MC Beamline

Tom lackowski

L1 Manager

Page 2: MC Beamline Tom lackowski L1 Manager. Project Organization Jan. 2013T. Lackowski - MC Beamline2

T. Lackowski - MC Beamline 2

Project Organization

Jan. 2013

Page 3: MC Beamline Tom lackowski L1 Manager. Project Organization Jan. 2013T. Lackowski - MC Beamline2

T. Lackowski - MC Beamline 3

Site Plan

Jan. 2013

Page 4: MC Beamline Tom lackowski L1 Manager. Project Organization Jan. 2013T. Lackowski - MC Beamline2

T. Lackowski - MC Beamline 4

Scope • Main Injector type enclosure

10 feet wide x 8 feet high (typical except near MC-1 where higher ceiling will be required.

Painted walls and ceiling, sealed floor. Floor to have 3” cover over rebar to enable stand anchorage.

Channel inserts walls and ceiling @ 8’ o/c. (no inserts 5’ from floor on aisle side)

• Shielding 13 feet of earth/concrete for M-4 beamline. (w/ beamline 4’ from clg.) 6 to 9 feet for g-2 beamline. Shielding needed within enclosure

between MC-1 building and M-4 / Delivery Ring.

• Access is provided from Ring enclosure- lift provided for magnet installation. Shielding hatch provided for magnet installation / replacement.

Jan. 2013

Page 5: MC Beamline Tom lackowski L1 Manager. Project Organization Jan. 2013T. Lackowski - MC Beamline2

T. Lackowski - MC Beamline 5

Typical Cross Section

Jan. 2013

Page 6: MC Beamline Tom lackowski L1 Manager. Project Organization Jan. 2013T. Lackowski - MC Beamline2

T. Lackowski - MC Beamline 6

Scope

• HVAC & Process Water A concept exits that integrates

the requirements for beamline

and Mu2e. G-2 is isolated from

beamline. LCW provided by g-2 and Mu2e

• Electrical 500 MCM ground along beamlines. Quad 120V & duplex 208V utility outlets at 60’ 480V welding outlets at 400’ Three 18” cable trays provided (one tray will contain line type heat

detection)

Jan. 2013

Page 7: MC Beamline Tom lackowski L1 Manager. Project Organization Jan. 2013T. Lackowski - MC Beamline2

T. Lackowski - MC Beamline 7

Cost by Division

Jan. 2013

Page 8: MC Beamline Tom lackowski L1 Manager. Project Organization Jan. 2013T. Lackowski - MC Beamline2

T. Lackowski - MC Beamline 8

Preliminary Costs

Jan. 2013

$9,200,000 Planned

$9,200,000 Planned

Page 9: MC Beamline Tom lackowski L1 Manager. Project Organization Jan. 2013T. Lackowski - MC Beamline2

T. Lackowski - MC Beamline 9

Cost Curve

Jan. 2013