Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
1
Mega Projects of the Americas
Woodrow Wilson Bridge
Mike McGee, EIFederal Highway Administration
2
Project Location
3
TelegraphRoad
US Route 1 River Crossing I-295 MD-210
VIRGINIA• Scope
2 Interchanges• Character
Urban Construction
DISTRICT OF COLUMBIA• I-295 Improvements
MARYLAND• Scope
2 Interchanges• Character
Over Water, Open
4
Bascule contract work from existing operator’s tower
5
Existing Woodrow Wilson Bridge
6
• Safety . . . has nearly twice the accident rate of similar
highways in Maryland and Virginia as well as the American Legion Bridge . . .
• Traffic Volume. . . is burdened with seven hours of congestion
daily and frequent several-mile backups . . .
Need For Replacement
7
Design Contest
8
Design Contest
9
Design Contest
10
Design Contest
11
Design Contest
12
Design Contest
13
Design Contest
14
Design Contest
15
Design Contest
16
Design Contest
17
Design Contest
18
Design Contest
19
Design Contest
20
Design Contest
21
Design Contest
22
• Joint Venture– Parsons Brinckerhoff (Lead)– URS Corporation– Rummel Klepper & Kahl
General Engineering Consultant Potomac Crossing Consultants
23
BR-1 Dredging Operation
• Weeks Marine Inc.• $14.5 M Contract• Sept. 00 - March 01• 300,000 cubic yards • Used to fill 50-acre hole at
the Shirley Plantation on the James River that was mined for sand and gravel
24
BR-2 Foundations Contract
• Joint Venture Tidewater/Kiewit/Clark
• $125M Contract• 5/2001 - 7/2003• 72” Pipe Piles (Bascule)• 35 Per Foundation x 4
25
BR-2 Foundations Contract
• Installed With Ringer Crane 300’ Boom
• -210’ Tip Depth• Sunk Up To -70’ Under
Self Weight• Excavated & Filled
W/Concrete To -135’
26
BR-2 Foundations Contract
27
BR-2 Foundations Contract
28
BR-2 Foundations Contract
29
BR-2 Foundations Contract
30
BR-2 Foundations Contract
31
BR-2 Foundations Contract
32
BR-2 Foundations Contract
33
BR-2 Foundations Contract
34
Bascule contract work from existing operator’s tower
35
Bascule contract work from existing operator’s tower
BR-3A Bascule Spans
36
Bascule contract work from existing operator’s tower
BR-3A Bascule Spans
37
Bascule contract work from existing operator’s tower
BR-3A Bascule Spans
38Finished V1 OL Pier
BR-3A Bascule Spans
39
BR-3A Bascule Spans
40
BR-3A Bascule Spans
41
BR-3A Bascule Spans
42
BR-3A Bascule Spans
43
BR-3A Bascule Spans
44
BR-3A Bascule Spans
45
BR-3A Bascule Spans
46
BR-3A Bascule Spans
47
BR-3A Bascule Spans
48
Virginia Approach ContractJones Point Park, Alexandria, VA
BR-3B Virginia Fixed Spans
49
Virginia Approach ContractJones Point Park, Alexandria, VA
BR-3B Virginia Fixed Spans
50
BR-3B Virginia Fixed Spans
51
BR-3B Virginia Fixed Spans
52
BR-3B Virginia Fixed Spans
53
View of the casting yard, for the Maryland Approach Spans,National Harbor property, Oxon Hill, MD
View of the shuttle-lift moving the pre-cast concrete forms
BR-3C Maryland Approach Spans
54
BR-3C Maryland Approach Spans
55
View of the pier erection for the Maryland Approach Spans,Potomac River
BR-3C Maryland Approach Spans
56
Virginia Right-of-Way Considerations
Relocation/Property Management
Hunting Towers
57
VA-3 Hunting Tower Demolition
58
VA-4 Virginia Tie-In Contract
59
Urban Deck
60
VA-4 Virginia Tie-In Contract
Early Tie-In Proposal
61
• On schedule
• On budget
• Excellent Safety Record
• Excellent Environmental Record
Current Status