Upload
pb7o61
View
235
Download
0
Embed Size (px)
Citation preview
7/27/2019 Matter in Times New Roman
1/33
1 | P a g e
1. INTRODUCTION
1.1 Introduction:
Madhya Pradesh Power Generating Co. Ltd. (MPPGCL) is a wholly owned company
of MP Government engaged in generation of electricity in the state of Madhya
Pradesh. It is a successor entity of erstwhile Madhya Pradesh State Electricity Board
(MPSEB). The Company, while operating and maintaining its existing units, is also
constructing new Power Plants for increasing capacity in the State of Madhya Pradesh.
1.2Brief History of the MPPGCL and context of its Formation:
The Company has taken over the Generation activities of MPSEB.
The Company is a public company fully owned by Govt. of M.P.
The Company was incorporated on 22.11.2001.
The Company obtained the Certificate of Commencement of Business on 16-07-2002.
The Registered office of the Company is at Shakti-Bhawan, Rampur, Jabalpur
The Authorized Capital of the Company at present is Rs. 10,000 Cr. (Ten
Thousand Crore) divided into 10,000,00,000 Shares of Rs.100 each.
The issued, subscribed and paid up capital is Rs.2,865,84,64,400 (Rs. Two
Thousand Eight Hundred Sixty Five Crores Eighty Four Lacs Sixty Four
Thousand Four Hundred only) divided into 28,65,84,644 shares of Rs.100 each.
The Govt. of MP vide Gazett Notification (Extraordinary) No. 226 notified
order no. 3679/ FRS/ 18/13/2002 Dtd. 31-05-2005 to give effect to the
reorganization of the Madhya Pradesh State Electricity Board. The Para2(a) of
the said order is reproduced below :
With effect from 01.06.2005 (the effective date) the function of Generation of
electricity as specified in schedule A to the Transfer Scheme Rules, 2003, shall
be conducted and shall be carried on by Madhya Pradesh Power Generating
Company Limited as its own business and not as an agent of or on behalf of the
Madhya Pradesh State Electricity Board.
The opening balance sheet of Madhya Pradesh Power Generating Company
Limited as on 31.05.2005 has also been notified.
Accordingly, the Company has started functioning independently, from 01-06-
2005.
Save Electricity - Save Power - Save Money
7/27/2019 Matter in Times New Roman
2/33
2 | P a g e
1.3 Introduction of Gandhi Sagar Dam
The Gandhi Sagar Dam is one of the four majordamsbuilt on India's Chambal River.
The dam is located in the Mandsaurdistrict of the state of Madhya Pradesh. It is a
masonry gravity dam, standing 62.17 metres (204.0 ft) high, with a gross storage
capacity of 7.322 billion cubic meters from a catchment area of
22,584 km
2
(8,720 sq mi). The dam's foundation stone was laid by Prime Minister ofIndia Pandit Jawaharlal Nehru on 7 March 1954, and construction of the main dam
was completed in 1960. Additional dam structures were completed downstream in the
1970s.
The dam sports a 115-MW hydroelectricpower station at its toe, with five 23-MW
generating units each providing a total energy generation of about 564 GWh. The
water released after power generation is utilized for the irrigation of 427,000 hectares
(1,060,000 acres) by the Kota Barrage, which is located 104 kilometers (65 mi)
downstream of the dam, near the city
ofKota in the state ofRajasthan.The dam's reservoir area is thesecond-largest in India (after
the Hirakud Reservoir), and attracts
a large number of migratory and
non-migratory birds throughout the
year. The International Bird LifeAgency (IBA) has qualified the
reservoir under "A4iii" criteria, as
the congregation of water birds isreported to exceed 20,000 at some
points.
http://en.wikipedia.org/wiki/Damhttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Chambal_Riverhttp://en.wikipedia.org/wiki/Mandsaurhttp://en.wikipedia.org/wiki/Indian_statehttp://en.wikipedia.org/wiki/Madhya_Pradeshhttp://en.wikipedia.org/wiki/Prime_Minister_of_Indiahttp://en.wikipedia.org/wiki/Prime_Minister_of_Indiahttp://en.wikipedia.org/wiki/Pandit_Jawaharlal_Nehruhttp://en.wikipedia.org/wiki/Hydroelectrichttp://en.wikipedia.org/wiki/Kota_Barragehttp://en.wikipedia.org/wiki/Kota,_Rajasthanhttp://en.wikipedia.org/wiki/Rajasthanhttp://en.wikipedia.org/wiki/Hirakud_Damhttp://en.wikipedia.org/wiki/Hirakud_Damhttp://en.wikipedia.org/wiki/Rajasthanhttp://en.wikipedia.org/wiki/Kota,_Rajasthanhttp://en.wikipedia.org/wiki/Kota_Barragehttp://en.wikipedia.org/wiki/Hydroelectrichttp://en.wikipedia.org/wiki/Pandit_Jawaharlal_Nehruhttp://en.wikipedia.org/wiki/Prime_Minister_of_Indiahttp://en.wikipedia.org/wiki/Prime_Minister_of_Indiahttp://en.wikipedia.org/wiki/Madhya_Pradeshhttp://en.wikipedia.org/wiki/Indian_statehttp://en.wikipedia.org/wiki/Mandsaurhttp://en.wikipedia.org/wiki/Chambal_Riverhttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Dam7/27/2019 Matter in Times New Roman
3/33
3 | P a g e
1.4 Geography of Gandhi Sagar
The Chambal River (known in ancient times as the Chamranyavati River) rises in
the Vindhya Range at an elevation of 853 meters (2,799 ft), 15 kilometers (9.3 mi)
west-southwest of the town ofMhow, nearIndore. It flows north-northeast
through Madhya Pradesh, runs for a time through Rajasthan, then forms the boundary
between Rajasthan and Madhya Pradesh before turning southeast to join the YamunaRiverin the state ofUttar Pradesh. Its total length from its source to
its confluence with the Yamuna River is 900 kilometers (560 mi).
The Chambal and its tributaries drain the Malwa region of northwestern Madhya
Pradesh, while its tributary, the Banas, which rises in the Aravalli Range, drains
southeastern Rajasthan. At its confluence with the Yamuna, the Chambal joins four
other rivers the Yamuna, Kwari, Sind, and Pahujat Pachnada nearBhareh in Uttar
Pradesh, at the border of the Bhind and Etawah districts. The river is drained by a rain-
fed catchment area with an average annual rainfall of 860 millimeters (34 in), a
temperature range of between 2 C (36 F) and 40 C (104 F), and a relative humidityranging from 30% to 90%.
Between 344 kilometers (214 mi) and 440 kilometers (270 mi) from the Chambal'ssource is an area of deep gorges; the Gandhi Sagar Dam is located in the middle reach
of this gorge section. The dam is situated at a distance of 168 kilometers (104 mi)
from the district administrative headquarters ofMandsaur.
1.5 Construction History of Gandhi Sagar
The Chambal River Valley Development marked one of the landmark actions ofthe First Five-Year Plan launched by the Government of India in 1951, afterIndia
attained independence in August 1947. The Chambal River had not until then beenutilized for any major developmental works, and was proposed to be developed under
a joint initiative of the state governments of Madhya Pradesh and Rajasthan. The
three-stage proposal, drawn up in 1953, called for three dams to provide hydroelectric
power generation, and a downstream barrage to utilize stored waters released from the
upstream dams forirrigation. The river's drop of 625 meters (2,051 ft) between itssource in Mhow and the city of Kota, which marks the exit of the river from its gorge
section into the plains of Rajasthan, was seen as having great hydroelectric potential.
1.5.1 Stage I
The first stage of the development involved construction of the Gandhi Sagar Dam to
a height of 62.17 meters (204.0 ft) as a storage dam to store 7,322,000,000 cubic The
hydroelectric power station is located at the toe of the dam on the right bank. The total
flow through the five turbines is 311.15 m3/s. The power station has an installation of
142 MW with five turbines of 23 MW and one unit of 27 MW capacities. The powerstation is 65 meters (213 ft) long and 56 feet (17 m) wide. Power is supplied first to
http://en.wikipedia.org/wiki/Vindhya_Rangehttp://en.wikipedia.org/wiki/Mhowhttp://en.wikipedia.org/wiki/Indorehttp://en.wikipedia.org/wiki/Madhya_Pradeshhttp://en.wikipedia.org/wiki/Yamuna_Riverhttp://en.wikipedia.org/wiki/Yamuna_Riverhttp://en.wikipedia.org/wiki/Uttar_Pradeshhttp://en.wikipedia.org/wiki/Confluencehttp://en.wikipedia.org/wiki/Malwahttp://en.wikipedia.org/wiki/Banas_Riverhttp://en.wikipedia.org/wiki/Aravalli_Rangehttp://en.wikipedia.org/wiki/Rajasthanhttp://en.wikipedia.org/wiki/Kuwari_riverhttp://en.wikipedia.org/wiki/Sindh_Riverhttp://en.wikipedia.org/wiki/Pahuj_Riverhttp://en.wikipedia.org/wiki/Pachnadahttp://en.wikipedia.org/wiki/Bharehhttp://en.wikipedia.org/wiki/Bhind_Districthttp://en.wikipedia.org/wiki/Etawah_Districthttp://en.wikipedia.org/wiki/Gorgehttp://en.wikipedia.org/wiki/Mandsaurhttp://en.wikipedia.org/wiki/Chambal_Riverhttp://en.wikipedia.org/wiki/Five-Year_plans_of_Indiahttp://en.wikipedia.org/wiki/Government_of_Indiahttp://en.wikipedia.org/wiki/History_of_the_Republic_of_Indiahttp://en.wikipedia.org/wiki/History_of_the_Republic_of_Indiahttp://en.wikipedia.org/wiki/Irrigationhttp://en.wikipedia.org/wiki/Irrigationhttp://en.wikipedia.org/wiki/History_of_the_Republic_of_Indiahttp://en.wikipedia.org/wiki/History_of_the_Republic_of_Indiahttp://en.wikipedia.org/wiki/Government_of_Indiahttp://en.wikipedia.org/wiki/Five-Year_plans_of_Indiahttp://en.wikipedia.org/wiki/Chambal_Riverhttp://en.wikipedia.org/wiki/Mandsaurhttp://en.wikipedia.org/wiki/Gorgehttp://en.wikipedia.org/wiki/Etawah_Districthttp://en.wikipedia.org/wiki/Bhind_Districthttp://en.wikipedia.org/wiki/Bharehhttp://en.wikipedia.org/wiki/Pachnadahttp://en.wikipedia.org/wiki/Pahuj_Riverhttp://en.wikipedia.org/wiki/Sindh_Riverhttp://en.wikipedia.org/wiki/Kuwari_riverhttp://en.wikipedia.org/wiki/Rajasthanhttp://en.wikipedia.org/wiki/Aravalli_Rangehttp://en.wikipedia.org/wiki/Banas_Riverhttp://en.wikipedia.org/wiki/Malwahttp://en.wikipedia.org/wiki/Confluencehttp://en.wikipedia.org/wiki/Uttar_Pradeshhttp://en.wikipedia.org/wiki/Yamuna_Riverhttp://en.wikipedia.org/wiki/Yamuna_Riverhttp://en.wikipedia.org/wiki/Madhya_Pradeshhttp://en.wikipedia.org/wiki/Indorehttp://en.wikipedia.org/wiki/Mhowhttp://en.wikipedia.org/wiki/Vindhya_Range7/27/2019 Matter in Times New Roman
4/33
4 | P a g e
the local district and then to other regions of Madhya Pradesh and Rajasthan. The
Gandhi Sagar Dam and Power Station were built at a total cost of about Rs. 2.3 billion.
1.5.2 Stage II
The second stage of development involved the utilization of the water released fromthe Gandhi Sagar Dam through another dam structure, the Rana Pratap Sagar Dam,
located 48 kilometers (30 mi) downstream of the Gandhi Sagar at Rawatbhata in
the Chittorgarh District of Rajasthan. Additional storage at this dam provides an
increase in irrigation benefits from the Kota Barrage, increasing its area of irrigation
from 445,000 hectares (1,100,000 acres) to 567,000 hectares (1,400,000 acres). In
addition, a powerhouse at the toe of the dam provides an additional hydroelectric
power generation capacity of 172 MW from four turbo generators, of 43 MW
capacities each. The second stage was completed in 1970. The power generated at the
Rana Pratap Sagar Dam is shared equally with Madhya Pradesh, as the Gandhi SagarDam provides the stored waters for utilization at this dam.
1.5.3 Stage III
The third and final stage of development envisaged an intermediate dam between the
Rana Pratap Sagar Dam and the Kota Barrage, called the Jawahar Sagar Dam. This
dam is a concrete gravity dam, 45 meters (148 ft) high, located approximately 23
kilometers (14 mi) upstream of Kota Barrage to its southwest, and provides ahydroelectric power generation capacity of 99 MW, with three generator units of 33
MW capacities each. This project was commissioned in 1972.
1.6 Features of Gandhi Sagar
Gandhi Sagar Dam is a masonry gravity dam with a height of 62.17 meters (204.0 ft)
and a length of 514 meters (1,686 ft). The reservoir has a gross storage capacity of
7.32 billion cubic meters, with a live storage of 6.79 billion cubic meters
corresponding to Full Reservoir Level (FRL) at 400 meters (1,300 ft). The spillway of
the dam is designed for a discharge of 21,238 cubic meters per second. There are 10gated spillway spans to pass the designed flood discharge. In addition, 9 river sluices
have also been provided, but these have not been functional.
The hydroelectric power station is located at the toe of the dam on the right bank. The
total flow through the five turbines is 311.15 m3/s. The power station has an
installation of 142 MW with five turbines of 23 MW and one unit of 27 MW
capacities. The power station is 65 meters (213 ft) long and 56 feet (17 m) wide.
Power is supplied first to the local district and then to other regions of Madhya
Pradesh and Rajasthan. The Gandhi Sagar Dam and Power Station were built at a totalcost of about Rs. 2.3 billion.
http://en.wikipedia.org/wiki/Rana_Pratap_Sagar_Damhttp://en.wikipedia.org/wiki/Rawatbhatahttp://en.wikipedia.org/wiki/Chittorgarh_Districthttp://en.wikipedia.org/wiki/Jawahar_Sagar_Damhttp://en.wikipedia.org/wiki/Jawahar_Sagar_Damhttp://en.wikipedia.org/wiki/Chittorgarh_Districthttp://en.wikipedia.org/wiki/Rawatbhatahttp://en.wikipedia.org/wiki/Rana_Pratap_Sagar_Dam7/27/2019 Matter in Times New Roman
5/33
5 | P a g e
1.7 Reservoir
The reservoir created by the dam is the second largest in India (after the Hirakud
Reservoir), with a total area of 723 km2 (279 sq mi). The catchment area of the
Chambal River from the Vindhyachal ranges to the south and Aravalli to the northeast,
covering a drainage area of 22,584 km2
(8,720 sq mi); important tributaries that
discharge into the Chambal upstream of this reservoir include the Shipra, Chhoti,Kalisindh, Ansar, and Rupniya on the eastern side, and the Tilsoi, Edar, Retum and
Shivna in the west. The maximum length and width of the reservoir are 68 kilometers
(42 mi) and 26 kilometers (16 mi), respectively. The Gandhi Sagar Wildlife Sanctuary,
which has an area of 36,700 hectares (91,000 acres), is shared by the Mandsaurand Neemuch districts, in the catchment area of the Gandhi Sagar reservoir. The
sanctuary's forested area was once a hunting area of the Holkarroyal family ofIndore.
The reservoir is under the control of the irrigation and fisheries departments of
the Government of Madhya Pradesh, and is mostly used for fisheries development
also.The mean depth of the reservoir is 11.73 meters (38.5 ft), with a shore development
index of 4.78, and a volume development index of 0.601 at the Full Reservoir Level.
Scientific studies indicate that the reservoir is productive as regards fisheries, with the
reservoir water indicating a moderate-to-high rate ofprimary productivity.Commercial Fisheries was initiated in 195960 in Gandhi Sagar, and has been credited
as the best-managed reservoir in the state. Fish capture in the reservoir is prohibited
between 16 June and 15 August.[ The reservoir attracts a large number of migratory
and non-migratory birds throughout the year, has been qualified under "A4iii criteria"
by the IBA, as the bird congregation is of more than 20,000 waterbeds.
1.8 Suggested Reservoir Amendment
Analysis of hydroelectric power generation performed by the three power plants in the
Chambal valley has been carried out by a non-governmental agency, based onstatistics provided by the Central Electricity Authority under the RTI Act. The results
indicate that the Gandhi Sagar reservoir attained its full storage condition only during
five years of its first five decades of operation. The energy generation of all the three
power plants declined by 25% in the same period of 50 years, relative to the projected
50-year figures. Keeping these aspects in view, it has been suggested that the full
reservoir level in the Gandhi Sagar Dam be reduced by suitable operational guidelines,
which would enable the release of substantial submergence area for cultivation by the
farmers who originally owned these lands.
http://en.wikipedia.org/wiki/Hirakud_Damhttp://en.wikipedia.org/wiki/Hirakud_Damhttp://en.wikipedia.org/wiki/Vindhyachalhttp://en.wikipedia.org/wiki/Aravallihttp://en.wikipedia.org/wiki/Neemuch_districthttp://en.wikipedia.org/wiki/Holkarhttp://en.wikipedia.org/wiki/Indorehttp://en.wikipedia.org/wiki/Government_of_Madhya_Pradeshhttp://en.wikipedia.org/wiki/Primary_productivityhttp://en.wikipedia.org/wiki/Primary_productivityhttp://en.wikipedia.org/wiki/Government_of_Madhya_Pradeshhttp://en.wikipedia.org/wiki/Indorehttp://en.wikipedia.org/wiki/Holkarhttp://en.wikipedia.org/wiki/Neemuch_districthttp://en.wikipedia.org/wiki/Aravallihttp://en.wikipedia.org/wiki/Vindhyachalhttp://en.wikipedia.org/wiki/Hirakud_Damhttp://en.wikipedia.org/wiki/Hirakud_Dam7/27/2019 Matter in Times New Roman
6/33
6 | P a g e
2. Equipment Details of MPPGCL Gandhi Sagar Dam
2.1 Francis Turbine
Francis turbines are most widely used in hydraulic power plant with medium effective
heads. There is a recent tendency that they are being applied to higher heads so that
effective heads range from 20 to 500 m. Since the runner for a Francis Turbine hasfixed blades, efficiency of the turbine in accordance with change of water quantity &
head will be lowered greatly in comparison with other type of hydraulic turbine but it
has high eat efficiency in maximum so that it is expected that it can be operated
effectively in case of the peak load operation or of the installation of many sets of
Francis turbine with a larger reservoir. The structure of the turbine & its runner is
comparatively simple & well researched so that it is easy to be maintained.
The speciation of the SIEMENS and VIOTH Francis turbine are the following:
Maximum Output 34,000 HP (25,4000KW)
Efficiency Head 45.4M
Water Volume 64.7M/
No. Of Revolution 188 R.P.M
Manufacturing No. 141493
The speciation of the HITACHI in Japan Francis turbine is the following:
Maximum Output 34,000 HP (25,4000KW)
Efficiency Head (Max.) 182 ft
Water Volume 64.7M/
No. Of Revolution 188 R.P.M
Manufacturing No. 13888
2.1.1 Installation Methods
Installation methods of Francis turbine differ in accordance with capacity but
generally either single floor concreted arrel or double floor type is adopted.
Double floor type whether they are beam typed or arch typed have on
advantage that they can be disassembled without disassembly of alternators.
7/27/2019 Matter in Times New Roman
7/33
7 | P a g e
Single floor concrete barrel type is applied to the large capacity turbine in which
double floor cannot support the large an advantage of stable operation with
shorter main shaft.
2.1.2 Structures
A Francis turbine has the rotating parts of the turbine is supported by a guide bearing
fixed to the head cover & the weight of hydraulic thrust on the turbine runner & the
weight of turbine rotating parts is supported as weight of generator rotating parts by a
generator thrust bearing. A sealing device is packing through the turbine head covers.
Water operating to the turbine is led from the reservoir to the spiral case controlled in
quantity by wicket gates & reaches the runner. After giving energy to the runner. It
will be discharged through the draft tube liner to the tail race.
2.1.3 Name of the Francis Turbine Parts
In Hitachi ltd names are used as for Francis turbine parts.
Although there may be slight difference between the structures of the turbine supplied
to your power station & the structure of this figure for avoidance of mutual
misunderstanding use these names in case of inquiry of parts or estimates of additional
parts.
1. AIR ADMISSION PIPE
2. SPIRAL CASE
3. STAY RINGE
4. HEAD COVER (OUTER)
5. COVER LINER (OR FACING PLATE)
6. WICKET GATE GLAND
7. WICKET GATE ADJUSTING PEDESTAL
8. ADJUSTING NUT
9. SEGMENT RING SUPPORT
10. SEGMENT RING
11. GATE RING LINER
12. GATE OPERATING LINER
13. HEAD COVER (INNER)
14. UPPER PROTECTING RING HOLDER
15. BOTTEM COVER
16. LOWER PROTECTING
17. LOWER PROTECTING LINER
7/27/2019 Matter in Times New Roman
8/33
8 | P a g e
18. BOTTEM RING
19. BOTTEM RING LINER
20. WICKET GATE LOWER BEARING
21. GUIDE BEARING HOUSING
22. WATER DEFLECTER
23. OIL DAM
24. COOLING COIL
25. BEARING SUPPPORT
26. SCREWED BUSH
27. ADJUSTING BOLT
28. BEARING SUPPORTING PLATE
29. LEAF SPRING
30. SEGMENTAL BEARING
31. BEARING HOUSING COVER
32. NUT GUARED
33. PLAT FROM OF BEARING HOUSING
34. COUPLING NUT
35. COUPLING BOLT
36. LOCKING WASHER
37. MAIN SHAFT
38. SHAFT FLANGE LINER
39. SHAFT SLEEVE
40. COUPLING BOLT
41. WATER SHEDDER
42. RUNNER KEY
43. FLANGE COVER
44. RUNNER
45. RUNNER CROWN
46. RUNNER BLADE
47. SHROUD BLADE
48. WICKET GATE
49. WICKET GATE KEY
50. WICKET GATE LEVER
51. U SHAPED PACKING
52. SHEAR PIN
53. GATE OPERATING RING
54. GATE OPERATING RING PIPE
55. EYE END PIPE
56. LOCKING PLATE
57. TURBINE
7/27/2019 Matter in Times New Roman
9/33
9 | P a g e
58. CONNECTING ROD
59. PIN LINER
60. WALK WAY
61. SEALING BOX
62. BUSHING
63. ADJUSTING NUT
64. STAY VANE
65. ROTATING WEARING RING
66. RUNNER CONE
67. RUNNER CONE FIXING BOLT
68. DRAFT PIPE
If the motion goes far enough, this motion causes the lever arms to pull down on a
thrust bearing, which moves a beam linkage, which reduces a rate of working fluid
entering the cylinder is thus reduced and the speed of the prime mover is controlled,preventing over-speeding. The direction of the lever arm holding the mass will be
along the vector sum of the reactive centrifugal force vector and the gravitational
force. This allows the two masses on lever arms to move outwards against gravity.
2.2 SPIRAL CASING
A spiral casing plays a role to distribute pressured water hade from penstock or head
tank evenly to the wicket gets & the runner.
The Francis turbine has usually a steel plates spiral case.
2.2.1 Construction of spiral case
Spiral case divided into several paces is sent & assembled at site for easiness of
transportation or other reasons.
They are three methods of its jointing.
1. Flange jointing.
2. Riveted jointing.
3. Fixed welded jointing.
1. Flange jointing: - Flanged jointing is applied to a comparatively small spiral
case with which will be divided into two to four pieces while riveted & welded
jointing is applied to a large case which has much division.
In case of flanged jointing the spiral case & the stay ring are fixed together.
7/27/2019 Matter in Times New Roman
10/33
10 | P a g e
2. Riveted jointing: - Hydrostatic pressure test is applied in the shop in case of
flanged jointing & at site in case of riveted & welded jointing if many pressure
tests at site are usually as for welded jointing casings.
Test pressure stipulated in JEC_151 is as follows.
First stage test pressure *1.3(10 minutes)
Second stage test pressure *1.5(1 minutes)
2.3 Runner
A Francis turbine runner is the most important part that is directly connected with the
efficiency. The shape of the runner differs according to the speed but the construction
is simple because of its fixed blades.
2.4 Draft Tube
The kinetic energy of water discharged from the runner is recovered as potential
energy thought a draft tube. The draft tube line generally used for the Francis turbine
is elbow type directly connects to the bottom ring is equipped with steel plates. When
the draft tube becomes large 1-2 center pipers will be equipped to the horizontal part
of the draft tube & steel plates nozzle will be generally equipped to this entrants.
The aim of the draft tube is also to convert the main part of the kinetic energy at the
runner outlet to pressure energy at the draft tube outlet. This is achieved by increasing
the cross section area of the draft tube in the flow direction.
In an intermediate part of the bend however, the draft tube cross sections are decreased
instead of increased in the flow direction to prevent separation and loss of efficiency.
The draft tube cone is a welded steel plate design and consist a normally of two parts.
And lower cone the inlet part of the upper cone is made of stainless steel. It is
normally provided with two manholes for inspection of the runner from below. The
lower part is designed as dismantling piece and is mounted to a flange on the draft
tube bend top. The design is always used for units where the runner is dismantled
downwards. Cone is made in one piece. The draft tube lining is completely embedded
in concrete. The penstock cone and the scroll casing of a submerged turbine can be
drained to a level corresponding to tail water level through the draft tube. The draft
tube is normally filled tube gate.
The turbine governor controls the servomotor, which transfers its force through a rod
to the regulating ring. This turbine governor controls the servomotor, which transfers
its force through a rod to the regulating ring. This transfers the movement to guide
vanes through a rod, lever and link.
7/27/2019 Matter in Times New Roman
11/33
11 | P a g e
2.4.1 Construction
A section through a part of the guide vane cascade, the stay vanes and the runner is the
guide vane exit in flow direction is varied by an equal rotation of each of the guide
vanes.
2.5 Main Shaft
The main shaft of a hydraulic turbine plays a role to transmit the power generated in
the runner generator rotor. The turbine & the generator shaft are coupled by reaming
bolts shaft & the runner or reaming bolts. The turbine main shaft is generally made of
forged steel for it transmits revolution power of the runner & support very large
hydraulic thrust simultaneously. In case of large capacity hydraulic turbine, weld
structure is sometimes applied.
It is most important to deal it with great care during assembly or disassembly. This
joint may be aborted reamed or friction coupling where the torques transferred by
means of shear or friction. Oil reservoir is bolted to the turbine shaft altogether with
the construction of the bearing system.
This bearing is a rather simple and commonly used design and has a simple way of
working and bearing is split in two halves and mounted on the upper flange of the
upper cover. The bearing pad support ring consists of two segments bolted together
and mounted to the underside of the bearing house. Shaped leading ramps ensuringstable centering of the turbine shaft. In the pad support ring there are also four oil
pockets.
2.6 Main Guide Bearing
Self-oil lubricating system is mostly applied to the main guide bearing of a vertical
shaft type hydraulic turbine. There are two types for the system is usually used. The
segmental type has many conveniences of easiness in adjusted maintenance and
replacement. There are two types of the system segment and cylindrical guide on the
other hand it is necessary that most care should be taken of its adjustment.
Bearing diameter Below 450 451-600 600-1000
Gap in radius 0.09-0.11 0.11-0.13 0.14-0.16
Bearing diameter - 1001-1500 1501-2000
Gap in radius - 0.17-0.19 0.20-0.22
7/27/2019 Matter in Times New Roman
12/33
12 | P a g e
2.7 Sealing Device
A sealing device box is provided where the main shaft passes through the head plays a
role to prevent the leakage from the water passage to the head cover.
Standard gapes between the rotating parts of shaft and sealing boxes are shown below.
Sealing box inner diameter Gap in diameter
120-180 0.540-0.660
180-260 0.540-0.660
260-360 0.660-0.790
360-500 0.840-0.980
The seal surfaces are lined with Babbitt metal, and depending on speed and size there
are as small radial clearances as 0.2-0.4 mm between the surfaces of the shaft seal and
the sleeve (B).
The sleeve is made of corrosion resistant material with the special pumping ringsystem mentioned above; the clearances in the seal box will run without water when
the turbine is running. This is why the seal box can be given a design without contact
between the Babbitt lined labyrinth and the shaft sleeve. A labyrinth this type is
suitable for operation in sand will reach the seal while the turbine is running at normal
speed.
Tube gate is exposed to a downstream water pressure. A water leakage flow may then
through the upper labyrinths and the box. This leakage water is removed from the box
by siphon pipe to the powerhouse drainage pump sump. For very deep submergence of
the turbine an inflatable rubber seal ring (A) is installed in the labyrinth seal box. This
ring is inflated during stand still in order to prevent leakage. During operation the air
pressure inside the rubber seal is released and the rubber is not in contact with the
shaft.
This air may be supplied through a separate air supply pipe connected to the shaft seal
box. Instead of the design described above, the shaft seal box may also be designed
with carbon seal and it cannot rings. These are without clearance to the rotating parts
and therefore subject to carbon damage.
7/27/2019 Matter in Times New Roman
13/33
13 | P a g e
2.8 Wicket Gate
Wicket gate plays the following three rules.
1. They guide water effectively from the spiral case to the runner.
2. They adjust the quality of water to the runner according to the variation of the
operating load.3. They sat off flowing water and stop the turbine.
Self-oil lubricating system is mostly applied to the main guide bearing of a vertical
shaft type hydraulic turbine. These are two types for the system is usually used. The
segmental type has many has many conveniences of easiness in adjusted maintenance
and replacement. These are two types of the system and cylindrical guide on the other
hand it is necessary that most care should be taken of its adjustment.
2.9 Wicket Gate Bearing
As to this type of wicket gate bearing an upper bearing a fixed to the turbine head
cover & a lower. A bearing fitting to the wall ring support they hydraulic pressure on
the wicket gate supported by a lower bearing.
This type of guide bearing used for turbine whose capacity is below medium where
there are no special condition.
1. UPPER BEARING: Upper bearing made by the cast iron or to gunmetal.
And these bearing are equipped with u shape packing & 2-5mm vertical
clearance.
2. LOWER BEARING: The lower bearing is also made by gun metal. The
lower bearing is so get at it upper shoulder in case of low head designed that
it supports the height of wicket turbine.
2.10 Air Pipe
2.10.1 Purpose
As for Francis turbine noise or vibration may be caused by water flow with in the
draft pipe during light load for its prevention beforehand the air admission into the
runner outlet portion is generally applied.
7/27/2019 Matter in Times New Roman
14/33
14 | P a g e
2.10.2 Structure
According to a normal structure as air is taken in through a T-shaped pipe from
outdoors. They depend upon containing quantity of sand and soil, operation and load,
but check pipes when needed.
3. COMPRESSOR USED IN PLANT
They are mainly three type of compressor used in Gandhi Sagar dam there name are
following.
3.1 Kirloskar Compressor
The compressor consists block in which piston executes a reciprocating motion it is
fitted with cylinder heads containing suction and delivery valves which are operated
automatically by difference of pressure across them.
3.1.1 Control System
As it receives pressure raises one to fall in air demand some firm of automatic
controls necessary to check the air delivery. This is controlled by an air
governor which is adjusted to come out when a fixed maximum pressure is
reached in air receives and to cut in again when it receives pressure has reduced
to the minimum pressure through a differential range of governor.
3.1.2 Lubricating System
In order to reduce the wear of lubricating parts all are lubricated by pressure
feed pump oil circuit diagram the details of oil flow path. Oil is pipe to the main
bearing feed its adjacent crank pin through the holes drilled in the crank shaft.
The connecting rods are opened to convey oil to the gudgeon pin bearing is
taken to the gudgeon pin through pipes attached to the connecting rods. Then oil
is splashed through the gudgeon pin to the cylinder, which lubricates it.
The pressure of the oil has been maintained between to 1to 8kg\cm2
7/27/2019 Matter in Times New Roman
15/33
15 | P a g e
3.1.3 Cooling System
The generation of heat by compressor makes it necessary to ensure that the m/c
is adequately cooled in order to do this the cylinder and then heads are
surrounding by water jackets.
3.1.4 Maintenance Schedule
Grease the nipples {motor bearings}.
Allow the safety valve to lift at the correct pressure.
Drain receiver and after cooler.
Check the opening range of the air governor filter and replace it if necessary.
Check the air filter and clean it if necessary.
3.1.5 Accessories
Non Return Valve
Safety Valve
Suction Silence
Pulsation Silence
After Cooler
Moisture Separator Low Oil Pressure Safety Switch
Low Water Pressure Safety Switch
3.2 Holman Compressor
When the set is received unpacks carefully cleans thoroughly and inspects for
possible loss of parts. When anything is found among report immediately. If it has
been dispatched from the works a considerable time before being put into service, also
remove the doors of crankcase and clean the interior, also remove the wall cover
inspect and, if necessary clean the valves.
Before replacing the cover oil the cylinder wall is to ensure lubricating of the piston
during the first few stocks take great care that everything is correctly replace see that
all nuts are properly tight end and that splits pins are inserted where provisions has
been made for them.
7/27/2019 Matter in Times New Roman
16/33
16 | P a g e
3.2.1 Control System
As it receives pressure rises due to fall in air demand some firm of automatic
control is necessary to check the air delivery. This is controlled by an air
governor which is adjusted to cut out when a fixed maximum pressure is
reached in air receives and to cut it again when they receive pressure has
reduced to the minimum pressure through a differential range of governor.
3.2.2 Lubricating System
The compressor has a force feed lubricating system incorporating a gear type
oil pump driven through spur gear from the crankshaft and the oil pressure
throughout the system is indicated by a pressure gauge. The correct working
pressure of the force feed lubricating system accepting the too approximately
15lb\in2.
On to the air compressor the pressure is 30lb\in2
A.Change the lubricating oil in the air compressor as under:
Change after 50 hour.
Change after 100 hour.
Change and the subsequent changes after every 150 house or underconditions change earlier.
B.The oil is taken out at the bottom of the crankcase by opening oil plug
VGG\A-1.
C.For filling new oil in the crankcase there is a fillies pipe VGC\B-118
fitted at the top of the crankcase wards the flywheel.
3.2.3 Cooling System
The generation of heat by compressor makes it necessary to ensure that the
machine is adequately cooled in order to do this the cylinder and then heads are
surrounding by water jackets
3.2.4 Maintenance Schedule
Grease the nipples {motor bearings}.
7/27/2019 Matter in Times New Roman
17/33
17 | P a g e
Allow the safety valve to lift at the correct pressure.
Drain receiver and after cooler.
Check the operating range of the air governor.
Check the air governor fitter and replace if necessary.
Check the air fitter and clean if necessary.
Fill crankcase to correct level with oil. Grease all nipples.
Check water in radiator.
Check the oil pressure.
3.2.5 Accessories
Non return valve
Safety valve
Suction silence
Pulsation vessel
After cooler
Moister separator
Low oil pressure safety switch
Low water pressure safety switch
4. GOVERNOR USED IN PLANT
A governor is a specific type of governor that controls the speed of the engine by
regulating the amount of fuel {or working fluid} admitted, so as to maintain a nearly
constant whatever the load or fuel supply conditions. It uses the principle of
proportional control. It is most obviously seen on stem engine where it regulates the
admission of steam into the cylinder.
It is also found on internal combustion engine and various fueled turbine, in some
modern striking clocks. The device shown is from steam engine power is supplied to
the governor from the engine output shaft or connected to the lower shaft.
7/27/2019 Matter in Times New Roman
18/33
18 | P a g e
The centrifugal governor is used to control the dynamic system. The dynamic system
includes forces which are generally centrifugal in nature and are acted when governor
moves.
4.1 Principle and Operation of Governor Used
4.1.1 Principle
The action of this principle is exactly like that of the centrifugal governor of the stem
engine. Which checks and corrects any irregularities almost before they become
evident? And in like manner no unbalanced deficiency in the animal kingdom can
even reach any conspicuous magnitude, because it would make it self felt at the very
first step, by rendering existence difficult and extinction almost sure soon to follow.
4.1.2 Operation
The device shown is from a steam engine. Power supplied to the governor from the
engines output shaft by a belt or chain connected to the lower belt wheel. The
governor is connected to a throttle valve that regulates the flow of working fluid
(steam) supplying the prime mover (prime mover is not shown here). As the speed of
the prime mover increases, the central spindle of the governor rotates at a faster rate
and the kinetic energy of balls increases.
7/27/2019 Matter in Times New Roman
19/33
19 | P a g e
Generally fly ball are used, another type of centrifugal governor consists of pair of
masses on a spindle inside a cylinder. The masses or cylinder being coated with pads,
somewhat like a drum brake.
The rate of working fluid entering the cylinder is thus reduced and the speed of prime
mover is controlled. For preventing over speeding mechanical stops may be used to
limit the range of throttle motion, as seen near the masses. The direction of lever arm
holding the mass will be along the vector sum of reactive centrifugal force vector and
gravitational force. This allows the two masses on lever arms to move outwards and
upwards against gravity.
5. INSTALLED CAPACITY OF PLANT
6. RESERVOIR LEVEL AT HYDRO POWER PLANT
A centrifugal governor is a specific
type ofgovernorthat controls
the speed of an engine by
regulating the amount
offuel (orworking fluid) admitted,
so as to maintain a near-constant
speed, irrespective of the load orfuel-supply conditions. It uses the
principle ofproportional control.
http://en.wikipedia.org/wiki/Governor_(device)http://en.wikipedia.org/wiki/Speedhttp://en.wikipedia.org/wiki/Enginehttp://en.wikipedia.org/wiki/Fuelhttp://en.wikipedia.org/wiki/Working_fluidhttp://en.wikipedia.org/wiki/Loadhttp://en.wikipedia.org/wiki/Proportional_controlhttp://en.wikipedia.org/wiki/Proportional_controlhttp://en.wikipedia.org/wiki/Loadhttp://en.wikipedia.org/wiki/Working_fluidhttp://en.wikipedia.org/wiki/Fuelhttp://en.wikipedia.org/wiki/Enginehttp://en.wikipedia.org/wiki/Speedhttp://en.wikipedia.org/wiki/Governor_(device)7/27/2019 Matter in Times New Roman
20/33
20 | P a g e
7. HOW HYDRO POWER PLANT WORKS?
Worldwide, hydropower plants produce about 24 percent of the world's electricity and
supply more than 1 billion people with power. The world's hydropower plants output a
combined total of 675,000 megawatts, the energy equivalent of 3.6 billion barrels
ofoil, according to the National Renewable Energy Laboratory. There are more than
2,000 hydropower plants operating in the United States, making hydropower the
country's largest renewable energy source.
In this article, we'll take a look at how falling water creates energy and learn about the
hydrologic cycle that creates the water flow essential for hydropower. You will also
get a glimpse at one unique application of hydropower that may affect your daily life.
7.1 The Power of Water
When watching a river roll by, it's hard to imagine the force it's carrying. If you have
ever been white-water rafting, then you've felt a small part of the river's power. White-water rapids are created as a river, carrying a large amount of water downhill,
bottlenecks through a narrow passageway. As the river is forced through this opening,
its flow quickens. Floods are another example of how much force a tremendous
volume of water can have.
Hydropower plants harness water's energy and use simple mechanics to convert that
energy into electricity. Hydropower plants are actually based on a rather simple
concept -- water flowing through a dam turns a turbine, which turns a generator.
Here are the basic components of a conventional hydropower plant:
SIMPLE BEGINNING
Use of hydropower peaked in the
mid-20th century, but the idea of
using water for power generation
goes back thousands of years. A
hydropower plant is basically an
oversized water wheel. More than
2,000 years ago, the Greeks are said
to have used a water wheel for
grinding wheat into flour. These
ancient water wheels are like the
turbines of today, spinning as a
stream of water hits the blades. The
gears of the wheel ground the wheat
into flour.
http://science.howstuffworks.com/environmental/energy/oil-refining.htmhttp://www.nrel.gov/http://science.howstuffworks.com/nature/natural-disasters/flood.htmhttp://science.howstuffworks.com/nature/natural-disasters/flood.htmhttp://www.nrel.gov/http://science.howstuffworks.com/environmental/energy/oil-refining.htm7/27/2019 Matter in Times New Roman
21/33
21 | P a g e
1) DamThe dam is the most important component of hydroelectric power plant. The dam is
built on a large river that has abundant quantity of water throughout the year. It should
be built at a location where the height of the river is sufficient to get the maximum
possible potential energy from water.
2) Water ReservoirThe water reservoir is the place behind the dam where water is stored. The water in the
reservoir is located higher than the rest of the dam structure. The height of water in the
reservoir decides how much potential energy the water possesses. The higher theheight of water, the more its potential energy. The high position of water in the
reservoir also enables it to move downwards effortlessly.
The height of water in the reservoir is higher than the natural height of water flowing
in the river, so it is considered to have an altered equilibrium. This also helps to
increase the overall potential energy of water, which helps ultimately produce more
electricity in the power generation unit.
3) Intake or Control GatesThese are the gates built on the inside of the dam. The water from reservoir is released
and controlled through these gates. These are called inlet gates because water entersthe power generation unit through these gates. When the control gates are opened the
water flows due to gravity through the penstock and towards the turbines. The water
flowing through the gates possesses potential as well as kinetic energy.
4) The PenstockThe penstock is the long pipe or the shaft that carries the water flowing from the
reservoir towards the power generation unit, comprised of the turbines and generator.The water in the penstock possesses kinetic energy due to its motion and potential
energy due to its height.
The total amount of power generated in the hydroelectric power plant depends on the
height of the water reservoir and the amount of water flowing through the penstock.The amount of water flowing through the penstock is controlled by the control gates.
5) Water TurbinesWater flowing from the penstock is allowed to enter the power generation unit, which
houses the turbine and the generator. When water falls on the blades of the turbine the
kinetic and potential energy of water is converted into the rotational motion of theblades of the turbine. The rotating blades cause the shaft of the turbine to also rotate.
The turbine shaft is enclosed inside the generator. In most hydroelectric power plants
there is more than one power generation unit.
7/27/2019 Matter in Times New Roman
22/33
22 | P a g e
There is large difference in height between the level of turbine and level of water in
the reservoir. This difference in height, also known as the head of water, decides thetotal amount of power that can be generated in the hydroelectric power plant.
There are various types of water turbines such as Kaplan turbine, Francis turbine,
Pelton wheels etc. The type of turbine used in the hydroelectric power plant depends
on the height of the reservoir, quantity of water and the total power generation
capacity.
6) GeneratorsIt is in the generator where the electricity is produced. The shaft of the water turbine
rotates in the generator, which produces alternating current in the coils of thegenerator. It is the rotation of the shaft inside the generator that produces magnetic
field which is converted into electricity by electromagnetic field induction. Hence the
rotation of the shaft of the turbine is crucial for the production of electricity and this is
achieved by the kinetic and potential energy of water. Thus in hydroelectricity power
plants potential energy of water is converted into electricity.
The water in the reservoir is considered stored energy. When the gates open, the water
flowing through the penstock becomes kinetic energy because it's in motion. The
amount of electricity that is generated is determined by several factors. Two of those
factors are the volume of water flow and the amount of hydraulic head. The headrefers to the distance between the water surface and the turbines. As the head and flow
increase, so does the electricity generated. The head is usually dependent upon the
amount of water in the reservoir.
7.2 Pumped-Storage Plants
There's another type of hydropower plant, called the pumped-storage plant. In a
conventional hydropower plant, the water from the reservoir flows through the plant,exits and is carried downstream. A pumped-storage plant has two reservoirs:
Upper reservoir - Like a conventional hydropower plant, a dam creates a reservoir.
The water in this reservoir flows through the hydropower plant to create electricity.
Lower reservoir - Water exiting the hydropower plant flows into a lower reservoir
rather than re-entering the river and flowing downstream.
Using a reversible turbine, the plant can pump water back to the upper reservoir. This
is done in off-peak hours. Essentially, the second reservoir refills the upper reservoir.
By pumping water back to the upper reservoir, the plant has more water to generate
electricity during periods of peak consumption.
7/27/2019 Matter in Times New Roman
23/33
23 | P a g e
7.3 Surge tank
A surge tank (or surge drum) is a standpipe or storage reservoirat the downstream end
of a closed aqueduct or feeder or a dam or barrage pipe to absorb sudden rises of
pressure, as well as to quickly provide extra water during a brief drop in pressure.
In mining technology, ore pulp pumps use a relatively small surge tank to maintain asteady loading on the pump.
Forhydroelectric poweruses, a surge tank is an additional storage space or reservoir
fitted between the main storage reservoir and the power house (as close to the power
house as possible). Surge tanks are usually provided in high or medium-headplants
when there is a considerable distance between the water source and the power unit,necessitating a long penstock. The main functions of the surge tank are: 1. when the
load decreases, the water moves backwards and gets stored in it. 2. When the load
increases, additional supply of water will be provided by surge tank.
In short, the surge tank mitigates pressure variations due to rapid changes in velocityof water.
7.3.1 Surge Tank Operation
Consider a pipe containing a flowing fluid. When a valve is either fully or partially
closed at some point downstream, the fluid will continue to flow at the original
velocity. In order to counteract the momentum of the fluid the pressure will rise
significantly (pressure surge) just upstream of the control valve and may result in
damage to the pipe system. If a surge chamber is connected to the pipeline justupstream of the valve, on valve closure the fluid instead of being stopped suddenly by
the valve will flow upwards into the chamber hence reducing the surge pressures
experienced in the pipeline.
Upon closure of the valve, the fluid continues to flow, passing into the surge tank
causing the water level in the tank to rise. The level in the tank will continue to rise
until the additional head due to the height of fluid in the tank balances the surge
pressure in the pipeline.[1]
At this point the flow in the tank and pipeline will reversecausing the level in the tank to drop. This oscillation in tank height and flow will
continue for some time but its magnitude will dissipate due to the effects of friction.
7.4 Spillway
A spillway is a structure used to provide the controlled release of flows from
a dam orlevee into a downstream area, typically being the river that was dammed. In
the UK they may be known as overflow channels. Spillways release floods so that thewater does not overtop and damage or even destroy the dam. Except during flood
periods, water does not normally flow over a spillway. In contrast, an intake is a
structure used to release water on a regular basis for watersupply, hydroelectricity generation, etc. Floodgates and fuse plugs may be designed
into spillways to regulate water flow and dam height. Other uses of the term
http://en.wikipedia.org/wiki/Reservoirhttp://en.wikipedia.org/wiki/Aqueduct_(water_supply)http://en.wikipedia.org/wiki/Water_hammerhttp://en.wikipedia.org/wiki/Water_hammerhttp://en.wikipedia.org/wiki/Hydroelectric_powerhttp://en.wikipedia.org/wiki/Hydraulic_headhttp://en.wikipedia.org/wiki/Surge_tank#cite_note-Marriott-1http://en.wikipedia.org/wiki/Surge_tank#cite_note-Marriott-1http://en.wikipedia.org/wiki/Surge_tank#cite_note-Marriott-1http://en.wikipedia.org/wiki/Damhttp://en.wikipedia.org/wiki/Leveehttp://en.wikipedia.org/wiki/Hydroelectricityhttp://en.wikipedia.org/wiki/Floodgatehttp://en.wikipedia.org/wiki/Fuse_plughttp://en.wikipedia.org/wiki/Fuse_plughttp://en.wikipedia.org/wiki/Floodgatehttp://en.wikipedia.org/wiki/Hydroelectricityhttp://en.wikipedia.org/wiki/Leveehttp://en.wikipedia.org/wiki/Damhttp://en.wikipedia.org/wiki/Surge_tank#cite_note-Marriott-1http://en.wikipedia.org/wiki/Hydraulic_headhttp://en.wikipedia.org/wiki/Hydroelectric_powerhttp://en.wikipedia.org/wiki/Water_hammerhttp://en.wikipedia.org/wiki/Water_hammerhttp://en.wikipedia.org/wiki/Aqueduct_(water_supply)http://en.wikipedia.org/wiki/Reservoir7/27/2019 Matter in Times New Roman
24/33
24 | P a g e
"spillway" include bypasses of dams or outlets of a channels used during high-water,
and outlet channels carved through natural dams such as moraines.
7.4.1 Types
A spillway is located at the top of the reservoirpool. Dams may also have bottom
outlets with valves or gates which may be operated to release flood flow, and a few
dams lack overflow spillways and rely entirely on bottom outlets.
The fuse plug is designed to over-top and wash out in case of a large flood, greater
than the discharge capacity of the spillway gates.
Although it may take many months to restore the fuse plug and channel after such anoperation, the total damage and cost to repair is less than if the main water-retaining
structures had been overtopped. The fuse plug concept is used where it would be verycostly to build a spillway with capacity for the probable maximum flood.
7.4.2 Chute Spillway
Chute spillways are common and basic in design as they transfer excess water from
behind the dam down a smooth decline into the river below. These are usually
designed following an ogee curve. Most often, they are lined on the bottom and sides
with concrete to protect the dam and topography. They may have a controlling device
and some are thinner and multiply lined if space and funding are tight. In addition,they are not always intended to dissipate energy like stepped spillways. Chute
There are two main types of spillways:
controlled and uncontrolled.
A controlled spillway has mechanical
structures or gates to regulate the rate of
flow. This design allows nearly the full
height of the dam to be used for water
storage year-round, and flood waters can be
released as required by opening one or more
gates.
An uncontrolled spillway, in contrast, does
not have gates; when the water rises above
the lip or crest of the spillway it begins to be
released from the reservoir. The rate of
discharge is controlled only by the depth of
water within the reservoir. All of the storage
volume in the reservoir above the spillway
crest can be used only for the temporary
storage of floodwater, and cannot be used aswater supply storage because it is normally
empty.
In an intermediate type, normal level
regulation of the reservoir is controlled by
the mechanical gates. If inflow to the
reservoir exceeds the gate's capacity, an
artificial channel called either
an auxiliary or emergency spillway that isblocked by a fuse plug dike will operate.
http://en.wikipedia.org/wiki/Morainehttp://en.wikipedia.org/wiki/Reservoir_(water)http://en.wikipedia.org/wiki/Ogee_curvehttp://en.wikipedia.org/wiki/Fuse_plughttp://en.wikipedia.org/wiki/Dike_(construction)http://en.wikipedia.org/wiki/Dike_(construction)http://en.wikipedia.org/wiki/Fuse_plughttp://en.wikipedia.org/wiki/Ogee_curvehttp://en.wikipedia.org/wiki/Reservoir_(water)http://en.wikipedia.org/wiki/Moraine7/27/2019 Matter in Times New Roman
25/33
25 | P a g e
spillways can be ingrained with a baffle of concrete blocks but usually have a 'flip lip'
and/or dissipater basin which creates a hydraulic jump, protecting the toe of the damfrom erosion.
7.4.2 Stepped Spillway
Stepped channels and spillways have been used for over 3,000 years. Recently, newconstruction materials (e.g. RCC, gabions) and design techniques (e.g. embankment
overtopping protection) have increased the interest in stepped spillways and
chutes. The steps produce considerable energy dissipation along the chute and reducethe size of the required downstream energy dissipation basin.
Research is still active on the topic, with newer developments on embankment damoverflow protection systems,converging spillwaysand small weir design.
7.4.3 Bell-mouth spillways
Some spillways are designed like an inverted bell so that water can enter all around theperimeter. These uncontrolled spillway devices are also called morning
glory, plughole, glory holeor bell-mouthspillways. In areas where the surface of the
reservoir may freeze, bell-mouth spillways are normally fitted with ice-breaking
arrangements to prevent the spillway from becoming ice-bound. Chaffey Dam, located
near Wales in Australia has a classic example of an inverted-bell spillway.
In some cases bell-mouth spillways are gate controlled. The spillway at Hungry Horse
Dam (pictured right), the highest morning glory structure in the world, is controlled by
a 64-by-12-foot (20 by 3.7 m) ring gate. However the largest remains in LakeBerryessa, measuring 72 feet in diameter at the lakes surface.
7.4.4 Design Consideration
The largest flood that needs be considered in the evaluation of a given project,
regardless of whether a spillway is provided; i.e., a given project should have
structures capable of safely passing the appropriate spillway design flood (SDF). A
100-year recurrence interval is the flood magnitude expected to be exceeded on theaverage of once in 100 years. It may also be expressed as an exceedance frequency
with a one per cent chance of being exceeded in any given year.
7.4.5 Safety
Spillway gates may operate suddenly without warning, under remote control.
Trespassers within the spillway run the risk of drowning. Spillways are usually fenced
and equipped with locked gates to prevent casual trespassing within the structure.
Warning signs, sirens, and other measures may be in place to warn users of the
http://en.wikipedia.org/wiki/Hydraulic_jumphttp://en.wikipedia.org/wiki/Stepped_spillwayhttp://en.wikipedia.org/wiki/Inverted_bellhttp://en.wikipedia.org/wiki/Chaffey_Damhttp://en.wikipedia.org/wiki/Hungry_Horse_Damhttp://en.wikipedia.org/wiki/Hungry_Horse_Damhttp://en.wikipedia.org/wiki/Lake_Berryessahttp://en.wikipedia.org/wiki/Lake_Berryessahttp://en.wikipedia.org/wiki/Lake_Berryessahttp://en.wikipedia.org/wiki/Lake_Berryessahttp://en.wikipedia.org/wiki/Hungry_Horse_Damhttp://en.wikipedia.org/wiki/Hungry_Horse_Damhttp://en.wikipedia.org/wiki/Chaffey_Damhttp://en.wikipedia.org/wiki/Inverted_bellhttp://en.wikipedia.org/wiki/Stepped_spillwayhttp://en.wikipedia.org/wiki/Hydraulic_jump7/27/2019 Matter in Times New Roman
26/33
26 | P a g e
downstream area of sudden release of water. Operating protocols may require
"cracking" a gate to release a small amount of water to warn persons downstream.
The sudden closure of a spillway gate can result in the stranding of fish, and this is
also usually avoided.
7.5 The Generator
The heart of the hydroelectric power plant is the generator. Most hydropower plants
have several of these generators.
The generator, as you might have guessed, generates the electricity. The basic process
of generating electricity in this manner is to rotate a series of magnets inside coils of
wire. This process moves electrons, which produces electrical current.
The Hoover Dam has a total of 17 generators, each of which can generate up to 133megawatts. The total capacity of the Hoover Dam hydropower plant is 2,074
megawatts. Each generator is made of certain basic parts:
Shaft
Exciter
Rotor
Stator
As the turbine turns, the exciter sends an electrical current to the rotor. The rotor is a
series of large electromagnets that spins inside a tightly-wound coil of copper wire,called the stator. The magnetic field between the coil and the magnets creates an
electric current.
In the Hoover Dam, a current of 16,500 amps moves from the generator to the
transformer, where the current ramps up to 230,000 amps before being transmitted.
7.6 Hydrologic Cycle
Hydropower plants take advantage of a naturally occurring, continuous process -- theprocess that causes rain to fall and rivers to rise. Every day, our planet loses a small
amount of water through the atmosphere as ultraviolet rays break water molecules
apart. But at the same time, new water is emitted from the inner part of the Earth
through volcanic activity. The amount of water created and the amount of water lost is
about the same.
At any one time, the world's total volume of water is in many different forms. It can be
liquid, as in oceans, rivers and rain; solid, as in glaciers; or gaseous, as in the invisible
water vapor in the air. Water changes states as it is moved around the planet by windcurrents. Wind currents are generated by the heating activity of the sun. Air-current
http://science.howstuffworks.com/nature/natural-disasters/volcano.htmhttp://science.howstuffworks.com/sun.htmhttp://science.howstuffworks.com/sun.htmhttp://science.howstuffworks.com/nature/natural-disasters/volcano.htm7/27/2019 Matter in Times New Roman
27/33
27 | P a g e
cycles are created by the sun shining more on the equator than on other areas of the
planet.
Air-current cycles drive the Earth's water supply through a cycle of its own, called
the hydrologic cycle. As the sun heats liquid water, the water evaporates into vapor in
the air. The sun heats the air, causing the air to rise in the atmosphere. The air is colder
higher up, so as the water vapor rises, it cools, condensing into droplets. When enough
droplets accumulate in one area, the droplets may become heavy enough to fall back toEarth as precipitation.
The hydrologic cycle is important to hydropower plants because they depend on water
flow. If there is a lack of rain near the plant, water won't collect upstream. With no
water collecting up stream, less water flows through the hydropower plant and less
electricity is generated.
7.7Hydroelectric Footwear
The basic idea of hydropower is to use the power of a moving liquid to turn a turbine
blade. Typically, a large dam has to be built in the middle of a river to perform this
function. A new invention is capitalizing on the idea of hydropower on a much smaller
scale to provide electricity for portable electronic devices.
Inventor Robert Komarechka of Ontario, Canada, has come up with the idea of placing
small hydropower generators into the soles of shoes. He believes these micro-turbineswill generate enough electricity to power almost any gadget. In May 2001,
Komarechka received a patent for his unique foot-powered device.
Wateris one of the most useful
things on Earth. We drink it, bathein it, clean with it and use it to cook
food. Most of the time, it is
completely benign. But in large
enough quantities, the very same
stuff we use to rinse a toothbrush
can overturn cars, demolish houses
and even kill.
Flooding has claimed millions of
lives in the last hundred yearsalone, more than any other weather
phenomenon. Hurricane Katrina in
New Orleans and the 2008 cyclone
that struck Myanmar are recent
examples of the widespread
devastation that flooding can incur.
http://science.howstuffworks.com/environmental/earth/geophysics/h2o.htmhttp://science.howstuffworks.com/environmental/earth/geophysics/earth.htmhttp://science.howstuffworks.com/environmental/earth/geophysics/earth.htmhttp://science.howstuffworks.com/environmental/earth/geophysics/h2o.htm7/27/2019 Matter in Times New Roman
28/33
28 | P a g e
There's a very basic principle to how we walk: The foot falls heel-to-toe during each
step. As your foot lands on the ground, force is brought down through your heel.When you prepare for your next step, you roll your foot forward, so the force is
transferred to the ball of your foot. Komarechka apparently noticed this basic principle
of walking and has developed an idea to harness the power of this everyday activity.
There are five parts to Komarechka's "footwear with hydroelectric generator
assembly," as described in its patent:
As a person walks, the compression of the fluid in the sac located in the shoe's heelwill force fluid through the conduit and into the hydroelectric generator module. As
the user continues to walk, the heel will be lifted and downward pressure will beexerted on the sac under the ball of the person's foot. The movement of the fluid will
rotate the rotor and shaft to produce electricity.
An exterior socket will be provided to connect wires to a portable device. A power-
control output unit may also be provided to be worn on the user's belt. Electronic
devices can then be attached to this power-control output unit, which will provide a
steady supply of electricity.
Fluid - The system will use an electrically conductive
fluid.
Sacs to hold the fluid - One sac is placed in the heel
and another in the toe section of the shoe.
Conduits - Conduits connect each sac to a micro
generator.
Turbine - As water moves back and forth in the sole, itmoves the blades of a tiny turbine.
Micro generator- The generator is located between
the two fluid-filled sacs, and includes a vane rotor,
which drives a shaft and turns the generator.
http://patft.uspto.gov/netacgi/nph-Parser?Sect1http://patft.uspto.gov/netacgi/nph-Parser?Sect17/27/2019 Matter in Times New Roman
29/33
29 | P a g e
8. CONCLUSION
As an undergraduate of the Rajiv Gandhi Technical University studying in Mandsaur
Institute of Technology, I would like to say that this training program is an excellent
opportunity for us to get to the ground level and experience the things that we
would have never gained through going straight into a job. I am grateful to the Rajiv
Gandhi Technical University for giving us this wonderful opportunity.
The main objective of the industrial training is to provide an opportunity to
undergraduates to identify, observe and practice how engineering is applicable in the
real industry. It is not only to get experience on technical practices but also to observe
management practices and to interact with fellow workers.
It is easy to work with sophisticated machines, but not with people. The only chance
that an undergraduate has to have this experience is the industrial training period. I
feel I got the maximum out of that experience. Also I learnt the way of work in an
organization, the importance of being punctual, the importance of maximumcommitment, and the importance of team spirit.
The training program having three destinations was a lot more useful than staying at
one place throughout the whole six months. In my opinion, I have gained lots of
knowledge and experience needed to be successful in a great engineering challenge, as
in my opinion, Engineering is after all a Challenge, and not a Job.
Save Electricity - Save Power - Save Money
7/27/2019 Matter in Times New Roman
30/33
30 | P a g e
9. REFRENCES
1. Madhya Pradesh Power Generating Company Limited
2.http://www.wikipedia.org
3.http://www.howstuffworks.com
4.http://www.mppgenco.nic.in
Save Electricity - Save Power - Save Money
http://www.wikipedia.org/http://www.wikipedia.org/http://www.wikipedia.org/http://www.howstuffworks.com/http://www.howstuffworks.com/http://www.howstuffworks.com/http://www.mppgenco.nic.in/http://www.mppgenco.nic.in/http://www.mppgenco.nic.in/http://www.mppgenco.nic.in/http://www.mppgenco.nic.in/http://www.howstuffworks.com/http://www.wikipedia.org/7/27/2019 Matter in Times New Roman
31/33
31 | P a g e
7/27/2019 Matter in Times New Roman
32/33
32 | P a g e
7/27/2019 Matter in Times New Roman
33/33