10
1 Halsion | making buildings work for everyone MEP utility pod guide

MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

Embed Size (px)

Citation preview

Page 1: MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

1Halsion | making buildings work for everyone

MEP utilitypod guide

Page 2: MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

Making buildingsworkfor everyoneHALSION

BUILDING SERVICES ENGINEERS

LIM

ITED

With the need for construction projects to be rolled out in less timethan ever, Pre-Fabrication of key components has never been greater to

for fill key programme targets.

This seemingly complex task, can now be carried out in relativesimplicity, with the right team with the

building services engineering knowledge.

This guide is to explain, step by step, howHalsion Building Services Engineers

can for fill your targets, for low cost, less risk and in a timely manner.

Page 3: MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

Making buildingsworkfor everyoneHALSION

BUILDING SERVICES ENGINEERS

LIM

ITED

Benefits of Pre-Fabricated MEP Utility Cupboards

• Installation of MEP Components within the Utility podswithin our factory

An environment that benefits:• Less man hours on site reducing risk of accidents.• Mock up of a utility cupboard can be undertaken for a pod to be approved by

the client and all other parties before mass production takes place.• Better quality control – inspected, tested and signed off before site delivery for

final installation.• Consistency of installation – teams carry out specific tasks (Mechanical,

Electrical & Public Health as required).• Reduce risk of potential clashes with other services when the pods reach their

final destination.• Speed – from initial project discussions to the first pods being delivered and in

installed to their locations on site can be tailored to suit specific programmes.• Cost effective.

Page 4: MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

Making buildingsworkfor everyoneHALSION

BUILDING SERVICES ENGINEERS

LIM

ITED

Typical Options for MEP Utility Cupboards:

• POD shell inclusive of frame, ply lining and white rock finish.• Pipework• Pipework lagging• Drainage, (HepvO traps for condensate)• Valve assembly• Heat interface unit (HIU)• Mechanical whole house ventilation units (MHVR’s)• Incoming cut out and fuse• Distribution board• MCB’s/RCD’s• Dado trunking• TV connection box• BT connection box• Cable for utility cupboard circuity• All accessories/outlets• Protection & wrapping

All standard equipment listed above can be changed to suit specific design criteria.

Below are some typical BIM created installation drawings.

Page 5: MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

Making buildingsworkfor everyoneHALSION

BUILDING SERVICES ENGINEERS

LIM

ITED

The Typical Creation of A MEP Utility Cupboard:

• The pod design is approved via specifications, technical submittals &design drawings.

• The steel frame is fabricated, ply wood fixed to theframe to enable the MEP equipment to befastened to and white rock finish is applied.

• At this point, MEP equipment is ready to beinstalled within the Pod.

• The first piece of equipment to be installedis the MHVR.Mechanical Whole House Ventilation Unit.

• In this case a Nuaire MrXBox which has theability to have the air directions swapped,thus making it a very versatile unit.

• Next, we start the pipework installation.• The HIU (Heat Interface Unit/Boiler.• The Underfloor Heating Manifold.• First elements of the drainage.• In this photograph, the external casing of

the HIU is removed, so the pipeworkconnections can be tested.

Page 6: MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

Making buildingsworkfor everyoneHALSION

BUILDING SERVICES ENGINEERS

LIM

ITED

• Where possible, pipework isprefabricated, before being fixedto the inside of the pod.

• This is for speed and also to stop(where copper pipe is utilised andtherefore soldered) any burnsoccurring on the white rockfinished surface.

• The boosted cold water meterassembly is also installed withintegral pressure reducing valve.

• On the right hand side of this Podis also a cold water feed for awashing machine.

• Electrical Installation starts• 3 compartment dado trunking is

installed.• Consumer unit• BT connection unit• Switches, Sockets & Accessories

Page 7: MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

Making buildingsworkfor everyoneHALSION

BUILDING SERVICES ENGINEERS

LIM

ITED

• Here we can see the nearlycomplete MEP Utility Cupboard.

• Mechanical & Electrical finalconnections are made & tested.

• The HIU external cover is fitted.• Pipework is finished, pressure tested and then capped ready for shipping.

Page 8: MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

Making buildingsworkfor everyoneHALSION

BUILDING SERVICES ENGINEERS

LIM

ITED

• The Pre-Fabricated MEP Utility Cupboards are inspected before beingwrapped for transit to site.

• When the pods arrive at site, pre-installed lifting eyes are utilised tocrane the pod to the appropriate level of the building.

• The site crane is booked in advance for the pod delivery.

• Pods are unloaded onto a lifting platformand using a pallettruck, wheeled toeither a holding areaon the level or to theirfinal setting out point.

Page 9: MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

Making buildingsworkfor everyoneHALSION

BUILDING SERVICES ENGINEERS

LIM

ITED

• Here a MEP Utility Cupboardhas been located in its finalposition on the floor.

• The equipment to serve, inthis case a 1 bedroomapartment, is starting to befirst fixed to the pod.

• This includes:• Incoming pipework from the

buildings energy centre.• Drainage to a local soil stack.• Ductwork.• Electrical, incoming SWA

cabling to the consumer unit,Data & TV.

• External to thepod, theapartment isconstructed.

• Plasterboardcasework addedto the pod frame.

• The floor isformed.

• External switchesadded.

• Ceiling tieserected.

Page 10: MEP utility pod guide utility pod guide Making buildings work HALSION for everyone BUILDING SERVICES ENGINEERS L I M I T E D With the need for construction projects to be rolled out

Making buildingsworkfor everyoneHALSION

BUILDING SERVICES ENGINEERS

LIM

ITED

• The installation ofthe MEP UtilityCupboard is nearlycomplete.

• Plastered and mistcoated.

• It awaits the finalflooring added, it’sdoor and secondfix of externalaccessories.

• It has been testedin situ, signed offby the client.

• Below is a finished apartment• These apartments benefit from - Air conditioning, underfloor heating,separate metered water & heating supplies, individual metered Electrical

Data, TV supplies.• All options can be catered for, to approved specifications and cost.

• At low risk, quality controlled, quickly and cost effectively.