MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

Embed Size (px)

Citation preview

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    1/292

    Information Technology and Communications

    Complex

    Saudi Arabia - Riyadh

    MEP Design Verification Report

    Underground Services Final Report

    Report No. 1

    Prepared for

    Drake & Scull International

    January 14th

    , 2012

    Rev 1

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    2/292

    DVR 251011/109 P a g e | 2 /292

    Quality Control Sheet

    Project ITCC- 18 ParcelsLocation Riyadh, KSAClient Drake & Scull International

    Att. Mr. Saher Kamal, Project Director

    Prepared by Jain Consultants International

    Contact person Ammar Nahya , CEO

    Amman/ 7th Circle beside Royal Jordanian H.Q.

    P.O. Box 143833

    Amman 11814

    Jordan

    Tel: +962-6-5857690

    Fax: +962-6-5857035

    Email:[email protected]

    Submitted to Drake & Scull International

    PO Box 15130

    Riyadh 11444

    Kingdom of Saudi Arabia

    Tel: +966 1 464 3037

    Fax: +966 1 464 3375Contact person Mr. Saher Kamal, Project Director

    Document Register:

    Item Revision No. Date Description

    DVR251011 1 January 14th , 2012MEP Design verification report

    # 1

    Quality Control Log:

    Item Originator Reviewer Authorized By

    DVR251011 SIM, IMH AMH, IMH ASN

    mailto:[email protected]:[email protected]:[email protected]:[email protected]
  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    3/292

    DVR 251011/109 P a g e | 3 /292

    Table of Contents

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    4/292

    DVR 251011/109 P a g e | 4 /292

    TABLE OF CONTENTS

    I. PROJECT INFORMATION ..................................................................................... 5II.

    EXECUTIVE SUMMARY ........................................................................................ 5A. INTRODUCTION ............................................................................................... 5B. METHODOLOGY ............................................................................................... 6C. SUMMARY OF FINDING S ............................................................................... 6

    1. MECHANICAL ............................................................................................. 72. ELECTRICAL .............................................................................................. 8

    III. RECOMMENDATIONS ........................................................................................... 9A. MECHANICAL ................................................................................................... 9B. ELECTRICAL ..................................................................................................... 9

    IV. DETAILED ANALYSIS ............................................................................................ 57A. MECHANICAL ................................................................................................... 57

    1. PUBLIC HEALTH......................................................................................... 572. HVAC .............................................................................................................. 1733. FIRE FIGHTING ........................................................................................... 173

    B. ELECTRICAL ..................................................................................................... 1741. GROUNDING & LIGHTNING PROTECTION ........................................ 1742. NORMAL & EMERGENCY LIGHTING .................................................. 2023. POWER & LOW VOLTAGE DISTIBUTION ........................................... 2024. IT NETWORK ............................................................................................... 2025. FIRE ALARM & DETECTION ................................................................... 202

    V. REFERENCE STANDARDS .................................................................................... 203VI. APPENDICES ..................................................................................................... 205

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    5/292

    DVR 251011/109 P a g e | 5 /292

    I. PROJECT INFORMATIONThe project is located in the northern part of Riyadh at the intersection of Imam Saud

    Street and Takhasusi Street.

    The project consists of 13 buildings with a total built up area of 431,304 m2 divided into

    several building types of commercial and retail.The MEP design was done by Zuhair Fayez Partnership Consultants and the MEP

    contract was awarded to Drake & Scull International DSI. As a part of their contractual

    agreement, DSI is required to verify the MEP design for:

    1- Validity2- Constructability3- Functionality

    DSI has signed a contract with Jain Engineering Consultants International to verify the

    MEP design and issue their results in stages to coincide with construction activities. Since

    the main contractor is near casting the lowest basement slab, it is important for DSI to

    verify design of services below that slab (Drainage, sump pits, groundingetc) and

    produce related shop drawings first.

    II. EXECUTIVE SUMMARYA. Introduction

    The purpose of this report is to provide information regarding the design validation of

    the MEP systems for the Information Technology and Communications Complex(ITCC)- 18 Parcels Project in Riyadh, KSA. The design review was conducted to

    highlight any potential impact caused by the design on the construction activities of

    the project. The point of view expressed in this report is that of the author which is

    based on International Practices and Standards. It is no meant to be condemnatory or

    judgmental of the current design. The intention of this report is to highlight issues

    related to the progress of engineering works such as production of shop drawings and

    materials ordering. The design review was conducted on sample areas of the project

    for each discipline of the MEP systems as per the scope of work. This spot check is

    an indication of the general condition of the design and must not be taken as a

    complete list of design issues that might impact construction activities. The designreviewer reserves the right to highlight more issue should they arise in the future.

    The information presented in this report is based on the Issued for Construction (IFC)

    drawings, specifications and relevant calculations issued for the project.

    It must be noted that the review was done without altering any design parameters

    used by the original designer.

    The following is a summary of the design review for the underground MEP systems

    for all buildings. Supporting documents and more information may be found in

    subsequent sections (Underground services for this report means: All services

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    6/292

    DVR 251011/109 P a g e | 6 /292

    running below the lowest slab in a building and do not include analysis of

    underground services running outside the building):

    B. MethodologyA comprehensive review of IFC documents (MEP drawings, specifications andcalculations) was carried out using the best up-to-date quality assurance procedures to

    identify best practice that should be used and current problems in the design that

    should be avoided. The verification also considers the requirements for installation,

    commissioning, operation and control and subsequent maintenance of systems

    selected at the design stage.

    The design verification process provides information on required design inputs,

    outputs and practical key design watch-points for MEP building services topics which

    will lead to improvements in the subsequent implementation of the design, and

    reduce the risk of problems occurring during installation, commissioning or systemoperation. This was expressed as a summary tables as shown in further pages. These

    tables are then followed by detailed analysis for the drawings or specifications. The

    analysis will include minor and major comments, inconsistency and contradiction

    between drawings and/or drawings against specifications, lack of coordination with

    other trades and ended by recommendations.

    C. Summary of FindingsTables (M.1-M.13 & E.1-E.13) provide a summary of the following:

    1. Availability of design documents: The review included checking for completenessof design documents such as drawings, specifications, calculations, detailsetc

    2. Consistency between design documents within the same discipline: The reviewincluded examination of level of consistency between design documents prior to

    checking against sample outputs

    3. Coordination between design documents of an MEP discipline and otherdisciplines: The review included examination of coordination level between

    various disciplines such as between drainage and structural or grounding and

    structural

    4. Compliance of design with International Standards and project requirementslisted in the specifications: The review included examination of compliance level

    of the design with projects standards

    The following observations were noted for the systems reviewed namely

    UndergroundServices:

    1. Some data are available for some buildings but not others, such as detailsdrawings; we have assumed such data are typical to all buildings.

    2. Some buildings designs were compliant with specifications requirements butothers were not

    3. Some designs that comply with specifications requirements were not compliantwith International Standards listed in the same specifications

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    7/292

    DVR 251011/109 P a g e | 7 /292

    4. Many of the designs did not comply with sample calculations outputs.The following is a summary of review result for Mechanical and Electrical

    disciplines:

    1. Mechanical:a. HVAC (Not included in this report)b. Water (Only for underground services)

    The design does not contain any water tanks or pipes that shall impact

    underground services

    c. Waste and Soil Drainage (Only for underground services)The following is a summary of findings in regards to above system. More

    details, calculations and references may be found in subsequent sections:

    i. In general, it appears that gravity pipe sizes are adequate and in somecases oversized which is acceptable

    ii. In many cases, the forced flow discharge pipes are undersized (Up to1000 Pa/m)

    iii. There are many discrepancies in regards to sump pit sizes and depthsbetween MEP floor plans, calculations and structural plans and sections

    iv.

    Many sump pit sizes were underestimated. Detailed calculations weredone and sizes on design drawings were found to be less than required

    either due to deep pipe falls, pump physical size or flow

    v. Sump pump calculations in many buildings were based on incorrectparameters. Such parameters include incorrect fixture units, rainfall

    intensities, areasetc

    vi. Slopes of many pipes are not as per standards (UPC or IPC)vii. In many cases where pipes are running in a raft slab, the long pipe run

    final elevation is close to raft bottom. This is an issue that a structural

    engineer must review and provide an opinion. Also, this shall impact pit

    depths

    viii. Pipe connection between elevator drain to sump pit is not considering thelow level of elevator drain connection. Also, flow from fire fighters

    elevator drain is not considered in pump sizing

    ix. There are no sand traps at the entry of sump pitsx. There are no information (size, capacity, calculationsetc) provided for

    grease trap in WH06. Location of grease trap is close to populated areas

    which is going to cause bad odors to transfer to restaurant and other

    areas. Also, the grease trap is not shown on structural drawings

    xi. There is no service connection to grey water tank in WH06 shown onplans or riser diagrams. All drainage from above floors is directly

    connected to waste water network outside the building without any

    recycling. Note that the design includes a set of calculations for this tank.

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    8/292

    DVR 251011/109 P a g e | 8 /292

    In other buildings waste pipes are not connected to either external

    network or grey water tanks

    xii. There are many discrepancies in regards to grey water tank size betweencalculations, plans and structural drawings (In KB01, calculated size was

    102 m3 and on MEP plans is shown as 216 m3)

    xiii. All grey water tanks are oversized. In general, this is acceptable for othertypes of tanks. However, in a grey water system it is dangerous to store

    untreated water more than 72 hours (IPC). It was found that tanks were

    sized to store grey water for an average of 6-7 days

    xiv. Most of grey water tanks are not provided with vent, make up water, overflow or drain connections

    xv. In IT01, the plumbing drawings indicate grey water tank below ground.However, the same tank is shown on structural drawings above ground

    d. Storm Water Drainage (Only for underground services)The following is a summary of findings in regards to above system. More

    details, calculations and references may be found in subsequent sections:

    i. Rainfall intensity values and area calculations were found to be incorrectand inconsistent between buildings

    e. Fire Fighting (Not included in this report)2. Electrical:

    a. Grounding & Lightning Protection (For the complete system in all buildings)The following is a summary of findings in regards to above system. More

    details, calculations and references may be found in subsequent sections:

    i. Calculations for grounding and lightning systems were not provided withIFC documents

    ii. In general, lightning system designed overall resistance is withinstandard required values

    iii. Grounding conductor for main electrical equipment is over sized (Whichis acceptable) in some buildings while in many other buildings it is

    undersized

    iv. Telecommunication clean grounding is not provided in many buildings.This means that number of grounding pits must be increased

    v. Calculated Telecommunication grounding resistance (where provided)exceeds specification requirements. This means that number of

    grounding pits and/ or rods is underestimated

    vi. General grounding for RMUs, transformers, generators, LV switchgearsis not provided for many buildings

    vii. Calculated grounding resistance for RMUs, transformers, generators, LVswitchgears (where provided) exceeds specification requirements

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    9/292

    DVR 251011/109 P a g e | 9 /292

    viii. Available earth pits do not reflect the actual number of pits required fortelecommunication, general and lightning grounding system

    ix. There are inconsistency within system installation details provided onIFC design drawings

    x. Grounding rods within raft slabs (With a thickness of 0.7-1.3 meters) areshown to be 3.0 deep (Starting at 0.3 m below FFL). However, thestandard calls for 3.0 m of rod length to be extended vertically into earth.

    Also, main ring electrode is shown on drawings to be installed 0.3 meters

    below FFL of raft. This means the ring electrode is going to be buried

    within raft. However, the specifications call for it to be 0.6 m below

    grade and the NFPA 780 calls for it to be in direct contact with earth at a

    depth of not less than 0.46 m.

    xi. There are inconsistency between specifications and drawings in regardsto rod sizes, burial depth of ring electrode, embedded conduit sizesetc

    b. Normal & Emergency Lighting (Not included in this report)c. Power & Low Voltage Distribution(Not included in this report)d. Fire Alarm & Detection (Not included in this report)e. IT Network (Not included in this report)

    III. RECOMMENDATIONSIt is of the design reviewer opinion that underground services design requires revisions to bemade prior to proceeding with production of shop drawings or site installations as follows:

    A. Mechanical:1. Water System: No design revisions are required in relation to this system for

    underground services2. Waste and Soil Drainage System: In general pipe network design requires minor

    revisions. However, sump pits, pumps, grey water system and rain water systemrequire major revision. Calculations must be re-done and results must becoordinated with other disciplines such as structural, electrical power,architecturaletc

    B. Electrical:1. Lighting and Grounding System: Calculations must be redone based on actual

    soil resistivity measurements done on site. Also, number of grounding pits, sizeand depth of rods, number of down conductors and general layout of system mustbe revised prior to producing shop drawings or start of installation on site

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    10/292

    DVR 251011/109 P a g e | 10 /292

    Plumbing Drainage System

    Building KB 01-02

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type

    Column BaseCheck Drainage PipeEncasement

    Check Sump Pit FlowCalculations

    Check Sump Pit HeadCalculations

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Gray Water TankCalculations

    Check Non-Potable Water

    Tank Calculations

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Check Coordination BetweenGray Water System &

    Structual Drawings

    Table M.1

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    11/292

    DVR 251011/109 P a g e | 11 /292

    Plumbing Drainage System

    Building KB 03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type

    RaftCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit HeadCalculations

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Gray Water TankCalculations

    Check Non-Potable WaterTank Calculations

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Check Coordination BetweenGray Water System &

    Structual Drawings

    Table M.2

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    12/292

    DVR 251011/109 P a g e | 12 /292

    Plumbing Drainage System

    Building RD 03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type Column BaseCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit Head

    Calculations

    Data is not Available, refer todetailed Analysis

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Gray Water TankCalculations Data is not Available, refer todetailed AnalysisCheck Non-Potable Water

    Tank Calculations

    Data is not Available, refer todetailed Analysis

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Check Coordination Between

    Gray Water System &Structual Drawings

    Table M.3

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    13/292

    DVR 251011/109 P a g e | 13 /292

    Plumbing Drainage System

    Building RD 04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type

    Column BaseCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit Head

    Calculations

    Data is not Available, refer todetailed Analysis

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Gray Water Tank

    Calculations Check Non-Potable Water

    Tank Calculations

    Data is not Available, refer todetailed Analysis

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Check Coordination BetweenGray Water System &

    Structual Drawings

    Table M.4

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    14/292

    DVR 251011/109 P a g e | 14 /292

    Plumbing Drainage System

    Building WH 01-04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type

    Raft FoundationCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit HeadCalculations

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Gray Water TankCalculations

    Check Non-Potable WaterTank Calculations

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Check Coordination BetweenGray Water System &

    Structual Drawings

    Table M.5

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    15/292

    DVR 251011/109 P a g e | 15 /292

    Plumbing Drainage System

    Building WH 05

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type Raft FoundationCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit HeadCalculations

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Gray Water Tank

    Calculations

    Check Non-Potable WaterTank Calculations

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Check Coordination BetweenGray Water System &

    Structual Drawings

    Table M.6

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    16/292

    DVR 251011/109 P a g e | 16 /292

    Plumbing Drainage System

    Building WH 06

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type

    RaftCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit HeadCalculations

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Gray Water TankCalculations

    Check Non-Potable WaterTank Calculations

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Check Coordination BetweenGray Water System &

    Structual Drawings

    Table M.7

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    17/292

    DVR 251011/109 P a g e | 17 /292

    Plumbing Drainage System

    Building IT 01

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type Column BaseCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit HeadCalculations

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Gray Water TankCalculations

    Check Non-Potable WaterTank Calculations

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Check Coordination BetweenGray Water System &

    Structual Drawings

    Table M.8

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    18/292

    DVR 251011/109 P a g e | 18 /292

    Plumbing Drainage System

    Building IT02

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type Column BaseCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit Head

    Calculations

    Check Coordination Between

    Sump Pit & StructuralDrawings

    Check Gray Water TankCalculations Data is not Available, refer todetailed AnalysisCheck Non-Potable Water

    Tank Calculations

    Data is not Available, refer todetailed Analysis

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Check Coordination BetweenGray Water System &

    Structual Drawings

    Table M.9

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    19/292

    DVR 251011/109 P a g e | 19 /292

    Plumbing Drainage System

    Building IT 03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type

    Column BaseCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit HeadCalculations

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Gray Water TankCalculations

    Check Non-Potable WaterTank Calculations

    Data is not Available, refer todetailed AnalysisCheck Consistency Between

    Drainage Plans, RiserDiagram & Calculations

    Check Coordination BetweenGray Water System &

    Structual Drawings

    Table M.10

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    20/292

    DVR 251011/109 P a g e | 20 /292

    Plumbing Drainage System

    Building KB 04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type Column BaseCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit HeadCalculations

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Table M.11

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    21/292

    DVR 251011/109 P a g e | 21 /292

    Plumbing Drainage System

    Building KB 05

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Check Foundation Type Column BaseCheck Drainage Pipe

    Encasement

    Check Sump Pit FlowCalculations

    Check Sump Pit HeadCalculations

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Table M.12

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    22/292

    DVR 251011/109 P a g e | 22 /292

    Plumbing Drainage System

    Building KB 06

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not provided

    Owner/Operator requirement

    Not providedCheck Foundation Type

    Column Base

    Check Drainage PipeEncasement

    Check Sump Pit FlowCalculations

    Check Sump Pit HeadCalculations

    Check Coordination BetweenSump Pit & Structural

    Drawings

    Check Consistency BetweenDrainage Plans, Riser

    Diagram & Calculations

    Table M.13

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    23/292

    DVR 251011/109 P a g e | 23 /292

    Grounding & Lightning Protection

    Building KB 01-02

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement Data not provided, refer todetailed analysis for

    assumptions

    Check type of earthingsystem to be employed (such

    as TNS or TN-C-S)

    Check local electricalcompany requirements and

    electrical supplyarrangements

    Check connections to othersystems and determine any

    clean earth requirement

    Refer to detailed analysis

    Check earthing systemcalculations Data not provided, refer todetailed analysis andcalculations

    Check schematic of mainearth bar and connections Data not provided

    Check earth termination andspace required

    Check electrical bondingdetails and provisions for

    other systems such asceilings, catering equipment

    and raised floors

    Covered in the specificationsonly

    Check relevant specificationclauses Refer to detailed analysis

    Size of mainearthing/equipotentialbonding conductors

    Refer to detailed analysis andcalculations

    Check consistency betweenelectrical drawings Refer to detailed analysis

    Check consistency betweenspecifications and drawings Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    24/292

    DVR 251011/109 P a g e | 24 /292

    Grounding & Lightning Protection

    Building KB 01-02

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Checking arrangement andlocation of earth pits (such as

    coordination with othertrades (structural,Architectural and

    mechanical))

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient

    disturbances

    Refer to detailed analysisProvide main equipotential

    bonding (required forlightning protection,

    structure, incoming services,heating and ventilation).

    Refer to detailed analysisProvide supplementarybonding conductors to

    exposed and extraneousmetal work such as trunkingtrays, ceiling grid and raised

    access floors

    Covered in the specificationsonlyCheck that removable links

    for testing are specified. Covered in the details onlyCheck that test link locationis coordinated with Architect Refer to detailed analysisCheck for provision of

    protective earth and clean

    earth bars at eachswitchroom and riserlocation

    Refer to detailed analysisConsider whether dedicated

    earths are necessary (forexample telecommunications

    and electronic systems)

    Refer to detailed analysisCheck air terminals are

    considered with correct sizeand location

    Check roof strike terminationnetwork is considered with

    correct conductor size andlocation

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    25/292

    DVR 251011/109 P a g e | 25 /292

    Grounding & Lightning Protection

    Building KB 01-02

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check down coductors areconsidered with correct

    conductor size and spacing

    Refer to detailed analysis

    Table E.1

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    26/292

    DVR 251011/109 P a g e | 26 /292

    Grounding & Lightning Protection

    Building KB-03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement

    Data not provided, refer todetailed analysis forassumptions

    Check type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement

    Refer to detailed analysis

    Check earthing systemcalculations Data not provided, refer to

    detailed analysis andcalculations

    Check schematic of main earthbar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bonding

    details and provisions for othersystems such as ceilings,

    catering equipment and raisedfloors

    Covered in the specificationsonly

    Check relevant specificationclauses

    Refer to detailed analysisSize of main

    earthing/equipotential bondingconductors

    Refer to detailed analysis andcalculations

    Check consistency betweenelectrical drawings

    Refer to detailed analysisCheck consistency betweenspecifications and drawings

    Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    27/292

    DVR 251011/109 P a g e | 27 /292

    Grounding & Lightning Protection

    Building KB-03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Checking arrangement andlocation of earth pits (such ascoordination with other trades(structural, Architectural and

    mechanical))

    Refer to detailed analysis

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient disturbances

    Refer to detailed analysisProvide main equipotential

    bonding (required for lightningprotection,

    structure, incoming services,heating and ventilation).

    Refer to detailed analysis

    Provide supplementarybonding conductors to exposed

    and extraneous metal worksuch as trunking trays, ceilinggrid and raised access floors

    Covered in the specificationsonly

    Check that removable links fortesting are specified.

    Covered in the details onlyCheck that test link location is

    coordinated with Architect

    Refer to detailed analysis

    Check for provision ofprotective earth and clean earth

    bars at each switchroom andriser location

    Refer to detailed analysis

    Consider whether dedicatedearths are necessary (for

    example telecommunicationsand electronic systems)

    Refer to detailed analysisCheck air terminals are

    considered with correct sizeand location

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

    Check down coductors are

    considered with correctconductor size and spacing

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    28/292

    DVR 251011/109 P a g e | 28 /292

    Grounding & Lightning Protection

    Building KB-03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Table E.2

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    29/292

    DVR 251011/109 P a g e | 29 /292

    Grounding & Lightning Protection

    Building RD-03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement Data not provided, refer todetailed analysis for

    assumptions

    Check type of earthingsystem to be employed (such

    as TNS or TN-C-S)

    Check local electricalcompany requirements and

    electrical supplyarrangements

    Check connections to othersystems and determine any

    clean earth requirement

    Refer to detailed analysisCheck earthing system

    calculations

    Data not provided, refer todetailed analysis and

    calculations

    Check schematic of mainearth bar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bondingdetails and provisions for

    other systems such asceilings, catering equipment

    and raised floors

    Covered in the specifications

    only

    Check relevant specificationclauses

    Refer to detailed analysisSize of main

    earthing/equipotentialbonding conductors

    Refer to detailed analysis and

    calculations

    Check consistency betweenelectrical drawings

    Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    30/292

    DVR 251011/109 P a g e | 30 /292

    Grounding & Lightning Protection

    Building RD-03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check consistency betweenspecifications and drawings

    Refer to detailed analysisChecking arrangement and

    location of earth pits (such as

    coordination with othertrades (structural,Architectural and

    mechanical))

    Refer to detailed analysis

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient

    disturbances

    Refer to detailed analysis

    Provide main equipotentialbonding (required forlightning protection,

    structure, incoming services,heating and ventilation).

    Refer to detailed analysis

    Provide supplementarybonding conductors to

    exposed and extraneousmetal work such as trunkingtrays, ceiling grid and raised

    access floors

    Covered in the specificationsonly

    Check that removable linksfor testing are specified.

    Covered in the details onlyCheck that test link location

    is coordinated with Architect

    Refer to detailed analysis

    Check for provision ofprotective earth and clean

    earth bars at eachswitchroom and riser

    location

    Refer to detailed analysis

    Consider whether dedicatedearths are necessary (for

    example telecommunicationsand electronic systems)

    Refer to detailed analysis

    Check air terminals are

    considered with correct sizeand location Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    31/292

    DVR 251011/109 P a g e | 31 /292

    Grounding & Lightning Protection

    Building RD-03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

    Check down coductors are

    considered with correctconductor size and spacing

    Refer to detailed analysis

    Table E.3

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    32/292

    DVR 251011/109 P a g e | 32 /292

    Grounding & Lightning Protection

    Building RD-04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement Data not provided, refer todetailed analysis for

    assumptionsCheck type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement

    Refer to detailed analysis

    Check earthing systemcalculations

    Data not provided, refer todetailed analysis and

    calculations

    Check schematic of mainearth bar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bondingdetails and provisions for

    other systems such as ceilings,catering equipment and raised

    floors

    Covered in the specificationsonlyCheck relevant specification

    clauses Refer to detailed analysis

    Size of mainearthing/equipotentialbonding conductors

    Refer to detailed analysis

    and calculations

    Check consistency betweenelectrical drawings

    Refer to detailed analysisCheck consistency betweenspecifications and drawings

    Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    33/292

    DVR 251011/109 P a g e | 33 /292

    Grounding & Lightning Protection

    Building RD-04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Checking arrangement andlocation of earth pits (such ascoordination with other trades(structural, Architectural and

    mechanical))

    Refer to detailed analysis

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient disturbances

    Refer to detailed analysisProvide main equipotential

    bonding (required forlightning protection,

    structure, incoming services,heating and ventilation).

    Refer to detailed analysis

    Provide supplementarybonding conductors to

    exposed and extraneous metalwork such as trunking trays,ceiling grid and raised access

    floors

    Covered in the specificationsonly

    Check that removable linksfor testing are specified.

    Covered in the details onlyCheck that test link location is

    coordinated with Architect

    Refer to detailed analysis

    Check for provision ofprotective earth and clean

    earth bars at each switchroomand riser location

    Refer to detailed analysis

    Consider whether dedicatedearths are necessary (for

    example telecommunicationsand electronic systems)

    Refer to detailed analysis

    Check air terminals areconsidered with correct size

    and location

    Refer to detailed analysis

    Check roof strike terminationnetwork is considered with

    correct conductor size andlocation

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    34/292

    DVR 251011/109 P a g e | 34 /292

    Grounding & Lightning Protection

    Building RD-04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check down coductors areconsidered with correct

    conductor size and spacing

    Refer to detailed analysis

    Table E.4

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    35/292

    DVR 251011/109 P a g e | 35 /292

    Grounding & Lightning Protection

    Building WH 01-04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement Data not provided, refer todetailed analysis for

    assumptionsCheck type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement Refer to detailed analysis

    Check earthing systemcalculations Data not provided, refer to

    detailed analysis andcalculations

    Check schematic of main earthbar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bondingdetails and provisions for other

    systems such as ceilings,catering equipment and raised

    floors

    Covered in the specificationsonlyCheck relevant specification

    clauses Refer to detailed analysis

    Size of mainearthing/equipotential bonding

    conductors

    Refer to detailed analysis andcalculationsCheck consistency between

    electrical drawings Refer to detailed analysis

    Check consistency betweenspecifications and drawings

    Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    36/292

    DVR 251011/109 P a g e | 36 /292

    Grounding & Lightning Protection

    Building WH 01-04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Checking arrangement andlocation of earth pits (such ascoordination with other trades(structural, Architectural and

    mechanical))

    Refer to detailed analysis

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient disturbances

    Refer to detailed analysisProvide main equipotential

    bonding (required for lightningprotection,

    structure, incoming services,heating and ventilation).

    Refer to detailed analysis

    Provide supplementarybonding conductors to exposed

    and extraneous metal worksuch as trunking trays, ceilinggrid and raised access floors

    Covered in the specificationsonly

    Check that removable links fortesting are specified. Covered in the details only

    Check that test link location iscoordinated with Architect Refer to detailed analysis

    Check for provision ofprotective earth and clean earth

    bars at each switchroom and

    riser location

    Refer to detailed analysis

    Consider whether dedicatedearths are necessary (for

    example telecommunicationsand electronic systems)

    Refer to detailed analysisCheck air terminals are

    considered with correct sizeand location

    Refer to detailed analysis

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    37/292

    DVR 251011/109 P a g e | 37 /292

    Grounding & Lightning Protection

    Building WH 01-04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check down coductors areconsidered with correct

    conductor size and spacing

    Table E.5

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    38/292

    DVR 251011/109 P a g e | 38 /292

    Grounding & Lightning Protection

    Building WH-05

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement Data not provided, refer todetailed analysis for

    assumptionsCheck type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement Refer to detailed analysis

    Check earthing systemcalculations Data not provided, refer to

    detailed analysis andcalculations

    Check schematic of main earthbar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bonding

    details and provisions for othersystems such as ceilings,

    catering equipment and raisedfloors

    Covered in the specificationsonly

    Check relevant specificationclauses Refer to detailed analysisSize of main

    earthing/equipotential bondingconductors

    Refer to detailed analysis andcalculations

    Check consistency betweenelectrical drawings

    Refer to detailed analysisCheck consistency betweenspecifications and drawings

    Refer to detailed analysisChecking arrangement and

    location of earth pits (such ascoordination with other trades(structural, Architectural and

    mechanical))

    Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    39/292

    DVR 251011/109 P a g e | 39 /292

    Grounding & Lightning Protection

    Building WH-05

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient disturbances

    Refer to detailed analysis

    Provide main equipotentialbonding (required for lightningprotection,

    structure, incoming services,heating and ventilation).

    Provide supplementarybonding conductors to exposed

    and extraneous metal worksuch as trunking trays, ceilinggrid and raised access floors

    Covered in the specificationsonly

    Check that removable links for

    testing are specified.

    Covered in the details only

    Check that test link location iscoordinated with Architect Refer to detailed analysis

    Check for provision ofprotective earth and clean earth

    bars at each switchroom andriser location

    Refer to detailed analysis

    Consider whether dedicatedearths are necessary (for

    example telecommunicationsand electronic systems)

    Refer to detailed analysis

    Check air terminals areconsidered with correct size

    and location

    Refer to detailed analysis

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

    Check down coductors are

    considered with correctconductor size and spacing

    Table E.6

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    40/292

    DVR 251011/109 P a g e | 40 /292

    Grounding & Lightning Protection

    Building WH-06

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement Data not provided, refer todetailed analysis for

    assumptions

    Check type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement Refer to detailed analysis

    Check earthing systemcalculations

    Data not provided, refer todetailed analysis and

    calculations

    Check schematic of main earthbar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bonding

    details and provisions for othersystems such as ceilings,

    catering equipment and raisedfloors

    Covered in the specifications

    only

    Check relevant specificationclauses

    Refer to detailed analysisSize of main

    earthing/equipotential bondingconductors

    Check consistency between

    electrical drawings Refer to detailed analysis

    Check consistency between

    specifications and drawings

    Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    41/292

    DVR 251011/109 P a g e | 41 /292

    Grounding & Lightning Protection

    Building WH-06

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Checking arrangement andlocation of earth pits (such ascoordination with other trades(structural, Architectural and

    mechanical))

    Refer to detailed analysis

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient disturbances

    Refer to detailed analysis

    Provide main equipotentialbonding (required for lightning

    protection,structure, incoming services,

    heating and ventilation).

    Provide supplementary

    bonding conductors to exposedand extraneous metal work

    such as trunking trays, ceilinggrid and raised access floors

    Covered in the specificationsonly

    Check that removable links fortesting are specified. Covered in the details only

    Check that test link location iscoordinated with Architect Refer to detailed analysis

    Check for provision ofprotective earth and clean earth

    bars at each switchroom andriser location

    Refer to detailed analysisConsider whether dedicated

    earths are necessary (forexample telecommunications

    and electronic systems)

    Refer to detailed analysisCheck air terminals are

    considered with correct sizeand location

    Refer to detailed analysis

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    42/292

    DVR 251011/109 P a g e | 42 /292

    Grounding & Lightning Protection

    Building WH-06

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check down coductors areconsidered with correct

    conductor size and spacing

    Table E.7

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    43/292

    DVR 251011/109 P a g e | 43 /292

    Grounding & Lightning Protection

    Building IT-01

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement

    Data not provided, refer to

    detailed analysis forassumptions

    Check type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement

    Refer to detailed analysis

    Check earthing systemcalculations Data not provided, refer to

    detailed analysis andcalculations

    Check schematic of main earthbar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bondingdetails and provisions for other

    systems such as ceilings,catering equipment and raised

    floors

    Covered in the specificationsonly

    Check relevant specificationclauses Refer to detailed analysisSize of main

    earthing/equipotential bondingconductors

    Refer to detailed analysis andcalculationsCheck consistency between

    electrical drawings Refer to detailed analysisCheck consistency betweenspecifications and drawings Refer to detailed analysisChecking arrangement and

    location of earth pits (such ascoordination with other trades

    (structural, Architectural andmechanical))

    Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    44/292

    DVR 251011/109 P a g e | 44 /292

    Grounding & Lightning Protection

    Building IT-01

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient disturbances

    Refer to detailed analysisProvide main equipotential

    bonding (required for lightningprotection,

    structure, incoming services,heating and ventilation).

    Refer to detailed analysis

    Provide supplementarybonding conductors to exposed

    and extraneous metal worksuch as trunking trays, ceilinggrid and raised access floors

    Covered in the specificationsonly

    Check that removable links fortesting are specified. Covered in the details only

    Check that test link location iscoordinated with Architect Refer to detailed analysis

    Check for provision ofprotective earth and clean earth

    bars at each switchroom andriser location

    Refer to detailed analysis

    Consider whether dedicatedearths are necessary (for

    example telecommunicationsand electronic systems)

    Refer to detailed analysis

    Check air terminals areconsidered with correct size

    and location

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

    Check down coductors are

    considered with correctconductor size and spacing

    Refer to detailed analysis

    Table E.8

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    45/292

    DVR 251011/109 P a g e | 45 /292

    Grounding & Lightning Protection

    Building IT-02

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not providedSoil resistivity measurement

    Data not provided, refer todetailed analysis for

    assumptions

    Check type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement

    Refer to detailed analysis

    Check earthing systemcalculations

    Data not provided, refer todetailed analysis and

    calculations

    Check schematic of main earthbar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bondingdetails and provisions for other

    systems such as ceilings,

    catering equipment and raisedfloors

    Covered in the specificationsonly

    Check relevant specificationclauses Refer to detailed analysis

    Size of mainearthing/equipotential bonding

    conductors Refer to detailed analysis andcalculations

    Check consistency betweenelectrical drawings

    Refer to detailed analysisCheck consistency betweenspecifications and drawings

    Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    46/292

    DVR 251011/109 P a g e | 46 /292

    Grounding & Lightning Protection

    Building IT-02

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Checking arrangement andlocation of earth pits (such ascoordination with other trades(structural, Architectural and

    mechanical))

    Refer to detailed analysis

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient disturbances

    Refer to detailed analysisProvide main equipotential

    bonding (required for lightningprotection, structure, incoming

    services, heating andventilation).

    Refer to detailed analysis

    Provide supplementary

    bonding conductors to exposedand extraneous metal work

    such as trunking trays, ceilinggrid and raised access floors

    Covered in the specificationsonly

    Check that removable links fortesting are specified. Covered in the details only

    Check that test link location iscoordinated with Architect Refer to detailed analysis

    Check for provision of

    protective earth and clean earthbars at each switchroom and

    riser location

    Refer to detailed analysis

    Consider whether dedicatedearths are necessary (for

    example telecommunicationsand electronic systems)

    Refer to detailed analysis

    Check air terminals areconsidered with correct size

    and location

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    47/292

    DVR 251011/109 P a g e | 47 /292

    Grounding & Lightning Protection

    Building IT-02

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

    Check down coductors are

    considered with correctconductor size and spacing

    Refer to detailed analysis

    Table E.9

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    48/292

    DVR 251011/109 P a g e | 48 /292

    Grounding & Lightning Protection

    Building IT-03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement Data not provided, refer todetailed analysis for

    assumptionsCheck type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement

    Refer to detailed analysis

    Check earthing systemcalculations

    Data not provided, refer todetailed analysis and

    calculations

    Check schematic of main earthbar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bonding

    details and provisions for othersystems such as ceilings,

    catering equipment and raisedfloors

    Covered in the specificationsonly

    Check relevant specificationclauses

    Refer to detailed analysisSize of main

    earthing/equipotential bondingconductors

    Refer to detailed analysis andcalculationsCheck consistency between

    electrical drawings Refer to detailed analysis

    Check consistency betweenspecifications and drawings

    Refer to detailed analysisChecking arrangement and

    location of earth pits (such as

    coordination with other trades(structural, Architectural and

    Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    49/292

    DVR 251011/109 P a g e | 49 /292

    Grounding & Lightning Protection

    Building IT-03

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    mechanical))

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient disturbances

    Refer to detailed analysisProvide main equipotential

    bonding (required for lightningprotection,

    structure, incoming services,heating and ventilation).

    Refer to detailed analysis

    Provide supplementarybonding conductors to exposed

    and extraneous metal worksuch as trunking trays, ceilinggrid and raised access floors

    Covered in the specificationsonly

    Check that removable links for

    testing are specified.

    Covered in the details onlyCheck that test link location is

    coordinated with Architect Refer to detailed analysisCheck for provision of

    protective earth and clean earthbars at each switchroom and

    riser location

    Refer to detailed analysis

    Consider whether dedicatedearths are necessary (for

    example telecommunicationsand electronic systems)

    Refer to detailed analysis

    Check air terminals areconsidered with correct size

    and location

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

    Check down coductors are

    considered with correctconductor size and spacing

    Table E.10

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    50/292

    DVR 251011/109 P a g e | 50 /292

    Grounding & Lightning Protection

    Building KB-04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement

    Data not provided, refer todetailed analysis for

    assumptions

    Check type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement

    Refer to detailed analysis

    Check earthing systemcalculations

    Data not provided, refer todetailed analysis and

    calculations

    Check schematic of main earthbar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bonding

    details and provisions for othersystems such as ceilings,

    catering equipment and raisedfloors

    Covered in the specificationsonly

    Check relevant specificationclauses

    Refer to detailed analysisSize of main

    earthing/equipotential bondingconductors

    Refer to detailed analysis andcalculationsCheck consistency between

    electrical drawings Refer to detailed analysisCheck consistency betweenspecifications and drawings Refer to detailed analysisChecking arrangement and

    location of earth pits (such as

    coordination with other trades(structural, Architectural and

    Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    51/292

    DVR 251011/109 P a g e | 51 /292

    Grounding & Lightning Protection

    Building KB-04

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    mechanical))

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient disturbances

    Refer to detailed analysis

    Provide main equipotentialbonding (required for lightning

    protection,structure, incoming services,

    heating and ventilation).

    Provide supplementarybonding conductors to exposed

    and extraneous metal worksuch as trunking trays, ceilinggrid and raised access floors

    Covered in the specificationsonlyCheck that removable links for

    testing are specified. Covered in the details onlyCheck that test link location is

    coordinated with Architect Refer to detailed analysisCheck for provision of

    protective earth and clean earthbars at each switchroom and

    riser location

    Consider whether dedicated

    earths are necessary (forexample telecommunications

    and electronic systems)

    Check air terminals are

    considered with correct sizeand location

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

    Check down coductors are

    considered with correctconductor size and spacing

    Refer to detailed analysis

    Table E.11

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    52/292

    DVR 251011/109 P a g e | 52 /292

    Grounding & Lightning Protection

    Building KB-05

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement

    Not provided

    Soil resistivity measurement Data not provided, refer todetailed analysis for

    assumptionsCheck type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement

    Refer to detailed analysis

    Check earthing systemcalculations

    Data not provided, refer todetailed analysis and

    calculationsCheck schematic of main earth

    bar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bondingdetails and provisions for other

    systems such as ceilings,catering equipment and raised

    floors

    Covered in the specificationsonly

    Check relevant specificationclauses Refer to detailed analysis

    Size of mainearthing/equipotential bonding

    conductors Refer to detailed analysis andcalculations

    Check consistency betweenelectrical drawings Refer to detailed analysis

    Check consistency betweenspecifications and drawings Refer to detailed analysisChecking arrangement and

    location of earth pits (such ascoordination with other trades Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    53/292

    DVR 251011/109 P a g e | 53 /292

    Grounding & Lightning Protection

    Building KB-05

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    (structural, Architectural andmechanical))

    Check the use of transientearth clamps for clamping

    different earthing systems to

    prevent transient disturbances

    Refer to detailed analysisProvide main equipotential

    bonding (required for lightningprotection,

    structure, incoming services,heating and ventilation).

    Refer to detailed analysis

    Provide supplementarybonding conductors to exposed

    and extraneous metal worksuch as trunking trays, ceilinggrid and raised access floors

    Covered in the specificationsonly

    Check that removable links fortesting are specified. Covered in the details onlyCheck that test link location is

    coordinated with Architect Refer to detailed analysisCheck for provision of

    protective earth and clean earthbars at each switchroom and

    riser location

    Refer to detailed analysisConsider whether dedicated

    earths are necessary (forexample telecommunications

    and electronic systems)

    Refer to detailed analysis

    Check air terminals areconsidered with correct size

    and location

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

    Refer to detailed analysisCheck down coductors are

    considered with correctconductor size and spacing

    Table E.12

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    54/292

    DVR 251011/109 P a g e | 54 /292

    Grounding & Lightning Protection

    Building KB-06

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Final design report Not providedOwner/Operator requirement Not providedSoil resistivity measurement

    Data not provided, refer todetailed analysis for

    assumptionsCheck type of earthing systemto be employed (such as TNS

    or TN-C-S)

    Check local electricalcompany requirements and

    electrical supply arrangements

    Check connections to othersystems and determine any

    clean earth requirement

    Refer to detailed analysis

    Check earthing systemcalculations

    Data not provided, refer todetailed analysis and

    calculations

    Check schematic of main earthbar and connections

    Data not provided

    Check earth termination andspace required

    Check electrical bonding

    details and provisions for othersystems such as ceilings,

    catering equipment and raisedfloors

    Covered in the specificationsonly

    Check relevant specificationclauses

    Refer to detailed analysisSize of main

    earthing/equipotential bondingconductors

    Refer to detailed analysis andcalculationsCheck consistency between

    electrical drawings Refer to detailed analysis

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    55/292

    DVR 251011/109 P a g e | 55 /292

    Grounding & Lightning Protection

    Building KB-06

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check consistency betweenspecifications and drawings

    Refer to detailed analysisChecking arrangement and

    location of earth pits (such as

    coordination with other trades(structural, Architectural andmechanical))

    Refer to detailed analysis

    Check the use of transientearth clamps for clamping

    different earthing systems toprevent transient disturbances

    Refer to detailed analysis

    Provide main equipotentialbonding (required for lightning

    protection,structure, incoming services,

    heating and ventilation).

    Refer to detailed analysis

    Provide supplementarybonding conductors to exposed

    and extraneous metal worksuch as trunking trays, ceilinggrid and raised access floors

    Covered in the specificationsonly

    Check that removable links fortesting are specified. Covered in the details only

    Check that test link location iscoordinated with Architect Refer to detailed analysis

    Check for provision ofprotective earth and clean earthbars at each switchroom and

    riser location

    Refer to detailed analysis

    Consider whether dedicatedearths are necessary (for

    example telecommunicationsand electronic systems)

    Refer to detailed analysis

    Check air terminals areconsidered with correct size

    and location

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    56/292

    DVR 251011/109 P a g e | 56 /292

    Grounding & Lightning Protection

    Building KB-06

    Verification Checklist Summary

    Key Design Checks

    Checked Compliance

    Notes & Remarks

    Yes

    No

    Not

    Applicable

    Yes

    No

    Partially

    Not

    Applicable

    Check roof strike terminationnetwork is considered withcorrect conductor size and

    location

    Check down coductors are

    considered with correctconductor size and spacing

    Table E.13

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    57/292

    DVR 251011/109 P a g e | 57 /292

    IV. DETAILED ANALYSISA. MECHANICAL

    1. Public healthBelow is the detailed analysis related to plumbing drainage system considering the

    methodology specified above:

    a. BUILDING.(KB01&02)Underground piping, submersible pumps and pits, gray water concrete tank and

    related calculations have been reviewed.

    I. DESIGN PARAMETERS:The followings table shows the design parameters used in the IFC design documents and

    those extracted through the design review process

    Table M.14 : Design parameters

    ItemIFC Design Required Parameters

    Value Reference Value Reference

    Parking drain Fixtures Units 21 UPC 8 UPC2

    AHU & FCU Fixtures Units 2 UPC 2 UPC3

    Floor Drain Fixtures Units 2 UPC 2 UPC3

    Slope of Drainage piping

    (100 & 150 mm Diameters)Not

    Indicated- 1% IPC4

    Rainfall intensity 758 mm/hr UPC 50 mm/hr UPC5

    WC Flush flow rateNot

    Indicated-

    6.1 liter(1.6

    gallon/flush)UPC6

    Number of persons per m2Not

    Indicated- 14

    Plumbing EngineeringServicing Design

    Guide- The Institute ofPlumbing 20027

    Water consumption ratio per

    shower

    NotIndicated

    -5%

    Water consumption ratio pertoilet flushing

    NotIndicated

    - 32%

    Water consumption ratio per

    Laundry

    NotIndicated

    -20%

    Water consumption ratio per

    kitchen

    NotIndicated

    -15%

    Water consumption ratio per

    basin

    NotIndicated

    -9%

    1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPCcalls for 8 FU to be used in calculations.

    2. Refer to Appendix A, PageA.33. Refer to Appendix A, PageA.24. Refer to appendix A, Page A.11

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    58/292

    DVR 251011/109 P a g e | 58 /292

    Table M.14 : Design parameters

    ItemIFC Design Required Parameters

    Value Reference Value Reference5. Refer to Appendix A, Page A.56. Refer to Appendix A, Page A.17. Refer to Appendix A, Page A.48. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50

    mm/hr

    II. SUMP PITS & SUBMERSIBLE PUMPS (DSP-1):1. Submersible pump-1 (DSP-1) has been reviewed as an example for others in

    the same building. Results of this review indicate that same issues are found

    in other areas within the same building

    2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structuraldrawings and sections have been reviewed, the following table shows the

    results:

    Table M.15 ; DSP-1 Design data as per IFC Design Drawings & Calculations Output from design

    review

    IFC Mechanical Drawings IFC Calculations IFC Structural DrawingsDesign Review

    Output

    Plan Riser Plan Sections

    Drawingsreference

    3

    rd

    BasementMaster FloorPlumbing

    Plan(P-101)

    GroundFloor Master

    PlumbingPlan

    (P-116)

    SanitarySewerSystemRiser

    Diagram (P-401)

    CalculationsJ09-07800

    MasterFound-

    Ation Plan(S101)

    Sections &Details

    ( S-201)N/A

    FoundationType Column Base (Footing)

    Location3rd BasementGrids (A&5)

    N/A -

    3rdBasement

    Grids(A&5)

    - N/A

    Encasementfor DrainagePipe Under

    ground

    Not shown - - Shown ShownShould be indicated

    on Plumbingdrawings

    Pump Data

    2 pumpsFlow = 2.6

    L/s each

    Head = 1.2Bar

    Notprovided

    Not available - -

    2 pumps, flow = 2.2L/s each

    Head = 2.0 Bar

    IFC Pumpsaccepted

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    59/292

    DVR 251011/109 P a g e | 59 /292

    Table M.15 ; DSP-1 Design data as per IFC Design Drawings & Calculations Output from design

    review

    IFC Mechanical Drawings IFC Calculations IFC Structural DrawingsDesign Review

    Output

    Plan Riser Plan Sections

    Pit Size1.0 x 1.0x1.6

    m3Not

    providedNot available

    1.0 m x 1.0m

    Depth isnot

    available

    1.8 x 1.8 x2.4 m3

    1.3 x 1.3 x 2.0 m3

    Pumpdischargepipe size(ForcedFlow)

    100 mmNot

    providedNot provided 100 mm

    Sump pit Service

    Mechanical Drawings Calculations StructuralDesign Review

    Output

    Plan Riser Plan Sections

    Parkingdrains Included Included Not Included N/A N/A

    Should be indicatedon riser diagram

    and considered incalculations

    Elevator PitNot Included

    NotIncluded

    Not Included N/A N/AShould be includedin plans, riser and

    calculations

    Condensatedrain Not Included

    NotIncluded

    Not Included N/A N/AShould be shownon plans, riser and

    calculationsRed: Not Acceptable, Orange: Partially, Green: Acceptable

    3. Description of above findings:a. Pump Flow rate:

    i. In the same discipline there is discrepancy in the Tag numbersbetween risers, calculations and plans. Same mismatching found with

    other disciplines like structural

    ii. It is required to drain the elevator pit with a separate pump set or witha floor drain connected to sump pit.

    iii. Flow of condensate drain from FCUs & AHUs is not considered indesign calculations and not shown on plans or risers

    4. Pump Head:Calculations are not included in IFC design for pump head

    5. Pit Size:a. Modified calculations based on the above will change pit sizeb. Duplex Pump sizes are not taken into considerationc. Effective volume is not properly calculatedd. Pit depth is less than required (Waste pipe invert level connected to

    sump pit is not taken into consideration)

    e. Elevator pit is not taken into consideration in sizing the pit depth

  • 7/29/2019 MEP Design Verification Report-Report No. 1-Underground Services-Final- Rev 1

    60/292

    DVR 251011/109 P a g e | 60 /292

    f. No sand trap is provided at waste pipe connected to sump pit6. Sample calculations:-Below is a sample calculation for DSP-1

    a. Flow Rate calculations:Consists of all waste water connected into sump pit-1 including:

    i. Parking drainsii. Condensate drains

    iii. Floor drainsThe following table shows flow of connected fixtures to DSP-1 done by design reviewer

    (IFC Design does not contain similar calculations):

    Table M.16 : Connected Fixtures to DSP-1

    D.F.U.VNumberFixture

    TotalUnit

    264810Parking Drains

    1226AHU & FCU1226Floor Drain

    104--Total Fixtures units70 GPM(4.4 L/s)

    --Total Fixtures Flow Rate*

    75%Diversity (All systems shall not work together in any case)

    52.5 GPM

    (3.3 L/s)

    Total Flow

    Reference for converting D.F.U.V to flow rate is NBS Monograph, Fig 3-3 NBS Monograph 31, Design-flow curves for plumbing-drainage systems. Refer to Appendix A, Page A.15

    b. Pump head calculations done by design reviewer (IFC design does notcontain similar calculations):

    The below table shows pump head calculations for DSP-1

    Table M.17 : Pump Head Calculations

    StaticHead