’ file 

Investigation 

Investigation of accidents, dangerous occurrences or near misses will be at  the discretion of  the Safety 

Advisor  in  association with  the Managing  Director.    Accidents  and  dangerous  occurrences  reportable 

under ‘RIDDOR’ will generally be investigated. 

Investigations will  be  carried  out  by  the  Safety  Advisor  or  designated  person, where  appropriate,  in 

association with other personnel. 

Accident  investigations  will  be  formally  documented  either  onto  the  Investigation  Record  or  other 

suitable third pary documentation. 

Any actions identified as a result of the investigation will be recorded and reviewed by the Safety Advisor 

or designated person in association with other personnel deemed appropriate.  Any identified actions will 

be recorded and actioned by the Safety Advisor or designated person. 

If an investigation is carried out, the Investigation Record and all related documentation will be retained 

in the Incident File. 

Page 59: Method Statement for the Elvanite Gardens Client

 

 

 

Review 

The Safety Advisor or designated person will generate analysis records for all occurrrences and accidents 

and  review  the  findings  to  establish  causes,  identify  and  implement  appropriate  corrective  and/or 

preventative actions.