Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
* ~, ~~'K+.
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
In the Matter of
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
('Indian Point Station, Unit No. 2)
Docket No. 50-247 (Extension of Interim
Operation Period)
CON EDISON'S MEMORANDUM IN REPLY TO NRC REGULATORY STAFF'S PROPOSED FINDINGS OF FACT AND
CONCLUSIONS OF LAW AND SUPPORTING MEMORANDUM
- NOTICE THE ATTACHED FILES ARE OFFICIAL RECORDS OF THE DIVISION OF DOCUMENT CONTROL. THEY HAVE BEEN CHARGED TO YOU FOR A LIMITED TIME PERIOD AND MUST BE RETURNED TO THE RECORDS FACILITY BRANCH 016. PLEASE DO NOT SEND DOCUMENTS CHARGED OUT THROUGH THE MAIL. REMOVAL OF ANY PAGE(S) FROM DOCUMENT FOR REPRODUCTION MUST BE REFERRED TO FILE PERSONNEL.
'Regulatory Docket hie DEADLINE RETURN DATE
RECORDS FACILITY BRANCH
:4,~ A 19,77
L ,
8111120241 0504 PDR ADOICK 05000247 G PDR
Leonard M. Trosten Eugene R. Fidell M. Reamy Ancarrow LeBOEUF, LAMB, LEIBY & MacRAE
1757 N Street, N.W. Washington, D.C. 20036 (202) 457-7500
Edward J. Sack Joyce P. Davis Consolidated Edison Company
of New York, Inc. 4 Irving Place
New York, New York 10003
Attorneys for Consolidated Edison Company of New York, Inc.
TABLE OF CONTENTS
Page
INTRODUCTION....................
ARPGUMENT ................... ..... 3
I. The Regulatory Staff, like HRFA, has sought, in essence, to compel Con Edison to show in this case that the closed-cycle cooling condition should be vacated . . . . 3
Ii. The Regulatory Staff has misconstrued the License by attempting to award different weights to evidence based, on the one hand, on plant operations and, on the other hand, other empirical data obtained and analytical tools developed since the Indian Point 2 operating-license hearing record was closed .......... 28
III. The Regulatory Staff has repudiated the testimony of its own chief biological witness that numerous portions of the Ecological Study Program require independent Staff assessment or reassessment . . . . 39
IV. The Regulatory Staff's use of the Indian Point 3 Final Environmental Statement and Commission decision represents a misinterpretation of the history of that case, a distortion of the Indian Point 3 stipulation, an abandonment of the Staff's own pr ior representations to the Commission, and, if adopted, a denial of Con Edison's right to an adjudicatory hearing........44
V. The Regulatory Staff has, if anything, confirmed that its so-called Benefit-Cost Analysis was a mere post hoc rationalization that cannot be credited.........54
CONCLUSION......................72
CITATIONS
CASES
Arkansas Power & Light Co. (Arkansas Nuclear One Unit 2), ALAB-94, 6 AEC 25 (1973).......
Consolidated Edison Co. of New York, Inc. (Indian Point Station, Unit No. 2), ALAB-188, 7 AEC 323 (1974) . . . . . ... . ....... .. ......
Consolidated Edison Co. of New York, Inc. (Indian Point Station, Unit No. 2), ALAB-198, 7 AEC 475 (1974) .... ........... .......
Consolidated Edison Co. of New York, Inc. (Indian Point Station, Unit No. 3), ALAB-287, 2 NRC 379 (1975) ....... ...................
Consolidated Edison Co. of New York, Inc. (Indian Point Station, Unit No. 3), CLI-75-14, 2 NRC 835 (1975) ....... ...................
Home Building and Loan Association v. Blaisdell, 290 U.S. 398 (1934) ..... ..............
Houston Lighting and Power Co. (South Texas Project, Unit Nos. 1 and 2), ALAB-381, 5 NRC (1977) ...... ................
New England Power Co. (NEP Units 1 and 2) and Public Service Co. of New Hampshire, Inc. (Seabrook Station, Units 1 and 2), ALAB-390, 5 NRC (1977) ...... ................
Niagara Mohawk Power Corp. (Nine Mile Point, Unit No. 2), CLI-73-28, 6 AEC 995 (1973) .......
* . . 49, 50
* . . passim
* . . 56
* . . 48
28
• . . 28
• -• 10
. . . 48, 53
Public Service Co. of New Hampshire, Inc. (Seabrook Station, Units 1 and 2), CLI-77- , 5 NRC (1977)..... ........ ............... . .
Smith v. Allwright, 321 U.S. 649 (1944) ..........
37, 51
45
Vermont Yankee Nuclear Power Corp. (Vermont Yankee Nuclear Power Station), Public Service Electric & Gas Co. (Salem Nuclear Generating Station, Units 1 and 2), Philadelphia Electric Co. (Peach Bottom Atomic Power Station, Units 2 and 3), Metropolitan Edison Co. (Three Mile Island Nuclear Station, Units 1 and 2), Duquesne Light Co. (Beaver
- ii -
Page
g • O
Page
Valley Power Station, Units 1 and 2), Philadelphia Electric Co. (Limerick Generating Station, Units 1 and 2), Public Service Electric and Gas Co. (Hope Creek Generating Station, Units 1 and 2), Pennsylvania Power and Light Co. (Susquehanna Steam Electric Station, Units 1 and 2), Union Electric Co. (Callaway Plant, Units 1 and 2), CLI-76-18, 4 NRC 470 (1976) . . . .53
Virginia Petroleum Jobbers Association v. FPC, 259 F.2d 921 (D.C. Cir. 1958) ........... ..... 9,10
STATUTES
Federal Water Pollution Control Act, 33 U.S.C. SS 1251 et seq. (Supp.V 1975) ... ..........
National Environmental Policy Act of 1969, 42 U.S.C. §S 4321 et seq. (1970 & Supp. V 1975)......
"12
- 64
REGULATIONS
10 C.F.R. § 2.102(a) (1977)
10 C.F.R. § 2.754(b) (1977)
10 C.F.R. § 2.759 (1977) . .
10 C.F.R. S 50.90 (1977) . .
10 C.F.R. Part 51 (1977) . .
...... .............. 33
S. . . . . . .... . . .. 1
..... .............. 44
..... .............. 56
. . . . .. .. . . . .. . 8
MISCELLANEOUS
Consolidated Edison Co. of New York, Inc. (Indian Point Station, Unit No. 2), Dkt. No. 50-247, Final Environmental Statement (1972) .... ............ 36
Consolidated Edison Co. of New York, Inc. (Indian Point Station, Unit No. 2), Facility Operating License No. DPR-26 (1971) ....... ................. .passim
- iii -
Page
Consolidated Edison Co. of New York, Inc. (Indian Point Station Unit No. 2), Dkt. No. 50-247, Draft Environmental Statement, NUREG-0080 (1976)........................42,43
Consolidated Edison Co. of New York, Inc. (Indian Point Station, Unit No, 2), Dkt. No. 50-247, Final Environmental Statement, NUREG-0130 (1976) . . . . .42,43
Consolidated Edison Co. of New York, Inc. (Indian Point Station, Unit No. 3), Dkt. No. 50-286, Final Environmental Statement, NUREG-75/002 (1975) . . . . passim
M4atthew 7:7. ............... ....... ..... ....... 8
Oxford English Dictionary (Compact Ed. 1971) ....... 50
Water Resources Council, Principles and Standards for Planning Water and Related Land Resources, 38 Fed. Reg. 24778 (1973).............. .58
- iv -
INTRODUCTION
On April 22, 1977, the Regulatory Staff of the
Nuclear Regulatory Commission ("the Commission") submitted
Proposed Findings of Fact and Conclusions of Law in the Form
of an Initial Decision ("Staff Proposed Findings and Conclu
sions") and a Memorandum in Support of Proposed Findings of
Fact and Conclusions of Law ("Staff Memorandum in Support").
In accordance with § 2.754(b), 10 C.F.R. § 2.754(b) (1977),
and the Order of the Atomic Safety and Licensing Board ("the
Board") in this proceeding dated April 19, 1977, Consolidated
Edison Company of New York, Inc. ("Con Edison") submits its
Reply to the documents filed by the Regulatory Staff.
Con Edison has already stated its case in its own
Proposed Findings and Conclusions and supporting Memorandum
dated March 28, 1977, and in its April 27, 1977 Reply to the
Proposed Findings and Conclusions and supporting Memorandum
filed by the Hudson River Fishermen's Association ("HRFA")
on April 14, 1977. Accordingly, a number of the points made
by the Regulatory Staff do not require further comment from
Con Edison at this time. Still, the Regulatory Staff's
submittals in numerous respects are so far off the mark,
and/or represent previously unanticipated changes of posi
tion, that it is important that these matters be identified.
The Regulatory Staff, as was the case with HRFA,
has mistaken the issue before this Board--whether the
-2
interim operation period should be extended to May 1,
1981--for the question posed by Con Edison's March 15, 1977
application to vacate the cooling system condition in the
Indian Point 2 License ("the License"). The Regulatory
Staff also has in effect asked the Board to impose a higher
burden of proof on Con Edison than that contemplated by the
License and the Commission's Rules of Practice; unlike HRFA,
however, the Staff seeks to achieve this through a cramped,
sophistical and unfounded reading of the License condition.
Further, the Staff has inexplicably repudiated the testimony
of its own biological witness that new data and analyses re
quiring independent assessment or reassessment had already
been submitted by Con Edison. Other errors that the Regu
latory Staff has committed--and which the Board would commit
by adopting the Staff's Proposed Findings and Conclusions-
will also be noted.
THE REGULATORY STAFF, LIKE HRFA, *HAS SOUGHT, IN ESSENCE, TO COMPEL CON EDISON
TO SHOW IN THIS CASE THAT THE CLOSED.CYCLE COOLING CONDITION SHOULD BE VACATED
A.
By a variety of means, the Regulatory Staff has,
in this limited proceeding on Con Edison's request for an
extension of the interim operation period at Indian Point 2,
endeavored to require Con Edison to prove the case it will
eventually have to make in support of the March 15, 1977
application to vacate the cooling system condition of the
License. One way the Staff pursues this goal is by its
insistence, in the benefit-cost analysis, that the value of
the impact of Indian Point 2 operation with once-through
cooling must equal or exceed the cost of a cooling tower,
since the effect of this equation is to place an inordinate
cost on the scales.1
1/ Staff Proposed Findings and Conclusions at 48; but see Con Edison's Memorandum in Support of Proposed Findings of Fact and Conclusions of Law ("Con Edison's Memorandum in Support") at 26-29. The Staff has claimed that its position that the cooling question has been determined does not mean that Con Edison is "automatically" precluded from obtaining the relief here requested, but only that this circumstance "enters into the determination of whether the relief should be granted." Staff Memorandum in Support at 15 n.35. In a proceeding where so much attention has been paid to the theoreti
(Footnote continued)
-4-
.IThe Regulatory Staff's presentation most directly
on point is its claim that "the evidence must show more than
the availability of'substantial amounts of new data which
might lead to a change in the cool Iing tower requirement."-V
This is stated as an argument heading on page 5 of the
Memorandum in Support, but the text on that page shows the
Staff's position to be that it is merely "reasonable to
assume that some standard of review of the data which is
more rigorous than that proposed by Con Edison was intended."13/
The Staff finds this assumption reasonable on the basis of
an asserted rejection by-the Appeal Board of an extension of
1/ Footnote continued
cal underpinnings of benefit-cost analyses, Con Edison is at a loss to understand how a consideration such as this "enters into" the decisional process. We believe that this is only an effort to pass off the merits question in the guise of just another "factor", cf. Tr. 750, to stir into the benefit-cost analysis in tHie present limited proceeding. See also p. 46, n.6 infra.
2/ Staff Memorandum in Support at 5.
3/ Con Edison has indicated that the proper test to be applied to the sufficiency of the data and analyses in this case is whether "[tihe results of Con Edison's Ecological Study Program merit independent review by the Commission and hold forth the possibility of. demonstrating by a preponderance of the evidence that closed-cycle cooling at Indian Point 2 is unnecessary," Con Edison's Memorandum in Support at 1-2 (footnote omitted) , or whether there is "a substantial possibility that after evaluation of the results of Con Edison's Ecological Study Program the Commission might conclude, on the basis of a benefit-cost analysis, that closedcycle cooling should not be required for Indian Point 2." Con Edison's Proposed Findings and Conclusions at 14.
-5-
interim operation until May 1, 1981. Unfortunately, this
premise is false, since the Appeal Board was not asked by
Con Edison to insert a "reasonable termination date" of May
1, 1981 in the License; rather, Con Edison had asked that
the date be September 1, 1981. As we have pointed out
elsewhere,-/ the difference in the two dates accounts for an
entire striped bass spawning season--an error of no small
consequence, since the present proceeding is itself con
cerned with continued operation over only one spawning
season.
Proceeding, nevertheless, from this unfounded pro
position, the Regulatory Staff has laid out a complicated
obstacle course that Con Edison must complete before the
benefits and costs of the proposed extension can even be
addressed. Most of the Staff's obstacle course is inappro
priate to this limited proceeding.
The first test is that the "conclusions based on
the data, on their face, appear to demonstrate a probability
that once-through cooling will be acceptable."-/ The Staff
goes on to assert that "[i]f these conclusions are not
sufficient, in the absence of any independent evaluation
whatsoever, to demonstrate that probability, then they
4/ Con Edison's Reply to HRFA at 46-48.
5/ Staff Memorandum in Support at 6.
-6-
certainly do not justify an extension.".' If the Regulatory
Staff's intent, with this first hurdle, is simply to test
whether the unexamined conclusions of the Ecological Study
Program point to a marked reduction in plant impact on the
striped bass such that the costs of a closed-cycle cooling
system would be less than the benefits of such a system,
then surely the test has been met in this case.- The Staff
does not appear to question Con Edison's success in over
coming this hurdle.
Second, the Regulatory Staff claims that if the
parties, "without thorough independent review of the raw
data, . . . are able to sufficiently indict the conclusions
so that their credibility is undermined to the point that
they no longer demonstrate a probability that once-through
cooling will be acceptable, then these data do not justify
an extension of interim operation."'8/ This Staff-designed
hurdle truly confuses the issues in the present proceeding
6/ Id.
7/ See, e.g., Con Edison's Proposed Findings and Conclusions at 24 et seq. (summarizing areas of new information, including evidence that entrainment mortality is less than 100%, that the f, f and f factors are less than previously though, that compensatory mechanisms operate in the Hudson River striped bass fishery, that the Hudson River is not as great a contributor to the Atlantic coastal striped bass fishery as previously thought, and that a stocking program for hatchery-reared striped bass could be useful in offsetting power plant impacts).
8/ Staff Memorandum in Support at 6-7.
-7-
with those in the proceeding on the March 15, 1977 applica
tion. For this reason Con Edison submits that it represents
an inappropriate standard which the Board should reject.
However, even if the Board imposes this excessive burden on
Con Edison, the record of this proceeding supports a finding
that this test, couched by the Staff in terms more suitable
to a criminal trial than to an administrative hearing on
environmental issues, has clearly been met. Perhaps the
best evidence that even this unduly onerous test has been
met may be found in the testimony of Dr. Webster Van Winkle,
the Staff's biological consultant and witness, who listed
for the Board a number of areas where, based upon his
review, Con Edison's Ecological Study Program had produced
results that merited independent Staff assessment or reassess
ment,2 / and which could lead to a change in his opinion on
key issues related to the need for closed-cycle cooling.-0
Third, the Staff has set up at this late date a
standard that Con Edison's data must "admit of and expedite
9/ See PP.40-42- infra; Supplemental Testimony of NRC Staff in Response to Board Comments on Aquatic Impact Analysis, Dr. Webster Van Winkle ("Van Winkle"), following Tr. 1069, at 4-5; Testimony of NRC Staff on Relative Benefits and Costs Associated with Applicant's Request for Extension of Operation with Once-Through Cooling at Indian Point Unit No. 2, Dr. Robert L. Spore and Dr. Webster Van Winkle ("Spore & Van Winkle"), following Tr. 1076, at 15-16; see Con Edison's Proposed Findings and Conclusions at 28, 33, 34, 39, 40, 48, 55.
10/ See Con Edison's Proposed Findings and Conclusions at 55; Tr. 896.
-8-
full and prompt independent review." This criterion is
discussed in Part II of this Reply, infra, but we will
simply note at this point that this hurdle--nowhere referred
to in the License or Environmental Technical Specification
Requirements, nowhere referred to in ALAB-188I -/ or the
Commission's Indian Point 3 decision 1 2/ on which the Staff
places such great reliance, nowhere referred to in the
Commission's environmental regulations,1-/ and not the
subject of any generic request by the Staff throughout the
period of litigation over cooling systems at Indian Point-
must not distract the Board from its proper inquiry. The
record of this proceeding shows that the Staff has received
considerable amounts of information from Con Edison's
Ecological Study Program literally for years without ever
having complained, prior to isolated testimony in this case,
that the form or content of the data were such as to impede
the Staff's analysis. Con Edison stands ready to answer the
Staff's questions on the results of the Study Program, but
the Staff must come forward with those questions, 1 4/ and
not lie in wait only to ambush Con Edison for past submittals
11/ Consolidated Edison Co. of New York, Inc. (Indian Point Station, Unit No. 2), ALAB-188, 7 AEC 323 (1974).
12/ Consolidated Edison Co. of New York, Inc. (Indian Point Station, Unit No. 3), CLI-75-14, 2 NRC 835 (1975).
13/ 10 C.F.R. Part 51 (1977).
14/ Matthew 7:7.
-9-
that allegedly failed to meet data requirements that could
be known only by telepathy or clairvoyance.15/
Not content with setting up three hurdles for Con
Edison to overcome, the Regulatory Staff would also indirect
ly hold the Company to the standards applicable with respect
to judicial stays. 1-6/ Thus, the Staff coyly notes that it
does not argue for the direct application of the Virginia Petroleum Jobbers criteria to this case, but instead argues by analogy that the Staff's proposed minimum tests of probability of success on the ultimate question are more than justified in light of the more rigorous criteria which govern relief in the closely analogous circumstances of a stay pending further review or rehearing.17/
Con Edison's view is that the record before the Board would
support a finding that, balancing all the Virginia Petroleum
Jobbers criteria,18/ it would meet the standard set in that
15/ Applicants for facility license amendments, no less than applicants for initial licenses, "are entitled to know both what they must undertake to do in connection with their applications and against what criteria the acceptability of their proposal will be measured." New England Power Co. (NEP Units 1 and 2) and Public Service Co. of New Hampshire, Inc. (Seabrook Station, Units 1 and 2), ALAB-390, 5 NRC (1977) (opinion of Chairman Rosenthal and Drs. Buck and Johnson), slip op. at 20.
16/ See Staff Memorandum in Support at 7-8.
17/ Id.; see generally Virginia Petroleum Jobbers Ass'n v. FPC, 259 F.2d 921 (D.C. Cir. 1958).
18/ Though all the criteria were listed in a footnote by the Regulatory Staff, it is evident that only the first-probability of success on the merits--is of interest from the Staff's point of view. This has the effect of denying any weight to such traditional and highly
(Footnote continued)
-10-
case. But Virginia Petroleum Jobbers has no application
here, as the Staff has properly noted. Since the case has
no bearing on the instant proceeding, it is of no moment
that.the Staff's proposed criteria for this case are less
onerous, as if the Staff were making some charitable gesture.
These multifarious obstacles the Staff would erect
are, with the exception of the first criterion, inappro
priate to the issue now before the Board. Where, as here,
the question is not whether the fundamental character of the
license condition should be altered, but rather whether
"there is sufficient reason to look further into the matter,"
the Board should be loath to take or require any action that
exposes a licensee to potentially needless expenditures.
Because it is evident that there are substantial issues of
fact to be tried on the merits of the cooling system question,
denial of the June 6, 1975 application would be error.
B.
In its Proposed Findings and Conclusions, the
18/ Footnote continued
pertinent concerns as the public interest, and the potential injury to the parties if the proposed action is approved or denied. Thus, the Staff has used this ostensible "analogy" in a highly selective fashion that distorts the decisional process the case contemplates.
19/ Houston Lighting and Power Co. (South Texas Project, Unit Nos. 1 and 2), ALAB-381, 5 NRC (1977), slip op. at 12-13, n.8.
-11-
Regulatory Staff has presented a highly tendentious summary
of its views of the Con Edison Ecological Study Program.
These proposed findings run from page 25 to page 43, and it
is obvious that they go far beyond the level of detail that
is relevant or appropriate to this limited proceeding--the
purpose of which is to determine whether a plenary hearing
on the results of the Ecological Study Program is warranted.
This was the guiding theme which the Board set for the
hearing in this case,- / and it should be adhered to. As
the detailed matters go beyond the issue before the Board,
findings on them are not necessary. Moreover, findings on
these points would be in derogation of the parties' rights
to a full adjudicatory hearing on the merits of the cooling
system question. For this reason we believe that any find
ings in this limited proceeding would not be entitled to res
judicata or collateral estoppel effect. Nevertheless,
because of the danger that such treatment might be afforded
to the Initial Decision in this case, even though the issues
and the depth and scope of the examination were narrowly
confined,- 1/ the Board should eschew detailed findings of
thesort requested by the Regulatory Staff. The Board
should make clear that none of its determinations in this
20/ See, e..., Tr. 66-67, 906, 912, 1262-63, 1462-63.
21/ E.g., Tr. 906, 912.
-12-
proceeding will have binding e'ffect in the subsequent
proceeding occasioned by Con Edison's March 15, 1977 license
amendment application.
For the record, however, Con Edison objects to
many of the findings and conclusions proffered by the
Regulatory Staff, and will note at least some of the major
areas of disagreement in the following paragraphs.
First, a general. comment is in order. Proposed
findings and conclusions are, to be sure, an advocate's
document. Nevertheless, they are intended to be, in our
understanding, an aid to the Licensing Board in the prepa
ration of an Initial Decision. In important respects, both
of substance and of tone, this purpose seems to have poorly
served by the Staff's submittal of April 22.
With regard to tone, we can only observe that the
provocation of needless acrimony is not in keeping with the
highest traditions of the Staff, and cannot advance the
Commission's purposes. Con Edison questions, for example,
the Regulatory Staff's compulsion to precede a neutral term
such as "larval tables" with the contemptuous modifier "so
called". 22/ Another instance may be seen in the Regulatory
Staff's attempt to cast doubt on Con Edison's contribution
data by describing the innate tag sampling method as only
22/ Staff Proposed Findings and Conclusions at 26.
-13-
going so far as "necessary to fill a quota".23/ The Staff
failed to explain, as one might have hoped, that in this
context "quota" referred not to a bare minimum, but to the
statistical quantity derived, in advance of sampling, from a 24/
carefully formulated sample design.-
Impact Assessment - The Regulatory Staff's attempt
to impeach Con Edison's entrainment mortality data is un
successful. At the hearing, witnesses for Con Edison
explained that no compairsons between larval table and net
mortality data had been conducted because larval table data,
for a number of reasons, 2-/ had not been obtained for Indian
Point.
The Regulatory Staff refers to the "limitations"
of Con Edison's net mortality correction data, although
23/ Id. at 40.
24/ Tr. 401.
25/ Larval table data had not been collected at Indian Point prior to 1977 because use of larval table technique was viewed as being in an early stage of the art, Tr. 646, and further was not deemed essential at Indian Point, where discharge velocity is substantially lower than velocities at Bowline and Roseton. In addition, despite the Regulatory Staff's insinuations to the contrary, see pp. 31-32, Con Edison's research resources are not unlimited, and Con Edison was already required by its Environmental Technical Specification Requirements to use another collection method, i.e., nets. Tr. 645. Although the Regulatory Staff attempts to obscure this point by expressing its "receptiveness" to requests for technical specification modifications, its delay in processing other such applications, see p. 36, n. 20, infra, undermines this argument.
-14-
declining to provide the Board or parties with any citation
in the record.2 6 Even assuming arguendo that such "limita
tions" might exist, Con Edison notes that the f factors
used by Con Edison for purposes of this proceeding were
derived from those used by the Staff in the Indian Point 3
FES, and that the new correction data merely provide new and
more realistic values, particularly with regard to the
critical post-yolk sac larval stage, which indicate that the
impacts are lower than those values actually used by Con
Edison.--/ These new results, which will be subject to full
examination in the proceeding for Con Edison's March 15
application, therefore constitute significant new'data
requiring reassessment of the need for closed-cycle cooling.
Although the Regulatory Staff claims to have
independently analyzed Con Edison's f1 and f2 factors in the
Indian Point 3 proceeding, Con Edison emphasizes that in
that case this analysis was based upon only the 1973 data
available at that time. Since that time, the two additional
years of important data have been obtained. Hence the
Regulatory Staff's reliance upon an analysis which does not
include recent data should be discounted.
The Regulatory Staff's innuendo that Con Edison's
1974 and 1975 sampling techniques, "[d]espite previous
26/ Staff Proposed Findings and Conclusions at 2.
27/ See Campbell, Lawler, Marcellus, May & McFadden at 28-34.
-15-
criticisms''28 / nevertheless involved certain sampling
differences, suggests that these data were collected after
such "criticism" was rendered. In fact theRegulatory
Staff's ambiguous statement is merely referring to state
ments made at the hearing in this case. In any event, the
Regulatory Staff has offered no evidence that such differences
will distort conclusions, but only asserts that they "may"
do so. In view of the fact that further reliability study,
as warranted, will confirm these data, 29/ the Regulatory
Staff has shown nothing which would detract from the use
fulenss of this data for the purposes of this limited
proceeding.
In addressing Con Edison's latent mortality
material, the Regulatory Staff implies that Con Edison
blithely relied only upon 72-hour tests. In fact, although
Witness Dr. O'Conner firmly stated that this time-span is
appropriate for testing purposes, he emphasized that "(t]he
96-hour period was not dropped"'0/ but merely failed to
provide results that were significant.3 1/
In addressing more generally Con Edison's impact
assessment, the Regulatory Staff cited its witness's state
28/ Staff Proposed Findings and Conclusions at 28.
29/ Tr. 649.
30/ Tr. 632.
31/ Id.
-16-
ment that it would be difficult to assess plant impact at
population reduction levels of less than 50%. However, this
assertion, rather than being grounded in any scientific
analysis, was expressed as the witness "sort of intuitive
feeling".132/ Con Edison, on the other hand, has conducted
latent root multiple lineal regressions which have statis
tically assessed 79% of the variation in the fish population
as resulting from natural factors.33/
Although the Regulatory Staff attempts to list a
few difficulties with Con Edison's correlation analysis,
such difficulties are apparently more imagined than real.
The citation which the Regulatory Staff gives for the
proposition that "the selection of independent variables
has a dramatic effect on the results one gets" simply does
not support that statement. The observation that the
"sampling methods" (it is assumed that what is intended
here is collection methods) utilized to determine juvenile
abudance varied over the collection period fails to also
mention Dr. Campbell's detailed discussion of the follow-up
tests conducted to test for biases resulting from this 35/
variance.- The assertion that the margin of error caused
32/ Tr. 1020.
33/ Tr. 304-05; Campbell, Lawler, Marcellus, May & McFadden at 13-14.
34/ Staff Proposed Findings and Conclusions at 31.
35/ Tr. 299-302.
-17-
by extrapolating from a 15-mile stretch to total river
abundance is unknown casts aside Dr. McFadden's express
testimony that comparison of the 15-mile index with the
index based on a broader reach of the river in other years
36/ can show the validity of the 15-mile index,!- as well as
Dr. Campbell's testimony that there exists a significant
positive correlation between the 15-mile results and
riverwide results.37/
Compensation - The Regulatory Staff states that
"the various models utilized for impact assessment by Con
Edison all employ a compensation function which tends to
make estimates of percent reduction relatively insensitive
to other impact parameters. '"--/ This discussion stops
short, failing to note witness Dr. John P. Lawler's ex
planation at the hearing "that the model is relatively
insensitive to other parameters when ';ompensation is
operative, which you should expect, because that's what
compensation is all about. It says it will offset the
changes that are imposed on the system."3 9- / Dr. Lawler
further commented that when compensation is not operative,
36/ Tr. 429.
37/ Tr. 433.
38/ Staff Proposed Findings and Conclusions at 32.
39/ Tr. 274.
-18-
the system is fairly sensitive to the other impact para
40/ meters.
The Regulatory Staff says at page 33 of its
Proposed Findings, "[tihe Staff has criticized the compensa
tion function used in the LMS Hudson River striped bass
models, pointing out the lack of a sound biological basis
for the left limb of the function and the lack of a relation
ship between any of the three parameters in the LMS compensa
tion function and measurable biological phenomenon," referenc
ing Staff Exhibit OT-2. In view of the limited significance of Staff Exhibit OT-2 in this proceeding,41- / this Exhibit
cannot support a finding on the merits of Con Edison's use 42/
of compensation.
The Regulatory Staff cites its witness Dr. Van
Winkle for the proposition "that at most the empirical
data represents a! 3uggestion that compensation has been
or is occurring in the Hudson River striped bass popula
tions." 43/ However, Dr. Van Winkle also indicated a
significant interest in examining information to be
presented in the January 1977 report-4/ and stated that
compensation in the Hudson River striped bass population
40/ Tr. 1245-46.
41/ Tr. 1081.
42/ See p. 48 n.6 infra.
43/ Staff Proposed Findings and Conclusions at 33.
44/ Tr. 925.
-19-
was an area where an independent assessment appears
essential in regard to the question of the need for closed45/imliganefoa cycle cooling at Indian Point 3,- implying a need for a
careful review of Con Edison's new data which demonstrate
that compensationis operative in the Hudson River striped
bass population.
The Regulatory Staff draws attention to the uti
lization of commercial fishery data from 1955-75 to calculate
a Ricker stock-recruitment curve, pointing out inherent
biases within the data, which allegedly severely limit
its value in demonstrating compensatory responses in the
Hudson River striped bass population.4 6- / The Staff failed,
however, to acknowledge Dr. McFadden's discussion of the
commercial fishery data in .which he pointed out
The value of the long records typically outweighs the limitations and flaws in the data, and it has been a common experience in fishery science that, with appropriate interpretation and correction of the data, it's possible to make very important use of these types data in management of fish stocks.47/
Dr. McFadden further stated
The reason for wanting to emphasize this is, some of the most important long series of data relating to our assessment of qualified impact on the Hudson River
45/ Van Winkle at 4; Spore & Van Winkle at 15-16; Tr. 1274
75, 1328.
46/ Staff Proposed Findings and Conclusions at 34.
47/ Tr. 699.
-20-
stock are of this long-term series type. And the problems that are encountered in the Hudson, in my opinion, are no different generally speaking, and no more severe, than those commonly encountered in data of this type in their use in fishery science.48/
The Regulatory Staff asserts that the other
indicators of compensation, i.e., density dependent growth,
negative correlation between striped bass juvenile abundance
and adult bluefish abundance, and bluefish predation cannot
do more than indicate a possibility that compensation
operates in the population. This is an undisputed proposi
tion. The Regulatory Staff next asserts that the possi
bility of compensation was reflected in the impact analysis
for the Indian Point 3 FES. 4 9/ As noted elsewhere in this
Reply,-- / Con Edison considers that FES to be of no pro
bative value in assessing the importance of Con Edison's
new ecological data. Furthermore, the use of compensation
in that FES was extremely limited. 51/
The Regulatory Staff opines that a "negative
correlation between the bluefish population and the
striped bass population size does not, of course, neces
sarily reflect a casual link." -- / As Con Edison has dis
48/ Id.
49/ Staff Proposed Findings and Conclusions at 36.
50/ See pp. 44-53 infra.
51/ Tr. 1246.
52/ Staff Proposed Findings and Conclusions at 36.
-21-
cussed in its Memorandum in Reply to HRFA's Proposed
Findings and Conclusions, Con Edison has not based its
conclusions on bluefish predation upon this correlation
alone, but viewed it in conjunction with additional
tests revealing the existence of striped bass in stomachs
of bluefish.5 3/
The Regulatory Staff's criticism of Con Edison's
density-dependent growth data as utilizing an "absolute
measure of growth"5 4/ does not include witness Dr. K. Perry
Campbell's statement at the hearing that "we have looked
at all three methods of analyzing growth, the incremental
growth, relative growth and instantaneous growth rates
versus density. The same relationship appears with all
three methods."
the Regulatory Staff's confused effort to mitigate
the importance of Con Edison's monthly catch/unit effort56/
fails in two respects. Use of the term "fisheries data"
implies commercial fishery data, when in fact Con Edison
used research study seine catch effort data. Hence the
statement that "actual effort varies more than measured
effort"- / is not applciable to the monthly catch/effort
53/ Con Edison's Reply to HRFA at 28-29.
54/ Staff Proposed Findings and Conclusions at 37.
55/ Tr. 324-25.
56/ Staff Proposed Findings and Conclusions at 37.
57/ Id.
-22-
data, since the citation supporting that proposition refers
to the commercial fishery context, not the seine catch/
effort data. In fact, there is necessarily a 1:1 corres
pondence between measured effort (i.e., the number of tests)
conducted in the latter program and "actual effort," since
the "measured effort" is the "actual effort."
Secondly, with regard to the Regulatory Staff's
discussion of migration as a compensatory mechanism, Con
Edison has testified that migration may lead to greater
vulnerability of fish migrating out of the area to preda
tion or other stresses.- However, the Regulatory Staff
has offered no support, not even the educated guess of an
expert witness, for its counter proposition that migration
might also lead to lesser vulnerability to predation and
other stresses.-- / In any event, such a proposition would
not detract from the fact that migration occurring during
the months of September and October could be density
dependent.- / Con Edison believes that the abundance in
September and October is another demonstration, challenged
but unrefuted in the record of this proceeding, of compensa
tory mechanisms operating within the Hudson River striped
bass population.61/
58/ Campbell, Lawler, Marcellus, May & McFadden at 49.
59/ Staff Proposed Findings and Conclusions at 37.
60/ Campbell, Lawler, Marcellus, May & McFadden at 49.
61/ Id.
-23-
Contribution - The Staff unfairly denigrates
the importance of Con Edison's new information on contri
bution of Hudson River spawned striped bass to the Atlantic
coastal fishery. This testimony constitutes a significant
advance over the state of knowledge that existed in the
Indian Point 2 operating license proceeding.
Staff's notion that the as-zlassified estimates
presented in Con Edison's Exhibit OT-2 are the same as
those relied on by the Staff in the Indian Point 3 FES
is wrong.-2/ In the Indian Point 3 FES, Staff used a
90 percent estimate of contribution to the inner zone for
its benefit-cost analysis.m63 The as-classified estimates
show 32 percent.- Staff used a "hypothesis" for the
outer zone of 10 to 50 percent, an obviously wide range.65/
The as-classified estimates showed a contribution to the
outer zone of 19 percent and an overall contribution to
66 the Atlantic coastal fishery of 23 percent.-6/ Although
these numbers are in the middle of the Staff's range, the
difference is important in view of the tendency of the
Staff to use maximum values for a benefit-cost analysis.
62/ Staff Proposed Findings and Conclusions at 38.
63/ Tr. 1032.
64/ McFadden, May & Campbell, following Tr. 1464, Table 1.
65/ Tr. 1032.
66/ McFadden, May & Campbell, Table 1.
-24-
When Con Edison counsel sought to clarify the record on
this particular point, Dr. Van-Winkle said:
I think we're a bit flogging a dead horse here. I think what's relevant is your current iterative and adjusted estimates which I'm perfectly happy to admit certainly do require reconsideration on this issue.67/
The Staff's comment that there has been no
independent assessment-8/ is irrelevant. It is not
necessary for purposes of this proceeding to determine
the correct number but only the existence of new infor
mation on a critical issue which requires independent
assessment in connection with Con Edison's application
of March 15, 1977.
The Staff's criticism of the lack of more than
one year's data is misconceived. 9- - Most of its cited
references concern a general theory of compensation and
have nothing whatever to do with the contribution study.
The reference to Tr. 715 does at least refer to a dis
cussion of the contribution testimony but in a highly
misleading manner. The testimony was that as a general
matter more years' data would be useful. Samples taken
the next year would indicate about the same results and
67/ Tr. 1553.
68/ Staff Proposed Findings and Conclusions at 38.
69/ Id. at 39.
-25-
for the data to be useful, a delay of a fairly long number
of years would be required.--- The Staff is thus seizing
upon the obvious fact that more data would be useful as
support for the very different point that the existing
data are unreliable.-7 1/ Staff ignores the timing problem
referred to above which limited the data that could be
presented by January 1977 to that which could be obtained
in a single year. The Staff also ignores the fact that
these data are vastly superior to those which existed in
the earlier proceeding and led to a wide range of estimates.
The Regulatory Staff's challenge to the assumption
that spawning fish originate in the stream in which they
are found is similarly misplaced. The record shows that
the basis for this assumption was explained- 2/ and that
the results of the contribution study themselves constitute
strong evidence for separate gene pools.7 3/ Staff apparently
seems concerned that it is impossible to establish as an
absolute certainty that a spawning fish found on spawning
grounds originated in that area, but as previously discussed,
that is not the appropriate standard for making important
public policy decisions. This is another illustration
of the Staff's attempt to destroy the results of the
70/ Tr. 716.
71/ Staff Proposed Findings and Conclusions at 41.
72/ Tr. 403.
73/ Tr. 409.
-26-
Ecological Study Program by placing an impossible hurdle
in its path, ignoring the fact that this would leave
important environmental decisions to be made on the basis
of assumptions and general theory unsupported by data.
The Staff's attempt to criticize the iterative
procedure because it is sensitive to the number of
iterations 4/ merely illustrates Staff counsel's mis
understanding of this testimony. The whole purpose of an
iterative procedure is to establish by a series of cal
culations the iteration which best fits the known sample.75/
This is a statistical procedure which necessarily provides
a different result with each iteration. Its significance
should be determined in the proceeding on Con Edison's
application of March 15, 1977, not in this proceeding.
Stocking and Other Species - The Regulatory
Staff's proposed findings on stocking and effects on
species other than striped bass again illustrate that the
Staff has confused this limited proceeding with the
proceeding to vacate the cooling system condition from
the license.2-6/ The Staff acknowledged that Con Edison
has presented significant new information which was not
present in the earlier proceeding on both these issues
74/ Staff Proposed Findings and Conclusions at 41.
75/ McFadden, May & Campbell at 9-10.
76/ Staff Proposed Findings and Conclusions at 42-43.
-27-
when it notes that Con Edison has introduced evidence on
the survival of hatchery fish through a winter and that
Con Edison has testified to the collection of data on
other species. As previously discussed this is all that
need be shown in this limited proceeding. Further,
there is nothing in the record to justify the Staff's
implication that data on other species must permit an
assessment equivalent to that made for striped bass. The
lack of significant sport or commercial value to these
other species and the fact that the Commission's Environ
mental Technical Specification Requirements do not require
equivalent data on these species negate the Staff's
implication.
-28-
II
THE REGULATORY STAFF HAS MISCONSTRUED THE LICENSE BY ATTEMPTING TO AWARD DIFFERENT
WEIGHTS TO EVIDENCE BASED, ON THE ONE HAND, ON PLANT OPERATIONS AND, ON THE OTHER HAND
EMPIRICAL DATA OBTAINED AND ANALYTICAL TOOLS DEVELOPED SINCE THE INDIAN POINT 2 OPERATING
LICENSE HEARING RECORD WAS CLOSED
Where HRFA attempted boldly to assert that Con
Edison must carry a higher burden of proof than the pre
ponderance of the evidence standard that has been establ/
lished and recognized under J[ 2(E) (1) (c) of the License,
the Regulatory Staff has sought, by a more subtle, but
equally unfounded route, to set up essentially the same
impediment to the proper disposition of the present case.
In the course of its analysis, the Regulatory Staff commits
two fundamental errors. First, it reads the provision of
the License permitting applications for relief from the
cooling system condition "with literal exactness like a
mathematical formula,"- although even that reading is
flawed. Second, it erects a complex hierarchy of types of
data analyses, and awards discrete amounts of "weight" to
each, without any basis in the applicable regulations or the
terms of the License.
1/ See Con Edison's Reply to HRFA at 15-16; Con Edison's Memorandum in Support at 2 n.l.
2/ Home Building & Loan Ass'n v. Blaisdell, 290 U.S. 398, 428 (1934).
-29-
The License authorizes applications such as Con
Edison's June 4, 1975 application for an extension of the
interim operation period based upon "empirical data col
lected during . . . interim operation."2 / The Regulatory
Staff reads this in a cramped fashion to refer only to data
of a kind that can only be obtained when the plant or its
pumping system is operating. The License, however, does not
in terms require that the data be of this character. Such
data are obviously of interest, and the Appeal Board ex
pressed its desire that they be obtained in the decision
issued on April 4, 1974.
At the same time, however, the Appeal Board
dedicated much of its decision to an evaluation of areias of
the evidentiary record from the operating license case that
had to do with portions of the Con Edison Ecological Study
Program that were in no way dependent upon actual plant
operations. These included not only the gathering of other
types of empirical data, but the development and refinement
of analytical tools. Examples of this interest include the
entire discussion of the contribution of the Hudson River to
the Atlantic coastal striped bass fishery,-/ the use of
modeling techniques to estimate plant impact,.V/ the im
portant issue of compensation in the striped bass fishery, 6/
3/ Facility Operating License No. DPR-26, ~[2(E) (1)(c).
4/ 7 AEC at 361-65.
5/ id. at 381-87.
6/ Id. at 384-87.
-30-
and the feasibility of hatchery-rearing and stocking striped
bass in the Hudson.]/
Each of these areas was addressed by the Appeal
Board, and each represented an unresolved area of controversy.
Most of them formed the basis for provisions in the Environ
mental Technical Specification Requirements.-/ Each of them
could be studied (some completely, one only partially) in
the absence of plant impacts. To suggest, therefore, that
the fruits of the Ecological Study Program in these other
areas that do not strictly depend upon plant operation are
not proper bases for a jI 2(E) (1)(c) application is to read
the License condition as something separate and apart from
the record of the operating license case, and indeed, from
the terms of the Environmental Technical Specification
Requirements attached to that License.
It is possible to read the License condition as
narrowly as the Regulatory Staff does and come to the
conclusion that the data submitted by Con Edison are all
within its terms because they were collected "during" the
interim operation period, but there is no need to do so
here. We submit that the terms of the License condition
should be read as "words of purchase" rather than "words of
7/ Id. at 400-02.
8/ Facility Operating License No. DPR-26, App. B, § 4.1.2a.
-31-
limitation," and do not provide a basis for excluding from
consideration or giving less credence to the empirical data
obtained or analytical tools developed and refined in the
period since--and in light of--the Indian Point 2 operating
license proceeding. We do not believe it was the intent of
the Commission that 2(E) (1) (c) should be read as pre
scribing blinders for Licensing Boards.
Evidence of the Regulatory Staff's obdurate
perspective appears on page 4 of the Regulatory Staff's
Memorandum, which states that the Indian Point 2 decisions
and the Commission's Indian Point 3 decision "cannot be read
as a blank check for Con Edison to design any new research
project it wished, regardless of whether such research might
have been conducted prior to the decision in the Indian
Point 2 proceeding (or, for that matter, prior to the 'fresh
look' required by ALAB-188)." Passing over the fact that
this statement is in conflict with the Staff's observation,
on page 18 of the same document, that "Con Edison, by its
direction and control over the study program, can select
areas for 'targeted' research which are most likely to
provide evidence supporting their contention that cooling
towers are not required,"' this Staff position shows an
alarming hostility to the possibility of new data or analyses
that might in fact convince an impartial observer that the
balance provisionally struck in 1974 was no longer warranted.
9/ Staff Memorandum in Support at 18 (footnotes omitted).
-32-
No utility has endless funds, and it is unreason
able to characterize Con Edison as having a "blank check" to
conduct research. However, it is equally mistaken to
suggest that anything in the decisions the Staff cites bars
Con Edison (or, we might add, the Staff itself) from pur
suing any avenue that holds forth reasonable promise of
shedding new light on the issues in this case--particularly
where the interests of already hard-pressed ratepayers (who
would bear the cost of cooling towers) are at stake. Obvi
ously it is true that the Environmental Specifications
Requirements "do not preclude any additional study which Con
Edison elects to conduct."'1 0/ Nevertheless, the Environ
mental Technical Specification Requirements should be a
primary guide to the type of information the Staff at least
felt would be useful in addressing the ultimate question of
the need for closed-cycle cooling at Indian Point 2,11- and
nothing in those Requirements supports the suggestion that
some studies merit more attention than others.
Con Edison therefore respectfully submits that the
Regulatory Staff's dichotomy between "research which is
dependent on plant operation" and all other results of the
10/ Staff Proposed Findings and Conclusions at 24 n.86.
l1/ See generally Facility Operating License No. DPR-26, App. B, § 4.1.2a.
-33-
Ecological Study Program is a false one. By the same token,
the Board should reject the Staff's implication, at page 7
of its Memorandum in Support, that data that do not "admit
of and expedite full and prompt independent review" should
also somehow be entitled to less weight in the present pro
ceeding. It comes rather late in the day for the Regulatory
Staff to fault data it has received on the ground that those
data do not comply with the Staff's uncommunicated wishes.
Con Edison should not be penalized for its inability to read
the Regulatory Staff's mind.12 /
The Staff was, of course, in a position to request
that information be submitted in whatever reasonable fashion
it or its consultants felt was necessary.1 3- / No specific
requirements to supply data in "raw" or any other form are
laid down by the License, and the Regulatory Staff has not
made a general request in any other setting in this regard.
Where the Staff has asked for data in a particular form, Con
Edison has complied promptly, providing such materials as
computer tapes, punch cards and the like. The Staff's
12/ Moreover, the Regulatory Staff's own witnesses testified that where materials submitted to the Staff for review are not merely corroborative of earlier work, the process of independent Staff assessment or reanalysis is "substantially more complete and time consuming." See p. 4'0 infra. quoting Spore & Van Winkle at 15-16. Thus the StaT paradoxically appears to be willing to award less weight to the very parts of the data base and analytical tools that its consultants have testified required "full independent assessment or reanalysis."
13/ See 10 C.F.R. § 2.102(a) (1977).
-34-
biological witness testified that when he has asked for
information, Con Edison has provided it. 14/ Accordingly,
Con Edison denies the Staff's innuendo that it has not met
its obligations. In the circumstances, the Regulatory
Staff's Proposed Finding concerning the amenability of Con 15/
Edison's data to reanalysis- should be rejected by the
Board.1 6/ In any event, the Staff testimony was that the
data are being analyzed, and aside from the questions that
were responded to in Supplement 1 to the June 6, 1975 En
14/ Tr. 1507.
15/ Staff Proposed Findings and Conclusions at 24-25.
16/ The Board should, in addition, strike If 3 of Staff Proposed Finding No. 24, at 24-25, on the ground that besides being a distortion of Dr. McFadden's testimony, it uses that distortion to launch an ad hominem attack on a witness whose distinguished credentials are well known to the Commission's hearing boards. The distortion in the Staff's proposal lies in its misleading juxtaposition of Dr. McFadden's testimony on the preference for "repeatability of an experiment" with his attempt to respond to Staff's counsel's ambiguous question that failed to distinguish replicability of data from replicability of experiments. Tr. 1421-29. The Staff has twisted Dr. McFadden's recognition of the value of "repeatability of an experiment" into a "principle that research should always be reported in a manner which is susceptible of replication." Staff Proposed Findings and Conclusions at 25 & n.91. The transcript shows that Dr. McFadden said that sometimes he would find non-replicable results acceptable, and sometimes not. Tr. 1423. The questioning grew increasingly ambiguous, with the Chairman ultimately sustaining Con Edison counsel's objection. Tr. 1428-29. Hence the Staff's attack is unfounded, unfair (since Dr. McFadden does not have an opportunity to defend himself here) and irrelevant (since, shorn of its ad hominem character, it goes to the merits of the Final Research Report, which is not the subject of this proceeding).
-35-
vironmental Report,1 7-/ Con Edison has thus far received only
one isolated request for information--that attached to the
Spore and Van Winkle testimony.
Without any record justification, the Regulatory
Staff has also asserted that important portions of Con
Edison's Ecological Study Program could have been completed
much earlier than they in fact were. This is a preposterous
charge. The Ecological Study.Program has been an evolving
one, as anyone familiar with the history of Indian Point 2
would admit. It would have required the exercise of clair
voyance to know in advance the challenges that would be
encountered over the course of the program, and the areas of
investigation that would become apparent as the studies
proceeded. The Board, which is familiar with the history of
these investigations, must therefore, reject the Regulatory
Staff's irresponsible contention that much of the Ecological
Study Program could have been conducted "years ago".18/
17/ Con Edison Ex. OT-I ch. 9.
18/ Staff Proposed Findings and Conclusions at 38 n.163. This contention makes as much sense as saying that nuclear power should have been discovered earlier because the existence of uranium was known. In fact, the need for the contribution study was not identified until the Regulatory Staff took the position in the Indian Point 2 operating license Final Environmental Statement that, contrary to all previous literature on the subject, the Hudson River could contribute as much as 80 percent of the striped bass in the mid-Atlantic
-36-
con Edison is,.from its experience in this very
case, - painfully aware of the fact that-review of environ
mental reports by the Regulatory Staff and its consultants
can be a lengthy and time-consuming process.-0 Having been
barred by the Licensing Board from examining the Staff's
consult .ants on those consultants' priorities-l (a con
straint that was not imposed by the Board on the Regulatory
Staf'sconse), 2/we are not in a position even to
18/ Footnote continued
fishery. See generally Indian Point 2 FES at XII-35 to 38; Indian Point 3 FES at V-176. That necessitated a new study program which is described in detail in Con Edison's Exhibit OT-2. First, the study had to determine the feasibility of using innate tags to identify origins and to determine the best discriminant functions. Once the feasibility had been established and the appropriate functions were derived, it was necessary to apply a discriminant function to samples taken from the Atlantic coastal. fishery over a one-year period. As described in Con Edison's Exhibit OT-2, this necessarily required a two-year period because of the annual life cycle of the striped bass. The Staff's suggestion that this could have been done earlier is nonsense.
19/ The application and Environmental Report were filed on June 6, 1975. The draft environmental statement was published over 12 months later, in July 1976, with the final environmental statement following the draft in November 1976. Not until February 1977 did the Regulatory Staff perform a benefit-cost analysis.
20/ The same may be said of the Regulatory Staff's processing of requests for technical specification changes, contrary to the rosy picture of "receptiveness" conveyed by the Staff's Proposed Finding No. 25, at 27 & n.101. See Tr. 647.
21/ E.g., Tr. 1128-29..
22/ Tr. 470-76.
-37-
comment on what the Staff intends by its reference to a
"prompt" review (Memorandum at 7). In any case, the fact
that the Staff feels it may take a considerable time to
review the Final Research Report and other Con Edison .23/
submittals--- in no way supports the Staff's contention that
Con Edison's data, or some portion thereof, must be given
less credence. This is particularly true in light of the
fact that even a decision on the ultimate cooling system
question after construction has commenced could produce a
very substantial benefit in terms of avoiding costs.24
Finally, reference should be made to the Staff's
insistence that potential alternatives be "significantly
superior" or "clearly superior to the requested action."- 5/
26/ This puzzling usage--inspired, we assume, by Seabrook,
and offered here presumably as a "proxy" for a res judicata
argument--draws no support from that case, for the Com
mission there took pains to limit its ruling to siting
questions, warning in a footnote that "we do not wish to be
23/ Staff Proposed Findings and Conclusions at 56; Con Edison's Proposed Findings and Conclusions at 71-72.
24/ Con Edison's Proposed Findings and Conclusions at 72; Con Edison's Memorandum in Support at 44-47.
25/ Staff Memorandum in Support at 10, 26.
26/ Public Service Co. of New Hampshire, Inc. (Seabrook Station, Units 1 and 2), CLI-77- , 5 NRC (1977), slip op. at 43, 45.
-38-
misunderstood as suggesting that the obligations of NEPA
analysis are any less than have previously been required by
our staff with respect to alternate sites, or that the
standard adopted above is appropriate for deciding whether
to condition a proposed license." 27 1 Hence, the notion of.
"obvious superiority" has no bearing on this case, since we
deal here not with a siting issue but with a condition to an
operating license.
27/ Id. at 46 n.30 (emphasis in original).
-39-
THE REGULATORY STAFF HAS REPUDIATED THE TESTIMONY OF ITS OWN CHIEF BIOLOGICAL WITNESS THAT NUMEROUS PORTIONS OF THE
ECOLOGICAL STUDY PROGRAM REQUIRE INDEPENDENT STAFF ASSESSMENT OR REASSESSMENT
At the hearing, the Regulatory Staff presented
testimony by three witnesses: Dr. Robert P. Geckler, the
Environmental Project Manager, who served basically in an
editorial role in producing the draft and final environ
mental statements,-/ Dr. Robert L. Spore, an economist, and
Dr. Webster Van Winkle, a biologist. Dr. Van Winkle is the
Regulatory Staff's principal consultant on biological issues
in this case- and was the only Staff witness to testify on
the Staff's biological case or its an alysis of Con Edison's
Ecological Study Program.
Dr. Van Winkle was the co-sponsor of the Staff's
benefit-cost testimony presented in compliance with the
Board's directive of December 10, 1976,-/ and the Staff's
submittals make extensive reference to that testimony for
its economic analysis. In a footnote on page 5 of the
Regulatory Staff's Memorandum, the comment is made that
1/ Tr. 721.
2/ Professional Qualifications of Dr. Webster Van Winkle, following Tr. 719, at 2.
3/ Tr. 869-70.
-40-
"[tihe Staff's witnesses have testified that any piece of
research reporting new or different results will be inde
pendently reviewed," citing the Spore and Van Winkle testi
mony at page 15. An examination of the cited testimony is
revealing, however, for it evinces a Staff desire to abandon
its own witnesses' testimony. The Regulatory Staff's
footnote reference could be taken--indeed,.was probably
intended--to suggest that no such data have been submitted,
whereas the joint testimony of Drs. Spore and Van Winkle
states:
Should the submittals of further information appear to contain significantly new or different information, the staff will perform a full independent assessment or re-analysis of the subject area. This process is a substantially more complex and time-consuming one than that conducted for submittals which may be corroborative of earlier work done by Applicant's consultants or by the staff. For example, in the testimony of [Dr.] Campbell et al. of December 7, 1976, at least five areas appear-to warrant such an independent assessment. They include 1) relative contribution of Hudson River striped bass to the Atlantic coastal fishery; (2) estimates of entrainment mortality, including corrections for differential net mortality and larval-table data; (3) compensation in the Hudson River striped bass population; (4) the method of equilibrium reduction for impact assessment; and (5) consideration of a more comprehensive assessment of the impact of power plant operation.4/
The brief footnote on page 5 of the Regulatory Staff's
Memorandum is the Staff's sole reference to this important
4/ Spore & Van Winkle at 15-16 (emphasis added).
-41-
element of its own evidentiary presentation.
Still more mystifying is the Regulatory Staff's
failure to make any reference whatever to Dr. Van Winkle's
individual testimony--testimony that goes even further in
noting the need for assessment of Con Edison's study results.
At pages 4-5 of his separate testimonyj-/ Dr. Van Winkle,
after indicating the numerous Con Edison reports he had
reviewed,-/ as well as Con Edison's December 7, 1976 panel
testimony, stated:
Based upon a review of that testimony [which drew together information from the research reports], the principal subject areas which contain new information are:
5/ Van Winkle, following Tr. 1069.
6/ Since the December 1976 hearing, it may be added, the following additional reports have been provided to the Commission: (a) LaSalle Hydraulic Laboratory, Indian Point Generating Plants Hydraulic Model Study of Hudson River Flows Around Cooling Water intakes, (b) Dames & Moore, Indian Point Nuclear Generating Station, Intensive Thermal Program, May 1975 Survey, (c) Texas Instruments, Inc., A Synthesis of Available Data Pertaining to Major Physicochemical Variables within the Hudson River Estuary Emphasizing the period from 1972 through 1975, (d) Texas Instruments, Inc., Hudson River Ecological Study in the area of Indian Point, 1975 Annual Report, (e) Influence of Indian Point Unit 2 and Other Steam Electric Generating Plants on the Hudson River Estuary with Emphasis on-Striped Bass and Other Fish Populations ("Final Research Report"), (f) Consolidated Edison Co. of New York, Inc., Indian Point Nuclear Generating Staton, Thermal Survey Program, Routine Monthly Thermal Monitoring, October 1976 Survey, Report No. 1, (g) UMA Engineers, Inc., Striped Bass Rearing Experiments 1975, and (h) Texas Instruments, Inc., Production of Striped Bass for Experimental Purposes: 1976 Hatchery Report. These reports are in addition to those noted in Dr. Van Winkle's testimony.
-42-
1. Relative contribution of Hudson striped bass to the Atlantic Coastal fishery;
2. Estimates of entrainment mortality, including correction for differential net mortality and larval-table data;
3. Compensation in the Hudson River striped bass population;
4. The method of equilibrium reduction for impact assessment.
5. Further assessment of the impacts of power plant operation on the Hudson River white perch and tomcod populations.
In these five subject areas, at a minimum, an independent assessment by the NRC Staff appears essential to any reconsideration of the ultimate question of whether closed-cycle cooling should remain a requirement of the Indian Point 2 operating license. We expect the Applicant's January 1977 Report" to contain new information on
-each of these five subject areas,' although even then certaih important data may still not be available (e.g., larval-table data for 1976).7/
In the ever-changing progression of Regulatory
Staff positions that has characterized this proceeding- it
7/ Van Winkle at 4-5 (page references to Dec. 7, 1976 testimony omitted; emphasis added). In cross-examination, Dr. Van Winkle explained, with-reference to his use of the phrase "at a minimum," that in several other areas not included in his list independent Staff analysis or reanalysis was required. Tr. 1273-94. See also Tr. 756-60, 896, 914, 1309, 1328-29, 1297, 1553.
8/ See Con Edison's Proposed Findings and Conclusions at 11-12; Con Edison's Memorandum in Support at 14. Other changes of Regulatory Staff position include the belated insistence that the Staff was not under an obligation to evaluate extensions beyond May 1, 1981, compare DES S 5.2 and FES S 5.2 with Staff Memorandum in Support at 25; the assertion that there would be no benefit from the requested extension from the standpoint of the EPA adjudicatory hearing process, compare DES SS 4.1.1, 6.4.1 with Staff Memorandum at 26, discussed at pp. 59-61
(Footnote continued)
-43-
would seem that Dr. Van Winkle's testimony no longer suits
the Staff's convenience. Accordingly, the Staff has seen
fit to relegate it to oblivion as if it were the impeached
testimony of an adverse party's witness. Viewed another
way, the Staff appears to have put Dr. Van Winkle's testi
mony forward as a kind of cigar store-Indian, to be wheeled
back into the shop when the day is over.
In this respect we consider that the Regulatory
Staff has done an injustice not only to its own witness, but
also to the Commission's hearing proc ess, which assumes that
the testimony presented by the parties will be of sufficient
materiality that at least the major points will be-worthy of
preservation in the form of proposed findings. On balance,
the Staff's repudiation of Dr. Van Winkle's testimony on the
need for independent assessment or reassessment of the
information provided by Con Edison only tends to confirm the
notion that the Staff's true position is based on undis
closed policy reasons rather than sound biological judg
ment.
S/ Footnote continued
infra; and the expansion of the Staff's estimates of the time that will be required to complete the environmental review of the results of Con Edison's Ecological Study Program. Con Edison's Memorandum in Support at 40-42; see also DES SS 2.2.5.1, 4.1.2; FES § 6.4.1; Staff Prop osed Findings and Conclusions at 56.
9/ For another repudiation by the Regulatory Staff its own witnesses' testimony see P. 55 infra.
-44-
IV
THE REGULATORY STAFF'S USE OF THE INDIAN POINT 3 FINAL ENVIRONMENTAL STATEMENT AND
COMMISSION DECISION REPRESENTS A MISINTERPRETATION OF THE HISTORY OF THAT CASE, A DISTORTION OF THE INDIAN POINT 3 STIPULATION, AND ABANDONMENT OF THE STAFF'S
OWN PRIOR REPRESENTATIONS TO THE COMMISSION, AND, IF ADOPTED, A DENIAL OF CON EDISON'S
RIGHT TO AN ADJUDICATORY HEARING
Like HRFA, the Regulatory Staff has placed con
siderable emphasis on the contents of the Final Environ
mental Statement ("FES") prepared by the Staff in connection
with the Indian Point 3 operating license hearing. The
Staff has essentially sought to recast the issue to focus
not on what has changed in term of plant impact, since the
contested Indian Point 2 license hearing, but rather what
has changed since the settled Indian Point 3 licensing. We
have explained elsewhere the error of this approach,!/ as
well as the dangers inherent in it from the standpoint of
the Commission's expressed recognition that the public
interest is served by appropriate stipulated dispositions of
proceedings that might otherwise be contested.2 /
The error of the Regulatory Staff's position is
compounded, however, because it flatly contradicts repre
1/ Con Edison's Memorandum in Support at 61; Con Edison's Reply to HRFA at 53.
2/ Con Edison's Reply to HRFA at 57; 10 C.F.R. 9 2.759 (1977).
-45-
sentations that the Staff has previously made to the Com
mission and to this Board, leaving one with the sense that
the Staff's positions are in "the same class as a restricted
railroad ticket, good for- this day and train only."3/
The starting point for this discussion is the
letter addressed by the Regulatory Staff to the Board on
February 14, 1977, indicating an intent to request the Board
to take official notice of the Indian Point 3 FES "for the
limited purpose of identifying the contents of that document
as the Staff's position with regard to the necessity for
closed-cycle cooling at Indian Point Unit Nos. 2 and 3 as of
that date." Like HRFA, however, the Staff has insisted on
using this FES--never the subject of an adjudicatory hear
4/ ing--for the truth of its contents.- / We believe that the
Staff is bound by the terms of its request, and is estopped
now, after the hearing, to seek to rely on this FES from
another proceeding for the truth of its contents.
More importantly, the Licensing Board is bound
by its prior ruling on this subject. It barred Con Edison
from cross-examinating the Staff on the substance of the
3/ Smith v. Allwright, 321 U.S. 649, 666 (1944) (Roberts, J., dissenting).
4/ E.g., Staff Memorandum in Support at 10 (arguing that "Con Edison must demonstrate that the data collected during interim operation warrant an extension on the basis of differences in the conclusions they compel as comparred to the conclusions in the Indian Point 3 FES") (emphasis added); cf. Staff's Proposed Findings and Conclusions at 22 & n.73.
-46-
Indian Point 3 FES on the grounds that the merits of closed
cycle cooling were not in issue in this limited proceedS/
ing.
Beyond any estoppel (which applies, as well, to
the Staff's reliance on the merits of its Exhibit OT-2,
which was explicitly offered in evidence only for the
limited purpose of showing that there was disagreement as to
the use of compensation in striped bass modeling),-/ the
Regulatory Staff's use of this FES is in contradiction to
prior representations made to the Commission and constitutes
an effort to "get something for nothing." As we pointed out
in our response to HRFA, the Staff advised the Appeal Board
in 1974 that "the merits of [the Staff's] position can
better be explored .... within the framework of the up
coming evidentiary proceeding in Indian Point Unit 3 rather
than through the mechanism of a petition for reconsidera
tion."' As must be clear, no such evidentiary proceeding
5/ Tr. 906, 912.
6/ Tr. 1090-94; Con Edison's Proposed Findings and Conclusions at 44. The Staff has reneged on this limitation in its Proposed Findings and Conclusions at 44 n. 189. The reason given is without merit, since the circumstance there cited by the Staff was known at the time the Staff made its "limited purpose" offer, and since it demonstrates quite plainly the Staff's wish to confuse the instant case with the merits issues to be resolved in connection with Con Edison's March 15, 1977 application to vacate the cooling system condition.
7/ See Con Edison's Reply to HRFA at 55 n.125, quoting AEC Regulatory Staff statement as to a Petition for Reconsideration, Dkt. No. 50-247, June 14, 1974.
-47-
was held in the Indian Point 3 case, but the Regulatory
Staff treats the FES as if it had been approved following a
contested hearing. 8
The Regulatory Staff is seemingly attempting to
insulate from the hearing process so much of its analysis as
was presented in the Indian Point 3 FES. But by using the
Commission's Indian Point 3 decision to achieve this, the
Staff contradicts its own submission to the Commission in
that case. In its Brief in response to the Commission's
October 23, 1975 Order the Regulatory Staff contended that
an agency cannot modify a license under the guise of interpretive action, thus bypassing the statutory requirements for a hearing. Andrew G. Nelson v. United States, 355 U.S. 554 (1958); USAC Transport v. United States, 235 F. Supp. 689 (D. Del. 1964). We submit that the Appeal Board's action in ALAB287, if it is permitted to stand, is, therefore, erroneous as a matter of law in that the Appeal Board effected a modification of License No. DPR-26 without affording interested persons the opportunity for a hearing.9/
This, however, is precisely what the Regulatory
Staff would have the Board do now with the Indian Point 3
8/ See Staff Memorandum in Support at 10. As we have pointed out elsewhere, the Indian Point 3 case was settled by a stipulation among the parties. That stipulation was limited to Indian Point 3 and its nonwaiver provision would be violated by the approach urged by the Regulatory Staff. Con Edison's Memorandum in Support at 65 & n.189.
9/ Brief of the NRC Staff in Response to the Nuclear Regulatory Commission's October 23, 1975 Order, Dkt. No. 50-286, Nov. 10, 1975, at 48.
-48-
FES, for as the Staff's own witness pointed out1- that
document was no more the subject of a prior adjudicatory
hearing than were, in the Staff's view, the Appeal Board's
dicta in ALAB-287 concerning Indian Point 2. Now that the
shoe is on the other foot--now that it is Con Edison's right
to a hearing that is at stake--the same principle must
apply.
But what of the Commission's power? May the
Commission not, in the exercise of its supervisory author
ity,- I take the necessary measures to control and guide the
course of licensing cases? This is the Regulatory Staff's
contention in this case in support of its allegations that
the Commission has approved the Indian Point 3 FES on the
merits, and that that approval applies as well to Indian
Point 2.12/
There are two problems with this position. First,
it treats the Arkansas Power rule as a constraint only upon
the lower boards, and second, it neglects an important
10/ Tr. 982-83 (testimony of Dr. Van Winkle that the Indian Point 3 FES "was never cross-examined, and there was never a full-blown hearing at that time").
11/ See Niagara Mohawk Power Corp. (Nine Mile Point, Unit No. 2), CLI-73-28, 6 AEC 995 (1973).
12/ As we have elsewhere shown, all the Commission did -and all it had to do -- in the Indian Point 3 case was find the FES to be an adequate environmental disclosure for the stipulated license condition in that case. Con Edison's Reply to HRFA at 56-58.
-49-
limitation that the Commission recognized with respect to
its own action in the recent Seabrook decision, quoted
selectively in the Regulatory Staff's submittal. On each of
these points the Staff's construction is clearly erroneous.
In Arkansas Power,1-/ the Regulatory Staff filed
an exception with respect to what it termed "the [Licensing]
Board's supererogatory recommendation" in the hearing on
issuance of a construction permit for Arkansas Nuclear One
Unit 2 that the operating license for Arkansas Nuclear One
Unit 1 be conditioned in a particular fashion. The Staff
argued that
[tihe record here is limited to Unit 2 and, as [the Licensing Board] recognized .
the Board has no jurisdiction with respect to Unit 1. . . .14/
On review, the Appeal Board granted the Staff's exception,
commenting that "[wihenever an adjudicatory body seeks to
supply answers to questions which are not posed by the
litigation before it, and to which the record in the pro
ceeding is not addressed, there is at minimum an enlarged
potential for an erroneous conclusion. '1 5/
If Arkansas Power was a "going beyond what is
13/ Arkansas Power & Light Co. (Arkansas Nuclear One Unit 2), ALAB-94, 6 AEC 25 (1973).
14/ Regulatory Staff's Brief in Support of its Exceptions to Initial Decision Dated December 1, 1972, Arkansas Power and Light Co. (Arkansas Nuclear One--Unit 2), Dkt. 50-368, at 12.
15/ ALAB-94, 6 AEC at 31.
-50-
require,,'16/ commanded or required,"-1 one wonders why the Staff does not
view the Commission's references to Indian Point 2 in its
Indian Point 3 decision in the same light. The Regulatory
Staff's Memorandum in the instant case attempts to dis
tinguish Arkansas Power on the ground that that decision
"addresses the scope of the Appeal Board's review powers
with respect to a docket not before it." 1 7-/ This suggestion
that the case dealt with the Appeal Board's powers is, of
course, false. The issue posed by the Staff's own exception
in that case had to do with the power of the Licensing Board
rather than the Appeal Board. The fact of the matter is
that the principle for which the Staff was there arguing is
of more general applicability. The Staff took aim at what
it perceived to be a "supererogatory recommendation" per
taining to another facility at the same site, characterizing
that recommendation as "gratuitous". The same may be said
for the discussion of Indian Point 2 by both the Appeal
Board and the Commission in the Indian Point 3 case: the
Indian Point 2 License was not before either body at that
time. The policy expressed by the Appeal Board in Arkansas
Power, then, would be applicable here as well.
16/ 2 Oxford English Dictionary 3159 (Compact Ed. 1971) ("supererogatory").
17/ Staff Memorandum in Support at 9 n.18 (emphasis in original).
-51-
The Regulatory Staff's rejoinder is that the Com
mission, "[w]hen exercising its sua sponte review powers,
• . . is 'not a court constrained by the "passive virtues"
of judicial action. . . . Ultimately the members of the
Commission are responsible for the actions and policy of
this agency, and for that reason [they] have inherent
authority to review and act upon any adjudicatory matter
before a Commission tribunal'." 1 8/ The quoted language is
from the recent Seabrook decision. That decision will not,
however, bear the burden which the Staff would apply to it.
For one thing, the Staff has omitted from its quotation from
Seabrook critical portions of that decision. Thus, the Com
mission prefaced its remark about the "passive virtues" with
the acknowledgment that "we may deal with matters before us
in adjudicatory hearings only on the basis of the record
which has been compiled."1 9/ Similarly, the Commission
noted (in a part of the "inherent authority" discussion that
was not reproduced in the Staff's Memorandum) that that
authority was subject to the constraint, among other things,
of "action on the record."3 -' With the Indian Point 2
18/ Staff Memorandum in Support at 9, quoting Public Service Co. of New Hampshire, Inc. (Seabrook Station, Units 1 and 2), CLI-77- , 5 NRC (1977), slip op. at 19-20.
19/ Seabrook, slip op. at 19.
20/ Id. at 20.
-52-
operating license record not pending before the Commission
or its Boards at the time of the Indian Point 3 decision,
and in any event, with no adjudicatory hearing having been
held even as to Indian Point 3, it is plain that this
"constraint" operates to bar any suggestion that the Commis
sion was at liberty in the Indian Point 3 decision either
(1) to approve the Indian Point 3 FES as a correct statement
on the merits of the cooling system question as applied to
Indian Point 2, (2) to retrofit it to the Indian Point 2
operating license hearing record that was by then long
closed,-1/ or (3) to insulate its conclusions in advance 22/ TeCmiso'
from scrutiny in the present case.- The Commission's
Indian Point 3 decision purports to do none of these things.
Further, since any of these actions would constitute a
denial or material truncation of hearing rights of Con
Edison and other parties, it would be improper to assume
that it was the Commission's intent to have any direct
21/ The Regulatory Staff suggests, at page 10 of its Memorandum in Support, that the Commission did precisely this, when it argues that "the analysis and conclusions of the Indian Point 3 FES have been expressly held by the Commission to fully support the requirement of closed-cycle cooling at Indian Point 2.
The suggestion overlooks the Staff's earlier position that the "fresh look" would be subject to a hearing in the Indian Point 3 case, and its recognition that that hearing has still not occurred. See Con Edison's Reply to HRFA at 55 n.125.
22/ Consistent with its apparent understanding of the impact of the Indian Point 3 decision, the Regulatory Staff did not offer the Indian Point 3 FES in evidence in the present case.
-53-
effect on the Indian Point 2 case.-3 Accordingly, the
Board should reject the Regulatory Staff's attempt to
extract an adjudicatory windfall from the Indian Point 3
FES.
23/ It should also be noted that the Commission did not expand the caption of its Indian Point 3 decision, cf. Vermont Yankee Nuclear Power Corp. (Vermont Yankee Nuclear Power Station), Public Service Electric & Gas Co. (Salem Nuclear Generating Station, Units 1 & 2), Philadelphia Electric Co. (Peach Bottom Atomic Power Station Units 2 & 3), Metropolitan Edison Co. (Three Mile Island Nuclear Station, Units 1 &.2), Duquesne Light Co. (Beaver Valley Power Station, Units 1 & 2), Philadelphia Electric Co. (Limerick Generating Station, Units 1 & 2), Public Service Electric and Gas Co. (Hope Creek Generating Station, Units 1 & 2), Pennsylvania Power-and Light Co. (Susquehanna Steam Electric Station, Units 1 & 2), Union Electric Co. (Callaway Plant, Units 1 & 2), CLI-76-18, 4 NRC 470 (1976), as might have been expected if it had been exercising its "inherent supervisory power," Nine Mile 2, supra Inote 11, with respect to Indian Point 2. Even this power, however, may not be so used as to deprive a party of hearing rights whether in the case at bar, or a fortiori, in some other docket.
-54-
V
THE REGULATORY STAFF HAS, IF ANYTHING CONFIRMED THAT ITS SO-CALLED BENEFIT
COST ANALYSIS WAS A MERE POST HOC RATIONALIZATION THAT CANNOT BE CREDITED
A. Post Hoc Rationalization
The Regulatory Staff's April 22, 1977 Memorandum
in Support in effect confirms Con Edison's argument that the
Staff's benefit-cost testimony was a post hoc rationaliza
tion, by its statement on page 14 that its analysis assumed
a position "which the Staff had earlier articulated." This
position was that the economic value of the fishery had been
determined in prior litigation. The fact is that such a
position had never been articulated by the Staff, or any
other party to these proceedings, until the presentatio n of
the Staff's benefit-cost testimony.-! In that testimony the
Staff for the first time asserted that the cost of cooling
towers could be used to estimate the value of the risk of
damage to the fishery. The assertion that the Staff had
earlier articulated this notion is erroneous and this error
serves to underscore the fact that the concept was in truth
a post hoc rationalization.
The Staff's earlier testimony was that the bio
logical impact of a two-year extension was negligible. The
1/ Spore & Van Winkle at 19-20.
-55-
last sentence on page 14,of the Staff's Memorandum, which
says that the benefit-cost testimony illustrates the
reasonableness of Staff's earlier analysis, is wrong because
it is impossible to reconcile how the economic costs square
with the Staff's earlier analysis of negligible impacts.
The difficulty with this patent inconsistency is
illustrated on-page 24 of the Staff's Memorandum. When it
asks the Board not to rely on the Staff's own biological
witness' conclusion of negligible impact, it is in effect
asking the Board to reject the testimony of its own bio
logical witness. When the Staff goes on to assert that its
"analysis of costs provides a reasonable translation of this
same impact (utilizing the very data upon which the 'negli
gible' conclusion was drawn). into fairly substantial economic
terms", the Staff asserts that negligible biological impact
equals substantial economic impact. This argues that the
Staff's biological witness does not know the meaning of
"negligible," and should not be credited. The assertion
only serves to illustrate that something is very wrong with
either the Staff's biology or the Staff's economics. Since
the biological conclusion of negligible impact is unchal
lenged in the record of this proceeding, the Board must find
that the error lies in the economic assessment, especially
in view of the fact that the economic testimony was a post
hoc rationalization of the Staff's earlier policy and legal
decision to recommend denial of the requested license amend
ment and is inconsistent with its earlier analysis of impacts.
-56-
B. The Staff's Assumption of An Immutable Decision on Cooling Towers
The Regulatory Staff has replied to Con Edison's
objections to the Staff's treatment of the prior cooling
system decisions as being immutable, with the statement that
all licenses can be amended.-/ The Staff is in effect
attempting to value a prior decision by phantasizing as to
the rationale behind it. But there is no need to phantasize.
The Appeal Board made its reasoning very clear in its two
3/ decisions.- The conditions attached to the License were an
inherent part of the Appeal Board's decisions, as the sub
stantially similar conditions were an inherent part of the
Commission's decision with respect to Indian Point 3. The
Appeal Board and the Commission were both well aware of the
existence of § 50.90 of the regulations, cited in the
Staff's Memorandum in Support at page 13, yet it was found
necessary to place in the License, and in the case of the
Commission, to approve, the specific conditions which the
Staff chooses to ignore. It should not lightly be assumed
that the added language was mere surplusage. The insistence
on placing 1 2(E) (1) (c) in the License must have some
meaning, and that meaning is explained in the decisions.
2/ Staff's Memorandum in Support at 13.
3/ ALAB-188, 7 AEC 323 (1974) ; ALAB-198, 7'AEC 475 (1974).
-57-
The Board must reject Staff's Proposed Finding
No. 39 on page 48 that t he conditions need not be con
sidered because the decision has been stated to fulfill the
requirements of NEPA. The only decisions which have been
held to fulfill the requirements of NEPA are decisions which
have approved licenses which included these conditions.
Accord ingly, those decisions cannot justify ignoring condi
tions which those decisions approved.
The Regulatory Staff's witness conceded that if
there had been no previous immutable decision to build a
cooling tower, his methodology could not be used.- He said
that economists would prefer to use a different technique to
provide a direct measurement of the economic value to
society of the impact to the fishery.-V If an immutable
requirement for a cooling tower had not been imposed, the
Staff witness conceded that a technique "along the lines
such as the Applicant used" could be utilized to measure the
value to society.-Y Since, as discussed above, the license
requirement for a cooling tower is not immutable, the
Staff's concessions indicate that the Con Edison methodology
is the appropriate one for use in this proceeding.
Furthermore, the Staff has ignored the fact that
its methodology is not authorized by its own guidelines for
4/ Tr. 1330.
5/ Tr. 1178.
6/ Tr. 1330.
-58-
preparation of benefit-cost analyses,.-/ and the Staff's
witnesses made no attempt to determine whether their anal
ysis was consistent with the guidelines issued by the Water
Resources Council, 8-/ th official government document for
evaluating water resources projects.-/ The Staff's own
guidelines should have greater significance than Staff's
general references to economic theory and literature.1- /
C. The Staff's Computation of Costs
The Regulatory Staff asserts that its use of a
proxy for probability is correct because the proxy proba
bility value varies directly with the true probability
value. I- / The Staff refers to this as a "simple assump
tion."' 2/ It certainly is simple, but the proper question
is whether it is valid. Dr. Van Winkle's only explanation
of his use of this assumption was that "[wie don't have any
7/ Tr. 1175.
8/ Id.; see generally Water Resources Council, Principles and Standards for Planning Water and Related Land Resources, 38 Fed. Reg. 24778 (1973).
9/ See Con Edison Ex. OT-I at 4-37.
10/ Staff Proposed Findings and Conclusions at 48-49.
11/ Staff Proposed Findings and Conclusions at 51; Staff Memorandum in Support at 16.
12/ Staff Proposed Findings and Conclusions at 51.
-59-
information to make any more complicated assumption."1 3/
Dr. Van Winkle readily agreed that the relationship could be
otherwise.14/ Staff witnesses also were aware of the
novelty of the use of this measure of risk 5/ and no evi
dence was presented to support the invariant linearity of
the summation ratios used as proxies for probability or of
their components as a function of relative yield or time.
Indeed, the Staff suggested a possible alternative
assumption to take into account the expected disproportional
greater weight of incremental effects incurred later in
time.1 6/ If this more reasonable alternative measure had
been used with the same impact curves, the ratio of the two
areas measured would be a smaller number than that used in
the Staff's analysis. In other words, the ratio would be
different from that obtained by making the "simple assump
tion" that the units used by the Staff in its testimony as a
"proxy" for probability "varied directly" with probability.
Of all the possible relationships that could exist
between the "proxy" measure and the true probability, there
is no basis in the record for the assumption that the proxy
measure would "vary directly" with true probability through
13/ Tr. 1217.
14/ Tr. 1217.
15/ Tr. 1236.
16/ Spore & Van Winkle at 26.
-60-
out the range of this measure of time and relative yield of
interest here. If there is not a direct proportionality
over this range, then the proxy for a particular case cannot
be expressed as a "constant"- times the unknown "true"
probability associated with that case. Although the proxy
measure for each case might be expressed as a factor times
the unknown "true" probability associated with the case, the
factor for each case would be different (not "constant"),
and thus when the ratio of two proxy measures is taken, the
factors would not "cancel" as stated by the Staff.17
Therefore, the ratio would not represent the true ratio of
probabilities, as the Staff contends, but an unknown factor
times that ratio from which it is impossible--with the
information given--to determine the true ratio of proba
bilities. Unless the ratio used in the analysis is the true
ratio of probabilities, its use to derive an economic
valuation using the Staff's methodology would be erroneous,.
since the Staff's methodology hinges on this vital assump
tion of direct proportionality. 1 8 /
A further aspect of the Regulatory Staff's pro
posed benefit-cost findi ngs is its claim that the inter
17/ Staff Proposed Findings and Conclusions at 51; Staff memorandum in Support at 16.
18/ Further evidence that contradicts the Staff's "simple assumption" is its concession that the proxy probability could exceed 1. Tr. 1217. Since a true probability can never exceed 1, it is clear that the proxy probability cannot vary directly with the true probability throughout its full range.
-61-
action between the Commission's proceedings and the adju
dicatory hearing to be held by the Environmental Protection
Agency ("EPA") is "neither a cost nor a benefit." 9- The
Staff points, in this regard, to our suggestion that the
extension of interim operation "will facilitate the EPA
hearing process by permitting a continuation of the status
quo while EPA's hearing process runs its course. "3O/ The
Staff, having first opined (properly, in our view) that a 21/
benefit would accrue in this respect,- now has taken the
position that there is neither a benefit nor a cost ap
parently because of the independence of the two agencies'
jurisdictions. The Staff is, in this sense, still relying
on EPA's opaque comments on the Draft Environmental State
22/ ment,- for its Memorandum in Support observes that "EPA's
comments should certainly be deferred to for their rejection
of the idea that the extension would somehow benefit their
proceedings."2 3/ Given the Regulatory Staff's failure to
examine the basis of EPA Region II's comments on the DES,24/
19/- Staff Memorandum in Support at 26.
20/1 Con Edison's Memorandum in Support at 13.
21/ Draft Environmental Statement at-i, §§ 4.1.1, 6.4.1.
22/ FES at A-10.
23/ Staff Memorandum in Support at 26 n.74.
24/ See Con Edison's Proposed Findings and Conclusions at 79; Con Edison's Memorandum in Support at 14-16.
-62-
and the fact that those comments themselves do not provide
an intelligible explanation of EPA's contention that the
requested extension to May 1, 1981 would ,confuse or inter
fere with the EPA hearing process, this suggestion--which
flies in the face of common sense--must be rejected.
The purpose of the requested extension of interim
operation to May 1, 1981 is to avoid the possibility of sunk
costs for a cooling system that turns out, upon examination
of the results of the Ecological Study Program to be un
necessary, or, in the alternative, to limit Con Edison's
exposure to a forced outage imposed by the License in the
event a final decision on the ultimate cooling system
question is reached at a time that does not permit com
pletion of the closed-cycle system by the deadline now
provided in the License. These are substantial interests of
Con Edison and its ratepayers, and they are as real in the
context of action under the Federal Water Pollution Control
Act (whether by EPA or the State of New.York) as they are in
the context of the instant proceeding before the Commission.
Thus, even if the EPA has been silent on the matter, or has • . .25/
submitted ill-conceived and unsupported- comments suggesting
that action in this case will prejudice its own proceeding,
25/ Significantly, EPA Region II's comments on the DES were filed before Con Edison's Final Research Report was submitted to that agency.
-63-
the Board can and should take note of the fact that approval
of the requested extension would in fact serve to avoid or
reduce both sunk costs and needless exposure to a forced
outage not only with respect to the Commission's action on
the March 15, 1977 application, but with respect to EPA's
proceeding as well. This we deem a benefit.
The Regulatory Staff asserts that its analysis
included compensation.2-/ This is a distortion of the
record achieved by selective citation of one portion of a
long colloquy which ended with Dr. Van Winkle's explanation
that in the case of the runs in question the young-of-the
year striped bass model had no compensation and the life
cycle model had fishing compensation.27 / But the point is
that Dr. Van Winkle refused to characterize this impact
estimate as anything more than one of several possible
estimates. He stated that Figure V-13a in the Indian Point
3 FES was equally reasonable.2-8/ This figure had a factor
FI = 0.5, 29 / and produced a lower estimate-of costs.-30 /
The balance of the Staff's Proposed Finding No. 40
is bootstrap, but the statement that this analysis has been
found by the Commission to support the closed-cycle cooling
26/ Staff Proposed Findings and Conclusions at 49.
27/ Tr. 1246.
28/ Tr. 1247.
29/ Id.
30/ Tr. 1254.
-64-
requirement is itself a significant misstatement of. the
record. Dr. Van Winkle repeatedly characterized the Indian
Point 3 FES as presenting a family of curves.-1 Assuming
arg uendo that the Commission approved anything, it approved
this approach, not a particular impact assessment which the
Staff has seized upon in this proceeding. Furthermore, as
noted elsewhere, the Commission's NEPA finding was not that
a cooling tower was required, but a finding which supported
a license which contained several important conditions to
that requirement.
The Staff's calculation also hinges on the crit
ical assumption that a 0.5 impact level is a correct index
of risk of irreverisble damage. The requested Staff finding
that this is 32/oabe is not supported by the record of
this proceeding, which includes the statement that its
selection was arbitrary.-' To say that 0.5 is mc _-e reason34/ Lt
able than other specified extremes- is not the same as
saying 0.5 itself is reasonable. This is critical because
of the extreme sensitivity of the analysis to the selection
of this index. At the 0.4 level the costs go to zero.-5
31/ See Staff Proposed Findings and Conclusions at 20.
32/ Staff Proposed Findings and Conclusions at 50.
33/ Tr. 908.
34/ Tr. 1523.
35/ Tr. 1259.
-65-
When the Staff presented its family of curves, it
said:
Before presenting results, a caveat is in order to the effect that the staff wishes to de-emphasize and discourage efforts to play meaningless games with 'soft' numbers by treating them as 'hard' numbers.36/
When the Staff selects one of its family of curves
for a precise numerical calculation of impact, it is playing
the very game it had previously described as "meaningless".
In summary, the portion of the Regulatory Staff's
Proposed Finding No. 43 on page 52 that its estimate is a
"minimum figure" must be disapproved on the ground that it
is clearly in conflict with the record of this proceeding.
D. Staff's Criticisms of Con Edison's Testimony
The Regulatory Staff 1 ommences its analysis of Con
Edison's benefit-cost testimony by using Staff Exhibit OT-2
for the truth of its contents. 37 / This is absolutely
contrary to the Staff's offer of this document into evi
dence.38- / Staff counsel stated that this document was
offered for a limited purpose "rather than for its probative
36/ Indian Point 3 FES at B-179.
37/ Staff Proposed Findings and Conclusions at 44.
38/ See p. 46 n.6 supra.
-66-
value of for its bottom-line conclusion about the compensa
tion function."39- The Staff now proposes a finding which
is that very same "bottom-line conclusion" for which this
document was not placed in evidence. The Licensing Board
should not tolerate such tactics.
The Staff criticizes Con Edison's use in its
benefit-cost testimony of the estimate of 25% contribution
of Hudson River spawned striped bass to the Atlantic fishery. 0-- /
Contrary to this proposed finding, the basis for Con Edison's
assumption was explained.-'l/ This estimate was not updated
because the benefit-cost testimony of January 18, 1977 was
prepared concurrently with the contribution testimony of
February 23, 1977. In view of the low impact levels, a
refinement to incorporate the latest information on con
tribution was-not considered necessary. The result was an
overstatementi-of cost to the fishery and the Staff's com
plaint is accordingly ill-founded.
The Staff's proposed finding on the value of
impacts other than on recreational striped bass fishery is
inherently inconsistent.--! The Staff asks the Board to
reject Con Edison's zero value as inconsistent with the
39/ Tr. 1081.
40/ Staff Proposed Findings and Conclusions at 44-45.
41/ Con Edison Ex. OT-I, App. C, at 28.
42/ Staff Proposed Findings and Conclusions at 45-46.
-67-
Staff's characterization of impacts as negligible. Since
the Staff's negligible impact included the striped bass
fishery as well as other impacts, it is difficult to
comprehend what value could be placed on these less than
negligible impacts other than zero which could.be supported
by the record.
The Regulatory Staff's notion that there is some
significance to the absence of a biologist and an economist
from Con Edison's benefit-cost panel is misconceived. Con
Edison's witnesses stated that they derived their informa43/•
tion from appropriate sources- and an examination of their
testimony shows that it is based on other testimony in this
proceeding which was presented by appropriate experts.
Benefit-cost methodology is commonly used in engineering
evaluations and it is not unique to biology or economics.
i l The Staff made no motion to disqualify these witnesses and
accordingly has waived any right to challenge their exper
tise.
E. Staff's Analysis of Benefits
The Regulatory Staff asserted that the treatment
of reserve capacity dramatically affects the results of the
43/ Tr. 1565.
-68-
.44/ benefit-cost analysis.- This is inconsistent with the
Staff's subsequent correct observation that its own and Con
Edison's estimates of total economic benefits are substan
tially similar.- Treatment of reserve capacity is only
important if Mr. Briggs' suggested methodology is pur
sued.46_
The purpose of a benefit-cost analysis is to
measure impacts. The impact in question is the loss of
capacity by reason of outage of Indian Point 2, which must
be valued in each case under consideartion. If the 1980
loss of capacity is valued at zero, as Mr. Briggs suggests,
that means that the projected reserve level for 1980 is
perfect. The record of this proceeding does not support a
finding that that or any other level of reserves is perfect.
Reliability involves a gradient, i.e., the more the better.47
The fact that a reserve level is above a minimum is impor
tant when planning capacity additions but is not relevant
when valuing a loss of capacity, because a minimum level of
reserves is not perfect.
The Staff is mistaken when it says that Con Edison
argues that the amount of reserve capacity is a fact un
44/ Staff Proposed Findings and Conclusions at 54.
45/ Id. at 55 n.245.
46/ See Con Edison's Memorandum in Support at 55-58.
47/ The Staff misunderstands Con Edison's use of the word "gradient". See Staff Memorandum in Support at 21. Con Edison said that reliability involved a gradient while the Staff associates a gradient with the value of lost capacity as a function of level of reserves.
-69-
related to these proceedings.4-8/ Con Edison's argument was
that the method suggested by Mr. Briggs makes the valuation
of loss of reliability (i.e., bringing 1981 reserves up to
the 1980 level) dependent on facts unrelated to Indian
Point, e.g., outage of an in-city plant, unavailability of
purchased power becuase of delays experienced by other
utilities in constructing generating plants or transmission
lines, and so forth. If such an event occurred in 1980, it
would reduce the cost differential between a 1980 outage and
a 1981 outage. Thus, under this methodology, the computa
tion of the value of an outage of Indian Point 2 becomes
dependent on extraneous events.
The Staff reiterates the notion that the decision
on Con Edison's March 15, 1977 application must be made
before the start of construction of a cooling tower, but
provides no indication of its rationale.4 9/ As previously
indicated, Con Edison considers this a non sequitur.50/
48/ Staff Memorandum in Support at 21.
49/ Staff Proposed Findings and Conclusions at 56-57; Staff Memorandum in Support at 23.
50/ Con Edison's Memorandum in Support at 44-48; Con Edison's Reply to HRFA at 41-42.
-70-
The Regulatory Staff adds the suggestion that
there is no benefit in the probability that Con Edison will
not have to build a cooling tower because such a probability
cannot be measured.5-I/ The whole concept of Staff's deter
mination of the need for a cooling tower is its belief that
there is an unquantifiable probability of irreversible
damage to the Hudson River fishery from once-through
52/ cooling.- If the probability of Con Edison's ultimate
success must be valued at zero because it is unquantifiable,
then by the same logic the probability of damage to the
fishery must also be valued at zero because it too is
unquantifiable. The Staff modifies this position somewhat on
the following page by stating that the value of the pro
bability of Con Edison's success "would not be high."53
Since Con Edison has shown that even a low probability of
success would justify granting the instant application,5- /
this statement by the Staff would support Con Edison's
position in this proceeding.
F. Speculation on Future Actions
The Regulatory Staff has proposed a finding that a
hidden cost of this proceeding is the possibility of some
51/ Staff Proposed Findings and Conclusions at 55.
52/ Indian Point 3 FES at xi.
53/ Staff's Proposed Findings and Conclusions at 56.
54/ Con Edison's Proposed Findings and Conclusions at 53; Con Edison Ex. OT-I, S 4.1.4.
-71-
hypothetical future action under the license condition.55/
This is an impermissible consideration, for the Board must act on the instant application without such speculation.56/
Any future applications will be decided on the record of
those future proceedings and in the light of circumstances
as they then exist. The Staff is asking the Board to
speculate that some future decisionmaker will make an
erroneous decision and such speculation is clearly im
permissible. Accordingly this proposed finding should be
disapproved.
55/ Staff Proposed Findings and Conclusions at 53.
56/ Cf. ALAB-188, 7 AEC at 405.
€
€
-72
CONCLUS ION
For the foregoing reasons, a.nd the further reasons
stated in Con Edison's Proposed Findings and Conclusions and
Memorandum in Support dated March 28, 1977, and Memorandum
in Reply to HRFA's Proposed Findings of Fact and Conclusions
of Law and Supporting Memorandum. dated Aoril 27, 1977, the
Atomic Safety and Licensing Board should rule that the bene
fits of the proposed extension of the interim operation period
to May 1,.1981 exceed the costs, and that, as a result, the
application should be granted.
Respectfully submitted,
LeBOEUF, L.!MB, LEIBY & MacRAE
Leonard M. Trosten Partner
1757 N Street, N.W. -Washington, D.C. 20036
Attorneys for Consolidated Edison Company of New York, Inc.
Of Counsel:
EUGENE R. FIDELL M. REA-MY ANCARROW LeBoeuf, Lamb, Leiby & MacRae
1757 N Street, N.W. Washington, D.C. 20036
EDWARD J. SACK JOYCE P. DAVIS Consolidated Edison Company
of New York, Inc. 4 Irving Place New York, New York 10003
Dated: May 4, 1977