Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
SIERRA POINTE SPECIFIC PLAN
OAKDALE, CALIFORNIA
PUBLIC FACILITIES FINANCING PLAN
AND
FISCAL IMPACT ANALYSIS
Final Draft
MAY 28, 2013
Sierra Pointe Specific Plan
Oakdale, California
Public Facilities Financing Plan and Fiscal Impact Analysis
Table of Contents
1. INTRODUCTION ................................................................................................ 1 Objective ........................................................................................................................1
Project Description.........................................................................................................2
Project Scenarios ............................................................................................................4
2. PUBLIC FACILITIES FINANCING PLAN ............................................................ 6 Facility Needs and Cost Estimates .................................................................................6
Financing Mechanisms ..................................................................................................7
Project Feasibility ........................................................................................................11
3. FISCAL IMPACT ANALYSIS ............................................................................ 13 Methodology ................................................................................................................13
Major Assumptions ......................................................................................................15
Fiscal Revenues ...........................................................................................................16
Fiscal Expenses ............................................................................................................20
Net Fiscal Impacts........................................................................................................20
4. CONCLUSIONS ................................................................................................ 22 Public Facilities Financing ...........................................................................................22
Fiscal Impacts ..............................................................................................................24
REPORT TABLES & FIGURES
REPORT TABLES
Table 2-1: Infrastructure Cost Estimates by Development Scenario ....................................... 6
Table 2-2: Infrastructure Cost Estimates by Funding Category .............................................. 7
Table 3-1: Summary of Net Fiscal Impacts .............................................................................. 21
REPORT MAPS Local Vicinity Map ........................................................................................................................ 2
Development Phasing Map ............................................................................................................ 4
APPENDICES
APPENDIX 1 – DETAILED FACILITIES COST ESTIMATES (FROM G&K) ............. A-1
APPENDIX 2 – FISCAL IMPACT ANALYSIS TABLES Table 1: Summary Results of Fiscal Impact Analysis ................................................................... A-12 Table 2: City Population and Employment, 2004-2011 ................................................................. A-13 Table 3: Market Assumptions by Land Use ................................................................................... A-14 Table 4: New Service Population and Real Estate Development Detail ...................................... A-15 Table 5: City of Oakdale Gross Expenditures FY 2004-2011 ....................................................... A-16 Table 6: City of Oakdale Expenditures per Person Served FY 2004-2011 ................................. A-17 Table 7: Fiscal Impacts of New Development ................................................................................ A-18 Table A1: City of Oakdale Gross Revenues FY 2004-2011........................................................... A-19 Table A2: City of Oakdale Gross Revenues per Capita FY 2004-2011 ....................................... A-20 Table A3: Property Tax Allocation, Estimated .............................................................................. A-22 Table A4: CFD No. 2007-1 (Public Safety Services) Revenue ...................................................... A-23 Table A5: Sales and Use Tax Assumptions .................................................................................... A-24 Table A6: Sales Tax Analysis ........................................................................................................... A-25 Table A7: Property Transfer Tax Revenue .................................................................................... A-26 Table A8: Property Tax In-Lieu of Vehicle License Fee Revenues .............................................. A-27
APPENDIX 3 – INFRASTRUCTURE COST ESTIMATES FOR EXISTING DEV’T ...... A-28
SPSP Financing Plan and Fiscal Impact Analysis 1 May 28, 2013
Chapter 1
INTRODUCTION
OBJECTIVE
This report analyzes the public facilities burden that must be carried by the land uses proposed in
the Sierra Pointe Specific Plan (Specific Plan, SPSP, or Project) and the potential recurring fiscal
impacts to the City of Oakdale (City) from the development proposal. The SPSP is a public
policy document that sets guidelines for the long-term use of land within the Project area.
Similarly, the Public Facilities Financing Plan (PFFP or Finance Plan) and Fiscal Impact
Analysis (FIA) provide a long-term look at the burdens associated with providing infrastructure
to the SPSP area and the annual fiscal impacts that will be generated by the Project once it is
built out.
The Finance Plan identifies infrastructure required to serve the Project, its corresponding costs,
and implementation measures to ensure those costs are funded. It represents the culmination of a
cooperative process that involved public and private participants with interests in the SPSP. The
Finance Plan will serve as a blueprint to guide individual development applications and ensure
that future development conforms to the strategy outlined in this Finance Plan. The Finance Plan
also includes a brief summary of overall feasibility. As development progresses, the timing and
mix of costs and funding sources may change. Furthermore, the costs and infrastructure
obligations are estimates at this time, and demonstrate one approach to fund required
infrastructure needs; actual results may be different. However, regardless of the extent to which
proposed financing mechanisms are used or other financing mechanisms are introduced later in
the Project, the feasibility of the overall burden has been evaluated. The PFFP is a planning
document that includes a proposed financing strategy for the Project; it does not commit the City
or landowners to a specific financing obligation. Furthermore, the PFFP does not establish any
impact fees. Adoption of any development impact fee program to fund SPSP infrastructure
needs can only occur after a comprehensive update of the City’s Capital Facilities Fee (CFF)
Program has been completed.
The Fiscal Impact Analysis establishes the fiscal feasibility for the City by analyzing the
potential recurring fiscal impacts to the City produced by new development. The analysis
compares the annual costs of providing public services to the annual revenues that will be
generated by new development to determine the net fiscal impact. Districts and funds supported
by development fees and user charges (e.g., enterprise funds), state funding (e.g., school
districts), or a specific allocation of property taxes (e.g., school districts, irrigation districts,
mosquito abatement districts) are not included in the analysis. This report focuses solely on the
fiscal impacts to the City’s General Fund, Development Services Fund, and Engineering &
Public Works Fund.
In summary, this report does the following:
Describes the proposed land uses as well as developed value and demographic
assumptions
SPSP Financing Plan and Fiscal Impact Analysis 2 May 28, 2013
Summarizes public facilities required to serve future development in the SPSP area
Presents the costs of required public facilities and assigns the costs to one of three
funding categories (i.e., CFF Program, SPSP Fee Program, and Developer funded in-tract
costs)
Summarizes the financial feasibility of the Project
Projects the annual fiscal revenues to the City’s General Fund, Development Services
Fund, and Engineering & Public Works Fund generated from the Project
Projects the annual fiscal expenses incurred by the City’s General Fund, Development
Services Fund, and Engineering & Public Works Fund to provide services to the Project
PROJECT DESCRIPTION
The City lies in the northeastern portion of Stanislaus County, approximately 11 miles northeast
of Modesto in California’s agricultural Central Valley. Regionally, Sacramento is located
approximately 60 miles to the north and San Francisco is approximately 125 miles to the west.
The Project consists of approximately 297 acres along the eastern edge of the City. The SPSP
includes approximately 284 acres of new development, which are incorporated into the PFFP and
FIA. The remaining 13 acres comprise 45 existing homes and are not included in this study.
The SPSP area is located approximately 1.5 miles east of Downtown Oakdale along Highway
120/East F Street and consists of multiple parcels generally bounded by Highway 120/East F
Street to the north, South Stearns Road to the east, Orsi Road to the west, and Sierra Avenue to
the south. A local vicinity map of the SPSP area is shown below.
SPSP Financing Plan and Fiscal Impact Analysis 3 May 28, 2013
Land Uses
At buildout, the Project is expected to include 856 new residential units and approximately 1.1
million square feet of non-residential development. The residential component of the Project
area encompasses approximately 152 gross acres and will include very low density residential
(VLDR), low density residential (LDR), medium density residential (MDR), and high density
residential (HDR) units. There are currently 45 existing VLDR units in the SPSP, but these
existing units are excluded from the analyses because the units are served by existing
infrastructure. Regarding non-residential land uses, the SPSP includes general commercial, flex
use/general commercial, and office land uses that are anticipated to develop on approximately 69
gross acres. An additional 18 gross acres is also planned for public/semi-public use that is
anticipated to be a new community college campus. It is assumed that the general commercial
land uses will be comprised of an evenly distributed mix of retail and other commercial uses
based on a cursory market analysis that was prepared as part of the City’s current General Plan
Update. For purposes of this analysis, the estimated gross acreage does not include the acreage
associated with major roads, parks, and open space. Unless otherwise indicated, the terms gross
acres and acres are used interchangeably throughout this report.
The SPSP is divided into three phases of development: i) Residential Neighborhood Phase; ii)
Mixed Use Corridor Phase; and iii) North County Corridor (NCC) Future Phase. The boundaries
of each phase of development are shown in the map below. The City’s General Plan refers to the
entire SPSP area as Planning Area 9. A breakdown of the proposed land uses within the Project
is presented in Table 4 of Appendix 2. Unless otherwise specifically stated, the remaining text in
this report refers to the development of the entire SPSP area. Where necessary, discussion of the
separate development areas is provided.
Estimated Market Values
Estimated market values for each residential and non-residential land use category reflect values
used in the City’s General Plan Update Fiscal Impact Analysis (General Plan FIA), dated
April 15, 2011. Average values of $350,000 per very low density residential unit, $300,000 per
low density residential unit, $240,000 per medium density residential unit, $150,000 per high
density residential unit, and $200 per building square foot of general commercial, flex
use/general commercial, and office uses are used in this analysis. These values are shown in
Table 3 of Appendix 2.
Demographic Assumptions
It is anticipated that development will result in approximately 2,266 new residents and 3,257
employees at Project buildout. Population and employment estimates are presented in Table 4 of
Appendix 2. Population per household and square feet per job assumptions are provided in
Table 3 of Appendix 2.
SPSP Financing Plan and Fiscal Impact Analysis 4 May 28, 2013
PROJECT SCENARIOS
At the time of approval of the SPSP, the North County Corridor (NCC) was in its planning
stages, and no final alignments had been selected. The NCC is proposed to be a parallel route to
Highway 108 and is envisioned to ultimately provide an east/west connection from Highway 99
to Highway 108/120 at the eastern edge of the City. Alignment 1A, one of the potential
alignments being considered, would run through the southeast and northeast corners of the SPSP,
with partial interchanges located immediately east of the SPSP area – one along Stearns Road
and one along Highway 120/East F Street.
SPSP Financing Plan and Fiscal Impact Analysis 5 May 28, 2013
To account for this possible alignment, two development scenarios are incorporated into the
PFFP and FIA. The first scenario evaluates the financial viability and potential recurring fiscal
impacts associated with new growth in the Residential Neighborhood Phase and Mixed Use
Corridor Phase only. The NCC Future Phase area, which encompasses 68 acres, is assumed to
be selected as the location for a portion of Alignment 1A; therefore, no development is
anticipated in this area. A summary of the proposed land uses excluding the NCC Future Phase
is presented in Table 3 of Appendix 2.
The second scenario analyzes feasibility and fiscal impacts associated with new growth in the
entire SPSP area, including the NCC Future Phase. This scenario implicitly assumes that
Alignment 1A is not selected. The tables in Appendix 1 and Appendix 2 are explained in detail
in this report. In many instances, information for both scenarios is presented on one table in
order to easily compare the results between development scenarios. In addition to the land use
assumptions of each development scenario being different, Giuliani & Kull, Inc., the Project
engineer, identified the infrastructure costs for each development scenario.
SPSP Financing Plan and Fiscal Impact Analysis 6 May 28, 2013
Chapter 2
PUBLIC FACILITIES FINANCING PLAN
FACILITY NEEDS AND COST ESTIMATES
The Sierra Pointe Specific Plan describes in detail the water, storm drainage, sewer, irrigation,
street, and park improvements proposed to meet the needs of the community. The Specific Plan
also includes a series of maps and exhibits for all Project-specific infrastructure needed to serve
future development within the Project area. Giuliani & Kull, Inc., provided preliminary cost
estimates for the SPSP area excluding the NCC Future Phase as well as separately for the NCC
Future Phase. These two sets of cost estimates are summed to determine the cost for the entire
SPSP area, including the NCC Future Phase. A mark-up of 35% is applied to all facility costs to
account for soft-costs such as design and engineering, construction management, facility
inspection, and cost contingencies. The total cost of backbone infrastructure required for the
entire SPSP area is estimated to be approximately $26.2 million including the NCC Future
Phase. The total cost is reduced to approximately $23.1 million if Alignment 1A is selected for
the NCC and, therefore, no development occurs within the NCC Future Phase.
Giuliani & Kull also organized each infrastructure item into one of three funding categories:
CFF; SPSP; or in-tract. These categories are described more fully below, but they essentially
relate to infrastructure that would be included in the City’s capital facilities fee program (CFF),
that would be part of a newly-created fee program unique to the specific plan area, or that would
be constructed as homebuilders and commercial/industrial developers install subdivision or
in-tract improvements.
Summaries of the required infrastructure costs, including a 35% mark-up for contingency and
soft costs, to serve each development scenario and by funding category are presented in
Table 2-1 and Table 2-2 below. Detailed cost estimates from Giuliani & Kull, Inc., are presented
in Appendix 1.
TABLE 2-1
INFRASTRUCTURE COST ESTIMATES BY DEVELOPMENT SCENARIO ($ IN MILLIONS)
Improvement
SPSP
Excluding
NCC Future
Phase
Entire
SPSP Area
(Including NCC
Future Phase)
Water $3.6 $3.7
Storm Drainage $2.3 $2.4
Sewer $1.9 $2.0
Irrigation $2.5 $2.5
Street 1 $10.6 $11.3
Park $2.2 $4.2
Total 2 $23.1 $26.2
1 Includes costs related to entries, rails, and open space as well as dry utilities.
2 Totals may not sum due to rounding.
SPSP Financing Plan and Fiscal Impact Analysis 7 May 28, 2013
TABLE 2-2
INFRASTRUCTURE COST ESTIMATES BY FINANCING MECHANISM ($ IN MILLIONS)
Improvement
CFF
Costs
SPSP
Costs
In-Tract
Costs
Total
Costs 2
Water $3.3 $0.0 $0.4 $3.7
Storm Drainage $2.4 $0.0 $0.0 $2.4
Sewer $1.1 $0.9 $0.0 $2.0
Irrigation $0.0 $2.5 $0.0 $2.5
Street 1 $8.1 $3.2 $0.0 $11.3
Park $4.2 $0.0 $0.0 $4.2
Total 2 $19.2 $6.6 $0.4 $26.2
1 Includes costs related to entries, rails, and open space as well as dry utilities.
2 Totals may not sum due to rounding.
In addition to the Project-specific infrastructure costs identified in the tables above, certain
infrastructure will be required to serve existing development within the Project area. While these
infrastructure costs are not included in the feasibility analysis, they have been identified by
Giuliani & Kull, Inc., and are presented in Appendix 3.
FINANCING MECHANISMS
Several different funding mechanisms will likely be used to pay for public facilities required to
serve new development within the Project area. Impact fees, land-secured bonds, and other
funding alternatives must be analyzed in detail prior to development. However, for purposes of
this Finance Plan, all required infrastructure is categorized into one of three funding categories
(i.e., CFF Program, SPSP Program, developer equity/private financing for in-tracts). The
primary features of each funding category and its potential application to the SPSP area are
discussed below.
Development Impact Fees
Assembly Bill 1600 (AB 1600), which was enacted by the State of California in 1987, created
Section 66000 et seq. of the Government Code. In order to establish, increase, or impose a fee as
a condition of approval of a development project, AB 1600 (also known as the Mitigation Fee
Act) requires a public agency to specifically identify the public facilities funded by the impact
fees, and determine how there is a reasonable relationship, or “nexus,” between the type of
development project and the need for the facilities, the cost of the facilities, and the need to
impose a fee.
Development impact fees are monetary exactions (other than taxes or special assessments) that
are charged by local agencies in conjunction with approval of a development project. The fees
are paid by builders or developers, typically at the time a building permit is issued. Impact fees
are levied for the purpose of defraying all or a portion of the costs of a public facility,
improvement, or amenity that benefits the Project. The collection of impact fees does not require
SPSP Financing Plan and Fiscal Impact Analysis 8 May 28, 2013
formation of a special district; an impact fee program is implemented by a public agency’s
adoption of a resolution or ordinance.
Further, the City impact fees will be an important component of this Finance Plan. Once the
SPSP area is annexed into the City, a fee ordinance may need to be adopted (or a development
agreement would need to be executed) by the City and the City’s existing capital facilities fee
program should be updated prior to development of the Project; fee programs may also be
updated and revised as part of future development phases. Because fees are collected as
development occurs and many of the facilities identified in this report are expected to be in place
prior to development, fee revenues collected in future years may be used to reimburse developers
that have paid to cover more than their fair share of Project costs prior to the availability of fee
revenues.
1. CFF Program
Development in the SPSP area is expected to participate in the City’s Capital Facilities
Fee (CFF) Program. The City of Oakdale CFF Program includes components to fund
various types of infrastructure, public facilities, and equipment that will serve future
development in the City and will provide a City-wide benefit. As shown in Table 2-2 and
Appendix 1, approximately $19.2 million of infrastructure costs required to serve the
Project is anticipated to be funded through the CFF Program. However, the City will
need to conduct a comprehensive update of the CFF Program to ensure that the Project’s
required infrastructure needs are incorporated. Potential overlaps between infrastructure
included in the CFF Program and that included in the proposed SPSP Fee Program should
be resolved as part of the CFF update. The CFF Program update will also need to address
how land costs associated with regional road right-of-way acquisition, water well and
tank facilities, storm drainage infrastructure, and various other public improvements will
be treated, as well as how the need for a second pipeline crossing will be handled.
Any SPSP infrastructure included in the CFF Program will be treated in the same manner
as existing CFF improvements. For example, if the CFF Program currently funds the cost
of wells elsewhere in the City, then wells needed to serve development in the SPSP
would also be funded by the CFF Program. In addition, a separate storm drainage zone
may be created in the CFF Program to fund storm drainage facilities within the SPSP to
be consistent with the treatment of other storm drainage systems within the existing CFF
Program. However, certain SPSP improvements may be needed prior to when sufficient
CFF revenue is available to fully fund the needed improvements. In the event that CFF
revenues are not sufficient, the Project developer will be required to construct the
required improvements and be reimbursed through the CFF Program as development
within the Project and around the City occurs.
2. Proposed SPSP Fee Program
Certain types of infrastructure provide a general benefit to the entire SPSP, but they do
not provide a general benefit to the entire City. Consequently, these types of Project-
specific infrastructure cannot be included in the CFF Program. One potential source of
funding for Project-specific improvements will be a Project-specific fee program. The
SPSP Financing Plan and Fiscal Impact Analysis 9 May 28, 2013
proposed SPSP Fee Program is anticipated to fund approximately $6.6 million in sewer,
irrigation, and street improvements, as shown in Table 2-2 and Appendix 1. The
proposed SPSP Fee Program will need to be adopted by the City prior to development to
ensure full participation from the entire SPSP area and that everyone within the Project
pays their fair share of required facilities costs.
New development in the SPSP will be subject to costs associated with preparation and
adoption of the Specific Plan and related documents, estimated at a total amount of
$750,000. This cost would be spread to all land uses within the SPSP. SPSP
development will also be subject to costs associated with agricultural land mitigation. It
is estimated that approximately 63 acres of farmland in the SPSP area will be converted
to residential land uses, and that total agricultural land mitigation costs will amount to
approximately $0.5 million. This cost would be allocated to all residential land uses
within the SPSP. Specific Plan preparation costs and agricultural land mitigation costs
are likely to be included in the SPSP Fee Program.
3. Other Fee Programs
Lastly, development in the SPSP area is expected to participate in development impact
fee programs administered by other public agencies, including the County Public
Facilities Fee (PFF) Program and Oakdale Joint Unified School District fee program.
The Finance Plan assumes the Project will pay the applicable fees imposed during the
construction and permitting process.
Developer Equity/Private Financing
In addition to improvements anticipated to be funded by the City’s CFF Program and proposed
SPSP Fee Program, this analysis includes improvements that are classified as in-tract
improvements. In-tract improvements are commonly referred to as subdivision or discretionary
permit infrastructure, and include local water and storm drainage improvements within a single
subdivision project. These improvements serve a given subdivision or development and are
commonly provided as a condition of development. In-tract improvements are typically incurred
and funded privately by developers, together with the costs related to vertical construction of
homes and commercial buildings. Developers build these costs into their private pro forma cash
flow analyses as individual lot costs, and do not receive fee credits or reimbursements for these
costs. Approximately $0.4 million in in-tract improvement costs is assumed to be installed by
developers and dedicated to the City.
Mello-Roos Community Facilities District
The Mello-Roos Community Facilities Act (Act) [Section 53311 et seq. of the Government
Code] was enacted by the California State Legislature in 1982 to provide an alternate means of
financing public infrastructure and services subsequent to the passage of Proposition 13 in 1978.
Complying with Proposition 13, and with Proposition 218 passed in 1996, the Act permits cities,
counties, and special districts to create defined areas within their jurisdiction and, by a two-thirds
vote within the defined area, impose special taxes to pay for the public improvements and
SPSP Financing Plan and Fiscal Impact Analysis 10 May 28, 2013
services needed to serve that area. The Act defines the area subject to a special tax as a
Community Facilities District (CFD).
A CFD may provide for the purchase, construction, expansion, or rehabilitation of any real or
other tangible property with an estimated useful life of at least five years. A CFD may also
finance the costs of planning, design, engineering, and consultants involved in the construction
of improvements or formation of the CFD. The facilities financed by the CFD do not have to be
physically located within the CFD. The facilities that can be financed by a CFD include, but are
not limited to, the following:
Roads, water and sewer lines, flood control channels
Local park, recreation parkway, and open-space facilities
School sites, structures, furnishings, and equipment
Libraries
Child care facilities
Dry utility improvements (limited to five percent of bond proceeds if improvements are
to be taken over by a non-publicly owned utility agency)
Any other governmental facilities which the legislative body creating the CFD is
authorized by law to contribute revenue to, construct, own, or operate
A CFD may also pay for public services, including the following:
Road maintenance
Police protection
Fire protection
Recreation program services
Library services
Park and open space maintenance
Flood and storm protection services
Removal or cleanup of hazardous substances
Sandstorm protection
Seismic retrofitting
School facilities maintenance
A CFD may only finance the services mentioned above to the extent that they are in addition to
those provided in the area before the CFD was created and may not supplant services already
available within that area.
There are two limitations on the amount of financing available from a CFD, the first being the
value-to-lien-ratio. “Value” is considered to be the appraised value of the property, including
entitlements and improvements in place on the date the CFD bonds are to be sold. The value of
SPSP Financing Plan and Fiscal Impact Analysis 11 May 28, 2013
improvements to be constructed with bond proceeds is included in the value calculation. “Lien”
refers to the proposed bond issue, as well as any other debt secured by the property. Senate Bill
1464, which became effective January 1993, requires a minimum value-to-lien ratio of 3:1.
The second restriction on the amount of financing available from a CFD is the total effective tax
rate (ETR) paid by a homeowner or property owner in the CFD. The ETR consists of the basic
one percent ad valorem property tax levy mandated by Proposition 13, plus overrides from
voter-approved bonded indebtedness and non-ad valorem taxes, assessments, and parcel charges
(expressed as a percentage of market value). Market value can be determined based on input
from local developers, a market consultant, local realtors, or an appraiser. There is no legal
limit, but a maximum ETR of 2.00% of market value has developed as a standard for residential
development in many areas throughout the State, although it tends to be closer to 1.80% in
northern California and even lower in some areas of the Central Valley. It is thought that ETRs
higher than these amounts may lead to market resistance by prospective homebuyers, or potential
“taxpayer revolts” by overburdened homeowners. The maximum supportable ETR for a given
project should also consider the maximum tax rates paid by homes in competing projects in the
area and, based on the strength of the real estate market, the demand for homes in general.
Formation of a CFD authorizes a public agency to levy a special tax on all taxable property
within the CFD in the manner prescribed in the formation documents. Property owned or
irrevocably offered to a public agency may be exempted from the special tax. Mello-Roos
special taxes are collected at the same time and in the same manner as property taxes, unless
otherwise specified by the agency. Special tax revenues may be used to pay debt service on
bonds sold or may also be used to pay directly for facilities and public services.
CFD bonds can be short- or long-term obligations. Typically, long-term bonds have either a
twenty-five or thirty year maturity. Short-term notes or bonds can be issued to provide interim
funding; these obligations are then retired when another source of revenue becomes available.
Due to the flexibility associated with the Act and the wide range of facilities that can be funded
by it, it is likely that CFD bonds will be used to fund facilities within the SPSP area and help fill
funding gaps. Developers will want to ensure that special tax levels are competitive with other
areas of the City and with surrounding jurisdictions. The City will want to ensure that special
taxes are collected and bonds repaid in a timely manner as promised to bond investors. Note
that, depending on land values, development status, infrastructure phasing requirements, and
other factors, multiple series of bonds may need to be issued over time rather than one bond issue
occurring when the Project starts. Any initial bond issue may be constrained by the appraised
value of the land in the CFD and market interest rates at the time bonds are sold.
PROJECT FEASIBILITY
Most of the facilities identified in Appendix 1 are generally required to be in place prior to any
development. However, the actual facilities needed will depend on the development scenario
that occurs. This Finance Plan does not include a detailed feasibility analysis based on the
specific infrastructure costs identified in Appendix 1; however, a detailed feasibility analysis was
prepared for the Project based on similar infrastructure needs and costs. That detailed feasibility
SPSP Financing Plan and Fiscal Impact Analysis 12 May 28, 2013
analysis indicated that the Project, with and without the NCC Future Phase, appears to be
financially feasible. The Project changes reflected in this version of the report do not appear to
adversely affect the overarching feasibility findings from that original analysis; in fact, it is likely
that the Project is even more feasible now than it was estimated to be when that original analysis
was conducted.
Financial feasibility of proposed development is based on a common test used to gauge Project
feasibility: the burden-to-value ratio. While there are no results from this test that guarantee
Project feasibility, a burden-to-value ratio that is no more than 15% to 20% in this area of the
Central Valley is typically considered feasible. The ratios for each land use designation within
each development scenario fell either below or within this range.
SPSP Financing Plan and Fiscal Impact Analysis 13 May 28, 2013
Chapter 3
FISCAL IMPACT ANALYSIS
Fiscal impacts arising from land development can be categorized broadly as either one-time
impacts or recurring impacts, both of which involve a revenue and expense component. For
example, a development project may create the need for a police substation, and the one-time
construction cost of the station may be offset by a development impact fee; these costs and
revenues would be included in a public facilities financing plan. The annual expenses associated
with staffing and maintaining the police substation may be offset by annual property taxes and
other revenues generated by new development to the City; these costs and revenues are part of a
fiscal impact analysis. The fiscal impacts evaluated in this report are the annual, or recurring,
revenues and expenses that affect the City as a result of new development associated with the
proposed Project.
METHODOLOGY
The fiscal analysis compares the annual costs of providing public services against the annual
revenues that will be generated by new development to determine the net fiscal impact. This
FIA focuses solely on the fiscal impacts to the City’s General Fund, Development Services Fund,
and Engineering & Public Works Administration Fund.
Two methodologies are employed in estimating recurring fiscal impacts. First, the case study
method is used to estimate recurring revenues and expenses by applying defined service
standards, existing tax and fee rates, and suggested operating and maintenance costs to the land
uses and services proposed in the Project. The second methodology used is the multiplier
method, which assumes that fiscal impacts will result from proposed development at forecasted
rates per person served based on historical averages for the City. The City’s budgets from fiscal
years 2003-04 through 2010-11 are used to estimate average revenues and expenses. The case
study and multiplier methods are generally used under the following conditions:
Case Study Method
1. Marginal cost is a better approximation of the actual costs to provide similar services.
2. The land use distribution of the project being analyzed does not resemble the land use
distribution within the public agency’s area.
3. Service standards and estimated future costs for new projects are anticipated to be
different than they are now.
Multiplier Method
1. Average cost is a reasonable approximation of the actual costs to provide similar
services to specific developments in future years.
2. Specific revenues and expenses are generated based on population (e.g., gas taxes,
social services).
SPSP Financing Plan and Fiscal Impact Analysis 14 May 28, 2013
3. Service standards and other information are not available or accurate.
The multiplier method relies on a “persons served” factor, which is most often the sum of all
residents plus a certain percentage of employees. The exact relationship of service demands and
revenue potential between residents and employees is difficult to measure, but a service
population comprised of all residents and 31% of employees is utilized in this analysis. The 31%
ratio suggests that a resident generally has approximately three times the impact of an employee.
For example, employees are assumed to be in the City for 2,080 hours per year (based on 52
weeks per year for five days a week for eight hours a day) while residents are assumed to be in
the City for 6,656 hours per year (based on 52 weeks per year for seven days a week for 16 hours
a day, plus 52 weekends in a year for 2 days a week for eight hours a day). The ratio of
employee hours to resident hours is approximately 31%. Table 2 in Appendix 2 presents
historical demographic and employment statistics in the City, ranging from 2004 through 2011,
and includes the number of persons served.
In addition, the FIA incorporates fiscal impacts associated with the public/semi-public land use
to capture potential impacts from students, faculty, and staff at the proposed community college
campus. For purposes of this analysis, community college students are assumed to have similar
impacts as employees and are considered employee equivalents.
Case study and multiplier approaches are used to estimate different recurring fiscal impacts for
new development as listed in the following table:
CITY OF OAKDALE
Case Study Method Multiplier Method
Recurring Revenues
Property Tax Gas Tax
CFD No. 2007-1 (Public Safety Services) Hotel Motel Tax
Sales & Use Tax Business License Fees
Public Safety Sales Tax Franchise Fees & Other Taxes
Real Property Transfer Tax Licenses & Permits
Property Tax In-Lieu of Vehicle License Fees Fines, Forfeitures & Penalties
Other Intergovernmental
Charges for Services
Other Revenues
Transfers In
Development Services Fund Revenues
Engineering & Public Works Administration Fund Revenues
Recurring Expenses
General Government
Fire
Police
Parks & Community Services
Public Works
Development Services Fund Expenses
Engineering & Public Works Administration Fund Expenses
SPSP Financing Plan and Fiscal Impact Analysis 15 May 28, 2013
MAJOR ASSUMPTIONS
Many assumptions are factored into the analysis of fiscal impacts. Pursuant to the scope of work
for this Project, the FIA incorporates general assumptions, methodologies, and formats reflected
in the City’s General Plan Update Fiscal Impact Analysis (General Plan FIA) dated April 15th
,
2011. A brief summary of the most critical assumptions, in terms of their effect on revenues and
expenses, are delineated below:
1. The projected annual fiscal impacts are presented in current year 2012 dollars. Future
impacts could be escalated by an inflation factor that is tied to an appropriate inflation index
such as the Engineering News Record (ENR) index or one of the regional consumer price
indexes (CPI).
2. A summary of the land use, value, and related assumptions that are incorporated into the
fiscal analysis for each development scenario is presented in Tables 3 and 4 of Appendix 2.
An important assumption that affects property tax and property tax in lieu of vehicle license
fees is the estimated value of dwelling units and non-residential development in the Project.
Average values of $350,000 per very low density residential unit, $300,000 per low density
residential unit, $240,000 per medium density residential unit, $150,000 per high density
residential unit, and $200 per building square foot of general commercial, flex use/general
commercial, and office uses are used in this analysis.
3. Legal actions taken at the state level in the 1990s diverted a percentage of the 1.0% property
tax into the Educational Revenue Augmentation Fund (ERAF). For purposes of the fiscal
analysis, it is assumed that this situation will continue in future years.
4. The Project is currently located in unincorporated Stanislaus County within Tax Rate Area
084-010; however, it is expected to annex into the City limits before development begins.
Pursuant to the Property Tax Sharing Agreement between the City of Oakdale and the
County of Stanislaus, the City will receive 30% of the County General Fund allocation of the
1% property tax associated with future incremental property tax revenue while the County
will retain the remaining 70% upon annexation of the development area. In addition, the
City will receive 100% of property tax allocations to the Oakdale Fire District. The resulting
allocation of the 1% property tax redistributed to the City General Fund (post ERAF) is
projected to be 8.47% of the 1% property tax, as shown in Table A3 of Appendix 2.
5. Fiscal revenue and expense standards reflect historical averages of revenues and expenses
based on eight City budgets, ranging from fiscal year 2003-04 through fiscal year 2010-11.
By using historical averages for revenues and expenses that capture periods of economic
expansion and contraction, this analysis also accounts for potential economic and real estate
cycles that may occur during development of the Project.
Not all assumptions and methodologies incorporated into the General Plan FIA apply to the
SPSP FIA or reflect current laws and regulations. Important changes reflected in the SPSP FIA
include the following:
1. Revised employment statistics from the California Employment Development Department.
SPSP Financing Plan and Fiscal Impact Analysis 16 May 28, 2013
2. Resident and employment generation rates for medium density residential units and
non-residential uses.
3. Incorporating fiscal impacts associated with the public/semi public land use to capture
potential impacts from students, faculty, and staff at the proposed community college
campus.
4. Incorporating fiscal impacts to the City’s Development Services Fund as well as Engineering
& Public Works Fund.
5. Revised methodologies to estimate Business License (i.e., based on employees only; students
at the proposed community college are excluded) and Gas Tax (i.e., based on residents)
revenues.
6. A revised methodology to estimate Police expenditures (i.e., based on residents and
employees only; students at the proposed community college are excluded) based on
discussions with Police Department staff.
7. Measuring taxable sales based on the supply of retail square footage planned within the
Project as opposed to measuring it based on the demand for retail generated by the Project.
8. Eliminating revenue associated with the remaining vehicle license fee pursuant to
Senate Bill 89.
FISCAL REVENUES
The City will provide the vast majority of public services to the Project. The City’s General
Fund, Development Services Fund, and Engineering & Public Works Fund are the primary
discretionary funds that will be impacted by new development proposed by the Project and, as a
result, are the only funds estimated in this study. As shown in Table 7 of Appendix 2, the annual
fiscal revenues generated by the Project, including the NCC Future Phase, at buildout are
estimated to be approximately $2.6 million. Annual fiscal revenues generated by the Project if
the NCC Future Phase does not develop are reduced to approximately $2.1 million at buildout.
Secured Property Tax
Property taxes, which are based on assessed valuation, are distributed to public agencies and
special districts based on the allocation factors of the applicable Tax Rate Area (TRA). At the
time this fiscal impact analysis was prepared, the Project was located within TRA 084-010.
Table A3 in Appendix 2 identifies the allocation factors of the 1% property tax to the various
districts, funds, and agencies in the TRA. The tax allocations for the County General Fund and
Oakdale Fire District Fund are adjusted to reflect the allocation to the City of Oakdale upon
property annexation, pursuant to the Property Tax Sharing Agreement between the City of
Oakdale and the County of Stanislaus. Furthermore, the total tax allocation is adjusted to reflect
the actual allocation distributed to the City General Fund after revenues have been shifted to the
SPSP Financing Plan and Fiscal Impact Analysis 17 May 28, 2013
Educational Revenue Augmentation Fund (ERAF). For purposes of the fiscal analysis, it is
assumed that this shift will continue into the future.
The resulting allocation of the 1% property tax redistributed to the City General Fund (post
ERAF) is 8.47% of the 1% property tax. The property tax allocation of the 1% basic property
tax is applied to the estimated assessed value created by the Project. Total annual secured
property tax revenues for the SPSP area, with and without the NCC Future Phase, are shown in
Table 7 of Appendix 2.
CFD No. 2007-1 (Public Safety Services)
The City established the City of Oakdale Community Facilities District No. 2007-1 (Public
Safety Services) (CFD No. 2007-1) through adoption of Resolution No. 2007-77 on May 7,
2007. CFD No. 2007-1 provides funding for public safety services, including fire services, law
enforcement, code enforcement, and animal control. It is assumed that the Project will annex
into CFD No. 2007-1 prior to development and pay the annual special tax, which is currently
$452 per single family unit and $301 per high density unit; there is no CFD No. 2007-1 special
tax for non-residential property, as shown in Table A4 in Appendix 2.
Sales and Use Tax
Several methodologies can be used to estimate taxable sales. One method measures taxable sales
based on the supply of retail square footage. Under this approach, a taxable sales per square foot
estimate is multiplied by the total retail square footage planned for a project. Another approach
looks at the demand side of the equation. Under that approach, household income, percentage of
household income spent on taxable goods and services, and a taxable sales capture rate for the
City are estimated to determine taxable sales.
The supply side approach, which simply counts taxable sales where point-of-sale transactions
occur, is the more conservative of the two approaches and is the one used in this analysis. Of
course, a significant portion of the taxable sales captured by the retail square footage developed
in the Project will be generated by new residential development that also occurs in the Project.
The industry standard for development projects in nearby areas is approximately $250 of taxable
sales per square foot of retail use, which is multiplied by approximately 182,000 building square
feet of retail uses to produce approximately $45.6 million in taxable sales. Other general
commercial, flex/general commercial, and office land uses are assumed to produce only minimal
taxable sales (from a few point-of-sale businesses operating out of office space) estimated to be
$5 per square foot, which is multiplied by approximately 697,000 building square feet of these
uses in the entire SPSP area to produce approximately $3.5 million in taxable sales. These
assumptions are presented in Tables A5 and A6 of Appendix 2.
In addition to the 1.0% local sales tax, the City also receives a portion of the County’s and
State’s pooled revenues. When a sale cannot be identified with a permanent place of business in
this state, the local sales tax is allocated to the local jurisdictions through countywide or
statewide pools. Accordingly, certain sellers are authorized to report their local sales tax either
on a countywide or statewide basis. These may include auctioneers, construction contractors
SPSP Financing Plan and Fiscal Impact Analysis 18 May 28, 2013
making sales of fixtures, catering trucks, itinerant vendors, vending machine operators, and other
permit holders who operate in more than one local jurisdiction, but are unable to readily allocate
taxable transactions to particular jurisdictions. Use tax is also allocated through a countywide
pool. Examples of taxpayers who report use tax allocated through the countywide pool include
out-of-state sellers who ship goods directly to consumers in the state from a stock of goods
located outside the state, and California sellers who ship goods directly to consumers in the state
from a stock of goods located outside of the state. The countywide pools are prorated, first
among the cities and the unincorporated area of each county using the proportion that the
identified tax for each city and unincorporated area of a county bears to the total identified for
the county as a whole. Next, the combined total of the direct sales tax allocation and the prorated
countywide pool amount is used to allocate the statewide pool amount to each city and county.
Furthermore, cities often make agreements to pay for services provided by the county in which
the city is located, by providing a percentage of the city’s local tax directly to the county in-lieu
of writing a check. The city must enact an ordinance reducing the local sales and use tax rate by
the amount that will be defaulted to the county.
Based on data from the State Board of Equalization, the City of Oakdale’s share of revenues
from the pooled funds is approximately 11.2% of its local sales tax revenue. In addition, Oakdale
currently receives 95% of the 1% local tax imposed in the City and the County of Stanislaus
receives the other 5%. These factors are presented in Table A5 of Appendix 2. It is assumed
that these percentages will continue to be received in the future; therefore, these revenues are
incorporated into the analysis, as shown in Table A6 of Appendix 2.
Public Safety Sales Tax
Proposition 172 created a one-half cent sales tax for local public safety. Each county allocates
Proposition 172 revenues to each city in that county based on their proportionate share of net
property tax loss due to ERAF. A figure of 0.40% is used to calculate the percentage of public
safety sales tax revenue accruing to the City of Oakdale, as shown in Table A5 of Appendix 2.
Real Property Transfer Tax
When a residential dwelling unit or non-residential structure is sold within a city, a tax
representing a small percentage of the value is generally transferred to a fund to be split between
the city and the county in which it resides. As shown in Table A7 of Appendix 2, the current rate
in Oakdale is $0.55 per $500 of value, and the City receives 50% of the amount generated from
real property transfers.
Property Tax In-Lieu of Vehicle License Fees
The City’s net assessed value for the 2011-12 tax roll and property tax in lieu of VLF for
2011-12 were obtained from the County Auditor-Controller’s office and are shown in Table A8
of Appendix 2. The property tax in lieu of VLF allocated to the City as a result of growth in the
SPSP area, with and without the NCC Future Phase, can be calculated by increasing the City’s
2011-12 allocated property tax in lieu of VLF amount in proportion to the increase in the
SPSP Financing Plan and Fiscal Impact Analysis 19 May 28, 2013
assessed value from each development scenario. Property tax in lieu of VLF estimates for each
development area are summarized in Table A8 of Appendix 2.
Fiscal Revenues Estimated Using the Multiplier Method
Of the various revenue sources itemized in Table 7 of Appendix 2, twelve are calculated using
the multiplier method. Gross revenues from fiscal years 2003-04 through 2010-11 as well as the
8-year average are shown in Table A1 of Appendix 2, while the resulting multipliers are shown
in Table A2 of Appendix 2. These multipliers are applied to the appropriate residents,
employees and students, or persons served estimate for each calculation, and are summarized in
Table 7 of Appendix 2.
Gas tax revenues are based on the number of residents within the City.
Hotel and motel tax revenues relate to residential and non-residential land uses; therefore, an
average charge per person served is used to determine additional revenue in this category.
Business license fee revenues are based strictly on an employee multiplier; students at the
proposed community college are excluded.
Franchise fees and other taxes relate to residential and non-residential land uses; therefore, an
average charge per person served is used to determine additional revenue in this category.
Licenses and permits relate to residential and non-residential land uses; therefore, an average
charge per person served is used to determine additional revenue in this category.
Both residents and businesses generate various fine revenues; therefore, the multiplier for
fines, forfeitures, and penalties is calculated on a persons served basis.
Revenue from other agencies (intergovernmental) is calculated on a persons served basis.
Service charges relate to both residents, employees, and students; therefore, an average
charge per person served is used to determine additional revenue in this category.
The multiplier for other revenues is calculated on a persons served basis.
The multiplier for transfers in to the General Fund from other City departments is calculated
on a persons served basis.
Development Services Fund charges relate to both residents and employees; therefore, an
average amount per person served is used to determine additional revenue in this category.
Engineering & Public Works Administration Fund services charges relate to both residents
and employees; therefore, an average amount per person served is used to determine
additional revenue in this category.
SPSP Financing Plan and Fiscal Impact Analysis 20 May 28, 2013
FISCAL EXPENSES
Each development scenario will increase operation and maintenance costs for the City as the City
provides for the demands of the increased population. As shown in Table 7 of Appendix 2, the
annual fiscal expenses generated by the Project, including the NCC Future Phase, at buildout are
estimated to be approximately $2.4 million. Annual fiscal expenses generated by the Project if
the NCC Future Phase does not develop are reduced to approximately $2.0 million at buildout.
Fiscal Expenses Estimated Using the Multiplier Method
All of the expense categories are calculated using the multiplier method. Gross expenditures
from fiscal years 2003-04 through 2010-11 as well as the resulting 8-year average are shown in
Table 5 of Appendix 2, while the resulting multipliers are shown in Table 6 of Appendix 2.
These multipliers are applied to the appropriate residents, employees, or persons served estimate
for each category anticipated for each development scenario, and are presented in Table 7 of
Appendix 2.
General government services are estimated using a persons served multiplier. This category
includes the city council, city manager, human resources department, city clerk, finance
division, city treasurer, and city attorney as well as non-departmental functions.
Fire protection costs are estimated using a persons served multiplier.
Police protection costs are estimated using a persons served multiplier. Students from the
proposed community college are excluded in determining the number of persons served
based on discussions with Police Department staff.
Parks and community services costs are estimated using a persons served multiplier.
Public works expenditures are estimated on a persons served basis.
Development Services Fund expenditures include costs associated with planning, building,
and development services, and are estimated on a persons served basis.
Engineering and Public Works Administration expenditures are estimated on a persons
served basis.
NET FISCAL IMPACTS
SPSP Excluding NCC Future Phase
If the NCC Future Phase does not develop as residential uses, the Project is expected to generate
approximately $2.1 million in annual fiscal revenues to the City at buildout. Fiscal expenses are
estimated to be $2.0 annually when the Project is fully developed, resulting in an annual surplus
of approximately $0.1 million.
SPSP Financing Plan and Fiscal Impact Analysis 21 May 28, 2013
Entire SPSP Area (Including NCC Future Phase)
Assuming the NCC Future Phase develops as residential development, the Project is expected to
generate approximately $2.5 million in annual fiscal revenues to the City at buildout. Fiscal
expenses are estimated to be $2.4 annually when the Project is fully developed, resulting in an
annual surplus of $0.1 million. A summary of the net fiscal impacts anticipated at buildout of
each development scenario is included in Table 3-1 below and detailed in Table 7 of Appendix 2.
TABLE 3-1
SUMMARY OF NET FISCAL IMPACTS ($ IN MILLIONS)
SPSP
Excluding
NCC Future
Phase
Entire
SPSP Area
(Including NCC
Future Phase)
Annual Revenues $2.1 $2.5
Annual Costs $2.0 $2.4
Net Fiscal Impact $0.1 $0.1
Both development scenarios are anticipated to be fiscally positive. The difference in the net
fiscal impacts between the two scenarios is relatively small. The entire SPSP area (including
NCC Future Phase) development scenario is estimated to generate approximately $6,000 more in
annual surplus revenue than the SPSP excluding NCC Future Phase scenario.
As discussed previously, the estimated annual recurring fiscal impact associated with each
development area assumes the Project annexes into CFD No. 2007-1 and, therefore, will be
subject to the corresponding special tax to pay for public safety services. However, if the Project
does not annex into CFD No. 2007-1, the entire SPSP area (including NCC Future Phase)
development scenario will likely generate a $0.2 million annual deficit to the City at buildout.
Similarly, the surplus anticipated at buildout of the SPSP excluding NCC Future Phase scenario
would turn into a $0.1 million annual deficit.
Although fiscal impacts at various phases of development are not included in the FIA, it should
be noted that phasing is critical. Depending on which land uses develop first, the City could
experience either a period of recurring fiscal deficits or recurring fiscal surpluses as the Project
builds out. As a result, the City may require mechanisms to fund deficits in the interim years.
Furthermore, the City may require funding mechanisms (e.g., CFDs or Landscaping and Lighting
Districts) to cover Project-specific streetlight, park, and roadway and storm drain landscape
maintenance costs.
SPSP Financing Plan and Fiscal Impact Analysis 22 May 28, 2013
Chapter 4
CONCLUSIONS
PUBLIC FACILITIES FINANCING
As noted in prior areas of this report, many of the facilities identified in this report are generally
required to be in place prior to any development. However, the actual facilities needed will
depend on the development scenario that actually occurs. Fee revenue will not be available
upfront to fund the construction of these facilities, so the City and the Project proponent will
need to consider private financing or municipal debt financing alternatives. Since the developer
may be required to advance-fund the improvements constructed initially, the developer would
also be entitled to a fee credit or reimbursement from future development within the Project or
Citywide depending on the type of improvement (i.e., CFF Program, SPSP Program, or In-tract).
Developers will receive a fee credit or reimbursement for construction of facilities included in
the CFF Program or SPSP Fee Program, but they will not receive a fee credit or reimbursement
for in-tract facilities.
CFDs have been used throughout the City to fund various infrastructure and public services, and
a CFD could finance the vast majority of public improvements that the developer may need to
install to support SPSP development. The developer may want to use CFD financing to
accelerate reimbursement for some of the upfront infrastructure.
Although this Finance Plan does not include a detailed feasibility analysis based on the specific
infrastructure costs identified in Appendix 1, a detailed feasibility analysis was prepared for the
Project based on similar infrastructure needs and costs. That prior feasibility analysis indicated
that the Project, both with and without the NCC Future Phase, appears to be financially feasible.
If an updated feasibility analysis were to be conducted, it would probably reveal that the Project
is even more feasible now than when the original analysis was prepared.
Implementation
The SPSP identifies a program for both residential and non-residential growth within a specific
area of the City of Oakdale and will be subject to updates and revisions in future years as
development applications are submitted and processed.
The SPSP and the PFFP are based on assumptions of land use, facility demands, facility
standards and design, and cost estimates. Each of these assumptions may be subject to change in
future years; therefore, the PFFP may also be revised to reflect these changes. The ongoing
implementation of the PFFP will be parallel to the continued monitoring of the SPSP, and will
require the same degree of time and effort to keep it current and useful. In this manner, the PFFP
will guide the overall funding of community infrastructure required to serve the SPSP area.
1. Updates and Revisions
The PFFP should be updated each time there is a change in facility plans, land use plans,
or cost estimates. When these items are revised, there will be a corresponding change in
SPSP Financing Plan and Fiscal Impact Analysis 23 May 28, 2013
the fair share burden to each land use in the Project. Land use and facility changes will
result in revisions to the benefit analysis and corresponding fee allocation to each land
use. To the extent some properties in the SPSP area have been developed and paid their
fair share prior to a program update, revisions will apply only to future new development.
If facility costs are determined to be higher than estimated in the PFFP, the City will need
to increase fees in future years and/or call on developers to fund the extra expenses based
on the provisions of an acquisition agreement.
As the City adopts new ordinances or updates existing ordinances in future years, fees
will be adjusted based on actual costs realized after construction bids have been received
for public facilities. If actual costs are higher than expected, the City will have to
increase fees and/or rely on the terms of an acquisition agreement to avoid a financing
deficit in future years.
2. Action Items
Prior to commencement of development in the SPSP area, the City may need to adopt a
fee ordinance or resolution implementing a SPSP fee for each type of capital facility or
shared cost to be included in the SPSP Fee Program. The initial ordinance will reflect
fees based on information available at that time. Fees will be adjusted annually or on a
more frequent basis to reflect actual costs and current cost estimates. Alternatively, the
City could execute a development agreement, in accordance with Section 36-23.20 of the
Oakdale Zoning Code and as envisioned in the Specific Plan, with Project landowners
that, among other provisions, describes and quantifies the required fees.
Furthermore, before any SPSP fees are established, the City will need to update its
Capital Facilities Fee (CFF) program to, among other things, include applicable Project-
specific infrastructure costs and to resolve any potential overlaps between the proposed
SPSP Fee Program and the CFF. This will be especially important with respect to how
storm drainage and park facilities are treated in the CFF as opposed to the Specific Plan,
and how credits against the CFF for these facilities may be applied. In addition, land
costs associated with each infrastructure type should be addressed as part of the CFF
Program update and the creation of the proposed SPSP Fee Program.
Pursuant to Section 66006 of the Government Code, the City could establish a separate
SPSP capital facility account and a unique fund for each type of public facility for which
fees are collected. Establishment of this account will prevent commingling of the SPSP
fees with other City revenues and funds. Interest income earned by fee revenues in this
account will be deposited in the account and applied to facility construction costs.
Within one hundred eighty (180) days of the close of each fiscal year, the City will make
information pertaining to the account [as required by Section 66006 (b)(1)] available to
the public and will review this information at a regularly scheduled public hearing.
In addition, if the developer requests formation of a Mello-Roos CFD as discussed herein
and the City concurs with that request, the City must form a financing team made up of
experts in the various fields associated with implementation of such districts, including
bond counsel, bond underwriter, and special tax consultant. The City and financing team
SPSP Financing Plan and Fiscal Impact Analysis 24 May 28, 2013
will be responsible for forming the district, issuing bonds to pay for required facilities,
and levying special taxes to ensure timely repayment of bonds.
FISCAL IMPACTS
The FIA examines the fiscal impacts generated at buildout of the SPSP area, both including and
excluding the NCC Future Phase. Both development scenarios are anticipated to be fiscally
positive. The difference in the net fiscal impacts between the two scenarios is almost negligible.
Both development scenarios – the entire SPSP area (including NCC Future Phase) and the SPSP
excluding the NCC Future Phase – are estimated to generate an annual surplus of approximately
$0.1 million at buildout.
Implementation
Although fiscal impacts at various phases of development are not included in the FIA, it should
be noted that phasing is critical. Depending on which land uses develop first, the City could
experience either a period of recurring fiscal deficits or recurring fiscal surpluses as the Project
builds out. As the City enters into development agreements, as discussed above, this risk may
need to be shifted to Project landowners.
In addition, the Project will need to annex into CFD No. 2007-1, or implement an equivalent
financing mechanism, prior to commencing development. The City will also require the Project
to participate in additional funding mechanisms (e.g., Landscaping and Lighting Districts) to
cover Project-specific storm drain and landscape maintenance costs, since it is City standard
practice to require all new subdivisions to participate in an LLD (Landscaping and Lighting
District). Formation of, or annexation into, an LLD for these purposes must also consider a
sinking fund or other mechanism to fund potential landscape restoration costs in instances where
Oakdale Irrigation District pipelines running under new landscaped areas within the Project need
to be repaired or replaced.
APPENDIX 1
DETAILED FACILITIES COST ESTIMATES
(from Giuliani & Kull, Inc.)
Page A-1
Pre
limin
ary
Op
inio
n o
f P
rob
ab
le C
ost
of
Ba
ckb
on
e In
fra
stru
ctu
reSi
erra
Po
inte
Sp
ecif
ic P
lan
Ma
rch
21
, 20
13
Oa
kda
le, C
A
Des
crip
tio
nQ
uan
tity
Un
itC
ost
/Un
itTo
tal
Fee
Cat
ego
ry
WA
TER
MIX
ED U
SE C
OR
RID
OR
PH
ASE
8"
C9
00
PV
C P
IPE
42
0LF
$2
7$
11
,34
0IN
-TR
AC
T
12
" C
90
0 P
VC
PIP
E6
,43
0LF
$6
0$
38
5,8
00
CFF
8"
LATE
RA
L3
0LF
$3
5$
1,0
50
IN-T
RA
CT
8"
VA
LVES
2EA
$1
,50
0$
3,0
00
IN-T
RA
CT
12
" V
ALV
ES1
0EA
$2
,00
0$
20
,00
0C
FF
FIR
E H
YDR
AN
TS1
5EA
$3
,50
0$
52
,50
0C
FF
SUB
-TO
TAL
$4
73
,69
0
RES
IDEN
TIA
L N
EIG
HB
OR
HO
OD
PH
ASE
8"
C9
00
PV
C P
IPE
5,8
70
LF$
27
$1
58
,49
0IN
-TR
AC
T
12
" C
90
0 P
VC
PIP
E1
1,5
28
LF$
60
$6
91
,68
0C
FF
8"
LATE
RA
L3
00
LF$
35
$1
0,5
00
IN-T
RA
CT
12
" LA
TER
AL
42
0LF
$5
0$
21
,00
0C
FF
8"
VA
LVES
28
EA$
1,5
00
$4
2,0
00
IN-T
RA
CT
12
" V
ALV
ES4
6EA
$2
,00
0$
92
,00
0C
FF
FIR
E H
YDR
AN
TS5
0EA
$3
,50
0$
17
5,0
00
CFF
WEL
L1
EA$
1,0
00
,00
0$
1,0
00
,00
0C
FF
SUB
-TO
TAL
$2
,19
0,6
70
NC
C F
UTU
RE
PH
ASE
8"
C9
00
PV
C P
IPE
1,7
40
LF$
27
$4
6,9
80
IN-T
RA
CT
8"
LATE
RA
L9
0LF
$3
5$
3,1
50
IN-T
RA
CT
8"
VA
LVES
10
EA$
1,5
00
$1
5,0
00
IN-T
RA
CT
FIR
E H
YDR
AN
TS4
EA$
3,5
00
$1
4,0
00
IN-T
RA
CT
SUB
-TO
TAL
$7
9,1
30
TOTA
L W
ATE
R$
2,7
43
,49
0
No
te:
An
cilla
ry it
ems
such
as
late
rals
, va
lves
, fir
e h
ydra
nts
, etc
. in
dic
ate
d w
ith
in t
his
est
ima
te f
or
ba
ckb
on
e in
fra
stru
ctu
re f
aci
litie
s o
nly
.
Pa
ge
1 o
f 9
3/2
9/2
01
3
Page A-2
Des
crip
tio
nQ
uan
tity
Un
itC
ost
/Un
itTo
tal
Fee
Cat
ego
ry
STO
RM
MIX
ED U
SE C
OR
RID
OR
PH
ASE
24
" SD
R 2
6 P
VC
PIP
E 1
,64
0LF
$6
0$
98
,40
0C
FF
24
" LA
TER
AL
30
LF$
65
$1
,95
0C
FF
STO
RM
DR
AIN
MA
NH
OLE
3EA
$3
,00
0$
9,0
00
CFF
CA
TCH
BA
SIN
9EA
$2
,50
0$
22
,50
0C
FF
FREN
CH
DR
AIN
- S
R 1
20
/10
8 S
TREE
T D
RA
INA
GE
50
0LF
$1
50
$7
5,0
00
CFF
SUB
-TO
TAL
$2
06
,85
0
RES
IDEN
TIA
L N
EIG
HB
OR
HO
OD
PH
ASE
24
" SD
R 2
6 P
VC
PIP
E 3
,22
4LF
$6
0$
19
3,4
40
CFF
36
" SD
R 2
6 P
VC
PIP
E 2
,03
0LF
$8
0$
16
2,4
00
CFF
48
" SD
R 2
6 P
VC
PIP
E 1
70
LF$
10
7$
18
,19
0C
FF
24
" LA
TER
AL
21
0LF
$6
5$
13
,65
0IN
-TR
AC
T
36
" LA
TER
AL
90
LF$
85
$7
,65
0C
FF
STO
RM
DR
AIN
MA
NH
OLE
13
EA$
3,0
00
$3
9,0
00
CFF
CA
TCH
BA
SIN
26
EA$
2,5
00
$6
5,0
00
CFF
PA
RK
-1 B
ASI
N1
6,6
91
CY
$4
$6
6,7
64
CFF
PA
RK
-1 F
REN
CH
DR
AIN
3
,36
0LF
$1
50
$5
04
,00
0C
FF
PA
RK
-2 B
ASI
N1
2,0
66
CY
$4
$4
8,2
64
CFF
PA
RK
-2 F
REN
CH
DR
AIN
2,3
00
LF$
15
0$
34
5,0
00
CFF
SUB
-TO
TAL
$1
,46
3,3
58
NC
C F
UTU
RE
PH
ASE
24
" SD
R 2
6 P
VC
PIP
E 6
50
LF$
60
$3
9,0
00
CFF
36
" SD
R 2
6 P
VC
PIP
E 5
00
LF$
80
$4
0,0
00
CFF
48
" SD
R 2
6 P
VC
PIP
E 1
70
LF$
10
7$
18
,19
0C
FF
24
" LA
TER
AL
60
LF$
65
$3
,90
0IN
-TR
AC
T
STO
RM
DR
AIN
MA
NH
OLE
3EA
$3
,00
0$
9,0
00
CFF
CA
TCH
BA
SIN
6EA
$2
,50
0$
15
,00
0C
FF
SUB
-TO
TAL
$1
25
,09
0
TOTA
L ST
OR
M
$1
,79
5,2
98
Pa
ge
2 o
f 9
3/2
9/2
01
3
Page A-3
Des
crip
tio
nQ
uan
tity
Un
itC
ost
/Un
itTo
tal
Fee
Cat
ego
ry
SEW
ER
MIX
ED U
SE C
OR
RID
OR
PH
ASE
8"
SDR
26
PIP
E1
,79
0LF
$3
5$
62
,65
0SP
8"
LATE
RA
L 3
0LF
$4
0$
1,2
00
SP
SEW
ER M
AN
HO
LE5
EA$
3,0
00
$1
5,0
00
SP
SUB
-TO
TAL
$7
8,8
50
RES
IDEN
TIA
L N
EIG
HB
OR
HO
OD
PH
ASE
8"
SDR
26
PIP
E8
,30
0LF
$3
5$
29
0,5
00
SP
10
" SD
R 2
6 P
IPE
2,2
60
LF$
44
$9
9,4
40
SP
6"
C9
00
PV
C P
IPE
FOR
CE
MA
IN S
TUB
FO
R F
UTU
RE
30
LF$
25
$7
50
SP
8"
C9
00
PV
C P
IPE
FOR
CE
MA
IN6
30
LF$
27
$1
7,0
10
SP
8"
LATE
RA
L 2
70
LF$
40
$1
0,8
00
SP
10
" LA
TER
AL
90
LF$
50
$4
,50
0SP
SEW
ER M
AN
HO
LE2
4EA
$3
,00
0$
72
,00
0SP
LIFT
STA
TIO
N 8
"1
EA$
50
0,0
00
$5
00
,00
0C
FF
LIFT
STA
TIO
N 6
" 1
EA$
35
0,0
00
$3
50
,00
0C
FF
SUB
-TO
TAL
$1
,34
5,0
00
NC
C F
UTU
RE
PH
ASE
8"
SDR
26
PIP
E1
,54
0LF
$3
5$
53
,90
0SP
8"
LATE
RA
L 9
0LF
$4
0$
3,6
00
SP
SEW
ER M
AN
HO
LE4
EA$
3,0
00
$1
2,0
00
SP
SUB
-TO
TAL
$6
9,5
00
TOTA
L SE
WER
$1
,49
3,3
50
Pa
ge
3 o
f 9
3/2
9/2
01
3
Page A-4
Des
crip
tio
nQ
uan
tity
Un
itC
ost
/Un
itTo
tal
Fee
Cat
ego
ry
IRR
IGA
TIO
N
MIX
ED U
SE C
OR
RID
OR
PH
ASE
WES
T P
UM
P P
IPEL
INE
DEM
O E
XIS
TIN
G 3
0"
IRR
IGA
TIO
N P
IPEL
INE/
AP
PU
RTE
NA
NC
ES5
,10
0LF
$2
0$
10
2,0
00
SP
INST
ALL
NEW
30
" IR
RIG
ATI
ON
PIP
ELIN
E3
,00
0LF
$1
20
$3
60
,00
0SP
AIR
VEN
TS A
ND
MIS
C. S
TRU
CTU
RES
8EA
$3
,00
0$
24
,00
0SP
SUB
-TO
TAL
$4
86
,00
0
RES
IDEN
TIA
L N
EIG
HB
OR
HO
OD
PH
ASE
AD
AM
S N
o.1
PIP
ELIN
E
DEM
O E
XIS
TIN
G 4
2"
AD
AM
S N
o.1
IRR
IGA
TIO
N P
IPEL
INE/
AP
PU
RTE
NA
NC
ES2
,31
0LF
$3
0$
69
,30
0SP
DEM
O E
XIS
TIN
G 3
0"
LAN
E/C
ON
SOLI
IRR
IGA
TIO
N P
IPEL
INE/
AP
PU
RTE
NA
NC
ES5
00
LF$
20
$1
0,0
00
SP
INST
ALL
NEW
42
" IR
RIG
ATI
ON
PIP
ELIN
E3
,20
0LF
$1
70
$5
44
,00
0SP
AIR
VEN
TS A
ND
STR
UC
TUR
ES8
EA$
3,0
00
$2
4,0
00
SP
CO
NTR
OL
STR
UC
TUR
E FO
R L
AN
E/C
ON
SOLI
IRR
IGA
TIO
N P
IPEL
INE
1LF
$2
0,0
00
$2
0,0
00
SP
AD
AM
S C
REE
K P
IPEL
INE
INST
ALL
NEW
36
" IR
RIG
ATI
ON
PIP
ELIN
E5
,00
0LF
$1
45
$7
25
,00
0SP
SUB
-TO
TAL
$1
,39
2,3
00
NC
C F
UTU
RE
PH
ASE
N/A
SUB
-TO
TAL
$0
.00
TOTA
L IR
RIG
ATI
ON
$1
,87
8,3
00
Pa
ge
4 o
f 9
3/2
9/2
01
3
Page A-5
Des
crip
tio
nQ
uan
tity
Un
itC
ost
/Un
itTo
tal
Fee
Cat
ego
ry
STR
EETS
ENTR
IES,
TR
AIL
S, &
OP
EN S
PA
CE
Cit
y G
atew
ays
1EA
$5
0,0
00
$5
0,0
00
SP
Trai
ls (
Pav
ed)1
0LF
$2
3$
0SP
OS
Lan
dsc
apin
g21
.63
AC
$4
0,0
00
$6
5,2
00
SP
ENTR
IES/
TRA
ILS/
OS
SUB
-TO
TAL
$1
15
,20
0
MIX
ED U
SE C
OR
RID
OR
PH
ASE
STEA
RN
S R
OA
D -
NO
RTH
EN
TRY
80
0LF
DR
Y U
TILI
TIES
80
0LF
$1
00
$8
0,0
00
CFF
CU
RB
& G
UTT
ER (
2 E
AC
H)
1,6
00
LF$
13
$2
0,8
00
CFF
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")1
04
5TN
$7
5.2
$7
8,5
84
CFF
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
98
5C
Y$
56
$5
5,1
60
CFF
MED
IAN
CU
RB
1,6
00
LF$
10
$1
6,0
00
CFF
MED
IAN
LA
ND
SCA
PIN
G9
,60
0SF
$2
.50
$2
4,0
00
CFF
STR
EET
LIG
HTI
NG
3EA
$5
,00
0$
15
,00
0C
FF
STEA
RN
S R
OA
D -
NO
RTH
87
0LF
DR
Y U
TILI
TIES
87
0LF
$1
00
$8
7,0
00
CFF
CU
RB
& G
UTT
ER (
2 E
AC
H)
1,7
40
LF$
13
$2
2,6
20
CFF
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")1
31
6TN
$7
5.2
$9
8,9
63
CFF
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
12
41
CY
$5
6$
69
,49
6C
FF
MED
IAN
CU
RB
0LF
$1
0$
0C
FF
MED
IAN
LA
ND
SCA
PIN
G0
SF$
2.5
0$
0C
FF
STR
EET
LIG
HTI
NG
3EA
$5
,00
0$
15
,00
0C
FF
HIG
HW
AY
12
0/1
08
2,7
60
LF
DR
Y U
TILI
TIES
2,7
60
LF$
10
0$
27
6,0
00
CFF
CU
RB
& G
UTT
ER (
2 E
AC
H)
5,5
20
LF$
13
$7
1,7
60
CFF
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")6
07
2TN
$7
5.2
$4
56
,61
4C
FF
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
57
24
CY
$5
6$
32
0,5
44
CFF
MED
IAN
CU
RB
5,5
20
LF$
13
$7
1,7
60
CFF
MED
IAN
LA
ND
SCA
PIN
G4
4,1
60
SF$
4.0
0$
17
6,6
40
CFF
STR
EET
LIG
HTI
NG
9EA
$5
,00
0$
45
,00
0C
FF
SUB
-TO
TAL
$2
,00
0,9
41
Pa
ge
5 o
f 9
3/2
9/2
01
3
Page A-6
Des
crip
tio
nQ
uan
tity
Un
itC
ost
/Un
itTo
tal
Fee
Cat
ego
ry
STR
EETS
CO
NT'
D
RES
IDEN
TIA
L N
EIG
HB
OR
HO
OD
PH
ASE
SPEC
IAL
FEA
TUR
ESR
ou
nd
abo
uts
3EA
$5
0,0
00
$1
50
,00
0SP
Enh
ance
d C
ross
ings
3EA
$5
0,0
00
$1
50
,00
0C
FF
(O
rsi R
oad
at
J St
reet
& L
and
o, T
wild
oSt
earn
s In
ters
ecti
on
)
ENTR
IES/
TRA
ILS/
OS
SUB
-TO
TAL
$3
00
,00
0
RO
AD
WO
RK
SIER
RA
RO
AD
1,9
70
LF
DR
Y U
TILI
TIES
1,9
70
LF$
10
0$
19
7,0
00
CFF
CU
RB
& G
UTT
ER (
2 E
AC
H)
3,9
40
LF$
13
$5
1,2
20
CFF
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")2
98
0TN
$7
5.2
$2
24
,09
6C
FF
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
28
09
CY
$5
6$
15
7,3
04
CFF
MED
IAN
CU
RB
0LF
$1
0$
0C
FF
MED
IAN
LA
ND
SCA
PIN
G0
SF$
2.5
0$
0C
FF
STR
EET
LIG
HTI
NG
7EA
$5
,00
0$
35
,00
0C
FF
RO
AD
A1
,38
0LF
DR
Y U
TILI
TIES
1,3
80
LF$
10
0$
13
8,0
00
SP
CU
RB
& G
UTT
ER (
2 E
AC
H)
2,7
60
LF$
13
$3
5,8
80
SP
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")1
80
3TN
$7
5.2
$1
35
,58
6SP
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
16
99
CY
$5
6$
95
,14
4SP
MED
IAN
CU
RB
0LF
$1
0$
0SP
MED
IAN
LA
ND
SCA
PIN
G0
SF$
2.5
0$
0SP
STR
EET
LIG
HTI
NG
5EA
$5
,00
0$
25
,00
0SP
STEA
RN
S R
OA
D -
SO
UTH
3
,60
0LF
DR
Y U
TILI
TIES
3,6
00
LF$
10
0$
36
0,0
00
CFF
CU
RB
& G
UTT
ER (
2 E
AC
H)
7,2
00
LF$
13
$9
3,6
00
CFF
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")5
44
5TN
$7
5.2
$4
09
,46
4C
FF
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
51
33
CY
$5
6$
28
7,4
48
CFF
MED
IAN
CU
RB
0LF
$1
0$
0C
FF
MED
IAN
LA
ND
SCA
PIN
G0
SF$
2.5
0$
0C
FF
STR
EET
LIG
HTI
NG
12
EA$
5,0
00
$6
0,0
00
CFF
Pa
ge
6 o
f 9
3/2
9/2
01
3
Page A-7
Des
crip
tio
nQ
uan
tity
Un
itC
ost
/Un
itTo
tal
Fee
Cat
ego
ry
STR
EETS
CO
NT'
D
OR
SI R
OA
D3
,69
0LF
DR
Y U
TILI
TIES
3,6
90
LF$
10
0$
36
9,0
00
CFF
CU
RB
& G
UTT
ER (
2 E
AC
H)
7,3
80
LF$
13
$9
5,9
40
CFF
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")6
34
2TN
$7
5.2
$4
76
,91
8C
FF
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
59
79
CY
$5
6$
33
4,8
24
CFF
MED
IAN
CU
RB
0LF
$1
0$
0C
FF
MED
IAN
LA
ND
SCA
PIN
G0
SF$
2.5
0$
0C
FF
STR
EET
LIG
HTI
NG
12
EA$
5,0
00
$6
0,0
00
CFF
EAST
J S
TREE
T1
,50
0LF
DR
Y U
TILI
TIES
1,5
00
LF$
10
0$
15
0,0
00
CFF
CU
RB
& G
UTT
ER (
2 E
AC
H)
3,0
00
LF$
13
$3
9,0
00
CFF
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")1
95
9TN
$7
5.2
$1
47
,31
7C
FF
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
18
47
CY
$5
6$
10
3,4
32
CFF
MED
IAN
CU
RB
0LF
$1
0$
0C
FF
MED
IAN
LA
ND
SCA
PIN
G0
SF$
2.5
0$
0C
FF
STR
EET
LIG
HTI
NG
5EA
$5
,00
0$
25
,00
0C
FF
SEIR
RA
PO
INTE
DR
IVE
3,8
70
LF
DR
Y U
TILI
TIES
3,8
70
LF$
10
0$
38
7,0
00
SP
CU
RB
& G
UTT
ER (
2 E
AC
H)
7,7
40
LF$
13
$1
00
,62
0SP
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")5
05
5TN
$7
5.2
$3
80
,13
6SP
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
47
66
CY
$5
6$
26
6,8
96
SP
MED
IAN
CU
RB
0LF
$1
0$
0SP
MED
IAN
LA
ND
SCA
PIN
G0
SF$
2.5
0$
0SP
STR
EET
LIG
HTI
NG
13
EA$
5,0
00
$6
5,0
00
SP
LAN
DO
DR
IVE
40
0LF
DR
Y U
TILI
TIES
40
0LF
$1
00
$4
0,0
00
SP
CU
RB
& G
UTT
ER (
2 E
AC
H)
80
0LF
$1
3$
10
,40
0SP
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")5
23
TN$
75
.2$
39
,33
0SP
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
49
3C
Y$
56
$2
7,6
08
SP
MED
IAN
CU
RB
0LF
$1
0$
0SP
MED
IAN
LA
ND
SCA
PIN
G0
SF$
2.5
0$
0SP
STR
EET
LIG
HTI
NG
1EA
$5
,00
0$
5,0
00
SP
SUB
-TO
TAL
$5
,42
8,1
63
Pa
ge
7 o
f 9
3/2
9/2
01
3
Page A-8
Des
crip
tio
nQ
uan
tity
Un
itC
ost
/Un
itTo
tal
Fee
Cat
ego
ry
STR
EETS
CO
NT'
D
NC
C F
UTU
RE
PH
ASE
EAST
J S
TREE
T5
70
LF
DR
Y U
TILI
TIES
57
0LF
$1
00
$5
7,0
00
CFF
CU
RB
& G
UTT
ER (
2 E
AC
H)
1,1
40
LF$
13
$1
4,8
20
CFF
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")7
45
TN$
75
.2$
56
,02
4C
FF
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
70
2C
Y$
56
$3
9,3
12
CFF
MED
IAN
CU
RB
0LF
$1
0$
0C
FF
MED
IAN
LA
ND
SCA
PIN
G0
SF$
2.5
0$
0C
FF
STR
EET
LIG
HTI
NG
2EA
$5
,00
0$
10
,00
0C
FF
SEIR
RA
PO
INTE
DR
IVE
1,1
40
LF
DR
Y U
TILI
TIES
1,1
40
LF$
10
0$
11
4,0
00
SP
CU
RB
& G
UTT
ER (
2 E
AC
H)
2,2
80
LF$
13
$2
9,6
40
SP
ASP
HA
LT P
AV
ING
SEC
TIO
N (
5.5
")1
48
9TN
$7
5.2
$1
11
,97
3SP
CLA
SS II
AG
GR
EGA
TE B
ASE
SEC
TIO
N (
10
.5")
14
04
CY
$5
6$
78
,62
4SP
MED
IAN
CU
RB
0LF
$1
0$
0SP
MED
IAN
LA
ND
SCA
PIN
G0
SF$
2.5
0$
0SP
STR
EET
LIG
HTI
NG
4EA
$5
,00
0$
20
,00
0SP
SUB
-TO
TAL
$5
31
,39
3
TOTA
L ST
REE
TS$
8,3
75
,69
7
PA
RK
S
RES
IDEN
TIA
L N
EIG
HB
OR
HO
OD
PH
ASE
CO
NST
RU
CTI
ON
CO
STS
6.4
5A
C$
11
8,5
00
$7
64
,32
5C
FF
LAN
D C
OST
S6
.45
AC
$1
29
,00
0$
83
2,0
50
CFF
SOU
TH S
UB
-TO
TAL
$1
,59
6,3
75
NC
C F
UTU
RE
PH
ASE
CO
NST
RU
CTI
ON
CO
STS
6.1
4A
C$
11
8,5
00
$7
27
,59
0C
FF
LAN
D C
OST
S6
.14
AC
$1
29
,00
0$
79
2,0
60
CFF
SOU
TH S
UB
-TO
TAL
$1
,51
9,6
50
TOTA
L P
AR
KS
$3
,11
6,0
25
Pa
ge
8 o
f 9
3/2
9/2
01
3
Page A-9
Des
crip
tio
nQ
uan
tity
Un
itC
ost
/Un
itTo
tal
Fee
Cat
ego
ry
SUM
MA
RY
BY
PH
ASE
MIX
ED U
SE C
OR
RID
OR
PH
ASE
SU
B-T
OTA
L$
3,2
46
,33
1
RES
IDEN
TIA
L N
EIG
HB
OR
HO
OD
PH
ASE
SU
B-T
OTA
L$
13
,71
5,8
66
NC
C F
UT
UR
E P
HA
SE S
UB
-TO
TAL
$2
,32
4,7
63
ENTR
IES,
TR
AIL
S, &
OP
EN S
PA
CE
$1
15
,20
0
CO
MB
INED
SU
B-T
OTA
L $
19
,40
2,1
60
OTH
ER C
OST
SC
ON
TIN
GEN
CY
10
%$
1,9
40
,21
6
SOFT
CO
STS:
EN
GIN
EER
ING
, CO
NST
RU
CTI
ON
MA
NA
GEM
ENT/
INSP
ECTI
ON
25
%$
4,8
50
,54
0
GR
AN
D T
OTA
L$
26
,19
2,9
16
SUM
MA
RY
BY
CA
TEG
OR
Y
SUB
-TO
TAL
SOFT
CO
STS
TOTA
L
CFF
$1
4,1
86
,41
3$
3,5
46
,60
3$
19
,15
1,6
57
IN-T
RA
CT
$3
23
,06
0$
80
,76
5$
43
6,1
31
SPEC
IFIC
PLA
N$
4,8
92
,68
7$
1,2
23
,17
2$
6,6
05
,12
8
$1
9,4
02
,16
0$
4,8
50
,54
0$
26
,19
2,9
16
No
tes: 1.
This
est
imat
e is
bas
ed o
n a
co
nce
ptu
al d
esig
n.
Ch
ange
s o
r in
crea
ses
may
occ
ur
du
e to
go
vern
ing
age
ncy
req
uir
emen
ts, o
r d
ue
to o
ther
item
s th
at m
ay
be
dis
cove
red
du
rin
g th
e fi
nal
des
ign
ph
ase
of
the
pro
ject
.
CO
NTI
NG
ENC
Y
$1
,41
8,6
41
$3
2,3
06
$4
89
,26
9
$1
,94
0,2
16
Pa
ge
9 o
f 9
3/2
9/2
01
3
Page A-10
APPENDIX 2
FISCAL IMPACT ANALYSIS TABLES
Page A-11
Tabl
e 1:
Sum
mar
y R
esul
ts o
f Fis
cal I
mpa
ct A
naly
sis
Ann
ual I
mpa
cts
on C
ity
Ent
ire S
peci
ficP
lan
Are
a(In
cl. N
CC
Futu
re P
hase
)
SP
SP
Exc
ludi
ng N
CC
Futu
re P
hase
Incl
udes
CFD
No.
200
7-1
(Pub
lic S
afet
y Se
rvic
es) R
even
ueR
even
ues
2,55
7,63
1$
2,
081,
258
$
Cos
ts
2,43
8,35
8
1,
967,
946
Net
Rev
enue
119,
274
$
11
3,31
2$
Per
cent
of R
even
ues
5%5%
Sou
rces
: City
of O
akda
le; G
oodw
in C
onsu
lting
Gro
up, I
nc.
Sier
ra P
oint
e Sp
ecifi
c Pl
an
Page A-12
Tabl
e 2:
City
Pop
ulat
ion
and
Empl
oym
ent,
2004
-201
1
Item
2004
2005
2006
2007
2008
2009
2010
2011
Res
iden
ts17
,179
17
,393
17
,759
18
,488
19
,192
19
,558
19
,854
20
,839
Jobs
6,31
3
6,17
1
5,98
6
5,80
0
5,54
8
4,54
8
4,24
3
4,96
8
Serv
ice
Popu
latio
n119
,136
19
,306
19
,615
20
,286
20
,912
20
,968
21
,169
22
,379
1 Ser
vice
pop
ulat
ion
equa
ls th
e su
m o
f res
iden
ts a
nd 0
.31
times
the
num
ber o
f job
s.
Sou
rces
: Cal
iforn
ia D
epar
tmen
t of F
inan
ce; E
mpl
oym
ent D
evel
opm
ent D
epar
tmen
t; W
illda
n Fi
nanc
ial S
ervi
ces;
Goo
dwin
Con
sulti
ng G
roup
, Inc
.
Page A-13
Tabl
e 3:
Mar
ket A
ssum
ptio
ns b
y La
nd U
se
Den
sity
Res
iden
t or W
orke
r Eq
uiva
lent
Den
sity
Sale
s Pr
ice
Use
(uni
ts/a
cre
or
FAR
)(r
esid
ents
/uni
t or w
orke
r eq
uiva
lent
/100
0 sq
ft)($
/uni
t or
$/sq
ft)
Res
iden
tial U
ses
Ver
y Lo
w D
ensi
ty R
esid
entia
l2.
2
2.78
350,
000
$
Low
Den
sity
Res
iden
tial
5.0
2.
7830
0,00
0
M
ediu
m D
ensi
ty R
esid
entia
l8.
0
2.78
240,
000
Hig
h D
ensi
ty R
esid
entia
l16
.0
2.12
150,
000
Non
-Res
iden
tial/P
ublic
/Sem
i Pub
lic U
ses
Gen
eral
Com
mer
cial
- R
etai
l10.
30
2.50
200
$
G
ener
al C
omm
erci
al -
Oth
er1
0.30
3.
3320
0
Flex
Use
/Gen
. Com
mer
cial
0.30
3.
3320
0
Offi
ce0.
30
3.33
200
P
ublic
/Sem
i Pub
lic2
0.30
32
.02
n/a
1 A
ssum
es 5
0% o
f pro
pose
d G
ener
al C
omm
erci
al u
ses
will
be
reta
il us
es a
nd th
e re
mai
ning
50%
will
be
offic
e re
late
d us
es.
2 Ass
umes
a c
omm
unity
col
lege
cam
pus
will
be
deve
lope
d an
d th
e fo
llow
ing
ratio
s to
est
imat
e w
orke
r equ
ival
ents
:
1) 5
00 s
quar
e fe
et p
er fa
culty
/sta
ff m
embe
r (47
7 fa
culty
/sta
ff), a
nd 2
) 15
stud
ents
per
facu
lty/s
taff
mem
ber (
7,15
5 st
uden
ts).
Sou
rces
: Sie
rra
Poi
nte
Spe
cific
Pla
n; W
illda
n Fi
nanc
ial S
ervi
ces;
Cal
iforn
ia C
omm
unity
Col
lege
s C
hanc
ello
r's O
ffice
; Goo
dwin
Con
sulti
ng G
roup
, Inc
.
Page A-14
Tabl
e 4:
New
Ser
vice
Pop
ulat
ion
and
Rea
l Est
ate
Dev
elop
men
t Det
ail
Entir
e Sp
ecifi
c Pl
an A
rea
(Incl
. NC
C F
utur
e Ph
ase)
SPSP
Excl
udin
g N
CC
Fut
ure
Phas
e
Use
Uni
ts o
rS
qft
Res
iden
ts o
r W
orke
r E
quiv
alen
ts1
Ass
esse
d V
alue
($
000s
)U
nits
or
Sqf
t
Res
iden
ts o
r W
orke
r E
quiv
alen
ts1
Ass
esse
d V
alue
($
000s
)
Res
iden
tial U
ses
Ver
y Lo
w D
ensi
ty R
esid
entia
l287
242
30,4
50$
8724
2
30
,450
$
Lo
w D
ensi
ty R
esid
entia
l36
31,
009
10
8,90
0
15
041
7
45
,000
M
ediu
m D
ensi
ty R
esid
entia
l23
364
8
55
,920
17
348
1
41
,520
H
igh
Den
sity
Res
iden
tial
173
367
25,9
50
173
367
25,9
50
Subt
otal
, Res
iden
tial
856
2,26
6
221,
220
$
583
1,50
7
142,
920
$
Non
-Res
iden
tial/P
ublic
/Sem
i Pub
lic U
ses
Gen
eral
Com
mer
cial
- R
etai
l18
2,42
945
6
36
,486
$
18
2,42
945
6
36
,486
$
G
ener
al C
omm
erci
al -
Oth
er18
2,42
960
8
36
,486
18
2,42
960
8
36
,486
Fl
ex U
se/G
en. C
omm
erci
al24
6,20
282
1
49
,240
24
6,20
282
1
49
,240
O
ffice
268,
678
896
53,7
36
133,
555
445
26,7
11
Pub
lic/S
emi P
ublic
238,
361
7,63
2
-
238,
361
7,63
2
-
Subt
otal
, Non
-Res
iden
tial/P
ublic
/Sem
i Pub
lic1,
118,
099
10,4
13
17
5,94
8$
98
2,97
69,
962
14
8,92
3$
TOTA
L39
7,16
8$
29
1,84
3$
2 Exc
lude
s 45
exi
stin
g un
its.
Sou
rces
: Sie
rra
Poi
nte
Spe
cific
Pla
n; C
alifo
rnia
Com
mun
ity C
olle
ges
Cha
ncel
lor's
Offi
ce; G
oodw
in C
onsu
lting
Gro
up, I
nc.
3 Ass
umes
the
follo
win
g ra
tios:
1) 5
00 s
quar
e fe
et p
er fa
culty
/sta
ff m
embe
r (47
7 fa
culty
/sta
ff), a
nd 2
) 15
stud
ents
per
facu
lty/s
taff
mem
ber (
7,15
5 st
uden
ts).
1 Ass
umes
eac
h st
uden
t is
equa
l to
one
wor
ker w
ithin
the
Pub
lic/S
emi P
ublic
land
use
cat
egor
y.
SIER
RA
PO
INTE
SPE
CIF
IC P
LAN
33
Page A-15
Tabl
e 5:
City
of O
akda
le G
ross
Exp
endi
ture
s FY
200
4-20
111
Func
tion
FY 2
003-
2004
FY 2
004-
2005
FY 2
005-
2006
FY 2
006-
2007
FY 2
007-
2008
FY 2
008-
2009
FY 2
009-
2010
FY 2
010-
2011
8 Ye
ar A
vera
ge
Gen
eral
Fun
dC
ity C
ounc
il27
,849
$
33,4
36$
27
,275
$
37,5
75$
31
,570
$
31,2
29$
22
,204
$
21,6
84$
29
,103
$
C
ity M
anag
er77
,382
106,
489
13
0,43
0
145,
548
12
4,67
2
118,
796
10
7,24
0
104,
082
11
4,33
0
Hum
an R
esou
rces
-
-
-
-
106,
409
10
3,27
3
61,7
84
58
,457
41,2
40
City
Cle
rk24
,835
31,1
92
14
,333
24,2
58
11
5,20
1
116,
159
93
,836
110,
329
66
,268
Fina
nce
Div
isio
n80
,537
160,
393
15
9,61
0
204,
657
22
8,96
8
227,
501
18
4,63
5
147,
806
17
4,26
3
City
Tre
asur
er93
4
1,
117
1,
004
1,
043
1,
043
1,
044
1,
060
1,
060
1,
038
City
Atto
rney
34,5
16
29
,098
25,7
64
39
,538
90,0
44
87
,868
88,7
84
88
,908
60,5
65
Non
-Dep
artm
enta
l36
5,70
9
375,
965
36
7,42
5
408,
778
49
4,36
8
434,
804
38
3,53
0
383,
530
40
1,76
4
Fire
Dep
artm
ent2
1,78
6,31
6
1,
918,
367
2,66
4,14
5
3,
292,
893
3,42
9,43
6
3,
517,
898
3,08
2,50
3
2,
719,
958
2,80
1,44
0
Pol
ice
Dep
artm
ent
3,18
3,95
9
3,
585,
207
3,95
9,91
4
4,
371,
233
4,63
5,01
3
4,
682,
066
4,05
4,29
6
3,
814,
990
4,03
5,83
5
P
arks
and
Com
mun
ity S
ervi
ces3
815,
160
1,
404,
541
899,
396
96
2,26
1
1,00
8,87
2
1,
040,
350
763,
530
65
8,29
8
944,
051
Pub
lic W
orks
Dep
artm
ent
684,
717
73
1,46
8
688,
552
93
9,11
7
932,
270
87
1,08
8
750,
167
27
9,46
6
734,
606
TOTA
L G
ENER
AL
FUN
D7,
081,
914
$
8,37
7,27
3$
8,
937,
848
$
10,4
26,9
01$
11,1
97,8
66$
11,2
32,0
76$
9,59
3,56
9$
8,
388,
568
$
9,40
4,50
2$
Dev
elop
men
t Ser
vice
s Fu
nd4
Pla
nnin
g38
9,16
4$
416,
178
$
51
4,81
7$
470,
867
$
50
1,30
5$
398,
258
$
36
2,85
2$
307,
890
$
42
0,16
6
Bui
ldin
g In
spec
tion
388,
489
48
1,55
7
634,
059
60
3,36
5
413,
524
40
8,26
5
364,
246
22
4,84
8
439,
794
TOTA
L D
EV. S
ERVI
CES
FU
ND
777,
653
$
89
7,73
5$
1,14
8,87
6$
1,
074,
232
$
914,
829
$
80
6,52
3$
727,
098
$
53
2,73
8$
859,
961
$
Engi
neer
ing
& P
ublic
Wor
ks F
und4
Pub
lic W
orks
Adm
in/E
ngin
eerin
g34
0,72
5
399,
710
36
7,00
1
429,
499
44
7,06
2
427,
287
61
7,15
8
577,
225
45
0,70
8
TOTA
L EN
G. &
PW
FU
ND
340,
725
$
39
9,71
0$
367,
001
$
42
9,49
9$
447,
062
$
42
7,28
7$
617,
158
$
57
7,22
5$
450,
708
$
2 Incl
udes
Fire
Ser
vice
s C
FD tr
ansf
ers
to th
e G
ener
al F
und.
In a
dditi
on, t
he C
ity h
as a
sked
that
$10
0,00
0 be
add
ed to
eac
h of
the
eigh
t ann
ual e
xpen
ditu
res.
Sou
rces
: City
of O
akda
le F
Y 2
003-
2011
Ado
pted
Bud
gets
Prio
r to
FY 2
008-
2009
, the
se tw
o fu
nds
wer
e co
mbi
ned
as th
e D
evel
opm
ent S
ervi
ces
Fund
.
Not
es:
1 Exp
endi
ture
s co
ver p
re-r
eces
sion
and
pos
t-rec
essi
on fi
scal
yea
rs, o
r FY
2004
-FY
2011
. Fig
ures
for F
Y20
04-F
Y20
09 a
re b
udge
t act
uals
; fig
ures
for F
Y20
09-2
010
are
proj
ecte
d, a
nd F
Y20
10-2
011
are
adop
ted
budg
et v
alue
s.
3 Incl
udes
Gen
eral
Fun
d tra
nsfe
rs o
ut to
the
swim
min
g po
ol, c
omm
unity
cen
ter,
and
seni
or c
ente
r.4 C
ity fu
nds
all p
lann
ing,
bui
ldin
g, a
nd e
ngin
eerin
g de
velo
pmen
t act
ivity
from
sep
arat
e en
terp
rise
fund
s to
cle
arly
acc
ount
for t
he u
se o
f fun
ds p
aid
for d
evel
opm
ent-r
elat
ed s
ervi
ces
and
to s
how
if a
nd w
hen
Gen
eral
Fun
d su
ppor
t is
need
ed fo
r thi
s ac
tivity
.
Page A-16
Tabl
e 6:
City
of O
akda
le E
xpen
ditu
res
Per P
erso
n Se
rved
FY
2004
-201
11
Res
iden
t
Wor
ker
Equ
ival
ent
(WE
)R
esid
ent
WE
Res
iden
tW
ER
esid
ent
WE
Res
iden
tW
ER
esid
ent
WE
Res
iden
tW
ER
esid
ent
WE
Res
iden
tW
ER
esid
ent
WE
Gen
eral
Fun
dC
ity C
ounc
il1.
00
0.
31
1.46
$
0.
45$
1.73
$
0.
54$
1.39
$
0.
43$
1.85
$
0.
57$
1.51
$
0.
47$
1.49
$
0.
46$
1.05
$
0.
33$
0.97
$
0.
30$
1.43
$
0.
44$
City
Man
ager
1.00
0.31
4.
04
1.25
5.
52
1.71
6.
65
2.06
7.
17
2.22
5.
96
1.85
5.
67
1.76
5.
07
1.57
4.
65
1.44
5.
59
1.73
H
uman
Res
ourc
es1.
00
0.
31
-
-
-
-
-
-
-
-
5.09
1.
58
4.93
1.
53
2.92
0.
90
2.61
0.
81
1.94
0.
60
City
Cle
rk1.
00
0.
31
1.30
0.
40
1.62
0.
50
0.73
0.
23
1.20
0.
37
5.51
1.
71
5.54
1.
72
4.43
1.
37
4.93
1.
53
3.16
0.
98
Fina
nce
Div
isio
n1.
00
0.
31
4.21
1.
30
8.31
2.
58
8.14
2.
52
10.0
9
3.
13
10.9
5
3.
39
10.8
5
3.
36
8.72
2.
70
6.60
2.
05
8.48
2.
63
City
Tre
asur
er1.
00
0.
31
0.05
0.
02
0.06
0.
02
0.05
0.
02
0.05
0.
02
0.05
0.
02
0.05
0.
02
0.05
0.
02
0.05
0.
01
0.05
0.
02
City
Atto
rney
1.00
0.31
1.
80
0.56
1.
51
0.47
1.
31
0.41
1.
95
0.60
4.
31
1.33
4.
19
1.30
4.
19
1.30
3.
97
1.23
2.
90
0.90
N
on-D
epar
tmen
tal
1.00
0.31
19
.11
5.92
19
.47
6.04
18
.73
5.81
20
.15
6.25
23
.64
7.33
20
.74
6.43
18
.12
5.62
17
.14
5.31
19
.64
6.09
Fire
Dep
artm
ent2
1.00
0.31
93
.35
28.9
4
99
.37
30.8
0
13
5.82
42
.11
162.
32
50.3
2
16
3.99
50
.84
167.
78
52.0
1
14
5.61
45
.14
121.
54
37.6
8
13
6.22
42
.23
Pol
ice
Dep
artm
ent
1.00
0.31
16
6.39
51
.58
185.
70
57.5
7
20
1.89
62
.58
215.
48
66.8
0
22
1.64
68
.71
223.
30
69.2
2
19
1.52
59
.37
170.
47
52.8
5
19
7.05
61
.08
Par
ks a
nd C
omm
unity
Ser
vice
s31.
00
0.
31
42.6
0
13
.21
72.7
5
22
.55
45.8
5
14
.21
47.4
3
14
.70
48.2
4
14
.96
49.6
2
15
.38
36.0
7
11
.18
29.4
2
9.
12
46.5
0
14
.41
Pub
lic W
orks
Dep
artm
ent
1.00
0.31
35
.78
11.0
9
37
.89
11
.75
35.1
0
10.8
8
46
.29
14
.35
44.5
8
13.8
2
41
.54
12
.88
35.4
4
10.9
9
12
.49
3.
87
36
.14
11
.20
TOTA
L EX
PEN
DIT
UR
ES37
0.08
$ 11
4.73
$
433.
92$
134.
52$
455.
67$
141.
26$
513.
99$
159.
34$
535.
48$
166.
00$
53
5.68
$16
6.06
$ 45
3.18
$14
0.49
$ 37
4.84
$11
6.20
$ 45
9.11
$14
2.32
$
Dev
elop
men
t Ser
vice
s Fu
nd4
Pla
nnin
g1.
00
0.
31
20.3
4
6.
30
21.5
6
6.
68
26.2
5
8.
14
23.2
1
7.
20
23.9
7
7.
43
18.9
9
5.
89
17.1
4
5.
31
13.7
6
4.
26
20.6
5
6.
40
Bui
ldin
g In
spec
tion
1.00
0.31
20
.30
6.29
24
.94
7.
73
32
.33
10
.02
29.7
4
9.22
19.7
7
6.13
19
.47
6.
04
17
.21
5.
33
10
.05
3.
11
21
.73
6.
74
TOTA
L D
EV. S
ERVI
CES
FU
ND
40.6
4$
12
.60
$
46.5
0$
14
.42
$
58.5
7$
18
.16
$
52.9
5$
16
.42
$
43.7
5$
13
.56
$
38.4
6$
11
.92
$
34.3
5$
10
.65
$
23.8
1$
7.
38$
42.3
8$
13
.14
$
Engi
neer
ing
& P
ublic
Wor
ks F
und4
Pub
lic W
orks
Adm
in/E
ngin
eerin
g1.
00
0.
31
17.8
1
5.
52
20.7
0
6.42
18.7
1
5.80
21.1
7
6.56
21.3
8
6.63
20
.38
6.
32
29
.15
9.
04
25
.79
8.
00
21
.89
6.
78
TOTA
L EN
G. &
PW
FU
ND
17.8
1$
5.
52$
20.7
0$
6.
42$
18.7
1$
5.
80$
21.1
7$
6.
56$
21.3
8$
6.
63$
20.3
8$
6.
32$
29.1
5$
9.
04$
25.7
9$
8.
00$
21.8
9$
6.
78$
2 Incl
udes
Fire
Ser
vice
s C
FD tr
ansf
ers
to th
e G
ener
al F
und.
4 City
fund
s al
l pla
nnin
g, b
uild
ing,
and
eng
inee
ring
deve
lopm
ent a
ctiv
ity fr
om s
epar
ate
ente
rpris
e fu
nds
to c
lear
ly a
ccou
nt fo
r the
use
of f
unds
pai
d fo
r dev
elop
men
t-rel
ated
ser
vice
s an
d to
sho
w if
and
whe
n G
ener
al F
und
supp
ort i
s ne
eded
for t
his
activ
ity.
Sou
rces
: City
of O
akda
le F
Y 2
003-
2011
Ado
pted
Bud
gets
Prio
r to
FY 2
008-
2009
, the
se tw
o fu
nds
wer
e co
mbi
ned
as th
e D
evel
opm
ent S
ervi
ces
Fund
.
8 Ye
ar A
vera
ge
3 Incl
udes
Gen
eral
Fun
d tra
nsfe
rs o
ut to
the
swim
min
g po
ol, c
omm
unity
cen
ter,
and
seni
or c
ente
r.
1 Exp
endi
ture
s co
ver p
re-r
eces
sion
and
pos
t-rec
essi
on fi
scal
yea
rs, o
r FY
2004
-FY
2011
. Cos
ts p
er c
apita
repr
esen
t the
ave
rage
cos
ts o
f ser
vice
per
cap
ita fo
r FY
2004
-FY
2011
. Fig
ures
for F
Y20
04-F
Y20
09 a
re b
udge
t act
uals
; fig
ures
for F
Y20
09-2
010
are
proj
ecte
d, a
nd F
Y20
10-2
011
are
adop
ted
budg
et
Not
es:
FY 2
005-
2006
FY 2
004-
2005
FY 2
003-
2004
FY 2
010-
2011
Func
tion
FY 2
009-
2010
Wei
ghtin
g Fa
ctor
sFY
200
6-20
07FY
200
7-20
08FY
200
8-20
09
Page A-17
Table 7: Fiscal Impacts of New Development
Annual Impacts on City
Entire SpecificPlan Area(Incl. NCC
Future Phase)
SPSPExcluding NCCFuture Phase
RevenuesProperty Taxes 336,579$ 247,322$ Property Tax in Lieu of VLF 301,847 221,801 CFD No. 2007-1 (Public Safety Services) 360,598 237,287 Sales and Use Tax 518,688 511,550 Public Safety Sales Tax 976 962 Gas Taxes 39,149 26,036 Hotel Motel Tax 58,413 48,857 Property Transfer Tax 17,000 12,000 Business License Fee1 90,909 78,324 Franchise Fees and Other Taxes 184,209 154,073 Licenses & Permits 4,719 3,947 Fines, Forfeitures & Penalties 55,317 46,267 Other Intergovernmental 83,735 70,036 Charges for Services 71,527 59,825 Other Revenue 20,469 17,120 Transfers In 58,699 49,096 Dev. Services Fund: Revenues 222,081 185,749 Eng. & PW Fund: Revenues 132,718 111,005 Total Revenues 2,557,631$ 2,081,258$
Costs City Council 7,861$ 6,575$ City Manager 30,717 25,692 Human Resources 10,675 8,929 City Clerk 17,341 14,504 Finance Division 46,609 38,984 City Treasurer 279 233 City Attorney 15,958 13,347 Non-Departmental 107,889 90,239 Fire Department 748,413 625,975 Police Department2 645,526 468,417 Parks and Community Services Department 255,460 213,667 Public Works Department 198,552 166,069 Dev. Services Fund: Planning 113,463 94,900 Dev. Services Fund: Building Inspection 119,366 99,838 Eng. & PW Fund: PW Admin/Engineering 120,247 100,575 Total Costs 2,438,358$ 1,967,946$
Net Revenue 119,274$ 113,312$ Percent of Revenues 5% 5%
Without CFD No. 2007-1 (Public Safety Services)Revenues
CFD No. 2007-1 (Public Safety Services) (360,598) (237,287)
Net Revenue (241,324)$ (123,975)$ Percent of Revenues (9%) (6%)
Notes:1Business license revenue is estimated based on the number of new jobs. Worker equivalents associated with students at the proposed community college are not factored into this calculation.2Police expenditures are estimated based on the number of new residents and jobs. Worker equivalents associated with students at the proposed community college are not factored into this calculation.
Sources: City of Oakdale; Goodwin Consulting Group, Inc.
Sierra Pointe Specific Plan
Page A-18
Tabl
e A
1: C
ity o
f Oak
dale
Gro
ss R
even
ues
FY 2
004-
2011
1
Rev
enue
by
Type
FY 2
003-
2004
FY 2
004-
2005
FY 2
005-
2006
FY 2
006-
2007
FY 2
007-
2008
FY 2
008-
2009
FY 2
009-
2010
FY 2
010-
2011
8 Ye
ar A
vera
ge
GE
NE
RA
L FU
ND
Taxe
sP
rope
rty T
axes
931,
882
$
1,
046,
390
$
1,
457,
812
$
1,
731,
596
$
1,
802,
277
$
1,
606,
724
$
1,
430,
300
$
1,
390,
500
$
1,
424,
685
$
Pro
perty
Tax
in L
ieu
of V
LF-
-
1,18
4,85
0
1,39
1,58
2
1,54
5,24
9
1,34
1,62
9
1,28
4,30
0
1,24
5,70
0
999,
164
S
ales
& U
se T
axes
3,05
4,38
1
3,
193,
359
3,
184,
441
3,
299,
160
3,
061,
197
2,
880,
873
2,
355,
479
2,
319,
000
2,
918,
486
Hot
el M
otel
Tax
188,
156
204,
937
231,
199
249,
251
248,
781
215,
000
200,
000
200,
000
217,
166
P
rope
rty T
rans
fer T
ax94
,389
243,
971
261,
656
126,
507
113,
129
82,0
00
52
,000
52,0
00
12
8,20
7
Bus
ines
s Li
cens
e Fe
e11
3,93
5
14
4,16
5
13
6,56
4
17
6,74
8
14
8,15
1
16
5,00
0
15
0,00
0
15
0,00
0
14
8,07
0
Fran
chis
e Fe
es a
nd O
ther
Tax
es59
3,44
6
53
5,40
5
62
5,91
7
66
4,05
0
76
9,40
1
78
1,00
0
76
1,00
0
78
0,00
0
68
8,77
7
Subt
otal
, Ta
xes
4,97
6,18
9$
5,
368,
227
$
7,
082,
439
$
7,
638,
894
$
7,
688,
185
$
7,
072,
226
$
6,
233,
079
$
6,
137,
200
$
6,
524,
555
$
Lice
nses
& P
erm
its12
,530
$
10,4
19$
10
,580
$
9,05
7$
12,1
09$
11
,000
$
40,0
00$
38
,000
$
17,9
62$
Fine
s, F
orfe
iture
s &
Pen
altie
s13
4,25
9$
150,
756
$
176,
357
$
228,
855
$
219,
690
$
234,
500
$
258,
500
$
258,
500
$
207,
677
$
Inte
rgov
ernm
enta
l Rev
enue
sM
otor
Veh
icle
In-L
ieu
743,
877
$
1,
097,
204
$
10
3,66
5$
11
2,06
0$
94
,615
$
112,
000
$
50,0
00$
50
,000
$
295,
428
$
O
ther
Inte
rgov
ernm
enta
l20
4,05
4
45
8,00
5
25
8,02
1
27
5,93
0
33
1,25
0
38
9,35
0
29
2,07
8
28
1,49
5
31
1,27
3
Subt
otal
, Int
ergo
vern
men
tal
947,
931
$
1,
555,
209
$
36
1,68
6$
38
7,99
0$
42
5,86
5$
50
1,35
0$
34
2,07
8$
33
1,49
5$
60
6,70
1$
Cha
rges
for S
ervi
ces
182,
549
$
17
3,81
3$
21
9,36
0$
30
9,37
0$
25
5,15
3$
31
3,52
4$
34
7,44
3$
34
9,32
0$
26
8,81
7$
Oth
er R
even
ue11
6,43
1$
94,4
30$
67
,879
$
76,5
51$
10
8,83
9$
87
,200
$
27,0
00$
21
,400
$
74,9
66$
Tran
sfer
s In
259
5,65
2$
77,0
00$
10
3,54
0$
44
,000
$
139,
000
$
231,
000
$
349,
988
$
195,
000
$
216,
898
$
TOTA
L G
EN F
UN
D R
EVEN
UES
6,96
5,54
1$
7,
429,
854
$
8,
021,
841
$
8,
694,
717
$
8,
848,
841
$
8,
450,
800
$
7,
598,
088
$
7,
330,
915
$
7,
917,
575
$
PU
BLI
C S
AFE
TY T
AX
FU
ND
Pub
lic S
afet
y S
ales
Tax
111,
754
$
15
1,99
5$
15
0,21
7$
16
8,92
0$
16
2,26
0$
11
5,53
5$
11
3,00
0$
11
3,00
0$
13
5,83
5$
Inve
stm
ent E
arni
ngs
13
511
2,01
9
2,57
9
1,68
8
204
2,00
0
2,00
0
1,37
7
Su
btot
al, P
ublic
Saf
ety
Fund
111,
767
$
15
2,50
6$
15
2,23
6$
17
1,49
9$
16
3,94
8$
11
5,73
9$
11
5,00
0$
11
5,00
0$
13
7,21
2$
GA
S T
AX
FU
ND
Gas
Tax
es35
0,92
9$
324,
893
$
325,
126
$
463,
906
$
340,
006
$
165,
947
$
300,
000
$
300,
000
$
321,
351
$
O
ther
Rev
enue
s1,
663
1,
871
83
,378
6,74
7
4,45
2
315,
805
1,00
0
1,00
0
51,9
90
Su
btot
al, G
as T
ax F
und
352,
592
$
32
6,76
4$
40
8,50
4$
47
0,65
3$
34
4,45
8$
48
1,75
2$
30
1,00
0$
30
1,00
0$
37
3,34
0$
DE
VE
LOP
ME
NT
SE
RV
ICE
S F
UN
DR
even
ues
964,
064
$
1,
515,
961
$
1,
372,
273
$
96
7,84
7
51
7,02
2
35
2,55
7
31
1,60
0
45
9,80
0
80
7,64
1
Subt
otal
, Dev
elop
men
t Ser
vice
s Fu
nd96
4,06
4$
1,51
5,96
1$
1,37
2,27
3$
967,
847
$
517,
022
$
352,
557
$
311,
600
$
459,
800
$
807,
641
$
EN
GIN
EE
RIN
G &
PU
BLI
C W
OR
KS
FU
ND
Rev
enue
s78
,368
$
815,
282
$
392,
011
$
1,44
8,07
5
339,
522
195,
396
320,
200
333,
000
490,
232
Su
btot
al, E
ng. &
PW
Fun
d78
,368
$
815,
282
$
392,
011
$
1,44
8,07
5$
339,
522
$
195,
396
$
320,
200
$
333,
000
$
490,
232
$
1 Exp
endi
ture
s co
ver p
re-r
eces
sion
and
pos
t-rec
essi
on fi
scal
yea
rs, o
r FY
2004
-FY
2011
. Fig
ures
for F
Y20
04-F
Y20
09 a
re b
udge
t act
uals
; fig
ures
for F
Y20
09-2
010
are
proj
ecte
d, a
nd F
Y20
10-2
011
are
adop
ted
budg
et v
alue
s.2 E
xclu
des
trans
fers
in fr
om th
e P
ublic
Saf
ety
Tax
Fund
, Gas
Tax
Fun
d, C
FD N
o. 2
003-
1 (F
ire P
rote
ctio
n S
ervi
ces)
, and
CFD
No.
200
7-1
(Pub
lic S
afet
y S
ervi
ces)
.
Sou
rces
: City
of O
akda
le F
Y 2
004-
2011
Ado
pted
Bud
gets
.
Not
es:
Page A-19
Tabl
e A
2: C
ity o
f Oak
dale
Gro
ss R
even
ues
Per C
apita
FY
2004
-201
11
Gen
Fun
d R
even
ue b
y Ty
peR
esid
ent
Wor
ker
Equ
ival
ent
(WE
)R
esid
ent
WE
Res
iden
tW
ER
esid
ent
WE
Res
iden
tW
E
GE
NE
RA
L FU
ND
Taxe
sP
rope
rty T
axes
--
----
----
Est
imat
ed in
Cas
e S
tudy
----
----
--P
rope
rty T
ax in
Lie
u of
VLF
----
----
--E
stim
ated
in C
ase
Stu
dy--
----
----
Sal
es a
nd U
se T
ax--
----
----
Est
imat
ed in
Cas
e S
tudy
----
----
--H
otel
Mot
el T
ax1.
00
0.
31
9.
83$
3.05
$
10
.62
$
3.29
$
11
.79
$
3.65
$
12
.29
$
3.81
$
P
rope
rty T
rans
fer T
ax--
----
----
Est
imat
ed in
Cas
e S
tudy
----
----
--B
usin
ess
Lice
nse
Fee
n/a
1.00
-$
18
.05
$
-$
23
.36
$
-$
22.8
1$
-
$
30.4
7$
Fr
anch
ise
Fees
and
Oth
er T
axes
1.00
0.31
31.0
1$
9.61
$
27
.73
$
8.60
$
31
.91
$
9.89
$
32
.73
$
10.1
5$
Su
btot
al,
Taxe
s40
.84
$
30.7
1$
38
.35
$
35.2
5$
43
.70
$
36.3
6$
45
.02
$
44.4
3$
Lice
nses
& P
erm
its1.
00
0.
31
0.
65$
0.20
$
0.
54$
0.17
$
0.
54$
0.17
$
0.
45$
0.14
$
Fine
s, F
orfe
iture
s &
Pen
altie
s1.
00
0.
31
7.
02$
2.17
$
7.
81$
2.42
$
8.
99$
2.79
$
11
.28
$
3.50
$
Inte
rgov
ernm
enta
l Rev
enue
sV
ehic
le In
-Lie
u Fe
es1.
00
0.
31
--
----
----
Est
imat
ed in
Cas
e S
tudy
----
----
--O
ther
Inte
rgov
ernm
enta
l1.
00
0.
31
10
.66
$
3.
31$
23.7
2$
7.
35$
13.1
5$
4.
08$
13.6
0$
4.
22$
Subt
otal
, Int
ergo
vern
men
tal
10.6
6$
3.
31$
23
.72
$
7.35
$
13.1
5$
4.
08$
13.6
0$
4.
22$
Cha
rges
for S
ervi
ces
1.00
0.31
9.54
$
2.
96$
9.00
$
2.
79$
11.1
8$
3.
47$
15.2
5$
4.
73$
Oth
er R
even
ue1.
00
0.
31
6.
08$
1.89
$
4.
89$
1.52
$
3.
46$
1.07
$
3.
77$
1.17
$
Tran
sfer
s In
1.00
0.31
31.1
3$
9.
65$
3.
99$
1.24
$
5.28
$
1.64
$
2.
17$
0.67
$
TOTA
L G
ENER
AL
FUN
D10
5.93
$
50.8
9$
88
.30
$
50.7
4$
86
.31
$
49.5
7$
91
.54
$
58.8
5$
PU
BLI
C S
AFE
TY T
AX
FU
ND
Pub
lic S
afet
y S
ales
Tax
----
----
--E
stim
ated
in C
ase
Stu
dy--
----
----
GA
S T
AX
FU
ND
Gas
Tax
es1.
00
n/
a20
.43
$
-
$
18
.68
$
-$
18.3
1$
-
$
25.0
9$
-
$
CFD
NO
. 200
7-1
(PU
BLI
C S
AFE
TY S
ER
VIC
ES
)S
peci
al T
axes
----
----
--E
stim
ated
in C
ase
Stu
dy--
----
----
DE
VE
LOP
ME
NT
SE
RV
ICE
S F
UN
DR
even
ues
1.00
0.31
50.3
8$
15.6
2$
78
.52
$
24.3
4$
69
.96
$
21.6
9$
47
.71
$
14.7
9$
EN
GIN
EE
RIN
G &
PU
BLI
C W
OR
KS
FU
ND
Rev
enue
s1.
00
0.
31
4.
10$
1.27
$
42
.23
$
13.0
9$
19
.99
$
6.20
$
71
.38
$
22.1
3$
Sou
rces
: City
of O
akda
le F
Y 2
004-
2011
Ado
pted
Bud
gets
.
FY 2
005-
2006
Wei
ghtin
g Fa
ctor
s
1 Cos
ts p
er c
apita
repr
esen
t the
ave
rage
cos
ts o
f ser
vice
per
cap
ita fo
r FY
2004
-FY
2011
. Fig
ures
for F
Y20
04-F
Y20
09 a
re b
udge
t act
uals
; fig
ures
for F
Y20
09-2
010
are
proj
ecte
d, a
nd F
Y20
10-2
011
are
adop
ted
budg
et v
alue
s.
FY 2
003-
2004
FY 2
004-
2005
Not
e:
FY 2
006-
2007
Page A-20
Tabl
e A
2, c
ont.:
City
of O
akda
le G
ross
Rev
enue
s Pe
r Cap
ita F
Y 20
04-2
0111
Gen
Fun
d R
even
ue b
y Ty
peR
esid
ent
WE
Res
iden
tW
ER
esid
ent
WE
Res
iden
tW
ER
esid
ent
WE
GE
NE
RA
L FU
ND
Taxe
sP
rope
rty T
axes
--
----
----
Est
imat
ed in
Cas
e S
tudy
----
----
--P
rope
rty T
ax in
Lie
u of
VLF
----
----
--E
stim
ated
in C
ase
Stu
dy--
----
----
Sal
es a
nd U
se T
ax--
----
----
Est
imat
ed in
Cas
e S
tudy
----
----
--H
otel
Mot
el T
ax11
.90
$
3.69
$
10
.25
$
3.
18$
9.45
$
2.
93$
8.94
$
2.
77$
10.6
3$
3.
30$
Pro
perty
Tra
nsfe
r Tax
----
----
--E
stim
ated
in C
ase
Stu
dy--
----
----
Bus
ines
s Li
cens
e Fe
e-
$
26.7
0$
-
$
36.2
8$
-
$
35.3
5$
-
$
30.1
9$
-
$
27
.90
$
Fran
chis
e Fe
es a
nd O
ther
Tax
es36
.79
$
11.4
1$
37
.25
$
11
.55
$
35.9
5$
11
.14
$
34.8
5$
10
.80
$
33.5
3$
10
.39
$
Subt
otal
, Ta
xes
48.6
9$
41
.80
$
47.5
0$
51
.01
$
45.4
0$
49
.43
$
43.7
9$
43
.77
$
44.1
6$
41
.59
$
Lice
nses
& P
erm
its0.
58$
0.18
$
0.
52$
0.16
$
1.
89$
0.59
$
1.
70$
0.53
$
0.
86$
0.27
$
Fine
s, F
orfe
iture
s &
Pen
altie
s10
.51
$
3.26
$
11
.18
$
3.
47$
12.2
1$
3.
79$
11.5
5$
3.
58$
10.0
7$
3.
12$
Inte
rgov
ernm
enta
l Rev
enue
sV
ehic
le In
-Lie
u Fe
es--
----
----
Est
imat
ed in
Cas
e S
tudy
----
----
--O
ther
Inte
rgov
ernm
enta
l15
.84
$
4.91
$
18
.57
$
5.
76$
13.8
0$
4.
28$
12.5
8$
3.
90$
15.2
4$
4.
72$
Subt
otal
, Int
ergo
vern
men
tal
15.8
4$
4.
91$
18
.57
$
5.76
$
13
.80
$
4.28
$
12.5
8$
3.
90$
15
.24
$
4.72
$
Cha
rges
for S
ervi
ces
12.2
0$
3.
78$
14.9
5$
4.64
$
16
.41
$
5.09
$
15
.61
$
4.84
$
13
.02
$
4.04
$
Oth
er R
even
ue5.
20$
1.61
$
4.
16$
1.29
$
1.
28$
0.40
$
0.
96$
0.30
$
3.
73$
1.15
$
6.65
$
2.
06$
11
.02
$
3.42
$
16
.53
$
5.13
$
8.71
$
2.
70$
10
.68
$
3.31
$
TOTA
L G
ENER
AL
FUN
D99
.67
$
57.6
0$
10
7.91
$
69.7
3$
10
7.51
$
68
.68
$
94.9
0$
59
.61
$
97.7
6$
58
.21
$
PU
BLI
C S
AFE
TY T
AX
FU
ND
Pub
lic S
afet
y S
ales
Tax
----
----
--E
stim
ated
in C
ase
Stu
dy--
----
----
GA
S T
AX
FU
ND
Gas
Tax
es17
.72
$
-$
8.48
$
-
$
15.1
1$
-
$
14
.40
$
-$
17.2
8$
-
$
CFD
NO
. 200
7-1
(PU
BLI
C S
AFE
TY S
ER
VIC
ES
)S
peci
al T
axes
----
----
--E
stim
ated
in C
ase
Stu
dy--
----
----
DE
VE
LOP
ME
NT
SE
RV
ICE
S F
UN
DR
even
ues
24.7
2$
7.
66$
16.8
1$
5.21
$
14
.72
$
4.56
$
20
.55
$
6.37
$
40
.42
$
12.5
3$
EN
GIN
EE
RIN
G &
PU
BLI
C W
OR
KS
FU
ND
Rev
enue
s16
.24
$
5.03
$
9.
32$
2.89
$
15
.13
$
4.69
$
14
.88
$
4.61
$
24
.16
$
7.49
$
Sou
rces
: City
of O
akda
le F
Y 2
004-
2011
Ado
pted
Bud
gets
.
1 Cos
ts p
er c
apita
repr
esen
t the
ave
rage
cos
ts o
f ser
vice
per
cap
ita fo
r FY
2004
-FY
2011
. Fig
ures
for F
Y20
04-F
Y20
09 a
re b
udge
t act
uals
; fig
ures
for F
Y20
09-2
010
are
proj
ecte
d, a
nd F
Y20
10-2
011
are
adop
ted
budg
et v
alue
s.
8 Ye
ar A
vera
ge
Not
e:
FY 2
007-
2008
FY 2
008-
2009
FY 2
009-
2010
FY 2
010-
2011
Page A-21
Tabl
e A
3: P
rope
rty
Tax
Allo
catio
n, E
stim
ated
Allo
catio
n08
4-01
0P
re-A
nnex
atio
n08
4-01
0P
ost-A
nnex
atio
nA
nnex
atio
n N
otes
ERA
F Sh
ift
Age
ncy
Pre-
ERA
FC
ount
y G
ener
al F
und
0.26
6784
0.18
6749
Cou
nty
split
s G
en F
und
with
City
; Cou
nty
keep
s 70
%
Cou
nty
Sup
erin
tend
ent o
f Sch
ools
0.00
4371
0.00
4371
Cou
nty
Fire
Ser
vice
0.00
6255
0.00
6255
City
of O
akda
le G
ener
al F
und
0.00
0000
0.12
3090
City
sha
res
30%
Cou
nty
Gen
Fun
d &
10
0% O
akda
le F
ire
Oak
dale
Fire
Dis
trict
0.04
3055
0.00
0000
Oak
dale
Fire
tran
sfer
s to
City
Eas
tsid
e M
osqu
ito A
bate
men
t0.
0090
080.
0090
08O
akda
le Ir
rigat
ion
0.07
2932
0.07
2932
Oak
dale
Uni
fied
Sch
ool D
istri
ct0.
4593
400.
4593
40Y
osem
ite C
omm
unity
Col
lege
0.07
8117
0.07
8117
Cou
nty
Sch
ools
0.02
8271
0.02
8271
Sch
ools
-Equ
aliz
atio
n A
id0.
0203
070.
0203
07S
choo
ls-T
uitio
n0.
0115
600.
0115
60O
akda
le R
edev
elop
men
t0.
0000
000.
0000
00TO
TAL
1.00
0000
1.00
0000
Age
ncy
Post
-ER
AF
Cou
nty
Gen
eral
Fun
d0.
1202
660.
0841
86-5
4.92
%C
ount
y S
uper
inte
nden
t of S
choo
ls0.
0043
710.
0043
710.
00%
Cou
nty
Fire
Ser
vice
0.00
5803
0.00
5803
-7.2
3%C
ity o
f Oak
dale
Gen
eral
Fun
d0.
0000
000.
0847
45-3
1.15
%O
akda
le F
ire D
istri
ct0.
0315
280.
0000
00-2
6.77
%E
asts
ide
Mos
quito
Aba
tem
ent
0.00
8163
0.00
8163
-9.3
8%O
akda
le Ir
rigat
ion
0.07
2932
0.07
2932
0.00
%O
akda
le U
nifie
d S
choo
l Dis
trict
0.45
9340
0.45
9340
0.00
%Y
osem
ite C
omm
unity
Col
lege
0.07
8117
0.07
8117
0.00
%C
ount
y S
choo
ls0.
0282
710.
0282
710.
00%
Sch
ools
-Equ
aliz
atio
n A
id0.
0203
070.
0203
070.
00%
Sch
ools
-Tui
tion
0.01
1560
0.01
1560
0.00
%O
akda
le R
edev
elop
men
t0.
0000
000.
0000
000.
00%
ER
AF
0.15
9342
0.14
2205
TOTA
L1.
0000
001.
0000
00
Sou
rce:
Sta
nisl
aus
Cou
nty
Aud
itor-
Con
trolle
r
Page A-22
Tabl
e A
4: C
FD N
o. 2
007-
1 (P
ublic
Saf
ety
Serv
ices
) Rev
enue
Use
Tax
Rat
eU
nits
Ann
ual
Rev
enue
sU
nits
Ann
ual
Rev
enue
s
Res
iden
tial U
ses
Ver
y Lo
w D
ensi
ty R
esid
entia
l$4
51.6
987
39,2
97$
8739
,297
$
Lo
w D
ensi
ty R
esid
entia
l$4
51.6
936
316
3,96
3
15
067
,754
M
ediu
m D
ensi
ty R
esid
entia
l/Fle
x U
se$4
51.6
923
310
5,24
4
17
378
,142
H
igh
Den
sity
Res
iden
tial
$301
.12
173
52,0
94
173
52,0
94
Tota
l85
636
0,59
8$
58
323
7,28
7$
Sou
rce:
City
of O
akda
le
Entir
e Sp
ecifi
c Pl
an A
rea
(Incl
. NC
C F
utur
e Ph
ase)
SPSP
Excl
udin
g N
CC
Fut
ure
Sier
ra P
oint
e Sp
ecifi
c Pl
an
Page A-23
Tabl
e A
5: S
ales
and
Use
Tax
Ass
umpt
ions
Bas
ic S
ales
Tax
Rat
e (in
clud
es p
rope
rty ta
x in
-lieu
of s
ales
tax)
1.00
%C
ount
ywid
e an
d S
tate
wid
e P
oole
d S
ales
Tax
Rev
enue
as
a P
erce
ntag
e of
Bas
ic S
ales
Tax
Rat
e11
.21%
Cou
nty'
s S
hare
of O
akda
le's
Sal
es T
ax R
even
ue5.
00%
Pub
lic S
afet
y (P
rop.
172
) Sal
es T
ax R
ate
0.50
%P
erce
nt o
f Pub
lic S
afet
y S
ales
Tax
Rev
enue
Allo
cate
d to
City
0.40
%
Taxa
ble
Sal
esG
ener
al C
omm
erci
al -
Ret
ail (
per I
mpr
oved
Squ
are
Foot
)$2
50G
ener
al C
omm
erci
al -
Oth
er (p
er Im
prov
ed S
quar
e Fo
ot)
$5Fl
ex U
se/G
en. C
omm
erci
al (p
er Im
prov
ed S
quar
e Fo
ot)
$5O
ffice
(per
Impr
oved
Squ
are
Foot
)$5
Sou
rces
: City
of O
akda
le; C
ount
y of
Sta
nisl
aus;
Sta
te B
oard
of E
qual
izat
ion;
ULI
; Goo
dwin
Con
sulti
ng G
roup
, Inc
.
Page A-24
Tabl
e A
6: S
ales
Tax
Ana
lysi
s
Ent
ire S
peci
ficP
lan
Are
a(In
cl. N
CC
Futu
re P
hase
)
SP
SP
Exc
ludi
ng N
CC
Futu
re P
hase
Non
-Res
iden
tial T
axab
le S
ales
Gen
eral
Com
mer
cial
- R
etai
l$4
5,60
7,25
0$4
5,60
7,25
0G
ener
al C
omm
erci
al -
Oth
er$9
12,1
45$9
12,1
45Fl
ex U
se/G
en. C
omm
erci
al$1
,231
,010
$1,2
31,0
10O
ffice
$1,3
43,3
90$6
67,7
75To
tal T
axab
le S
ales
$49,
093,
795
$48,
418,
180
Dire
ct S
ales
and
Use
Tax
$466
,391
$459
,973
Cou
ntyw
ide
and
Stat
ewid
e Po
oled
Sal
es T
ax$5
2,29
7$5
1,57
7Pu
blic
Saf
ety
(Pro
p. 1
72) S
ales
Tax
$976
$962
Sou
rce:
Goo
dwin
Con
sulti
ng G
roup
, Inc
.
Sier
ra P
oint
e Sp
ecifi
c Pl
an
Page A-25
Tabl
e A
7: P
rope
rty
Tran
sfer
Tax
Rev
enue
Item
Ent
ire S
peci
ficP
lan
Are
a(In
cl. N
CC
Futu
re P
hase
)
SP
SP
Exc
ludi
ng N
CC
Futu
re P
hase
Tota
l Ass
esse
d V
alue
(Res
iden
tial)
A22
1,22
0,00
0$
142,
920,
000
$
A
vera
ge P
rope
rty H
oldi
ng P
erio
d (y
ears
)B
10
10
C =
A /
B22
,122
,000
$
14,2
92,0
00$
Tota
l Ass
esse
d V
alue
(Non
-Res
iden
tial)
D17
5,94
7,60
0$
148,
923,
000
$
A
vera
ge P
rope
rty H
oldi
ng P
erio
d (y
ears
)E
20
20
F =
D /
E8,
797,
380
$
7,44
6,15
0$
Ann
ual A
ppra
ised
Val
ue o
f Tra
nsfe
rred
Pro
perty
G =
C +
F30
,919
,380
$
21,7
38,1
50$
P
rope
rty T
rans
fer T
ax R
ate
- City
Sha
re1
H0.
055%
0.05
5%
Prop
erty
Tra
nsfe
r Tax
Rev
enue
, Ann
ual
I = G
x H
17,0
00$
12
,000
$
Not
e: T
otal
s ha
ve b
een
roun
ded.
Sou
rces
: City
of O
akda
le; G
oodw
in C
onsu
lting
Gro
up, I
nc.
1 P
rope
rty T
rans
fer T
ax ra
te is
$0.
55 p
er $
500
sale
s va
lue.
Rev
enue
is s
plit
even
ly b
etw
een
City
and
Cou
nty.
Thi
s re
sults
in
reve
nue
to th
e C
ity o
f 0.0
55 p
erce
nt o
f sal
es p
rice.
Sier
ra P
oint
e Sp
ecifi
c Pl
an
Page A-26
Tabl
e A
8: P
rope
rty
Tax
In-L
ieu
of V
ehic
le L
icen
se F
ee R
even
ues
Ent
ire S
peci
ficP
lan
Are
a(In
cl. N
CC
Futu
re P
hase
)
SP
SP
Exc
ludi
ng N
CC
Futu
re P
hase
Pro
perty
Tax
In-L
ieu
of V
LFTo
tal E
xist
ing
City
Net
Ass
esse
d V
alue
(FY
201
1-12
)1,
565,
511,
526
$
1,56
5,51
1,52
6$
C
ityw
ide
VLF
Pro
perty
Tax
In-li
eu R
even
ue (F
Y 2
011-
12)
1,18
3,14
5
1,
183,
145
VLF
Prop
erty
Tax
In-li
eu P
er $
1000
Ass
esse
d Va
lue
0.76
$
0.
76$
Gro
wth
in A
sses
sed
Valu
e39
7,16
7,60
0$
291,
843,
000
$
Prop
erty
Tax
In-L
ieu
of V
LF R
even
ue30
1,84
7$
221,
801
$
Not
e: F
igur
es ro
unde
d w
here
app
ropr
iate
.
Sou
rces
: Cou
nty
of S
tani
slau
s; G
oodw
in C
onsu
lting
Gro
up, I
nc.
Sier
ra P
oint
e Sp
ecifi
c Pl
an
Page A-27
APPENDIX 3
INFRASTRUCTURE COST ESTIMATES FOR EXISTING DEVELOPMENT
Page A-28
Preliminary Opinion of Probable Costfor
Existing Communities within the Sierra Pointe Specific Plan
Oakdale, CA
Specific Plan-Phase: SIERRA POINTE - RESIDENTIAL
Community Name: TWILDO AVE AND SEAMAN DRIVE
Residential Street 2,462 LFCURB & GUTTER 5,610 LF $13 $72,930ASPHALT PAVING SECTION (3.5") 2182 TN $90.00 $196,380CLASS II AGGREGATE BASE SECTION (6") 3741 CY $56.00 $209,496STREET LIGHTING 8 EA $5,000 $41,033
$519,839
Water10" C900 PVC PIPE 560 LF $35 $19,600
10" VALVES 3 EA $1,750 $5,250FIRE HYDRANTS 2 EA $3,500 $7,000TEMP TRENCH PATCH 600 SF $1.30 $780
$32,630
Sewer8" SDR 26 PIPE 3,461 LF $35 $121,135SEWER MANHOLE 15 EA $4,000 $60,000SEWER LATERAL 50 EA $1,000 $50,000TEMP TRENCH PATCH 13,844 SF $1.30 $17,997
$249,132
Storm12" SDR 35 PIPE 790 LF $40 $31,60018" RCP 373 LF $45 $16,785DRYWELL 3 EA $8,000 $24,000
DRAINAGE INLET 12 EA $1,500 $18,000STORM MANHOLE 5 EA $4,000 $20,000TEMP TRENCH PATCH 5,000 SF $1.30 $6,500
$116,885
Total $918,487Unit Cost per Street Foot 373.07$
Note: The estimate shown below was prepared to provide probable construction costs associated with annexing
the named community into the City of Oakdale. It is assumed that annexation will require improvements (sewer,
water, streets, etc) to meet current City of Oakdale Standards. Please see the attached exhibit for an illustration of
the improvements assumed to be required.
Prepared by Giuliani Kull, Inc.
11/6/2012 Page 1 of 1
Page A-29
Page A-30