MELTON PLANNING SCHEME SCHEDULE 1 TO CLAUSE 45.11 INFRASTRUCTURE CONTRIBUTIONS OVERLAY Shown on the planning scheme map as ICO1. PLUMPTON & KOROROIT INFRASTRUCTURE CONTRIBUTIONS PLAN, APRIL 2018 1.0 Permit requirement None specified. 2.0 Monetary component – Standard levy Class of development Infrastructure category Levy rate payable Residential development Community and recreation construction $86,800 per NDHa Transport construction $108,700 per NDHa Total standard levy rate payable $195,500 per NDHa Commercial and industrial development Community and recreation construction None specified Transport construction $108,700 per NDHa Total standard levy rate payable $108,700 per NDHa 3.0 Monetary component – Supplementary levy Class of development Infrastructure category Levy rate payable Residential development Community and recreation construction None specified Transport construction $31,256 per NDHa Total standard levy rate payable $31,256 per NDHa Commercial and industrial development Community and recreation construction None specified Transport construction $31,256 per NDHa Total standard levy rate payable $31,256 per NDHa 4.0 ICP land contribution percentage Class of development ICP land contribution percentage OVERLAYS – CLAUSE 45.11 – SCHEDULE 1 PAGE 1 OF 9 --/--/--- - Proposed --/--/--- - Proposed --/--/--- - Proposed --/--/--- - Proposed --/--/--- - Proposed

Melton C195 45_11s01 melt exhibition final€¦ · Web view$2,055,400.31 P-54 Residential 11.27% $0.00 $374,598.29 P-55 Residential 18.04% $886,563.60 $0.00 P-R1 (Plumpton Road) Residential

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Melton C195 45_11s01 melt exhibition final€¦ · Web view$2,055,400.31 P-54 Residential 11.27% $0.00 $374,598.29 P-55 Residential 18.04% $886,563.60 $0.00 P-R1 (Plumpton Road) Residential

MELTON PLANNING SCHEME

SCHEDULE 1 TO CLAUSE 45.11 INFRASTRUCTURE CONTRIBUTIONS OVERLAY

Shown on the planning scheme map as ICO1.

PLUMPTON & KOROROIT INFRASTRUCTURE CONTRIBUTIONS PLAN, APRIL 2018

1.0 Permit requirement

None specified.

2.0 Monetary component – Standard levy

Class of development

Infrastructure category Levy rate payable

Residential development

Community and recreation construction

$86,800 per NDHa

Transport construction $108,700 per NDHa

Total standard levy rate payable $195,500 per NDHa

Commercial and industrial development

Community and recreation construction

None specified

Transport construction $108,700 per NDHa

Total standard levy rate payable $108,700 per NDHa

3.0 Monetary component – Supplementary levy

Class of development

Infrastructure category Levy rate payable

Residential development

Community and recreation construction

None specified

Transport construction $31,256 per NDHa

Total standard levy rate payable $31,256 per NDHa

Commercial and industrial development

Community and recreation construction

None specified

Transport construction $31,256 per NDHa

Total standard levy rate payable $31,256 per NDHa

4.0 ICP land contribution percentage

Class of development ICP land contribution percentage

Residential 14.11%

Commercial and industrial 5.20%

5.0 Land component

PSP parcel ID

Class of development

Parcel contribution percentage

Land credit amount

Land equalisation amount

OVERLAYS – CLAUSE 45.11 – SCHEDULE 1 PAGE 1 OF 7

--/--/----Proposed C195

--/--/----Proposed C195

--/--/----Proposed C195

--/--/----Proposed C195

--/--/----Proposed C195

--/--/----Proposed C195

Page 2: Melton C195 45_11s01 melt exhibition final€¦ · Web view$2,055,400.31 P-54 Residential 11.27% $0.00 $374,598.29 P-55 Residential 18.04% $886,563.60 $0.00 P-R1 (Plumpton Road) Residential

MELTON PLANNING SCHEME

P-1 Employment 0.00% $0.00 $4,861.63

P-2 Employment 0.00% $0.00 $487,686.91

P-3 Employment 0.00% $0.00 $441,334.76

P-4 Employment 0.00% $0.00 $438,166.43

P-5 Employment 9.76% $268,406.11 $0.00

P-6 Employment 0.27% $0.00 $530,749.82

P-7 Employment 0.00% $0.00 $41,266.12

P-8 Residential 0.00% $0.00 $3,670.37

P-9 Residential 2.66% $0.00 $1,872,620.47

P-10 Residential 8.03% $0.00 $1,026,252.65

P-11 - R Residential 22.79% $789,230.43 $0.00

P-11 - E Employment 53.70% $456,516.87 $0.00

P-12 - R Residential 16.67% $2,084,835.28 $0.00

P-12 - E Employment 4.17% $0.00 $374,607.55

P-13 Employment 9.86% $417,961.51 $0.00

P-14 Employment 18.34% $1,131,235.82 $0.00

P-15 Employment 12.90% $564,653.79 $0.00

P-16 Residential 10.04% $0.00 $804,319.10

P-17 Residential 7.20% $0.00 $1,147,171.07

P-18 Residential 78.68% $6,593,243.87 $0.00

P-19 Residential 2.45% $0.00 $1,301,228.80

P-20 Residential 7.66% $0.00 $1,310,942.78

P-21 Residential 0.00% $0.00 $3,441,229.63

P-22 Residential 0.00% $0.00 $648,277.04

P-23 Residential 7.81% $0.00 $1,201,331.58

P-24 Residential 23.70% $1,555,525.42 $0.00

P-25 Residential 48.54% $3,305,586.58 $0.00

P-26 Residential 0.00% $0.00 $435,684.00

P-27 Residential 2.06% $0.00 $8,695,491.59

P-28 Residential 5.74% $0.00 $6,802,200.92

P-29 Residential 49.24% $5,715,402.30 $0.00

P-30 Residential 52.31% $6,113,578.72 $0.00

P-31 Residential 10.88% $0.00 $546,335.97

P-32 Residential 25.62% $3,078,004.36 $0.00

P-33 Residential 43.39% $1,821,280.37 $0.00

P-34 Residential 7.23% $0.00 $1,416,045.64

P-35 Residential 73.15% $5,811,469.37 $0.00

P-36 Residential 70.30% $3,006,036.08 $0.00

P-37 Residential 67.89% $2,918,009.99 $0.00

P-38 Residential 16.53% $202,153.94 $0.00

OVERLAYS – CLAUSE 45.11 – SCHEDULE 1 PAGE 2 OF 7

Page 3: Melton C195 45_11s01 melt exhibition final€¦ · Web view$2,055,400.31 P-54 Residential 11.27% $0.00 $374,598.29 P-55 Residential 18.04% $886,563.60 $0.00 P-R1 (Plumpton Road) Residential

MELTON PLANNING SCHEME

P-39 - R Residential 0.00% $0.00 $2,887,155.07

P-39 - E Employment 0.00% $0.00 $36,315.96

P-40 Residential 0.00% $0.00 $1,036,846.36

P-41 Residential 5.41% $0.00 $969,962.81

P-42 Residential 8.00% $0.00 $1,138,134.60

P-43 Residential 9.04% $0.00 $657,501.26

P-44 Residential 5.81% $0.00 $1,267,364.66

P-45 Residential 8.36% $0.00 $846,374.24

P-46 Residential 6.49% $0.00 $918,036.24

P-47 Residential 12.40% $0.00 $315,714.52

P-48 Residential 19.09% $5,263,824.05 $0.00

P-49 Residential 6.04% $0.00 $3,468,181.67

P-50 Residential 0.00% $0.00 $0.00

P-51 Residential 0.00% $0.00 $0.00

P-52 Residential 7.22% $0.00 $19,996.42

P-53 Residential 0.28% $0.00 $2,055,400.31

P-54 Residential 11.27% $0.00 $374,598.29

P-55 Residential 18.04% $886,563.60 $0.00

P-R1 (Plumpton Road)

Residential 0.00% $0.00 $0.00

P-R2 (Tarleton Road)

Residential 0.00% $0.00 $0.00

P-R3 (Beattys Rd)

Residential 0.00% $0.00 $0.00

P-R4 (Saric Ct)

Residential 0.00% $0.00 $0.00

P-R5 (Taylors Rd)

Residential 0.00% $0.00 $0.00

K-1 Residential 0.03% $0.00 $1,602,853.96

K-2 Residential 12.55% $0.00 $223,867.65

K-3 Residential 0.61% $0.00 $1,381,750.78

K-4 Residential 2.11% $0.00 $1,292,623.87

K-5 Residential 0.00% $0.00 $2,383,194.38

K-6 Residential 0.00% $0.00 $997,494.04

K-7 Residential 15.56% $135,023.99 $0.00

K-8 Residential 0.12% $0.00 $1,332,994.38

K-8a Residential 0.00% $0.00 $0.00

K-9 Residential 7.30% $0.00 $431,941.87

K-9a Residential 0.00% $0.00 $0.00

K-10 Residential 21.61% $1,110,741.01 $0.00

K-11 Residential 92.63% $5,553,378.17 $0.00

OVERLAYS – CLAUSE 45.11 – SCHEDULE 1 PAGE 3 OF 7

Page 4: Melton C195 45_11s01 melt exhibition final€¦ · Web view$2,055,400.31 P-54 Residential 11.27% $0.00 $374,598.29 P-55 Residential 18.04% $886,563.60 $0.00 P-R1 (Plumpton Road) Residential

MELTON PLANNING SCHEME

K-12 Residential 9.75% $0.00 $59,408.98

K-13 - E Employment 0.03% $0.00 $16,265.97

K-13 - R Residential 39.84% $6,517,347.41 $0.00

K-14 Residential 14.65% $54,583.51 $0.00

K-15 Residential 29.97% $2,217,545.49 $0.00

K-16 Residential 0.00% $0.00 $2,036,692.57

K-17 Residential 0.00% $0.00 $639,831.53

K-18 Residential 0.00% $0.00 $154,391.61

K-19 Residential 14.11% $442.92 $0.00

K-20 Residential 16.55% $80,430.54 $0.00

K-21 Residential 23.54% $1,684,354.61 $0.00

K-24 Residential 10.50% $0.00 $638,617.77

K-25 Residential 18.48% $759,051.96 $0.00

K-26 Residential 3.82% $0.00 $2,201,565.83

K-27 Residential 0.07% $0.00 $2,167,734.87

K-28 Residential 0.00% $0.00 $862,430.29

K-29 Residential 0.00% $0.00 $0.00

K-30 Residential 1.95% $0.00 $1,183,278.46

K-31 Residential 0.00% $0.00 $862,003.21

K-31a Residential 0.00% $0.00 $0.00

K-32 Residential 11.25% $0.00 $377,794.11

K-33 Residential 148.86% $8,876,041.70 $0.00

K-34 Residential 3.13% $0.00 $2,587,113.20

K-35 Residential 8.88% $0.00 $618,549.08

K-36 Residential 0.00% $0.00 $1,453,301.44

K-37 Residential 25.79% $1,572,710.00 $0.00

K-38 Residential 9.72% $0.00 $671,503.85

K-39 Residential 2.29% $0.00 $1,620,020.35

K-40 Residential 0.00% $0.00 $2,632,227.52

K-41 Residential 9.15% $0.00 $806,600.15

K-42 Residential 0.00% $0.00 $2,499,218.49

K-43 Residential 21.58% $1,051,625.45 $0.00

K-44 Residential 0.00% $0.00 $1,445,620.17

K-45 Residential 17.03% $236,529.29 $0.00

K-46 Residential 113.71% $6,114,271.39 $0.00

K-47 Residential 118.73% $6,467,206.98 $0.00

K-48 Residential 34.11% $2,045,948.35 $0.00

K-49 Residential 0.00% $0.00 $444,165.44

K-50 Residential 0.00% $0.00 $618,740.11

K-51 - E Employment 13.57% $61,776.83 $0.00

OVERLAYS – CLAUSE 45.11 – SCHEDULE 1 PAGE 4 OF 7

Page 5: Melton C195 45_11s01 melt exhibition final€¦ · Web view$2,055,400.31 P-54 Residential 11.27% $0.00 $374,598.29 P-55 Residential 18.04% $886,563.60 $0.00 P-R1 (Plumpton Road) Residential

MELTON PLANNING SCHEME

K-51 - R Residential 12.92% $0.00 $40,256.70

K-51a Residential 0.00% $0.00 $0.00

K-52 Residential 12.50% $0.00 $144,638.33

K-53 Residential 13.93% $0.00 $18,846.18

K-54 Employment 0.06% $0.00 $83,859.26

K-55 Residential 1.54% $0.00 $419,658.01

K-56 Residential 2.81% $0.00 $375,463.38

K-57 Residential 28.17% $469,325.16 $0.00

K-58 Residential 0.00% $0.00 $357,898.63

K-59 Residential 0.00% $0.00 $5,002.65

K-60 Residential 0.00% $0.00 $498,422.35

K-61 Residential 0.00% $0.00 $177,976.58

K-62 (not used)

  0.00% $0.00 $0.00

K-63 Residential 5.52% $0.00 $1,318,420.63

K-64 Residential 14.32% $36,379.40 $0.00

K-65 Residential 10.22% $0.00 $698,267.28

K-66 Residential 2.42% $0.00 $3,954,975.37

K-66a Residential 8.49% $0.00 $91,227.60

K-67 Residential 7.35% $0.00 $1,345,147.09

K-67a Residential 0.00% $0.00 $0.00

K-68 Residential 15.64% $847,375.60 $0.00

K-69 Residential 10.75% $0.00 $2,277,827.57

K-70 Residential 100.00% $0.00 $0.00

K-R1 (Taylors Rd)

Residential 0.00% $0.00 $0.00

K-R2 (Vere Ct)

Residential 0.00% $0.00 $0.00

K-R3 (Sinclairs Rd)

Residential 0.00% $0.00 $0.00

K-R4 (Monaghans Ln)

Residential 0.00% $0.00 $0.00

K-R5 (Reed Ct)

Residential 0.00% $0.00 $0.00

K-R6 (Deanside Ct)

Residential 0.00% $0.00 $0.00

K-R7 (Gray Ct)

Residential 0.00% $0.00 $0.00

K-R8 (Neale Rd)

Residential 0.00% $0.00 $0.00

K-R9 - E Employment 0.00% $0.00 $170,976.04

K-R9 - R Residential 0.00% $0.00 $818,742.08

OVERLAYS – CLAUSE 45.11 – SCHEDULE 1 PAGE 5 OF 7

Page 6: Melton C195 45_11s01 melt exhibition final€¦ · Web view$2,055,400.31 P-54 Residential 11.27% $0.00 $374,598.29 P-55 Residential 18.04% $886,563.60 $0.00 P-R1 (Plumpton Road) Residential

MELTON PLANNING SCHEME

Note: Refer to Plan 01 of the incorporated Plumpton & Kororoit Infrastructure Contributions Plan, April 2018 for PSP parcel ID numbers.

6.0 Method and timing of indexation – Standard levy rate

Infrastructure category Indexation method Timing

Community and recreation construction

Producer Price Index Numbers for Non-Residential Building Construction – Victoria published by the Australian Bureau of Statistics (Catalogue 6427.0, Table 17, Output of the Construction Industries, subdivision and class index numbers).

1 July each year

Transport construction Producer Price Index Numbers for Road and Bridge Construction – Victoria published by the Australian Bureau of Statistics (Catalogue 6427.0, Table 17, Output of the Construction Industries, subdivision and class index numbers).

1 July each year

7.0 Method and timing of indexation – Supplementary levy rate

Infrastructure category Indexation method Timing

Community and recreation construction

Australian Bureau of Statistics Producer Price Indexes Non-Residential Building Construction Index, Victoria (Catalogue 6427.0, Table 17 Output of the Construction Industries).

1 July each year

Transport construction Australian Bureau of Statistics Producer Price Indexes Road & Bridge Construction Index,Victoria (Catalogue 6427.0, Table 17 Output of the Construction Industries).

1 July each year

8.0 Method and timing of adjustment – Land component

Adjustment method Timing

Index prepared by the Valuer-General Victoria as specified in the Ministerial Direction on the Preparation and Content on Infrastructure Contributions Plans

1 July each year

9.0 Land or development exempt from payment of an infrastructure contribution

Use and development for a non government school.

OVERLAYS – CLAUSE 45.11 – SCHEDULE 1 PAGE 6 OF 7

--/--/----Proposed C195

--/--/----Proposed C195

--/--/----Proposed C195

--/--/----Proposed C195

Page 7: Melton C195 45_11s01 melt exhibition final€¦ · Web view$2,055,400.31 P-54 Residential 11.27% $0.00 $374,598.29 P-55 Residential 18.04% $886,563.60 $0.00 P-R1 (Plumpton Road) Residential

MELTON PLANNING SCHEME

Use and development associated with a dwelling that is existing or approved at the approval date of this provision.

Notes: This schedule sets out the levies prescribed in the infrastructure contributions plan. Refer to the incorporated infrastructure contributions plan for full details.

OVERLAYS – CLAUSE 45.11 – SCHEDULE 1 PAGE 7 OF 7