Upload
kale
View
22
Download
0
Embed Size (px)
DESCRIPTION
The Cell Controller Pilot Project (CCPP): From Surviving System Black-Out to Market Support. Energinet.dk Spirae Inc Energynautics GmbH SE. MARTENSEN – DE – Session 4 – 1221. CCPP: Background. Blackout experience due to transmission system failure - PowerPoint PPT Presentation
Citation preview
Frankfurt (Germany), 6-9 June 2011
MARTENSEN – DE – Session 4 – 1221
The Cell Controller Pilot Project (CCPP):From Surviving System Black-Out
to Market Support
Energinet.dk Spirae Inc Energynautics GmbH SE
Frankfurt (Germany), 6-9 June 2011
CCPP: Background
Blackout experience due to transmission system failure
Large amount of Distributed Energy Resources in Denmark
Further increasing share of renewable energy sources in the future
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
Surviving transmission system black-outby safely transitioning into island operation
TSO support: Virtual Power Plantsfor active and reactive power
independently DNO Support: Advanced voltage control Platform for market aggregators
of distributed generation resourcesMARTENSEN – DE – Session 4 – 1221
CCPP: Objectives
Frankfurt (Germany), 6-9 June 2011
60 kV grid cell below one 150/60 kV transformer 13 each 60/10 kV substations with tap changer
controlled transformers
5 CHP plants / 15 synchronous generators, total installed capacity of 32.5 MW
47 Danish-style wind turbines, total installed capacity of 37 MW
Rural area, villages and small cities (>1000 km²)MARTENSEN – DE – Session 4 – 1221
CCPP: The Pilot Cell
Frankfurt (Germany), 6-9 June 2011
Started in 2005 Field Tests with reduced-sized Cell in 2008
Grid-connected and island functions
Field tests using the entire Cell in 2010 Grid-connected functions
Final field tests using the entire Cell in 2011 Grid-connected and island functions
MARTENSEN – DE – Session 4 – 1221
CCPP: Project Status
Frankfurt (Germany), 6-9 June 2011
To be used by Power Balance Authorities Group and dispatch of CHPs or Wind Turbines Multiple Markets:
Day-ahead scheduling Merit order dispatch based on price information Up-regulation and down-regulation
Automatic dispatch validation against power system/component limits
MARTENSEN – DE – Session 4 – 1221
CC Functions: Market Operations
Frankfurt (Germany), 6-9 June 2011
Conventional distribution systems use only transformer tap changers for voltage control.
The Cell Controller uses reactive power setpoints of distributed energy resources first, where available. Reduced wear on tap changers Smoother voltage for consumers and generators
MARTENSEN – DE – Session 4 – 1221
CC Functions: DNO Voltage Control
Frankfurt (Germany), 6-9 June 2011
Controlled load flow at single point of connection Active Power VPP
Automatic asset dispatch to meet setpoint Disables Market Operations
Reactive Power VPP Uses assets dispatched by other means Reduces voltage control to tap changer control
Consideration of local system/component limitsMARTENSEN – DE – Session 4 – 1221
CC Functions: TSO Virtual Power Plants
Frankfurt (Germany), 6-9 June 2011
Based on receipt of external trigger signal Balance load and generation
Load/generation shedding if necessary
Open the Cell circuit breaker (within <5 seconds) Automatic voltage & frequency control in island Automatic load restoration Resynchronization
MARTENSEN – DE – Session 4 – 1221
CC Functions: Emergency Island
Frankfurt (Germany), 6-9 June 2011
MARTENSEN – DE – Session 4 – 1221
Field Tests 2010: DNO Voltage Control
Blue: DNO Preferred Operating Voltage Ranges (and changes)
Red: Nominal Voltage Set Point and Actual Values
Holsted CHPGenerator ReactivePower Production
Frankfurt (Germany), 6-9 June 2011
MARTENSEN – DE – Session 4 – 1221
Field Tests 2010: Reactive Power VPP
TSO operator request reactive power set point of -7 MVAr
Measured reactive power
TSO reactive power import/export disabled
Tap changer operations at different 60/10 kV substations
Frankfurt (Germany), 6-9 June 2011
MARTENSEN – DE – Session 4 – 1221
Field Tests 2010: Active Power VPP
Frankfurt (Germany), 6-9 June 2011
All originally envisioned functions implemented and tested in simulations and in the field
Grid-connected functions working in 2010 Minor improvements for 2011
Grid-connected functions comprehensively field tested in May 2011 with success
Island functions to be field tested in June 2011
MARTENSEN – DE – Session 4 – 1221
Conclusions
Frankfurt (Germany), 6-9 June 2011
Cell Controller Pilot Project is concluded with final field tests 2011.
Possible further deployment of the Cell Controller system on the island of Bornholm
Future distribution systems will provide further/improved distributed control resources that can be utilized by the Cell Controller.
MARTENSEN – DE – Session 4 – 1221
Outlook