Measure H Projects Updatepresented to ACSS Division

As of 11/14/2018

Page 2: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Facilities Master Plan – Amendment One

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

About SC / Planning Documents / Facilities Master Plan‐Amendment One (May 2018)

• Maps• Proposed Projects• Neighborhoods

Academic  Student Services

• Buildings (Interior/Exterior) Color Textures Space Prototypes

• Landscaping

Page 3: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Our “new” look!179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles

Proposed Exterior

Front

Back

Student Services One‐Stop‐Shop Building

(100 Building)

Page 4: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Veterans Support & Success Center

Page 5: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Regional Public Safety Training Center

Project Start:  8/2018

Est. Completion:2/2019

Project Start:  6/2018

Est. Completion:1/2019

SHIELD Consortium RPSTC Tour

Page 6: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Regional Public Safety Training Center

Page 7: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Regional Public Safety Training Center

Fire Tower Prop

Rappelling Tower Prop

Page 8: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Athletic Fieldhouse with Restrooms

Project Start:  8/2018

Est. Completion:2/2019

Page 9: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Gymnasium Air Conditioning

Project Start:  10/2018

Est. Completion:1/2019

Page 10: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

179,000

TrinityCampus

61 miles51 miles

Solar Project – East Parking Lot

• 1.6 Megawatts• 8 Bays• Electric Auto Charging Stations (for 10 parking spaces)

Project Start:  10/2018

Est. Completion:6/2019

Page 11: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Solar Project – East Parking Lot

Page 12: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Solar Project – East Parking Lot

Page 13: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

2400 Bldg. – Electrical Upgrade Project

New Distribution Transformer

Electrical Line Rerouting New Electrical Panel

Page 14: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

HSUC Folding Wall Project

WHITEBOARD    PAINT     FABRICANY COMBINATION  

Page 15: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Projects Update

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Approval Received

Construction Commenced/To Commence:• Regional Public Safety Training Center – Phase One (recommenced 9/10/18)

Gifford Construction, Inc. (Infrastructure) and Trent Construction (Props)

• Athletic Fieldhouse with Restrooms Cerami & Browning Construction, Inc. (commenced 8/27/18)

• Gymnasium Air Conditioning Cerami & Browning Construction, Inc. (commenced 10/8/18)

• Solar Project – East Lot  Sunpower (commenced 10/8/18)

In Bid Process:• Campus Safety Relocation – Interior remodel (Bid opening: 11/13/18)

• Veterans Center Building (Holding on bid to combine with CTE Building)

Page 16: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Projects Update (continued)

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Under DSA Review• CTE Building and Covered Storage• Regional Public Safety Training Center Classroom Buildings

DSA Submission Pending• Tehama Campus Student Services Building (to DSA late November)

Design Phase• CIS Building

Page 17: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

Non-DSA Projects179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Current/Upcoming Projects

• HSUC Folding Wall Replacement Bid documents being prepared

• SC Main Campus Keying & Access Control Ongoing construction document preparation

• SC Safety & Security Standards  In Progress

• Campus Wide Infrastructure Projects (water, sewer, storm drain, electrical, fire alarm, technology fiber, gas lines)  CCTV scoping:  Sewer pipes can be sleeved Storm drains have no structural issues (require cleaning)

Page 18: Measure H Projects Update...2018/11/14  · Projects Update 179,000 Trinity Campus Shasta College Main Campus 51 miles 61 miles Approval Received Construction Commenced/To Commence:

18

For more information…About SC / Bond Information / 2016 Bond Measure H

[email protected] / 242‐7699

Theresa Markword, Bond Program Manager