Market Street – Federal Phase between Hickory & Bronson St. General Information. Functional Classification – Major Collector Number of Lanes – Two (2) Approximate Length of Project: ¾ of a mile Posted Speed – 30 mph AADT – 4,001 (8% Truck). 30. Project Purpose. Rehabilitate and widen - PowerPoint PPT Presentation
Citation preview
Market Street – Federal Phasebetween Hickory & Bronson St
General InformationFunctional Classification – Major CollectorNumber of Lanes – Two (2)Approximate Length of Project: ¾ of a milePosted Speed – 30 mphAADT – 4,001 (8% Truck)
30
Rehabilitate and widen
Improve direct connectivity to three municipal parks
Include ADA accessible sidewalks
Roadway lighting, storm improvements, and intersection improvements
Project Purpose
The road does not allow sufficient movement of vehicular traffic with on street parking
Limited pedestrian movement and significant ADA deficiencies
The project will provide safe connections to the rest of the City
Safety Considerations
Market St.
Bronson St.
Lincoln Hw
y
North
Phase Total Federal Local Match
Funds Year
Preliminary Engineering $227,500 $182,000 $45,500 08/201
4
Right of Way $50,000 $40,000 $10,000 06/2016
Construction $1,682,000 $1,345,600 $336,400 03/2018
Construction Inspection $252,300 $201,840 $50,460 03/201
8
Total $2,211,800 $1,769,440 $442,360
Financial Plan
Supported By:Highlighted in the City of
Warsaw Transportation and Thoroughfare Plan
Kosciusko County 2035 Transportation Plan
Support form:Kosciusko EDC City of WarsawLocal neighborhood
associationLocal businesses
Planning & Community Support
Total Federal Funding Awarded$1,769,440
Hickory to Bronson
Project Split
Market Street – Local Phasebetween Bronson St & Argonne Rd
Market Street Design Concept