1: Activity C has a Day 26 LFT and a Day 18 EFT. Select the total float for Activity C. A. 26 daysB. 18 days
C. 44 days
D. 8 days
Answer: D
2: What is float? A. The latest time an activity can be started without affecting the next activity’s earliest
startB. The length of time an activity can be deferred without affecting the project duration
C. The length of time an activity can be deferred without affecting the next activity’s earliest start
D. The latest time an activity can be started without affecting the project duration
Answer: B
3: Select the correct equation for calculating total float for an activity. A. Total Float = LFT - ESTB. Total Float = EFT - EST
C. Total Float = LFT - EFT
D. Total Float = LST – EFT
Answer: C
4: The length of time an activity can be deferred without affecting the earliest start time of any immediate successor activity is called ______________.
A. non-floatB. free float
C. zero float
D. intermediate float
Answer: B
5: What is the term for an activity that cannot be deferred without affecting the project completion date or another activity’s start date?
A. Standard floatB. Intermediate float
C. Free float
D. Zero float
Answer: D
6: PERT stands for :
A. Programme evaluation and review techniqueB. Project estimation and review technique
C. Programme estimation and renew technology
D. None of these
Answer: A
7: Activities which have zero float are called:
A. Critical ActivitiesB. Dummy activities
C. Non-critical activities
D. None of these
Answer: A
8: Select the two time estimates that are used to determine project duration by using PERT.
A. Optimistic and least likelyB. Optimistic and most likely
C. Ideal and pessimistic
D. Most likely and least likely
Answer: B
9: Consider an EST of five days and duration of four days. Now, calculate the EFT of the activity.
A. 1 dayB. 9 days
C. 10 days
D. 20 days
Answer: B
10: What is crashing?
A. Using more time to complete activities not on the critical pathB. Using more resources to complete activities on the critical path
C. Using fewer activities to shorten the overall project duration
D. Using fewer resources to complete activities on the critical path
Answer: B