Measure A Modernization Program 1 65 schools Infrastructure Upgrades Health and Safety Technology Upgrades $253 million State Funding $250 million local bond – June 2012 21 schools completed

Measure A Modernization Program

  • Upload
    tale

  • View
    46

  • Download
    1

Embed Size (px)

DESCRIPTION

Measure A Modernization Program. 65 schools Infrastructure Upgrades Health and Safety Technology Upgrades $253 million State Funding $250 million local bond – June 2012 21 schools completed. Measure A Projects in Progress. Group IV – 27 Elementary Schools - PowerPoint PPT Presentation

Citation preview

Page 1: Measure A Modernization Program

1

Measure AModernization Program

65 schools Infrastructure Upgrades

Health and Safety

Technology Upgrades

$253 million State Funding

$250 million local bond – June 2012

21 schools completed

Page 2: Measure A Modernization Program

2

Group IV – 27 Elementary Schools 6 Schools started December 2013 13 Schools start Spring/Summer 2014 6 Schools start Spring/Summer 2015 2 Schools start Summer 2016

Interim Housing Group IV – Elementary Schools Setting Portables now for Summer 2014 Group V – Intermediate and High Schools Setting 122 Portables in July for Fall 2014

Measure AProjects in Progress

Page 3: Measure A Modernization Program

3

Measure AModernization Update

Page 4: Measure A Modernization Program

4

Measure AModernization Update

Page 5: Measure A Modernization Program

5

Measure AModernization Update

Student Restroom

Page 6: Measure A Modernization Program

6

Measure AModernization Update

Page 7: Measure A Modernization Program

7

Group V 9 Intermediate Schools7 High SchoolsCombined into 7 contracts

Measure AProjects for Award by June 30

Page 8: Measure A Modernization Program

8

Measure A Schedule

Page 9: Measure A Modernization Program

9

Measure A Schedule

Page 10: Measure A Modernization Program

10

Future Projects

Air Conditioning Seismic Repairs Lighting Upgrades Window Replacement Seismic Replacement - La Quinta High Seismic Replacement - Pacifica High

105,000 square feet each SAB Conceptual Approval Submit to DSA June 2014 (fast tracked)

Page 11: Measure A Modernization Program

GARDEN GROVE UNIFIED SCHOOL DISTRICTLA QUINTA HIGH SCHOOL – WESTMINSTER, CA - AB-300 BUILDING REPLACEMENT

Page 12: Measure A Modernization Program

BLDG“L”

(DEMO) BLDG“C”

(DEMO)

GARDEN GROVE USD – LA QUINTA HIGH SCHOOLEXISTING BUILDINGS TO BE REPLACED

Page 13: Measure A Modernization Program

STAFF PARKING

STAFF PARKING

NEW STUDENT DROP-OFF / VISITOR PARKING

NEWSTUDENTDROP-OFFSTUDENT PARKING

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CAFETERIA

MEDIACENTER

AUDITORIUM

GARDEN GROVE USD – LA QUINTA HIGH SCHOOLPROPOSED NEW SITE PLAN

Page 14: Measure A Modernization Program

GARDEN GROVE USD – LA QUINTA AND PACIFICA HIGH SCHOOLSCLASSROOM BUILDING TYPICAL SECTION AND ELEVATIONS

Page 15: Measure A Modernization Program

GARDEN GROVE USD – LA QUINTA AND PACIFICA HIGH SCHOOLSMEDIA CENTER BUILDING SECTION AND ELEVATIONS

Page 16: Measure A Modernization Program

GARDEN GROVE USD – LA QUINTA AND PACIFICA HIGH SCHOOLSCAFETERIA BUILDING SECTIONS AND ELEVATIONS

Page 17: Measure A Modernization Program

GARDEN GROVE USD – LA QUINTA AND PACIFICA HIGH SCHOOLSAUDITORIUM BUILDING SECTION AND ELEVATIONS

Page 18: Measure A Modernization Program

GARDEN GROVE USD – LA QUINTA AND PACIFICA HIGH SCHOOLSAUDITORIUM BUILDING PERSPECTIVE