34
Marine Safety Investigation Unit MARINE SAFETY INVESTIGATION REPORT Safety investigation into the escape of steam and hot water resulting in one fatality and three serious injuries on board the Maltese registered passenger vessel CELEBRITY CONSTELLATION approximately 30 nautical miles East of Bonaire on 12 April 2012 201204/005 MARINE SAFETY INVESTIGATION REPORT NO. 06/2013 FINAL

Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

Marine Safety Investigation Unit

MARINE SAFETY INVESTIGATION REPORT

Safety investigation into the escape of steam and hot water

resulting in one fatality and three serious injuries on board the

Maltese registered passenger vessel

CELEBRITY CONSTELLATION

approximately 30 nautical miles East of Bonaire

on 12 April 2012

201204/005

MARINE SAFETY INVESTIGATION REPORT NO. 06/2013

FINAL

Page 2: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

ii

Investigations into marine casualties are conducted under the provisions of the Merchant

Shipping (Accident and Incident Safety Investigation) Regulations, 2011 and therefore in

accordance with Regulation XI-I/6 of the International Convention for the Safety of Life at

Sea (SOLAS), and Directive 2009/18/EC of the European Parliament and of the Council of 23

April 2009, establishing the fundamental principles governing the investigation of accidents

in the maritime transport sector and amending Council Directive 1999/35/EC and Directive

2002/59/EC of the European Parliament and of the Council.

This report is not written, in terms of content and style, with litigation in mind and pursuant to

Regulation 13(7) of the Merchant Shipping (Accident and Incident Safety Investigation)

Regulations, 2011, shall be inadmissible in any judicial proceedings whose purpose or one of

whose purposes is to attribute or apportion liability or blame, unless, under prescribed

conditions, a Court determines otherwise.

The objective of this safety investigation report is precautionary and seeks to avoid a repeat

occurrence through an understanding of the events of 12 April 2012. Its sole purpose is

confined to the promulgation of safety lessons and therefore may be misleading if used for

other purposes.

The findings of the safety investigation are not binding on any party and the conclusions

reached and recommendations made shall in no case create a presumption of liability

(criminal and/or civil) or blame. It should be therefore noted that the content of this safety

investigation report does not constitute legal advice in any way and should not be construed

as such.

© Copyright TM, 2013

This document/publication (excluding the logos) may be re-used free of charge in any format

or medium for education purposes. It may be only re-used accurately and not in a misleading

context. The material must be acknowledged as TM copyright.

The document/publication shall be cited and properly referenced. Where the MSIU would

have identified any third party copyright, permission must be obtained from the copyright

holders concerned.

MARINE SAFETY INVESTIGATION UNIT

Malta Transport Centre

Marsa MRS 1917

Malta

Page 3: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

iii

CONTENT

LIST OF REFERENCES AND SOURCES OF INFORMATION .......................................... iv

GLOSSARY OF TERMS AND ABBREVIATIONS ................................................................v

SUMMARY ............................................................................................................................. vi

1 FACTUAL INFORMATION .............................................................................................1 1.1 Vessel, Voyage and Marine Casualty Particulars .......................................................1 1.2 Description of Vessel .................................................................................................2 1.3 Narrative .....................................................................................................................3 1.4 The Power Generation System ...................................................................................7 1.5 Training and Qualifications ......................................................................................11 1.6 Company’s Job Safety Analysis Form .....................................................................12

2 ANALYSIS .......................................................................................................................13 2.1 Aim ...........................................................................................................................13 2.2 Accident Dynamics ..................................................................................................13

2.2.1 Preparation for the removal of the safety relief valve ..........................................13 2.2.2 Protective clothing ................................................................................................14 2.2.3 The sudden discharge of hot condensate and steam .............................................14 2.2.4 Drainage of hot condensate and steam .................................................................16

2.3 Risk Assessment .......................................................................................................17 2.3.1 Manifestation of risk assessment issues ...............................................................17 2.3.2 Risk assessments and limited hazards control ......................................................19 2.3.3 Situation awareness ..............................................................................................20

2.4 System Defences ......................................................................................................21 2.5 Operational Safety from a Systemic Perspective......................................................22

3 CONCLUSIONS ...............................................................................................................24 3.1 Immediate Safety Factor ...........................................................................................24 3.2 Latent Conditions and other Safety Factors .............................................................24 3.3 Other Findings ..........................................................................................................25

4 ACTIONS TAKEN ...........................................................................................................25 4.1 Safety Actions Taken During the Course of the Safety Investigation ......................25

5 RECOMMENDATIONS ..................................................................................................26

ANNEXES ...............................................................................................................................28 Annex 1: Job Safety Analysis Form .................................................................................28

Page 4: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

iv

LIST OF REFERENCES AND SOURCES OF INFORMATION

Glendon, I. (1998). Management of risks by individuals and organisations. Safety

Science Monitor, 3(Special Edition), 1-11.

Hale, A. R., Heming, B. H. J., Smit, K., Rodenburg, F. G. T., & van Leeuwen, N. D.

(1998). Evaluating safety in the management of maintenance activities in the

chemical process industry. Safety Science, 28(1), 21-44.

Harms-Ringdahl, L. (2001). Safety analysis: principles and practice in occupational

safety (2nd

ed.). Florida: CRC Press LLC.

Managers and crew members MV Celebrity Constellation.

Marine Accident Investigation Branch [MAIB]. (2003). Report on the investigation of the

escape of steam and hot water on board Queen Elizabeth 2 in the mid Atlantic resulting in

one fatality. Report No. 17/2003. Southampton: Author.

Oltedal, H. A., & Engen, O. A. (2011). Safety management in shipping: making

sense of limited success. Safety Science Monitor, 15(3), 1-19.

Owen, C., Béguin, P., & Wackers, G. (Eds.). (2009). Risky work environments:

reappraising human work within fallible systems. Surrey: Ashgate Publishing

Limited.

Raafat, H. M. N. (1989). Risk assessment and machinery safety. Journal of

Occupational Accidents, 11(1), 37-50.

Reason, J. (1997). Managing the risks of organizational accidents. Aldershot:

Ashgate Publishing Limited.

Trimpop, R., & Zimolong, B. (n.d.). Risk perception. Retrieved 27 November, 2006,

from http://www.ilo.org/encyclopedia/?d&nd=857100076&prevDoc=857000106

Vatn, J., & Aven, T. (2010). An approach to maintenance optimization where safety

issues are important. Reliability Engineering and System Safety, 95(1), 58-63.

Wilson, R. (1984). Commentary: risks and their acceptability. Science, Technology,

& Human Values, 9(2), 11-22.

Page 5: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

v

GLOSSARY OF TERMS AND ABBREVIATIONS

ABB Asea Brown Boveri

COGES Combined Gas, Electric, and Steam turbines

DHW Domestic Hot Water

DNV Det Norske Veritas

DWT Deadweight

FW Fresh Water

GE General Electric

GMTS Global Maritime Transportation Services

GRT Gross Tonnage

HP High Pressure

HRSG Heat Recovery Steam Generators

IMO International Maritime Organization

ISO International Organization for Standardization

Kgs Kilograms

kV Kilovolts

LP Low Pressure

LR Lloyds Register of Shipping

LT Local Time

MAIB Marine Accident Investigation Branch

MV Motor Vessel

MW Mega Watt

OEM Original Equipment Manufacturer

QE II Queen Elizabeth II

RCCL Royal Caribbean Cruises Ltd.

SMS Safety Management System

SOLAS International Convention for the Safety of Life at Sea, 1974, as

amended

STCW International Convention on Standards of Training, Certification

and Watchkeeping for Seafarers, 1978, as amended

TM Transport Malta

Page 6: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

vi

SUMMARY

On 12 April 2012, while on passage from Curacao to Grenada in the Caribbean Sea,

four of the engine-room crew members on board the passenger ship

Celebrity Constellation were badly scalded. The accident happened when steam and

condensate unexpectedly escaped from a three bar safety relief valve that was being

removed in preparation for a classification society ship survey. One of the crew

members subsequently died as a result of his injuries.

The accident happened when the second engineer, under the direct supervision of

chief engineer, was in the process of removing the bonnet of the safety relief valve on

a low pressure (3 bar) steam line that had been identified as being defective (seized).

The valve overhaul started about an hour after it was isolated from the live side of the

steam system and after the system was vented. Hot water and steam escaped from the

line as the bonnet and trim were removed from the valve body, and consequently

seriously injured the four men.

It was concluded that although the relief valve was isolated, the piping contained

residual hot condensate and steam. It was possible that the system did not allow for

adequate draining of residual hot condensate or steam. The safety investigation also

found that the risk assessment was not thorough enough, with the hazard not being

eliminated or mitigated to minimise or even prevent injuries to the crew members.

Further to the safety actions already taken, recommendations were made to the ship

managers and Lloyd’s Register of Shipping regarding the provisions of adequate

drainage arrangements for steam pipelines. Additional recommendations were made

to the ship management company to ensure in-depth risk assessment and continuous

awareness on the importance of efficient drainage of condensate.

Page 7: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

1

1 FACTUAL INFORMATION

1.1 Vessel, Voyage and Marine Casualty Particulars

Name Celebrity Constellation

Flag Malta

Classification Society Lloyd’s Register of Shipping

IMO Number 9192399

Type Passenger

Registered Owner Constellation Inc.

Managers Celebrity Cruises Inc.

Construction Steel

Length overall 294.0 m

Registered Length 262.9 m

Gross Tonnage 90,280

Minimum Safe Manning 21

Authorised Cargo N/A

Port of Departure Curacao

Port of Arrival Grenada

Type of Voyage Short International

Cargo Information N/A

Manning 939

Date and Time 12 April 2012 at 23:55 (LT)

Type of Marine Casualty or Incident Very Serious Marine Casualty

Location of Occurrence 12° 10.3’N 067° 42.7’W

Place on Board Engine-room

Injuries/Fatalities One fatality and three seriously injured

Damage/Environmental Impact None

Ship Operation In passage

Voyage Segment Transit

External & Internal Environment Fresh breeze and clear skies, with a visibility of

about 18 nautical miles. The sea was slight with

a south-easterly one metre swell. Sea

temperature was 26°C and the air temperature

was 25°C. Engine-room was well lit with white

neon tubes.

Persons on Board 2,972

Page 8: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

2

1.2 Description of Vessel

Celebrity Constellation (Figure 1) was a Millennium class passenger ship1 built at

Chantiers de l’Atlantique Shipyard in St. Nazaire, France. She was launched in May

of 2002 as Constellation. Renamed Celebrity Constellation in May 2007, she has an

overall length of 294 m and a beam of 32.3 m. The vessel has a deadweight (DWT)

of 11,928 and a gross tonnage of 90,280. Celebrity Constellation has 13 decks.

Originally, the 50 MW power was provided by two combined gas, electric and steam

turbines (GE COGES) and this was later augmented by a single Wärtsilä 16V38 diesel

engine that was installed in May 2007. With a propulsive system consisting of two

Rolls-Royce Alstom Mermaid POD with two Azimuth thrusters of 19 MW each and

three variable pitch thrusters, she manages a maximum speed of 22 knots. In her 11

passenger decks, Celebrity Constellation has a capacity to accommodate 2038

passengers.

At the time of the accident, Celebrity Constellation was registered under the Maltese

flag and owned by Constellation Inc.. The vessel is classed with Lloyd’s Register of

Shipping (LR) and had a crew of 941 of different nationalities.

Figure 1: MV Celebrity Constellation

1 The Millennium was the world's first COGES-powered passenger ship.

Page 9: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

3

© 2013 Google

U.S. Dept. of State Geographer

Image U.S. Geological Survey

Data SIO, NOAA, U.S. Navy, NGA, Geeco

1.3 Narrative

On 12 April 2012, Celebrity Constellation was en route from Curacao to Grenada in

the Caribbean Sea (Figure 2). Several of the crew members were making the

necessary preparations for an LR survey. One of the items to be surveyed, and which

formed part of the low pressure (LP) steam system of the COGES power generating

system, was a three bar steam safety / relief valve.

Figure 2: Caribbean route of Celebrity Constellation from Curacao to Grenada

This valve was found to have seized and was not operating. The ship’s engineering

crew made the necessary preparations to remove, inspect and repair the valve. The

valve (Figure 3) was a conventional spring loaded type, and which could be actuated

manually by lever.

The make of the valve was RSBD Serial No. 6536.1C.150.115.200PF and weighed

approximately 105 kgs. The valve was part of a compound COGES power system

where the exhaust gases of a gas turbine and those of the prime movers, which drive

electrical generators, heat the medium of a steam system. The high pressure (HP)

steam, at 32 bar, drives a steam turbine. The power generated is used by electric

motors, which eventually drive the propellers.

Page 10: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

Fig

ure 3

: A cr

oss-sec

tion

al v

iew o

f the sa

fety re

lief va

lve

4

Page 11: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

5

Fitter

Chief engineer

Fitter

Third

Engineer

Deck

Fitter

Second

Engineer

The LP steam (which operates at two pressure levels of three and nine bar), was used

to drive steam driven auxiliary equipment and also for ship and hotel services. Both

the diesel generator and the steam turbine were stopped and the valve was isolated by

closing a number of other valves. Drain valves were opened in order to drain the

steam pipes from condensate and steam. The isolation of this part of the system

necessitated that some of the valves are closed, whilst others had to be opened.

Valves on the steam plant were operated either locally or remotely from the engine

control room. The gas turbine was kept running and it was planned that until the

maintenance task was completed, it would serve as the only source of power on the

vessel.

The chief engineer recalled that the system was allowed about one hour to cool down.

Then, when the local and remote pressure readings read zero2, the engine-room crew

positioned themselves around the relief valve (Figure 4) and started to dismantle the

valve under the instructions of the chief engineer.

Figure 4: Positions of engine-room crew members at time of accident

2 Locally, the pressure gauge is situated close to the relief valve.

Page 12: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

6

The second engineer started to undo the eight bolts, which held down the valve in

place (Figure 5).

Figure 5: Safety relief valve and pressure gauge in line

Gradually, the second engineer unscrewed all the bolts except for two, which were

loosened but not removed. There were no signs of steam or water leaking or escaping

from underneath the bonnet. The open gap between the bonnet and the valve body

was substantial whilst the second engineer started to move the bonnet sideways.

Seeing no steam or hot water escaping, the chief engineer instructed the second

engineer to undo the last two bolts and to lift off the bonnet (Figure 6).

Page 13: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

7

Figure 6: Safety relief valve bonnet (in the workshop after the accident)

At this stage, steam and hot condensate escaped from the opening. It was

immediately evident that four of the crew members assisting or overseeing the

overhaul operation were seriously injured. The chief engineer managed to escape and

medical assistance was immediately given to the crew members. The four injured

crew members were all transferred ashore for medical treatment. Notwithstanding the

medical treatment being administered in the hospital, one of the fitters succumbed to

his injuries.

1.4 The Power Generation System

The engine-room of Celebrity Constellation is situated on the tank top deck and runs

almost the full length of the ship. Celebrity Constellation was powered by a COGES

plant. The Wärtsilä diesel engine was not part of the original propulsion plant but was

fitted in May 2007 to increase versatility and economy. Figure 7 is a simplified

overview of the steam system fitted on board.

Page 14: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

8

Figure 7: Steam plant overview

The economiser, evaporator and superheater housed in the two heat recovery steam

generators (HRSG), use exhaust gases from the prime movers and the gas turbines to

generate steam into the steam drum (Figure 8). The steam drives a steam turbine at

high pressure (32 bar) and is also expanded (to 9 and 3 bar) to drive auxiliary

equipment (e.g. fresh water generators) and hotel services (e.g. kitchen and domestic

hot water (DHW)).

Page 15: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

Fig

ure 8

: Bo

iler feed

from

HR

SG

9

Page 16: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

10

The gas turbine (Figure 9) is of the two shaft type with a 16 stage 18:1 axial

compressor providing compressed air to an annular burner or combustor where fuel is

injected and burned. The gas produced is fed into the power turbine where it is

expanded and pressure energy converted into rotational kinetic energy. The power

turbine shaft is coupled to the axial compressor shaft by means of a flexible coupling.

The power turbine drives one of the 11kV 25 MW electric generators.

Figure 9: A GE LM2500 gas turbine generator set similar to the one fitted on the vessel

The steam plant consists of a seven stage Fincantieri back pressure steam turbine

(Figure 10), which is coupled through a gearbox to another electrical generator. The

two Heat Recovery Steam Generators (HRSG) are installed in the exhaust ducts of

each of the gas turbine and the diesel generator.

Figure 10: A Fincantieri back pressure steam turbine

The generated steam is led into the steam turbine, into the flash steam fresh water

generators (Serk Como), for sanitary water heating, heating system in galley and

Page 17: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

11

laundry and accommodation heating system. Steam enters the turbine at 32 bar and

410 C, while for heating and the operation of auxiliary equipment, steam was

supplied at two pressure levels namely at nine bar and three bar (Figure 11).

Figure 11: Steam distribution

1.5 Training and Qualifications

Managers have made available copies of all certificates and familiarisation checklists

of the crew members involved in the accident. The familiarisation training of the

engineer officers included ‘Boiler and Steam Systems’. The second engineer was

provided this training on 22 February 2012, whilst the third engineer had received his

training on 07 January 2012. The familiarisation training provided to the two fitters

did not seem to include ‘Boilers and Steam Systems’.

The provided documents neither indicated the duration nor the detail provided during

the familiarisation training. The crew members were qualified in accordance with the

relevant requirements of the STCW Convention.

Page 18: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

12

1.6 Company’s Job Safety Analysis Form

The Company’s safety management system (SMS) required that a Job Safety Analysis

Form is completed prior to the overhaul of the safety valve. The Form is reproduced

as Annex 1 to this safety investigation report.

There is no indication on the Form as to who should have filled the document. This

would suggest that the pre-job safety analysis process requires neither the

involvement of a safety officer nor a person who would assume responsibility to

oversee and manage the safety component of the task that was identified as potentially

hazardous.

The date and time entered on the Form indicate that it was completed about 24 hours

prior to the accident. However, there were no instructions or guidelines to indicate at

what stage of the job, the Form should have been completed and to whom it should

have been distributed. Moreover, the Form was not authorised / endorsed in any way

by a member of the crew in accordance with the procedures laid down in the

Company’s SMS.

A Det Norske Veritas (DNV) survey report (Renewal DOC and ISO 9001 & 14001

Audits (Being Harmonized with RCCL Audits)) referenced as DNV 145279, Job ID

298226, and conducted for Celebrity Cruises Inc. between 06 and 10 August 2012,

made the following observations:

5. ISO 9001:2008, 7.1: (Equipment & System Failure) OEM and specialist vendors –

how to manage change when operating procedures change on board and some crucial

inspection and maintenance objectives slip between the cracks. (Example: Switchboard

(ABB Sace) - CCI does this during Dry Dock and RCCL annually. When this sort of

change is made, is a Risk/Gap assessment carried out as part of change management?

(GMTS)

6. ISO 9001:2008, 7.1: (Equipment & System failure) Technical bulletins for specialist

equipment: It was not clear as to who the owner of the latest information is and how is

it assessed for implementation and made available to all relevant personnel within the

company (e.g. Marioff’s latest bulletins). Also review in order to share best practices

and keep abreast with latest technical updates within all brands.

Page 19: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

13

2 ANALYSIS

2.1 Aim

The purpose of a marine safety investigation is to determine the circumstances and

safety factors of the accident as a basis for making recommendations, to prevent

further marine casualties or incidents from occurring in the future.

2.2 Accident Dynamics

2.2.1 Preparation for the removal of the safety relief valve

The engine-room crew members were preparing for a Class survey, whilst the vessel

was at sea. It was noted that the low pressure (3 bar) safety relief valve was seized.

The seizure of the relief valve was attributed to the lack of periodical testing by the

crew members. The Company’s preventive maintenance system did not include the

periodical testing of any of the relief valves fitted on the low and high pressure

system.

Although the decision was made to isolate the valve and to dismantle it for inspection,

there was no evidence available which indicated that the Company had clear

guidelines and instructions on the isolation of the valve from the system. The way

steam and hot condensate leaked as the safety valve was removed, indicated that the

procedure adopted was not totally effective. However, the matter is seen from a wider

perspective, which would encompass what seemed to be an ad hoc risk assessment

prior to the task was taken in hand.

Most of the normal power systems had to be shut down in order to be able to isolate

the valve, drain, and cool the relevant part of the steam system (only gas turbine no. 1

was left in operation). Moreover, sections of the system had to be isolated from the

live side of the plant, vented to atmosphere and drained of condensate. The decision

to remove the valve bonnet was taken after the pressure upstream of the valve was

reduced to zero and the system allowed to cool for one hour.

The understanding is that the pressure gauge upstream of the valve and the sensing

components of the control system were functioning correctly, and the system drained

and had adequately cooled down. However, it was evident that hot condensate and

Page 20: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

14

steam were still present in that part of the system where the maintenance job was

being undertaken.

2.2.2 Protective clothing

There was no doubt that the second engineer, under the supervision of the chief

engineer, was cautious in his actions; he slowly and partially removed the nuts that

held down the bonnet to the valve body. The bonnet was only removed when the

crew members satisfied themselves that there was no indication of residual

pressurised steam or hot condensate. There was no indication that the valves isolating

the relief valve were opened at some stage during its removal.

The removal of the bonnet was also done by moving the body to and fro to further

ensure that no steam was trapped under the valve seat. The release of the steam and

hot condensate is addressed further below. However, it has to be stated that the severe

injuries sustained by the crew members confirmed that they were not wearing

adequate protective clothing.

2.2.3 The sudden discharge of hot condensate and steam

The fact that steam and hot condensate leaked when the top part (bonnet and trim) of

the safety relief valve was removed indicated that actually, steam or hot condensate

was possibly trapped either underneath the valve disc (upstream) or under the valve

guide (downstream). Although it is understood that the pressure gauge upstream of

the valve and the control room monitoring system were in good operational condition,

and that the steam pressure upstream of the valve was zero gauge pressure

(atmospheric pressure), this would not have excluded the presence of condensate at

relatively high temperature inside the pipeline.

At atmospheric pressure, or zero gauge pressure, steam and condensate can co-exist at

100 C. Assuming a one metre length of pipe, 60 minutes should have been adequate

for the system to cool enough for maintenance to be carried out and relieve itself of

steam and hot condensate; but this depends on the amount or mass of any trapped

condensate. Moreover, to determine whether or not sufficient cooling time had

elapsed, one had to take into consideration the pipe insulation and the possibility of

relatively high ambient temperature in the space, which would have significantly

delayed cooling.

Page 21: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

15

Figures 4 and 5 indicate that the relief valve is fitted at the bottom of a U shaped pipe.

It was not excluded that hot condensate could have collected at the lower levels of the

pipeline (if not adequately drained). Masses of hot condensate would contain

relatively high levels of enthalpy. With the pressure further reduced, the latent energy

would have vaporised the hot condensate. The (large volumes) of generated steam

would also tend to travel in the direction of the lower pressure, (even if this was

slight), such as where the valve was opened.

If this does not bring into question the accuracy of the pressure gauge and pressure

transducer, it would, however, question their sensitivity and monitoring. The gauge

indicated as P1 4036 (Figure 12) has a full scale deflection of six bar and the minor

graduations read up to 0.1 bar. This would imply that although the pressure gauge

was apparently reading zero, there could actually have been a slight pressure, above

the atmospheric pressure (which is nominally assumed to be 1.013 bar absolute)

within the pipeline and which the gauge or transducer were not sensitive enough to

indicate.

It should also be noted that if condensate was trapped at relatively high temperature,

the thermal energy could change into pressure energy during the cooling down period,

ejecting the steam / condensate through an exit point, such as the one provided as a

result of the removal of the valve. It must be stressed that this could only happen if

the means of drainage in the specific section of pipeline were inadequate.

Figure 12: Pressure gauge fitted close to the relief valve

Page 22: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

16

2.2.4 Drainage of hot condensate and steam

As indicated in sub-section 2.2.3, the steam and hot condensate escape would have

happened only if the draining of the steam from the system was inadequate. This was

very possible, taking into consideration that the flushing lines (steam drainage) are at

a level higher than the section of pipe were the relief valve was fitted, making it

difficult, if not impossible, to drain the lower parts of the system.

A very similar occurrence happened on the UK registered Queen Elizabeth II (QE II)

on 23 June of 20023. QE II was on a passage from New York to Southampton when

two engine-room crew members were badly scalded (one eventually succumbed to his

injuries) while removing a steam valve. The safety investigation had revealed that a

slight leak in an isolating steam valve led to localised heating of trapped condensate in

the isolated steam line, which resulted in some of the condensate boiling and escaping

through the dismantled valve. The safety investigation report explained that

…the system of drainage of steam of the installation of the ship presented operational

and structural deficiencies that indicate a lack of care with the safety of human life at

sea, during the conception of the initial project…

Adequate drainage of condensate is also a requirement under SOLAS II-1/33.2, which

requires that

Means shall be provided for draining every steam pipe in which dangerous water

hammer action might otherwise occur.

and LR’s Rules and Regulations for the Classification of Ships, Part 5 Main and

Auxiliary Machinery (Steam Piping Systems):

…the slope of the pipes and the number and position at the drain valves or cocks are

to be such that water can be efficiently drained from any portion of the steam piping

system when the ship is in normal trim and is either upright or has a list of up to 5°.

Whilst the above requirements were designed to ensure adequate facilities for the

drainage of condensate of steam pipes, the accident on board Celebrity Constellation

showed that the installation did not satisfy these requirements. To add further to the

complexity of the situation, the low pressure system did not permit individual

3 UK’s Marine Accident Investigation Branch’s safety investigation report on the investigation of the

escape of steam and hot water on board QE II in the mid Atlantic resulting in one fatality on 23

June 2002. Report No. 17/2003.

Page 23: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

17

components to be isolated for maintenance. Whilst the system as designed has the

benefit of having less flanges and therefore less potential for leaks, it does not allow

for access and isolation of the existing components. Moreover, the system does not

have direct bilge drain lines to allow for the system to be de-energised completely and

individual lines emptied. The lack of flanges has also prevented the crew members to

insert blind flanges.

2.3 Risk Assessment

The aim of a risk assessment exercise is to qualify whether the status of any system is

acceptable and help determine what changes are necessary to make it acceptable.

Such exercise is so important that it will not only provide an estimate of the size of

risk but should also enable a comparison of the risk level with some given criteria and

serve as a platform for a professional judgement to be made in determining what

system improvements are needed to increase safety.

2.3.1 Manifestation of risk assessment issues

As it has already been implied in sub-section 1.6, the risk assessment was not

thorough enough and this has been manifested through the following:

1. The hazard was not eliminated or reduced;

2. Appropriate safe guards were not selected;

3. Recommended safe working practices for the overhaul of valves were not

adequately described;

4. The crew members were not sufficiently informed about the residual risk in

the system; and

5. No extra protective clothing was worn or protective equipment used.

It is a fact that whereas some industries have the benefit to judge the level of risk by

analysing relevant accident statistics, this was not the case for Celebrity Constellation.

This meant that a different technique was necessary in order to establish the actual

level of risk which the system posed, especially with the dismantling of the relief

valve; a situation which would have altered the (stable) status of the system. Given

that such assessment was either not done at the design stage or not available to the

Page 24: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

18

crew members, there was no other option but to conduct the assessment onboard prior

to the overhaul of the relief valve.

A typical overall risk assessment procedure is represented in figure 13.

Figure 13: A typical risk assessment procedure

Adopted: Raafat, H. M. N. (1989). Risk assessment and machinery safety. Journal of Occupational

Accidents, 11(1), 37-50.

Academic literature provides numerous examples and methods of risk assessment and

Figure 13 depicts a practical way of analysing risk in a dynamic system. Albeit linear,

the procedure may be adopted to represent a situation which indicates the importance

of crew members to be extremely familiar with the system and know where its safety

boundaries were located. The safety investigation did not have evidence which

suggested that the crew members were not familiar with the system. From the

theoretical and operational aspects, the engineers were able to operate the system

safely and take action where required. Sound engineering knowledge was not

considered to be a contributing factor to this accident.

Page 25: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

19

To a certain extent, system hazards were known to the crew members. What was

lacking, however, was a clear4 understanding of what is defined as continuing hazards

(i.e. hazards inherent in the system) and those hazards which were a direct result of

the maintenance task. Whilst figure 13 shows a procedure, it is also indicating that

missing on particular hazards will lead to an incomplete assessment of risk,

evaluation, and eventual corrective measures, which may well include protective

barriers.

2.3.2 Risk assessments and limited hazards control

Whilst risk assessments are part of organisational functioning, they are also strongly

influenced by each individual’s unique experiences and interpretation of the ‘input

signal’. Academia shows that understanding risk is vital as it correlates to the degree

with which risk is observable.

Risk perception is the understanding of perceptual realities and hazard indicators. The

residual steam and hot water in the low pressure steam system was a hazard – and a

very serious one. It was not detected. What distorted the perception of the crew on

the severity of the hazard was the lack of perceptible indicators. The way the system

was built and designed (i.e. complexity) was a contributing factor to this distortion.

Thus, the lack of depth in the risk analysis, influenced by the distortion mentioned

above, and the lack of past experience of similar accidents, precipitated into a

situation where the crew members could only react in a reflex mode as a result of the

sudden occurrence of escaping hot water and steam.

The problem with lack of perceptible indicators is a hazard per se and this

phenomenon is not endemic to a particular safety critical domain. Studies in domains

other than transport also revealed similar problems. It was revealed that less than half

of the hazard indicators were perceptible to the human senses and almost a quarter

had to be perceived and inferred from comparisons with standards. Lack of past

experience was also an identified common problem – retrieval from memory would

have only occurred if the crew members had past experience of similar accidents or

incidents.

4 The term ‘clear’ is used on purpose. It is the safety investigation’s view that a significant degree of

hazard understanding was available. Before overhauling the relief valve, the crew members had

taken a number of precautions – per se indicative that there was a degree of awareness of the hazard

and related risks.

Page 26: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

20

Studies in hazard perception indicate that the process is intricate with different

cognitive processes involved. It is also acknowledged that inaccurate hazard

perception is a source of limited hazards control.

2.3.3 Situation awareness

Maintenance activities cause deviations during normal operations. Thus, whilst

maintenance increases component reliability and hence safety, accidents often occur

during maintenance. The importance of risk assessment has already been described

above. From the perspective of situation awareness, risk assessment is crucial. Risk

assessment is a process (which depends on, inter alia, perception), that will generate a

person’s knowledge of the system or situation awareness. Naturally, the distinction

between risk assessment and situation awareness may not necessarily be crystal clear

and some scholars even claim that psychology is unable to separate the process from

the product.

To a certain extent, the safety investigation has considered the two separately.

However, what is of utmost importance is the understanding that rather than two

mutually exclusive constructs, risk assessment and situation awareness are

interdependent. It is submitted that situation awareness also arises from the

interaction between crew members and the work environment – and risk assessment is

one way of ensuring crew members-environment interaction. Thus, situation

awareness is a phenomenon, which is not only identifiable with the individual but, as

expressed scientifically, is a function which is achieved by coordination between the

human and the environment within the socio-technical system on board.

The link between risk assessment and situation awareness is that the former is vital to

pave the way for a compatible representation of people and systems i.e. when the

awareness of system status in the minds of the crew members becomes a true

reflection of the actual and real status of the system. Incompatible representations

(either on the crew member’s side or the machine’s status) would definitely mean

potential problems. On board Celebrity Constellation, the information exchanges

were hampered by system complexity and a shallow risk assessment – severely

compromising the information flow between system components that included the

crew members.

Page 27: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

21

What actually happened prior and during the unfolding of the events was that the crew

members were neither able to comprehend the system status nor project accurate

future status.

2.4 System Defences

It has already been pointed out in the safety investigation report that the protective

clothing , which the crew members were wearing, did not provide enough protection

against possible injuries from contact with hot water and steam. The main problem

stemmed from the belief that the hazards were mitigated by the:

1. entire steam section being taken off line;

2. closure of valves supplying the three bar and nine bar systems;

3. allowance for the system to cool for approximately one hour;

4. reading on the pressure gauge of zero pressure;

5. release of the safety spring tension; and

6. systematic and cautionary slacking of the bolts holding the bonnet to the valve

body.

Whilst the above points suggest preventive barriers5, effective protection would have

been achieved by the application of skills and the use of protective barriers. The

safety investigation had no doubt that the crew members involved in the job had the

necessary skills. However, protective barriers, i.e. those barriers, which would have

deflected or minimised the consequences were limited. Considering the close

proximity of the crew members to the relief valve, the limited protective barriers were

manifested, for instance, in the lack of adequate protective clothing.

5 Other actions, which could have prevented the accident, could include the monitoring of

temperature as the pipe section was allowed to cool down, replacing the pressure gauge with a more

sensitive one to ensure that the pressure in the pipeline was actually zero, and improvise and ensure

that the pipe section was adequately drained by removing the pressure gauge and opening the cock

upstream of the gauge. These preventive measures would have emerged in a detailed risk

assessment exercise, which is a preventive measure per se.

Page 28: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

22

2.5 Operational Safety from a Systemic Perspective

The vessel’s managers had established procedures to ensure that each vessel is

maintained in conformity with the provisions of the relevant National and

International rules and regulations, in addition to the requirements of the Company.

Maintenance is an integral part of the safety management system of the company –

not only because it permits the vessel to remain in Class but also because it

compliments the Company’s safety policy, ensuring compliance with the

requirements of the International Safety Management Code.

Despite the safety management system in place (one of its scopes is to avoid accidents

similar to this one), the risks materialised into an accident. It is the view of the safety

investigation that the problem was not at policy level but at the middle level of the

system. The middle level of the safety management system is the level where general

safety policy objectives are translated into maintenance concepts, planning and

procedures to achieve improved safety. The translation process is the responsibility of

the senior management. The lack of operational procedures (including a detailed risk

assessment) for the overhaul of the relief valves is indicative of a problem in the

translation process.

The accident dynamics suggested that the policy level was not representing the

operational realisation of the system. Safety management relates to the actual

practices (associated with remaining safe) and this is where a formal procedure was

missing and not highlighting potential job safety related issues.

In this particular case, i.e. work on the low pressure steam system, a specific company

procedure was lacking and when the operations did not follow the rules of logic and

unforeseen risk materialised, the crew members became unsafely exposed to the

residual hazards.

Page 29: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

23

THE FOLLOWING CONCLUSIONS, SAFETY

ACTIONS AND RECOMMENDATIONS SHALL IN NO

CASE CREATE A PRESUMPTION OF BLAME OR

LIABILITY. NEITHER ARE THEY BINDING OR

LISTED IN ANY ORDER OF PRIORITY.

Page 30: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

24

3 CONCLUSIONS

Findings and safety factors are not listed in any order of priority.

3.1 Immediate Safety Factor

.1 The injuries sustained by the four crew was the result of steam and hot

condensate escaping into the machinery space when part of a low pressure

safety relief valve was being removed from the steam system.

3.2 Latent Conditions and other Safety Factors

.1 There was no written procedure on how to isolate the valve from the rest of

the system, how to drain the system, and how to ensure that it was safe to

remove the valve;

.2 Not all the crew members involved in the incident were actually required to

be on site while the valve part was being removed;

.3 The overalls and other protective equipment did not provide adequate

protection against hot condensate and steam;

.4 The ‘Job Safety Analysis’ indicates that the risk assessment exercise was

not thorough enough to provide an accurate situation awareness of the

system status prior to the removal of the valve;

.5 The position of the relief valve in the system was critical in the sense that it

was at the lower end of a U shaped piece of line that contributed to the

collection of hot condensate;

.6 The design and installation of the section of system concerned neither had

an adequate steam drainage nor a drainage facility to ensure safe drainage;

.7 The routine operation and testing of the relief valves on the steam system

were not part of the vessel’s preventive maintenance procedure.

.8 Although the crew members relied on the installed pressure gauge to

determine the conditions of system, the sensitivity of the gauge was not

verified before the task was initiated.

Page 31: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

25

3.3 Other Findings

.1 The crew members took all the necessary general precautions, during the

removal of the valve from the system;

.2 Although the system is very complex, the vessel did not have a schematic

drawing which would have clearly indicated which valves had to be closed

and / or opened prior to the removal of the relief valve.

4 ACTIONS TAKEN

4.1 Safety Actions Taken During the Course of the Safety Investigation

1. As a short term action, soon after the accident, Celebrity Cruises Inc. issued a

Fleet Bulletin, which was sent to all the vessel under its management. In its

Bulletin, the Company has highlighted the precautions which should be

followed when working on the system, mainly:

1.1. Ensuring that all lockout procedures are implemented so that the entire

system is isolated and de-energised, including the draining of standing

water and residual pressure in the lines by opening flanges or removing

steam traps;

1.2. Minimise the number of crew members in the area;

1.3. Allow for as much cooling time as possible before working on the system,

taking into consideration itinerary and ports;

1.4. Remove heavy components using a block and tackle to keep crew members

as far away from the component as possible;

1.5. Provide barriers or fire blankets to cover any components being serviced

before they are removed to provide a barrier between the crew and

potential release of steam or hot water.

Page 32: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

26

2. Aluminised safety clothing has been provided on company ships which has to

be worn whenever work is to be carried out on the steam system.

3. A Steam System Permit-to-Work Form has been created and added to the

Company’s standard practice. The completion of the Job Safety Analysis Form

remains obligatory.

4. The testing of the low and high pressure steam safety valves has now been

included in the vessel’s preventive maintenance system. The crew is now

required to ensure that the valve properly lifts in accordance with the

manufacturers specifications. Any deviations from this are to be reported to the

Company. For Millennium Class vessels, the safety valves listed are the three

and nine bar valves, and those on the stream drum, superheater, de-aerator and

all auxiliary and waste gas boilers.

5 RECOMMENDATIONS

In view of the conclusions reached and taking into consideration the safety actions

taken during the course of the safety investigation,

Celebrity Cruises Inc. is recommended to:

06/2013_R1 Consider establishing an internal safety committee where high safety

impact maintenance tasks identified from the preventive maintenance system

are transferred from the maintenance team to this safety committee and

discussed with respect to impact on safety and risk analysis;

06/2013_R2 Fit adequate drains to the steam system of this vessel and other vessels

under its management in such a way that efficient means of draining

condensate can be achieved;

06/2013_R3 Ensure that the safety management system highlights continuous

awareness of the importance of efficient drainage of condensate.

Page 33: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

27

Lloyd’s Register of Shipping is recommended to:

06/2013_R4 Consider raising the matter with the International Association of

Classification Societies in order to provide advice to shipbuilders,

classification societies, owners, surveyors and ship management companies on

the need to ensure that efficient draining of steam pipelines on board vessels is

available in accordance with mandatory requirements.

Page 34: Marine Safety Investigation Unit Repository/MSIU... · where the exhaust gases of a gas turbine and those of the prime movers, which drive electrical generators, heat the medium of

28

ANNEXES

Annex 1: Job Safety Analysis Form