Upload
mylfie-orcullo-mezo
View
231
Download
0
Embed Size (px)
DESCRIPTION
MATERIAL QUANTITY AND COSTCOMPUTATION
Citation preview
CHAPTER II
MATERIAL QUANTITY AND COST
COMPUTATION
BEAMS Forms
Lateral Perimeter = 2d + b + 0.10 = 2(0.30) + 0.20 + 0.10 = 0.90
For RB1:length = (4
EMBED Equation.3 18 beams) + (1.5
EMBED Equation.3 1 beam)
+ (3
EMBED Equation.3 1 beam) = 76.5
For RB2:length = (5
EMBED Equation.3 3 beams) + (4.5
EMBED Equation.3 1 beam) = 19.5
For CB:length = (1
EMBED Equation.3 2 beams) = 2.0
Total length: 76.5 + 19.5 + 2.0 = 98.0
Area = PerimeterLength = 0.90
EMBED Equation.3 98.0 = 88.20
# of Plywood:
Order: say 31 pcs. 1/448 plywood
Cost: 31 pcs x Php 260/pc = Php 8,060.00Refer to Table 5-2 by Fajardo
Wood frame using 22 Lumber
Order:31pcs. 25.06 = 767.46 bd.ftCost: 767.46bd.ft. x Php 12.00/bd.ft. = Php 9,209.52 Nails
For beam forms:
Refer to Table 8-10 by Fajardo
Area = 88.20
Using 2d CWN Nails @ 30cm o.c.
Order:88.20
EMBED Equation.3 0.033 = 2.91, say 3 2d NailsCost: 3 x Php 46.50/= Php 139.50
For wood frame (Velasco)
Order:
say 10.5 8d NailsCost: 10.5. x Php 41.50/= Php 435.75For beam scaffolding:
Total length = 98.0
Refer to Table 8-10 by Fajardo
Using 20d CWN Nails @ 30cm o.c.
Order:98.0
0.73 = 71.54, say 72 20d NailsCost: 72. x Php 38.50/= Php 2,772.00 Scaffoldings
Total length = 98.0
Refer to Table 5-3 by Fajardo
Order: Vertical Support (22 Lumber)= 98
EMBED Equation.3 4.0 = 392.0 bd.ft
Horizontal Support (22 Lumber) = 98
EMBED Equation.3 4.7 = 460.60 bd.ftCost: 852.60bd.ft. x Php 12.00/bd.ft. = Php 10,231.20 Steel Requirements
Main Reinforcement
For RB1:L = 474.92
For RB2:L = 140.4
For CB:L = 14
Total length: 474.92 + 140.4 + 14 = 629.32
Using 6m long steel bars
Order:say 105 pcs. 12mm ( steel bars @ 6 longCost: 105 pcs. x Php 185.00/pc. = Php 19,425.00Stirrups
Spacing: based from the specification
Length per stirrup: 0.85
For RB1:
# of stirrups: for 4 length beam:32 per beamfor 3 length beam:26 per beamfor 1.5 length beam:14 per beam
Total # of stirrups: (18 x 33) + (1x 26) + (1x14) = 634 stirrupsFor RB2:
# of stirrups: for 5 length beam:42 per beamfor 4.5 length beam:22 per beam Total # of stirrups: (3 x 42) + (1x 22) = 148 stirrups
For CB:
# of stirrups: for 1 length beam:11 per beamTotal # of stirrups: (2 x 11) = 22 stirrups
Total # of stirrups for all beams: 634 + 148 + 22 = 804 stirrups
Using 6m long steel barsOrder: 804 stirrups x 0.85 =, say 114pcs. 10mm ( steel bars @ 6 longCost: 114 pcs. x Php 125.00/pc. = Php 14,250.00 Tie WireFor RB1:
# of intersection = 634 stirrups6 bars = 3,804 ties
For RB2:
# of intersection = 148 stirrups7 bars = 1,036ties
For CB:
# of intersection = 22 stirrups 8 = 176 ties
Total # of intersection: 3,804 + 1,036 + 176 = 5,016 ties
Using 30cm long ties
5,016 ties0.3 = 1,504.8
Converting to
Order: say 29 #16 G.I. tie wire
Cost: 29. x Php 80.00/ = Php 2,320.00 Concrete MixFor RB1:
Length = 76.5
Volume = 76.5
EMBED Equation.3 0.30
EMBED Equation.3 0.20= 4.59
For RB2:
Length = 19.5
Volume = 19.5
EMBED Equation.3 0.30
EMBED Equation.3 0.20= 1.17
For CB:
Length = 2.0
Volume = 2.0
EMBED Equation.3 0.30
EMBED Equation.3 0.20= 0.12
Total Volume = 4.59
1.17
0.12= 5.91
Refer to Table 1-2 by Fajardo
Using 40 cement Class A Mixture
Order:Cement:5.88
EMBED Equation.3 9.0 = 52.92, say 53 bags
Sand:
5.88
EMBED Equation.3 0.5 = 2.94, say 3
Gravel:5.88
EMBED Equation.3 1.0 = 5.88, say 6
Cost:
53 bags x 225/bags = 11,925.00
3 x 800/ = 2,400.00
6 x 1,200/ = 7,200.00 Total cost: Php 21,525.00
CHAPTER III
MAN POWER, DURATION AND LABOR COST
COMPUTATIONBeam Works
Reinforcements
rate =0.09M-H/kgs
reinforcements:105pcs 12 mm bars,factor 5.33
114pcs 10 mm bars,factor3.7
weight of reinforcements =factor x number of reinforcements
weight of reinforcements =(105pcs x 5.33) +(114pcs x 3.70) = 981.45
M-H = 981.45 x 0.09 M-H/kgs = 88.3305M-H
M-D = , say 11 man-days
Manpower:3 men(3 steel fixers)
Duration =, say 4 days Concreting
Total Volume = 5.91
rate =0.25m/M-D
M-D =
, say 24 man-days
Manpower :4 men(3 masons, 1 laborer)
Duration = 6 days Forms and Scaffoldings
Forms
area =88.20m
rate =3.12M-H/m
carpenter:1.90M-H/m
laborer:1.22M-H/m
M-H =88.20 m x 3.12 M-H/kgs = 275.184M-H
M-D = , say 35 man-days
Scaffolding
sections: say 37 sections
rate =0.7M-H/section
M-H =37 sections x 0.7 M-H/section = 25.90 M-H
M-D = , say 4 man-days
Erecting forms and scaffoldingsrate =1.86m2/MH
M-H =
say 48 M-H
M-D = 6 man-daysRemoval of forms rate =1.86m2/MH
M-H =
say 48 M-HM-D = 6 man-days
Total M-D: 35 + 4 + 6 + 6 = 51 man-daysManpower :8 men(4 carpenters, 4 laborers)
Duration =6.37, say 7 days
Hence, manpower required for beam works,
2 steel fixers
3 masons
4 carpenters
5 laborers
Labor cost
Steel fixers: 2men x 4 days x Php 256/day = 2,048.00
masons: 3men x 6 days x Php 300/day = 5,400.00 carpenters: 4men x 7 days x Php 300/day = 8,400.00 laborers: 5men x 7 days x Php 200/day = 7,000.00 Total cost: Php 22,848.00
MATERIAL QUANTITY AND COST
COMPUTATION
TRUSS
FULL TRUSS
FT-1 (2)
( Using 2 x 4 x 10 )
TOPCHORD = 65.82 bd.ft
WEB MEMBERS = 91.05 bd.ft
(Using 2 x 6 x 10)
BOTTOMCHORD = 186.30 bd.ft
KINGPOST = 16.4 bd.ft
Total length Ft-1 = 438.01 ft
Total board foot = 359.57 bd.ft
Ft - 2
( Using 2 x 4 x 10 )
TOPCHORD = 33.33 bd.ft
WEB MEMBERS = 67.79 bd.ft
( Using 2 x 6 x 10 )
BOTTOMCHORD = 101.02 bd.ft
KINGPOST = 8.2 bd.ft
Total length Ft 2 = 260.89 ft
Total board foot = 203.78 bd.ft
Ft - 3
( Using 2 x 4 x 10 )
TOPCHORD = 23.66 bd.ft
WEB MEMBERS = 24.93 bd.ft
( Using 2 x 6 x 10 )
BOTTOMCHORD = 66.91 bd.ft
KINGPOST = 5.904 bd.ft
Total length Ft 3 = 145.70 ft
Total board foot = 121.40 bd.ft
Ft - 4
( Using 2 x 4 x 10 )
TOPCHORD = 12.20 bd.ft
WEB MEMBERS = 8.27 bd.ft
( Using 2 x 6 x 10 )
BOTTOMCHORD = 34.11 bd.ft
KINGPOST = 3.28 bd.ft
Total length Ft 4 = 68.10 ft
Total board foot = 57.86 bd.ft
Ft - 5
( Using 2 x 4 x 10 )
TOPCHORD = 8.83 bd.ft
BOTTOMCHORD = 16.18 bd.ft
KINGPOST = 2.624 bd.ft
Total length Ft 4 = 40.15 ft
Total board foot = 27.634 bd.ft
HALF TRUSS Ht 2 (4)
( Using 2 x 4 x 10 )
TOPCHORD = 90.18 bd.ft
WEB MEMBERS = 149.83 bd.ft
BOTTOMCHORD = 174.93 bd.ft
Total length Ht 2 = 622.41 ft
Total board foot = 414.94 bd.ft
Ht 3 (6)
( Using 2 x 4 x 10 )
TOPCHORD = 80.95 bd.ft
WEB MEMBERS = 113.36 bd.ft
BOTTOMCHORD = 228.29 bd.ft
Total length Ht 2 = 519.75 bd.ft
Total board foot = 422.60 bd.ft
Ht 4
( Using 2 x 4 x 10 )
TOPCHORD = 8.37 bd.ft
WEB MEMBERS = 7.48 bd.ft
( Using 2 x 6 x 10 )
BOTTOMCHORD = 24.27 bd.ft
Total length Ht 2 = 48.05 bd.ft
Total board foot = 40.12 bd.ft
COMPUTATION OF MATERIAL COST AND LABOR COST
Total length of truss = 2,136.50 ft
Total board foot = 1,654.46 bd.ft
(2 x 4 x 10) Total length = 1,465.73 ft
(2 x 6 x 10) Total length = 677.32 ft
Truss fabrication
Labor rate = 46 (Refer to Velasco , pp 107)
= 35.96 md
Truss erection
Labor rate = 40 (Refer to Velasco , pp 107)
= 41.36 md
77.32 md + 7.11 md
TOTAL = 84.437 mdManpower: 6 men (4 carpenters, 2 helpers)
DURATION: = 15 days
FASCIA BOARD
By direct counting:
Perimeter = 64.5 m = 218.25 ft
No. of lumber = 26.66 pcs say 27 pieces of 6 x 8
NAILS
15 pieces per fascia board
15 pieces x 27 pieces = 405 pieces
Refer to table 8-8 by Fajardo
= 1.06 kg say 1.25 kg
MATERIAL COST
Description Quantity Unit price Total
Wood (2 x 4 x 10) 147 pieces 794 php 116,718 php
Wood (2 x 6 x 10)
68 pieces 1190 php 80,920 php
20mm x 75 mm (bolt) 645 pieces 43 php 27,735 php
Fascia board 27 pieces 300 php 8,100 phpNails (6 d) 1.25 kg 70 php 87.5 php TOTAL = 233,561 phpLABOR COST
Manpower Rate Duration Total
4 carpenters 300/day 15 18,000 php
2 helpers 200/day 15 6,000 php
TOTAL = 24,000 php
TOTAL DIRECT COST = 257,561 php
PURLINS
Total length of purlins = 1,571.12 ft
Total board foot = 785.56 bd.ft
Labor rate = 40 (Refer to Velasco , pp 107)
= 19.64 md say 20 md
Manpower: 4 men (4 carpenters)
DURATION: = 5 days
Nails:
By ratio and proportion
Area = 0.20 (Using 0.7 m spacing)
Area = x (Using 0.5 m spacing)
=
x = 0.15 x 220 m2 = 33 kg
MATERIAL COST
Description Quantity Unit price Total
Wood (2 x 3 x 10) 158 pieces 594 php 93,852 php
Nails (20 d)
33 pieces 55 php 1,815 php
TOTAL = 95,667 phpLABOR COST
Manpower Rate Duration Total
4 carpenters 300/day 5 6,000 php
TOTAL = 6,000 php
TOTAL DIRECT COST = 101,667 php
COLUMNS
C1 & C3
Dimension: 0.30 m x 0.30 m
No. of column: 12 C1 + 3C3 = 15
Height of column: 3.5 + 0.8 = 4.3 m
C2
Dimension: 0.30 m diameter
No. of column: 4.3 m
CONCRETE MIX
C1 & C3
Volume per column = 0.30 m x 0.30 m x 4.3 m = 0.387 m3
Total volume (C1 & C3 only) = 0.387 m x 15 column = 5.805 m3
C2
Volume per column = h = 1.216 m3
Total volume (C2 only) = 1.216 m3 x 3 = 3.648 m3Total volume for all column = 5.805 m3 + 3.648 m3 = 9.453 m3Refer from table 1 2 by Velasco
Using 40 kg Portland cement class A
Cement: 9.453 x 9.0 = 85.077 bags say 86 bags
Sand: 9.453 m3 x 0.50 = 4.73 m3 say 5 m3
Gravel: 9.453 m3 x 1.0 = 9.45 m3 say 10 m3COST
Quantity Unit price Total86 bags 225/bag 19,350 php
5 m3 800/ m3 4,000 php10 m3 1,200/ m3 12,000 php
TOTAL COST = 35,350 php
STEEL REINFORCEMENT
Total length of the main bar reinforcement
Bend @ the base footing
= 0.20 m
Length from footing to ground floor= 0.90 m
Floor to ceiling
= 3.20 m
Floor thickness
= 0.30 m
Anchorage to beam (12 d)
= 0.15 m
4.75 m
C1 & C2
Main rebars:
No. of bars = 6 bars per column
Total no. of bars = 90 pcs (C1 & C2 only)C3
Main rebars:
No. of bars = 8 bars per column
Total no. of bars = 24 pcs (C1 & C2 only)
Total no. of bars for C1 , C2 and C3 = 90 + 24 = 114 pcs
Using 6m long steel bar
Order:
114 x 4.75 = = 90.25 pcs say 91 pcs
Therefore order 91 pcs 12 mm steel bars
Cost:
91 pcs x 185/pc = 16,835.00 phpLATERAL TIES
C1, C2 & C3
Spacing: based from the specification
No. of lateral ties per column = 23 ties
Total no. of lateral ties: 23 ties x 3 column type x 18 # of columns = 1,242 ties
Length of a tie: 1.20 m
Using 6 m long steel bar
= 5 pcsOrder:
= 249 pcs say 91 pcs
Therefore order 249 pcs 10 mm steel bars
Cost:
249 pcs x 125/pc = 31,125.00 phpCOLUMNS
C1 & C3
Dimension: 0.30 m x 0.30 m
No. of column: 12 C1 + 3C3 = 15
Height of column: 3.5 + 0.8 = 4.3 m
C2
Dimension: 0.30 m diameter
No. of column: 4.3 m
TIE WIRE
C1 & C2
No. of intersection per column = 0.30 m x 0.30 m x 4.3 m = 0.387 m3
Total no. of intersection = 138 x 15 columns = 2,070 ties
C3
No. of intersection per column = 8 bars x 23 ties
Total no. of intersection = 184 x 3 columns = 552 ties
Total no. of intersection for C1 , C2 & C3 = 2,622 ties
Using 30 cm long tie wire per tying point
2,622 x 0.30 m = 786.6 m G.I wire
Using no. 16 G.I tie wire:
Order: = 14.84 say 15 kg
Cost:
15 kg x 80/kg = 1,200.00 php HARDWARE
Nails:
C1 & C3 ( Forms for column )
Refer to table 8 10 by Fajardo
Area = 90.30 m2
Using 2d CWN:
Kilogram required = 90.30 m2 x 0.033 = 2.98 kg
Order: 3 kg
Cost: 3 kg x 80/kg = 240.00 php
C2 ( Forms for column )
Refer to table 8 10 by Fajardo
Area = 12.158 m2
Using 2d CWN:
Kilogram required = 12.1583 m2 x 0.033 = 0.40 kg
Order: 0.5 kg
Cost: 0.5 kg x 60/kg = 30.00 php
C1 & C3 ( Forms for column )
For 2 x 2 wood frame (Refer to Velasco)
where D = desired nail size
= 12.66 kgC1, C2 & C3 (Columns scaffolding)
Refer to table 8 10 by Fajardo
Total length = 52.5 + 10.5 = 63 m
Using 20d CWN
Order:
63 x 0.73 = 45.99 kg say 46 kg
Cost:
46 kg x 55/kg = 2,530.00 php
FORMS
C1 & C3
Lateral perimeter = 2( a + b) + 0.20
Lateral perimeter = 2(0.30 + 0.30) + 0.20 = 1.4 m
Total area of the forms;
Area = 1.40 m x 4.3 m x 15 columns = 90.30 m2
No. of plywood forms:
Order:
32 pcs ( x 4 x 8 plywood)Cost:
32 pcs x 260/pc = 8,320 php
For wood frame (Using 2 x 2 lumber)
Order:
32 pcs ( x 4 x 8 plywood) x 29.67 = 949.44 bd.ft
Cost:
949.44 bd.ft x 12/bd.ft = 11,393.28 php
C2
Circumference = 3.1416 x 0.30 = 0.9425 m
Total area of the forms;
Area = 0.9425 m x 4.3 m x 3 columns = 12.1583 m2
Refer to table 5 -2 by Fajardo
Using 1.20 x 2.40 black sheet (4 x 8)
Order:
12.1583 x 0.347 = 4.22 say 5 pcs
Cost:
5 pcs x 1,280/pc = 6,400 php
Vertical support on ribs: 12.1583 x 25 = 303.9575 m
Using 6m long steel bars
Circumferential Ties: 12.1583 x 9.52 = 115.747
Using 6m long steel bars
Order:
50.66 + 19.29 = 69.95 say 70 pcs 10mm steel barCost:
70 pcs x 125/pc = 8,750 php
SCAFFOLDINGS
C1 & C3
Clear height = 3.2 + 0.3 = 3.5 m
Total length = 3.5 m x 15 columns = 52.5 m
Refer to table 5 3 by Fajardo
Vertical support (Using 2 x 2 lumber) = 276.75 bd.ft
Horizontal support (Using 2 x 2 lumber) = 1,102.50 bd.ft
Diagonal braces (Using 2 x 2 lumber) = 614.25 bd.ft
C2
Total length = 3.5 m x 3 columns = 10.5 m
Refer to table 5 3 by Fajardo
Vertical support (Using 2 x 2 lumber) = 49.35 bd.ft
Horizontal support (Using 2 x 2 lumber) = 220.5 bd.ft
Diagonal braces (Using 2 x 2 lumber) = 122.85 bd.ft
Order:
2,386.20 bd.ft Cost:
2,386.20 bd.ft x 12/bd.ft = 28,634.40 phpSUMMARY: MATERIAL COST AND QUANTITIES
MATERIALSQUANTITYUNIT PRICECOST
Premium Cement86 bags19,350.00 php
Washed Sand5 m34,000.00 php
Washed Gravel, 10 m312,000.00 php
12mm x 6mm DRB91 pcs16,835.00 php
10mm x 6mm DRB319 pcs39,875.00 php
# 16 G.I tie wire15 kg1,200.00 php
CWN # 13 kg240.00 php
CWN # 20.5 kg30.00 php
CWN # 446 kg2,530.00 php
x 4 x 8 ordinary plywood32 pcs8,320.00 php
2 x 2 x 10 red lauan3,335.64 bd.ft40,027.00 php
G.I sheet G.16 4 x 85 pcs6,400.00 php
MATERIAL COST 150,807.68 php
MANPOWER COMPUTATION
Steel works
Rate = 0.09
Reinforcements:
91 pcs 12 mm = 5.33
249 pcs 10 mm = 3.7
Total weight: (91 x 5.33) + (249 x 3.7) = 1,406.33 kg
MH = 1,406.33 kg x 0.09 = 126.5697 MH
MD = = 15.82 MD
CONCRETING
Rate = 0.25
Total volume = 5.805 + 3.648
MD = = 15.82 MD
FORMS AND SCAFFOLDING
FORMS
Total Area = 90.30 + 12.1583
Rate = 2.02
MH = 102.4583 x 2.02 = 206.966 MH
MD = = 25.87 MD
SCAFFOLDING
Total # of columns = 18
Rate = 1.2
MH: 18 column x 1.2 = 21.6 MH
MD: = 2.7
ERECTING OF FORMS AND SCAFFOLDINGS
Area = 102.4583 m2
Rate = 1.86
MH: = 55.09 MH
MD = = 6.89 MD
REMOVAL OF FORMS AND SCAFFOLDINGS
Area = 102.4583 m2
Rate = 1.86
MH: = 55.09 MH
MD = = 6.89 MD
Total M D : 25.87 + 2.7 + 6.89 = 42.35 MDTOTAL MANDAYS
For Column Works : 15.82 + 37.812 + 42.35 = 95.98 say 96 MD
Manpower : 8 men (2 steel fixers, 2 masons , 2 carpenters , 2 laborers)
Duration: = 12 daysLABOR COSTManpower Duration Rate Total
2 steel fixers 12 256/day 6,144
2 masons 12 300/day 7,2002 carpenters 12 300/day 7,2002 laborers 12 200/day 4,800
TOTAL COST = 25,344 phpTOTAL DIRECT COST = 176,151.68 PHP
ROOFING
Using Color bond Ttrimdex HI TEN
Available length
= 15 m
Nominal width
= 0.83 m
Effective width coverage
= 0.76 m
Effective area coverage
= 11.4 m2/sheet
Total roof Area = 220 m2
No. of sheets = = 19.30 say 20 sheets
Assuming 5% wastage due to cutting:
Order:
20 sheets + (0.05 x 20 sheets) = 21 sheets
Cost:
21 sheets x ( ) = 13,440 php
Fasteners using umbrella nails ( )
Say umbrella nails per area:
220 m2 x 10 = 2,200 pieces
Order:
= 2,200 pieces
Cost:
19 kg x ( ) = 1,140 php Fascia cover (preprinted)
Available length = 2.44 m
Nominal width = 0.305 m
Thickness = 0.6 m
Effective length = 2.35 m
Perimeter of roof = 65 m
Therefore = 27.66 pieces
Order:
28 pieces
Cost:
28 pieces x ( ) = 16,604 php
Ridge and Hipped roll
Total length = 43.85 m
Using 1.2 m x 2.5 m G.I plain sheet
Width = 120 cm
Effective length = 2.20 m
= 19.23 say 20 pieces
In one G.I plain sheet
= 2 pieces of ridge roll & hipped roll can be made
Order:
# of plain sheet = 10 sheets
Cost:
10 sheets x ( ) = 12,800 phpValley roll
Total length = 13.95 m
Using 1.2 m x 2.5 m G.I plain sheet
Width = 120 cm
Effective length = 2.30 m
= 6.07 say 6 pieces
In one G.I plain sheet
= 2 pieces of valley roll can be made
Order:
# of plain sheet = 3 sheets
Cost:
3 sheets x ( ) = 3,840 php
Gutter
Perimeter of roof = 65 m
Refer to table 6-6 Fajardo
= 27.66 pieces say 28 pieces
G.I sheet = = 2 pieces
Order:
14 sheets
Cost:
14 sheets x ( ) = 17,920 php
ROOFING WORKS SUMMARY: MATERIAL COST AND QUANTITIES
MATERIALSQUANTITYUNIT PRICECOST
Colorbond trimdex Hi-ten21 sheets13,440.00 php
2 1/2 umbrella nails19 kgs1,140.00 php
Fascia cover (prepainted)28 pcs16,604.00 php
G.I sheet27 pcs34,560.00 php
TOTAL = 65,744 php
PAINTING WORKS
1.Masonry paintingArea = 531.2 m2
Neutralizer:
Using Boysen masonry neutralizer
# of gallons = = 13.28 gallons
If one quartz of neutralizer is mixed with 2 gallon of water
Therefore = 5.312 quartz neutralizer
Order:
6 quartz neutralizer x = 1.5 gallons
Cost:
1.5 gallons x ( ) = 510 php
`
First coating:
Using Boysen concrete sealer
# of gallons = = 13.28 gallons
Order:
14 gallonsCost:14 gallons x ( ) = 7,700 php
Final coating:
Using Boysen glass latex
# of gallons = = 13.28 gallons
Order:
14 gallonsCost:
14 gallons x ( ) = 7,560 php
11. Ceiling Painting
Area = 234.68 m2
First coating:
Using Boysen wood primer
# of gallons = = 6.794 gallons
Order:
7 gallons
Cost:
7 gallons x ( ) = 4,060 php
` Paint thinner:
liter thinner will be added to 1 gallon paint
# of gallon of boysen wood primer = 7 gallons
# of gallon of boysen quick drying enamel = 7 gallons
Total = 14 gallons
14 gallons x = 7 liters
7 liters/ 3.78 = 1.85 gallons
Order:
2 gallonsCost:
2 gallons x ( ) = 760 php
111. Accessories
3 roller brush (9) with pan x = 540 php
3 roller brush (9) refill x = 255 php
3 paint brush # 2 x = 270 php
3 paint brush # 1.5 x = 105 phpMANPOWER
Painting works
Rate = 350 x = 27.871
Total area
= 234.68
= 531.2
= 765.88
Therefore = 27.48 say 28 md
Manpower : 4 men (3 painter , 1 helper)
Duration: = 7 daysLABOR COST
Manpower Rate Duration Total
3 painters 300/day 7 6,300 php
1 helper 200/day 7 1,400 php
Roofing works
Rate =0.1345
Total area = 220
Therefore 220 (0.1345 ) = 29.59 mdG.I Fabrication
Rate = 2.3
Total no. of sheets:
Ridge and Hipped roll = 10 sheets
Valley roll
= 3 sheets
Gutter
= 14 sheets
TOTAL = 27 sheets
Therefore = 11.739 md Installation
Rate = 16 x = 4.8768
Total length:
Ridge and Hipped roll = 43.85 m
Valley roll = 13.95 m
Gutter = 65 m
Fascia cover = 65 m
TOTAL = 187.8 m
Therefore = 38.51 md
Total md = 29.59 md + 38.51 md
Total md = 79.839 md
Manpower: 6 men (4 carpenters , 2 helpers)
Duration : = 13.3065 say 14 daysPAINTING WORKS
SUMMARY: MATERIAL COST AND QUANTITIES
MATERIALSQUANTITYUNIT PRICECOST
Boysen masonry neutralizer1.5 gallons510.00 php
Boysen concrete sealer14 gallons7,700.00 php
Boysen gloss latex14 gallons7,560.00 php
Boysen wood primer7 gallons3,675.00 php
Boysen quick drying enamel7 gallons4,060.00 php
Boysen paint thinner2 gallons760.00 php
Roller brush( 9) with pan3 pcs540.00 php
Roller brush (9) refill3 pcs255.00 php
Paint brush ( 1.5)3 pcs105.00 php
Paint brush (2)6 pcs270.00 php
MATERIAL COST 25,435.00 php
QUANTITY OF MATERIALSCOLUMN FOOTING EXCAVATION
COSTING OF ITEMS
Excavation (column footing)
Volume of column = length x width x depth
= 1.0 x 1.0 x 7.2 m
Volume of column = 1.5 m3Total volume for 18 posts:
= 1.2 m3 x 18
Total volume for 18 posts = 21.6 m3
Total volume of excavation = 21.6 m3
Manpower rate = 1.35
Manpower: = 16 md
Manpower: 4 men
Duration: 4 days
Labor cost:
21.6 m3 x 210 php
Labor cost: 4,536 php
Total direct cost = 4,536 php
COLUMN FOOTING
F1
Volume = 1 m x 0.3 m = 0.3 m3 x 10 footings
Volume of concrete = 3 m3Spacing = 0.12 m
16 bars of 1m long
160 pcs - 640 intersections F2
Volume = 1 m x 0.3 m = 0.3 m3 x 5 footings
Volume of concrete = 1.5 m3Spacing = 0.10 m
18 bars of 1m long
90 pcs - 405 intersections
F3
Volume = 1 m x 0.3 m = 0.3 m3 x 3 footings
Volume of concrete = 0.9 m3Spacing = 0.08 m
22 bars of 1m long
66 pcs - 363 intersections
Total volume of concrete: 5.4 m3 (class A)Refer to table 1-2 by Fajardo
Cement: 5.4 m3 x 6.0 = 32.4 say 33 bags
Sand: 5.4 m3 x 0.5 = 2.7 say 3 m3
Gravel: 5.4 m3 x 1.0 = 5.4 say 3 m3
Total no. of 1m long 16 mm bars : 316 pcs
Total length: 316 pcs x 10 m = 316 m
Therefore buy 52.67 say 53 pcs 16 mm x 6m
Total no. of intersections to be connected: 1,408
No. of ties required : 1408 (use 300 mm ties)
Total length required: 422.4 m
Total kilograms : = 7.97 say 8 kgTherefore 8 kg of # 16 G.I wire
Column footing
Total volume of concrete works = 5.4 m3
Total kg. of steel works = 316 m x 1.58 = 499.28 kg
Manpower rate: (Refer p. 106 by Fajardo)
Concrete works: 0.91 (Refer p. 106 by Fajardo)
Steel works : 0.071 (Refer p. 103 by Fajardo)
Concrete works
Manpower : = 5.93 mdsteel works
Manpower : 499.28 kg x 0.071 = 4.43 mdMATERIAL COST
Description Quantity Unit price Total
Cement 33bags 225.00 php 7,425.00 php
Sand
3 m3 800 php 2,400.00php
Gravel ( ) 5.5 m3 1,200 php 6,600.00 php
Tie wire # 16 8 kg 80 php 640.00 php
16mm x 6m DRB 53 pcs 380 php 20,140.00 php TOTAL = 37,205 phpLABOR COST
Manpower Rate Duration Total
1 mason 300/day 3 900 php
1 steel fixer 256/day 3 768 php
2 helper 200/day 3 1,200 php
TOTAL = 2,868.00
TOTAL DIRECT COST = 40,073 PHP
PLASTERING (20 mm thick: class B 40 kg)
Total area to be plastered : 281.75 m2
Total volume of plaster : 5.635 m3 Refer to table 1-2 by Fajardo
Cement: 6.35 m3 x 12 = 67.62 say 68 bags
Sand: 6.35 m3 x 1.0 = 5.635 say 6 m3
Manpower rate = 2 men plaster
Manpower: = 70.44 say 71 md
Manpower: 6 men (4 masons, 2 labors)
Duration: 12 days
MATERIAL COST
Description Quantity Unit price Total
Premium cement 68bags 225.00 php 15,300.00 php
Sand
6 m3 800 php 4,800.00php
TOTAL = 20,100 php LABOR COST
Manpower Rate Duration Total
4 mason 300/day 12 14,400.0 php
2 laborers 250/day 12 4,800.00 php
TOTAL = 19,200.00
TOTAL DIRECT COST = 39,300.00 php
BACKFILL (earth and gravel)
Total volume backfill : 59.02 m3 say 60 m3 Backfill (soil fill) 1.) Soil fill of column footing
Volume of rectangular column = (0.3 x 0.3 x 0.8) x 15 posts
= 1.08 m3
Volume of circular column = 0.7854 (0.3 m3)2 x 0.8 x 3 posts
= 1.08 m3 Volume of footing = 1 x 1 x 0.3 x 18 footings
= 5.4 m3
Total volume = 6.65 m3
Volume of backfill = volume of excavation volume of column & footing
Volume of backfill = 14.95 m3 2.) Wall footingVolume of 75m wall = 0.4 x 0.10 x 75 m
= 3 m3
Volume of 75m wall footing = 0.10 x 0.3 x 75 m
= 2.25 m3
= 5.4 m3
Total volume = 5.25 m3
Volume of backfill = volume of excavation volume of column & footing
Volume of backfill = 7.13 m3 3.) Masters bedroom
Volume of backfill = Area x height of fill
= 4 x 4 x 0.25
Volume of backfill = 4 m34.) 2 Bed Rooms
Volume of backfill = Area x height of fill
= 2 ( 4 x 4 x 0.25)
Volume of backfill = 8 m35.) Living area
Volume of backfill = Area x height of fill
= (4.5 x 4 x 0.10) + ( 3 x 1.5 x 0.25)
Volume of backfill = 2.93 m36.) 2 Bath Rooms
Volume of backfill = Area x height of fill
= 3 x 4 x 0.10
Volume of backfill = 1.2 m37.) Dining area and kitchen
Volume of backfill = Area x height of fill
= (5 x 4 + 5 x 4) x 0.25
Volume of backfill = 10 m3BACKFILL (Gravel)
Thickness of gravel in slabs = 0.05
1.) Column footing
Volume of gravel = (0.1 x 1 x 1) x 18 posts
Volume of gravel = 1.8 m32.) Wall footing
Volume of gravel = 0.3 x 0.05 x 75
Volume of gravel = 1.13 m33.) Masters bedroom
Volume of gravel = Area x 0.05
Volume of gravel = 0.8 m34.) 2 Bed Rooms
Volume of gravel = Area x 0.05
Volume of gravel = 1.6 m35.) Living area
Volume of gravel = Area x 0.05
Volume of gravel = (4.5 x 4 + 3 x 1.5) x 0.05
Volume of gravel = 1.13 m36.) 2 Bath Rooms
Volume of gravel = Area x 0.05
Volume of gravel = 3 x 4 0.05
Volume of gravel = 0.6 m37.) Dining area and kitchen
Volume of gravel = Area x 0.05
Volume of gravel = (10 x 4 ) 0.05
Volume of gravel = 2 m37.) Laundry and parking area
Volume of gravel = Area x 0.05
Volume of gravel = (4 x 5 + 5 x 3) 0.05
Volume of gravel = 1.75 m3SUMMARY
Total volume of earth fill = 48.21 m3
Total volume of earth fill = 10.81 m3BACKFILL
Manpower rate =
Manpower: = 15.50 say 16 md
Manpower: 4 men
Duration: 4 daysLabor cost: 60 m3 x 70 = 4,200 phpMATERIAL COST
Description Quantity Unit price Total
Gravel ( ) 11 m3 1,200.00 php 13,200.00 php
Earth
49 m3 500 php 24,500.00php
TOTAL = 37,700.00 php
TOTAL DIRECT COST = 41,900 php
DOOR AND WINDOW INSTALLATION
Manpower
DoorsTotal doors = 8 pcs
Rate : 1 man install
Hence: = 4 md Window
Total doors = 28 pcs
Rate : 1 man install
Hence: = 7 md Manpower and duration
Total mandays = 11 md
Manpower: 6 men (4 carpenters , 2 labors)
Duration : 4 days
LABOR COST
Manpower Rate Duration Total
4 carpenters 300/day 4 4,800.0 php
2 laborers 200/day 4 1,600.00 php
TOTAL = 6,400.00 php
DOOR AND WINDOWSMATERIAL COST
Windows: Use brown glass with brown aluminum casement, see window details. Materials include casement and screws.
Kitchen windows Quantity Unit cost Total
1.6 m x 0.9 (WO3) 1 4,174 1,174
2.4 m x 0.9 (WO4) 1 6,261 6,261 0.8 m x 0.9 (WO3) 1 2,087 2,087
Living area Quantity Unit cost Total
0.5 m x 1.6 (WO2) 3 2,782 8,346
2.0 m x 1.2 (WO1) 2 7,066 14,132 Bedroom windows Quantity Unit cost Total
2.0 m x 1.2 (WO1) 6 7,066 42,396
Toilet and bathrooms Quantity Unit cost Total
0.6 m x 0.5 (WO6) 4 870 3,480
DOOR (see door details)
Quantity Unit cost Total
Main entrance door
1
3,800
3800 Service door
2
3,500
7,000 Bedroom door
3
2,650
7,950 Toilet & Bathroom door
2
1,350
2700
TOTAL = 102,326 php
TOTAL DIRECT COST = 108,726.00 phpSCHEDULE OF ACTIVITIESACTIVITYDURATIONESEFLSLFFLOATREMARKS
TFFF
A. SITE CLEARING & STAKE LAYOUT
6060600CRITICAL
B. COLUMN FOOTING EXCAVATION
461061000CRITICAL
C. FOUNDATION WORKS
31013101300CRITICAL
D. COLUMN WORKS
121325132500CRITICAL
E. BEAM WORKS
102535253500CRITICAL
F. CURING
73542354200CRITICAL
G. TRUSS FABRICATION &ERECTION
154257425700CRITICAL
H. PURLINS WORKS
55762576200CRITICAL
I. ROOFING WORKS
146276627600CRITICAL
J. REMOVAL OF BEAM FORMS & SCAFFOLDINGS
335385255170N.C
K. WALL FOOTING
338415558170N.C
L. WALLING
1441555872170N.C
M. BACKFILLING
4555972761717N.C
N. CHB CANAL
410147781670N.C
O. SEPTIC VAULT
10142481916766N.C
P. ELECTRICAL ROUGH INSTALLATION
47680768000CRITICAL
Q. DOOR & WINDOW INSTALLATION
47680768000CRITICAL
R. PLUMBING ROUGH INSTALLATION
57681778210N.C
S. PLASTERING
128092809200CRITICAL
T. CEILING WORKS
14921069210600CRITICAL
U. FINISHING WORKS
310610910610900CRITICAL
V. FLOORING
98190829110N.C
W. PLUMBING FIXTURES INSTALLATION
79097919810N.C
X. TILE WORKS
11971089810911N.C
Y. PAINTING WORKS
710911610911600CRITICAL
Z. ELECTRICAL FIXTURES INSTALLATION
411612011612000CRITICAL
AA. CLEARING & DEMOBILIZATION
212012212012200CRITICAL
_1330099971.unknown
_1330100003.unknown
_1330100019.unknown
_1330100035.unknown
_1330100052.unknown
_1330100060.unknown
_1330100064.unknown
_1330100066.unknown
_1330100068.unknown
_1330100069.unknown
_1330100070.unknown
_1330100067.unknown
_1330100065.unknown
_1330100062.unknown
_1330100063.unknown
_1330100061.unknown
_1330100056.unknown
_1330100058.unknown
_1330100059.unknown
_1330100057.unknown
_1330100054.unknown
_1330100055.unknown
_1330100053.unknown
_1330100043.unknown
_1330100048.unknown
_1330100050.unknown
_1330100051.unknown
_1330100049.unknown
_1330100046.unknown
_1330100047.unknown
_1330100045.unknown
_1330100039.unknown
_1330100041.unknown
_1330100042.unknown
_1330100040.unknown
_1330100037.unknown
_1330100038.unknown
_1330100036.unknown
_1330100027.unknown
_1330100031.unknown
_1330100033.unknown
_1330100034.unknown
_1330100032.unknown
_1330100029.unknown
_1330100030.unknown
_1330100028.unknown
_1330100023.unknown
_1330100025.unknown
_1330100026.unknown
_1330100024.unknown
_1330100021.unknown
_1330100022.unknown
_1330100020.unknown
_1330100011.unknown
_1330100015.unknown
_1330100017.unknown
_1330100018.unknown
_1330100016.unknown
_1330100013.unknown
_1330100014.unknown
_1330100012.unknown
_1330100007.unknown
_1330100009.unknown
_1330100010.unknown
_1330100008.unknown
_1330100005.unknown
_1330100006.unknown
_1330100004.unknown
_1330099987.unknown
_1330099995.unknown
_1330099999.unknown
_1330100001.unknown
_1330100002.unknown
_1330100000.unknown
_1330099997.unknown
_1330099998.unknown
_1330099996.unknown
_1330099991.unknown
_1330099993.unknown
_1330099994.unknown
_1330099992.unknown
_1330099989.unknown
_1330099990.unknown
_1330099988.unknown
_1330099979.unknown
_1330099983.unknown
_1330099985.unknown
_1330099986.unknown
_1330099984.unknown
_1330099981.unknown
_1330099982.unknown
_1330099980.unknown
_1330099975.unknown
_1330099977.unknown
_1330099978.unknown
_1330099976.unknown
_1330099973.unknown
_1330099974.unknown
_1330099972.unknown
_1330099954.unknown
_1330099962.unknown
_1330099967.unknown
_1330099969.unknown
_1330099970.unknown
_1330099968.unknown
_1330099964.unknown
_1330099966.unknown
_1330099963.unknown
_1330099958.unknown
_1330099960.unknown
_1330099961.unknown
_1330099959.unknown
_1330099956.unknown
_1330099957.unknown
_1330099955.unknown
_1330099946.unknown
_1330099950.unknown
_1330099952.unknown
_1330099953.unknown
_1330099951.unknown
_1330099948.unknown
_1330099949.unknown
_1330099947.unknown
_1330099942.unknown
_1330099944.unknown
_1330099945.unknown
_1330099943.unknown
_1330099940.unknown
_1330099941.unknown
_1330099939.unknown