MEP MATRIX

Embed Size (px)

Citation preview

  • 7/30/2019 MEP MATRIX

    1/4

    AS OF :

    PROJECT:

    CLIENT:

    CONSULTANT:

    MAIN CONSTRACTOR:

    Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs

    Plaza Level-1

    Plaza Level-2

    Plaza Level-3

    Plaza Level-4

    Tower Basement Floor 12 6 15 6 25 24 7 3 8 4

    Ground Floor 3 6 7 6 7 3 1 2

    Level - 1 4 6 1 2

    Level - 2 4 6 1 2 4 2 2 2

    Level - 3 4 6 1 2 4 2 2 2

    Level - 4 4 6 1 2 4 2 2 2

    Level - 5 4 6 1 2 4 2 2 2

    Level - 6 4 6 1 2 4 2 2 2

    Level - 7 4 6 1 2 4 2 2 2

    Level - 8 4 6 1 2 4 2 2 2

    Level - 9 4 6 1 2 4 2 2 2

    Level - 10 4 6 1 2 4 2 2 2

    Level - 11 4 6 1 2 4 2 2 2

    Level - 12 4 6 1 2 4 2 2 2

    Level - 13 4 6 1 2 4 2 2 2

    Level - 14 4 6 1 2 4 2 2 2

    Level - 15 4 6 1 2 4 2 2 2

    Level - 16 4 6 1 2 4 2 2 2

    Level - 17 4 6 1 2 4 2 2 2

    Level - 18 4 6 1 2 4 2 2 2

    Level - 19 4 6 1 2 4 2 2 2

    Level - 20 4 6 1 2 4 2 2 2

    Level - 21 4 6 1 2 4 2 2 2

    Level - 22 4 6 1 2 4 2 2 2

    Level - 23 4 6 1 2 4 2 2 2

    Level - 24 4 6 1 2 4 2 2 2

    Level - 25 4 6 1 2 4 2 2 2

    Level - 26 4 6 1 2 4 2 2 2

    Level - 27 4 6 1 2 4 2 2 2

    Level - 28 1 3 4 6 1 2 4 2 2 2

    ROOF -1 8 3 7 6 6 15 4 3 7 3 4 4 6 4 2 2

    15 5 2

    510

    25 4

    6

    DuctriserApartment

    8 9

    Floor Levels

    WatersupplyTower

    area/Plaza/Roof

    DrainageriserTower

    area/Plaza/Roof

    DuctApartment/

    Podiumarea/Roof

    FireFighting

    Tower

    area/Plaza/Roof

    Cablepullingforriser

    Cabletrays(Mainpower

    cableriser)

    Cabletray&trunking

    (Power&LowCurrent)

    Electricalfloorconduits

    Watersupplyrisers&

    core

    DrainageriserCore

    7

    Cablepullingforriser

    Cabletrays(Low

    Current)

    Busbar(Vertical+

    Horizontal)

    77

    ChilledwaterTower

    area/Plaza/Roof

    8 9 10

    Cabletray(GSM)

    Electricalwallconduits

    ApartmentDB

    Enclosures

    UPSinstall.

    (abovefall

    ceiling)

    6

    30 8

    6

    RISER WORKSTOWER AREA WORKS

    1 2 3 4 5 6

    Chilledwaterpump

    roomworks

    Plumbing&Drainpump

    roomworks

    FireFightingpumproom

    works

    PUMP ROOM + SUB STATION

    PROGRESS MATRIX TABLE - MEP WORKS

    45 6 1

    8 6 30 6

    10 11 12

    Page 1 of 4

  • 7/30/2019 MEP MATRIX

    2/4

    AS OF :

    TESTING & COMM. WORKS

    Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs

    15

    6 30

    6 90

    6

    19 20 21

    Plumbingtesting&

    comm.works

    FirefightingSystesting

    &comm.

    HVACTesting,Adjusting

    ,Balancing&

    Commissioning

    3 30

    2

    ElectricalSubstation

    roomworks

    Chilledwater

    Connection@QatarCool

    PortableWater+Drain

    connection

    KAHRAMAAPower

    supply(TF&HVSwitch

    gear)

    13 14 15

    WORKS PLOT UTILITY CONNECTIONS

    5 4 20

    6 10

    15

    4

    16 17 18

    ENVAC(Vacuumsolid

    wasteconnection)

    StructuredCabling

    system(Active

    Component/IDFMDF)

    Page 2 of 4

  • 7/30/2019 MEP MATRIX

    3/4

    AS OF :

    PROJECT:

    CLIENT:

    CONSULTANT:

    MAIN CONSTRACTOR:

    Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs

    Plaza Level-1

    Plaza Level-2

    Plaza Level-3

    Plaza Level-4

    Tower Basement Floor 25 12 10 5 15 6 10 6 6 9 12 6 90 18 20 9 4 3 60 10 30 15 15 10 15 6

    Ground Floor 10 12 5 5 5 6 5 6 6 18 12 6 10 9 20 9 4 3 10 10 5 6 8 6 6 6

    Level - 1 5 6 7 6 12 18 12 6 10 9 20 9 4 3

    Level - 2 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 3 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 4 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 5 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 6 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 7 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 8 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 9 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 10 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 11 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 12 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 13 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 14 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 15 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 16 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 17 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 18 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 19 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 20 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 21 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 22 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 23 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 24 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 25 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6Level - 26 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 27 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    Level - 28 12 10 8 6 7 6 7 6 14 24 12 6 10 9 12 9 6 3 6 6 4 4 8 8 6 6

    ROOF -1 30 12 10 8 7 6 7 6 14 9 12 6 5 6 12 9 4 3 25 10 25 15 10 10 6 6

    6 7 8 9 101 2 3 4 5 17 1811 12 13 14 15 16

    Powercables

    Buildingwire

    Ceiling

    rose+flexible

    Cable

    Ductrisers

    FireFighting

    pipes

    Elec-wall

    Box's&

    conduits

    FloorConduits

    Watersupply

    pipes

    Drainpipes

    Ductwork

    PROGRESS MATRIX TABLE - MEP 1st Fix WORKS

    Chilledwater

    pipes

    DFCUUnits

    Lowcurrent

    Cable

    Page 3 of 4

  • 7/30/2019 MEP MATRIX

    4/4

    PROJECT:

    CLIENT:

    CONSULTANT:

    MAIN CONSTRACTOR:

    Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days

    Plaza Level-1

    Plaza Level-2

    Plaza Level-3

    Plaza Level-4

    Tower Basement Floor 3 3 6 3 4 3 1 3 7 3 1 3 4 4 15 10 6 6 12 9 6 4 2 3 3

    Ground Floor 3 3 3 3 3 3 3 3 1 3 4 3 1 3 4 4 10 8 6 6 3 4 6 4 2 3 3

    Level - 1 5 3 3 3 9 3 3 3 1 3 7 3 1 3 3 4 2 3 3

    Level - 2 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 3 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 4 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 5 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 6 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 7 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 8 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 9 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 10 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 11 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 12 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 13 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 14 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 15 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 16 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 17 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 18 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 19 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 20 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 21 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 22 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 23 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 24 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 25 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 26 10 3 3 3 9 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 27 7 3 3 3 7 6 3 3 1 3 7 3 1 3 6 6 5 4 3 4 4 4 6 4 2 3 3

    Level - 28 7 3 3 3 3 6 3 3 1 3 6 3 1 3 6 6 5 4 3 4 3 4 6 4 2 3 3

    ROOF -1 2 3 3 3 3 3 3 3 1 3 7 3 1 3 6 6 5 4 3 4 2 4 6 4 2 3 3

    7 8 91 2 3 4 5 6 10 11 12 13 1

    Chilledwater

    valves

    F.H.cabine

    t

    Sanitary

    fixture

    ZCV(Zone

    Control

    Valves)

    Watersupply

    P.R.V

    Airtermina

    l

    devices

    Coreduct

    risers

    Wiringdevic

    es

    lightingfixtu

    re

    FireAlarm

    devices

    Sprinklers

    Ele.Room

    D.B

    'sInstall.

    &

    termination

    Watersupply

    risers

    Chilledwater

    PROGRESS MATRIX TABLE - ME

    Page 4 of 4