54
McGraw-Hill/Irwin © 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

Embed Size (px)

Citation preview

Page 1: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

McGraw-Hill/Irwin © 2008 The McGraw-Hill Companies, All Rights Reserved

Developing a Project Plan

Chapter 6

Page 2: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-2

Page 3: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-3

Developing the Project Plan The Project Network

A flow chart that graphically depicts the sequence, interdependencies, and start and finish times of the project job plan of activities that is the critical path through the network

Page 4: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-4

From Work Package to Network

FIGURE 6.1

WBS/Work Packages to Network

Page 5: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-5

From Work Package to Network (cont’d)

FIGURE 6.1 (cont’d)

WBS/Work Packages to Network (cont’d)

Page 6: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-6

Constructing a Project Network Terminology

Activity: an element of theproject that requires time.

Merge activity: an activity that has two or more preceding activities on which it depends.

Parallel (concurrent) activities: Activities that can occur independently and, if desired, not at the same time.

A

C

B D

Page 7: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-7

Constructing a Project Network (cont’d)

Terminology

Path: a sequence of connected, dependent activities.

Critical path: the longest path through the activity network that allows for the completion of all project-related activities; the shortest expected time in which the entire project can be completed. Delays on the critical path will delay completion of the entire project.

D

C

A B

(Assumes that minimum of A + B > minimum of C in length of times to complete activities.)

Page 8: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-8

Terminology Event: a point in time when an activity is started

or completed. It does not consume time. Burst activity: an activity that has more than one

activity immediately following it (more than one dependency arrow flowing from it).

Two Approaches Activity-on-Node (AON)

o Uses a node to depict an activity Activity-on-Arrow (AOA)

o Uses an arrow to depict an activity

B

D

A C

Constructing a Project Network (cont’d)

Page 9: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-9

Basic Rules to Follow in Developing Project Networks

Networks typically flow from left to right. An activity cannot begin until all of its activities are

complete. Arrows indicate precedence and flow and can cross

over each other. Identify each activity with a unique number; this

number must be greater than its predecessors. Looping is not allowed. Conditional statements are not allowed. Use common start and stop nodes.

Page 10: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-10

Activity-on-Node Fundamentals

FIGURE 6.2

Page 11: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-11

Activity-on-Node Fundamentals (cont’d)

FIGURE 6.2 (cont’d)

Page 12: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-12

Network Information

TABLE 6.1

Page 13: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-13

Koll Business Center—Partial Network

FIGURE 6.3

Page 14: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-14

Koll Business Center—Complete Network

FIGURE 6.4

Page 15: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-15

Network Computation Process Forward Pass—Earliest Times

How soon can the activity start? (early start—ES) How soon can the activity finish? (early finish—EF) How soon can the project finish? (expected time—

ET) Backward Pass—Latest Times

How late can the activity start? (late start—LS) How late can the activity finish? (late finish—LF) Which activities represent the critical path? How long can it be delayed? (slack or float—SL)

Page 16: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-16

Network Information

TABLE 6.2

Page 17: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-17

Activity-on-Node Network

FIGURE 6.5

Page 18: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-18

Activity-on-Node Network Forward Pass

FIGURE 6.6

Page 19: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-19

Forward Pass Computation

Add activity times along each path in the network (ES + Duration = EF).

Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless…

The next succeeding activity is a merge activity, in which case the largest EF of all preceding activities is selected.

Page 20: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-20

Activity-on-Node Network Backward Pass

FIGURE 6.7

Page 21: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-21

Backward Pass Computation Subtract activity times along each path in

the network (LF - Duration = LS).

Carry the late start (LS) to the next activity where it becomes its late finish (LF) unless...

The next succeeding activity is a burst activity, in which case the smallest LF of all preceding activities is selected.

Page 22: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-22

Determining Slack (or Float) Free Slack (or Float)

The amount of time an activity can be delayed without delaying connected successor activities

Total SlackThe amount of time an activity can be delayed

without delaying the entire project The critical path is the network path(s) that

has (have) the least slack in common.

Page 23: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-23

Sensitivity of a Network The likelihood the original critical path(s)

will change once the project is initiated.Function of:

oThe number of critical pathsoThe amount of slack across near critical

activities

Page 24: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-24

Activity-on-Node Network with Slack

FIGURE 6.8

Page 25: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-25

Practical Considerations Network logic errors Activity numbering Use of computers to develop networks Calendar dates Multiple starts and multiple projects

Page 26: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-26

Illogical Loop

FIGURE 6.9

Page 27: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-27

Air Control Project

FIGURE 6.10

Page 28: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-28

Air Control Project (cont’d)

FIGURE 6.11

Page 29: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-29

Extended Network Techniques to Come Close to Reality

Laddering Activities are broken into segments so the following

activity can begin sooner and not delay the work.

Lags The minimum amount of time a dependent activity

must be delayed to begin or endo Lengthy activities are broken down to reduce the delay

in the start of successor activities.

o Lags can be used to constrain finish-to-start, start-to-start, finish-to-finish, start-to-finish, or combination relationships.

Page 30: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-30

Example of Laddering Using Finish-to-Start Relationship

FIGURE 6.12

Page 31: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-31

Use of Lags

FIGURE 6.13

FIGURE 6.14

Finish-to-Start Relationship

Start-to-Start Relationship

Page 32: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-32

Use of Lags (cont’d)

FIGURE 6.15

Use of Lags to Reduce Detail

Page 33: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-33

New Product Development

Process

FIGURE 6.16

Page 34: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-34

Use of Lags (cont’d)

FIGURE 6.17

FIGURE 6.18

Finish-to-Finish Relationship

Start-to-Finish Relationship

Page 35: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-35

Network Using Lags

FIGURE 6.20

Page 36: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-36

Hammock Activities Hammock Activity

An activity that spans over a segment of a project

Duration of hammock activities is determined after the network plan is drawn.

Hammock activities are used to aggregate sections of the project to facilitate getting the right amount of detail for specific sections of a project.

Page 37: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-37

Hammock Activity Example

FIGURE 6.21

Page 38: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-38

Key Terms

Activity

Activity-on-arrow (AOA)

Activity-on-node (AON)

Burst activity

Concurrent engineering

Critical path

Early and late times

Gantt chart

Hammock activity

Lag relationship

Merge activity

Network sensitivity

Parallel activity

Slack/float—total and free

Page 39: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-39

Activity-on-Arrow NetworkBuilding Blocks

FIGURE A6.1

Page 40: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-40

Activity-on-Arrow Network Fundamentals

FIGURE A6.2

Page 41: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-41

Activity-on-Arrow Network Fundamentals

FIGURE A6.2 (cont’d)

Page 42: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-42

Koll Center Project: Network Information

TABLE A6.1

Page 43: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-43

Partial Koll Business CenterAOA Network

FIGURE A6.3

Page 44: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-44

Partial AOA Koll Network

FIGURE A6.4

Page 45: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-45

Partial AOA Koll Network (cont’d)

FIGURE A6.4 (cont’d)

Page 46: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-46

Activity-on-Arrow Network

FIGURE A6.5

Page 47: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-47

Activity-on-Arrow NetworkForward Pass

FIGURE A6.6

Page 48: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-48

Activity-on-Arrow Network Backward Pass

FIGURE A6.7

Page 49: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-49

Activity-on-Arrow Network Backward Pass, Forward Pass, and Slack

FIGURE A6.8

Page 50: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-50

Air Control Inc. Custom Order Project—AOA Network Diagram

FIGURE A6.9

Page 51: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-51

Comparison of AON and AOA Methods

TABLE A6.2

Page 52: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-52

Theory relating to Programme Evaluation and Review Technique (PERT) networks..

Given the optimistic (a), most probable(m) and pessimistic(b) times of completing the job, the most expected time for completing the job is given by

mhu = ( a + 4m + b ) / 6 . ( the network drawing is similar to CPM methods)

The variance (standard deviation squared) of the job time equals (sigma)**2 = (( b – a ) / 6) ** 2

Given that the activity times are beta distributed, by the Central Limit theorem, the project completion time is normal distributed

Adding the expected completion times of jobs on the critical path gives the expected time for completing the project.

The variance of the project duration is the sum of all the variances of the jobs in thecritical path. Sqrt(variance) = standard deviation

There is a 68% probability that the project will be completed within one standard deviation of the mean and a 99.7% probability that the project will be completed within 3 standard deviations of the mean.

Page 53: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-53

PROBLEM : A road construction project consists of the following nine jobs with the following precedence relations and time estimates in days. Assuming that all the jobs are independent and identically distributed, draw an AON network and find

a. expected duration and variance of each job.b. expected duration and variance of the project duration.c. Probability of completing the project by the expected duration date.d. Probability of completing the project not 5 days later than expectede. Probability of completing the project 4 days earlier than expected.

Job Predecessors Optimistic Most prob. Pessimistic time(a) time(m) time(b)

A - 2 5 8B A 6 9 12C A 6 7 8D B,C 1 4 7E A 8 8 8F D,E 5 14 17G C 3 12 21H F,G 3 6 9I H 5 8 11

Page 54: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6

6-54

Some agencies of the US government use other methods for project planning, execution and control.

Phase I - advanced schedule planning – basic project schedule is derived directly from the Work breakdown Structure, lists all elements of the project and forms the basic proposal which is to be put to Congress and other funding agencies

Phase II – Preparation of the operational schedule – equivalent to the project master schedule

Phase III – Schedule Administration – project is monitored and master schedule is updated through the use of bi-weekly reports. Corrections and alterations to the project master schedule are made as a result of this process.