12
® Questions & Solutions® Engineering, Inc. 1079 Falls Curve Chaska, Minnesota 55318 QSEng.com Master Commissioning Plan Project Customization Guideline American University Washington, DC March 20, 2012

Master Commissioning Plan Project Customization Guideline

  • Upload
    others

  • View
    12

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Master Commissioning Plan Project Customization Guideline

®

Questions & Solutions® Engineering, Inc.1079 Falls CurveChaska, Minnesota 55318QSEng.com

Master Commissioning Plan Project Customization GuidelineAmerican UniversityWashington, DCMarch 20, 2012

Page 2: Master Commissioning Plan Project Customization Guideline

®

Questions & Solutions® Engineering, Inc.1079 Falls CurveChaska, Minnesota 55318QSEng.com

Rebecca Ellis, PE, LEED AP BD+C, CCP, CPMP, CxAPrincipal In [email protected]

Bob deVeyra, EIT, LEED AP BD+C, QCxPProject [email protected]© 2012 Questions & Solutions Engineering, Inc. All Rights Reserved.All other trademarks are the property of their respective owners.

Master Commissioning Plan Project Customization GuidelineAmerican UniversityWashington, DCMarch 20, 2012

Page 3: Master Commissioning Plan Project Customization Guideline

Table of Contents

1. Introduction

Purpose

When to Customize the Commissioning Plan?

2. Initial Considerations

Is Commissioning Necessary?

Who will Serve as Commissioning Manager?

3. Develop a Project-Specific Commissioning Plan

Update Introduction

Establish the Commissioning Team

Define the Systems to be Commissioned

Define the Applicable Commissioning Activities

Updated and/or Additional Commissioning Documentation Templates & Examples

4. Commissioning Requirements for LEED Certification

Fundamental Commissioning: Energy & Atmosphere Prerequisite 1

Enhanced Commissioning: Energy & Atmosphere Credit 3 (2 points)

5. Suggested Commissioning Scope for CRDM Projects

6. Update the Master Commissioning Plan

Page 4: Master Commissioning Plan Project Customization Guideline

1. Introduction

Purpose

When to Customize the Commissioning Plan?

Page 5: Master Commissioning Plan Project Customization Guideline

2. Initial Considerations

Is Commissioning Necessary?

Who will Serve as Commissioning Manager?

Page 6: Master Commissioning Plan Project Customization Guideline
Page 7: Master Commissioning Plan Project Customization Guideline

3. Develop a Project-Specific Commissioning Plan

Update Introduction

Establish the Commissioning Team

Define the Systems to be Commissioned

Page 8: Master Commissioning Plan Project Customization Guideline

Define the Applicable Commissioning Activities

Updated and/or Additional Commissioning Documentation Templates & Examples

Page 9: Master Commissioning Plan Project Customization Guideline

4. Commissioning Requirements for LEED Certification

Fundamental Commissioning: Energy & Atmosphere Prerequisite 1

Planning Phase

Preliminary Commissioning

Plan

Owner’s Project Requirements (OPR)

Document

Design Phase

Basis of Design (BOD) Document

Preliminary Prefunctional Checklists & Functional

Performance Tests

Commissioning Specification

Construction Phase

Commissioning Schedule

Prefunctional Checklists

Completion

Final Prefunctional Checklists & Trend Log Specifications

Functional Performance

Testing

Commissioning Report

Deferred Testing

Final Commissioning Plan

Acceptance Phase Warranty Phase

Go to Design Phase

Go to Construction Phase

Go to Acceptance Phase

Go to Warranty Phase

On-Going Cx Phase

Final Functional Performance Tests

Commissioning Action List

Functional Performance

Re-Testing

Design Phase Commissioning Coordination

Meetings

Construction Phase Commissioning Coordination

Meetings

Acceptance Phase Commissioning Coordination

Meetings

On-Going Cx Phase

On-Going Operations

Page 10: Master Commissioning Plan Project Customization Guideline

Enhanced Commissioning: Energy & Atmosphere Credit 3 (2 points)

Planning Phase

Preliminary Commissioning

Plan

Owner’s Project Requirements (OPR)

Document

Design Phase

Basis of Design (BOD) Document

Commissioning Design Reviews

O&M Training Planning

Preliminary Prefunctional Checklists & Functional

Performance Tests

Commissioning Specification

Construction Phase

Commissioning Schedule

Submittal Reviews

O&M Training Delivery

Prefunctional Checklists

Completion

Final Prefunctional Checklists & Trend Log Specifications

Functional Performance

Testing

Commissioning Report

Systems Manual & On-Going

Commissioning Plan

Deferred Testing

Warranty Phase Check-up & Meeting

Final Commissioning Plan

Acceptance Phase Warranty Phase

Go to Design Phase

Go to Construction Phase

Go to Acceptance Phase

Go to Warranty Phase

On-Going Cx Phase

O&M Training Agenda Reviews

Final Functional Performance Tests

Commissioning Action List

Functional Performance

Re-Testing

Design Phase Commissioning Coordination

Meetings

Construction Phase Commissioning Coordination

Meetings

Acceptance Phase Commissioning Coordination

Meetings

On-Going Cx Phase

On-Going Operations

Page 11: Master Commissioning Plan Project Customization Guideline

5. Suggested Commissioning Scope for CRDM Projects

Planning Phase

Preliminary Commissioning

Plan

Owner’s Project Requirements (OPR)

Document

Design Phase

Basis of Design (BOD) Document

Commissioning Design Reviews

Preliminary Prefunctional Checklists & Functional

Performance Tests

Construction Phase

Commissioning Schedule

Submittal ReviewsFunctional

PerformanceTesting

Commissioning Report

Deferred Testing

Final Commissioning Plan

Acceptance Phase

Test, Adjust, and Balance (TAB) Report Review

Warranty Phase

Go to Design Phase

Go to Construction Phase

Go to Acceptance Phase

Go to Warranty Phase

On-Going Cx Phase

Final Functional Performance Tests

Commissioning Action List

Functional Performance

Re-Testing

Design Phase Commissioning Coordination

Meetings

Construction Phase Commissioning Coordination

Meetings

Acceptance Phase Commissioning Coordination

Meetings

On-Going Cx Phase

On-Going Commissioning

Activities

On-Going Operations

Page 12: Master Commissioning Plan Project Customization Guideline

6. Update the Master Commissioning Plan