12
Mayo Renewable Power-Killala Progress Report March 2016 MRP-Killala

Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

Mayo Renewable Power-Killala

Progress Report March 2016

MR

P-K

illal

a

Page 2: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MR

P-K

illal

aMRP - Killala March 2016

• Siteworks• Works including general ducting and

drainage continue to all areas.• Sprinkler mains installation is

substantially complete• Main access road Kerbing has

commenced

• Turbine Hall• Construction of the Turbine Plinth

has commenced, 1st pour has been completed, reinforcement for 2nd pour is being placed.

• 1st section of floor slab has been poured.

• Control Building• Steel Frame is complete.• 1st floor concrete slabs are in place.• 1st floor slab has been poured.

• Boiler House• Piling for foundations is complete• Reinforcement placement for both

North and South Boiler foundations has commenced

• Monthly Environmental monitoring is continuing by external monitoring specialist (NVM)

• Monthly monitoring report has been issued for

• July - February• February (21st March).

• There have been 234 people ‘inducted’ on site to date

• Currently there are approximately 100 people working on site.

General Summary

• We continue to record the details of all job seekers who call to the site offices.This information is maintained in site database and is shared with each sub-contractor as packages are let. This database currently contains the details of 249 people.

• Killala ‘Services Available’ signage being reviewed by Community Representatives

• Works to Turning Lanes on R314 – Crash Barriers well advanced

Page 3: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MRP Progress Report - March 2016 – Image 01

Turbine Plinth – Reinforcement

Page 4: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MRP Progress Report - March 2016 – Image 02

Turbine Hall – 1st Section Of Floor Preparation

Page 5: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MRP Progress Report - March 2016 – Image 03

Control Building – 1st Floor Screed Pour

Page 6: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MRP Progress Report - March 2016 – Image 04

Control Building – 1st Floor Screed Pour Complete

Page 7: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MRP Progress Report - March 2016 – Image 05

Switch-room – Substructure / Blockwork Commenced

Page 8: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MRP Progress Report - March 2016 – Image 06

Boiler – North Raft Reinforcement

Page 9: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MRP Progress Report - March 2016 – Image 07

Boiler – South Raft Reinforcement

Page 10: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MRP Progress Report - March 2016 – Image 08

Western Carpark – Rock Breaking and Preparation

Page 11: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MRP Progress Report - March 2016 – Image 09

MLO – Prefabricated off site

Page 12: Mayo Renewable Power-Killala · Mayo Renewable Power-Killala Progress Report March 2016 MRP-a. MRP-a MRP - Killala March 2016 ... MRP Progress Report - March 2016 –Image 08

MRP Progress Report - March 2016 – Image 10

Aerial View of Site