Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Measure H Projects Updatepresented to ACSS Division
As of 11/14/2018
Facilities Master Plan – Amendment One
179,000
TrinityCampus
Shasta CollegeMain Campus
61 miles51 miles
About SC / Planning Documents / Facilities Master Plan‐Amendment One (May 2018)
• Maps• Proposed Projects• Neighborhoods
Academic Student Services
• Buildings (Interior/Exterior) Color Textures Space Prototypes
• Landscaping
Our “new” look!179,000
TrinityCampus
Shasta CollegeMain Campus
61 miles
Proposed Exterior
Front
Back
Student Services One‐Stop‐Shop Building
(100 Building)
179,000
TrinityCampus
Shasta CollegeMain Campus
61 miles51 miles
Veterans Support & Success Center
Regional Public Safety Training Center
Project Start: 8/2018
Est. Completion:2/2019
Project Start: 6/2018
Est. Completion:1/2019
SHIELD Consortium RPSTC Tour
Regional Public Safety Training Center
179,000
TrinityCampus
Shasta CollegeMain Campus
61 miles51 miles
Regional Public Safety Training Center
Fire Tower Prop
Rappelling Tower Prop
Athletic Fieldhouse with Restrooms
Project Start: 8/2018
Est. Completion:2/2019
Gymnasium Air Conditioning
Project Start: 10/2018
Est. Completion:1/2019
179,000
TrinityCampus
61 miles51 miles
Solar Project – East Parking Lot
• 1.6 Megawatts• 8 Bays• Electric Auto Charging Stations (for 10 parking spaces)
Project Start: 10/2018
Est. Completion:6/2019
Solar Project – East Parking Lot
Solar Project – East Parking Lot
2400 Bldg. – Electrical Upgrade Project
New Distribution Transformer
Electrical Line Rerouting New Electrical Panel
HSUC Folding Wall Project
WHITEBOARD PAINT FABRICANY COMBINATION
Projects Update
179,000
TrinityCampus
Shasta CollegeMain Campus
61 miles51 miles
Approval Received
Construction Commenced/To Commence:• Regional Public Safety Training Center – Phase One (recommenced 9/10/18)
Gifford Construction, Inc. (Infrastructure) and Trent Construction (Props)
• Athletic Fieldhouse with Restrooms Cerami & Browning Construction, Inc. (commenced 8/27/18)
• Gymnasium Air Conditioning Cerami & Browning Construction, Inc. (commenced 10/8/18)
• Solar Project – East Lot Sunpower (commenced 10/8/18)
In Bid Process:• Campus Safety Relocation – Interior remodel (Bid opening: 11/13/18)
• Veterans Center Building (Holding on bid to combine with CTE Building)
Projects Update (continued)
179,000
TrinityCampus
Shasta CollegeMain Campus
61 miles51 miles
Under DSA Review• CTE Building and Covered Storage• Regional Public Safety Training Center Classroom Buildings
DSA Submission Pending• Tehama Campus Student Services Building (to DSA late November)
Design Phase• CIS Building
Non-DSA Projects179,000
TrinityCampus
Shasta CollegeMain Campus
61 miles51 miles
Current/Upcoming Projects
• HSUC Folding Wall Replacement Bid documents being prepared
• SC Main Campus Keying & Access Control Ongoing construction document preparation
• SC Safety & Security Standards In Progress
• Campus Wide Infrastructure Projects (water, sewer, storm drain, electrical, fire alarm, technology fiber, gas lines) CCTV scoping: Sewer pipes can be sleeved Storm drains have no structural issues (require cleaning)
18
For more information…About SC / Bond Information / 2016 Bond Measure H
[email protected] / 242‐7699
Theresa Markword, Bond Program Manager