1
Market Systems Release Update
Modifications Committee Meeting 55
June 19th 2014
2
• Deployed successfully to Central Market Systems on May 16th.• Change Requests were finalised and closed.• Project is now closed.
SEM R2.4.0 – May 2014
3
• Release Cut-Off Date has passed. • Relevant Design Notes received from our vendors. • Design notes now under review internally. • Project schedule agreed with vendor – software delivery
agreed for end of July.• Test Phases will commence following successful software
delivery.
SEM R2.5.0 – May 2014
4
• The following table outlines the approved scope for the release:
SEM R2.5.0 – November 2014
SEM R2.5.0 Approved Scope
CR Ref Description
SEM_PC_CR322 Eligible Availability for Energy Limited Units Under Test
SEM_PC_CR327 Event Queuing
SEM_PC_CR333 Functionality to apply PUGDOG TTariff on a Trading Day basis
SEM_PC_CR332 Issue Zero Invoices
SEM_PC_CR330 Changes to IART Report
Total Vendor Effort: 2144 hours
5
• Design closed July 25th
• Publication of MPUD Aug 11th
• Software delivery July 31st
• System Integration Test Execution Aug 4th to Oct 10th
• Market Test Execution Oct 13th to Oct 24th
• Deployment * Nov 14th
* subject to successful completion of all testing.
SEM R2.5.0 – November 2014 - Milestones
6
• Release Cut-Off Date is Sept 5th (Friday) 2014.
SEM R2.6.0 – May 2015
7
Questions