MBR Design & Construction Presented by: Deb Hart, P.E.

MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

  • Upload
    others

  • View
    3

  • Download
    2

Embed Size (px)

Citation preview

Page 1: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

MBR Design & Construction

Presented by: Deb Hart, P.E.

Page 2: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

Details… Details… Details…

Design ConstructionDesign Construction

Page 3: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

Details… Details… Details…

• CONTRACTUAL ARRANGEMENTS –MANAGING CHANGE

• DESIGN ISSUES – WORKING TOGETHER•

• CONSTRUCTION – MEETING DESIGN REQUIREMENTS

Page 4: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

CONTRACTUAL ARRANGEMENTS –MANAGING CHANGE

• MBR is a proven technology and widely expanding• New generations of manufacturer provided

equipment advance quicklyTake advantage of value-added equipment without • Take advantage of value-added equipment without adding significant additional costs or time

Page 5: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

CONTRACTUAL ARRANGEMENTS – MANAGING CHANGE

Project Timeline – Past Approach

Preliminary DesignDesign-Construction

DocumentsConstruction

Additional Cost & Time

MBR Equipment New MBR Equipment

Redesign

Page 6: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

CONTRACTUAL ARRANGEMENTS – MANAGING CHANGE

Project Timeline – Current Approach

Preliminary DesignDesign-Construction

DocumentsConstructionConceptual Design

Minimized Additional

Cost & Time

Redesign

MBR Procurement Contract with Owner

Work with Selected MBR MFRTeam Reviews/AcceptsNew MBR Equipment

Page 7: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

CONTRACTUAL ARRANGEMENTS –MANAGING CHANGE

Advantages of Early Equipment Procurement:• Aligns MBR equipment and plant footprint

requirementsrequirements• Establishes hydraulic grade line and

requirements for treatment train pumping• Establishes baseline for evaluating potential

MBR changes

Page 8: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

DESIGN ISSUES – WORKING TOGETHER

• Refine P&IDs, written control strategies and software programming protocols

• Refine and improve hydraulic profile and pumping systems requirementspumping systems requirements

• Confirm ancillary equipment design criteria e.g. WAS pumps, permeate pumps, process blowers

• Review seismic anchorage requirements

Page 9: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

DESIGN ISSUES – WORKING TOGETHER

• Make components, valves and fittings accessible within a dry area

Page 10: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

DESIGN ISSUES – WORKING TOGETHER

Corrosion Issues• Piping and valve materials• Dissimilar Metals• Dissimilar Metals• Valve locations

Page 11: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

DESIGN ISSUES – WORKING TOGETHER

MBR Cover vs. No Cover• Determine if a cover is required early in design

–Cold climate?–Cold climate?

–Debris / leaves?

– Structural implications

–Maintenance implications

Page 12: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

DESIGN ISSUES – WORKING TOGETHER

Equipment Delivery• Specify staged deliveries in 3 steps:– Delivery of membrane components within

membrane tankagemembrane tankage– Delivery of balance of membrane equipment– Delivery of membrane cassettes

Page 13: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

CONSTRUCTION – MEETING DESIGN REQUIREMENTS

Testing and Start-up Requirements: • Treatment plant typically does not start at full

design capacitydesign capacity• K/J developed STRESS TEST procedure that

simulates full design capacity

Page 14: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

CONSTRUCTION – MEETING DESIGN REQUIREMENTS

• During design, confirm testing requirements with Manufacturer

• During construction, review Testing and Start-• During construction, review Testing and Start-up Procedures with Contractor and Manufacturer before planned test dates

• Run hydraulic test with clean water

Page 15: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

CONSTRUCTION – MEETING DESIGN REQUIREMENTS

MBR Warranty Period/Special Guarantee• MBR equipment - 1 year warranty• Membrane Cassettes Special Guarantee• Membrane Cassettes Special Guarantee

Page 16: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

CONSTRUCTION – MEETING DESIGN REQUIREMENTS

Optimize Operations with Manufacturer Service Contract

• Most deficiencies occur within first year of operationoperation

• Set up one year service contract with option to extend

• Allows Owner’s O&M personnel to learn the system

Page 17: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

SUMMARY

• Manage time and cost changes during construction by procuring MBR equipment early

• Work together during design to address MBR and overall plant design and compatibility

• Meet design requirements during construction through start-up and testing procedures

Page 18: MBR Design & Construction - PNCWA PNCWA... · • MBR is a proven technology and widely expanding • New generations of manufacturer provided equipment advance quickly ... Project

SUMMARY

• Pay attention to the details. You don’t want to end up with the project from …