Mayo Renewable Power-Killala
Progress Report March 2016
MR
P-K
illal
a
MR
P-K
illal
aMRP - Killala March 2016
• Siteworks• Works including general ducting and
drainage continue to all areas.• Sprinkler mains installation is
substantially complete• Main access road Kerbing has
commenced
• Turbine Hall• Construction of the Turbine Plinth
has commenced, 1st pour has been completed, reinforcement for 2nd pour is being placed.
• 1st section of floor slab has been poured.
• Control Building• Steel Frame is complete.• 1st floor concrete slabs are in place.• 1st floor slab has been poured.
• Boiler House• Piling for foundations is complete• Reinforcement placement for both
North and South Boiler foundations has commenced
• Monthly Environmental monitoring is continuing by external monitoring specialist (NVM)
• Monthly monitoring report has been issued for
• July - February• February (21st March).
• There have been 234 people ‘inducted’ on site to date
• Currently there are approximately 100 people working on site.
General Summary
• We continue to record the details of all job seekers who call to the site offices.This information is maintained in site database and is shared with each sub-contractor as packages are let. This database currently contains the details of 249 people.
• Killala ‘Services Available’ signage being reviewed by Community Representatives
• Works to Turning Lanes on R314 – Crash Barriers well advanced
MRP Progress Report - March 2016 – Image 01
Turbine Plinth – Reinforcement
MRP Progress Report - March 2016 – Image 02
Turbine Hall – 1st Section Of Floor Preparation
MRP Progress Report - March 2016 – Image 03
Control Building – 1st Floor Screed Pour
MRP Progress Report - March 2016 – Image 04
Control Building – 1st Floor Screed Pour Complete
MRP Progress Report - March 2016 – Image 05
Switch-room – Substructure / Blockwork Commenced
MRP Progress Report - March 2016 – Image 06
Boiler – North Raft Reinforcement
MRP Progress Report - March 2016 – Image 07
Boiler – South Raft Reinforcement
MRP Progress Report - March 2016 – Image 08
Western Carpark – Rock Breaking and Preparation
MRP Progress Report - March 2016 – Image 09
MLO – Prefabricated off site
MRP Progress Report - March 2016 – Image 10
Aerial View of Site