8
Paper Number 33, Proceedings of ACOUSTI CS 2011 2-4 November 2011, Gold Coast, Australia Measurement and Prediction of Construction Vibration Affecting Sensitive Laboratories Kym Burgemeister (1 ), Kai F is her (1) and Kathy Franklin (2) (I) Arup Acoustics, Melbourne, Australia (2) Arup Advanced Technology and Research, Sydney, Australia ABST RACT Heavy mechanised construction works, for example, excavation, piling and vibratory compaction cause groundbome vibration due to the interaction of the machines with the ground. This construction vibration can be perceptible to humans, often adversely impacts on se nsitive receh ers located very close to the construction site and in extreme cases may cause structural damage to nearby buildings. An assessment of construction Yibration impacts is therefore usually restricted to sites directly adjacent to constrnction sites. However, laboratory buildings for nano-science, elec- tronics lithography, high-magnification electron microscopy or imaging are significantly more sensitive to vibration than conventional commercial or residential buildings. A theoretical analysis indicates that it is possible that con- struction vibration from particular machinery could exceed the usual sensitive laboratory Yibration velocity limits (eg VC-E, 3 μmis) at distances up to 100-150 m from the construction site. This could necessitate the implementation of restrictive limitations on construction sites at relatively large distances from laboratory buildings to avoid adverse impacts on vibration sensitive equipment and processes. In this study, predictions of vibration from typical heavy constrnction works at long distance are made using both geometric spreading and frequency dependant attenuation models. The results of the predictions are compared to long-distance vibration velocity measurements undertaken on typical development sites due to the operation of bored piling and vibratory compaction equipment. The measurement results show good agreement with the empirical predictions, and show that vibration from heavy construction works can be expected to exceed VC-E at distances of I 00-150 m from the construction site. INTRODUCTION Groundbome vibration from heavy construction works, par- ticularly excavation and foundation works, has the potential to adversely affect nearby receiYers. The potential impacts commonly include subjective disturbance to human (and sometimes animal) occupants - between vibration levels 1- 5 mm/s, or concern regarding building or infrastructure dam- age (between 5-50 mm/s). Due to the relatively high vibra- tion levels necessary to be perceptible in adjacent buildings, these types of impacts are generally only of concern in im- mediate proximity to the construction works. Recent construction vibration guidance (Construction Noise Strategy, 2007) suggests 'appropriate distances' of between 2-25 m are adequate to control vibration to prevent building damage, although they may not be sufficient to ensure rea- sonable amenity for human perception. Although these 'rules of thumb' may be a reasonable means of managing com- plaints, they do not translate well to the management of vi- bration impact for sensitive equipment, since these usually have more onerous requirements. For example, laboratory buildings for nano-science, electron- ics lithography, or high-magnification electron microscopy or imaging are sig nificantly more sensitive to vibration than conventional commercial or residential buildings. These types of buildings are commonly designed to achieve internal vibration levels between VC-E (3 μm /s) and VC-B (25 μm/s) (Ungar et al., 1990). While this type of sensitive technical equipment is sometimes supported on local equipment-based isolation system or on vibration isolating floated floor systems, these systems usu- ally increase the mobility of the equipment support, and al- most always amplify low-frequency occupati onal vibration. It is therefore common to locate this type of equipment on at- Acoustics 201 I grade or basement slabs to provide a solid, high-impedance and low-vibration base. Furthermore, while exceeding specified vibration criteria may sometimes result in manageable temporary interruptions, for some laboratory research, even sho1t-term vibration can result in the loss of many months or even years of research time. This means that existing vibration sensitive facilities at labo- ratories or hospitals are highly sensitive to vibration from construction works, even when that construction is a consid- erable distance from the laboratory site. In tum, this means that vibration from construction works will need to be care- fully managed during the constru ction process to minimise the potential for adverse impacts on the operation of the labo- ratories. The extent of potential construction vibration impacts at large distances is subject to considerable uncertainty due to ground conditions, and there are few studies that particularly con- sider co nstruction vibration on highly sensitive buildings (Amick & Gendreau, 2000). Arup has recently undertaken studies for several existing and proposed technical buildings for highly vibration sensitive equipment which will be sub- ject to future construction works within several hundred me- tres of the equipment. This paper documents the results from these construction vibration investigations for high-technology building s. Ini- tially. a desktop investigation was undertaken using empirical prediction equations, and combining measurement results from previous site investigations with geometric and fre- quency dependant propagation loss models. Site vibration measurements were also undertaken using high-sensitivity equipment at large distances for several 'worst case' con- struction processes - installation of bored piles (augering, vibrating casings), usi ng a vibratory roller for ground com- paction and general movement of heavy site equipment.

Measurement and Prediction of Construction Vibration Affecting … · 2016-12-16 · Heavy mechanised construction works, for example, excavation, piling and vibratory compaction

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Measurement and Prediction of Construction Vibration Affecting … · 2016-12-16 · Heavy mechanised construction works, for example, excavation, piling and vibratory compaction

Paper Number 33, Proceedings of ACOUSTICS 2011 ~ 2-4 November 2011, Gold Coast, Australia

Measurement and Prediction of Construction Vibration Affecting Sensitive Laboratories

Kym Burgemeister (1 ), Kai Fisher (1) and Kathy Franklin (2)

(I) Arup Acoustics, Melbourne, Australia (2) Arup Advanced Technology and Research, Sydney, Australia

ABSTRACT Heavy mechanised construction works, for example, excavation, piling and vibratory compaction cause groundbome vibration due to the interaction of the machines w ith the ground. This construction vibration can be perceptible to humans, often adversely impacts on sensitive receh ers located very close to the construction site and in extreme cases may cause structural damage to nearby buildings. An assessment of construction Yibration impacts is therefore usually restricted to sites directly adjacent to constrnction sites. However, laboratory buildings for nano-science, elec­tronics lithography, high-magnification electron microscopy or imaging are significantly more sensitive to vibration than conventional commercial or residential buildings. A theoretical analysis indicates that it is possible that con­struction vibration from particular machinery could exceed the usual sensitive laboratory Yibration velocity limits (eg VC-E, 3 µmis) at distances up to 100-150 m from the construction site. This could necessitate the implementation of restrictive limitations on construction sites at relatively large distances from laboratory buildings to avoid adverse impacts on vibration sensitive equipment and processes. In this study, predictions of vibration from typical heavy constrnction works at long distance are made using both geometric spreading and frequency dependant attenuation models. The results of the predictions are compared to long-distance vibration velocity measurements undertaken on typical development sites due to the operation of bored piling and vibratory compaction equipment. The measurement results show good agreement with the empirical predictions, and show that vibration from heavy construction works can be expected to exceed VC-E at distances of I 00-150 m from the construction site.

INTRODUCTION

Groundbome vibration from heavy construction works, par­ticularly excavation and foundation works, has the potential to adversely affect nearby receiYers. The potential impacts commonly include subjective disturbance to human (and sometimes animal) occupants - between vibration levels 1-5 mm/s, or concern regarding building or infrastructure dam­age (between 5-50 mm/s). Due to the relatively high vibra­tion levels necessary to be perceptible in adjacent buildings, these types of impacts are generally only of concern in im­mediate proximity to the construction works.

Recent construction vibration guidance (Construction Noise Strategy, 2007) suggests ' appropriate distances' of between 2-25 m are adequate to control vibration to prevent building damage, although they may not be sufficient to ensure rea­sonable amenity for human perception. Although these 'rules of thumb' may be a reasonable means of managing com­plaints, they do not translate well to the management of vi­bration impact for sensitive equipment, since these usually have more onerous requirements.

For example, laboratory buildings for nano-science, electron­ics lithography, or high-magnification electron microscopy or imaging are significantly more sensitive to vibration than conventional commercial or residential buildings. These types of buildings are commonly designed to achieve internal vibration levels between VC-E (3 µm/s) and VC-B (25 µm/s) (Ungar et al., 1990).

While this type of sensitive technical equipment is sometimes supported on local equipment-based isolation system or on vibration isolating floated floor systems, these systems usu­ally increase the mobility of the equipment support, and al­most always amplify low-frequency occupational vibration. It is therefore common to locate this type of equipment on at-

Acoustics 201 I

grade or basement slabs to provide a solid, high-impedance and low-vibration base.

Furthermore, while exceeding specified vibration criteria may sometimes result in manageable temporary interruptions, for some laboratory research, even sho1t-term vibration can result in the loss of many months or even years of research time.

This means that existing vibration sensitive facilities at labo­ratories or hospitals are highly sensitive to vibration from construction works, even when that construction is a consid­erable distance from the laboratory site. In tum, this means that vibration from construction works will need to be care­fully managed during the construction process to minimise the potential for adverse impacts on the operation of the labo­ratories.

The extent of potential construction vibration impacts at large distances is subject to considerable uncertainty due to ground conditions, and there are few studies that particularly con­sider construction vibration on highly sensitive buildings (Amick & Gendreau, 2000). Arup has recently undertaken studies for several existing and proposed technical buildings for high ly vibration sensitive equipment which will be sub­ject to future construction works within several hundred me­tres of the equipment.

This paper documents the results from these construction vibration investigations for high-technology buildings. Ini­tially. a desktop investigation was undertaken using empirical prediction equations, and combining measurement results from previous site investigations with geometric and fre­quency dependant propagation loss models. Site vibration measurements were also undertaken using high-sensitivity equipment at large distances for several 'worst case' con­struction processes - installation of bored piles (augering, vibrating casings), using a vibratory roller for ground com­paction and general movement of heavy site equipment.

Page 2: Measurement and Prediction of Construction Vibration Affecting … · 2016-12-16 · Heavy mechanised construction works, for example, excavation, piling and vibratory compaction

2-4 November 2011, Gold Coast, Australia

EMPIRICAL STUDY

Initially, an empirical study was undertaken using established empirical data for vibration levels generated by typical con­struction processes and equipment from published literature and previous site measurements.

The aims of the empirical study were to:

1. Identify construction activities that could potentially cause unacceptable vibration levels at the sensitive receiver.

2. Define vibration impact zones around the receiver and determine constmction activities within these zones that could influence the vibration perfonnance within the sensi­tive receiver.

In order to achieve these goals, predictions of anticipated vibration levels at various distances due to typical constntc­tion activities were required. This included prediction of vibration propagation over large distances for vibration sensi­tive facilities.

Vibration Propagation Models

Vibration in soil can propagate with various types of waves, propagating both on the surface of the soil and through the body of the soil. These different wave types travel at different speeds. Close to the source, it is expected that all forms of vibration will be important, but at larger distances, typically in the hundreds of meters, the relative levels of these vibra­tions can vary depending on the soil type. This is because different types of waves are attenuated at different rates due to their differences in speed and propagation methods.

There are two broad mechanisms that attenuate vibration as it propagates through the soil (Bomitz, 193 1 ). These are

• Geometric loss - where attenuation is modelled by geometric spreading to match empirical data

• Material loss - where attenuation is modelled by fric­tional loss in the soil to match empirical data

Geometric loss is due to the spreading of waves as they propagate out from the source. The rate of loss depends on the type of wave.

Material loss is due to viscous behaviour of the soil and is a loss per unit distance travelled. It can also be considered to be frequency dependant, the attenuation increasing with increas­ing frequency (Woods & Jedele, 1985; Amick, 1999).

Typically, empirical work in the past has used either a geo­metric loss model, where the loss due to spreading is deter­mined from regression analysis of measured data, or by using material loss with an assumed constant geometric loss.

Frequency Dependant Material Loss Propagation Model

Amick (1999) proposed a propagation model with a fre­quency dependant material damping loss function as shown in Equation (1). It defines the vibration level at location b relative to the vibration level at location a, and provides a damping constant for material loss. Assuming Raleigh wave propagation is dominant, y is set to 0.5.

2

Proceedings of ACOUSTICS 201 1

Where; Va is the vibration level at location a vb is the vibration level at location b r" is the distance from the source at location a rb is the distance from the source at location b yis the geometric propagation loss term. p is the material damping loss f is the frequency of the vibration

(1)

Ranges of material damping loss, p, fo r various categories of soil types are shown in Table 1 (Woods & Jedele, 1985).

Table 1 Soil Classes and Material Attenuation

Class

IV

ITT

II

Description

Hard. competent rock (difficult to break with rock hammer): bedrock, freshly exposed hard rock

Hard soils (cannot dig with shovel, must use pick to break up) : dense compacted sand, dry consolidated clay, consolidated glacial till, some exposed rock

Competent soils (can dig with shovel); most sands, sandy clays, silty clays, gravel, silts, weathered rock.

Weak or soft soils (Soi l penetrates easily); lossy soils, dry or partially saturated peat and muck, mud, loose beach sand and dune sand, recently plowed ground, soft spongy forest or jungle floor, or­ganic soils, topsoil

Geometric Loss Models

< l.8xl0·6

J.8x I o·6·

to 1.8x 10-5

l.8x 10·5

to 6. lx!0"5

6.lxto·5

to 1.8x I 04

Geometric loss models ignore the material damping (loss) coefficient (pin Equation (1) ), assuming it is zero. To allow for different propagation losses, y is varied. y is generally selected based on soil type and typically varies between 0.5 and 2.0. In the initial empirical studies y was set to 1.5.

It is expected that different site conditions wi ll require d iffer­ent y values, in addition, different types of vibration sources may in general have d ifferent y values even for the same site. However due to large variation in measured vibration levels, detennining a y which varies by both vibration source and soil type is difficult. Usually in the case of prediction, un­knowns about the soil type and input vibration levels in the soil are far more significant than variation in gamma between vibration equipment for short to medium range distances (up to approximately 80-100 m).

Empirical Vibration Source Levels

The UK Transport Research Laboratory (TRL) (Hiller & Crabb, 2000) has undertaken specific ground vibration meas­urements for a wide range of typical construction equipment and processes, across a wide range of distances and ground

Acoustics 2011

Page 3: Measurement and Prediction of Construction Vibration Affecting … · 2016-12-16 · Heavy mechanised construction works, for example, excavation, piling and vibratory compaction

Proceedings of ACOUSTICS 201 1

conditions. The TRL empirical data is widely used as the basis of construction vibration prediction, but is only vali­dated for short to intermediate distances (up to 100 m)

The TRL data has been supplemented with vibration meas­urements recently undertaken by Arup for some excavation, pi ling and construction works on Australian sites.

For the purposes of the study empirical equations for the vibration levels of impact piling, vibratory piling, vibratory compaction, and mobile plant operation were used as follows (Hiller & Crabb, 2000);

Vibratory Compaction:

[ A 1'°5

v,..s = k".j;; x + Ld J (2)

Where k,= 175, nd = 1, A = 1 mm, Ld = 2.5 m.

Percussive Piling:

v,,, ~ k,[ ~~ (3)

WherekP = 1.5, W = 60 kJ and?= L2 + x2,L = 27 m

Vibratory Piling:

(4)

Where k,. = 160, <5 = 1.3

In addition, Hiller (2003) determined linear function lines in the logarithm of velocity and distance for large quantities of pile data in the UK. The regression functions were used to predict the vibration level as a function of distance.

EMPIRICAL VIBRATION PREDICTIONS

Vibration predictions were conducted for a range of construc­tion activities which have been categorised into: • Piling

o Screw/Augered Piling o Continuous Flight Auger Piling (CF A) o Impact Piling o Sheet Piling

• Vibratory Compaction • General Mobile Plant Movement and Operation

Overall empirical v ibration levels were determined using TRL (H iller & Crabb, 2000) and Hiller (2003) equations as functions of distance from the source.

The predicted vibration levels at 20 m using TRL and Hiller were also used as reference levels for use in the geometric loss propagation models (ie Equation (I) with p = 0 and

r = 1.5).

Where spectra were available (from previous site measure­ments) at short distances, vibration levels as a function of distance have been predicted using the Amick ( 1999) fre­quency dependant propagation model in one-third octave bands. The soil type at the subject site was determined to be C lass ll. An initial value for the material damping p = 6.1x l0-5 m·1Hz·1 was used (see Table 1 ).

Acoustics 20 I I

2-4 November 20 11, Gold Coast, Austra lia

The spectra used for predicting vibration levels w ith the Amick ( 1999) model are presented in Figure 1.

10'

~ 10' E ;;. g ~ 101

] ~

10° ~ e ~ ~ IO·I

w-1

180

170

++uuuu~~iHiiH1 160 i

ISO

16 Jl.5 6) !ZS

frequotnc:) (Third Od.:r.vc B.ind Cenlrc.s). Hz

'C•liUt C~ ._,..,., ;;::• &.'w~t Pllc ilf J,• • + a. ••: t• A •r•Jc \. .a: ~atory ~ ion n , • Y

-...•ca.ir ed. .1t r•gt l'4C'b1lt Ph nt •t I\• )i(

'•••.,~~ """~""' )'l;:,b lle i>l•n~ •t 1:0 "' 0

140

1.10

120

110

100

90

80 25-0

-~

ill .~ 1 ~ 1

Figure I Source vibration velocity spectra measured at Aus­tralian sites for various construction activities.

Predictions of both overall vibration levels as a function of distance and frequency spectra are presented at the end of the following section.

Note that vibration using Equation ( 1) for augered piling was not possible due to lack of reference spectral levels.

CONSTRUCTION VIBRATION SITE MEASUREMENTS

Following the initial theoretical study using empirical data, site measurements were undertaken of actual construction vibration at the future site of a high-technology laboratory facility. The objectives of the site measurements were: • To provide some actual measured vibration levels of

likely construction activi ties at this site. • Confirm vibration propagation predictions through the

ground at the laboratory site for activity at surface and rock levels

• Particular investigation of vibration levels generated at standoff d istances >I 00 m and for low levels of vibra­tion around VC-E where there is little empirical data

Measurements of v ibration levels generated at the laboratory site by various construction sources were made in D ecember 20 l 0 . Vibration levels were measured using a Data Physics Quattro 4 channel data acquisition system and Larson-Davis 2 channel data acquisition system with PCB39312 and Brue! & Kjrer 4370 high sensitivity accelerometers.

The accelerometers were installed in three different layouts for the various measurements. Accelerometers were mounted as follows to ensure good coupling:

Soil surface - Accelerometers were mounted using beeswax or mounting studs to the top of a wooden stake driven fomly into the ground at each measurement location.

Test pile - Accelerometers were mounted using beeswax to the concrete surface of a test pi le installed at the site.

Measurement Borehole: - Accelerometer was fixed to the base of a heavy waterproof canister and lowered to the bot­tom of a site borehole.

3

Page 4: Measurement and Prediction of Construction Vibration Affecting … · 2016-12-16 · Heavy mechanised construction works, for example, excavation, piling and vibratory compaction

2-4 November 2011, Gold Coast, Australia

The sensitivity (noise floor) of the combined accelerometers and data acquisition systems was confirmed to be below VC-E in each case.

Construction Activities

Site vibration measurements were undertaken at various dis­tances from the following construction works: • bored piling • vibratory pile casing • vibro-compaction using a vibratory roller • general movement of mobile plant (eg piling rig, exca­

vators)

Bored piling was selected for the measurements instead of impact piling because it is a common construction process, and it would be difficult to find a lower vibration alternative. It will also cause vibration at both rock level as well as in the softer soils above.

Vibro-compaction was selected because the input is fairly clearly defined in terms of magnitude and frequency. Moving the plant provides an indication of the effect of general plant and vehicle movements.

COMPARISON OF EMPIRICAL PREDICTIONS TO MEASUREMENT

Empirical predictions of vibration levels for the various con­struction equipment and processes are compared to the values measured at a future high-sensitivity laboratory site in Figure 2 to Figure 7.

JO 20 50 JOO 200

Dtstanc\:. m

J60

" 140 ~

,;. 8

120 ~ ii E >

100 ~

She : ' Pile iM1 ~· 1 -- -:-ect Pll e ((•,•4tnel · · · ·· ··· ~a .. 1.u c <J l. • • 1"11 l;uu .... , + V;.bra~o -~ n . 1 -- \ Lb;. •t<1ry t -ct'1"") , •. , .. u ....- i >~~.- A

, _, , ,. c~l • .~I -- . ,.,.C'-"'"iv,.. f .. ,...-lric..I .l.JotJ• " f'.ll cr l -- lo]er lCk~t tc) c~·. 1..J l • • ' ' - - e<A c<. •. •• u . .:1

Figure 2 Comparison between empirical predictions and measurements of pi ling vibration velocity.

4

.~

E e ,;. ·~

;:'

Proceedings of ACOUSTICS 2011

10·1 JOO

10·2 80

10·1 60

IC 40

c 0

JO

JO .. ~-~~~--~-~-~--~-~-~ 0 1 16 Jl.5 63 125 250

Frequency (Third Oc1:avc B.ind Centres), H7.

..-.... . .... ...t '1 .. + ~ea.a -~re . oc ,. ( .. ,... r ed : J,; "' •

• -n\ore<i ~$( • 0

Anarlt'll • ( rf!>t t --

,,.Jck '.OCI 111 1•1.::lc U C • M .. u. l SO • •

e "' ., ~ j > ..l

Figure 3 Simultaneously measured vibration spectra due to augered piling at various distances from the source at future high sensitivity laboratory site. Theoretical prediction of the loss as a function of distance is presented using Equation (I) relative to the vibration levels as measured at 63 m.

J01

"

,;. J01 ·· ...

· ~

;:' ] JO'

~ ~ :i: 10·1

E € ~

10~!

~ "'

1o·J JO

····· ...

20

Oi.>tancc. m

;o !00 :?00

t .: ~ .... .,. + "S'J~ It .:>! X

160

""-·. 80

60 500

Figure 4 Empirical predictions of vibration due to vibratory compaction at different RPM. Measurements at future high sensitivity laboratory site are shown and compared to the VC-E vibration criteria.

rn·•

10·1

,;. ~ > 10· '

~ ~

> JO~

~ E "" ~ 1o·s

JO .. J

.. ..

J6 j J 5 6J J25

Frequency (Thud Oc1:n-e F.b.nd Ccn1res). Hz

~-~ · n•'1 (: \ + i '' ~ r@"! : ·V "' )( •, ,.,..,,.,.d l) C ,. lilt

•"r .. a.,;.u·..i ~s o ,. ;,J

,. .,j~k ~ l • h'll ) - ­..... t · ic" 1oc ..

JOO

80

60 " ~ ~

40 i >

;J ]

20

0 250

Figure 5 Simultaneously measured vibration spectra due to vibratory compaction at various distances from the source at future high sensitivity laboratory site. Theoretical prediction of the loss as a function of distance is presented using Equa­tion ( l) relative to the vibration levels as measured at 63 m.

Acousti cs 2011

Page 5: Measurement and Prediction of Construction Vibration Affecting … · 2016-12-16 · Heavy mechanised construction works, for example, excavation, piling and vibratory compaction

Proceedings of ACOUSTICS 2011

10' 160

~ 101 l•O ~

f ;a

j > ] 10° 120 ~ 5 Q >

~ ~

0 :i: 10 I 100 " • ~ ~ E ~ e ::;:

10·' go i ~ ~ "'

ltf' 60 10 20 50 100 200 500

Ois1ancc, m

""''""'-- Gy..- trt.; · M~-''""'' ""- + '-~Ci'.

Figure 6 Empirical predictions of vibration due to various types of mobile plant operating. Measurements at future high sensitivity laboratory site are shown and compared to the VC-E vibration criteria.

10·1

]

" 10·'

c ~ > 10·l

]

~ !l, 10" c ~ <

~ w·~

10·0

., "

16 31..5 63 125

1-'rc:qucncy (Third Octave Band CrnlJ'.:s), Hz

""• i; .1r•j CJ• + Me 1; • • d 1::. 1 •

.. c • n c <i u• • If fl n .. zr i~.-. • C'

..,.iekt.:> n l r e r . l --

100

80

] 60 ~

!ll ]!.

40 j ~ ]

w

0 2:50

Figure 7 Simultaneously measured vibration spectra various types of mobile plant operating at various distances from the source at future high sens itivity laboratory site. Theoretical prediction of the loss as a function of distance is presented using Equation ( l) relative to the vibration levels as measured at 63 m.

Discussion

The measured vibration levels generally show broad agree­ment with the empirical predictions, and confirm that con­struction vibration levels are likely to exceed the criteria for the most sensitive laboratory uses, even at distances of be­tween 100-200 m from the construction works.

Clearly, this will place enormous constraints and manage­ment requirements on future construction works that are un­dertaken in the proximity of the laboratory sites.

Examination of Figure 3, Figure 5 and Figure 7 demon­strates the material damping loss as a function of frequency which was assumed (p = 6.1 x I o·5) may not be large enough due to the slight over prediction in the frequency range ap­proximately between 16 and 80 Hz. The high frequency (above approximately I 00 Hz) is controlled the noise floor of the instrumentation. The slight over prediction also broadly corresponds to the slight over prediction for overall vibration levels which is observed in Figure 4 and Figure 6 at large distances.

Acoustics 2011

2-4 November 2011, Gold Coast, Australia

Theoretical Predictions Using Class I Soil Type Propagation Loss

To test the applicability of the frequency dependant propaga­tion model, a material loss constant of p = L8xlO"" was tested. This c01Tesponds to the upper limit for Class I soils (Woods & Jedele, 1985). The measurements have been com­pared to calculations using a Class I soil type and are pre­sented in Figure 8 to Figure 13.

]!. g ;i! ~ ~ ~ :i:

~ ~ :1 "'

!Ol

101

10°

1u·1

10·1

160

" 140 ~

~

] 120 > .,.

• : ~

100 ~ ., :i:

go

io·l '--~-..._,~......._.,___,__ _ _,_~ ......... ---'-~~ 60

10 20 so 100 200 500

_hu:t "il• .-ictl -- F" • • t •• la 1o ••• .....,t11.: ! •·••· ••• ,.,. ,.,.d t ., ,., 1t. r .. t1..,., + VJb1 •to~-y cr>t..1 ll-utny iJ.oi..,.et~i' '111•• ... nJ ;>.• i1n X

p,.r \1•1 .. :r·L> -- P~ reuaa1·,.- '~ ... tr1e ) ':-1 - - - -A•~er lllillfl ~) -- 1'.. ;•te i:k.. Hric)

Figure 8 Empirical predictions of vibration due to various types of piling (frequency dependant propagation, p = l.8xl0.4

). Measurements at future high sensitivity labora­tory site are shown and compared to the VC-E vibration crite­ria.

100

IO

60

"' 0 r 40 ;J -,

20

10·6 ~-~~~--~-~--'--~~-~-~ 0 I 16 Jl.S 63 l ?S 2:50

Frcqucnc}' (Third Octa\ c Band Ccnh'CS), Hz

fl<"l~.1rrd H • + " • u •.ra-:1 ~'1 0 • ~·

........ . 1"~ ~);. JIE

U•j1• 1-­\.lo l' ~ 1 ., .. ..,,.. :1'1 IJO a

~

" ~ i-g ~ ]

Figure 9 Simultaneously measured vibration spectra due to augered piling at various distances from the source at future high sensitivity laboratory site. Theoretical prediction of the loss as a function of distance is presented using Equation (1) (p = l.8x 10·4) relative to the vibration levels as measured at 63 m.

5

Page 6: Measurement and Prediction of Construction Vibration Affecting … · 2016-12-16 · Heavy mechanised construction works, for example, excavation, piling and vibratory compaction

2-4 November 2011, Gold Coast, Australia

101

.. ..

rn' ,;;

~ x +

~ 10° ------------~ --

140 e 'C

~

~ 10· 1

~ ~

10<? ~

80

"' I0-1 '--~"-~--'~~'--~'--~--'~-....l'--~'--'~\__, w

10 20 50 100 200 500 Oistance, m

Figure 10 Empirical predictions of vibration due to vibratory compaction (frequency dependant propagation, p = l .8x l 0-4). Measurements at future high sensitivity laboratory site are shown and compared to the VC-E vibration criteria.

io·t

io·2

,:;· g ~ 10-J

1i ''2 > f0-4

~ <

~ 10·5

rn·"

"' "

16 3 1.5 6}

Frequency (Third Ocun c B;md Ct:ntn:s), Hz

f" <t U'" l <:' ~:1 ~ + ·~aa\Jr~d 100 .. "<

" llc,,• v• ~c:l 1~1 '"' i;

a....!ck; 1 ~-i ,,..

Allie\: \ l~ 11

100

80

" " w • !1l

"' ·~ •o ~

0 .... l 20

125 250

Figure 1 t Simultaneously measured vibration spectra due to vibratory compaction at various distances from the source at future high sensitivity laboratory site. Theoretical prediction of the loss as a function of distance is presented using Equation ( 1) (p = l.8x 10-4) relative to the vibration levels as measured at 63 m.

101

~ E 10

1

"" ·~

~ .. • .

;; ro0 .. • . • ..

~ 'll " io· l !j ~ i 10·2

~ io·J

Oi~t;incc.m

·~;i..

Figure 12 Empirical predictions of vibration due to mobile plant operation (frequency dependant propagation, p = l .8x l 0-4). Measurements at future high sensitivity labora­tory site are shown and compared to the VC-E vibration crite­ria.

6

Proceedings of ACOUSTICS 2011

11 E

10·1

"' ~ w·~

"

Frequency lThird Oc1avt Band Ccn1res), Hz

~< •~1J r --I JCl + '11".t h Hl I OC"' X

........ '*"' ! ) () '" * ,,.,,.,.._u•i : so"' 0

.... -.ic. .. toe ... IYlll( il DC"'

100

80

-~

w " :g

40 :;i ~ .... l

20

Figure 13 Simultaneously measured vibration spectra due to mobile plant operation at various distances from the source at future high sensitivity laboratory site. Theoretical prediction of the loss as a function of distance is presented using Equation (1) (p = l.8xl0-4) relative to the vibration levels as measured at 63 m.

Discussion

The use of Class T soil instead of Class IT appears generally to provide a marginal improvement to the agreement between the theory and measurement in the frequency range between approximately 1~100 Hz over distances between 63- 150 m. However, variation in the measurement levels on site indicate that for the assumed model a propagation loss anywhere in the range of Class I soils is probably reasonable, particularly since the initial estimate used the upper limit of Class II (which is also the lower limit of Class I soils) also provided reasonable (although slightly high) predictions compared to measurement.

In general the frequency dependant loss agrees reasonably with measurement.

It is also noted that generally speaking the overall level pre­dictions from both TRL (Hiller & Crabb, 2000) and Hiller (2003) were quite reasonable for the types of soil and activi­ties examined in this study.

CONCLUSION

Generally speaking, for large offset distances (greater than 100 m from the source), a geometric loss alone is expected to be less accurate than a frequency dependant vibration propa­gation model. At large distances the behaviour of the overall vibration levels become non-linear, and in particular depends strongly on the source spectrum. For moderate distances (approximately 1~100 m) using a geometric loss for the overall vibration level appears to generally be a reasonable assumption.

Vibration activities with very strong low frequency compo­nents are more likely to agree with a simple geometric loss and those with more high frequency content are likely to either require a different value ofy for the same soil type or a frequency dependant propagation loss should be considered.

Due to the frequency dependant nature of the propagation losses, the. input vibration levels are important for accurate predictions at large distances. This in tum means that input vibration levels for any given construction activity them­selves will be dependant on the soil type.

Acoustics 20 I 1

Page 7: Measurement and Prediction of Construction Vibration Affecting … · 2016-12-16 · Heavy mechanised construction works, for example, excavation, piling and vibratory compaction

Proceedings of ACOUSTICS 2011

To improve predictions, both frequency dependant propaga­tion losses and also typical spectra at a defined reference distance could be documented for various construction activi­ties and soil classes. This would enable selection of soil class and construction activity to determine the reference spectrum and then use of the propagation model to predict the vibration levels at large distances. A reference distance of 20 m is pro­posed as it is close enough that frequency dependant propa­gation is unlikely to have significantly dominated the overall level, and far enough that the assumed Raleigh wave propa­gation is likely to be dominant. Whilst this would not remove the need for vibration measurements for specific sensitive sites it may assist with initial site selection and desktop stud­ies to evaluate risks associated with construction activities negatively impacting sensitive laboratories.

In general, the vibration velocity due typical construction works such as Yibratory compaction and other activities which are usually considered to have relatively low impact, such as augured piling and general site equipment move­ments is expected to be considerably higher than the stringent VC-E vibration criteria, even at stand-off distances of be­tween 100-200 m. This means that construction near to sensi­tive laboratories is likely to impact sensitive equipment and processes within the laboratories and will require careful management and in general will require on site measurement specific to the particular site due to the large variation in vibration levels due to specific site conditions.

REFERENCES Amick, H 1999, 'A Frequency-Dependent Soil Propagation

Model ', Proceedings of SPIE Conference on Current De­velopments in Vibration Control for Optomechanical Sys­tems, Denver.

Amick, H, Gendreau, M 2000, 'Construction vibrations and their impacts on Vibration-Sensitive facilities ', Proc. ASCE Construction Congress, Florida.

Amick, H, Gendreau, M, Busch, T & Gordon, C 2005, 'Evolving criteria for Research Facilities: I-Vibration ', Proc SPIE Buildings for Nanoscale Research and Be­yond, San Diego, CA.

Born itz, G 1931 , Uber die A usbreitung der von Grozklol­benmaschinen erzeugten Bodenschwingungen in die Tiej e, J. Springer

Construction Noise Strategy (Rail Projects), 2007, NSW Transport Infrastructure Development Corporation.

Hiller, D & Crabb, 2000, Gmundborne Vibration Caused by Mechanised Construction Works, Transportation Re­search Laboratory

Hiller, DM 2003, ' A comparison of noise and vibration from percussive and bored piling', Proc Underground Con­struction 2003, 213-224 .

Nelson, P ed 1987, Transportation Noise Reference Book, Chapter 16, Butterworth & Co.

Ungar, EE, SturZ, DH, Amick, H 1990, 'Vibration control design of high-technology facilities', J. Sound and Vibra­tion .

Woods, RD, & Jedele, LP 1985, 'Energy - Attenuation Rela­tionships from Construction Vibrations ', Vibration Prob­lems in Geotechnical Engineering, Proc. ASCE Conven­tion, Detroit, October 1985.

Acoustics 20 I I

2-4 November 201 1, Gold Coast, Australia

7

Page 8: Measurement and Prediction of Construction Vibration Affecting … · 2016-12-16 · Heavy mechanised construction works, for example, excavation, piling and vibratory compaction