8
OneSubsea MARS Multiple Application Reinjection System Enabling processes for every well

MARS - Multiple Application Reinjection System

Embed Size (px)

DESCRIPTION

MARS - Multiple Application Reinjection System

Citation preview

  • OneSubsea MARS Multiple Application Reinjection SystemEnabling processes for every well

  • uniquE tEchnOlOgy. univERSAl ApplicAtiOn.

    Historically, installing processing hardware on

    existing subsea trees has been a high-risk and costly

    activity due to potential required field shutdown, new

    hardware foundation, and pipeline decommissioning or

    recommissioning.

    The OneSubsea MARS Multiple Application

    Reinjection System serves as a universal interface for trees

    (topside and subsea), enabling processing equipment to

    be installed between the existing isolation barriers, thus

    eliminating the need for high-risk and costly intervention

    to the field architecture. The MARS system enables

    flexibility and choice for production optimization in new

    and existing fields, providing:

    Low-cost intervention

    Low-risk intervention

    Cost-effective wellhead processing

    MARS technology can be used for both vertical and

    horizontal Christmas trees in surface and subsea

    applications. The system has been adopted by operators

    in various regions of the world for multiple applications,

    including a pump system installation in the Gulf of

    Mexico and well stimulation systems in the North Sea

    and West Africa.

    MARS-EnAblEd PoSSibilitiES

    MARS technology enables multiple processing

    possibilities on new and existing wells at any time

    in the life of a field. The MARS system establishes

    the wellhead as the unit of production, enabling

    the connection of production optimization

    systems to be installed easily in the field, either on

    or off the subsea tree.

    The system enables any process on any well;

    therefore any number of existing or emerging

    processing technologies can be fitted into a field

    with minimal risk.

    Applications include:

    Multiphase pumping

    Multiphase metering

    Fluid sampling

    Separation

    Bulk water management and reinjection

    Raw seawater injection

    Pressure boosting

    Chemical injection

    HIPPS

    Well Kill

    Flushing

    1

  • MARS tEchnOlOgy

    Sensor Replacement

    Subsea Processing

    HIPPS

    Separation

    Sand Filtering

    Water Injection Pumping Multiphase Pumping

    Process Metering

    Existing Choke Body

    on Tree

    MARS Dual-bore

    Insert

    MARSProcess Module

    From Well

    To Flowline

    2

  • MARS Injection InsertTypical Section

    (Flowline Flow Path)

    Flowline Flushing

    Existing Choke Body on Tree

    Existing Choke Body on Tree

    Well Stimulation Chemical Injection

    Well Kill

    Well Stimulation Chemical Injection

    MARS Injection InsertTypical Section

    (Well Bore Flow Path)

    MARS Injection ChokeTypical Section

    3

  • thE MARS SyStEM in thE fiEld

    Gulf of MExico

    In 2007, the first subsea multiphase pump was

    installed in the Gulf of Mexico in 5430 ft (1700 m)

    water depth. Using two MARS inserts to gain access

    to the production flow allowed the pumps to increase

    production from mature assets by 20% and is expected

    to extend field life by five years. In addition, the

    MARS system eliminated the installation risk normally

    associated with implementing new deepwater processing

    technology on brownfield assets.

    WESt AfRicA

    The system increased production from a field offshore

    Angola through scale-squeeze operations on 14 wells.

    Equipment for this project included 16 chokes modified

    with MARS technology, two off short-term injection

    inserts and two off injection skids. The deployment

    system used two off reelers complete with 2 x 2461

    ft (750 m)-long hoses, a 1/2 reeler complete with a

    1/2 x 2461 ft (750 m)-long hose, a 30-ton deployment

    winch, an overboarding chute complete with clamping

    station, a hydraulic power unit and an associated remote

    control station. The full scope of the project included

    chemical delivery and deck handling packages, making

    the operation safer, faster and more cost-efficient. Scale-

    squeeze operations have been ongoing on a regular basis

    since installation.

    Following the successful application of MARS

    technology offshore Angola, similar MARS technology

    for multiphase metering was applied throughout a

    field offshore Nigeria in 2953 ft (900 m) water depth

    at pressures up to 5000 psi and temperatures between

    -0.4 F and 216 F (-18 C and 102 C). A total of 24

    dedicated flowbase manifolds have been supplied, which

    house the retrievable MARS-enabled multiphase

    flow meters.

    4

  • noRth SEA

    MARS technology was used on a field in the West of

    Shetlands to reinstate critical production management

    instrumentation that had failed in situ. Working with

    the original tree manufacturer, replacement

    instrumentation was introduced into a MARS-enabled

    flow loop at the tree which restored full functionality to

    the production system.

    Here, the MARS system was the solution for retrofitting

    pressure sensors and isolation valves on an existing

    horizontal tree using the existing subsea control

    system while retaining full choke functionality. Rapid

    installation and redeployment was possible using an

    ROV support vessel.

    Also in the North Sea, two fields incorporated MARS-

    enabled subsea well stimulation packages. Prior to

    adopting MARS technology at the first field, subsea

    scale-squeeze operations at that location were diver

    intensive, infrequent and expensive. By upgrading the

    existing subsea trees (two in situ and one new tree pre-

    deployment) with a MARS-enabled choke, the operator

    effectively gained a new safe-access point into both their

    reservoir and the pipeline system.

    At this field, MARS technology resulted in a safer, faster

    and more cost-efficient operation since it was installed

    on both new and existing trees. This application reduced

    well risk, enabled multiple-well concurrent campaigns,

    reduced vessel time and costs, reduced shutdown time

    and increased the weather window. In addition, divers

    no longer were required to perform work in hazardous

    environments. MARS technology yielded an estimated

    60% reduction in OPEX.

    Following this success, the operator specified that the

    same technology be used at a second field. Here, the

    scope of supply included one off injection skid assembly,

    four off choke change-out interface extension sets, one

    off choke change-out extension running tool, four off

    choke protection plates, operational tooling and project

    and services testing. Production has been optimized due

    to safer, faster and less-expensive (and therefore more

    frequent) scale-squeeze operations.

    A MARS-enabled multiphase flow meter was used via

    the tree cap at another field in the North Sea. A single

    assembly consisting of a MARS system and the flow

    meter was deployed by a wireline crew. Normal hot

    work permits no longer were required as no flowlines

    or existing infrastructure were modified. In addition,

    the system provided a low-risk, low-cost method to

    retrofit flow meters to every platform wellhead,

    enabling production optimization from improved

    data management.

    5

  • 4646 W. Sam houston pkwy. n.

    houston, tX 77041

    uSA

    tel 1 713 939 2211

    5 Mondial Way

    harlington

    hayes, uB3 5AR

    England, uK

    tel 44 208 990 1800

    Sandslikroken 140

    pO Box 174

    Sandsli, n-5862

    Bergen, norway

    tel 47 55 92 88 00

    level 11, 12-14

    the Esplanade

    perth, Western Australia

    6000

    tel 61 8 6389 5000

    MARS

    pavilion 4, prospect Road

    Arnhall Business park

    Westill, AB32 6fE

    Scotland, uK

    tel 44 1224 748 460

    www.onesubsea.com

    2013 cameron | OneSubsea and MARS are trademarks of OneSubsea. | SB 1M 05/13 Ad00625OSS