Master Plan Update May 2014
Luther High SchoolOnalaska, WI
Master Plan• Vision and Mission of LHS
• Facility Study
• Strategic Plan for School
• RFP Development
• Recommendation to COD
2
Vision and Mission of LHS• Focus
− On the Vision and Mission statement of Luther HS and ensure that planning process is in line with statements
− Ensure that all decisions affecting LHS are tested against Vision and Mission
3
Vision Statement of LHSLuther High School desires that its students, mindful of baptismal grace, live the holiness that God gave to them in Christ.
Mission Statement of LHSLuther High School provides a Christ-centered education that encourages and equips students for life and for eternity.
4
Objectives of LHS• Therefore, Luther High School will keep Christ in higher
education by: − faithfully proclaiming and applying the Word of God
through the teaching of classes, life skills, and activities in accordance with the Lutheran Confessions.
− promoting spiritual growth and maturity through the proper use of God’s Law and Gospel.
− encouraging and training students to share their faith throughout their lives whether in personal or public ministry.
− instilling a desire for knowledge, understanding and wisdom while taking “every thought captive and making it obedient to Christ.” (2 Corinthians 10:5)
5
Master Plan• Vision and Mission of LHS
• Facility Study
• Strategic Plan for School
• RFP Development
• Recommendation to COD
6
Facility Study• Survey Results
• Curriculum Review
• Enrollment Trends
• Historical Timeline of Facility
• Existing Facility Review
7
Adult Survey Highlights • Responses identified a number of space
needs (shop, art classroom, storage) followed by a desire to improve the traffic flow in the parking lots
• Main Focus was Chapel/Auditorium and Curriculum Needs
• Curriculum Responses showed a desire for more class choices; including AP classes, Industrial Arts, and Technology
• See appendix for a breakdown8
Student Survey Highlights• Responses indicated an overwhelming
need to improve the comfort in the building(Heat, AC, Renovate Bathrooms, Fix Cracks in Walls, Better Insulation).
• Future needs include: New Home Maint. Shop, New Art Room, Upgrade Old Classrooms, and Improve Parking Lot.
• Curriculum Responses showed a desire for more class choices; including AP classes, Foreign Language, and other electives.
• See appendix for a breakdown 9
Curriculum Review• Faith Focused
• Current curriculum available and the resources and space allocation required
• Identify more productive adjacencies
• Identify shared use possibilities
• Future curriculum adjustments and inclusions; and impact on facility
10
Curriculum Over the Years
Year Faculty CoursesOffered
1957 3(FT) 5(PT) 43
1967 14 43
1977 18 48
1987 17 63
1997 18(FT) 3(PT) 69
2007 20 66
2013 20 66
11
Curriculum Proposals • Low Census Courses
− Offer on alternate years to reduce course load while maintaining availability
− Utilize remotely taught on-line classes (currently not offered for credit)
• Course Changes− Additional Social Studies, English, Math, Art, and
Home Maintenance courses− Additional AP Courses
• AP Biology• AP Psychology• AP Statistics 12
Curriculum Space Needs • Immediate Needs
− Industrial Arts/Home Maintenance Shop− 2D and 3D Art Rooms with Clean-Up Sinks− New/Renovated Science Labs− Robotics Lab/Classroom− Digital Media
• Future Needs− Additional Shop and Art Courses− Additional Math Courses− AP Biology Lab− Individual/Remote Learning Stations 13
Shared Use Possibilities• Home Maintenance Shop/Classroom
− Robotics Lab/Classroom− Digital Media− Additional CAD courses− Agriculture courses− Drama prop construction area− Custodial/Maintenance Staff Uses
• Individual Instructional Assistance Room− Remote Learning Stations− One-on-One/Small Group Uses− Special Needs Students 14
Enrollment Trends• Student post secondary aspirations to
ensure proper preparation in curriculum
• Review enrollment levels over the years to determine Increase / Decrease
• Anticipated future enrollment levels
• Other factors
15
After Graduation
4 – Year College: 60%
Technical College: 30%
Military Service: 5%
Employment: 5%
16
Enrollment TrendsYear Students
1957 29
1967 245
1977 330
1987 263
1997 253
2007 255
2008 275
2009 273
2010 279
2011 278
2012 267
2013 268 17
Enrollment ProjectionsSchool Year Freshmen Total 9-12 Students
2013-2014 60 255
2014-2015 66 259
2015-2016 67 266
2016-2017 73 269
2017-2018 76 289
2018-2019 67 291
Projections based on 60% of 8th grade LES classes enrolling at Luther.
18
Existing Facility Review• When was it built?
• How are we currently using the building?
• Can we fit any more courses in the current building?
• Are they the right type of classrooms?
• How many years are left in the older portions of the building?
• How much would it cost to extend the life of the existing building?
• What would it cost to replace it?19
Past Building Phases• 1957 Initial East Wing Erected (57 years old)
• 1959 Classrooms and Gym Additions (55 years old)
• 1963 West Wing Addition (51 years old)
• 1966 Choir Room Addition (48 years old)
• 1971 LMC – Study Hall/Garage Addition (37 years)
• 1993 Band/Commons/Office/New Classrooms (21)
• 1999 ACE Lobby/Gym/Locker Rooms (15 years)
• See appendix for map20
Past Building Phases
21
Space Usage
22
Current Space Allocation
23
Existing Facility Review• State of the Facility
− Phase 1 Environmental Study • Asbestos – Old Floor Tiles• Lead paint – No Known Problems• Contaminations – No Known Problems
− MEP Systems • Indoor Air Quality – Weight Room, Science Labs, Home
Maintenance, Art, Exercise Bike Room• Electrical Loads – East/West Wing at or near capacity• Lighting requirements – Recent Upgrades Completed• Water usage – Irrigation Well Pump Replaced 2013
− Energy efficiency and sustainability review• Recent study completed and under review 24
Existing Facility Review (cont.)• State of the Facility
− Code Compliant• ADA – Art and Choir Rm, Entrance Doors, Bathrooms• Life Safety – Parking Lot, Emergency Lighting• Energy codes?
− Durability• Flooring – Carpet needs replacing, tile is dated• Bathrooms – replace/remodel, East/West wing
− Roofing report− Technology needs
25
Existing Facility Review (cont.)• State of the Facility
− Security – Camera System, A/C− Natural Lighting - Limited− Structurally sound - TBD− Site Conditions
26
Space Usage – Sorted by Time
27
Space Usage – Sorted by Category
28
Percent Usage by Major Category
29
Space Conflicts
30
Chapel/Auditorium Capacity Needs
• Seating for 550 to 650
0 100 200 300 400 500 600 700 800 900 1000
Coulee Chorale5th Grade Science Day
ChapelFall Drama Production
Childrens'…Knight Revue
Grandparents' Day…Drama Production (4)Reformation Service
Easter ConcertScience and Fine…
Grandparents' Day…Winter Band Concert
Opening ServiceHeidelberg
Spring SpotlightChristmas Concert -…Christmas Concert -…
Christmas ConcertGraduation
Estimated Attendance
31
Other Space Needs• Indoor Storage
• Outdoor Storage
• Faculty/Administrative Office Space
• Athletic Center Addition
• Future Athletic Facilities
• Parking
32
Master Plan• Vision and Mission of LHS
• Facility Study
• Strategic Plan for School
• RFP Development
• Recommendation to COD
33
Strategic Plan for School• Prioritizing needed enhancements
• Combine areas of work that should be included when considering renovation work, additions, and or remodeling
• Establish timeline of other improvements and determine how to accomplish them.
34
Priority Evaluation CriteriaA priority system was developed to evaluate future needs campus wide (from highest to lowest):
• Health & Life Safety/ADA Needs
• Curriculum Support/Improved Worship or Learning Environment
• Building/Energy Efficiency and Maintenance Reduction
• Improved Event Quality and Time/Effort Savings
• Classroom Interior Upgrades and Infrastructure
• Aesthetics/Site Development and Landscaping
• Expansion of Facilities
Other criteria used were: Frequency of Use and the Urgency of the Time Frame when needed. 35
Weighted Prioritized ListDuring the discovery phase of the Master Planning Process:
• Each sub-committee prepared a list of projects/needs for the school based on their area of study.
• The project lists were submitted to the Steering Committee.
• The Steering Committee consolidated them into one combined list.
• Each project was reviewed and a numerical value was assigned based on the Priority Evaluation Criteria.
• The project list was then sorted highest to lowest based on the weighted priority score.
36
High Priority Projects• Build Art Classroom(s) and Home Maintenance Shop with CAD
Design Classroom (also use for Robotics Lab/Classroom)
• Renovate East & West Wing Restrooms
• Permanent Bleachers for Track/Football Field
• Parking Lot - Improve Traffic Flow, Add Green Bay St. Entrance
• New Chapel/Auditorium with Changing Rooms & Storage
• Convert Old Gym to Chapel/Auditorium & Build New Gym
• Repurpose Space for Digital Video Classroom
• New Football Concession Stand/Press Box/Outdoor Storage
• Build Athletic Center Addition with Visitor Locker Rooms & Football/Track Bathrooms
• Install Handicap Entrance Doors and Classroom Desks
• Renovate/New Science Labs, Add Science Lecture Classroom37
Medium Priority Projects• Renovate Old Locker rooms
• Perform Energy Audit/Energy Reduction Projects
• Parking - Pave North Gravel Lot/Add Parking Spaces
• Athletic Department Storage
• New Interior Signage, especially for visitors
• Zoned Heating plan for ACE Gym and Mezzanine
• Individual Instructional Assistance Room(s)
• Track/Football scoreboard upgrade
• Maintenance Department Storage with Floor Drain
• Outdoor class space/school forest
• Exterior Signage
• Ace Roof Replacement 38
Low Priority Projects• Epoxy Floors in Existing Classrooms and Hallways
• Replace Worn Carpet in Office and Library
• Building Landscaping - shrubs, trees, perennials
• Build Tennis Courts
• Upgraded Athletic Fields (Football, Baseball)
• Auxiliary Gym Renovation/Replace Scoreboards
• Air Condition Existing Building Classrooms, etc.
• Repaint/Powder Coat all Student Lockers
• Additional Office/Conference/Meeting Rooms needed
• Long Range Increased Parking Space Needs
• Purchase/Develop Additional Land for a JV Baseball Field39
Future Desires• What if …
− Think 25 years from now− No limitations− Out of the box − If only we could…
40
Current campus of
Luther High School
41
Extension of Green Bay St. allows for ~50% increased
traffic entrance/exit
Moving Varsity softball diamond
maximizes parking &
reduces damage from softballs
JV baseball field maximizes space by sharing outfield with
football – no conflicts, temp snow fence for
outfield
Discus & Shot can be relocated or
redirected with no conflicts
Existing building removed for
safer traffic flow
Chapel-Auditorium with space for
Vocational rooms & Maintenance
garage
Bus pickup/drop off lane increases
safety
Additional classrooms can form a circle w/courtyard
Parking lot redesign allows safer, closer,
increased parking spaces
JV softball field
Shared concessions & storage
New Entrance/Office Space
Maintenance Garage
Phy Ed/Sports Addition
42
Obstacles• Financial Restrictions
− Construction cost increasing faster than fundraising− Aversion to debt − No clear vision/project/timeline for fundraising
• Enrollment Growth− Pool of students primarily limited to association
LES students.− Increasing tuition cost
• Land Locked− Expansion needs include: building, parking,
athletic facilities 43
Master Plan Steps / Phases• Vision and Mission of LHS
• Facility Study
• Strategic Plan for School
• RFP Development
• Recommendation to COD
44
RFP Development• Objective of RFP
• Identify delivery options
• Proposal Submission / Format requirements
• Selection Criteria / Process− Past experience / Capabilities− Management plan
• Scope of work desired
• Timeframe / Cost45
Master Plan Steps / Phases• Vision and Mission of LHS
• Facility Study
• Strategic Plan for School
• RFP Development
• Recommendation to COD
46
Recommendation to COD• The Master Planning Steering Committee is seeking
approval from the COD to send out the Request for Proposal to 3-6 Design Firms, for the purpose of completing a Facilities Study and selecting a Design Firm for any near term building/remodel projects.
• The Master Planning Steering Committee also recommends that the COD empower a Finance Committee to research options for financing any future building/remodel projects at LHS and to present those options at the Aug. 2014 COD meeting
47
Timeline• May 14th 2014 – COD Approves the letting of an RFP
• May 30th 2014 – RFP Bid’s Received from Design Firms
• June 1st 2014 – Award contract(s) to complete Facilities Study
• June 1st 2014 – Finance Committee begins work
• June – July 2014 – Steering Committee meets with Design Firms to provide background information on LHS
• July 31st 2014 – Steering Committee Receives Facilities Study from Design Firm(s)
• Aug 2014 COD Meeting - Steering Committee and Finance Committee provide update to COD.
48
August 2014 COD Meeting• Update to include:
− Draft Copy of Master Plan− List of Short Range Projects with
Budgetary Pricing− Design Firm Recommendation− Draft copy of one-line floor plans− Timeline for moving forward− Finance Options
• Not to include:− Detailed floor plans− Detailed cost estimates 49