http://nodal.ercot.com 1

Market Readiness Seminar 6

Remaining Market Trials and Cutover Activities

Sept 01, 2010

Page 2: Market Readiness Seminar 6

http://nodal.ercot.com 2

Antitrust Admonition

ANTITRUST ADMONITION

ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws.

DISCLAIMER

All presentations and materials submitted by Market Participants or any other Entity to ERCOT staff for this meeting are received and posted with the acknowledgement that the information will be considered public in accordance with the ERCOT Websites Content Management Operating Procedure.

Page 3: Market Readiness Seminar 6

http://nodal.ercot.com 3

Agenda

• Review of Phase 5 Activities

• 168-Hour Test Breakdown of Activities– 168-Hour Measurements

• Objective / Participation Requirements• Entry / Exit Criteria• Evaluation Criteria

– Preparation Activities• Completed – Full System Market and Reliability Tests• Completed – Outage Scheduling Verification and Synchronization• Completed – CRR September Auction• Network Model Load• Data Used for 168-Hour Test

– Nodal Production Environment– 168-Hour Test Execution

• Schedule• Communications Plan

• Post 168-Hour Testing Activities• Cutover and Market Readiness Activities

Page 4: Market Readiness Seminar 6

http://nodal.ercot.com 4

Review of Phase 5 Activities

Page 5: Market Readiness Seminar 6

Review of Phase 5 Activities Market Trials 2010 Roadmap

http://nodal.ercot.com 5

Page 6: Market Readiness Seminar 6

http://nodal.ercot.com 6

168-Hour Test Measurements

Page 7: Market Readiness Seminar 6

http://nodal.ercot.com 7

168-Hour Test Breakdown of Activities: Objective / Participation Requirements

• Objective• Conduct a full rehearsal of the Nodal Day-Ahead Market (DAM), Reliability Unit

Commitment (RUC), Real Time Market and Load Frequency Control (LFC)• Continuous seven day period of Market Systems and 48 hours of Closed Loop LFC• Components required and to be exercised during the 168-Hour test:

• The Day Ahead functions including DAM, DRUC, HRUC and WRUC • The Real Time systems performing SCADA, Network Security Analysis,

Transmission Constraint Management, SCED, and LFC • The Nodal support systems including Network Model Management, Outage

Scheduler, Outage Evaluation tools• Credit Monitoring and Management (CMM)• Settlements and Billing• Posting of applicable Reports and Extracts

• Participation Requirements• The value of the 168-Hour Test is dependent on participation by the Market. • The 168-Hour Test is required by all registered Market Participants intending to be

involved in the Nodal Market• Participation data and metrics will be published and made readily available to the

ERCOT Board, Independent Market Monitor and the related Market Participant Forums (NATF, TAC)

• Metrics will also include comparisons of Zonal Resource Plans to Nodal COPs.• Participation should be reasonably reflective of post Go-Live behavior

 

Page 8: Market Readiness Seminar 6

http://nodal.ercot.com 8

168-Hour Test Breakdown of Activities: Entry / Exit Criteria

Entry Criteria for the 168-Hour test will be as follows:• All defined Market Trials Testing up until the 168-Hr test has been completed

in accordance with the Market Trials Handbooks published to the Nodal Readiness Center

• ERCOT declares readiness for initiating the 168-Hour test to TAC and the Board and obtains director level sign off from ERCOT management.

Exit Criteria• 168 hours of continuous Nodal systems testing have been completed without

encountering any major system issues that would prevent the Nodal Market from going live while maintaining system security and reliability as required by the ERCOT Protocols, Operating Guides, other binding documents, and NERC Reliability Standards.

• ERCOT provides a test summary report to TAC and the Board outlining the successful testing processes.

Page 9: Market Readiness Seminar 6

http://nodal.ercot.com 9

168-Hour Test Breakdown of Activities: Evaluation Criteria

• Evaluation Criteria was agreed on in coordination with the Market at the NATF and TAC forums

• Evaluation Criteria will be reviewed holistically in that no one issue from this list will necessarily constitute a failure of the test

• Evaluation Criteria is included in the Appendix of this presentation and in the 168-Hour Handbook

Page 10: Market Readiness Seminar 6

http://nodal.ercot.com 10

168-Hour Test Breakdown of Activities: Preparation Activities

• Full System Market and Reliability Tests• The following tests have been completed prior to the start of the 168-Hour tests:

• 2-Hour Test – Completed May 20, 2010• 8-Hour Test – Completed June 17, 2010• 5-Hour Test – Completed July 21, 2010• 24-Hour Test 1 – Completed August 5, 2010• 24-Hour Test 2 – Completed August 20, 2010• 40-Hour Test – Completed August 28, 2010

• Total Full System Tests completed prior to the 168-Hour Tests: 103

• Outage Scheduling Transition Plan• 08/16/2010: ERCOT released the Outage Scheduler to be synchronized and

verified by TSPs and QSEs for outages effective for the month of September• 08/30/2010: TSP and QSE deadline to complete synchronization and verification• Market Participants that have not yet completed this should:

• Continue work on this activity• If there are questions or issues, contact ERCOT at [email protected]

• Congestion Revenue Rights Auction• 08/27/2010: ERCOT posted the Auction Results for the September Monthly Auction

Page 11: Market Readiness Seminar 6

http://nodal.ercot.com 11

168-Hour Test Breakdown of Activities: Preparation Activities

• Network Model Load• 09/01/2010: Network model to be used during the 168-Hour test loaded to the

Nodal Production Environment• Going forward the network model loads will generally follow the Zonal schedule

• Data from Market Trials Phase 5 to be used in the 168-Hour test• To the extent necessary to support settlement and credit operations, ERCOT will

use estimated and/or settled data from Operating Days in July and August from MT5 as well as the CRR inventory from the September CRR auction (see above) during the 168-hour test.

Page 12: Market Readiness Seminar 6

http://nodal.ercot.com 12

Nodal Production Environment

Page 13: Market Readiness Seminar 6

http://nodal.ercot.com 13

Nodal Production Environment

• During the 168-Hour Test, applicable Nodal systems will be managed as if the systems were fully in production 7x24, exercising the same procedures used for Zonal production operations

• Change Controls during and leading up to the test shall adhere to a similar SLA as Zonal Production

• If an outage is required, a Market Notice will be issued and determination will be made if this will require a restart of the 168-Hour test

Page 14: Market Readiness Seminar 6

http://nodal.ercot.com 14

168-Hour Execution

Page 15: Market Readiness Seminar 6

http://nodal.ercot.com 15

168-Hour Execution: Schedule

• September 8, 2010 - 168-Hour Test begins– Day ahead Market will run for Operating Day September 9, 2010 using the DAM ACL sent from CMM – DRUC and WRUC will run per protocol timelines starting the first day of the test – ERCOT will begin running hourly HRUC at 1800 when the Adjustment Period opens.– All Real Time telemetry, and Market Submission shall continue to be submitted by the Market– All postings delivered in previous Market Trials Phases delivered per Nodal Protocol timelines– Initial DAM / RTM statements posted per the Nodal settlements calendar– Production level support, including those systems that are supported 24x7, goes into effect for the duration of the 168-Hour

Test– For the duration of the test, DAM, RUC, Settlements and Credit processes will run per Nodal Protocol guidelines in an open

loop format. Zonal will continue to commit units using the RPRS processes and actual, binding settlements will execute per Zonal Protocols.

• September 12 – September 14, 2010 – Full System Market and Reliability Test During the 168-Hour Test– September 12, 2010 at 2:00 PM, all generation will begin transitioning to Nodal control estimated to be completed by 3:00 PM– The ERCOT grid will run under Nodal Control through September 14, amounting to a total of 48 Hours of Full System Market

and Reliability Testing during the 168-Hour Test– Day Ahead Market, RUC processes and SASM will continue to be executed per Nodal Protocols.

• Zonal will continue to commit units using the RPRS and OOMC processes and actual, binding settlements will execute per Zonal Protocols.– September 14, 2010 all generation will transition back to Zonal starting at 1:00 PM, estimated to be completed by 2:00 PM

• September 14, 2010 – September 15, 2010– ERCOT will continue to run the remaining operating days of the 168-Hour test, executing DAM, RUC, settlements and credit

processes– The final day of the 168-Hour test will be on September 15, 2010

• September 16 or 17, 2010– Special NATF session will be held to review the DAM testing results of the 168-Hour test and determine remaining testing

objectives for Market Trials. RT testing results will be evaluated once RT settlement statements are received.

Page 16: Market Readiness Seminar 6

http://nodal.ercot.com 16

168-Hour Execution: Communications Plan

• ERCOT will host a daily WebEx / Conference call• This will occur at 10am each day of the 168-Hour Test• Details will be posted to the ERCOT calendar at

http://www.ercot.com/committees/nodal/mt/ • ERCOT will maintain a list of known issues to updated each day on these conference

calls• This will be posted to the ERCOT Readiness Center on a daily basis• Additionally, this will also be posted to the ERCOT calendar instance for that day.

• Issues Raised by the Market• Market Participants will continue to utilize the [email protected] email address

outside of the daily conference calls

• Full System Market and Reliability Test• ERCOT will maintain a separate WebEx conference during the 48-Hour test

• 9/12/2010: 12:00 PM – 12:00 AM• 9/13/2010: 6:00 AM – 12:00 AM• 9/14/2010: 6:00 AM – 2:30 PM

• Details for this WebEx will be sent out by Friday 09/03/2010

Page 17: Market Readiness Seminar 6

http://nodal.ercot.com 17

168HR Supporting Materials

Page 18: Market Readiness Seminar 6

http://nodal.ercot.com 18

Evaluation Criteria

• Validate ERCOT and Market Participants have the proper resources and expertise to manage a Nodal system for 7 days. This will be measured by the successful adherence to internal ERCOT procedures during the 168-Hour test to be validated by the ERCOT Training Department during the test and evidenced to the market within a report. Market Participant’s Nodal Accountable Executive will self attest to their criterion.

• Credit – monitor credit exposures, create credit reports and accurately reflect each market participant’s credit position based on their activity during the 168-Hour test.

• Validate data model accuracy between all systems including integration of the upstream NMMS system with downstream systems (e.g. DAM, MMS, EMS and CRR). This will be measured by existing ERCOT procedures. All issues observed regarding inaccurate modeling during the 168-Hour test will be reported on by ERCOT to the ERCOT Board, Independent Market Monitor, and the related Market Participant forums (NATF and TAC) as to the problem found, root cause of the error in the first place, and what process changes are being implemented to ensure that similar model accuracy issues do not reoccur going forward. ERCOT shall attest to the data model accuracy in and between all systems as a result of TSP and Resource Entity data passing the ERCOT validation rules.

• Execute DAM, DRUC, HRUC and WRUC for 7 days within timelines set by Nodal Protocols. If any activities fall outside of expected timelines, procedures for handling such incident must be executed by ERCOT personnel in adherence with Nodal Protocols and internal ERCOT procedures.

• Verify RT Operators can maintain system frequency to scheduled frequency, maintain ancillary obligations and resolve constraints during the period in which ERCOT will be performing Full System Market and Reliability tests during the 168-Hour Test.

Page 19: Market Readiness Seminar 6

http://nodal.ercot.com 19

Evaluation Criteria

• Validate ERCOT can effectively and accurately manage all constraints in both DAM and RT (i.e. not constrain on invalid contingencies or inaccurate line ratings) and system will utilize full list of competitive constraints.

• Validate that ERCOT can execute and manage all SPS, RAPs, PCAPs, MPs, and TOAPs to control congestion in the DAM, DRUC, HRUC, and RT as appropriate.

• Validate that ERCOT is accurately reflecting all congestion mitigation measures (SPS, RAPs) in DAM.

• The rolling CPS1 one minute average score must equal or exceed 100% during the Full System Market and Reliability test period. The target minimum is 125.

• Note that the CPS1 average will not take into account the two one-hour periods when ERCOT is transitioning to Nodal and then back to Zonal and any periods in which ERCOT must deploy RRS in response to system contingencies.

• Zonal Commercially Significant Constraints (CSCs) and Closely Related Elements (CREs). managed below thermal limits.

• Local Congestion managed below thermal limits.

• Stability limits managed below transfer limits.

• No NERC Disturbance Control Standard (DCS) failure if applicable.

• No LFC-SCED system issues that result in termination of the test.

• The 168-Hour test will provide adequate data to set the GREDP/CLREDP performance. criteria variables X, Y, and Z. ERCOT shall produce appropriate reports that can be used to set these variables.

• Bilateral trades are processed and flow through the market systems with results returned to MPS.

• Outputs from the Day Ahead Market, Reliability Unit Commitment, and Real Time Market can be reasonably explained based on the inputs.

Page 20: Market Readiness Seminar 6

20

04/21/23

Cut-Over Milestones

01 September 2010 Market Readiness Seminar

Page 21: Market Readiness Seminar 6

21

Nodal Cutover and Market Transition – Key Cut-Over Milestones

Key Cut-Over Milestones

Network Model

Nodal Protocol Section 3.10 goes into effect (Sept. 1)• TAC Approval – July 1 (July 20)• Board Approval – July 20• Market Notice – July 30

Congestion Revenue Rights

Nodal Protocol Section 7 goes into effect (Oct. 13)• TAC Approval – August 5• Board Approval – August 17• Market Notice – September 13

Outage Scheduler

Nodal Protocol Section 3.1 goes into effect (Nov. 1)• TAC Approval – August 5• Board Approval – August 17• Market Notice – October 1

Full Nodal Operations

Nodal Protocol Sections 3, 4, 5 and 6 go into effect as well as all other unimplemented Protocol Sections (Nov. 23)

• TAC Approval – October 7th • Board Approval – October 19th • Market Notice – October 23rd

01 September 2010 Market Readiness Seminar

Page 22: Market Readiness Seminar 6

22

04/21/23

Key Cutover ActivitiesThru December 2010

01 September 2010 Market Readiness Seminar

Page 23: Market Readiness Seminar 6

23

Cut-Over Timeline – Thru December 2010

01 September 2010 Market Readiness Seminar

Page 24: Market Readiness Seminar 6

24

Functional Area

Task Plan

Data Prep

Decommission/Retirement Template

Contingency/Back-out Template

May June July Aug Sept Oct Nov Dec

Cut-Over Monthly Outlook – August

Key Cut-Over Activities for August 2010•(08/01) Model: Begin network modeling timelines-Complete

•(08/13) OS: Outage Scheduler Zonal to Nodal Import process run

•(08/13) CRR: Last day to register for CRR December monthly auction

•(08/16) OS: ERCOT releases Outage Scheduler to Market

•(08/16-09/17) OS: Market Participants synchronize / verify outages in the Nodal Outage Scheduler to the Zonal Outage Scheduler for Outages effective during and after December 2010

Network Model Outage Scheduler Congestion Revenue Rights

Entities InvolvedERCOTTSPREsCRRAHQSE

Impacts•TSPs/REs submit Transmission and Resource data for December model (05_Nodal_Load_transition_1_0.doc posted on 06/01 NATF Materials)•Resource outages will NOT be imported during Zonal to Nodal import into Outage Scheduler•CRRAH must register by deadline to be eligible to participate in the December Auction (Protocol 16.8.2)•TSPs/QSEs can begin entering outages in Outage Scheduler via Web Service or UI •TSPs/QSEs are responsible for verifying outages imported to Nodal Systems and correcting any missed outages or incorrect outages by 09/17/2010

Functional Area

01 September 2010 Market Readiness Seminar

Page 25: Market Readiness Seminar 6

25

Key Cut-Over Activities for September 2010

• (09/01) Model: Network Model Go-Live

• (09/01) Model: Deadline to submit Model changes for Month of December

• (09/02) Model: Begin interim update process

• (09/01) CRR: ERCOT publishes CRR Activity Calendar to MIS

• (09/08) CRR: Deadline for PCRR NOIE Contract Eligibility

• (09/17-12/01) OS: Outages are synched. Market Participants maintain outages in both the Zonal and Nodal Outage Scheduler for outages effective December and beyond.

Network ModelOutage SchedulerCongestion Revenue Rights

Functional Area

May June July Aug Sept Oct Nov Dec

Cut-Over Monthly Outlook – September

Entities InvolvedERCOTTSPREsCRRAHQSE

Impacts•TSPs / REs that submit Model changes to ERCOT by 09/01 will be applied prior to Go-Live

•From 09/02 forward until Go-Live any Model changes submitted to ERCOT for application prior to Go-Live will leverage the interim update process.  

•MPs can retrieve the CRR Activity Calendar from MIS public with a valid Digital Certificate

01 September 2010 Market Readiness Seminar

Page 26: Market Readiness Seminar 6

26

Impacts

•MIS UI and EWS Get Report unavailable from 10/03-10/11 for production reconfiguration**

•CRRAH able to retrieve ACLs from CRR system each business day.

•MPs can post additional collateral until 11/08/2010 for Dec 2010 CRR Auction

•MPs able to start retrieving Go-Live postings on MIS. Refer to EMIL for dates per posting.

•Dec 2010 CRR Model available on MIS

•Dec 2010 Monthly Auction Notice available on MIS

Functional Area

Network ModelOutage SchedulerCongestion Revenue RightsCreditMIS

May June July Aug Sept Oct Nov Dec

Cut-Over Monthly Outlook – October

Key Cut-Over Activities for October 2010

• (10/01) CRR: CRR system data clean up for Go-Live

• (10/01) Credit: ERCOT assesses each CPs credit worthiness for the Dec CRR Auction

• (10/02) OS: First pull of December Outages for CRR Network Model (for PCRR Allocation)

• (10/02) Model: Network Model built for CRR Allocation and Auction

• (10/03-10/11) MIS UI and EWS Get Report function not available (ERCOT back end reconfiguration)

• (10/13) OS:  Changes to December Outages considered for CRR Auction Model

• (10/13) Model:  Changes to Model considered for CRR December Auction

01 September 2010 Market Readiness Seminar

Page 27: Market Readiness Seminar 6

27

Impacts

•CRRAH able to retrieve ACLs from CRR system each business day.

•MPs can post additional collateral until 11/08/2010 for Dec 2010 CRR Auction

•MPs able to start retrieving Go-Live postings on MIS. Refer to EMIL for dates per posting.

•Dec 2010 CRR Model available on MIS

•Dec 2010 Monthly Auction Notice available on MIS

Functional Area

Network ModelOutage SchedulerCongestion Revenue RightsCreditMIS

May June July Aug Sept Oct Nov Dec

Cut-Over Monthly Outlook – October

Key Cut-Over Activities for October 2010

• (10/14-10/19) CRR: ERCOT begins accepting PCRR Nominations for December Monthly Auction (updated)

• (10/15-11/15) Model: Network Operations Model posted to TSP Citrix location and TSPs begin validation process

• (10/26) CRR: ERCOT shall allocate PCRRs to NOIEs for the 2010 December Monthly Auction and publish to MIS

• (10/26) CRR: ERCOT shall post CRR Network Model for the 2010 December Monthly Auction to MIS

• (10/28-11/08) Credit: ERCOT posts ACLs daily for CRR December monthly auction to CRR

• (10/29) CRR: ERCOT to post December 2010 Monthly Auction Notice to MIS

01 September 2010 Market Readiness Seminar

Page 28: Market Readiness Seminar 6

28

MIS UI and EWS Get Report Reconfiguration Details (10/03/2010 – 10/11/2010)

• Market Participants will not have access to the MIS UI and EWS Get Reports functionality.

• Market Participants will need to use the direct links (listed on next slide) or Citrix to access system applications.

• All other EWS will be left on and from 10/1 up until the First Run Date as defined in EMIL of the CDR report, the EWS will return ‘no reports found’ during that time.

MIS UI and EWS Get Report Go-Live (10/12/2010)

• Postings will be made available based on the EMIL posting date going forward.

• Postings live prior to 10/12/2010 will continue to be made available at this time.

• Market Participants will only have access to go-live posting data. Data from Market Trials activities is no longer available for download.

Cut-Over Monthly Outlook – October – MIS UI and EWS Get Report Reconfiguration Details

01 September 2010 Market Readiness Seminar

Page 29: Market Readiness Seminar 6

29

URLs to be used during cutover activities:

– Network Model via Citrix:– https://gateway.ercot.com/vpn/index.html

– Market Manager User Interface:– https://mis.ercot.com/mmsui/mmsui/displayTradesLanding.action

– Outage Scheduler Application:– https://mis.ercot.com/osrui/osrui/Summary.action

– CRR Application (MUI):– https://mis.ercot.com/crr/mui/ListAllUserMessage.do - direct link for CRRAHs– https://mis.ercot.com/crr/mui/editSMPCreditLimit.do - direct link for CPs

– Web Services Endpoint URL:– https://misapi.ercot.com/2007-08/Nodal/eEDS/EWS

Cut-Over Monthly Outlook – October – MIS UI and EWS Get Report Reconfiguration Details

01 September 2010 Market Readiness Seminar

Page 30: Market Readiness Seminar 6

30

Impacts•Available Credit Limit is locked for CRRAHs•CRRAHs can submit disputes against CRR Auction Invoice via the API or MIS •CRRAHs can receive postings on MIS •QSEs can begin DAM Bid submission (15 submission items)•Market checkpoint calls begin to facilitate issues and readiness•LFC testing in November will not include Settlements•Daily Market Conference Bridge starts 11/23

Functional AreaSettlementsCreditCongestion Revenue RightsDisputesMarket Management

May June July Aug Sept Oct Nov Dec

Cut-Over Monthly Outlook – November

Key Cut-Over Activities for November 2010

• (11/8/2010 12:00pm) Credit: Collateral Posting Deadline (Dec Auction)

• (11/8/2010 5:00pm) CRR: Credit Lock for Dec CRR Auction

• (11/9/2010 – 11/11/2010) CRR: December CRR Auction Bid Open/Close

• (11/12/2010) CRR: December CRR Auction Executes

• (11/15/2010) CRR: December CRR Auction Results published

• (11/16/2010) Settlements: December CRR Auction Invoice published

• (11/16/2010) Disputes: Dispute submitted to ERCOT for CRR Invoice

• (11/19/2010) Credit: Payment Due for December CRR Auction Invoices

• (11/22/2010) Settlements: Payments to CRRAH (Dec Auction)

• (11/23/2010) Credit: ERCOT to Release ACL (TPE and ACL Reports Available on MIS)

• (11/23/2010) Market Submission Opens (Remaining Protocol Go-Live)

• (11/24/2010) Model: Network Model Load

• (11/29/2010) Credit: ERCOT to Publish ACL for the initial Day-Ahead Market execution by ERCOT

01 September 2010 Market Readiness Seminar

Page 31: Market Readiness Seminar 6

31

Go-Live Sequencing

Market Readiness Seminar01 September 2010

Cut-Over Monthly Outlook – Go-Live Sequence of Events

Time Action Comments

up to 10:00 Bids and Offer submission  QSE submit bids and offers

10:00 Close DAM  

10:00 Execute Dam Clearing Process  

13:30 Approve DAM resultsDay Ahead results will be posted to MIS

14:00 LFC CutoverGeneration control moves to Nodal systems

1330-1430Submit Post DAM COP and offers

 QSE submit Post Dam COPs and Offers

14:30 Close for RUC  

14:30 Begin Execution of DRUC  

16:00 Approve DRUC Results  

16:00 Post DRUC Results  

18:00 HRUC executions HourlyHRUC runs hourly thru 23:59:59 of Operating Day

Page 32: Market Readiness Seminar 6

32

Impacts

•Daily Market Calls continue for issue facilitation•MPs receive 1st Nodal Invoice for DAM and RTM via MIS•MPs can submit Disputes via MIS or API

Functional AreaNetwork ModelSettlementsCongestion Revenue RightsCreditMarket Management System

May June July Aug Sept Oct Nov Dec

Cut-Over Monthly Outlook – December

Key Cut-Over Activities for December 2010

• (12/01/10) Nodal Program: Nodal Go-Live (Operating Day 1)

• (12/3/2010) Settlements: Nodal Day Ahead Market Statement & Invoice Available

• (12/3/2010) Disputes: Disputes submitted to ERCOT for DAM Invoice

• (12/8/2010) Credit: Nodal Payment Due for OD12/01/2010

• (12/9/2010) Credit: Nodal Payout for OD12/01/2010

• (12/15/2010) Model: Network Model Load

• (12/13/2010) Settlements: Nodal Real-Time Statement Available

• (12/16/2010) Settlements: Nodal Real-Time Invoice Available

• (12/27/2010) Credit: Nodal Payment Due for Real-Time Invoice 12/16/10

• (12/28/2010) Credit: Nodal Payout for Real-Time Invoice 12/16/10

01 September 2010 Market Readiness Seminar

Page 33: Market Readiness Seminar 6

33

Nodal Cutover – Nodal System Readiness Criteria

Nodal System Readiness Update

01 September 2010 Market Readiness Seminar

Page 34: Market Readiness Seminar 6

34

Nodal Cutover Communications – Zonal Protocol 21.12.3

21.12.3 Notice to Market Participants of Effective Date for Nodal Protocol Provisions and Retirement of Zonal Protocol Provision

No part of the nodal market design may start operation until all the Market Readiness Criteria for that part of the nodal market design have been met. Certification that all Market Readiness Criteria have been met must be made at least by each of the following: the Technical Advisory Committee (TAC), ERCOT and the ERCOT Board. Upon such certification, ERCOT shall issue two Notices alerting Market Participants to the effective date of Nodal Protocol sections and the retirement of Zonal Protocol sections, as applicable. ERCOT shall issue the first Notice no less than thirty (30) days prior to the effective date or retirement date, as applicable, and the second Notice no less than ten (10) days prior to the effective date or retirement date, as applicable. The Notice shall include:

(1) The Nodal Protocol Sections to become effective; and

(2) The Zonal Protocol Sections to be retired, if any

01 September 2010 Market Readiness Seminar

Page 35: Market Readiness Seminar 6

35

Nodal Program Communications

Readiness Signoff Schedule

Network Operations Modeling

06/30

07/01

07/20

07/30

09/01

ERCOT Management Readiness Signoff

TAC Approval

Board of Directors Approval

30 Day Market Notice sent

Nodal Protocol Section 3.10 goes into effect

Congestion Revenue Rights

08/04

08/05

08/17

09/13

10/13

ERCOT Management Readiness Signoff

TAC Approval

Board of Directors Approval

30 Day Market Notice sent

Nodal Protocol Section 7 goes into effect

Outage Scheduling

08/04

08/05

08/17

10/01

11/01

ERCOT Management Readiness Signoff

TAC Approval

Board of Directors Approval

30 Day Market Notice sent

Nodal Protocol Section 7 goes into effect

Full Nodal Operations

10/01

10/07

10/19

10/23

11/23

ERCOT Management Readiness Signoff

TAC Approval

Board of Directors Approval

30 Day Market Notice sent

Nodal Protocol Sections 3,4,5,6 go into effect as well as all other unimplemented Protocol Sections

01 September 2010 Market Readiness Seminar

Page 36: Market Readiness Seminar 6

36

Readiness Methodology

ERCOT will measure readiness by the following categories:• System Readiness – an evaluation of a particular system

needed to support identified market activities• Process Readiness – an evaluation of the Processes and

Procedures necessary to support identified market activities• People Readiness – an evaluation of ERCOT and Market

Participant capabilities to support identified market activities

ERCOT plans to review the Market Readiness Criteria at NATF and subsequently request a vote from TAC per Section 21.12.3, Notice to Market Participants of Effective Date for Nodal Protocol Provisions and Retirement of Zonal Protocol Provision

01 September 2010 Market Readiness Seminar

Page 37: Market Readiness Seminar 6

37

Readiness Methodology

System Readiness – evaluation of the Nodal system to support the market design– Core system functionality delivered

• Protocol required system functionality available for market testing

– System Integration delivered• System to system integration delivered to support Market Timeline

and Business Processes

– Known defects resolution plan• All ‘Must fix prior to go-live’ defects have a resolution plan in place

– Active Readiness Metrics• Current status of Readiness Metrics

01 September 2010 Market Readiness Seminar

Page 38: Market Readiness Seminar 6

38

Readiness Methodology

Process Readiness – evaluation of the Processes and Procedures necessary to support the market design– Procedures complete

• ERT project procedures to support business processes complete

– System cutover transition plan established• ERCOT and Market Participant business activities required for

transitioning into Go-Live have been established and communicated.

– Market rules transition communicated• Nodal and Zonal Protocol effective / retirement dates identified and

communicated for Market Participant review

01 September 2010 Market Readiness Seminar

Page 39: Market Readiness Seminar 6

39

Readiness Methodology

People Readiness – evaluation of ERCOT employee readiness and Market Participant knowledge to support the market design– ERCOT staff supporting Market Trials

• ERCOT Business teams supporting system execution, problem resolution, and Market questions

– ERCOT staff trained on System and Processes• ERCOT Business teams training status based on identified ERT

training metrics

– Market Participant Training delivered• ERT external training classes and web based training provided by

the Nodal training project

01 September 2010 Market Readiness Seminar

Page 40: Market Readiness Seminar 6

40

NMMS Overview

Technical Advisory Committee2 September 2010

ERCOT

NATF

TAC

BOD

Recommendation of Certification

Open Defects:

Sev 1

Sev 2

Sev 3-5

0

Status / Other Issues: • Stability issue resolved as of July 1 (ERCOT continues to monitor production) • Navigation performance issues improved Aug 1st (43% reduction in response time measured)• Validation performance improvement patch was added on Friday, August 27 th (expected a 20-40% reduction in validation time). Improvement on validation times were tested as follows:

•Average: 45.18%•Median: 66.41%•Max: 97.46%

Deferred Defects:

Deferred 110

0

Page 41: Market Readiness Seminar 6

41

Network Operations Modeling – Go Live

System Readiness Planned Completion

Status

SEM Go-Live 8/31/09 Complete

TSP Model Validation (Metric MP14C) 4/30/10 Complete

Model Change Request Tools Support Market Updates Ongoing Green

Regular Model Loads into Market Trials Systems Ongoing Green

8 Hour LFC Test Executed w/ Network Model from NMMS 6/17/10 Complete

Process Readiness

Network Operations Change Request Timeline Transition Plan established

6/03/10 Complete

Network Modeling Procedures Ready 8/01/10 Complete

Market Rules – Protocol Transition Plan for September 7/23/10 Complete

01 September 2010 Market Readiness Seminar

Status updated post ERCOT, TAC, BOD approval – in RED

Page 42: Market Readiness Seminar 6

42

Network Operations Modeling – Go Live

People Readiness Planned Completion

Status

ERCOT Staff Support of Market Trials Ongoing Green

ERCOT Staff Trained on System and Processes 6/22/10 Green

Market Participant Training Delivered 7/29/09 Complete

Readiness Review and Approval

NATF Review6/23/107/08/10

Complete

ERCOT Management Approval 6/30/10 Complete

TAC Approval 7/20/10 Complete

BOD Approval 7/20/10 Complete

30 Day Market Notice 7/30/10 Complete

10 Day Market Notice 8/20/10 Complete

01 September 2010 Market Readiness Seminar

Status updated post ERCOT, TAC, BOD approval – in RED

Page 43: Market Readiness Seminar 6

43

OS Overview

Technical Advisory Committee2 September 2010

ERCOT

NATF

TAC

BOD

Recommendation of Certification

Open Defects:

Sev 1

Sev 2

Sev 3-5

0

Status / Other Issues: • No defects reported in the Outage Scheduler

– Outage Scheduler transition tasks were completed on 8/13 and the system was ready for dual entry and validation on 8/16

– Market Notice for dual entry and validation was sent on August 16 th

•All Outage scheduler issues within the TSP Issues list have either been addressed or are resolved

Deferred Defects:

Deferred 11900

Page 44: Market Readiness Seminar 6

44

Outage Scheduling – Go Live

System Readiness Planned Completion

Status

Outage Scheduler released to Market Trials 2/01/10 Complete

Outages Scheduler Integrated with DAM, RUC 4/15/10 Complete

Outage Scheduler Qualification Connectivity Qualification (MP20) 4/01/10 Green

Process Readiness

Verify Outage Evaluation System Functionality (EMO3 #1) 6/23/10 Green

Outage Coordination Procedures 7/16/10 Complete

Nodal Protocol Transition Plan Updated for Outage Scheduling 7/29/10 Complete

Outage Scheduling Transition Plan Established 7/08/10 Complete

01 September 2010 Market Readiness Seminar

Page 45: Market Readiness Seminar 6

45

Outage Scheduling – Go Live

People Readiness Planned Completion

Status

ERCOT Staff Support of Market Trials Ongoing Green

ERCOT Staff Trained on System and Processes 09/03/10 Green

Market Participant Training Delivered 7/15/10 NMMS/OS work-

shop added

Overall Readiness

NATF Review7/08/10,

07/29/10 Complete

ERCOT Management Signoff 8/04/10 Complete

TAC Approval 8/05/10 Complete

BOD Approval 8/17/10 Complete

30 Day Market Notice 10/01/10

10 Day Market Notice 10/21/10

01 September 2010 Market Readiness Seminar

Page 46: Market Readiness Seminar 6

46

CRR Overview

Technical Advisory Committee2 September 2010

ERCOT

NATF

TAC

BOD

Recommendation of Certification

Open Defects:

Sev 1

Sev 2

Sev 3-5

0

Status / Other Issues: • Working with Siemens on automated processor fix. Expectation is to receive fix before Go-Live

– Incorrect Loadzone Designation from Topology Processor Output file– Resource Nodes missing from Settlement Point output file produced by Topology Processor– Topology Processor cannot consume outages information for CRR modeling– CRR MUI requires a system reboot for Bid Limit to take effect (internal to ERCOT) workaround is nuisance -

targeting 09/13/2010 resolution

Deferred Defects:

Deferred 40

4

Page 47: Market Readiness Seminar 6

47

CRR Allocation and Auction – Readiness Update

System Readiness Planned Completion

Status

CRR System released to Market Trials 2/01/10 Complete

CRR Integrated in Market Trials 5/01/10 Complete

CRR Account Holder Connectivity Qualification MP 15 (B) 9/17/10 Red**

Operation of CRR Auctions and Allocations (CRR3) 8/17/2010 Complete

Verify CRR Auction Invoices (CO8) 8/17/2010 Complete

Process Readiness

CRR Procedures 6/25/10 Complete

Nodal Protocol Transition Plan Updated for CRR 7/29/10 Complete

TCR to CRR Transition Plan (CRR4) 9/29/09 Complete

** Red due to MPs registering but not working to get qualified. (inflated denominator)

01 September 2010 Market Readiness Seminar

Page 48: Market Readiness Seminar 6

48

CRR Allocation and Auction – Go Live

People Readiness Planned Completion

Status

ERCOT Staff Support of Market Trials Ongoing In Progress

ERCOT Staff Trained on System and Processes 06/25/10 Complete

Market Participant Training Delivered 07/15/09 Complete

Overall Readiness

ERCOT Management Signoff 08/04/10 Complete

NATF Review 07/08/10, 07/29/1008/03/10

Complete

TAC Approval 08/05/10 Complete

BOD Approval 08/17/10 Complete

30 Day Market Notice 09/13/10

10 Day Market Notice 10/03/10

01 September 2010 Market Readiness Seminar

Page 49: Market Readiness Seminar 6

49

MMS – Day Ahead, Adjustment Period, RT Market Overview

Market Readiness Seminar01 September 2010

ERCOT

NATF

TAC

BOD

Recommendation of Certification

Open Defects:

Sev 1

Sev 2

Sev 3-5

0

Status / Other Issues: •MMS currently has 58 Open defects in Test targeted to be fixed by September 3.

•21 DAM•2 AS Mgr•1 CIM, 1 SASM, 1 CCT, 1 Validation Rules•9 Background Processing•3 SCED•6 RUC•13 Market Infrastructure including 6 GUI

•MMS currently has 24 Open defects in development targeted to be fixed by October 1.•6 DAM, 4 RUC, 4 SCED, 3 MI, 7 GUI

•MMS remaining 13 (7 performance, 3 MOI, 3 MI) defects are being reviewed by business for final disposition.

Deferred Defects:

Deferred 4443

52

Page 50: Market Readiness Seminar 6

50

MMS – Day Ahead, Adjustment Period, RT Market – Readiness Update

System Readiness Planned Completion

Status

MMS System release to Market Trials 2/01/10 Complete

Market Submission Connectivity Qualification (MP3) Ongoing Green

Real-Time Market Daily Participation (MP15A) Ongoing Green

Generate LMP’s for 6 months (MO5) Ongoing Green

Verify SCED Price Validation (MO4) Ongoing Green

DAM Participation (MP16) Ongoing Amber

Generate Day-Ahead LMPs (MO9) Ongoing Green

Verify DAM Price Validation (MO8) Ongoing Green

DRUC Execution (MO10) Ongoing Green

Verify Supplemental Ancillary Services Market (MO3) Ongoing Green

Process Readiness

Day Ahead, Adjustment Period and RTM Procedures 8/31/10 Complete

MMS Day Ahead & Real Time Price Validation Procedures 8/31/10 Complete

Nodal Protocol Transition Plan Updated for DAM, RUC, SASM, SCED

People Readiness

ERCOT Staff Support of Market Trials 09/30/2010 In Process

ERCOT Staff Trained on System and Processes 8/27/10 Complete

Market Participant Training Delivered Ongoing In Process

01 September 2010 Market Readiness Seminar

Page 51: Market Readiness Seminar 6

51

EMS – Real-Time Operations

Market Readiness Seminar01 September 2010

ERCOT

NATF

TAC

BOD

Recommendation of Certification

Open Defects:

Sev 1

Sev 2

Sev 3-5

0

Status / Other Issues: • EMS currently has 20 Open defects in development targeted to be fixed by October 1.

•1 EMS Interface, 1 CIM Importer, 1 PSSE export•6 STNET/SMTNET/OE•1 VSAT•3 RLC•1 SE•2 TCM•3 LFC/Generation

Deferred Defects:

Deferred 32112

8

Page 52: Market Readiness Seminar 6

52

EMS – Real-Time Operations Readiness Update

System Readiness Planned Completion

Status

EMS System Release to Market Trials 2/1/10 Complete

Verify ACE Performance (EMO5) 4/21/2008 Complete

Individual LFC Testing (EMO6) 5/31/2010 Green

Telemetry / ICCP System Failover (N2) Ongoing Green

Telemetry Compliance (MP6) 6/2/2010 Green

Validate Telemetry / SE ISM / Data Accuracy (E3) Planned Planned

State Estimator Standards Performance (EMO9) Ongoing Green

RTCA Zonal to Nodal Modeling Differences (EMO9) Ongoing Amber

RTCA CSC Zonal to Nodal Comparison (EMO9) Ongoing Green

Verify Voltage Support Functionality (EM02) 9/8/2010 Planned

Anomalous/Auto-Disabled Telemeted Points (EMO10) Ongoing Green

Verify Load Forecast Accuracy (EMO7) Planned Planned

Process Readiness

RT Operations Business Procedures 8/31/10 Complete

Nodal Protocol Transition Plan Updated for RT Operations 7/29/10 Complete

People Readiness

ERCOT Staff Support of Market Trials 9/30/10 In Process

ERCOT Staff Trained on System and Processes 9/3/10 In Process

Market Participant Training Delivered Ongoing In Process

01 September 2010 Market Readiness Seminar

Page 53: Market Readiness Seminar 6

53

COMS – Settlement & Billing, Metering, and Data Aggregation - Overview

Technical Advisory Committee2 September 2010

ERCOT

NATF

TAC

BOD

Recommendation of Certification

Open Defects:

Sev 1

Sev 2

Sev 3-5

0

Status / Other Issues: • There are only 5 Open defects related to Core Systems at this time that are scheduled to be resolved by 09/03/2010.

-Adjustment to queries in Appworx Scheduling Job-IDR Staging Performance Enhancement-Adjustment to DAM Start Logic-Adjustment to Data Aggregation to prevent file aborts from missing data-Adjustment for AIEC calculation logic when RTPERFIP missing

There are 11 Commercial System Integration (CSI) defects related to transfer of data

Deferred Defects:

Deferred 456

9

Page 54: Market Readiness Seminar 6

54

S&B – Settlements and Billing, Metering, and Data Aggregation Readiness Update

System Readiness Planned Completion

Status

S&B System release to Market Trials 5/01/10 Complete

Verify RTM Settlement Statements (CO5) Ongoing Green

Verify RTM Settlement Invoices (CO6) Ongoing Green

Verify DAM Settlement Statements (CO3) Ongoing Green

Verify DAM Settlement Invoices (CO7) Ongoing Green

Verify CRR Auction Invoices (CO8) Ongoing Green

Settle Market for 7 days and provide appropriate extracts (CO1) 8/25/2010 Planned

Verify Dispute Process (CO2) 9/22/2010 Planned

Zonal/Nodal Coordinated Settlement Operations (CO4) 8/25/2010 Planned

Process Readiness

Settlements and Billing Procedures 8/24/10 Complete

Nodal Protocol Transition Plan Updated for Settlements and Billing 7/29/10 Complete

People Readiness

ERCOT Staff Support of Market Trials 9/30/10 In Process

ERCOT Staff Trained on System and Processes 7/30/10 In Process

Market Participant Training Delivered Ongoing In Process

01 September 2010 Market Readiness Seminar

Page 55: Market Readiness Seminar 6

55

COMS – Credit Overview

Market Readiness Seminar01 September 2010

ERCOT

NATF

TAC

BOD

Recommendation of Certification

Open Defects:

Sev 1

Sev 2

Sev 3-5

0

Status / Other Issues: • Open issues related to an intermittent performance issue and reporting and notifications. All items are internal ERCOT fixes targeting a 09/03/2010 resolution date.

– NPRR 241 - CMM:FCE Detail reports runs long– Exposure calculation engine hung process on– EAL Detail Report - In the OIA Section the corresponding Invoice data display– E-factors- Email notification about e-factors values to the counter-parties is not working correctly– Entity Name field is missing from the Enter CP Estimates screen – AIL Report- if the RTM Estimated data is missing for an Operating Date the report is not displaying data correctly

Deferred Defects:

Deferred 455

1

Page 56: Market Readiness Seminar 6

56

CMM – Credit Management and Monitoring – Go Live draft

System Readiness Planned Completion

Status

Credit Management Integrated in Market Trials 5/3/10 Complete

Verify Credit Calculations (CO10) 9/8/2010 Planned

Process Readiness

Credit Management Procedures 8/24/10 Complete

Nodal Protocol Transition Plan Updated for Credit Management 7/29/10 In Process

People Readiness

ERCOT Staff Support of Market Trials 9/30/10 In Process

ERCOT Staff Trained on System and Processes 8/13/10 Complete

Market Participant Training Delivered Ongoing In Process

01 September 2010 Market Readiness Seminar

Page 57: Market Readiness Seminar 6

57

MIS - Market Information System Overview

Market Readiness Seminar01 September 2010

ERCOT

NATF

TAC

BOD

Recommendation of Certification

Open Defects:

Sev 1

Sev 2

Sev 3-5

0

Status / Other Issues: • MIS defects of highest priority are around Extract Subscriber and LMP Contour Map and are targeting a resolution date by 10/11/2010. Fixes for most of these are already developed and will be tested during the MIS reconfiguration downtime. Examples are:

– Extract Subscriber - No choice to select the extract format – Extract Subscriber - Unable to unsubscribe the subscribed extract. – Extract Subscriber – ‘Help’ icon is not being displayed in Extract Subscriber application– LMP Contour Map Dashboard does not allow for alternate dates

Deferred Defects:

Deferred 79

3

Page 58: Market Readiness Seminar 6

58

MIS – Market Information System – Go Live draft

System Readiness Planned Completion

Status

MIS System release to Market Trials 2/1/10 Complete

MIS Compliance Test (E12) 9/8/2010 Planned

Process Readiness

MIS Procedures 8/25/10 Complete

Nodal Protocol Transition Plan Updated for MIS 7/29/10 Complete

People Readiness

ERCOT Staff Support of Market Trials 9/30/10 In Process

ERCOT Staff Trained on System and Processes 8/20/10 Complete

Market Participant Training Delivered Ongoing In Process

01 September 2010 Market Readiness Seminar

Page 59: Market Readiness Seminar 6

59

Nodal – Overall Readiness – Go Live draft

Market Participant Readiness Items Planned Completion

Status

QSE with Resource Connectivity to EDS Environment (MP2) 9/4/2008 Complete

ICCP Point to Point Telemetry Test (MP5) 9/4/2008 Complete

QSE Ability to Submit Transactions via MIS (MP8) 9/4/2008 Complete

QSE Ability to Submit Web Services Transactions (MP9) 9/4/2008 Complete

Resource Registration (MP11) 8/25/2010 Green

Wind Generation Resources ICCP Metrological Telemetry (MP21) Ongoing Amber

New Entrant Readiness (MP22) 8/25/2010 Green

Telemetry Quality (MP to ICCP Server) (MP23) Ongoing Green

Mapping of Resource and Loads in Private Area Networks (MP18) 8/25/2010 Green

Telemetry Compliance (MP6 - TSP) 6/2/2010 Green

Market Participant Nodal Readiness Declaration (R0) 10/19/2010 Planned

Independent Market Monitor

Market Monitor Systems Capability (IMM1) 10/19/2010 Planned

Validate ISM Access & Accuracy of Postings Required by the IMM (E7) 10/19/2010 Planned

01 September 2010 Market Readiness Seminar

Page 60: Market Readiness Seminar 6

60

Nodal – Overall Readiness – Go Live draft

ERCOT Readiness Planned Completion

Status

ERCOT Internal Training (E1) Ongoing Green

Develop Nodal Procedures (E9) Ongoing Green

Develop Nodal Operating Guides (E6) 8/25/2010 Planned

Validate ISM, CDR, and Lodestar Source Reporting Access & Accuracy for internal ERCOT use (E10)

10/19/2010 Planned

Verify ERCOT Performance Monitoring Test Plan (E2) 10/19/2010 Planned

Nodal SAS 70 Preparedness (E5) 10/19/2010 Planned

ERCOT Staffed for Texas Nodal Operations (E8) 8/25/2010 Green

Verify QSE Performance Monitoring Test Plan (E14) 10/19/2010 Planned

Verify TSP Performance Monitoring Test Plan (E15) 10/19/2010 Planned

Operating Personnel and Facilities Readiness (EMO13) 8/11/2010 Complete

ERCOT Operating Personnel and Facilities Readiness (MO7) 8/11/2010 Complete

Conduct EEA Test (EMO8) 9/8/2010 Planned

168-Hour Test Completion (R3) 9/22/2010 Planned

ERCOT Nodal Readiness Declaration (R1) 10/19/2010 Planned

Develop Texas Nodal Market Launch Plan (R2) 9/22/2010 Planned

01 September 2010 Market Readiness Seminar

Page 61: Market Readiness Seminar 6

61

Nodal – Overall Readiness – Go Live draft

Contingency Plans Planned Completion

Status

Contingency Plan for Weekly, Daily and Hourly RUC Failure (C1) 10/01/2010 Planned

Contingency Plan for DAM / LMP Failure (C2) 10/01/2010 Planned

Contingency Plan for ICCP Data Failure (C3) 10/01/2010 Planned

Contingency Plan for SCED Failure (C4) 10/01/2010 Planned

Contingency Plans for Key Settlement and Financial Transfer Processes (C5) 10/01/2010 Planned

Develop Plan for SE Failure (C6) 10/01/2010 Planned

Contingency Plan for a Backup Facility (C7) 10/01/2010 Planned

Contingency Plan for Portal/API Failure (C8) 10/01/2010 Planned

Contingency Plan for Site Unavailability (C9) 10/01/2010 Planned

Verify Single Point of Failure Recovery EMS/MMS/NMMS/CRR/COMS (C10) 10/01/2010 Planned

01 September 2010 Market Readiness Seminar

Page 62: Market Readiness Seminar 6

62

04/21/23

Cut-Over Communication Plan

01 September 2010 Market Readiness Seminar

Page 63: Market Readiness Seminar 6

63

Nodal Cutover and Market Transition – Communication Plan

Friday Market Calls Starting 09/03/2010 at 9AM-12noon these calls will be combined, without breaks, into a single Market Trials and Cut-over Activities call

Market Participants should plan on attending the full duration of this call as it will provide the primary means of communication between ERCOT and the Market.

Information and materials covered in this call will continue to be posted to the ERCOT calendar website every Friday at the following URL: http://www.ercot.com/committees/nodal/mt/

Monday Kick-Off Calls As needed to review the cutover activities for the week

Market Notices and Market Participant Contact ListsERCOT will continue to leverage Market Notices to communicate pertinent information that is required to be consumed by the Market as a whole.

Market Participants employees can subscribe to the Market Notices on the ERCOT Lists website at the following URL: http://lists.ercot.com/scripts/wa-ercot.exe?HOME.Market Participants may verify their contact information on file with ERCOT through their assigned Whole Client Services Representative.

01 September 2010 Market Readiness Seminar

Page 64: Market Readiness Seminar 6

64

Nodal Cutover and Market Transition – Communication Plan (Cont.)

Market Participants Contacting ERCOT

•Market Trials email inbox: [email protected]. This inbox will continue to be maintained throughout Nodal Cutover. This will serve as a “catch-all” forum for questions if there is any doubt as to where a question should be submitted.

•Friday Market Calls: In line with the previously mentioned schedule, these Market Calls not only serve as the primary means for ERCOT to communicate to the Market, but also for MPs to field general questions concerning the Nodal Cutover plan.

•ICCP email inbox: [email protected] for specific MP questions regarding their Nodal ICCP / Telemetry, this email address should be leveraged for the fastest response.

•ERCOT Wholesale Client Services Account Manager: Whenever possible MPs should leverage the Market Trials email inbox, however, MP’s Wholesale Client Services Account Manager will also be equipped to either answer your questions or route you to the correct support personnel.

•Nodal Advisory Task Force (NATF): NATF will serve as a forum for initially reviewing changes in activities during the ERCOT Nodal Cutover, NPRRs and any concerns from the Market that would impact the overall Cutover plan. To that end, NATF will be meeting more frequently to ensure expedient coverage of these types of issues. Details regarding meeting agendas and materials from past meetings will continue to be maintained at the following URL: http://www.ercot.com/committees/board/tac/natf/

01 September 2010 Market Readiness Seminar

Page 65: Market Readiness Seminar 6

65

Nodal Cutover and Market Transition – Communication Plan (Cont.)

Go-Live Communication StrategyPurpose and Objectives •Maintain reliable grid operations during the Go-Live period•Maintain constant interaction to respond quickly and effectively to issues that arise during the go-live period•Respond and report any observed anomalies in market performance or behavior

Go-Live Period Communication•Market Calls•Daily and at times hourly conference calls between ERCOT and Market Participants will start on 11/23/2010. ERCOT will set up the logistics of the calls and communicate via a Market Notice and the Cutover Handbook

Stabilization Period Communication•Market Calls•Daily Market Calls thru 12/07/2010 then adjust to weekly/biweekly based on need

•Daily Issue / Inquiry •Wholesale Client Service Reps•Retail Client Service Reps•ERCOT Helpdesk

**More details and updates on the Go-Live Communication plan to be presented in the coming months

01 September 2010 Market Readiness Seminar

Page 66: Market Readiness Seminar 6

66

Nodal Cutover and Market Transition – Reversion Plan

Reversion Plan Approach:

•12/01/2010 – 12/02/2010: Zonal and Nodal systems continue to process in parallel. This allows for 48hrs of stabilization (2 Operating Days) with parallel processing similar to the level of effort being performed with the LFC Testing

•12/03/2010 – 12/31/2010: Zonal systems “Retire” where processing is disabled, but remain in place in the event they are needed to be reinstated quickly.

•01/01/2011: Zonal System Decommissioning begins

01 September 2010 Market Readiness Seminar

Page 67: Market Readiness Seminar 6

67

Nodal Cutover and Market Transition – Upcoming Events

Event Agenda Date Location

Nodal Market Call

Combined Market Trials and Cutover call between ERCOT and Market Participants begins

09/03/20109am-12pm

Conf. Call/Web Ex

Nodal Cutover Update

Post Go-Live Activities for January, February, March, and Reversion Plan

End September

Conf. Call/Web Ex

01 September 2010 Market Readiness Seminar

Page 68: Market Readiness Seminar 6

68

Next 60-days of Nodal Classes/Workshops

Course Start Date Location

Congestion Revenue Rights August 31 ERCOT Met Center (Austin)

Generation 201 September 1 Hilton Austin Airport (Austin)

Economics of LMP September 13 ERCOT Met Center (Austin)

ERCOT 101 for Wind Generation September 13 Optim Energy (Dallas)

ERCOT Nodal 101 September 14 StarTex Power (Houston)

Generation 101 September 15 Hilton Austin Airport (Austin)

Basic Training Program September 20 LCRA (Austin)

Load Serving Entity 201 September 27 ERCOT Met Center (Austin)

Congestion Revenue Rights September 29 Suez Energy (Houston)

ERCOT Nodal 101 October 5 RBS Sempra (Stamford, CT)

Basic Training Program October 18 Suez Energy (Houston)

Enrollment at: http://nodal.ercot.com/training/courses/index.html

01 September 2010 Market Readiness Seminar