7/23/2019 Mechanical Equipment Procedure TSE http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 1/11 JOINT OPERATING BODY PERTAMINA - TALISMAN JAMBI MERANG DOCUMENT NO : - CONSORTIUM PT. SULUH ARDHI ENGINEERING -  PT. MEGA PRATAMA UNGGUL  PROJECT NO : 4500001473 11 pages JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK MECHANICAL EQUIPMENT ERECTION PROCEDURE PROJECT : EPC GAS METERING AT GRISSIK LOCATION : GRISSIK, MUSI BANYUASIN – SUMATERA SELATAN OWNER : JOB PERTAMINA – TALISMAN JAMBI MERANG CONTRACTOR : CONSORTIUM PT. SAE – PT. MPU PO. NO. : GRS-CT-N-002 PO. DESCRIPTION : PIPING, MECHANICAL AND STEEL SRUCTURE WORK REQUISITION NO. : - VENDOR NAME : PT. TRISERAPHIM ENGINEERING VENDOR DOC. NO : TSE-GRS-PR-006 A  01  /04  /2014 Issued for Approval Rev. Date Description  BY CHK’D APP’D APP’D CONTRACTOR CLIENT

Mechanical Equipment Procedure TSE

Embed Size (px)

Citation preview

Page 1: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 1/11

JOINT OPERATING BODY 

PERTAMINA - TALISMAN JAMBI MERANG 

DOCUMENT NO : 

CONSORTIUM 

PT. SULUH ARDHI ENGINEERING - 

PT. MEGA PRATAMA UNGGUL 

PROJECT NO : 4500001473

 

11 pages 

JAMBI MERANG DEVELOPMENT PROJECT 

EPC GAS METERING AT GRISSIK 

MECHANICAL EQUIPMENT ERECTION PROCEDURE

PROJECT : EPC GAS METERING AT GRISSIK 

LOCATION : GRISSIK, MUSI BANYUASIN – SUMATERA SELATAN 

OWNER : JOB PERTAMINA – TALISMAN JAMBI MERANG 

CONTRACTOR : CONSORTIUM PT. SAE – PT. MPU 

PO. NO. : GRS-CT-N-002 

PO. DESCRIPTION : PIPING, MECHANICAL AND STEEL SRUCTURE WORK

REQUISITION NO. : - 

VENDOR NAME : PT. TRISERAPHIM ENGINEERING

VENDOR DOC. NO : TSE-GRS-PR-006 

A   01 /04 /2014 Issued for Approval

Rev. 

Date 

Description 

BY CHK’D APP’D APP’D

CONTRACTOR CLIENT

Page 2: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 2/11

JAMBI MERANG DEVELOPMENT PROJECT

EPC GAS METERING AT GRISSIK 

Doc. No : - Rev: AMECHANICAL EQUIPMENT

ERECTION PROCEDURE 

Date : 01/04/2014 

Page 2 of 11

REVISION TABLE 

PAGEREVISION

PAGEREVISION

ATTACHMENTREVISION

A B 0 1 2 3 4 A B 0 1 2 3 4 A B 0 1 2 3 4

1 X 31

2 X 32

3 X 33

4 X 34

5 X 35

6 X 36

7 X 37

8 X 38

9 X 39

10 X 40

11 41

12 42

13 43

14 44

15 45

16 46

15 47

18 48

19 49

20 50

21 51

22 52

23 53

24 54

25 55

26 56

27 57

28 58

29 59

30 60

Page 3: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 3/11

JAMBI MERANG DEVELOPMENT PROJECT

EPC GAS METERING AT GRISSIK 

Doc. No : - Rev: AMECHANICAL EQUIPMENT

ERECTION PROCEDURE 

Date : 01/04/2014 

Page 3 of 11

RECORD OF REVISION 

Rev No  Section  Page  Company Comment  Implemented (Y/N)  Explanation 

 A   All   All  -  -  - 

Page 4: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 4/11

JAMBI MERANG DEVELOPMENT PROJECT

EPC GAS METERING AT GRISSIK 

Doc. No : - Rev: AMECHANICAL EQUIPMENT

ERECTION PROCEDURE 

Date : 01/04/2014 

Page 4 of 11

TABLE OF CONTENTS

1. GENERAL  5

2. PURPOSE  5

3. REFFERENCE 5

4. DESCRIPTION OF PROCEDURE  5

4.1 Receipt and Storage 5

4.2 Inspection before Installation 5

5. EQUIPMENT INSTALLATION  65.1 Equipment 6

a Sales Gas Filter 6

 b Vent CO2 Snuffing Package 6

c Vent Stack 6

d Emergency Diesel Generator Package 6

e Diesel Supply Tank 6

f Potable Water Overhead Tank 6

g Fire Fighting and Safety System 6

h Sales Gas Metering Package  6

6. GROUTING  7

6.1 Chipping 7

6.2 Cleaning 7

6.3 Making Formwork 7

6.4 Preparing Grouting Equipment and Water 7

6.5 Clean Up 7

6.6 Grouting Process 7

7. ATTACHMENT 

Table 1.1. 8

Drawing 1.1. 8

Flow Chart of Static Equipment Erection Procedure 9

SikaGrout 125 10

Page 5: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 5/11

JAMBI MERANG DEVELOPMENT PROJECT

EPC GAS METERING AT GRISSIK 

Doc. No : - Rev: AMECHANICAL EQUIPMENT

ERECTION PROCEDURE 

Date : 01/04/2014 

Page 5 of 11

1. GeneralInstallation of Sales Gas Metering Package, Venting System, Power Generation system,Potable

Water and Fire Fighting and Safety System for EPC Gas Metering at Grissik ’s project, JOB

Pertamina - Talisman, Jambi.

2. PurposeThis procedure covers the installation Mechanical with reference to specifications, standards

and drawings provided by the client and as a guide for companies to carry out the above work.

3. Refference

3.1. PQP

3.2. Flow Chart Mechanical Prosedur

3.3. Equipment Installation Procedure Manual Book.

3.4 Equipment Construction Drawing.

4. Description of Procedure

4.1 . Receipt and Storage

All Equipment must be checked before being installed first. Inspection is done togetherwith the client and vendor equipment. Check is performed to see whether the condition

of the equipment is damaged or accessories missing.

In the inspection process must be tailored to the list by taking into account the size of

the shipment. In the event of damage or loss of the components to be made in the form

of a written report MRR.

In the work JOB Pertamina-Talisman Jambi company has the scope of work on the

truck then mounted admission to the foundation.

4.2. Inspection before Installation.

The following are the steps that must be done prior to installation:-  Assure that the foundation has been properly inspected in accordance with the

dimensions given in the drawings and have markers at the point coordinates.

(Accompanied by the report of the surveyor and the results of the inspection along

with the client).

-  Ensure that it is raining at the time of installation

-  Check the position of the anchor bolt and tilt tolerance is in accordance with the

specifications and construction drawings and compare it to the dimensions of the

 bolt holes on the equipment that will be installed.

-  Setting up the instrument in the form of cranes, chain blocks, slings wire / belt

slings, sackle and others that will be used in accordance with the capacity toconvince and adoptive.

Page 6: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 6/11

JAMBI MERANG DEVELOPMENT PROJECT

EPC GAS METERING AT GRISSIK 

Doc. No : - Rev: AMECHANICAL EQUIPMENT

ERECTION PROCEDURE 

Date : 01/04/2014 

Page 6 of 11

-  Ensure that the crane had a solid foundation, if it should be necessary hardening or

setting up a steel plate that corresponds to the capacity.

-  Perform chipping at the foundation approximately 3-5 cm.

-  Then mark the position of the padding plate

-  The surface to be cleaned, and the former chipping moistened, then given cemen

grouting for padding plate and make sure that the elevation of padding plate in

accordance with the specifications or drawing.

5. Equipment Installation

5.1 Equipment :

a. Sales Gas Filter 38 Inch (OD), 120 Inch (H), Weight 4.800 Kg

 b. Vent CO2 Snuffing Package

c. Vent Stack 

d. Emergency Diesel Generator Package Dim. 2 m x 1.2 m x 1.35 m, Weight 1.100 Kg

e. Diesel Supply Tank Dimension 2.54 m x 76.2 m x 1.35 m, Weight 330 Kg

f. Potable Water Overhead Tank 

g. Equipment Fire Fighting and Safety System

Installation procedure as follows:

-  Installation of using a crane with a capacity of 10 tons (for load above 50 Kg)

-  Position the crane in a safe place, where there are no objects or disturbing material

at the time of swing

-  Use as a spreader and chain block lifting aids if necessary

-  Setting up a sling and sackle according to capacity and there should be no damage

to the lifting tools

-  Assure that sackle accordance with the dimensions of the hole in the lifting lug

equipment 

-  Taking into account the position of the direction of the equipment is in conformitywith the specifications and drawings 

-  Install the Equipment 

-  Assure that at the time of installation in accordance with the specification and the

desired elevation 

-  Install the anchor bolt nut 

-  When the installation is in accordance with the drawings and specifications, then

remove the sling and other tools 

-  Have a general elevation in accordance with the specifications and drawings

(accompanied by the inspection report with clients) 

-  Grouting (See Grouting Procedure) 

Page 7: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 7/11

JAMBI MERANG DEVELOPMENT PROJECT

EPC GAS METERING AT GRISSIK 

Doc. No : - Rev: AMECHANICAL EQUIPMENT

ERECTION PROCEDURE 

Date : 01/04/2014 

Page 7 of 11

h. Equipment Sales Gas Metering Package Dim. : 12.55 m x 2.8 m x 2.16 m, Weight

17.500 kg

Installation procedure as follows:

-  Installation of using a crane with a capacity of 10 tons

-  Position the crane in a safe place, where there are no objects or disturbing material

at the time of swing

-  Use as a spreader and chain block lifting aids if necessary

-  Setting up a sling and sackle according to capacity and there should be no damage

to the lifting tools

-  Assure that sackle accordance with the dimensions of the hole in the lifting lug Gas

Metering equipment skid. -  Taking into account the position of the direction of the equipment is in conformity

with the specifications and drawings 

-  Install the Gas Metering equipment

-  Assure that at the time of installation in accordance with the specification and the

desired elevation 

-  Install the anchor bolt nut

-  When the installation is in accordance with the drawings and specifications, then

remove the sling and other tools 

-  Have a general elevation in accordance with the specifications and drawings

(accompanied by the inspection report with clients) 

-  Grouting (See Grouting Procedure)

6. GroutingPreparation :

a. Chipping

Perform cipping the concrete surface is still flat, so it can penetrate the grout cement

slurry and blend with the concrete base.

 b. Cleaning

After chipping activities done then proceed with cleaning the floor surface until no dust,

and other materials to cause the cement grout that may not converge

c. Making Formwork 

Formwork need to be made so that at the time of pouring cement grout did not come out

of the foundation going in the grout

d. Preparing Grouting Equipment and Water 

Prepare all equipment for the preparation of a grouting cement mixers, clean water.

e. Clean up

After all the preparation is done, then pour water into the location that will digrouting

and let the condition for about 2 hours, then dry the area.

Page 8: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 8/11

JAMBI MERANG DEVELOPMENT PROJECT

EPC GAS METERING AT GRISSIK 

Doc. No : - Rev: AMECHANICAL EQUIPMENT

ERECTION PROCEDURE 

Date : 01/04/2014 

Page 8 of 11

f. Grouting Process

-  After all the preparation is done, it should be noted that the temperature of the water 

must follow the appropriate temperature required in the procedure (procedure

 parbik).

-  Ensure that the results of mixing cement grout according to manufacturer's

standards

-  Add water into the mixing vessel and stir slowly until the condition completely

fused cement with water for approximately 5 minutes. (See table 1.1)

-  Once the mixture is completely blended, pour cement grout mixture is stirred slowly

into bagasting that has been provided on one side (see figure 1.1).

-  Mortar shall evenly to fill every pore under the base plate-  After all the grouting process is done, then let the cars for 3 days (72) hours and the

condition should be kept moist by watering.

Table. (1.1)

SikaGrout 215

No Flow ConditionWater Requirement

( Litres / 25 Kg bag )

01 Trowellable 2.75

02 Flowllable 4.25

Drawing 1.1

Page 9: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 9/11

JAMBI MERANG DEVELOPMENT PROJECT

EPC GAS METERING AT GRISSIK 

Doc. No : - Rev: AMECHANICAL EQUIPMENT

ERECTION PROCEDURE 

Date : 01/04/2014 

Page 9 of 11

Page 10: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 10/11

JAMBI MERANG DEVELOPMENT PROJECT

EPC GAS METERING AT GRISSIK 

Doc. No : - Rev: AMECHANICAL EQUIPMENT

ERECTION PROCEDURE 

Date : 01/04/2014 

Page 10 of 11

Page 11: Mechanical Equipment Procedure TSE

7/23/2019 Mechanical Equipment Procedure TSE

http://slidepdf.com/reader/full/mechanical-equipment-procedure-tse 11/11

JAMBI MERANG DEVELOPMENT PROJECT

EPC GAS METERING AT GRISSIK 

Doc. No : - Rev: AMECHANICAL EQUIPMENT

ERECTION PROCEDURE 

Date : 01/04/2014 

Page 11 of 11