DEERFIELD ELEMENTARY SCHOOL MODERNIZATION May 6, 2010 Irvine Unified School District HMC Architects

May 6, 2010 Irvine Unified School District HMC Architects

Embed Size (px)

Citation preview

DEERFIELD ELEMENTARY

SCHOOLMODERNIZATION

May 6, 2010

Irvine Unified School District

HMC Architects

What is a Modernization?

Eligibility Permanent buildings - 25 years oldPortable buildings - 20 years old

DSA RequirementsADA ComplianceFire, Life, Safety Upgrades

Maintenance Requirements

Budget and Funding

Board Approved Project BudgetConstruction CostsSoft Costs

○ Architect Fees○ Agency Fees (DSA, Health Dept., IRWD, etc.)○ Testing and Inspection Fees

$12,600,000 ($12.6m)○ Anticipated State Funding: $3,992,966○ Local Matching Funds: $8,607,034

Planned Scope of Work: DSA Requirements Required Fire Life Safety/ADA Compliance/Structural

components:Upgrade restrooms to ADA complianceAdd restroom fixtures based on student and staff capacityUpgrade drinking fountains for ADA complianceUpgrade fire alarm systemUpgrade ADA accessible parking stallsUpgrade path of travel (exterior)Upgrade/create updated exitingLoss of mezzanine/pit areas and current teachers loungeRelocation/replacement of shade structureRelocation/replacement of current classroom relocatables

Planned Scope of Work:Maintenance Needs Scope includes:

Roof replacementFlooring replacementNew PA/Clock systemElectrical upgradePaint all interior/exterior surfacesHVAC control replacement

Pre-Modernization Site Plan

Pre-Modernization Floor Plan

Post-Modernization Floor Plan

New Administration Floor Plan

New Classroom Layout

Interim Housing: El Camino Board Approved Transportation Zone Interior

Wall restoration Carpet repair/patch Paint Plumbing

Exterior Asphalt, concrete Playground

Childcare Restroom Facility Street Signs

Install approximately one-two weeks prior to start of school

Interim Housing: El Camino Real

Deerfield to El Camino

Childcare

CDCClosed Friday, June 25th*

Reopens at El Camino Monday, June 28th*See CDC for more information regarding

childcare and availability

Timeline

Moving OutTeachers - Friday, June 25thAdministration staff - Wednesday, June 30th

Moving InBy September 1, 2011*

ConstructionPhase I

○ July 12, 2010 - December 31,2010Phase II

○ January 3, 2011- August 19, 2011