1. GENERAL
The document describes the installation of Ventilation Fan, and consists of materials, equipment & tools, working
procedure, quality control and installation flow � chart. Detall of the procedure contained herein may be modified
based on the actual site condition.
2. MATERIALS
Ventilation Fans
3. Equipment & Tools
Basic equipment for installation of ventilation fan is as follows :
3.1 Ladder
3.2 Scaffolding
3.3 Driling Machine
SYSTEM : AIR CONDITION & VENTILATION
METHOD STATEMENT
METHOD STATEMENT
ON
VENTILATION FAN INSTALLATION
PM 6.07_E
Rev. 1
Issued 12/1/53
3.3 Driling Machine
3.4 Open � End Wrench
3.5 Monkey Wrench
3.6 Chain Block
3.7 Spirit Level
3.8 Pliers
4. WORKING PROCEDURE
4.1 Axial Fan / Inline � Centrifugal / Inline Mix Flow Fan.
4.1.1 Check Builder7s work and installation location
4.1.2 Check equipment type and model
4.1.3 Check fan components have no any visible damage.
4.1.4 Rotate fan blower by hand for abnormality check of blower and housing.
4.1.5 Ensure that there is no foreign material inside blower and housing.
4.1.6 Check dimension of fan base or mounting point.
4.1.7 Install expansion bolts.
4.1.8 Check air flow direction of fan.
4.1.9 Mount the fan with vibration isolator on steel base or hanging support, Fix bolts, nuts and washer.
4.1.10 Level the Fan.
X:\OFFICE DOC\ISO\Secco ISO doc\Project Management\Method Statement\Eng\PM6.07_E Page : 1/4
SYSTEM : AIR CONDITION & VENTILATION
METHOD STATEMENT PM 6.07_E
Rev. 1
Issued 12/1/53
4.2 Centrifugal Fan
4.2.1 Check Builder7s work and installation location.
4.2.2 Check equipment type and model.
4.2.3 Check fan components have no any visible damage.
4.2.4 Rotate fan blower by hand for abnormallty checked of blower and housing.
4.2.5 Adjust tension of fan beits and pre � alignment.
4.2.6 Ensure that there is no foreign material inside blower and housing.
4.2.7 Set up belt guard (If requlred)
4.2.8 Check dimension to fan base or mounting point.
4.2.9 Install expansion bolts.
4.2.10 Check air flow direction of fan
4.2.11 Mount the fan with vibration isolator on steel base or hanging support, fix bolts, nuts and washer.
4.2.12 Level the Fan.
5. QUALITY CONTROL
Quality control works should be performed in the particular works as described in the following
5.1 Fan and Vibration isolator Type and Model shall be check before transportation to installation place.5.1 Fan and Vibration isolator Type and Model shall be check before transportation to installation place.
5.2 Installation work shall be performed in accordance with approved shop drawing and acceptance by
inspection and check list as per attachment.
X:\OFFICE DOC\ISO\Secco ISO doc\Project Management\Method Statement\Eng\PM6.07_E Page : 2/4
SYSTEM : AIR CONDITION & VENTILATION
METHOD STATEMENT PM 6.07_E
Rev. 1
Issued 12/1/53
SPLIT TYPE AIR CONDITIONER INSTALLATION FLOW - CHART
START
CHECK NAME PLATE AND MODEL
CHECK DIMENSION OF FAN BASE OR MOUNTING POINT
CHECK TYPE OF VIBRATION ISOLATOR
INSTALLTHE FAN
CHECK FAN LEVEL &
NO
END
FIXNG ALL BOLTS & NUTS
ADJUST
YES
X:\OFFICE DOC\ISO\Secco ISO doc\Project Management\Method Statement\Eng\PM6.07_E Page : 3/4
SYSTEM : AIR CONDITION & VENTILATION
METHOD STATEMENT PM 6.07_E
Rev. 1
Issued 12/1/53
PROJECT NAME : _______________________ Ref. No. : _________________
LOCATION : ___________________________ DATE : ____ / ____ / _____
GRIDLINE : ________________________
REFER DRAWING NO : _______________ REV. NO : _________
REMARKS
SATISFIED UNSATISFIED
1 Materiels
1.1 Ventilation Fan
1.2 Vitration Isolator
Type and Model
2 Installation
2.1 Hanger and / or Support
2.2 Fan Level
STATUS
VENTILATION FAN INSTALLATIN
ITEM
CHECK LIST FOR
DESCRIPTIONINSPECTION AND
TEST REQUIRED
2.2 Fan Level
2.3 Bolts & Nuts
2.4 Fan Orientation
Note : __________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
_________________________________________________________________________________________
Inspected by : Approved by :
Signature : ________________ Signature : ________________
Name : ____________________ Name : ____________________
Date : ___________________ Date : ___________________
X:\OFFICE DOC\ISO\Secco ISO doc\Project Management\Method Statement\Eng\PM6.07_E Page : 4/4