Upload
nkem-joseph-agwu
View
200
Download
4
Embed Size (px)
DESCRIPTION
Step by step method for solid waste disposal
Citation preview
NAOC LAND AREA LOCATION -OB/OB AND EBOCHA OIL CENTER. PAG GLOBAL RESOURCES LTD.METHOD STATEMENT FOR SOLID WASTES PACKAGING, TRANSPORTATION AND DISPOSAL.
This document and information therein may not be used, disclosed or reproduced for other purposes without the specific written prior permission of pag global resources (nig.) Ltd page 1
NAOC LAND AREA LOCATION -OB/OB AND EBOCHA OIL CENTRE. PAG GLOBAL RESOURCES LTD.METHOD STATEMENT FOR WASTE MANAGEMENT.
TABLE OF CONTENTS
1.0 PURPOSE
2.0 PERSONNEL PROTECTIVE EQUIPMENT
3.0 TOOLS AND EQUIPMENT
4.0 PERSONNEL IN CHARGE
5.0 WASTE SEGREGATION AND PACKAGING
6.0 METHOD OF WASTE LOADING
7.0 WASTES TRANSPORTATION
Page 2
NAOC LAND AREA LOCATION -OB/OB AND EBOCHA OIL CENTRE. PAG GLOBAL RESOURCES LTD.METHOD STATEMENT FOR WASTE MANAGEMENT.
1.0 PURPOSE
The purpose of this method statement is to portray the safety guidelines and best
procedure for this task at NAOC LAND AREA LOCATION -OB/OB AND EBOCHA OIL
CENTRE.
2.0 PERSONAL PROTECTIVE EQUIPMENT
Safety Shoes
Coverall
Hand Gloves
Protective Safety Eyeglasses
Hard Hat
Nose Mask
Rain Boots and Rain Coats
3.0 TOOLS & EQUIPMENT
Spade
Rakes
Knifes/Bolo
Motor Trucks
Hand Brush
Certified truck
Tarpaulin/ Plastic Nets
4.0 PERSONNEL IN CHARGE
Subcontractor’s Safety Officer
Subcontractor’s Supervisor
Subcontractor’s Truck Driver
Subcontractor’s Waste Handlers
Page 3
NAOC LAND AREA LOCATION -OB/OB AND EBOCHA OIL CENTRE. PAG GLOBAL RESOURCES LTD.METHOD STATEMENT FOR WASTE MANAGEMENT.
5.0 WASTE SEGREGATION AND PACKAGING
Contractor’s waste team shall bring the semi-segregated wastes collected from various
areas on site to the temporary dumpsite where proper segregation and packaging will be
done jointly by the Contractor’s team and that of waste Subcontractor.
Wastes such as cartoon, paper, cans/ containers, glass bottles, polythene bags,
floaters, rags, wood dust shall be properly packaged in waste bags before transporting to
the final dumpsite.
Food wastes, waste oil, contaminated soil and oil filters are contained in drums, scrap
metals; wood wastes are always loaded into trucks before disposal. Waste such as grits
are contained in poly propylene bags before disposal.
Both Contractor’s and Subcontractor’s Waste Team shall be properly dressed with the
required PPE.
Personnel shall be advised to rest at intervals during the operation to combat work stress.
Drinking water to be provided and worker to take rest breaks during hot weather in the
shield.
The personnel shall be advised not touch his /her face ,smoke ,eat or drink unless you
he washed his hands and face with soap and water and change out of contaminated
clothing before eating , drinking ,smoking.
6.0 METHOD OF WASTES LOADING.
The loading shall be supervised jointly by the Contractor’s Environmental Coordinator
and the Subcontractor’s Supervisor and Safety Officer
Personnel shall ensure that loading of the truck will not exceed the weight of the truck to
avoid truck overturning on transportation.
Correct positioning shall always be ensured by waste handlers.
Only competent trained personnel to carry out Loading and Unloading operations.
All tools and equipment to be checked before work starts.
Personnel shall ensure that manually lifted loads do not exceed his lifting capacity and
such loads shall be lifted jointly.
Page 4
NAOC LAND AREA LOCATION -OB/OB AND EBOCHA OIL CENTRE. PAG GLOBAL RESOURCES LTD.METHOD STATEMENT FOR WASTE MANAGEMENT.
7.0 WASTES TRANSPORTATION
A certified operator shall be provided whose has knowledge of the route and able to read
traffic signs (SPDC certified driver is preferable).
IVMS shall be installed in the truck by the Subcontractor to checkmate the speed of the
truck operator.
Operator shall comply with the project approved routes
Proper journey management shall be ensured by the Subcontractor’s truck operator
putting into consideration ETA and ETD
Always cover the truck with tarpaulin or plastic Nets to avoid flying off of lights from waste truck during transportation.
Page 5