WATERPROOFING QUALITY CONTROL CHECKLIST
Belle Grande Manila Bay
MEP SERVICES/ELV WORKS CHECKLIST1ST, 2ND AND FINAL FIX
LOCATION:__________________ WALL _____TOWER: ____________________ CEILING _____LEVEL: _____________________ROOM: ______________________Package No.:PC 311 5 STAR HOTEL TOWER 5&6
Request for Inspection of Works (RIW) No.:CGI_RIW_INT_
FIRST FIXCOMPLETEDREMARKSSIGNATUREDATE
YesNo
ACFCU
Chilled water and condensate drain pipe.
Fire damper
Valves and accessories
AC conduit
PDPL water pipe and valves
Drain pipe inc. waste pipe
Drain acoustic insulation
FSFS water pipe
FS conduit
Power conduit
Lighting conduit
FDAS
adFaade lighting conduit
TV and AV conduit
LAN conduit
Access Control conduit
Telephone conduit
SECOND FIX
CHW pipe Hydrostatic Test
Chilled water pipe insulation
Control wiring
PL water inside drywall
Shower mixer concealed box
Drain pipe inside drywall
Power conduit inside drywall
Lighting conduit inside dry wall
Power cable test
Lighting cable test
Power board Install Checking
Faade lighting cable test
TV and AV cables Test
Access Control cables Test
LAN cable Test
Telephone cable Test
AFA cable
Visual inspection for conduit installation
Visual inspection / light test of AC duct and duct joint installation
Visual inspection and hydraulic test for sprinkler pipe
Visual inspection and hydraulic test for PL water pipe.
Visual inspection and gravity leak test of waste and drain pipes.
Marking and tagging of systems
FINAL FIX
Light switch
Power socket
FDAS
Down light
Wall Light
Pendant light
TV wall plate
LAN wall plate
Access control wall plate
Telephone wall plate
Water closet
Bason
Bath
Shower head and trap
Water tap for basin
Jemflo device
Thermostat
Air grille
Sprinkler
Smoke detector and EVAC speaker
To be completed before closing false ceiling.
To be completed before closing 2nd sheet dry wall panel.
We herby certify that above area is ready for closure (wall/ceiling) as of date:_______________________.
Balance of work should be finished within 3days, if not done corresponding charges will be impose.
ELV Supervisor /Manager _____________________ ______________________ __________________
Sign Print Name
Date
MEP Supervisor /Manager _____________________ ______________________ __________________
Sign Print Name
Date
LCPI Supervisor /Manager _____________________ ______________________ __________________
Sign Print Name
Date
CGI_INT_TOWER5&6_PC311 CGI_FRM_QAL_100