W:\04 Board of Managers\Agendas\2015\May 20, 2015 Agenda - Board Workshop.docx Board Workshop of Capitol Region Watershed District (CRWD) Board of Managers for Wednesday, May 20, 2015, 5:00pm at CRWD, 1410 Energy Park Drive, Suite 4, St. Paul, MN. BOARD WORKSHOP AGENDA The Board Workshop is a meeting of CRWD Board Managers, CRWD Administrator and staff from communications firm Fourth Sector Consulting, LLC. A quorum will be present, however, the meeting is informational only and no actions will be taken by the Board. I. Call to Order of Board Workshop (President Joe Collins) A) Introductions B) Workshop objective II. Communications interview questions (Cathy Kennedy, Fourth Sector Consulting, LLC.) III. Adjournment

May 20, 2015 CRWD Board Packet

Embed Size (px)

DESCRIPTION

 

Citation preview

W:\04 Board of Managers\Agendas\2015\May 20, 2015 Agenda - Board Workshop.docx

Board Workshop of Capitol Region Watershed District (CRWD) Board of Managers for

Wednesday, May 20, 2015, 5:00pm at CRWD, 1410 Energy Park Drive, Suite 4, St. Paul, MN.

BOARD WORKSHOP AGENDA

The Board Workshop is a meeting of CRWD Board Managers, CRWD Administrator and staff

from communications firm Fourth Sector Consulting, LLC. A quorum will be present, however,

the meeting is informational only and no actions will be taken by the Board.

I. Call to Order of Board Workshop (President Joe Collins)

A) Introductions

B) Workshop objective

II. Communications interview questions (Cathy Kennedy, Fourth Sector Consulting, LLC.)

III. Adjournment

W:\04 Board of Managers\Agendas\2015\May 20, 2015 Agenda - Board Workshop.docx

Workshop objective

Fourth Sector Consulting, LLC is developing a strategic communications plan to be shared by

CRWD, Ramsey-Washington Metro Watershed District and Mississippi Watershed Management

Organization. The objective of this workshop is to receive Board comments about the

communications questions below. The questions were developed by CRWD and Fourth Sector

staff and will inform the development of the plan. The workshop will be recorded.

Questions

What do you see as some of the most important things CRWD needs to tackle in the

next year? In the next three years?

How do you think communications could help achieve these goals?

Whom do you see as the priority audiences for CRWD? Name your top three.

For each of these audiences, what do you think is the most important information they

need to know?

Currently, what do you consider CRWD’s most effective communications strategies

and tactics? Least effective?

How do you think this list should change in the next year or two? Do practices need to

be added or stopped?

In your opinion, what resources are needed to achieve the communications vision? (E.g.

Staff? Tools? Technology? Training? Etc.)

Whom do you consider the CRWD spokesperson? Who manages the daily

communications work? Do you have opinions about how it should be organized?

Do you feel external partners have a clear sense of CRWD’s work? Why or why not?

What else do you think is important for me to know about CRWD’s communications

work?

Is there anything else you feel is important for me to know?

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

Regular Meeting of Capitol Region Watershed District (CRWD) Board Of Managers, for Wednesday, May 20,

2015 6:00 p.m. at the office of CRWD, 1410 Energy Park Drive, Suite 4, St. Paul, Minnesota.

REGULAR MEETING AGENDA

I. Call to Order of Regular Meeting (President Joe Collins)

A) Attendance

B) Review, Amendments and Approval of the Agenda

II. Public Comment – For Items not on the Agenda (Please observe a limit of three minutes per person.)

III. Permit Applications and Program Updates (Permit Process: 1) Staff Review/Recommendation, 2) Applicant Response, 3) Public Comment, and 4) Board Discussion

and Action.)

A) Permit # 15-010 Como- Chatsworth SPSVP (Kelley)

B) Permit # 15-013 Jamestown Homes (Hosch)

C) Permit Close-out # 13-008, Phalen Office Park (Hosch)

IV. Special Reports– Building Committee Update, Managers Texer and Thienes

V. Action Items

A) AR: Approve Minutes of the May 6th Regular Meeting (Sylvander)

B) AR: Approve April 2015 Accounts Payables/Receivables (Sylvander)

C) AR: Award Bid and Order Project for Upper Villa Park Stormwater Project (Kelley)

D) AR: Approve Contract Amendment for the Eustis Street Stormwater Feasibility Study (Eleria)

E) AR: Authorize 2015 Fish Surveys (Suppes)

VI. Unfinished Business

A) CHS Field (Lowertown Ballpark) Update (Zwonitzer)

B) Willow Reserve Restoration Plan Update (Eleria)

C) Ford Site Update (Fossum)

VII. General Information

A) Administrator’s Report

VIII. Next Meetings

A) Wednesday, June 3, 2015 CRWD Board Meeting

B) Wednesday, June 10, 2015 CAC Tour

IX. Adjournment

W:\04 Board of Managers\Agendas\2015\May 20, 2015 Agenda Regular Mtg.docx

Materials Enclosed

Capitol Region Watershed District Permit 15-010 Como Chatsworth

Permit Report 15-010 Board Meeting Date: 05/20/15

Applicant: Barbara Mundahl St. Paul Public Works 25 West Fourth Street (CHA 900) St. Paul, MN 55102

STAFF RECOMMENDATION: Approve with 3 Conditions: 1. Provide a copy of the NPDES permit. 2. Revise plans to include the following:

a. Specify the rim elevation of structures 264 and 269 to verify the volume retention available in the east and west basins.

b. Provide additional detail to show how runoff from CB 245 and CB 247 enter the west basin and how runoff from CB 265 and CB 266 enter the east basin.

c. Provide specific erosion control on the perimeter of the filtration basins. The erosion control should limit construction activity on top of the filtration basins to prevent sediment deposition and compaction of subsoils.

d. Label the aggregate backfill as “washed, angular, non-carbonate rock.” e. Specify the planting media in the filtration basins on sheets 14 and 15 shall be 80% sand, 20%

compost. 3. Revise SWPPP to include provisions a-e as outlined in the 15-010 Permit Report.

Consultant:

,

Description: Reconstruction of select residential streets in Como-Chatsworth area Stormwater Management: Applicant proposes two surface filtration basins and volume bank District Rule: —C D F Disturbed Area: 6.27 Acres Impervious Area: 6.27 Acres

Permit Location

Aerial Photo

Como Ave

Chatsworth

Capitol Region Watershed District Permit Report

CRWD Permit #: 15-010 Review date: May 14, 2015 Project Name: Como-Chatsworth Phase I Applicant: Barb Mundahl

City of St. Paul Public Works 25 West Fourth Street St. Paul, MN 55102 651.266.6112 [email protected]

Purpose: Reconstruction of streets, curb and gutter, base material, storm

sewer, street lighting, and installation of two filtration basins. Location: Churchill between Jessamine and Horton

Oxford between Jessamine and Como Argyle between Jessamine and Como Como between Lexington and Chatsworth West Como between Horton and Chatsworth Van Sylke between Front and West Como Jessamine between Churchill and Chatsworth

Applicable Rules: C, D, and F Recommendation: Approve with 3 Conditions EXHIBITS:

1. Como-Chatsworth Watershed Permit Submittal, by City of St. Paul Public Works, dated 4/15/15, recd. 4/15/15.

2. Watershed map, by City of St. Paul Public Works, not dated, recd. 4/15/15. 3. Soil Boring Log, by American Engineering Testing, Inc., dated 9/27/14, recd.

4/15/15. 4. Construction Plan, by City of St. Paul Public Works, dated 4/14/15, recd. 4/15/15.

HISTORY & CONSIDERATIONS: Application previously submitted under permit 15-010.

W:\07 Programs\Permitting\2015\15-010 Como-Chatsworth\15-010 Como-Chatsworth_Review_01.doc Page 1 of 5

RULE C: STORMWATER MANAGEMENT Standards Proposed discharge rates for the 2-, 10-, and 100-year events shall not exceed

existing rates. Developments and redevelopments must reduce runoff volumes in the amount

equivalent to an inch of runoff from the impervious areas of the site. Stormwater must be pretreated before discharging to infiltration areas to

maintain the long-term viability of the infiltration area. Developments and redevelopments must incorporate effective non-point

source pollution reduction BMPs to achieve 90% total suspended solid removal.

Findings 1. A hydrograph method based on sound hydrologic theory is not used to analyze

runoff for the design or analysis of flows and water levels. However, the applicant is reducing impervious surface area.

2. Runoff rates for the proposed activity do not exceed existing runoff rates for the 2-, 10-, and 100-year critical storm events. Stormwater leaving the project area is discharged into a well-defined receiving channel or pipe and routed to a public drainage system.

3. Stormwater runoff volume retention is not achieved onsite in the amount equivalent to the runoff generated from one inch of rainfall over the impervious surfaces of the development.

a. The amount of proposed impervious onsite is 272,968 square feet. b. Volume retention:

Volume Retention Required (cu. ft.)

BMP

Volume Retention

Provided below outlet (cu. ft.)

1 inch Runoff (cu. ft.)

2 inch Runoff (cu. ft.)

20,473 Filtration Basin East 1,787 2,875 5,750

Total 1,787 cf

c. Filtration is proposed due to clay soils: Filtration Volume Required (cu. ft.)

BMP

Filtration Volume

Provided below outlet (cu. ft.)

1 inch Runoff (cu. ft.)

2 inch Runoff (cu. ft.)

26,614 (24,292

remaining)

Filtration Basin (E) 1,640 2,875 5,750 Filtration Basin (W) 3,097 2,875 5,750

Total 4,737 cf

d. Banking of excess volume retention is not proposed. e. Filtration volume and facility sizes have been calculated using the

appropriate hydrological soil group classification and design filtration rate.

W:\07 Programs\Permitting\2015\15-010 Como-Chatsworth\15-010 Como-Chatsworth_Review_01.doc Page 2 of 5

f. The filtration areas are capable of filtering the required volume within 48 hours.

g. Stormwater runoff is pretreated to remove solids before discharging to infiltration areas.

4. Alternative compliance sequencing has been requested. a. The applicant partially complies with the volume retention standard. b. The project is linear, and the cost cap has not been reached. c. The applicant partially complies with the volume retention standard

through the use of qualified banking credits of 15,370 cubic feet [20,473-1,787-(4,737*0.7)].

5. Best management practices do not achieve 90% total suspended solids removal from the runoff on an annual basis. However, the applicant is exempt through the use of banking credits.

6. A memorandum of agreement for maintenance of stormwater facilities exists between the City of St. Paul and the CRWD. Adequate maintenance access is provided for surface and underground systems.

RULE D: FLOOD CONTROL Standards Compensatory storage shall be provided for fill placed within the 100-year

floodplain. All habitable buildings, roads, and parking structures on or adjacent to a

project site shall comply with District freeboard requirements. Findings 1. There is no floodplain on the property according to FEMA. 2. It is not known if all habitable buildings, roads, and parking structures on or

adjacent to the project site comply with CRWD freeboard requirements. However, adequate conveyance has been provided to prevent flooding.

RULE E: WETLAND MANAGEMENT Standard

Wetlands shall not be drained, filled (wholly or in part), excavated, or have sustaining hydrology impacted such that there will be a decrease in the inherent (existing) functions and values of the wetland.

A minimum buffer of 25 feet of permanent nonimpacted vegetative ground cover abutting and surrounding a wetland is required.

Findings 1. There are no known wetlands located on the property.

RULE F: EROSION AND SEDIMENT CONTROL

W:\07 Programs\Permitting\2015\15-010 Como-Chatsworth\15-010 Como-Chatsworth_Review_01.doc Page 3 of 5

Standards A plan shall demonstrate that appropriate erosion and sediment control

measures protect downstream water bodies from the effects of a land-disturbing activity.

Erosion Control Plans must adhere to the MPCA Protecting Water Quality in Urban Areas Manual.

Findings 1. Erosion and sediment control measures are consistent with best management

practices, as demonstrated in the MPCA manual Protecting Water Quality in Urban Areas.

2. Adjacent properties are protected from sediment transport/deposition. 3. Wetlands, waterbodies and water conveyance systems are protected from

erosion/sediment transport/deposition. 4. Project site is greater than 1 acre; an NPDES permit is required. A SWPPP has

not been submitted and does not satisfy NPDES requirements. The applicant has provided the Application for General Stormwater Permit for Construction Acticity.

RULE G: ILLICIT DISCHARGE AND CONNECTION

Standard Stormwater management and utility plans shall indicate all existing and

proposed connections from developed and undeveloped lands for all water that drains to the District MS4.

Findings 1. New direct connections or replacement of existing connections are not

proposed. 2. Prohibited discharges are not proposed.

Recommendation: Approve with 3 Conditions Conditions:

1. Provide a copy of the NPDES permit. 2. Revise plans to include the following:

a. Specify the rim elevation of structures 264 and 269 to verify the volume retention available in the east and west basins.

b. Provide additional detail to show how runoff from CB 245 and CB 247 enter the west basin and how runoff from CB 265 and CB 266 enter the east basin.

c. Provide specific erosion control on the perimeter of the filtration basins. The erosion control should limit construction activity on top of the filtration basins to prevent sediment deposition and compaction of subsoils.

d. Label the aggregate backfill as “washed, angular, non-carbonate rock.”

W:\07 Programs\Permitting\2015\15-010 Como-Chatsworth\15-010 Como-Chatsworth_Review_01.doc Page 4 of 5

e. Specify the planting media in the filtration basins on sheets 14 and 15 shall be 80% sand, 20% compost.

3. Provide a SWPPP that includes the following: a. Filtration perimeter control and erosion control practices shall remain in

place until the final completion of the project or vegetation has been established (whichever is later).

b. Installation of filtration practices shall be done during periods of dry weather and completed before a rainfall event. Placement of engineered soils shall be on dry native soil only.

c. The bottom excavation surface of filtration areas shall be level without dips or swales.

d. Engineered soil shall remain uncontaminated (not mixed with other soil) when installed.

e. During construction, stormwater must be routed around filtration areas until all construction activity has ceased and tributary surfaces are cleaned of sediment.

W:\07 Programs\Permitting\2015\15-010 Como-Chatsworth\15-010 Como-Chatsworth_Review_01.doc Page 5 of 5

Capitol Region Watershed District Permit 15-013 Jamestown Homes

Permit Report 15-013 Board Meeting Date: 5/20/2015

Applicant: Ken Isaacson Twin Cities Housing Development Corporation 400 Selby Ave. Saint Paul, MN 55102

STAFF RECOMMENDATION: Approve with 5 Conditions: 1. Receipt of $6,800 surety and documentation of maintenance agreement recorded with Ramsey County. 2. Provide a site specific plan, schedule and narrative for maintenance of the proposed stormwater management

practices. At a minimum, require annual maintenance of infiltration areas to include removal of accumulated sediment and debris.

3. Provide a copy of the NPDES permit. 4. Demonstrate that the Environmental Construction Contingency Plan has been approved by the MPCA. 5. Revise plans and HydroCAD to remain consistent for the underground system outlet control structure. Sheet

C-2.0, Detail 10 on Sheet C4.1, and HydroCAD each have varying rim elevations, invert elevations, and naming conventions.

a. Sheet C-2.0 labels the outlet structure as Storm MH 87 with a rim elevation of 893.50 and an invert of 889.35 and references Detail 10 on sheet C-4.1.

b. Sheet C-4.1 Detail 10 is named Outlet Rate Control Structure 57 with rim elevation 895.60 and invert elevation 889.55.

c. HydroCAD lists the outlet structure invert at 889.60.

Consultant: Rhonda Pierce Pierce Pini and Associates, Inc.

9298 Central Ave. NE Blaine, MN 55434

Description: Renovation to an existing facility for improved parking lots, sidewalks, grading/drainage, playgrounds, and interior spaces. Stormwater Management: 1 underground infiltration system. District Rule: C, D, F Disturbed Area: 2.63 Acres Impervious Area: 1.36 Acres

Permit Location

Aerial Photo

Dale

St.

94

Capitol Region Watershed District Permit Report

CRWD Permit #: 15-013 Review date: May 8, 2015 Project Name: Jamestown Homes Applicant: Ken Isaacson

TCHDC 400 Selby Ave, Suite C St. Paul, MN 55102 651.292.0211 [email protected]

Purpose: Reconstruction of parking lots, sidewalks, play areas, and green

space for four (4) apartment buildings. The apartment buildings are also receiving interior renovations.

Location: 600 Central Avenue West Applicable Rules: C, D, and F Recommendation: Approve with 5 Conditions EXHIBITS:

1. Stormwater Calculations, by Pierce Pini and Associates, Inc., dated 2/25/15, recd. 3/6/15.

2. HydroCAD Model, by Pierce Pini and Associates, Inc., dated 5/2/15, recd. 5/5/15. 3. Construction Plans (Sheets C-1.0, C-2.0, C-3.0, C-3.1, C-3.2, C-3.3, C-4.0, C-4.1,

L-1, L-2, L-3, L-4, L-5, L-5, L-6), by Spencer Jones and Cermak Rhodes Architects, dated 4/20/15, recd. 5/5/15.

4. Construction Plans (Sheets C-1.0, C-2.0, C-3.1, C-3.2, C-4.0), by Spencer Jones and Cermak Rhodes Architects, dated 3/23/15, recd. 3/24/15.

5. Phase II Environmental Investigation, by Landmark Environmental LLC, dated July 2013, recd. 3/6/15.

6. Proposed Conditions Drainage Map, by Pierce Pini and Associates, Inc., dated 2/25/15, recd. 3/24/15.

7. CRWD Review Comments-Response Memo, by Pierce Pini and Associates, Inc., dated 3/23/15, recd. 3/24/15.

W:\07 Programs\Permitting\2015\15-013, Jamestown Homes\15-013 Jamestown Homes_Review_02.doc Page 1 of 4

8. Environmental Construction Contingency Plan, by Landmark Environmental LLC, dated April, 2015, recd. 5/5/15.

9. Response to Comments Memo, by Pierce Pini and Associates, Inc., dated 5/5/15, recd. 5/5/15.

10. Design Geotechnical Report, by Chosen Valley Testing, dated 4/29/15, recd. 5/5/15.

11. Draft Operations and Maintenance agreement, undated recd 2/25/15. HISTORY & CONSIDERATIONS: A Phase I ESA investigation suggested that the site may have some contamination due to neighboring properties. The Phase II Environmental Investigation Report suggests that no action is needed to remediate the site but a Construction Contingency Plan should be prepared in the event contamination is found on site during construction. RULE C: STORMWATER MANAGEMENT

Standards Proposed discharge rates for the 2-, 10-, and 100-year events shall not exceed

existing rates. Developments and redevelopments must reduce runoff volumes in the amount

equivalent to an inch of runoff from the impervious areas of the site. Stormwater must be pretreated before discharging to infiltration areas to

maintain the long-term viability of the infiltration area. Developments and redevelopments must incorporate effective non-point

source pollution reduction BMPs to achieve 90% total suspended solid removal.

Findings 1. A hydrograph method based on sound hydrologic theory is used to analyze

runoff for the design or analysis of flows and water levels. 2. Runoff rates for the proposed activity do not exceed existing runoff rates for

the 2-, 10-, and 100-year critical storm events. Stormwater leaving the project area is discharged into a well-defined receiving channel or pipe and routed to a public drainage system.

3. Stormwater runoff volume retention is achieved onsite in the amount equivalent to the runoff generated from one inch of rainfall over the impervious surfaces of the development.

a. The amount of proposed impervious onsite is 59,335 square feet. b. Volume retention:

Volume Retention Required (cu. ft.)

BMP

Volume Retention

Provided below outlet (cu. ft.)

1 inch Runoff (cu. ft.)

2 inch Runoff (cu. ft.)

4,450 Underground (N) 18,480 4,226 8,452

Total 8,452 cf

W:\07 Programs\Permitting\2015\15-013, Jamestown Homes\15-013 Jamestown Homes_Review_02.doc Page 2 of 4

c. Banking of excess volume retention is not proposed. d. Infiltration volumes and facility sizes have been calculated using the

appropriate hydrological soil group classification and design infiltration rate.

e. The infiltration areas are capable of infiltrating the required volume within 48 hours.

f. Stormwater runoff is pretreated to remove solids before discharging to the northern infiltration area.

4. Alternative compliance sequencing has not been requested. 5. Best management practices achieve 90% total suspended solids removal from

the runoff generated on an annual basis. 6. A recordable executed maintenance agreement has not been submitted.

Adequate maintenance access is provided for underground systems.

RULE D: FLOOD CONTROL Standards Compensatory storage shall be provided for fill placed within the 100-year

floodplain. All habitable buildings, roads, and parking structures on or adjacent to a

project site shall comply with District freeboard requirements. Findings 1. There is no floodplain on the property according to FEMA. 2. All habitable buildings, roads, and parking structures on or adjacent to the

project site comply with CRWD freeboard requirements. However, revised HydroCAD modeling may increase the 100-yr flood elevation in the underground systems.

RULE E: WETLAND MANAGEMENT Standard

Wetlands shall not be drained, filled (wholly or in part), excavated, or have sustaining hydrology impacted such that there will be a decrease in the inherent (existing) functions and values of the wetland.

A minimum buffer of 25 feet of permanent nonimpacted vegetative ground cover abutting and surrounding a wetland is required.

Findings 1. There are no known wetlands located on the property.

RULE F: EROSION AND SEDIMENT CONTROL

Standards A plan shall demonstrate that appropriate erosion and sediment control

measures protect downstream water bodies from the effects of a land-disturbing activity.

W:\07 Programs\Permitting\2015\15-013, Jamestown Homes\15-013 Jamestown Homes_Review_02.doc Page 3 of 4

Erosion Control Plans must adhere to the MPCA Protecting Water Quality in Urban Areas Manual.

Findings 1. Erosion and sediment control measures are consistent with best management

practices, as demonstrated in the MPCA manual Protecting Water Quality in Urban Areas.

2. Adjacent properties are protected from sediment transport/deposition. 3. Wetlands, waterbodies and water conveyance systems are protected from

erosion/sediment transport/deposition. 4. Project site is greater than 1 acre; an NPDES permit is required. A SWPPP has

been submitted and satisfies NPDES requirements. RULE G: ILLICIT DISCHARGE AND CONNECTION

Standard Stormwater management and utility plans shall indicate all existing and

proposed connections from developed and undeveloped lands for all water that drains to the District MS4.

Findings 1. New direct connections or replacement of existing connections are not

proposed. 2. Prohibited discharges are not proposed.

RECOMMENDATION: Approve with 5 Conditions Conditions:

1. Receipt of $6,800 surety and documentation of maintenance agreement recorded with Ramsey County.

2. Provide a site specific plan, schedule and narrative for maintenance of the proposed stormwater management practices. At a minimum, require annual maintenance of infiltration areas to include removal of accumulated sediment and debris.

3. Provide a copy of the NPDES permit. 4. Demonstrate that the Environmental Construction Contingency Plan has been

approved by the MPCA. 5. Revise plans and HydroCAD to remain consistent for the underground system

outlet control structure. Sheet C-2.0, Detail 10 on Sheet C4.1, and HydroCAD each have varying rim elevations, invert elevations, and naming conventions.

a. Sheet C-2.0 labels the outlet structure as Storm MH 87 with a rim elevation of 893.50 and an invert of 889.35 and references Detail 10 on sheet C-4.1.

b. Sheet C-4.1 Detail 10 is named Outlet Rate Control Structure 57 with rim elevation 895.60 and invert elevation 889.55.

c. HydroCAD lists the outlet structure invert at 889.60.

W:\07 Programs\Permitting\2015\15-013, Jamestown Homes\15-013 Jamestown Homes_Review_02.doc Page 4 of 4

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District.

DATE: May 11, 2015

TO: CRWD Board of Managers

FROM: Elizabeth Hosch, BMP Inspector

RE: Permit Closeouts

Background

Construction activity is complete for permit 13-008, Phalen Office Park.

Issues

Final inspection has been conducted to confirm demolition of existing structures, construction of a new

parking lot, storm sewer connections to adjacent filtration basins, and final stabilization. The filtration

basins were constructed under separate permit (#12-006), providing the related stormwater treatment for

the parking lot.

$7,750 of surety was retained for the project.

Action Requested

Approve Certificate of Completion and associated $7,750 surety return for permit #13-008, Phalen

Office Park.

cc: Jim Mogen, Ramsey Country Attorney’s Office

W:\07 Programs\Permitting\Board Memos\2015-5-20 Permit Closeout Board Memo.docx

May 20, 2015

III. Permit Applications

(C.) Permit Close Outs

(Hosch)

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District.

DATE: May 13, 2015

TO: Board of Managers

FROM: Mark Doneux, Administrator

RE: Building Committee Update

Background

At the May 7, 2014 Board Meeting the Managers approved an agreement for Real Estate Services with

DTZ. Former DTZ employees Mark Evenson and Kate Gillette are now with the firm of Avison Young

who are now are real estate consultants. In March of 2015, Mark Evenson and Kate Gillette gave the

Building Committee an update on the CRWD Program assumptions and corresponding square footage.

The list of possible properties was also updated to include a 1-3 ranking system. This system ranks a “1”

as a good prospect for a future office space, a “2” means that the site or building has some limitations and

may be marginal at meeting our needs and a “3” means that will come off the list and no longer be

considered. Mark Evenson and Kate Gillette also developed two timelines for a new office facility. One

timeline is specific for the purchase of an existing building because that process would take less time. The

second timeline is for a construction (Build to Suit) timeline due to the additional time necessary to plan,

design and construct a new facility.

Issues

At the May 20th Board meeting, Mark Evenson and Architect Jeff Gears will review the current property

list and discuss the pros and cons of each site. They will also review the CRWD program and the estimated

square footage required for either a purchase or build option. Finally, Mark and Jeff will review the budget

and timeline with the Board. The budget will reflect costs that are currently reflected in the market for

properties being considered by the District.

Action Requested

No Action Requested. Provide feedback, comments and direction to staff, consultants and Building

Committee on next steps.

enc: Avison Young Facility Update, May 20, 2015

W:\01 Administration\Facility Management\2014 Phase II Facility Planning\Board Memo - District Office Facility Update 5-13-15.docx

May 20, 2015

IV. Special Reports

Building Committee Update

(Doneux)

Partnership. Performance.

Facility UpdateProgram | Timeline | Properties | Financials 

Presented to:Capitol Region Watershed DistrictMay 20,2015

Partnership. Performance.

Facility Update

Table of Contents1. Program & Bubble Diagram2. Timelines

a) Build to Suitb) Purchase or Lease

3. Properties Considered4. Financial Estimates & Projections

Capitol Region Watershed District : Space Program01.28.15

Program Area Approx. Dimensions Size SF Notes

Office

Open Office Workstation 8' x 8' 64 13 832 23 1,472 Based on info from Program & Facility Plan dated 04.10.14

Private Office 10' x 12' 120 5 600 7 840 Based on info from Program & Facility Plan dated 04.10.14

Conference Room 15' X 22' 330 1 330 2 660 Based on info from Program & Facility Plan dated 04.10.14

Assembly Area 30' x 45' 1,350 1 1,350 1 1,350 Based on current Board Room size

Locker Room/Shower 10' x 12' 120 1 120 1 120 Based on current Locker Room size

Lobby/Reception 14' x 18' 250 1 250 1 250 Based on current Lobby size

Break Room 14' x 16' 225 1 225 1 225 Based on current Break Room size

Office Work Room 12' x 14' 170 1 170 1 170 Based on info from Program & Facility Plan dated 04.10.14

Server Room/IT 10' x 12' 120 1 120 1 120 Based on info from Program & Facility Plan dated 04.10.14

Plotter 60 1 60 1 60 Based on info from Program & Facility Plan dated 04.10.14

Toilet Room 9' x 16' 145 2 290 2 290 Based on current Toilet Room size

Garage/Storage 20' x 42' 840 1 840 1 840 Based on current Garage size

Subtotal - Net 5,187 6,397

Circulation Grossing Factor 1.25 1.25

TOTAL SPACE 6,484 7,996

Current

Need Total SF

Future

Need Total SF

Build to Suit Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar

15 15 15 15 15 15 15 15 15 15 16 16 16 16 16 16 16 16 16 16 16 17 17 17 17Phase I - Initial Strategic PlanningKickoff MeetingSpace ProgrammingInitial Survey of Available Properties

Phase II - Space Identification / PlanningFormal Market Tours

Select Best Case AlternativesPrepare & Request Proposals from Land Owners

Design Building Shell

Phase III - Acquisition NegotiationAnalyze Initial Responses to ProposalsNegotiations of Terms & ConditionsPrepare & Execute Letter of Intent For Future LocationNegotiate Purchase AgreementAcquire SiteCity Approval

Phase IV - Design / Construction / Move-inDesign Interiors

Bid Working Drawings & Select Contractor

Apply for Permits

Construct BuildingPunch List & Install FF&E Move In / Move Out

Lease or PurchaseExisting Building Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct

15 15 15 15 15 15 15 15 15 15 16 16 16 16 16 16 16 16 16 16Phase I - Initial Strategic Planning2015 Kickoff MeetingSpace ProgrammingRevise & Update Survey of Available Properties

Phase II - Space Identification / PlanningTour Available OpportunitiesOngoing Market SurveysSelect Best Case AlternativesPrepare & Request Proposals from Landlord and/or Developers

Phase III - Acquisition NegotiationAnalyze Initial Responses to ProposalsOngoing Negotiations of Terms & ConditionsPrepare & Execute Letter of Intent For Future LocationNegotiate Final DocumentsSecure Location

Phase IV - Design / Construction / Move-inDesign Space

Bid Working Drawings & Select Contractor

Construct SpacePunch List & Install FF&E Move In / Move Out

Map # Photo AddressScore?                         (1 Yes, 2 Maybe, 3 No)

Listing Type (Sale, Lease, Land)

SQ/FT Available  Total Building/Land Size Purchase PriceLease Rate (Gross)

Year BuiltProperty Type 

(Ofc/Ind)Parking Spaces Notes

1 1664 University Ave          St. Paul, MN 55104

1 Land/Sale n/a 0.88 Acres $1.5M n/a n/a Lnd/Ret‐General n/a Former Ember's restaurant. Ample parking and great visibility on University. Price recently lowered.

2 Island Station Development 2 Land/Sale n/a n/a Unknown n/a n/a Lnd n/aDevelopment opportuinty along side the National Parks Service. Pending approval and viability of the current developers financing. 

3 1192 Dale St                 St Paul, MN 55117 

2 Land/Sale Unknown ~1 Acre Unknown n/a n/a Retail n/aProperty is owned by May Building, Inc. We have obtained information that they may be interested in selling, but have not been able to connect with the ownership to discuss. 

4Sites B&C at Cleveland & 

University                   St. Paul, MN 55114

2 Land/Sale n/a 4.64 Acres (Total) See Notes n/a n/a Lnd/Ind‐Other n/a

Site B:2108 University Avenue73,181 SF$1,730,000 ($25/SF)Site C:2109 University Avenue46,609 SF$1,025,000 ($22/SF)

5 411‐417 Lexington Pkwy St. Paul, MN 55104

2 Land/Sale n/a 2.05 Acres $2.6M n/a n/a Lnd/Other n/a Site can be divided. Great location on Lexington. 

Capitol Region Watershed District Property Survey ‐ Properties for Consideration

May 2015

6 1509‐1535 Marshall Ave      St. Paul, MN 55104

2 Land/Sale n/a 0.86 Acres $1 M n/a n/a Lnd/Other n/a3 parcels totaling 1.26 arcres. The Blue + Red site is .86 acres and the portion the seller is going to be the most motivated on. They believe the Green (corner) site is best for multi‐family and will yield a higher sale price. 

7 1263 Donohue               St. Paul, MN 55104

2 Existing/Sale 25,777 25,777 $1.195M $10.00 Net 1947 Ret/Mixed Use 7 Potentially a good fit for CRWD, per the listing broker. 

8 474 W Minnehaha Ave        St. Paul, MN 55103

2 Existing/Sale 16,845 16,845 $490K n/a 1966Ind/Warehouse‐Distribution

not listedIndustrial/Office building. Nice office space with convference room. Large parking lot, fenced in. Currently under contract, but may become available again. 

9 1000 University Ave          St. Paul, MN 55104

2 Lease 40,000 54,526 n/a $22.00 Gross 1913 Ofc/General 179Lease opportunity. Newly renovated building with multiple space options. Controlled parking below, can be caged in for controlled storage space. Ample surface parking.

10 652‐684 Transfer Rd          St. Paul, MN 55104

2 Lease 44,052 44,052 n/a $9.50 Net 1975 Ind/Flex/R&D not listed Currently under renovation. New floor plans with more flexibility and higher image. 

11 2400 University Ave          St. Paul, MN 55114

2 Sale/Lease 39,715 39,715 $3.250M $12.00 Net 1917Ret/Neighborhoo

d Ctr20 May be a good lease option, is currently being reposition as a neighborhood center. 

Road Map

Address City, State Zip Number on report1664 University Ave Saint Paul, MN 55104-3725 1

380 Randolph Ave Saint Paul, MN 55102-3046 2

1192 Dale St Saint Paul, MN 55117 3

567 Cleveland Ave N Saint Paul, MN 55114-1813 4

411-417 Lexington Pkwy Saint Paul, MN 55104 5

1509-1535 Marshall Ave Saint Paul, MN 55104-6785 6

1263 Donohue Ave Saint Paul, MN 55104 7

474 W Minnehaha Ave Saint Paul, MN 55103-1523 8

1000 University Ave W Saint Paul, MN 55104-4706 9

652 Transfer Rd Saint Paul, MN 55104-1427 10

2400 University Ave Saint Paul, MN 55114-1709 11

Avison YoungInformation obtained from sources deemed reliable. While considered accurate, we make no guarantee, warranty or representation.

Date: 05/13/2015

Page 1 of 1

Build to Suit Build to Suit Existing Building Build to Suit Existing Building Tenant Income* Lease 1000 Univ2‐Story 1‐Story ‐ 1‐Story ‐ ‐ ‐

n/a n/a10/1/2016 10/1/2016 10/1/2016 10/1/2016 10/1/2016 10/1/2016 10/1/20169/30/2026 9/30/2026 9/30/2026 9/30/2026 9/30/2026 9/30/2026 11/30/202610 Yrs 0 Mos 10 Yrs 0 Mos 10 Yrs 0 Mos 10 Yrs 0 Mos 10 Yrs 0 Mos 10  Yrs 0 Mos 10 Yrs 2 Mos

Square Feet Occupied by CRWD 10,000 10,000 10,000 20,000 20,000 7,500 (tenant) 8,781**

$1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 n/a n/a$157,900 $165,540 $95,000 $284,680 $109,380 n/a n/a$215,000 $215,000 $125,000 $215,000 $180,000 n/a n/a$2,000,000 $2,150,000 $655,000 $3,800,000 $1,200,000 n/a n/a$120,000 $120,000 $25,000 $120,000 $25,000 n/a n/a$3,492,900 $3,650,540 $1,900,000 $5,419,680 $2,514,380 n/a n/a

$3,820,133 $3,992,542 $2,078,002 $5,927,424 $2,749,940 n/a n/a

Build to Suit Build to Suit Existing Building Build to Suit Existing Building Tenant Income* Lease1000 Univ2‐Story 1‐Story ‐ 1‐Story ‐ ‐ ‐

$2,169,309 $2,235,471 $1,500,755 $3,681,303 $2,461,924 $1,380,607 $2,130,321$2,095,006 $2,168,035 $1,357,074 $3,464,486 $2,118,566 $921,731 $1,439,863$216,931 $223,547 $150,076 $368,130 $246,192 $138,061 $209,540$18,078 $18,629 $12,506 $30,678 $20,516 $11,505 $17,462$21.69 $22.35 $15.01 $18.41 $12.31 n/a $23.86$30.30 $31.36 $19.63 $25.05 $15.32 n/a $23.46

Project Budget ComparisonsMay 20, 2015

**Plus garage/storage space 

No property taxes

*Tenant Income may be subtracted from the totals of the 20ksf buildings

Building Size 10,000 SF 20,000 SF

Purchase Assumptions:20% Down6% Interest Rate20 Year Amortization10% Fee on Sale1% Annual Appreciation$6.00 psf Operating Costs

Tenant Lease Assumptions:$11.00 Net$7.50 psf in transaction costs7,500 SF (25% vacancy built in)10 Year TermBuild out included in construction costs 

Total AmountPresent valueAverage per annumAverage per monthRSF ‐ AverageRSF ‐ Net effctv rate p/a

CommenceExpirationTerm

Purchase Price (land or building)Fees (design, civil, structural, MEP)Demo/Prep

Assumptions

Totals

Construction/Build OutSite workTOTAL

Sale Price in 10 Years

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

Regular Meeting of the Capitol Region Watershed District (CRWD) Board of Managers, for Wednesday,

May 6, 2015 6:00 p.m. at the office of CRWD, 1410 Energy Park Drive, Suite 4, St. Paul, Minnesota

REGULAR MEETING MINUTES

I. A) Call to Order of Regular Meeting (President Joe Collins)

Managers

Joe Collins

Seitu Jones

Shirley Reider

Mike Thienes

Mary Texer

Staff Present

Elizabeth Beckman, CRWD

Mark Doneux, CRWD

Bob Fossum, CRWD

Elizabeth Hosch, CRWD

Forrest Kelley, CRWD

Michelle Sylvander, CRWD

Nate Zwontizer, CRWD

Jim Mogen, Ramsey County

Attorney

Public Attendees Carrie Wasley, Ramsey

Conservation District

Steve Duerre, CAC

Linda Jungwirth, Tri Area

Block Club

Dan Mielke, HR Green

Andrew Corkery, U of M

Student

Ian Olson-Holmly, U of M

Student

Dillon Nelson, U of M Student

Anthony Vecchi, U of M

Student

B) Review, Amendments and Approval of the Agenda

President Collins asked for additions or changes to the agenda. Administrator Doneux requested the addition of

Action Item D, Special Grant Agreement.

Motion 15-108: Approve the May 6, 2015 agenda, with the addition of Action Item D, Special Grant

Agreement.

Texer/Jones

Unanimously approved

II. Public Comment – For Items not on the Agenda

Ms. Linda Jungwirth from the Tri Area Block Club thanked the Board of Managers for the nomination for the

Sustainable St. Paul Award. Ms. Jungwirth invited the Managers to the Trout Brook Nature Sanctuary grand

opening on Saturday, May 30th from 1:00 pm to 3:00 pm. The official ribbon cutting will take place at 1:00

followed by tours.

III. Permit Applications and Program Updates

A) Permit #15-018 Highland’s on Graham II (Hosch)

May 20, 2015 Board Meeting

V. Action Item A) Approve Minutes

of May 6, 2015

DRAFT Regular Board Meeting

(Sylvander)

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

Ms. Hosch reviewed Permit #15-018. The applicant, River Road Investments II, is constructing a new senior

housing complex. The applicable rules are Stormwater Management (Rule C), Flood Control (Rule D), and

Erosion and Sediment Control (Rule F). The disturbed area of this project is 1.07 acres with .65 acres of

impervious surface.

Motion 15-109: Approve variance from Stormwater Rule D, Flood Control requirements.

The freeboard from the East Underground System (Filtration 2) is proposed at 0.5 feet. CRWD requires 1.0

feet, but the applicant has maximized the driveway slope and cannot achieve greater than 0.5 feet.

1. A high point in the driveway has been added to provide positive drainage to Norfolk Ave. in the 100+

year rain event. This serves to maximize the effective low floor elevation of the parking garage. This

break is at the highest point possible based on other constraints, including:

a. The fixed length of the driveway based on the need for separation from the alley to the east.

b. The fixed elevation difference from the garage entrance to the existing sidewalk based on

accessibility slope requirements.

Thienes/Reider

Unanimously approved

Motion 15-110: Approve permit 15-018 Highland’s on Graham II with 4 conditions:

1. Receipt of $3,300 surety and document recording of maintenance agreement with Ramsey County.

2. Provide a site specific plan, schedule and narrative for maintenance of the proposed stormwater

management practices that includes the following.

a. Frequency of inspection or specific dates.

b. At a minimum, require annual maintenance to include removal of accumulated sediment and

debris.

3. Provide a copy of the NPDES permit.

4. Revise plans to include the following:

a. A detail of the underground filtration outlet pipe with Contech HydroBrake.

Thienes/Reider

Unanimously approved

B) Permit # 15-019 Northern Salt (Hosch)

Ms. Hosch reviewed Permit #15-019. The applicant, Northern Salt Properties, is removing two existing buildings, construction of rail spurs and new building, and construction of an underground infiltration basin. The applicable rules are Stormwater Management (Rule C), Flood Control (Rule D), and Erosion and

Sediment Control (Rule F). The disturbed area of this project is 2.25 acres with 2.56 acres of impervious

surface.

Motion 15-111: Approve permit 15-019 Northern Salt with 3 conditions:

1. Receipt of $11,500 surety and documentation of maintenance agreement recorded with Ramsey County.

2. Provide a site specific plan, schedule and narrative for maintenance of the proposed stormwater

management practices that includes the following:

a. At a minimum, requires annual maintenance of infiltration areas to include removal of

accumulated sediment and debris.

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

3. Provide a copy of the NPDES permit.

4. Revise plans or HydroCAD to remain consistent. Plans indicate the outlet orifice in the weir wall has an

invert of 903.73. HydroCAD indicates 902.5.

5. Revise the underground system in HydroCAD to include the overflow weir at 908.49.

Thienes/Reider

Unanimously approved

C) Permit # 15-021 Joy of the People (Hosch)

Ms. Hosch reviewed Permit #15-021. The applicant, Joy of the People, is installing synthetic turf and

performing site improvements. The applicable rules are Stormwater Management (Rule C), Flood Control

(Rule D), and Erosion and Sediment Control (Rule F). The disturbed area of this project is 1.5 acres with 0.73

acres of impervious surface.

Motion 15-112: Approve permit 15-021 Joy of the People with 5 conditions:

1. Provide documentation of maintenance agreement when finalized with the property owner.

2. Provide a site specific plan, schedule and narrative for maintenance of the proposed stormwater

management practices that includes the following.

a. At a minimum, require annual maintenance of infiltration areas to include removal of

accumulated sediment and debris.

3. Provide a copy of the NPDES permit.

4. Revise plans to include the following:

a. Provide a section view of the turf that confirms the volume retention provided. Only volume

retained below the low outlet will be credited to the volume retention requirement.

b. State that the bottom of the storage volume shall be flat. Sheet C1.41 shows the turf with a slope.

The underlying storage system should be flat.

c. State that clay soils encountered during excavation shall be over-excavated and replaced with

clean washed sand.

d. Geotextile fabric shall not be placed below the infiltration area.

e. State that aggregate fill shall be “washed, angular, non-carbonate rock.”

f. Add cleanouts to the perforated pipe system. At a minimum, provide one cleanout per row of

pipe.

5. Revise SWPPP to include the following:

a. Infiltration perimeter control and erosion control practices shall remain in place until the final

completion of the project or vegetation has been established (whichever is later).

b. Installation of infiltration practices shall be done during periods of dry weather and completed

before a rainfall event. Placement of engineered soils shall be on dry native soil only.

c. Excavation of infiltration areas shall be completed using a backhoe with a toothed bucket.

d. Native soils in infiltration areas shall be de-compacted to a minimum depth of 18 inches prior to

placing engineered soil.

e. The bottom excavation surface of infiltration areas shall be level without dips or swales.

f. Engineered soil shall remain uncontaminated (not mixed with other soil) when installed.

g. During construction, stormwater must be routed around infiltration areas until all construction

activity has ceased and tributary surfaces are cleaned of sediment.

Reider/Thienes

Unanimously approved

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

D) Permit # 15-022 The Good Acre (Kelley)

Mr. Kelley reviewed Permit #15-022. The applicant, Pohlad Foundation, is constructing a new commercial

building and urban farm area. The applicable rules are Stormwater Management (Rule C), Flood Control (Rule

D), and Erosion and Sediment Control (Rule F). The disturbed area of this project is 2.47 acres with 1.27 acres

of impervious surface.

Motion 15-113: Approve permit 15-022 The Good Acre with 6 conditions:

1. Receipt of $6,400 surety and documentation of maintenance agreement recorded with Ramsey County.

2. Provide a site specific plan, schedule and narrative for maintenance of the proposed stormwater

management practices that includes the following:

a. Inspect in winter months to ensure plowed snow is not being stored on infiltration/filtration practices.

b. Establish a watering plan that extends a minimum of one year after planting.

c. At a minimum, requires annual maintenance of infiltration areas to include trimming vegetation,

replacing vegetation where needed, mulch replacement, and removal of accumulated sediment and

debris.

3. Provide a copy of the NPDES permit.

4. Specify an outlet for Basin 3 that discharges to a public drainage system, or provide documentation

from adjacent landowner that proposed drainage route is acceptable.

5. Provide a landscaping plan that includes the following:

a. Specify potted plants or plant plugs to vegetate infiltration areas. Basin seeding should be avoided.

b. Provide signage that deters snow management from using the infiltration/filtration basin for snow

storage.

Reduce total area that runs off without receiving treatment to achieve 90% TSS removal.

Reider/Texer

Unanimously approved

E) Permit # 15-024 Saints Tailgating Lot (Kelley)

Mr. Kelley reviewed Permit #15-024. The applicant, St. Paul Saints Baseball, is constructing a new tailgating

lot for the Saints Ballpark. The applicable rules are Stormwater Management (Rule C), Flood Control (Rule D),

and Erosion and Sediment Control (Rule F). The disturbed area of this project is 2.5 acres with 1.77 acres of

impervious surface.

Motion 15-114: Approve permit 15-024 St. Paul Saints Baseball with 9 conditions:

1. Receipt of $8,850 surety and documentation of maintenance agreement recorded with Ramsey County.

2. Update the maintenance plan to include inspection in winter months to ensure plowed snow is not being

stored on filtration practices.

3. Provide plans signed by a professional engineer per the Minnesota Board of AELSLAGID.

4. Provide a copy of the NPDES permit.

5. Revise plans to include the following:

a. Provide specific erosion control on the perimeter of the biofiltration basins. The erosion control

should limit construction activity on top of the filtration basins to prevent sediment deposition.

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

b. Provide inlet protection for the proposed catch basins on site and immediately downstream of

disturbed areas. Include all catch basins at the intersection of Willius Street and E. Prince

Street.

c. Provide signage that deters snow management from using the filtration basins for snow storage.

d. Provide a minimum of 18” of filtration media in the biofiltration basins. The Biofiltration Swale

Section on sheet C5.0 of the plans specifies 1 foot of filtration media.

6. Revise SWPPP to include the following:

a. Filtration perimeter control and erosion control practices shall remain in place until the final

completion of the project or vegetation has been established (whichever is later).

b. Installation of filtration practices shall be done during periods of dry weather and completed

before a rainfall event.

c. The bottom excavation surface of filtration areas shall be level without dips or swales.

d. Engineered soil shall remain uncontaminated (not mixed with other soil) when installed.

e. During construction, stormwater must be routed around filtration areas until all construction

activity has ceased and tributary surfaces are cleaned of sediment.

7. Provide a minimum of 7,534 cubic feet of filtration volume to comply with Rule C of the CRWD Rules.

8. Demonstrate that the site achieves a minimum of 90% TSS removal from runoff..

9. Revise HydroCAD model to include the following:

a. Include all disturbed areas in the existing and proposed models and include all proposed

impervious area in the volume reduction standard. The proposed reconstruction of East Prince

Street constitutes a common plan of development and must comply with the CRWD rules.

b. Reduce the exfiltration rate to 1.0 inch per hour for all biofiltration basins, or justify how a rate

of 4.0 inches per hour will be achieved.

c. Update biofiltration basin areas to better reflect plan contours. Consider separating basins with

rock berms into multiple basins.

d. Revise outlet elevations to reflect plans.

i. The plans show the CBMH 2 rim elevation at 713.75 while HydroCAD shows 713.25.

ii. The plans show the CBMH 4 rim elevation at 713.25 while HydroCAD shows 712.25.

iii. The plans show the CBMH 6 rim elevation at 710.75 while HydroCAD shows 712.2.

Thienes/Reider

Unanimously approved

IV. Special Reports – U of M Capstone Project, Trout Brook East Branch Subwatershed Study

Mr. Zwonitzer provided an update on the U of M Capstone Project. Since 2010, the District, with assistance

from local engineering firms (H.R. Green Company and HDR Inc.), have worked with groups of students in the

Civil Engineering Department of the University of Minnesota on their Capstone Project. The projects vary each

year but are related to water quality or flooding issues within the District. This partnership helps further the

work of the District while also offering real-world experience for college level students in the water resources

field.

For the spring 2015 semester, the District and H.R. Green worked with students at the University of Minnesota

Civil Engineering Department on their Capstone Project. The students: Andrew Corkery, Ian Olson-Holmly,

Dillon Nelson, and Anthony Vecchi worked on a subwatershed analysis project for the Trout Brook East Branch

subwatershed. The students reviewed the goals of the project and provided a presentation with recommendations.

The Managers thanked the students for their presentation.

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

V. Action Items

A) AR: Approve Minutes of the April 15, 2015 Workshop and Regular Meeting (Sylvander)

Motion 15-115: Approve Minutes of the April 15, 2015 workshop and regular meeting.

Jones/Texer

Unanimously approved

B) AR: Approve Grant to City of Roseville for Wetland Protection (Doneux)

Administrator Doneux reviewed that as part of CRWD Permit # 15-008 Victoria Street, the City of Roseville will

be acquiring land or an easement to construct wetland mitigation areas. In the process of the City conducting an

appraisal for the property, it became apparent that the cost for an easement alone, an outright purchase may be in

the best interest of the City. At the April 15, 2015 Board Meeting, Managers discussed the possibility of

supporting the City of Roseville in acquiring the parcel.

On April 22, 2015, the District received a grant request from the City of Roseville of up to $38,600 from the

District in support of the purchase of the parcel. Administrator Doneux drafted Land Conservation Analysis of

Victoria Wetland, City of Roseville. Administrator Doneux recommended offering the City of Roseville a grant

not to exceed $38,600 for the acquisition of this parcel. The 1.5 acre parcel straddles both a high quality wetland

and buffer area but also abuts existing public land to the north and east as well as nearly connecting to a City Park

(Pioneer) on the west. Administrator Doneux recommended that conditions be placed on the approval of funds.

Attorney Mogen recommended conditions 1-3. An agreement will be drafted for review by the Board. The

agreement will include goals such as: The City may provide a low impact future trail connection through the

property but no further park development including but not limited to buildings, parking and active recreational

facilities. The City shall develop and implement a restoration and management approved by the District for the

parcel. The City may only construct stormwater and/or wetland mitigation features on this parcel associated with

CRWD Permit #15-008 Victoria Street. In keeping with park connectivity and public access, an unobstructed

wide east/west trail or access lane must be maintained.

Motion 15-116: Approve grant funding not to exceed $38,600 to the City of Roseville for the acquisition of

Victoria Street wetland parcel and direct Attorney and Administrator to draft an agreement subject to

conditions 1-3:

1) The land remain in public ownership in perpetuity for primarily wetland protection and buffer purposes, as

well as open space/park connectivity;

2) The City grant to the District a conservation easement, deed restriction or similar instrument that provides

the District with controls to ensure the requirements of the grant are being met;

3) The City is responsible for all future ownership costs, maintenance and land management costs associated

with the parcel.

Reider/Texer

Unanimously approved

C) AR: Board Workshop for Watershed Management Plan – Mid Term Review (Fossum)

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

Mr. Fossum reviewed that on September 1, 2010, the Board of Managers adopted the District’s Watershed

Management Plan (WMP). The plan covers the term from 2010—2020. The District is currently at the half-

way point in the term of the WMP, it is a good time to evaluate implementation of the plan and consider

adjustments (if any) to the WMP.

Staff and EOR, Inc. have completed significant work on the on Mid-Term WMP Review. Specifically, we have

thoroughly reviewed the Initiatives, Goals, Issues, and Themes. The elements of the plan were also reviewed

with the CAC at a special meeting on April 29th. Mr. Fossum requested that the Board set a Board workshop

for later in May to review and discuss the work on this project thus far. The focus of the Managers review will

be focused on the WMP Issues, Goals, and Themes. The Managers discussed having a workshop on May 12th

from 5:00—6:30pm.

Motion 15-117: Set Board workshop for the Watershed Management Plan—Mid-Term Review for May 12th,

2015, at 5:00pm.

Texer/Jones

Unanimously approved

D) AR: Special Grant Agreement (Zwontizer)

Mr. Zwontizer reviewed that CRWD is currently managing funds from three grant awards for stormwater

retrofits at Central High School. A $50,000 2014 Special Grant to the school has $44,735.75 remaining after

some funds were used to develop the stormwater concepts in the master plan. BWSR awarded $175,000 to

CRWD for design finalization and implementation of stormwater features. Additionally, CRWD’s Board has

committed $150,000 in funds (match) for the project that will be available beginning in 2016.

Since the School District will be managing the project, CRWD needs an agreement to transfers funds and

provide project assurances. This agreement must be approved and executed by both parties in order for funds to

be available for the project. It is scheduled to be approved at the School District’s May 19th Board meeting.

Motion 15-118: Approve grant agreement with St. Paul Public Schools in the amount of $369,735.75 for

stormwater retrofits at Central High School pending review and approval by Ramsey County attorney.

Reider/Jones

Unanimously approved

VI. Unfinished Business

A) Education and Outreach Plan Update (Beckman)

Ms. Beckman reviewed that in fall of 2014, CRWD hired the communications firm Fourth Sector Consulting in

collaboration with Ramsey-Washington Metro Watershed (RWMWD) and Mississippi Watershed Management

Organization (MWMO) to design a shared communications plan. In February 2015, CRWD Board of Managers

approved a Memorandum of Understanding with MWMO and RWMWD who will manage the contract with

Fourth Sector.

CRWD staff has made progress toward establishing the shared Strategic Communications Plan. On April 27,

CRWD staff hosted Fourth Sector Communications staff Katie Eukel, Tom Elko and Cathy Kennedy for an

onboarding field day. Staff gave the consultant team tours of some of our most impressive projects and

described the details of our programs.

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

CRWD staff and the consultant team have developed a set of communications-related interview questions.

Fourth Sector will conduct group interviews with Staff and Board Managers. A Board workshop will be held

on May 20th, 2015 at 5:00 p.m.

B) CHS Field (Lowertown Ballpark) (Zwonitzer)

Mr. Zwonitzer reviewed the progress at the Lowertown Ballpark. The ballpark is scheduled to open on May 18,

2015 for the first game. Mr. Zwonitzer shared artistic renderings of signage to be sandblasted into the cement

area above the location of the rain water storage tank. The first design was made up of dots depicting the image

of numerous rain drops rippling in a puddle. Each dot would represent one gallon of water stored in the rain water

reuse storage tank. The cost of design one would range from $25,000-$35,000. The second design was a solid

circle around the area of the rain water storage tank. The cost of the second design was $5,000. Because of the

tight time schedule of the park opening the Board discussed modifying the design and having it installed at a later

time during the off season. The Board agreed to increase the funding of the design.

Motion 15-119: Authorize additional funding not to exceed $10,000 to the Lowertown Ballpark for signage of

the rainwater reuse system.

Thienes/Texer

Unanimously approved

C) Lake McCarron’s Aquatic Plant Harvesting Update (Zwonitzer)

Mr. Zwonitzer provided a review of the Lake McCarron’s Aquatic Plant Harvesting. Three bids were received

from contractors. The new contractor will be Waterfront Restoration LLC. Twenty one homeowners will

participate in two rounds of the plant harvesting. After this season staff will review the homeowner’s contribution.

D) Upper Villa Stormwater Improvement Project Update (Kelley)

Mr. Kelley reviewed that the project went out to bid on April 3rd. Bids were due by April 24th. Seven bids were

received. Mr. Kelley will be providing a recommendation for New Look Contracting at the May 20th Board

meeting.

E) Ford Site Update (Fossum)

Mr. Fossum reviewed the former Ford Twin Cities Assembly Plant will be redeveloped in the coming years on

more than 135 acres of land situated along the Mississippi River. The City of St. Paul’s vision for the site is that

it will be a livable, mixed-use neighborhood that looks to the future with clean technologies and high quality

design for energy, buildings and infrastructure. This site will support walking, biking and transit, and provide

services, jobs and activities that every generation can enjoy.

The Ford Site Redevelopment represents a tremendous opportunity to Bring Water Back to St. Paul. The Ford

Site (Hidden Falls extension) was identified in the District’s Stream Corridor Restoration Plan completed as part

of the 2010 Watershed Management Plan. Significant emphasis was placed on stream corridor restoration in the

2010 WMP and the Hidden Falls project was ranked high. As the District moves into the planning of this

significant project, it is timely to review how the stream corridor restoration opportunity at the Ford Site was

identified and ranked in the 2010 Watershed Management Plan.

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

A public meeting is scheduled for June 23rd at the Gloria Dei Church by the City of St. Paul. The Great River

Park Plan will be reviewed. Mr. Fossum will send out more information to the Board of Managers.

F) Building Committee Update (Texer & Thienes)

Manager Texer reviewed some sites that the committee is taking into consideration as possible locations for a

new office. The District’s Real Estate consultant will be present at the May 20th Board meeting to provide a more

detailed review of the sites.

VII. General Information

A) Administrators Report

1) Administrator Approved or Executed Agreements

a) Amend. No. to 2014 Partner Grant Agreement with Roseville Area Schools – Harambee to extend

deadline to December 31. 2015.

b) 2015 Partner Grant Agreement with Roseville Area Schools for additional water themed education

and teacher training – not to exceed $5,000.

2) Board Approved or Executed Agreements

No new agreements.

3) General updates including recent and upcoming meetings and events

a) The 21st Annual Great River Gathering is May 14 at Saint Paul River Centre.

b) Trout Brook Nature Sanctuary planting and opening celebration with Great River Greening and the

City of Saint Paul is May 30. The volunteer planting event is coordinated by Great River Greening

and the opening celebration will be held afterwards.

c) Saint Paul Street Vitality Program boulevard rain garden planting events are planned for Saturday,

May 16 (Montana-Greenbrier project area) and Saturday, June 6 (Montreal Avenue project area).

d) Landscape Revival Native Plant Expo and Market is Saturday June 6 from 9 am – 3 pm at the Cub

Foods Community Pavilion on Larpenteur in Roseville.

e) Bugs Night Out, macroinvertebrate sampling event for children is Thursday, June 18 at Como

Lakeside Pavilion from 6 – 7:30 pm.

f) Como Lake Land and Water Cleanup with the Minnesota Standup Paddleboarders Association is

Sunday, July 12 from 10 am – 1 pm at Como Lakeside Pavilion.

VIII. Next Meeting

A) Wednesday, May 13, 2015 CAC Meeting, President Collins plans to attend

B) Wednesday, May 20, 2015 Board Meeting,

Manager Thienes will be absent from May 26th – July 29th.

A public meeting regarding the former Ford site has been rescheduled for June 23rd. Mr. Fossum plans to attend

this public meeting.

WEFTEC 2015 abstracts were approved for Curtis Pond, RSVP Program, CHS field, and Villa Park dredging

project and will be presented. Administrator Doneux was appointed to be a chair for the WEFTEC National

Municipal Stormwater and Green Infiltration Award.

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

MAWD Summer Tour will be June 24-26th in Duluth. Administrator Doneux and Manager Reider plan to attend.

Motion 15-120: Adjournment of the May 6, 2015 Regular Board Meeting at 8:05 p.m.

Texer/Reider

Unanimously Approved

Respectfully submitted,

Michelle Sylvander

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District.

DATE: May 14, 2015

TO: CRWD Board of Managers

FROM: Michelle Sylvander, Office Manager

RE: April 2015 Accounts Payable/Receivable and Administrative/Program Budget

Report

_________________________________________________________________________________

Background

Enclosed are the Accounts Payable/Receivable and the Administrative/Program Budget Reports for the

Month of April 2015.

Issues

The District Accountant Redpath has changed the accounting software to Sage 100. Because most staff

are salaried and now entering their time directly into Sage, payroll expenses are going directly to a job

cost using a burdened hourly rate that includes all benefits per employee. Because of the burdened hourly

rate and the timing of when invoices are entered into the new software, the amount of the accountants

payable will not match the budget report.

Summary of Accounts Payable/Receivable Report: Accts Payable $ 323,967.32

(Actual Paid in May) Accounts Receivable $ 238,961.53

Summary of Preliminary Budget Report: Administrative Budget $ 69,958.90

(Actual April Expenses) Program Budget $ 73,206.01

Project Budget $ 32,261.46

Capital Improvement Budget $ 99,135.12

TOTAL $ 274,561.49

Request Action

Approve April 2015 Accounts Payable/Receivable and April Budget Report, direct Treasurer and Board

President to endorse and disperse checks for these payments.

enc: April 2015 Accounts Payable

April 2015 Preliminary Budget Report

W:\02 Budget and Finance\Board Memos\Board Memos 2015\BD Memo AP Budget Report 5.20.15.docx

May 20, 2015

Board Meeting

V. Action Items – B) Accounts

Payable & Budget Update

(Sylvander)

Capitol Region Watershed District

Check RegisterFor the Period From May 1, 2015 - May 31, 2015

Date Payee Amount Check Total Check # Description

05/20/15 Al's Coffee 271.00 271.00 16618 Office Supplies05/20/15 Anna L. Eleria 16.63 16.63 16619 Staff Expense05/20/15 Avision Young 14,538.00 14,538.00 16620 New Office/Consulting05/20/15 Barr Engineering 14,073.29 14,073.29 16621 Engineering Expense05/20/15 Ben Meadows Company 53.82 53.82 16622 CSE Equipment05/20/15 Benefit Extras, Inc. 63.25 63.25 16623 Emplyee Benefits05/20/15 C Lanphear Communications 1,325.00 1,325.00 16624 Contracted/Supplies05/20/15 Century College 2,563.00 2,563.00 16625 Safety Training05/20/15 City of St. Paul-Forestry 100.00 100.00 16626 Events05/20/15 City of St. Paul Financial Services 4,050.00 4,050.00 16627 Lease/Work Trucks05/20/15 City of St. Paul Park & Rec. 3,000.00 3,000.00 16628 Partnership Funding05/20/15 Computer Revolution 2,394.25 2,394.25 16629 Equipment Purchase/Rental/Lease05/20/15 Dynamex 28.53 28.53 16630 Permit Deliveries05/20/15 Emmons & Olivier Resources 3,546.40 3,546.40 16631 Engineering Expense05/20/15 Energy Park Plaza 5,927.15 5,927.15 16632 Rent05/20/15 Fleet One, LLC 95.85 95.85 16633 Vehicle Expense05/20/15 Ford Credit 535.81 535.81 16634 Equipment Lease/Purchase05/20/15 Ford Credit 454.44 454.44 16635 Equipment Lease/Purchase05/20/15 ForesterMedia, Inc. 1,180.00 1,180.00 16636 Registration/Storm Conference05/20/15 Forrest Kelley 480.00 480.00 16637 Utilities05/20/15 Fresh Color Press 688.81 688.81 16638 RSVP's/Events05/20/15 Geosyntec 5,224.62 5,224.62 16639 Villa Park Subwaters05/20/15 Gustavus Adolphus Lutheran Church 100.00 100.00 16640 RSVP Rain Garden05/20/15 Hamline Midway Coalition 75.00 75.00 16641 Events05/20/15 HealthPartners 12,980.20 12,980.20 16642 Emplyee Benefits05/20/15 Houston Engineering, Inc. 832.50 832.50 16643 Engineering Expense05/20/15 Houston Engineering, Inc. 4,000.00 4,000.00 16644 Engineering Expense05/20/15 HR Specialist 97.00 97.00 16645 HR/Employment Law05/20/15 IAF Beacon I, LLC 7,750.00 7,750.00 16646 Surety Return/13-00805/20/15 Impressive Print 111.93 111.93 16647 RSVP Rain Garden05/20/15 Integra-Monthly 791.13 791.13 16648 Utilities05/20/15 Integra-Repairs 201.80 201.80 16649 Utilities05/20/15 International Erosion Control Assoc. 170.00 170.00 16650 Membership Renewal05/20/15 Marco-Minolta 678.47 678.47 16651 Equipment Purchase/Rental/Lease05/20/15 Mark Doneux 96.58 96.58 16652 Staff Expense05/20/15 Mennards 46.62 46.62 16653 Baseline Monitoring05/20/15 MetLife 581.19 581.19 16654 Emplyee Benefits05/20/15 Metropolitan Council 6,567.75 6,567.75 16655 Stormwater Runoff Studies05/20/15 Midway Ford 36.89 36.89 16656 Vehicle Expense05/20/15 Minnesota Brownfields 250.00 250.00 16657 Membership Renewal05/20/15 Minnesota DNR 140.00 140.00 16658 Aquatic Plant Harvest05/20/15 Minnesota Environmental Partnership 25.00 25.00 16659 Baseline Monitoring05/20/15 Minnesota Native Landscapes, Inc. 6,958.60 6,958.60 16660 RSVP Rain Garden05/20/15 MN Assoc. of Watershed Districts 250.00 250.00 16661 MAWD Summer Tour05/20/15 MN Pollution Control Agency 23,828.59 23,828.59 16662 MPCA - Clean Water05/20/15 MSC 289.35 289.35 16663 Baseline Monitoring05/20/15 Nelson Cheese & Deli 271.77 271.77 16664 Meeting Supplies05/20/15 Pioneer Press 2,032.40 2,032.40 16665 Legal Notices05/20/15 Ramsey Conservation District 9,558.00 9,558.00 16666 Design/Site Visits

5/12/2015 at 4:24 PM Page: 1

Capitol Region Watershed District

Check RegisterFor the Period From May 1, 2015 - May 31, 2015

Date Payee Amount Check Total Check # Description

05/20/15 Ramsey County-Attorney 2,756.25 2,756.25 16667 Legal Fees05/20/15 Redpath & Company, Ltd 7,222.05 7,222.05 16668 Accounting Expense05/20/15 SRF Consulting, Inc. 19,759.09 19,759.09 16669 Villa Park Subwaters05/20/15 UPS 7.05 7.05 16670 Postage 05/20/15 Verizon Wireless 170.18 170.18 16671 Telecommunications05/20/15 Viking Industrial Center 256.52 256.52 16672 CSE Equipment05/20/15 Walters 54.95 54.95 16673 Utilities05/20/15 Wenck Associates, Inc. 20,148.25 20,148.25 16674 Engineering Expense05/20/15 Xcel Energy 560.26 560.26 16675 Utilities05/20/15 St. Paul Stamp Works 64.73 64.73 16676 Office Supplies05/20/15 Staples Business Advantage 302.56 302.56 16677 Office Supplies05/20/15 Target Corporation 50,000.00 50,000.00 16678 Grants/Partnerships05/20/15 Tierney Brothers, Inc. 120.88 120.88 16679 New Lowertown Ballpark05/20/15 Total Tool 668.70 668.70 16680 Baseline Monitoring05/20/15 US Bank 712.47 712.47 16681 Various/Credit Card

April A/P: $242,134.56 $242,134.56

April Payroll/Benefits: $81,832.76 $81,832.76

April Total: $323,967.32 $323,967.32

APPROVED FOR PAYMENT: 5/20/2015

APRIL 2015 RECEIPTS:

Ramsey Wash. Metro Watershed Dist. 200.00 Confined Space TrainingHighland Assited Living-Permit Fee 2,000.00 Permit Fee - 15-018Seven Corners 10,650.00 SuretyThe Good Acre 2,000.00 SuretyCity of St. Paul 34,392.19 Highland Ravine ReimbursementNorthern Salt 2,000.00 Permit FeePatrick Coleman 100.00 Weed HarvestingWashington Safety Training 50.00 Miscellaneous IncomeMN Finance 187,500.00 BWSR Clean Water Grant4M Fund 69.34 April Interest

APRIL RECEIPTS: $238,961.53

5/12/2015 at 4:24 PM Page: 2

CAPITOL REGION WATERSHE DISTRICTJOB COST RECAP

FOR THE PERIOD Apr 1, 2015 - Apr 30, 2015

2015 CURRENT MONTH YEAR-TO-DATE % OF BUDGET JOB COST #/NAME ANNUAL BUDGET EXPENDITURES EXPENDITURES EXPENDED

15970 - General Adminitration 15 584,200.00 69,958.90 248,422.64 42.52%15999 - New Office 150,000.00 - - 0.00%00000 - Administration Allocation (122,500.00) - - 0.00%

TOTAL GENERAL ADMINISTRATION: $611,700.00 $69,958.90 $248,422.64 40.61%200 - Administration 80,850.00 - - 0.00%201 - Groundwater 8,050.00 534.25 19,758.29 245.44%207 - Rulemaking/Rule Revisions 21,150.00 436.77 19,660.81 92.96%208 - Permitting 192,590.00 4,851.50 29,995.46 15.57%210 - Stewardship Grants 257,980.00 12,652.62 38,534.46 14.94%211 - Monitoring & Data Collection 560,874.00 30,776.21 111,865.21 19.94%220 - Education & Outreach 185,590.00 14,603.22 52,459.61 28.27%225 - Technical Resources & Information Sharing 33,610.00 5,243.13 8,192.36 24.37%228 - Innovative BMP's Research 108,420.00 585.12 12,758.84 11.77%230 - Geographic Informatin Systems (GIS) 77,710.00 255.45 3,622.98 4.66%240 - Safety Program 35,790.00 3,267.74 7,856.07 21.95%

TOTAL PROGRAMS: $1,562,614.00 $73,206.01 $304,704.09 19.50%300 - Administration 41,650.00 - - 0.00%301 - Shoreline & Streambank Maintenance 36,200.00 - - 0.00%305 - Como Lake Subwatershed 133,400.00 1,217.29 3,436.91 2.58%310 - Lake McCarron's Subwatershed 63,660.00 1,058.20 2,609.53 4.10%313 - Loeb lake Subwatershed 27,000.00 1,671.32 2,026.74 7.51%315 - Trout Brook Subwatershed 231,635.00 11,723.40 98,580.52 42.56%317 - Crosby Lake Subwatershed 12,000.00 - 1,198.60 9.99%325 - Wetland, Stream & Ecosystem Restoration 77,000.00 80.07 160.14 0.21%330 - Mississippi River Subwatershed 125,158.00 12,566.41 44,340.26 35.43%370 - Watershed Management Plan 60,000.00 3,944.77 5,143.37 8.57%

TOTAL PROJECTS: $807,703.00 $32,261.46 $157,496.07 19.50%TOTAL OPERATING FUND: $2,982,017.00 $175,426.37 $710,622.80 23.83%

401 - Shoreline & Streambank Restoration 32,000.00 1,946.35 2,430.78 7.60%405 - Como Lake BMP's 85,000.00 1,369.69 11,091.04 13.05%410 - Lake McCarron's BMP's 929,050.00 30,007.65 152,642.92 16.43%415 - Trout Brook BMP's 90,600.00 55.20 49,566.28 54.71%417 - Crosby Lake BMP's 38,200.00 10,650.37 133,285.64 348.92%425 - Wetland, Stream & Ecosystem Restoration 154,000.00 107.43 427.71 0.28%430 - Mississippi River Subwatersheds BMP's 110,000.00 75.30 698.19 0.63%440 - Special Projects & Grants 735,250.00 54,923.13 141,532.66 19.25%490 - Debt Service 368,131.00 - - 0.00%

TOTAL CAPITAL IMPROVEMENT: $2,542,231.00 $99,135.12 $491,675.22 19.34%TOTAL ALL FUNDS: $5,524,248.00 $274,561.49 $1,202,298.02 21.76%

Unaudited Fund Balance Year-to-Date Year-to-Date Unaudited Fund BalanceFUND BALANCES @ 12/31/14 Revenue Expenditures @ 04/30/15

Operations 1,848,072.19 41,364.39 $710,622.80 1,178,813.78 Capital Improvement 3,571,332.70 222,079.69 491,675.22 3,301,737.17 Debt Service 49,377.78 - - 49,377.78

TOTAL FUND BALANCE: $5,468,782.67 $263,444.08 $1,202,298.02 4,529,928.73

CAPITOL REGION WATERSHE DISTRICTJOB COST DETAIL

FOR THE PERIOD Apr 1, 2015 - Apr 30, 2015

2015 CURRENT MONTH YEAR-TO-DATE % OF BUDGET

JOB COST #/NAME ANNUAL BUDGET EXPENDITURES EXPENDITURES EXPENDED15970 - General Adminitration 15 584,200.00 69,958.90 248,422.64 42.52%15999 - New Office 150,000.00 - - 0.00%10000 - Administration Allocation (122,500.00) - - 0.00%

TOTAL GENERAL ADMINISTRATION: $611,700.00 $69,958.90 $248,422.64 40.61%20000 - Administration Allocation 80,850.00 - - 0.00%15000 - Implement Permit Program 99,060.00 3,821.93 25,577.32 25.82%15101 - Permit Tracking Data Mgmt 15 9,930.00 905.56 4,190.84 42.20%15102 - Construction Inspection 15 62,950.00 124.01 203.95 0.32%15103 - Permit Closure & Post Construction 20,650.00 - 23.35 0.11%15120 - Evaluate Rules & Conduct 15 21,150.00 436.77 19,660.81 92.96%15130 - Groundwater Prot Well Seal 15 8,050.00 534.25 19,758.29 245.44%15143 - Stewardship Grants 15 92,560.00 3,788.69 23,012.73 24.86%15144 - Partner Grants 15 85,900.00 227.67 1,336.25 1.56%15145 - Inspiring Communities Prog 15 60,600.00 30.14 2,725.39 4.50%15146 - RSVP Rain Garden Proj 15 18,920.00 8,606.12 11,460.09 60.57%15200 - Baseline Monitor & Data Col 15 301,254.00 19,230.75 86,937.95 28.86%15205 - Lake Monitor & Data Coll 15 89,980.00 1,326.51 3,090.92 3.44%15210 - Villa Park Mon & Data Coll 15 36,700.00 827.71 1,405.19 3.83%15215 - Wetland Bio Monitoring 15 20,020.00 - 192.35 0.96%15220 - Long-term Mon Data Devel 15 16,320.00 107.43 8,570.45 52.52%15225 - Remote Data Acct/Set-up 15 0.00 373.51 1,503.69 0.00%15230 - BMP Monitoring 15 96,600.00 2,242.05 2,711.71 2.81%15231 - AHUG Exfiltration Monitoring 0.00 6,668.25 7,452.95 0.00%15250 - General 15 49,740.00 5,139.18 22,665.43 45.57%15253 - Community Capacity Assess 15 34,450.00 - 294.71 0.86%15255 - Clean Streets Outreach 15 17,900.00 122.91 445.00 2.49%15260 - Municipal Outreach 15 16,150.00 4,159.66 4,467.84 27.66%15262 - Youth Outreach 0.00 61.46 191.34 0.00%15265 - Partnerships 15 12,550.00 3,526.22 19,254.77 153.42%15270 - Website & Social Media 15 12,900.00 195.09 879.33 6.82%15271 - Master Water Stewards 0.00 32.66 32.66 0.00%15275 - Events 15 30,000.00 1,366.04 4,036.54 13.46%15285 - Awards & Recognition Prog 15 11,900.00 - 191.99 1.61%15300 - Local & Agcy Plan Rev Tech Com 16,840.00 241.11 1,135.31 6.74%15303 - BMP Database Maint Updates 15 16,770.00 5,002.02 7,057.05 42.08%15330 - Innovative BMPs Research 15 9,000.00 477.69 12,317.18 136.86%

CAPITOL REGION WATERSHE DISTRICTJOB COST DETAIL

FOR THE PERIOD Apr 1, 2015 - Apr 30, 2015

2015 CURRENT MONTH YEAR-TO-DATE % OF BUDGET

JOB COST #/NAME ANNUAL BUDGET EXPENDITURES EXPENDITURES EXPENDED15333 - Public Art Program 15 24,920.00 - - 0.00%15334 - Green Infrastructure Incentive 8,350.00 - - 0.00%15335 - Existing Site Stormwater Retro 11,000.00 - - 0.00%15336 - Climate Change Impacts 15 18,150.00 - - 0.00%15337 - Floating Island Pilot Proj 15 37,000.00 107.43 441.66 1.19%15370 - GIS Program Developement 15 27,850.00 255.45 3,622.98 13.01%15375 - Data Acquisition 15 10,000.00 - - 0.00%15376 - Internal Mapping System 15 11,600.00 - - 0.00%15377 - Impervious Surface Data Set 15 28,260.00 - - 0.00%15390 - Safety Training 15 12,830.00 2,880.18 4,524.75 35.27%15395 - Safety Program Update/Audit 15 10,650.00 77.22 1,084.56 10.18%15396 - CSE Equipment 15 12,310.00 310.34 2,246.76 18.25%

TOTAL PROGRAMS: $1,562,614.00 $73,206.01 $304,704.09 19.50%30000 - Administration Allocation 41,650.00 - - 0.00%15100 - Watershed Plan Audit 15 60,000.00 3,944.77 5,143.37 8.57%15400 - Lake McCarrons Shoreline Resto 16,600.00 - - 0.00%15405 - St Paul Natural Res Inter Prog 8,000.00 - - 0.00%15410 - Loeb Lake Shoreline Asses 15 5,800.00 - - 0.00%15411 - Crosby Lake Shoreline Asses 15 5,800.00 - - 0.00%15420 - Como Reg Park Stormwater 15 70,000.00 858.18 2,296.33 3.28%15421 - Como BMP Maint & Insp 15 42,750.00 230.41 881.59 2.06%15422 - Como Lake Impl Rpt Aud 15 20,650.00 128.70 258.99 1.25%15470 - Aquatic Plant Harvest 15 40,460.00 1,058.20 2,609.53 6.45%15471 - Aquatic Invasive Mgt Plan 15 23,200.00 - - 0.00%15510 - Willow Reserve Mgnt Plan 15 27,000.00 1,671.32 2,026.74 7.51%14550 - TB Inspection/Minor Maintenance 0.00 - 62,486.43 0.00%15550 - Inspection & Annual Maint 112,725.00 3,194.30 24,301.79 21.56%14552 - TBI Easement Verification/Doc 78,000.00 - 1,843.33 2.36%15554 - TBI Hydraulic/Hydrolic Model 17,000.00 - - 0.00%15570 - NPDES MS4 Stormwater Prog 15 7,170.00 460.12 813.49 11.35%15575 - Illicit Discharge Detn/Elim 15 16,740.00 81.62 334.71 2.00%15576 - Lafayette Stormwater Project 0.00 7,987.36 8,800.77 0.00%15600 - Wetland/Stream Reestab Feas 15 77,000.00 80.07 160.14 0.21%15620 - Green Line Redevelop SSGI 15 36,000.00 51.48 2,708.53 7.52%15622 - Ford Stie Planning 15 0.00 12,460.26 15,217.59 0.00%14625 - Eustis St Stormwater Improv 30,100.00 (528.38) 25,187.47 83.68%15624 - CCLRT BMP Maintenance 15 59,058.00 583.05 1,226.67 2.08%15631 - Crosby Lake Mgmt Pl Imple 15 12,000.00 - 1,198.60 9.99%

TOTAL PROGRAMS: $807,703.00 $32,261.46 $157,496.07 19.50%TOTAL OPERATING FUND: $2,982,017.00 $175,426.37 $710,622.80 23.83%

CAPITOL REGION WATERSHE DISTRICTJOB COST DETAIL

FOR THE PERIOD Apr 1, 2015 - Apr 30, 2015

2015 CURRENT MONTH YEAR-TO-DATE % OF BUDGET

JOB COST #/NAME ANNUAL BUDGET EXPENDITURES EXPENDITURES EXPENDED15680 - Shoreline & Streambank Restoration 15 0.00 1,895.51 1,895.51 0.00%15681 - Ravine Stablization Poj 15 32,000.00 50.84 535.27 1.67%13700 - Curtis Pond * 85,000.00 1,369.69 11,091.04 13.05%12751 - Villa Park Subwatershed BMP 929,050.00 30,007.65 152,642.92 16.43%12801 - Highland Ravine Stabilization * 38,200.00 10,650.37 133,285.64 348.92%12815 - TBI Repair 35E to Cayuga 0.00 - 45,258.56 0.00%13818 - Farrington/Cottage 90,600.00 55.20 4,307.72 4.75%13852 - Trillium Site Water Resource * 154,000.00 107.43 427.71 0.28%15881 - Green Line Redev BMPs 15 110,000.00 - - 0.00%15882 - East Kittsondale Retrofit Project 0.00 75.30 698.19 0.00%15910 - Special Grants 15 616,000.00 52,864.54 130,730.98 21.22%14916 - Central High School 0.00 1,096.91 8,666.29 0.00%14918 - Great River School 0.00 390.73 1,403.60 0.00%15913 - Stormwater Retrofit Program 15 119,250.00 - 160.84 0.13%15915 - Dellwood Gardens 0.00 151.52 151.52 0.00%15916 - Upper Villa Park Wetland 0.00 - - 0.00%15917 - Harambee Elementary 0.00 303.04 303.04 0.00%15918 - Midway Stadium Redevelopment 0.00 - - 0.00%15919 - Swede Hollow Final Design 0.00 - - 0.00%15920 - Rondo Education Complex 0.00 - - 0.00%15921 - Wilder Square 0.00 116.39 116.39 0.00%15104 - Debt & Loan Service 15 368,131.00 - - 0.00%

TOTAL CAPITAL IMPROVEMENT: $2,542,231.00 $99,135.12 $491,675.22 19.34%

TOTAL ALL FUNDS: $5,524,248.00 $274,561.49 $1,202,298.02 21.76%

DATE: May 12, 2015 TO: CRWD Board of Managers FROM: Forrest Kelley, PE Regulatory and Construction Program Manager SUBJECT: Upper Villa Infiltration and Reuse Project Bid Award Background The District was awarded a $275,000 Clean Water Partnership grant in 2012 for the identification, design, and construction of volume reduction practices upstream of Lake McCarrons. In March of 2013, the Managers adopted the Lake McCarrons BMP Subwatershed Analysis that identified the Upper Villa Park softball field as a priority site. In January of 2014, the District was awarded an additional $360,000 towards construction of the combined infiltration/harvest and reuse BMP underneath the Upper Villa Park Softball field. The Board of Managers approved the cooperative construction agreement with Roseville and authorized bid advertisement at the March 4, 2015 meeting. Issues Bids for the Upper Villa Infiltration and Reuse project were opened on April 24, 2015. CRWD received 7 bids ranging from $851,000 to $1.2M. The full bid results are enclosed. SRF Consulting Group has determined that the apparent lowest responsible bidder is New Look Contracting, Inc. per the project bidding documents. Staff have reviewed the bid alternate for a corrugated metal pipe cistern and recommend moving forward with the base bid for the StormTrap concrete vault. An updated budget and financing plan is provided in the table below.

Upper Villa Park Costs and Funding Costs Engineering and Bidding $ 200,000 Construction $ 851,467 Project Total $ 1,051,467

Funding MPCA Grant $ 275,000

BWSR Grant $ 360,000 Total Grant $ 635,000

CRWD $ 215,717 Roseville* $ 200,750 Total Local Match $ 416,467

Project Total $ 1,051,467

*Based maximum City contribution within Joint Powers Agreement

May 20, 2015 Board Meeting V. Action Items, C) Upper Villa

Project Bid Award

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

Requested Action Authorize the Board President and Administrator to execute a Notice of Award and Enter into an Agreement with New Look Contracting, Inc. for the Upper Villa Stormwater Infiltration and Reuse Project. enc: SRF Recommendation Letter and Bid Tabulation. W:\06 Projects\McCarrons\Lake McCarrons Subwatershed CWP Grant\Bidding and Specs\Brd Memo Lake McCarrons Bid Award 2015-05-20.docx

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

SRF No. 7896 0080

May 12, 2015 Board of Managers CAPITOL REGION WATERSHED DISTRICT 1410 Energy Park Drive, Suite 4 St. Paul, MN 55108 SUBJECT: UPPER VILLA PARK INFILTRATION AND REUSE PROJECT 12-751 Dear CRWD Board of Managers: Sealed bids were received for the above-referenced project on Friday, April 24, 2015, at the Capitol Region Watershed District offices. A total of seven (7) bids were received. All bids have been reviewed and checked and are tabulated in the enclosed bid abstract. The bid abstract indicates how the bids compared with the Engineer’s Estimate of $887,100.00 for the work. The two apparent lowest bidder’s qualifications for this type of project have been received and reviewed. The lowest bidder is New Look Contracting of Rogers, Minnesota, with a base bid in the amount of $851,467.00. An Alternative Deduction to utilize an underground corrugated metal pipe storage system rather than an underground precast concrete storage system in the amount of $45,000 was also bid by New Look Contracting. The base bid is approximately 4 percent below the Engineer’s Estimate. After reviewing the bid documents and contractor qualifications, we recommend awarding the contract to the lowest bidder, New Look Contracting, in the amount of $851,467.00. Because New Look Contracting’s bid was below the Engineer’s Estimate, we recommend that the Alternative Deduction not be exercised at this time. Sincerely,

SRF CONSULTING GROUP, INC.

Walter Eshenaur, PE (MN, ND) Senior Associate WCE/gjd Enclosed: Bid Tabulation cc: Mark Doneux, Administrator Forrest Kelley, Project Manager

H:\Projects\7896\WR\Bidding\Upper Villa Park bid recommendation.docx

Bid Tabulation SRF Consulting Group, Inc. 4/30/2015Upper Villa Park Infiltation and Reuse Project #12‐751 By WCECapitol Region Watershed District Check LAB

Bid Item Unit Quantity Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total PriceMobilization LS 1 40,323.00$                40,323.00$                50,000.00$                50,000.00$               25,000.00$               25,000.00$               40,000.00$               40,000.00$               7,609.00$                   7,609.00$                   35,000.00$                     35,000.00$                     94,350.00$            94,350.00$              31,000.00$             31,000.00$          Remove bituminous pavement SY 1020 3.00$                           3,060.00$                  3.00$                           3,060.00$                 3.00$                         3,060.00$                 7.65$                         7,803.00$                 3.80$                           3,876.00$                   2.50$                               2,550.00$                       3.18$                      3,243.60$                4.00$                       4,080.00$            Remove Curb and Gutter LF 403 4.00$                           1,612.00$                  4.00$                           1,612.00$                 5.00$                         2,015.00$                 5.50$                         2,216.50$                 4.00$                           1,612.00$                   3.00$                               1,209.00$                       3.82$                      1,539.46$                5.00$                       2,015.00$            Furnish & Install Project Sign EA 2 550.00$                      1,100.00$                  550.00$                      1,100.00$                 500.00$                    1,000.00$                 900.00$                    1,800.00$                 2,403.00$                   4,806.00$                   800.00$                          1,600.00$                       1,657.50$               3,315.00$                1,550.00$               3,100.00$            Salvage & Reinstall Flag Pole EA 1 300.00$                      300.00$                      1,327.00$                  1,327.00$                 1,200.00$                 1,200.00$                 2,600.00$                 2,600.00$                 5,607.00$                   5,607.00$                   1,500.00$                       1,500.00$                       2,015.00$               2,015.00$                875.00$                   875.00$               Salvage Irrigation Control EA 1 100.00$                      100.00$                      380.00$                      380.00$                    500.00$                    500.00$                    925.00$                    925.00$                    460.00$                      460.00$                      400.00$                          400.00$                          1,007.50$               1,007.50$                385.00$                   385.00$               Remove Irrigation Control Post EA 1 260.00$                      260.00$                      136.00$                      136.00$                    150.00$                    150.00$                    925.00$                    925.00$                    165.00$                      165.00$                      150.00$                          150.00$                          403.00$                  403.00$                    280.00$                   280.00$               Salvage 70‐ft B2 Light and Pole EA 2 500.00$                      1,000.00$                  1,496.00$                  2,992.00$                 1,400.00$                 2,800.00$                 2,450.00$                 4,900.00$                 1,815.50$                   3,631.00$                   1,600.00$                       3,200.00$                       2,213.20$               4,426.40$                1,515.00$               3,030.00$            Protect Light Pole Foundation EA 1 50.00$                         50.00$                         435.00$                      435.00$                    400.00$                    400.00$                    2,500.00$                 2,500.00$                 527.00$                      527.00$                      1,500.00$                       1,500.00$                       403.00$                  403.00$                    2,800.00$               2,800.00$            Remove Light Pole Foundation EA 1 500.00$                      500.00$                      3,234.00$                  3,234.00$                 4,000.00$                 4,000.00$                 2,525.00$                 2,525.00$                 3,925.00$                   3,925.00$                   1,500.00$                       1,500.00$                       3,107.00$               3,107.00$                3,270.00$               3,270.00$            Remove Drinking Fountain and Concrete Pad LS 1 500.00$                      500.00$                      719.00$                      719.00$                    500.00$                    500.00$                    850.00$                    850.00$                    494.00$                      494.00$                      500.00$                          500.00$                          201.50$                  201.50$                    450.00$                   450.00$               Clear and Grub Tree 10 350.00$                      3,500.00$                  548.00$                      5,480.00$                 450.00$                    4,500.00$                 525.00$                    5,250.00$                 601.00$                      6,010.00$                   350.00$                          3,500.00$                       403.00$                  4,030.00$                445.00$                   4,450.00$            Tree Protection EA 2 180.00$                      360.00$                      289.00$                      578.00$                    100.00$                    200.00$                    325.00$                    650.00$                    334.00$                      668.00$                      250.00$                          500.00$                          201.50$                  403.00$                    200.00$                   400.00$               Salvage Fence LF 240 6.00$                           1,440.00$                  12.00$                         2,880.00$                 10.00$                       2,400.00$                 6.00$                         1,440.00$                 13.00$                         3,120.00$                   11.00$                            2,640.00$                       4.20$                      1,008.00$                10.90$                     2,616.00$            Temporary Construction Fence LF 492 8.00$                           3,936.00$                  7.00$                           3,444.00$                 15.00$                       7,380.00$                 12.00$                       5,904.00$                 7.00$                           3,444.00$                   10.00$                            4,920.00$                       4.65$                      2,287.80$                9.50$                       4,674.00$            Remove Electrical Panel EA 1 300.00$                      300.00$                      462.00$                      462.00$                    500.00$                    500.00$                    1,250.00$                 1,250.00$                 561.00$                      561.00$                      500.00$                          500.00$                          600.80$                  600.80$                    470.00$                   470.00$               Salvage and Reinstall Sprinkler Heads EA 3 100.00$                      300.00$                      250.00$                      750.00$                    75.00$                       225.00$                    600.00$                    1,800.00$                 400.00$                      1,200.00$                   100.00$                          300.00$                          67.17$                    201.51$                    210.00$                   630.00$               Salvage and Reinstall Sprinkler Valve EA 6 200.00$                      1,200.00$                  125.00$                      750.00$                    75.00$                       450.00$                    600.00$                    3,600.00$                 667.50$                      4,005.00$                   150.00$                          900.00$                          100.75$                  604.50$                    320.00$                   1,920.00$            Salvage and Reinstall Sprinkler Pipe LF 162 4.00$                           648.00$                      20.00$                         3,240.00$                 5.00$                         810.00$                    12.00$                       1,944.00$                 11.00$                         1,782.00$                   10.00$                            1,620.00$                       24.88$                    4,030.56$                9.35$                       1,514.70$            Remove Buried Power LF 400 3.00$                           1,200.00$                  3.00$                           1,200.00$                 5.00$                         2,000.00$                 9.50$                         3,800.00$                 3.00$                           1,200.00$                   2.50$                               1,000.00$                       10.08$                    4,032.00$                1.50$                       600.00$               Remove Water Line LF 1 3.00$                           3.00$                           7.00$                           7.00$                         1,200.00$                 1,200.00$                 500.00$                    500.00$                    67.00$                         67.00$                        2,500.00$                       2,500.00$                       201.50$                  201.50$                    825.00$                   825.00$               Storm sewer Pipe 24" RCP CL III LF 223 60.00$                         13,380.00$                45.00$                         10,035.00$               58.00$                       12,934.00$               55.00$                       12,265.00$               48.00$                         10,704.00$                 80.00$                            17,840.00$                     71.58$                    15,962.34$              79.25$                     17,672.75$          Plastic Pipe 4" PVC SDR 21 LF 104 25.00$                         2,600.00$                  29.00$                         3,016.00$                 35.00$                       3,640.00$                 35.00$                       3,640.00$                 23.00$                         2,392.00$                   23.00$                            2,392.00$                       35.78$                    3,721.12$                41.90$                     4,357.60$            Plastic Pipe 12" PVC SDR 18 LF 7 45.00$                         315.00$                      94.00$                         658.00$                    75.00$                       525.00$                    120.00$                    840.00$                    118.00$                      826.00$                      50.00$                            350.00$                          187.76$                  1,314.32$                115.00$                   805.00$               Ductile Iron Pipe 10" DIP CL 350 LF 14 80.00$                         1,120.00$                  166.00$                      2,324.00$                 150.00$                    2,100.00$                 78.00$                       1,092.00$                 186.00$                      2,604.00$                   60.00$                            840.00$                          117.93$                  1,651.02$                130.30$                   1,824.20$            Ductile Iron Pipe 24" DIP CL 350 LF 24 100.00$                      2,400.00$                  170.00$                      4,080.00$                 250.00$                    6,000.00$                 140.00$                    3,360.00$                 261.00$                      6,264.00$                   175.00$                          4,200.00$                       202.04$                  4,848.96$                255.00$                   6,120.00$            Drainage Structure Des 84‐4020 LF 13.2 725.00$                      9,570.00$                  550.00$                      7,260.00$                 950.00$                    12,540.00$               675.00$                    8,910.00$                 840.00$                      11,088.00$                 925.00$                          12,210.00$                     1,244.85$               16,432.02$              800.00$                   10,560.00$          Drainage Structure Des 60‐4020 LF 15.9 375.00$                      5,962.50$                  300.00$                      4,770.00$                 550.00$                    8,745.00$                 450.00$                    7,155.00$                 445.00$                      7,075.50$                   600.00$                          9,540.00$                       663.49$                  10,549.49$              495.00$                   7,870.50$            Drainage Structure Des 48‐4020 LF 29.1 275.00$                      8,002.50$                  205.00$                      5,965.50$                 450.00$                    13,095.00$               325.00$                    9,457.50$                 347.00$                      10,097.70$                 325.00$                          9,457.50$                       449.86$                  13,090.93$              490.00$                   14,259.00$          Casting Assembly R‐1733 EA 7 600.00$                      4,200.00$                  800.00$                      5,600.00$                 550.00$                    3,850.00$                 750.00$                    5,250.00$                 724.00$                      5,068.00$                   400.00$                          2,800.00$                       260.00$                  1,820.00$                795.00$                   5,565.00$            Connect to Existing Storm Sewer EA 2 800.00$                      1,600.00$                  2,701.00$                  5,402.00$                 1,200.00$                 2,400.00$                 700.00$                    1,400.00$                 891.00$                      1,782.00$                   1,000.00$                       2,000.00$                       1,105.00$               2,210.00$                465.00$                   930.00$               Connect to underground storage and infiltration systems EA 5 300.00$                      1,500.00$                  401.00$                      2,005.00$                 1,200.00$                 6,000.00$                 700.00$                    3,500.00$                 573.00$                      2,865.00$                   1,000.00$                       5,000.00$                       1,989.00$               9,945.00$                640.00$                   3,200.00$            Connect to manhole EA 7 300.00$                      2,100.00$                  0.01$                           0.07$                         1,200.00$                 8,400.00$                 700.00$                    4,900.00$                 891.00$                      6,237.00$                   1,000.00$                       7,000.00$                       1,262.86$               8,840.02$                185.00$                   1,295.00$            24" Isolation Plug Valve LS 1 18,000.00$                18,000.00$                23,125.00$                23,125.00$               18,000.00$               18,000.00$               23,500.00$               23,500.00$               27,112.00$                 27,112.00$                 28,000.00$                     28,000.00$                     25,020.00$            25,020.00$              31,750.00$             31,750.00$          The Preserver Structural Pollution Control Device LS 1 7,500.00$                  7,500.00$                  12,070.00$                12,070.00$               1,400.00$                 1,400.00$                 475.00$                    475.00$                    7,828.00$                   7,828.00$                   6,000.00$                       6,000.00$                       19,890.00$            19,890.00$              5,675.00$               5,675.00$            Underground Stormwater Storage System LS 1 171,000.00$              171,000.00$              204,000.00$              204,000.00$             195,625.00$             195,625.00$             150,000.00$             150,000.00$             245,034.00$               245,034.00$              280,000.00$                 280,000.00$                 182,100.00$           182,100.00$            255,775.00$           255,775.00$       Packaged Pump Station LS 1 45,300.00$                45,300.00$                62,000.00$                62,000.00$               41,000.00$               41,000.00$               62,500.00$               62,500.00$               77,196.00$                 77,196.00$                 75,000.00$                     75,000.00$                     53,690.00$            53,690.00$              78,715.00$             78,715.00$          Underground Stormwater Infiltration System LS 1 181,680.00$              181,680.00$              191,000.00$              191,000.00$             209,500.00$             209,500.00$             190,000.00$             190,000.00$             235,514.00$               235,514.00$              225,000.00$                 225,000.00$                 269,687.00$           269,687.00$            212,250.00$           212,250.00$       Underground Storm Water Infiltration System Excavation CY 4000 6.00$                           24,000.00$                2.00$                           8,000.00$                 6.00$                         24,000.00$               4.00$                         16,000.00$               7.60$                           30,400.00$                 5.00$                               20,000.00$                     18.48$                    73,920.00$              4.95$                       19,800.00$          Rock Backfill for Infiltration System CY 1260 57.00$                         71,820.00$                51.00$                         64,260.00$               35.00$                       44,100.00$               51.00$                       64,260.00$               71.80$                         90,468.00$                 50.00$                            63,000.00$                     90.54$                    114,080.40$            48.60$                     61,236.00$          Suitable Material Backfill for Infiltration System CY 800 10.00$                         8,000.00$                  2.00$                           1,600.00$                 8.00$                         6,400.00$                 4.00$                         3,200.00$                 10.00$                         8,000.00$                   12.00$                            9,600.00$                       38.31$                    30,648.00$              30.70$                     24,560.00$          Disposal of Excavated Material CY 3890 20.00$                         77,800.00$                8.00$                           31,120.00$               12.00$                       46,680.00$               14.00$                       54,460.00$               9.70$                           37,733.00$                 10.00$                            38,900.00$                     3.89$                      15,132.10$              11.00$                     42,790.00$          OptiRTC Advanced Stormwater Monitoring and Control System LS 1 40,135.00$                40,135.00$                18,292.00$                18,292.00$               33,505.00$               33,505.00$               16,500.00$               16,500.00$               84,635.00$                 84,635.00$                 66,000.00$                     66,000.00$                     77,460.00$            77,460.00$              10,200.00$             10,200.00$          Electrical Cabinet, Reinstall Lighting and Irrigation Control Systems LS 1 12,000.00$                12,000.00$                25,495.00$                25,495.00$               22,560.00$               22,560.00$               17,600.00$               17,600.00$               28,782.00$                 28,782.00$                 25,000.00$                     25,000.00$                     22,044.35$            22,044.35$              24,000.00$             24,000.00$          2.5" BB Hackberry Tree EA 10 250.00$                      2,500.00$                  650.00$                      6,500.00$                 750.00$                    7,500.00$                 700.00$                    7,000.00$                 757.00$                      7,570.00$                   650.00$                          6,500.00$                       929.50$                  9,295.00$                975.00$                   9,750.00$            Reinstall Fence LF 240 25.00$                         6,000.00$                  18.00$                         4,320.00$                 25.00$                       6,000.00$                 25.00$                       6,000.00$                 31.00$                         7,440.00$                   26.00$                            6,240.00$                       7.80$                      1,872.00$                25.60$                     6,144.00$            Reinstall 70’ B2 Light EA 1 250.00$                      250.00$                      2,486.00$                  2,486.00$                 2,500.00$                 2,500.00$                 6,050.00$                 6,050.00$                 3,017.00$                   3,017.00$                   2,600.00$                       2,600.00$                       6,503.90$               6,503.90$                2,515.00$               2,515.00$            Reinstall 70 ‘ B2 Light and Foundation LS 1 14,000.00$                14,000.00$                8,030.00$                  8,030.00$                 7,500.00$                 7,500.00$                 10,000.00$               10,000.00$               9,745.00$                   9,745.00$                   8,395.00$                       8,395.00$                       10,723.10$            10,723.10$              8,120.00$               8,120.00$            Sod Type Lawn SY 1780 3.50$                           6,230.00$                  7.00$                           12,460.00$               8.00$                         14,240.00$               5.50$                         9,790.00$                 8.40$                           14,952.00$                 7.00$                               12,460.00$                     7.28$                      12,958.40$              6.40$                       11,392.00$          Sod Type Salt Tolerant SY 70 9.00$                           630.00$                      8.00$                           560.00$                    10.00$                       700.00$                    5.50$                         385.00$                    9.60$                           672.00$                      20.00$                            1,400.00$                       9.75$                      682.50$                    11.10$                     777.00$               Parking Lot Reconstruction SY 1020 25.00$                         25,500.00$                29.00$                         29,580.00$               35.00$                       35,700.00$               31.00$                       31,620.00$               32.90$                         33,558.00$                 25.00$                            25,500.00$                     46.91$                    47,848.20$              22.80$                     23,256.00$          Curb and Gutter LF 403 30.00$                         12,090.00$                22.00$                         8,866.00$                 25.00$                       10,075.00$               25.00$                       10,075.00$               29.00$                         11,687.00$                 25.00$                            10,075.00$                     23.40$                    9,430.20$                22.25$                     8,966.75$            Agg‐Lime TONS 280 17.50$                         4,900.00$                  34.00$                         9,520.00$                 35.00$                       9,800.00$                 45.00$                       12,600.00$               141.00$                      39,480.00$                 32.00$                            8,960.00$                       29.20$                    8,176.00$                51.70$                     14,476.00$          Erosion Control LS 1 3,000.00$                  3,000.00$                  3,333.00$                  3,333.00$                 3,500.00$                 3,500.00$                 4,500.00$                 4,500.00$                 4,354.00$                   4,354.00$                   15,000.00$                     15,000.00$                     5,655.00$               5,655.00$                16,050.00$             16,050.00$          Contingency (5%) LS 1 40,323.00$                N/A N/A N/A N/A N/A N/A N/ATotal Bid 887,100.00$              861,518.57$             880,804.00$             851,467.00$             1,126,949.20$           1,074,748.50$              1,218,612.50$         1,012,041.50$    

St. Paul Utilities, Inc. Dresel Contracting Minger Construction Co., Inc. VeitEngineer's Estimate Dave Perkins Contracting, Inc. New Look Contracting, Inc. Minnesota Utilities & Excavation

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District.

DATE: May 14, 2015 TO: CRWD Board of Managers FROM: Anna Eleria, Water Resource Project Manager RE: Approve Contract Amendment for Eustis Street Stormwater Improvement Feasibility Study

Background In late July 2014, CRWD’s Board of Managers approved Barr Engineering as the consultant for the Eustis Street Stormwater Improvement Feasibility Study in Lauderdale, MN. The goals of the study are to identify opportunities for implementing green infrastructure practices in both public and private (former Luther Seminary property) realm along Eustis Street and have construction coincide with Ramsey County’s 2015/2016 Eustis Street Project. The street work will include mill and overlay and construction of a new, 5-foot sidewalk on the east side of Eustis Street from Idaho Avenue south to the existing sidewalk. CRWD staff presented the preliminary concepts to the study partners including the private property owner, Aspen Waste Systems, in early February 2015. Issues In late April, CRWD staff met with the study partners to receive feedback on the preliminary concepts and discuss Ramsey County’s street improvement plans and construction schedule. We learned that the owner prefers to replace the concrete swales with pipes and is concerned about the volume of runoff being delivered to the swales from upstream areas. While the City of Lauderdale conducted H/H modeling of its subwatersheds nearly 10 years ago, they are coarse and missing key pieces of information including flood elevations of upstream stormwater ponds and identification of any deficiencies in the storm sewer system. The study partners are requesting that CRWD conduct subwatershed H/H modeling in the Saint Anthony subwatershed (labeled SA 1-4) which drains to the concrete swales. See enclosed map. Enclosed is the Barr letter summarizing a regional modeling effort in Lauderdale. The estimated cost for this work is $13,505. CRWD staff recommends the Board approve this expansion to the study’s scope for assisting the City and County in understanding local hydrology and in determining necessary modifications or improvements to the existing public drainage system including the stormwater ponds. Action Requested Approve a contract amendment for Barr Engineering for the Eustis Street Stormwater Improvement Feasibility Study at a cost not to exceed $13,505 and authorize Administrator to execute additional contract amendments in an amount not to exceed $3,000. encs: Barr Letter Dated May 7, 2015 and Lauderdale Storm Sewer System Map W:\06 Projects\Lauderdale\Eustis Street Stormwater Improvement Project\Board Memos\BM Eustis Street Study Contract Amendment 05-14-15.docx

May 20, 2015 V. Action Item - D) Contract Amendment for Eustis Street

Stormwater Improvement Feasibility Study (Eleria)

May 7, 2015 Ms. Anna Eleria Water Resource Project Manager Capitol Region Watershed District 1410 Energy Park Drive, Suite 4 St. Paul, MN 55108 Re: Eustis Street Regional Modeling Change Order Dear Ms. Eleria: The following is a description of the scope and budget required to perform regional modeling for the approximately 144 acres tributary to the open concrete swales along Eustis Street south of Idaho Avenue. All work covered by this scope of work will be charged on a time and materials basis and invoiced every month. Task 1: Data Compilation and Site Visit Barr will review watershed and stormsewer data provided by CRWD, Lauderdale, Falcon Heights and Ramsey County for the 144-acre watershed. Barr will develop a GIS database of all stormsewer information that will be imported into XP-SWMM H&H modeling software in Task 2. Two (2) Barr staff will perform a site inspection to review the configuration of the outlets for each pond. No survey is included in this task. The deliverable for this task is a map and GIS database of stormsewer information for the 165-acre watershed. No additional meetings beyond the site visit are included in this task. Task 2: Watershed Modeling and Technical Memo Barr will use the stormsewer information collected in Task 1 to create an XP-SWMM model of the existing conditions of the watershed. The model will delineate watersheds to catch basin clusters and storage areas. The model will be run for the 10- and 100-year, 24-hour storms using Atlas 14 precipitation values. The watershed will also be modeled using P8 to determine pollutant loads and the efficiency of the ponds in removing total suspended solids and total phosphorus. The deliverable will include:

Mapping showing the 10- and 100-year elevations of ponds, as well as any other major areas of flooding in the watershed

A technical memo describing the methodology used in the modeling effort as well as results of the existing conditions modeling, identifying locations of deficiencies in the stormsewer system

One round of edits with CRWD is included This task includes one (1) meeting at either CRWD’s or the City of Lauderdale’s offices, at a point in the project determined by CRWD. Schedule Assuming that Notice to Proceed is granted on May 21, the following is the proposed schedule:

Anna Eleria, CRWD May 7, 2015 Page 2

W:\06 Projects\Lauderdale\Eustis Street Stormwater Improvement Project\H-H Modeling\Eustis Street Regional Modeling Change Order.docxP:\Mpls\23 MN\62\23621162 Eustis St Strmwtr Improvement\ProjRiskMgmt\Additional Modeling Scope\Eustis Street Regional Modeling Change Order.docx

Task 1 Completion: June 15, 2015 Task 2 Draft Memo Completion: July 15, 2015 Task 2 Completion: August 15, 2015

Budget Task 1: $3,170 Task 2: $10,335 Total: $13,505 Our understanding is that this scope of work will be added to the existing Eustis Street Green Infrastructure project as a change order. Please contact me if you have any questions about our costs or scope of work. Sincerely, Kurt Leuthold P.E. Vice President Barr Engineering Co.

i:\532\53207001\GIS\Final_stormwater_system_map_081408.mxd

!

! !

!

!

!!

!

!

!

!!

!

!

")")!(!(")

")")

")")")")

")

")

")

")")

!(

!(

!(

!(

")")

")")

")

")

")

!(

#*

#*

!(

!( !( !(

")")

")

")")

")")

")

")

")")#*

!( !(!(

!(

")

")

")

")

!(")

!(

")

")

")")

") ")

")

") ")") ")

")")")

")") ")

")

")")

")")

")

") ")")

")

")

!(

!(

!(

#*

!(

")") ")

")")

")

")

")

!(

!(

!(")

")

")")")

")

")")

!(!( ")")")

") !(

!(

!(")

#*

") ")")

")")

")") ")

")")

!(

")

#*

#*

")

")

")")

!(

#*

#*

#*

#*

#*

#*#*

!(

#*

")

") ")

!( ")") ")

")")

")

")")

") ")")

")

")")

")

#*

!(") ")

")")

")") ")

")")

")

")

!(")

")

!(

#*

")

")")

")

")

!(!(

!(!(

!( !(

!(

!(!(

!(

!(

")

")")!(

")

")

")

")

")

")

")

")")

")

")")

")")")

")")

!(

!(

!( ")

!(!(

")

!(

")")

#*

#*# *

")")

")

")")

")

")

!(

!(

!(

")!(

")")

")")

")

")

#*

")

!( ")")")

")!(

!(

!(")!(

")") !(")")

") ")!(

!(

")") ")") ") ")

")

")

!(

")

!(

!(

!(

!(

")")

!(

,

, ,

,

, ,

,, ,

,

,,

,

,

,, , , ,

,,

,

,

,

,,

,

,

,

,

,

,

,

, , ,

,

,

,

,

,

,

,,,

,

,

,

,

,,

,

,

,

,

,,

,

,

,

,

,,

, ,

, , ,,,

,

,

,

,

,

,

,

, ,

,

,,

,

,

,

,

,

,

,

,

, ,, ,,

,,, ,,

,

,

,

,,

,

,, , ,,,

,

,,, ,,

,

,

,

,

,

, ,

,

,

,,

,,

,

,,,,

,

,, ,

, ,

,

,

,

,

,,

,,

,

,

,,

,

,

,,

,,

,

,,

,,

,

,

, , ,

,

,

,

, ,

,

, ,

,

,,,

,,,

,

,

,

,

,,

,,

,,

,

,

,, , ,

,

,

, Larpenteur Avenue

Hig

hway

280

Roselawn Avenue

Eust

is S

treet

Fulh

am S

treet

Lake

Stre

et

Ple

asan

t Stre

et

Car

l Stre

et

Mal

vern

Stre

et

Wal

nut S

treet

Ione Street

Spring Street

Summer Street

Idaho Street

Como Avenue

City

of M

inne

apol

is

City of Roseville

City of Falcon Heights

City of St Paul

Ryan Avenue

WalshLake

SeminaryPond

GasperrePond

BrandyChasePond

SA-2

HWY-1

WL-6.1S

WL-3A

WL-8

WL-6.2

WL-5

WL-2

SA-3

SA-4

WL-1

WL-6.1NWL-4

SA-1

WL-3B

Local Surface Water Management PlanMap 1Stormwater System Map

City of Lauderdale

August 2008

±600 6000 Feet

!

Lauderdale City BoundaryParcels

Drainage Areas

") Catch Basin") Catch Basin Sump#* Flared End Section!( Manhole!( Manhole Sump

StormsewerDrainage Direction

City Stormwater Basin

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District.

DATE: May 14, 2015

TO: CRWD Board of Managers

FROM: Britta Suppes, Monitoring Coordinator

RE: 2015 Fish Surveys: Como, Crosby and Little Crosby Lakes

Background

In 2014, the Managers reviewed the Enhanced Lake Biological Monitoring Work Plan, which included

initiating annual fisheries surveys on each CRWD lake (Como, McCarrons, Loeb, Crosby, Little

Crosby). The primary goal of this expanded monitoring is to enhance our understanding of how the

biological, chemical, and physical parameters of a lake interact to shape lake water quality to better

inform in-lake management decisions.

Subsequently, the District contracted with Wenck Associates, Inc. in August 2014 to conduct fish surveys

on Como and Little Crosby Lakes as part of the program’s expanded monitoring goals. This 2014

fisheries data is currently being incorporated into CRWD’s 2014 Lakes Report. Additionally, the 2014

data was provided to the DNR and is being used to better guide their fish population management

strategies (e.g. fish stocking).

Project Overview

CRWD has been developing plans to perform annual fisheries surveys on each District lake in 2015.

CRWD met with the DNR to discuss the proposed 2015 plans and they did not feel McCarrons on Loeb

needed annual fish surveys due to evidence of stable fish populations in these lakes. However, they did

recommend that fisheries surveys be replicated on Como, Crosby, and Little Crosby Lakes in 2015 in

order to capture annual variation in fish populations.

CRWD sought a proposal from Wenck Associates, Inc. that outlines tasks, schedule, and costs required

to perform fisheries surveys on Como, Crosby, and Little Crosby Lakes in 2015. The tasks and schedule

outlined in the 2015 proposal are similar to those performed in 2014 on Como and Little Crosby Lakes.

However, the costs in the 2015 proposal ($19,500) have been reduced in comparison to the 2014

proposal ($19,525), even though an additional lake has been added to the 2015 schedule. This was

achieved by reducing Wenck staff time and augmenting CRWD staff time instead. Also, equipment

purchased in 2014 (i.e. trap nets and gill nets) will be used again in 2015.

Requested Action

Approve Proposal for Fish Monitoring on Como, Crosby, and Little Crosby Lakes for an amount not to

exceed $19,500.

enc: Fish Monitoring on Como, Crosby, and Little Crosby Lakes (Wenck Associates, Inc.) "W:\07 Programs\Monitoring & Data Acquisition\0 Projects\Lakes Biological Monitoring\Fish Surveys\2015 Fish

Surveys\2015FishMemo_Board_051415.docx""

May 20, 2015

Board Meeting

V. E). 2015 Fish Surveys

(Suppes)

Trap net set in a Como Lake 2014

April 24th, 2015 Ms. Britta Suppes Monitoring Coordinator Capitol Region Watershed District 1410 Energy Park Drive, Suite 4 St. Paul, MN 55108 RE: Proposal for Fish Monitoring on Como, Crosby and Little Crosby Lakes Dear Britta: Wenck Associates, Inc. (Wenck) is pleased to present our proposal to conduct fish monitoring on Como, Crosby and Little Crosby Lakes in the Capitol Region Watershed District (CRWD). In 2014, Wenck was contracted by the CRWD to assist with lake fish surveys in two district lakes. Fish populations for lakes within the CRWD are routinely monitored by the Minnesota Department of Natural Resources (DNR). The lakes are monitored on a rotational basis, both across the state and the CRWD, with a subset of lakes monitored each year. In 2014, the DNR monitored Loeb Lake, Crosby Lake and Lake McCarrons while Wenck was contracted to monitor Como Lake at Little Crosby Lake. For the 2015 field season CRWD has indicated they would again like to conduct fish monitoring efforts beyond those conducted by the DNR, to include three lakes Como Lake, Crosby Lake and Little Crosby Lake. Wenck will complete the fish monitoring in the three lakes identified by CRWD following the methods and tasks described below. Task 1: Field Preparation

Prior to conducting fish monitoring, private or public entities must obtain a survey permit from the DNR. Wenck obtained the required survey permit from the DNR for the 2014 sampling effort and will send in the proper document to obtain the 2015 survey permit for Como, Crosby and Little Crosby Lakes. Wenck will coordinate with CRWD to possibly acquire a multi-year fish survey permit from the DNR to cover 2015 and future monitoring years. In addition to the survey permit, field preparation will also include contacting the DNR to obtain their previous survey information for both lakes to obtain sample locations (if possible). In 2014 the survey locations for Como Lake were obtained from the DNR and sampling efforts were conducted

Wenck Associates, Inc. | 1800 Pioneer Creek Center | P.O. Box 249 | Maple Plain, MN 55359-0249

Toll Free 800-472-2232 Main 763-479-4200 Email [email protected] Web wenck.com

Ms. Britta Suppes Monitoring Coordinator Capitol Region Watershed District April 24, 2015

Deploying gill net in Como Lake 2014

at those same previously established locations. Little Crosby Lake had not been previously surveyed by the DNR so new locations were established in 2014. Crosby Lake has been previously surveyed by the DNR and Wenck will obtain the lake management plan and past survey locations from the DNR. As a result the 2015 sampling locations will follow the established DNR locations for Como and Crosby Lake and follow the locations established in 2014 for Little Crosby Lake. Wenck will also review previous catch results to review species that are likely to be collected in 2015. Wenck will prepare field maps with the established sample locations for each lake and provide them to CRWD and the DNR. Wenck will also conduct one half day of field reconnaissance with one CRWD staff to observe each lake, boat launch/access points and survey conditions prior to actual fish monitoring. Task 2: Fish Monitoring

DNR lake fish monitoring traditionally includes two survey methods: trap nets and gill nets. One net placed in one location left out to collect fish for one day is considered one net set. The total number of sample locations and net sets for a lake is dependent on basin size. Based on the DNR Lake Finder website Como Lake is listed as 68 acres in size and Crosby Lake is listed as 48 acres. Based on review of an aerial photograph Little Crosby Lake is approximately 12 acres. For lakes less than 100 acres the number of trap net sets is up to nine. For smaller lakes gill net sampling is not required. Gill nets can result in a high percent of mortality of fish collected, especially during warm summertime conditions. Discussions between the DNR and CRWD indicate that gill netting is appropriate within these lakes even though they are relatively small. As a result Wenck will conduct trap net and gill net surveys in all three lakes. The target will be to conduct fish monitoring over the course of six to eight field days depending on field conditions. There will be eight trap net sets and two gill net sets on both Como Lake and Crosby Lake. There will be four trap net sets and one gill net set on Little Crosby Lake. Assuming the half day of field reconnaissance of the lakes has been previously completed, the estimated schedule for field sampling will be conducted as follows:

Day 1: Set trap nets at four locations and a gill net at one location on Como Lake. Day 2: Collect and process fish from all four trap nets and the gill net on Como Lake.

Deploy trap nets at four new locations and a gill net at one new location. Day 3: Collect and process fish from all four trap nets and the gill net on Como Lake.

All nets removed. Como Lake survey complete. Day 4: Set trap nets at four locations and a gill net at one location on Crosby Lake. Day 5: Collect and process fish from all four trap nets and the gill net on Crosby

Lake. Deploy trap nets at four new locations and a gill net at one new location. Day 6: Collect and process fish from all four trap nets and the gill net on Crosby

Lake. All nets removed. Crosby Lake survey complete.

2 T:\1486 CRWD\00\Lake Fish Monitoring 2015\16APR2015 - Lake Fish Monitoring Proposal.docx

Ms. Britta Suppes Monitoring Coordinator Capitol Region Watershed District April 24, 2015

Day 7: Set trap nets at four locations and a gill net at one location on Little Crosby

Lake. Day 8: Collect and process fish from all four trap nets and the gill net in Little Crosby

Lake. All nets removed. Little Crosby Lake survey complete.

Wenck will use standard DNR trap nets with ¼ inch mesh on four foot by six foot double frame nets. All trap nets will be deployed and processed following approved DNR methods for fish monitoring. Nets are typically deployed with the lead line net anchored on shore with a stake or rebar. The frame and bag of the trap nets are then stretched out and deployed in water 4 to 8 feet deep and marked with buoy. Fish swimming along shore bump into the lead net and are directed into the frame and bag of the trap net. Wenck will use standard graduated-mesh experimental gill nets per DNR specifications, which include 250 foot long nets with five 50 foot panels of different mesh sizes. The gill nets will be set in water 8 to 15 feet deep, depending on lake conditions, following DNR established survey locations where possible. All fish from the trap nets and gill nets will be collected and placed into sample tubs to reduce fish mortality. Fish will then be identified, counted, weighed to the nearest 0.1 ounces, measured to the nearest 0.1 inches and released. Using these methods for collection and processing, fish trap sampling typically has very low mortality. Gill net sampling will result in some fish mortality. All expired fish collected from gill nets will be properly disposed of as directed by the DNR. All data will be recorded on field sheets or with a field log book, including habitat conditions such as water depth, substrate type and presence of aquatic vegetation. Field photos of fish species, habitat conditions and survey locations will also be recorded. Wenck will coordinate with CRWD field staff to determine if paired water quality samples should be collected from the lake the week that fish monitoring is completed. Task 3: Data Reporting

Wenck prepared a field report detailing the results of the fish monitoring in 2014. The 2014 report included summaries of field conditions, fish species collected, fish lengths and weights, field photos and a comparison of the 2014 results to previous DNR monitoring efforts. CRWD has indicated that in 2015 they would like Wenck to provide data summaries of the 2015 results, which will then be incorporated into an updated report by CRWD staff, following the initial report format. Wenck will compile and summarize the field data from the 2015 surveys for all three lakes and provide these data summaries to CRWD for district staff to utilize to prepare the 2015 field report. Wenck will submit the results of the 2015 fish monitoring to the DNR, which is required as part of the survey permit conditions. Optional Task – Near Shore Seining

Depending on lake conditions, trap nets may not always capture an accurate sample of some smaller fish in the lake, including problematic species such as fathead minnows. A near-shore survey for minnows or small bluegills is helpful in identifying the potential for interactions between the fish populations and lake water quality. Wenck proposes an optional task to team with Dr. Pat Ceas of St. Olaf University for near-shore seining at up to

3 T:\1486 CRWD\00\Lake Fish Monitoring 2015\16APR2015 - Lake Fish Monitoring Proposal.docx

Ms. Britta Suppes Monitoring Coordinator Capitol Region Watershed District April 24, 2015

four locations on each lake, which would be conducted in one to two field days using one Wenck staff, one CRWD staff and Dr. Ceas. Results would be included in the data summary. Costs for this optional task can be provided if requested. Cost Proposal

Below is a table outlining Wenck’s proposed cost to complete the tasks described above. Wenck proposes completing the project on a time and materials basis.

Task Description Project

Manager Senior

QC Field

Biologist Direct(1) Labor Total

1

Field Prep & Acquire Survey Permit 4 12 $1,800 $1,800

2

Fish Surveys Como, Crosby & Little Crosby 28 4 102 $800 $15,100 $15,900

3 Data Summary 4 12 $1,800 $1,800

Project Total $19,500 1Direct charges are for field equipment and mileage. Schedule

It is our understanding that CRWD would like to time the fish surveys in Como, Crosby and Little Crosby to coincide with the DNR fish surveys which are set for early August 2015. This matches the timing of the 2014 surveys as well as previous DNR survey efforts on these lakes. Wenck would conduct the field preparation and acquire the survey permit during July and plan to conduct monitoring the first two weeks of August, depending on field conditions. A field data summary will then be provided to CRWD by September 15th, 2015. On behalf of the over 250 employee owners of Wenck, thank you for this opportunity to continue to serve the Capitol Region Watershed District. Please contact me at 763-479-4263 or Joe Bischoff at 763-479-4229 should you have any questions regarding our proposal. We are looking forward to the opportunity to work with you again on this project. Sincerely, Wenck Associates, Inc.

Jeff Madejczyk Joe Bischoff Associate Principal

4 T:\1486 CRWD\00\Lake Fish Monitoring 2015\16APR2015 - Lake Fish Monitoring Proposal.docx

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District.

DATE: May 12, 2015

TO: CRWD Board of Managers

FROM: Bob Fossum, Program Manager

RE: Ford Site Redevelopment Update

Background

Ford's former Twin Cities Assembly Plant will be redeveloped in the coming years on more than 135 acres

of land situated along the Mississippi River. The City of St. Paul’s vision for the site is that it will be a

livable, mixed-use neighborhood that looks to the future with clean technologies and high quality design for

energy, buildings and infrastructure. At the May 6, 2015 Board meeting, the Mangers reviewed how the

stream corridor restoration opportunity at the Ford Site was identified and ranked in the 2010 WMP.

Issues

The Ford Site Redevelopment represents a tremendous opportunity to Bring Water Back to St. Paul. Clearly

defining the District’s Goal and Vision for stormwater and water features at the Ford Site will prove useful

for the City as they develop their Public Realm Plan for the site. Staff have drafted a Goal/Vision statement

for the Board to consider. Staff will review the draft statement with the Board.

Requested Action

Review of the draft Ford Site Stormwater Goal/Vision Statement

enc: Ford Site Stormwater Goal/Vision Statement (draft)

Summary of Sustainability Goals for the Ford Site (see Goal 6.0, pg. 2)

W:\06 Projects\Ford Site\2015 Stormwater Feasibility\Brd Memo - Ford Update 5-12-15.docx

May 20, 2015

Unfinished Business VI. C)

Ford Site Update

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District

Ford Site Water Resource Goal/Vision Statement

Goal/Vision: Bring Water Back to St. Paul by reestablishing Hidden Falls Creek on the Ford Site and

incorporating sustainable, green infrastructure throughout the site that cleans stormwater and provides

community amenities.

To achieve this goal, the following design objectives should be achieved:

1. Protect Hidden Falls Creek by achieving pre-settlement runoff rates.

2. Optimize stormwater management to maximize public value while preserving developable area.

3. Ensure baseflow delivery to Hidden Falls Creek.

4. Develop green infrastructure that is resilient to climate change.

5. Develop green infrastructure that is sustainable to maintain by both the private and public sector.

W:\06 Projects\Ford Site\2015 Stormwater Feasibility\Ford Site Goal Statement draft, 05-13-2015.docx

The ultimate goal of the Ford Site Sustainable Redevelopment Report is to establish performance thresholds for site redevelopment ... ... inspiring policy makers and developers to make this site a national model for sustainable brown-field redevelopment.

Sustainable redevelopment of the 135-acre Ford site is a high priority for the City, regional and state agencies, the Ford Site Planning citizen task force, and much of the public.

A redeveloped Ford site can demonstrate that residents, employers, workers, and visitors can enjoy all the amenities and comforts of modern living while using much less energy, producing clean energy on site, reducing waste, reducing and treating storm-water runoff, restoring a natural ecosystem, and providing an infrastructure system that reduces vehicle trips and encourages walking, biking, and transit.

The report identifies key components of sustainable redevelopment for the Ford site, outlining goals, strategies and performance thresholds for each.

The District Sustainability Standards have eleven components: 1.0 Building Energy 2.0 Transportation & Public

Realm Network 3.0 Materials 4.0 Water & Wastewater 5.0 Solid Waste 6.0 Stormwater & Groundwater 7.0 Soil 8.0 Vegetation & Habitat 9.0 Recreation & Public Space 10.0 Night Sky Radiation 11.0 Urban Heat Island

1.0 Building Energy Sustainability Goals

• To maximize the use of renewable energy for buildings and infrastructure.

• To reduce operating energy use in all buildings and infrastructure.

• To maximize energy self-sufficiency. Minimum Performance Thresholds

1.1 Meet energy use and greenhouse gas (GHG) emission targets* specified in Minnesota 2030 program to be required for State buildings through Buildings, Benchmarks & Beyond (B3) Guidelines and consistent with Saint Paul’s Green Building Policy:

• 60% reduction by 2010 • 70% reduction by 2015 • 80% reduction by 2020 • 90% reduction by 2025 • 100% reduction by 2030

Ultimate Condition ⇒ Zero net energy and zero greenhouse gas

emissions*. * Greenhouse gas (GHG) emissions can be calculated based on operating energy, as well as on many other contributing factors measured by the Minnesota Building Carbon Calculator, including water, wastewater, waste, embodied in materials, transportation, vegetation, and soil. Energy use can be measured per square foot, per person, per hour of operation, per product output relative to equivalent industrial process, or a combination of these.

2.0 Transportation & Public Realm Network Sustainability Goals

• To create a transportation infrastructure that balances modal choice between walking, biking, and vehicular movement.

• To reduce average vehicle miles driven by persons living, working and visiting the site.

• To increase average walking and biking miles per year for persons living or working on the site.

• To reduce energy use and Green House Gas (GHG) emissions) related to high vehicle miles driven (VMD).

• To reduce adverse human health affects (such as asthma) related to air pollution.

• To maximize the diverse human benefits (such as childhood obesity reduction and lower family transportation costs) of safe and pleasurable pedestrian and multi-modal access to and from (on-site & off-site) transit stops, daily services, institutions, parks and public spaces.

Minimum Performance Thresholds 2.1 Provide mix of office, industrial, residential, and commercial uses on site that complement the existing mix of uses and services in the area. 2.2 Minimum residential density (du/acre) greater than 20 du/acre (Density to be calculated using LEED-ND computational method outlined NPD Credit 2.). 2.3 Minimum Non-Residential floor area ratio (FAR) greater than 1.50 (Non-Res. FAR to be calculated using LEED-ND computational method outlined NPD Credit 2.).

2.4 Internal street connectivity (intersections/square mile according to LEED-ND definition) equal to or greater than the highest connectivity found in adjacent neighborhoods, computed for adjoining area of same size and shape as site.

2.5 All streets and intersections to utilize design methodologies consistent with 2010 ITE Manual: Designing Walkable Urban Thoroughfares: A Context Sensitive Approach, An ITE Recommended Practice and “Complete Streets” design principles.

2.6 Zero dead ends and zero cul-de-sacs except to serve the rear of buildings. 2.7 95% of streets lined on both sides with sidewalks minimum 54” wide. (Per ADA requirements)

2.8 Provide designated bike lanes on streets at least every ½ mile. 2.9 50% of all residential and non- residential building entries within ¼ mile of vehicle sharing site or transit services.

Ultimate Condition ⇒ Decrease average vehicle miles driven to 4,000

or less per driving resident per year, a 50% reduction in carbon per mile traveled.

3.0 Materials Sustainability Goal

• To reduce embodied energy use, GHG emissions and other environmental impacts associated with building, infrastructure, and landscape materials..

Minimum Performance Threshold 3.1 Life-cycle performance of all buildings at least 10% better than the average building using Athena EcoCalculator in six of the eight output areas, or comply with State of Minnesota B3 Guidelines, Materials and Waste, section M.1 -- Life Cycle Assessment of Building Assemblies.

3.2 Comply with State of Minnesota B3 Guidelines, Materials and Waste, section M.2 -- Environmentally Preferable Materials.

3.3 At least 30 percent of the total value of materials used in site infrastructure are composed of pre- and post-consumer content.

Ultimate Condition ⇒ Life-cycle performance of all buildings at least

30% better than the average building using Athena EcoCalculator in seven of the eight output areas.

⇒ Exceed required performance criteria inof Minnesota B3 Guidelines, Materials and Waste, section M.2 -- Environmentally Preferable Materials, by 10 percent.

⇒ At least 50 percent of the total value of materials used in site infrastructure are composed of pre- and post-consumer content.

4.0 Water & Wastewater Sustainability Goals

• To reduce potable water consumption in all buildings and landscapes.

• To reduce wastewater leaving the site to treatment plants from all buildings and landscapes by increasing onsite wastewater reuse.

Minimum Performance Thresholds 4.1 Predicted potable water use must be 30% below EPA Policy Act of 1992 (consistent with Saint Paul Green Building Policy). 4.2 Predicted water use for landscaping must be at least 50% less than a traditionally irrigated site (consistent with Saint Paul Green Building Policy). 4.3 Fifty percent (50%) less black and/or gray water leaving the site than an average or typical development, during design phase and long-term operations.

Ultimate Condition ⇒ No more than five percent (5%) of the total

daily water requirement/person imported to site.

⇒ Zero gray water leaving the site, and ten percent (10%) or less black water leaving the site during design phase and long-term operations.

F o r u p d a t e d r e p o r t : h t t p : / / w w w . s t p a u l . g o v / i n d e x . a s p x ? N I D = 1 3 1 8

As published May 2, 2011 in the

Ford Site Sustainable Redevelopment Report: Summary of Sustainability Goals for the Ford Site

The Ford Site Sustainable Redevelop-ment Report was produced by the City of Saint Paul with the assistance of consultants on the "Ford Site Green Team" under a grant provided by the Minnesota Pollution Control Agency.

5.0 Solid Waste Sustainability Goals

• To reduce solid waste from construction in all buildings and landscapes.

• To reduce solid waste from operation of all buildings and landscapes.

Minimum Performance Thresholds 5.1 Seventy five percent (75%) of all construction waste must be recycled (consistent with Saint Paul Green Building Policy). 5.2 Fifty percent (50%) less household, commercial and industrial solid waste leaving the site than an average or typical development.

Ultimate Condition ⇒ Zero construction, residential, commercial and

industry solid waste leaving the site.

6.0 Stormwater & Groundwater Sustainability Goals

• To minimize surface and ground water pollution. • To minimize negative impacts of development

on the hydrological cycle by treating stormwater close to where it falls and recharging groundwater through infiltration as local soils and subsurface conditions allow.

• To not exceed natural erosion and sedimentation levels in streams and lakes.

• To protect plant, invertebrate, and animal life in lakes and streams.

• To utilize stormwater runoff as a resource rather than as a waste product.

• To pre-treat all water flowing to Hidden Falls and maintain a more constant flow volume.

Minimum Performance Thresholds 6.1 Comply with current local regulations for stormwater runoff volume and rate control (City of St. Paul, Minnesota Pollution Control Agency (MPCA), Capitol Region Watershed District (CRWD), State of Minnesota B3 guidelines). 6.2 Reduce runoff volume by at least 90% on an annual basis by infiltration (50%) and evaporation or re-use (40%) or provide a corresponding water quality benefit. 6.3 Reduce pollutants for which the water is impaired to 10% less than levels identified in Total Maximum Daily Load (TDML) study for that portion of the Mississippi River. 6.4 Maintain minimum cover (e.g. >3’) above bedrock and follow Minnesota Pollution Control Agency (MPCA) Guidelines on infiltrating. 6.5 Produce and implement a Stormwater Pollution Protection Plan per MPCA guidelines for use pre, during and post construction.

Ultimate Condition ⇒ Zero discharge of untreated stormwater from

site. ⇒ Re-direct low flows on adjacent properties

away from untreated storm sewers and onto the Ford site for treatment in site’s comprehensive stormwater management system.

7.0 Soil Sustainability Goals

• To protect and restore soil structure, stability, and biological health to optimize plant health and species richness and optimize water infiltration and filtration.

• To reduce soil loss and minimize disturbance of existing quality soil.

• To maximize on-site reuse of existing soils. • To address impacted soil conditions on site.

Minimum Performance Thresholds 7.1 Meet MPCA soil cleanup criteria with land use restrictions. 7.2 Meet State of Minnesota B3 Guidelines for soil management: • Organic matter >1.5% by dry weight • Bulk density < than 1.5 mg/m3 • Aeration porosity (% large pore volume) >2% • Infiltration rate > 0.25 in/hr site wide, >1 in/hr

in stormwater treatment areas • Soil pH 6-8.5 • Cation exchange capacity > 5 meg/100g • Potassium > than 124 lbs/acre • Phosphorus > than 44 lbs/acre • Mycorrhizae — Minimum 2 species in soil that

are naturally found in Minnesota • Soluble salt content < 600 ppm • Stormwater Pollution Prevention Plan (SWPPP)

- create and implement • Hydric and mesic soils profile >10% of open

space • Organic horizon > 4 inches throughout

Ultimate Condition ⇒ Meet thresholds 7.1 & 7.2, and in addition; ⇒ Meet Minnesota Pollution Control Agency

(MPCA) soil cleanup criteria with no land use restrictions.

⇒ Provide on-site composting location and provide composted material for on-site public and private gardening, landscaping and soil restoration.

⇒ Hydric and mesic soils—profile > 20% of proposed open space.

⇒ Organic horizon > 6 inches. ⇒ Minimum 4 species of mycorrhizae in soil that

are naturally found in Minnesota.

8.0 Vegetation & Habitat Sustainability Goals

• To maximize biodiversity of the site and provide maximum possible contribution to local landscape ecology.

• To reduce destruction and removal of existing vegetation.

• To increase vegetation on site with new plantings.

• To provide wildlife habitat. • To maximize ecological services on site and for

the surrounding area. Minimum Performance Thresholds

8.1 Comply with applicable codes, regulations and standards, including B3 guidelines, St. Paul zoning and land use regulations, and City of St Paul River Corridor Overlay District. 8.2 Greater than fifty percent (50%) aerial tree cover over all impervious surfaces on-site except roofs. 8.3 Greater than fifty percent (30%) of buildings include vegetated roofs. 8.4 Greater than twenty percent (20%) of site open space covered with vegetation. 8.5 Greater than seventy five percent (75%) native species in new landscaping, including keystone species; (at minimum) Burr Oak, Hickory/Walnut & Big Blue Stem. 8.6 Minimum plant species diversity greater than eighty percent (80%) species of native vascular flora – herbaceous perennials. No invasive species on the site. Use ten percent (10%) or less species of native Deciduous Trees and > 3 species of native Coniferous Trees, but not greater than ten percent (10%) of any one tree genus, so as to avoid catastrophic tree loss e.g. Dutch Elm Disease, Emerald Ash Borer. 8.7 Do not disturb habitat or natural resources determined significant by Minnesota DNR Natural Heritage Program or by local, state or federal government; maintain or install appropriate buffer width around significant habitats that comprise part of a development.

Ultimate Condition ⇒ 70% aerial tree cover over non-roof

impervious surfaces, and 50% of buildings include vegetated roofs.

⇒ 100% native tree, shrub, perennial and vine plantings compositions.

⇒ A species-rich, resilient, urban forest with ≥ 50% of tree population exceeding 20 inch Diameter Breast Height (DBH) and 20% exceeding 30 inch DBH.

⇒ Diverse ecosystem that supports at least the presence of key species as follows:

Amphibians (3 species); interior forest birds (10 species); interior grassland birds (3 species); bats (2 species); reptile (2 species).

9.0 Recreation & Public Space Sustainability Goals

• To improve personal health through increased physical activity, by providing on site facilities for a variety of active and passive exercise and recreational choices such as recreational walking and biking, informal play, or participation in organized sport activities.

• To encourage the development of (and connections to) biking and walking trails within, to, from and through the site.

• To encourage provision of and/or access to a comprehensive set of public gathering spaces for a full range of civic and community events.

• To provide space for community gardens, local agriculture, and the sale of locally-grown food.

Minimum Performance Thresholds 9.1 Comprehensive network of ADA accessible off-road trails for walking and biking throughout the site, connecting the site’s major uses and services and public spaces.

9.2 Four programmed sports fields on site. 9.3 One, large outdoor public gathering space for events, picnics, farm market, etc. 9.4 Twice weekly farmers’ market on or within one half (1/2) mile of site. 9.5 Three or more indoor public spaces (or private spaces accessible to public use) for community meetings, clubs, parties, etc.

Ultimate Condition ⇒ Each resident shall have potential to receive

60% of their produce from on site food production facilities or gardens during the local growing season, and 20% during the winter months.

⇒ 1/2 acre civic or passive public space within ¼ mile of 90% of dwellings, and non-residential building entries.

⇒ Create community center for public gathering, civic events, and sports & recreational programming for all ages.

10.0 Night Sky Radiation Sustainability Goals

• To reduce light emitted from site to the sky at night.

• To protect the environments of predator & prey. Minimum Performance Threshold

10.1 The average phototropic lumens for the entire site shall be 40,000 lumens per net acre using full-cutoff (fco) lighting, with no one individual area of the site exceeding 70,000 lumens/net acre.

Ultimate Condition ⇒ The average phototropic lumens for the entire

site shall be 10-20,000 lumens per net acre using full-cutoff (fco) lighting with no one individual area of the site exceeding 40,000 lumens/net acre.

11.0 Urban Heat Island Sustainability Goals

• To reduce urban heat island effects on site by reducing the heat absorption of materials used in buildings, landscaping and infrastructure.

• To increase vegetative cover to help keep the site and buildings cool in the summer.

• To reduce the need for air conditioning and irrigation in the summer.

Minimum Performance Threshold 11.1 Average surface albedo for the entire site greater than 0.1.

Ultimate Condition ⇒ Average surface albedo for the entire site

between 0.15-0.3.

F o r u p d a t e d r e p o r t : h t t p : / / w w w . s t p a u l . g o v / i n d e x . a s p x ? N I D = 1 3 1 8

Browse to the complete Ford Site Sustainable Redevelopment Report at the link below to see complete information about the categories, strategies for sustainable design, general findings, resources, and next steps to achieve this ambitious vision.

Our Mission is to protect, manage and improve the water resources of Capitol Region Watershed District.

DATE: May 14, 2015

TO: CRWD Board of Managers and Staff

FROM: Mark Doneux, Administrator

RE: May 20, 2015 Administrator’s Report

1) Administrator Approved or Executed Agreements

a) Agreement with Great River Greening for planting assistance during Montana Greenbrier and Montreal

SPSVP planting events – not to exceed $10,000.

b) Agreement with Waterfront Restoration, LLC for 2015 Lake McCarrons weed harvesting – not to

exceed $10,290.

c) Consultant Services Agreement with Bluestem Heritage Group for the Willow Reserve History Report

– not to exceed $6,250.

d) Consultant Services Agreement with Wenck Associates, Inc. for annual maintenance and technical

assistance related to the Highland Ravine Stabilization project – not to exceed $5,000 annually.

e) Consultant Services Agreement with Wenck Associates, Inc. for AHUG Exfiltration Monitoring and

Well Design – not to exceed $10,000.

2) Board Approved or Executed Agreements

a) Consultant Services Agreement with Houston Engineering, Inc. for 2015 BMP Database hosting and

maintenance services – not to exceed $21,863.

b) Joint Powers Agreement with City of Roseville for the Upper Villa Stormwater Volume Reduction

Project – not to exceed $817,500.

c) Special Grant Agreement with Roseville Area Schools – ISD 623 for a stormwater management plan

and BMP construction at Harambee Elementary School – not to exceed $55,000.

d) Consultant Services Agreement with Barr Engineering Co. for the Lafayette Park Campus Feasibility

Study – not to exceed $59,945.

3) General updates including recent and upcoming meetings and events

a) Trout Brook Nature Sanctuary planting and opening celebration with Great River Greening and the

City of Saint Paul is May 30. The volunteer planting event is coordinated by Great River Greening and

the opening celebration will be held afterwards.

b) Saint Paul Street Vitality Program boulevard rain garden planting events are planned for Saturday,

May 16 (Montana-Greenbrier project area) and Saturday, June 6 (Montreal Avenue project area).

c) Landscape Revival Native Plant Expo and Market is Saturday June 6 from 9 am – 3 pm at the Cub

Foods Community Pavilion on Larpenteur in Roseville.

d) Bugs Night Out, macroinvertebrate sampling event for children is Thursday, June 18 at Como

Lakeside Pavilion from 6 – 7:30 pm.

e) Como Lake Land and Water Cleanup with the Minnesota Standup Paddleboarders Association is

Sunday, July 12 from 10 am – 1 pm at Como Lakeside Pavilion.

4) CRWD events and meetings

a) Next Board meeting is Wednesday, June 3, 2015 from 6:00 – 8:00 p.m.

b) Next CAC meeting is the annual tour, Wednesday, June 10, 2015 from 7:00 – 9:00 p.m.